CONTRACTUAL DATA

1. Name of Project : Construction of Senior High School Classrooms and


Additional Foundation Works, Pasil NHS, Cebu City
2. Contract ID No. : 15HH0070
3. Project Component : Buildings (3 Storey 12 Classrooms)
4. Province : Cebu
5. Implementing Office : Cebu City District Engineering Office
6. Contractor : WERR CORPORATION INTERNATIONAL
7. Contractor Amount : ₱17,650,000.00
8. Contract Duration : 210 CD
9. Effectivity of Contract : December 26, 2016
10. Expiry Date : July 23, 2017
11. This proposed WSO No. 1 as requested :
by the Implemented Office - Calendar Days

Prepared by :

LITO O. CATUBIG
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City

CONTRACTUAL DATA

1. Name of Project : Construction / Improvement of Access Roads Leading to Declared


Tourism Destinations, S. Cabahug Street Leading to International
Hotel, Brgy. Mabolo, Cebu City
2. Contract ID No. : 17HH0121
3. Project Component : Road Concreting
4. Province : Cebu
5. Implementing Office : Cebu City District Engineering Office
6. Contractor : WIN CONSTRUCTION
7. Contractor Amount : Php 16,783,656.18
8. Contract Duration : 133 CD
9. Effectivity of Contract : March 15, 2018
10. Expiry Date : July 25, 2018
11. Approved Work Suspension Order No. 1 : 30 Calendar Days
12. This proposed CWSO No. 1a as requested :
by the Implemented Office 30 Calendar Days
13. Physical Accomplishment
15.1 Percent Work Accomplished
: 0.00%
(as of April 13, 2018)
15.2 Percent Work Scheduled
: 22.56%
(as of April 13, 2018)
15.3 Slippage : (-) 22.56%

Prepared by :

ELVIRA C. FERNANDEZ
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City

CONTRACTUAL DATA

1. Name of Project : Construction of Senior High School Classrooms and


Additional Foundation Works, Pasil NHS, Cebu City
2. Contract ID No. : 15HH0070
3. Project Component : Buildings (3 Storey 12 Classrooms)
4. Province : Cebu
5. Implementing Office : Cebu City District Engineering Office
6. Contractor : WERR CORPORATION INTERNATIONAL
7. Contractor Amount : ₱17,650,000.00
8. Contract Duration : 210 CD
9. Effectivity of Contract : December 26, 2016
10. Expiry Date : July 23, 2017
11. Approved Work Suspension Order No. 1 : 30 Calendar Days
12. Approved Cont. Work Suspension Order No. 1a : 30 Calendar Days
13. This proposed CWSO No. 1b as requested
by the Implemented Office : 30 Calendar Days
14. Approved Contract Time Extension No. 1 : 60 Calendar Days
15. Physical Accomplishment
15.1 Percent Work Accomplished
: 0.00%
(as of February 24, 2017)
15.2 Percent Work Scheduled
: 28.57%
(as of February 24, 2017)
15.3 Slippage : (-) 28.57%
16. Approved Expiry Date : September 21, 2017

Prepared by :

LITO O. CATUBIG
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City

CONTRACTUAL DATA

1. Name of Project : Construction / Improvement of Access Roads Leading to Declared


Tourism Destinations, S. Cabahug Street Leading to International
Hotel, Brgy. Mabolo, Cebu City
2. Contract ID No. : 17HH0121
3. Project Component : Concreting (Road)
4. Province : Cebu
5. Implementing Office : Cebu City District Engineering Office
6. Contractor : WIN CONSTRUCTION
7. Contractor Amount : Php 16,783,656.18
8. Contract Duration : 133 CD
9. Effectivity of Contract : March 15, 2018
10. Expiry Date : July 25, 2018
11. Approved Work Suspension Order No. 1 : 30 Calendar Days
12. Approved Cont. Work Suspension Order No. 1a : 30 Calendar Days
13. Approved Contract Time Extension No. 1 : 60 Calendar Days
14. Approved Cont. Work Suspension Order No. 1b : 30 Calendar Days
16. This proposed CWSO 1b as requested
by the Implemented Office : 150 Calendar Days
17. Physical Accomplishment
17.1 Percent Work Accomplished
: 0.00%
(as of August 23, 2017)
17.2 Percent Work Scheduled
: 100.00%
(as of August 23, 2017)
17.3 Slippage : (-) 100.00%
18. Approved Expiry Date : September 23, 2018

Prepared by :

LITO O. CATUBIG
Project Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City

CONTRACTUAL DATA

1. Name of Project : Construction of Senior High School Classrooms


and Additional Foundation Works, Pasil NHS,
Cebu City

2. Contract ID No. : 15HH0070


3. Project Component : Buildings (3 Storey 12 Classrooms)
4. Province : Cebu
5. Implementing Office : Cebu City District Engineering Office
6. Contractor : WERR CORPORATION INTERNATIONAL
7. Contractor Amount : ₱17,650,000.00
8. Contract Duration : 210 CD
9. Effectivity of Contract : December 26, 2016
10. Expiry Date : July 23, 2017
11. Approved Work Suspension Order No. 1 : 30 Calendar Days
12. Approved Contract Time Extension No. 1 : 30 Calendar Days
13. Approved Cont. Work Suspension Order No. 1a 30 Calendar Days
14. Approved Contract Time Extension No. 2 30 Calendar Days
15. Approved Cont. Work Suspension Order No. 1b 30 Calendar Days
16. Approved Contract Time Extension No. 3 30 Calendar Days
17. Approved Cont. Work Suspension Order No. 1c 30 Calendar Days
18. Approved Contract Time Extension No. 4 30 Calendar Days
19. This proposed CWSO No. 1d as requested :
by the Implemented Office - Calendar Days
20. Approved Expiry Date : March 20, 2018

Prepared by :

LITO O. CATUBIG
Project Engineer