Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


CEBU CITY DISTRICT ENGINEERING OFFICE
REGION VII
V. Sotto St., Cebu City

April 13, 2018

FOR : ADOR G. CANLAS, CESO IV


Regional Director

THRU : JUBY C. CORDON, CSEE


Assistant Regional Director

SUBJECT : Evaluation/Recommendation with Justification

This is in connection with the request of Continuance of Work Suspension for Construction /
Improvement of Access Roads Leading to Declared Tourism Destinations, S. Cabahug Street
Leading to International Hotel, Brgy. Mabolo, Cebu City. On the basis of submitted
documents, this office finds the request to be meritorious since it is not the fault of the
contractor and beyond the control of the Implementing Office that the contractor cannot
proceed due to pending of LGU permits and clearances.

Furthermore in accordance with Annex “K” of D.O. 70 series of 2017: Checklist of


Supporting Documents and Attachment for DoTS; Contract Time Suspension / Extension –
Additional supporting Documents for specific conditions:

K. Due to absence LGU permits / clearance / Homeowners Association


clearance / Permit

In view of the above evaluation, this request for continuance of work suspension order is
recommended for approval of the Regional Director, Ador G. Canlas, CESO IV.

Hoping for your kind consideration in this matter.

ELVIRA C. FERNANDEZ
Project Engineer

NOTED:

LITO O. CATUBIG
Chief, Construction Section

RO7.17.2 LOC/ecf