ANNEX A-1

WORK SUSPENSION ORDER NO. 1 Local

Contract I.D. No.: : 17HH0019


Name of Project : Construction of Water Supply System in Barangay Babag, Cebu City
Location : Cebu City
Date : April 17, 2017

To:

ULYSSES JOHN P. TAN


President
15-2 V. Sotto Street,
Cebu City

You are hereby directed to suspend all construction operations on the above project effective
December 16, 2016 due to City Moratorium.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 75 Suspension Order: Time Extension: Days Used to date:
Contract Time (cd) (cd) (cd)
including W.S.O No. 1 C.T.E No. 1
Extensions: W.S.O No. 2 C.T.E No. 2 Days remaining:
(cd). 75 (cd)
Total Due to V.O.
Total:

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

STEPHEN ERIC G. CASTRODES


Project Engineer

NOTED:

LITO O. CATUBIG
Chief, Construction Section

RECOMMENDING APPROVAL: APPROVED:

JOSE R. GAURAN, JR. NICOMEDES S. LEONOR, JR.


Assistant District Engineer District Engineer

I hereby acknowledge receipt of the above notice.

DATE:
ULYSSES JOHN P. TAN
A.T. TAN CONSTRUCTION CORPORATION
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City
ANNEX C-1

WORK RESUMPTION ORDER NO. 1 Local

Contract I.D. No.: : 17HH0026


Name of Project : Construction / Maintenance of Flood Control and Mitigation Structures along Lahug River,
Brgy. Tinago and Brgy. Tejero, Cebu City
Location : Cebu City
Date : April 28, 2017

To:

PETER L. DY
Proprietor / Manager
P.C Suico St. Tabok,
Mandaue City

Effective to date, you are directed to resume construction operations in the project site.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 199 Suspension Order: 30 Time Extension: Days Used to date:
Contract Time (cd) (cd) (cd)
including W.S.O No. 1 30 C.T.E No. 1
Extensions: W.S.O No. 2 C.T.E No. 2 Days remaining:
(cd). 199 (cd)
Total 30 Due to V.O.
Total: 0

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

LITO O. CATUBIG
Project Engineer

NOTED: APPROVED:

LITO O. CATUBIG NICOMEDES S. LEONOR, JR.


Chief, Construction Section District Engineer

I hereby acknowledge receipt of the above notice.

DATE:
PETER L. DY
PLD CONSTRUCTION
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City

ANNEX A-2

Local
WORK SUSPENSION ORDER NO. 2

Contract I.D. No.: : 16HH0056


Name of Project : Road Concreting of Guadalupe Road, Cebu City 2nd LD.
Location : Cebu City
Date : December 15, 2016

To:

ULYSSES JOHN P. TAN


President
15-2 V. Sotto Street,
Cebu City

You are hereby directed to suspend all construction operations on the above project effective
December 16, 2016 due to City Moratorium.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 199 Suspension Order: 30 Time Extension: 30 Days Used to date:
Contract Time (cd) (cd) 30 (cd)
including W.S.O No. 1 30 C.T.E No. 1 30
Extensions: W.S.O No. 2 C.T.E No. 2 Days remaining:
(cd). 229 199 (cd)
Total 30 Due to V.O.
Total: 30

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

STEPHEN ERIC G. CASTRODES


Project Engineer

NOTED:

JOSE R. GAURAN, JR.


Assistant District Engineer

RECOMMENDING APPROVAL: APPROVED:

NICOMEDES S. LEONOR, JR. ADOR G. CANLAS, CESO IV


District Engineer Regional Director

I hereby acknowledge receipt of the above notice.

DATE:
ULYSSES JOHN P. TAN
A.T. TAN CONSTRUCTION CORPORATION
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City
ANNEX C-1

WORK RESUMPTION ORDER NO. 2


Local
Contract I.D. No.: : 17HH0026
Name of Project : Construction / Maintenance of Flood Control and Mitigation Structures along Lahug
River, Brgy. Tinago and Brgy. Tejero, Cebu City
Location : Cebu City
Date : June 07, 2017

To:

PETER L. DY
Proprietor / Manager
P.C Suico St. Tabok,
Mandaue City

Effective to date, you are directed to resume construction operations in the project site.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 199 Suspension Order: 60 Time Extension: 30 Days Used to date:
Contract Time (cd) (cd) 47 (cd)
including W.S.O No. 1 30 C.T.E No. 1 30
Extensions: W.S.O No. 2 30 C.T.E No. 2 Days remaining:
(cd). 259 212 (cd)
Total 60 Due to V.O.
Total: 30

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

VIOLETO C. ORBETA
Project Engineer

NOTED: APPROVED:

LITO O. CATUBIG NICOMEDES S. LEONOR, JR.


Chief, Construction Section District Engineer

I hereby acknowledge receipt of the above notice.

DATE:
PETER L. DY
PLD CONSTRUCTION
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City
ANNEX A-3

WORK SUSPENSION ORDER NO. 3 Local

Contract I.D. No.: : 16HH0056


Name of Project : Road Concreting of Guadalupe Road, Cebu City 2nd LD.
Location : Cebu City
Date : February 03, 2017

To:

ULYSSES JOHN P. TAN


President
15-2 V. Sotto Street,
Cebu City

You are hereby directed to suspend all construction operations on the above project effective
February 06, 2017 due to obstruction of pipe utilities underneath the road section.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 199 Suspension Order: 60 Time Extension: 60 Days Used to date:
Contract Time (cd) (cd) 52 (cd)
including W.S.O No. 1 30 C.T.E No. 1 30
Extensions: W.S.O No. 2 30 C.T.E No. 2 30 Days remaining:
W.S.O No. 3 C.T.E No. 3
(cd). 259 207 (cd)
Total 60 Due to V.O.
Total: 60

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

STEPHEN ERIC G. CASTRODES


Project Engineer

NOTED:

NICOMEDES S. LEONOR, JR.


District Engineer

RECOMMENDING APPROVAL: APPROVED:

ADOR G. CANLAS, CESO IV ROBERTO R. BERNARDO


Regional Director Assistant Secretary for Regional Operations in the
Visayas

I hereby acknowledge receipt of the above notice.

DATE:
ULYSSES JOHN P. TAN
A.T. TAN CONSTRUCTION CORPORATION
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City

ANNEX C-1

Local
WORK RESUMPTION ORDER NO. 3

Contract I.D. No.: : 16HH0056


Name of Project : Road Concreting of Guadalupe Road, Cebu City 2nd LD.
Location : Cebu City
: March 08, 2017

To:

ULYSSES JOHN P. TAN


President
15-2 V. Sotto Street,
Cebu City

Effective to date, you are directed to resume construction operations in the project site.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 199 Suspension Order: 90 Time Extension: 60 Days Used to date:
Contract Time (cd) (cd) 52 (cd)
including W.S.O No. 1 30 C.T.E No. 1 30
Extensions: W.S.O No. 2 30 C.T.E No. 2 30 Days remaining:
W.S.O No. 3 30 C.T.E No. 3
(cd). 289 237 (cd)
Total 90 Due to V.O.
Total: 60

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

STEPHEN ERIC G. CASTRODES


Project Engineer

NOTED: APPROVED:

LITO O. CATUBIG NICOMEDES S. LEONOR, JR.


Chief, Construction Section District Engineer

I hereby acknowledge receipt of the above notice.

DATE:
ULYSSES JOHN P. TAN
A.T. TAN CONSTRUCTION CORPORATION
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City
ANNEX A-4

WORK SUSPENSION ORDER NO. 4 Local

Contract I.D. No.: : 16HH0056


Name of Project : Road Concreting of Guadalupe Road, Cebu City 2nd LD.
Location : Cebu City
Date :

To:

ULYSSES JOHN P. TAN


President
15-2 V. Sotto Street,
Cebu City

You are hereby directed to suspend all construction operations on the above project effective
December 16, 2016 due to obstruction of pipe utilities underneath the road section.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 199 Suspension Order: 90 Time Extension: 90 Days Used to date:
Contract Time (cd) (cd) 30 (cd)
including W.S.O No. 1 30 C.T.E No. 1 30
Extensions: W.S.O No. 2 30 C.T.E No. 2 30 Days remaining:
W.S.O No. 3 30 C.T.E No. 3 30
W.S.O No. 4 C.T.E No. 4
(cd). 289 259 (cd)
Total 90 Due to V.O.
Total: 90

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

STEPHEN ERIC G. CASTRODES


Project Engineer

NOTED:

NICOMEDES S. LEONOR, JR.


District Engineer

RECOMMENDING APPROVAL: APPROVED:

ADOR G. CANLAS, CESO IV RAFAEL C. YABUT


Regional Director Senior Undersecretary for Regional Operations in
Visayas and Mindanao

I hereby acknowledge receipt of the above notice.

DATE:
ULYSSES JOHN P. TAN
A.T. TAN CONSTRUCTION CORPORATION
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City

ANNEX C-1

Local
WORK RESUMPTION ORDER NO. 4

Contract I.D. No.: : 16HH0056


Name of Project : Road Concreting of Guadalupe Road, Cebu City 2nd LD.
Location : Cebu City
: January 15, 2017

To:

ULYSSES JOHN P. TAN


President
15-2 V. Sotto Street,
Cebu City

Effective to date, you are directed to resume construction operations in the project site.

Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.

Original Contract Approved Work Approved Contract


Time:(cd) 75 Suspension Order: 120 Time Extension: 90 Days Used to date:
Contract Time (cd) (cd) 30 (cd)
including W.S.O No. 1 30 C.T.E No. 1 30
Extensions: W.S.O No. 2 30 C.T.E No. 2 30 Days remaining:
W.S.O No. 3 30 C.T.E No. 3 30
W.S.O No. 4 30 C.T.E No. 4
(cd). 195 165 (cd)
Total 120 Due to V.O.
Total: 90

Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.

STEPHEN ERIC G. CASTRODES


Project Engineer

NOTED: APPROVED:

LITO O. CATUBIG NICOMEDES S. LEONOR, JR.


Chief, Construction Section District Engineer

I hereby acknowledge receipt of the above notice.

DATE:
ULYSSES JOHN P. TAN
A.T. TAN CONSTRUCTION CORPORATION
Contractor
By:

Authorized Representative