Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


ROMBLON
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE IV-B
Odiongan, Romblon

EXECUTIVE SUMMARY
(Request for Approval of Variation Order – Change Order)

FOR : NAPOLEON S. FAMADICO


District Engineer
This Office

THRU : ROGER F. DAVID


Assistant District Engineer

1. Subject : Request for Approval of Variation Order – Change Order for


the project: 18EH0082 – Construction of Kabaliwan to Boliganay Road, San
Agustin, Romblon

2. Action Recommended : For Approval

3. Implementing Office : DPWH, Romblon District Engineering Office

4. Reviewing Office : Construction Section

5. Reasons for this Request :

This proposed Final Variation Order involves increase and decrease in the quantities
of original work items in the contract which is based on the approved As-Staked Plan
to cover the changes which incorporate revisions/alterations deemed to suit with the
present/actual field conditions resulting to overrun and underrun of quantities.

The proposed Final Variation Order involves mainly the following:

5.1 Additive
102(2) – Surplus Common Excavation
103(3) – Foundation Fill
201(1) – Aggregate Base Course
500(1)b3 – Pipe Culverts 910 mm dia., Class IV
506(1) – Stone Masonry

5.2 Deductive
104(1)a – Embankment from Roadway Excavation (Common Soil)
505(2)a – Grouted Riprap

6. Project Contractor : SUNWEST CONSTRUCTION AND DEVELOPMENT


CORPORATION
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE IV-B
Odiongan, Romblon

7. Project Status as of June 30, 2018:

Contract Effectivity : May 09, 2018


Original Completion Date : January 15, 2019
Schedule of Work Accomplished-Planned : 9.08 %
Percentage of Work Accomplished-Actual : 20.00 %
Slippage : 10.92 %
Remarks : On-Going

8. Contractual Data
Description Amount Contract Time Remarks
Time Extension
Original Contract Php 252 C.D.
Amount 93,795,759.68
This V.O. No.1 Php (+) 1.11 - -
Revised Contract Php - - (+)
Amount (If V.O. 93,795,760.79 0.00000000118%
No. 1 is increase from the
approved) original contract.

9. The quantities as presented in the Itemized Cost of Revision were reviewed/checked


by the Construction Section based on the approved As-Built Plan, Detailed Technical
Justifications and Detailed Quantity Estimate.

10.Per review, the unit price of work items with increase in quantities and covered by
the proposed Change Order were found similar or exactly the same to those in the
original contract.

11. In view of this, we respectfully recommend the approval of Variation Order


No. 01 in accordance with Department Order No. 148, Series of 2018 known
as “Implementation of the Document Tracking System (DoTS) for Civil Works”
and based on the provisions of Annex E of the 2016 Revised Implementing
Rules and Regulations (IRR) of Republic Act (RA) 9184 states that:

1.2. A Change Order may be issued by the implementing official to cover any
increase/decrease in quantities of original work items in the contract, the
herein request is being submitted for favorable consideration and approval.
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE IV-B
Odiongan, Romblon

In view of the foregoing and as per favorable recommendation of the Project


Engineer, the herein Final Variation Order for the contract of SUNWEST CONSTRUCTION
AND DEVELOPMENT CORPORATION in connection with the implementation of the
above subject project, is respectfully submitted for approval.

ALAN T. SALVADOR
Chief, Construction Section

Approved by:

NAPOLEON S. FAMADICO
District Engineer