EXECUTIVE SUMMARY
(Request for Approval of C.T.E. No. 01)
1. Subject: Request for Approval of Contract Time Extension - C.T.E No. 01 for the
project: 17EH0013 - OFF-CARRIAGEWAY, IMPROVEMENT INCLUDING
DRAINAGE OF LUBI-BINOOG ROAD K0059+-1034-K0059+166(AS PER
RBIA), K0057+966-K0059+166(AS PER SURVEY)
2.
3. Action Recommended : For Approval
Per evaluation based on the attached documents, i.e. (1) Certification from the
Barangay Captain/City or Municipality Mayor that there is RROW problem and
the affected owners do not allow the entry of the contractor to their property; (2)
Geotagged pictures (with caption) of the site with RROW problem; (3) Certified True
Copy of Permit to Enter/writ of possession; (4) List of Properties/Lots/Structures
affected by RROW and with the recommendation of the Project Engineer.
Hereunder is the tabulated suspended days for the period March 30 to April 28, 2017
derived from the attached Approved Suspension and Resume Orders:
Scheduled : 100.00 %
Actual : 90.00 %
Slippage : (-) 10.00 %
10. Remarks:
10.3. Extension of contract time may be granted only when the affected
activities fall
within the critical path of the PERT/CPM network.
Based on the approved PERT/CPM Network Diagram, the items of Work within
the Critical Path that are affected by the suspension of works are; Item 102(2)
– Surplus Common Excavation; Item 103(3) – Foundation Fill; Item
104(1)a - Embankment from Roadway Excavation (Common Soil); Item
404(1)a – Reinforcing Steel Grade 40, Item 405(1)a2 – Structural
Concrete Class A; Item 506(1) – Stone Masonry.
With this proposed Contract Time Extension No. 1, the contractor has executed
an Affidavit of Quit Claim that they will not file any monetary/financial claim.
In view of the above premises, the request for Contract Time Extension No. 1
equivalent to thirty (30) calendar days is respectfully recommended pursuant to
D.O. No. 144, Series of 2016 and DO 106 Series of 2018, for the District
Engineer’s consideration and approval, subject however to the condition that
the written consent of bondsmen must be submitted and the validity of
the performance security shall be correspondingly extended in
accordance with the above mentioned provision of Sub-Section 10,5 of
Annex E of the Revised IRR of R.A. 9184.
ALAN T. SALVADOR
Chief, Construction Section
Approved:
NAPOLEON S. FAMADICO
District Engineer