Name of Project : Construction / Completion of Multi-Purpose Building in Brgy. Babag, Cebu City
To:
PETER L. DY
Proprietor / Manager
P.C Suico St. Tabok,
Manduaue City
You are hereby directed to suspend all construction operations on the above project effective
immediately due to revision of Master Site Development Plan in order to accommodate the future
development for Level 1 service capability.
Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.
Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.
VIOLETO C. ORBETA
Project Engineer
NOTED:
LITO O. CATUBIG
Chief, Construction Section
DATE:
PETER L. DY
PLD CONSTRUCTION
Contractor
By:
Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGION VII
V. Sotto Street, Cebu City
ANNEX B-2
Local
CONTINUATION OF WORK SUSPENSION ORDER NO. 1a
To:
PETER L. DY
Proprietor / Manager
P.C Suico St. Tabok,
Manduaue City
You are hereby directed to suspend all construction operations on the above project effective
immediately due pending approval of the revision of plan since the location of the proposed building is
not specified.
Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.
Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.
VIOLETO C. ORBETA
Project Engineer
NOTED:
DATE:
PETER L. DY
PLD CONSTRUCTION
Contractor
By:
Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City ANNEX B-3
To:
PETER L. DY
Proprietor / Manager
P.C Suico St. Tabok,
Manduaue City
You are hereby directed to suspend all construction operations on the above project effective
immediately due pending approval of the revision of plan since the location of the proposed building is
not specified.
Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.
Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.
VIOLETO C. ORBETA
Project Engineer
NOTED:
DATE:
PETER L. DY
PLD CONSTRUCTION
Contractor
By:
Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City
ANNEX B-4
To:
PETER L. DY
Proprietor / Manager
P.C Suico St. Tabok,
Manduaue City
You are hereby directed to suspend all construction operations on the above project effective
immediately due pending approval of the revision of plan since the location of the proposed building is
not specified.
Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.
Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.
VIOLETO C. ORBETA
Project Engineer
NOTED:
DATE:
PETER L. DY
PLD CONSTRUCTION
Contractor
By:
Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City
ANNEX B-5
To:
PETER L. DY
Proprietor / Manager
P.C Suico St. Tabok,
Manduaue City
You are hereby directed to suspend all construction operations on the above project effective
immediately due pending approval of the revision of plan since the location of the proposed building is
not
specified.
Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.
Please acknowledge receipt of this order by signing (with date) and returning the three (3) of the
attached copies. The fourth copy is for your file.
VIOLETO C. ORBETA
Project Engineer
NOTED:
DATE:
PETER L. DY
PLD CONSTRUCTION
Contractor
By:
Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU CITY DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
V. Sotto Street, Cebu City
To:
Effective to date, you are directed to resume construction operations in the project site.
Hereunder is the historical data of your approved Work Suspension Order and Contract Time
Extension.
Please acknowledge receipt of this order by signing (with date) and returning the three (3) of
attached copies. The fourth copy is for your file.
NOTED: APPROVED:
LITO O. CATUBIG NICOMEDES S. LEONOR, JR.
Chief, Construction Section District Engineer
DATE:
ULYSSES JOHN P. TAN
A.T. TAN CONSTRUCTION CORPORATION
Contractor
By:
Authorized Representative
S
project site.
d Contract Time
Days remaining:
75 (cd)
ERIC G. CASTRODES
oject Engineer
DES S. LEONOR, JR.
trict Engineer
JOHN P. TAN
UCTION CORPORATION
d Representative