Professional Documents
Culture Documents
EXECUTIVE SUMMARY
(Request for Approval of Variation Order – Change Order)
This proposed Final Variation Order involves increase and decrease in the quantities
of original work items in the contract which is based on the approved As-Staked Plan
to cover the changes which incorporate revisions/alterations deemed to suit with the
present/actual field conditions resulting to overrun and underrun of quantities.
5.1 Additive
102(2) – Surplus Common Excavation
103(3) – Foundation Fill
201(1) – Aggregate Base Course
500(1)b3 – Pipe Culverts 910 mm dia., Class IV
506(1) – Stone Masonry
5.2 Deductive
104(1)a – Embankment from Roadway Excavation (Common Soil)
505(2)a – Grouted Riprap
8. Contractual Data
Description Amount Contract Time Remarks
Time Extension
Original Contract Php 252 C.D.
Amount 93,795,759.68
This V.O. No.1 Php (+) 1.11 - -
Revised Contract Php - - (+)
Amount (If V.O. 93,795,760.79 0.00000000118%
No. 1 is increase from the
approved) original contract.
10.Per review, the unit price of work items with increase in quantities and covered by
the proposed Change Order were found similar or exactly the same to those in the
original contract.
1.2. A Change Order may be issued by the implementing official to cover any
increase/decrease in quantities of original work items in the contract, the
herein request is being submitted for favorable consideration and approval.
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE IV-B
Odiongan, Romblon
ALAN T. SALVADOR
Chief, Construction Section
Approved by:
NAPOLEON S. FAMADICO
District Engineer