You are on page 1of 172

COMMENTS RESOLUTION SHEET  

[ CRS ]
CONTRACT NUMBER:  GC16101100  QP PROJECT NUMBER  3963 
CONTRACT TITLE:  EPIC FOR  REPLACEMENT OF OLD 3‐PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DUKHAN 
QP EXTERNAL TRANSMITTAL REFERENCE :  EDD/GC16101100/EXT/TN/3945  DATE: 13‐11‐2018 
DOCUMENT NUMBER:  3963‐DGEN‐0‐04‐0001  DOCUMENT REVISION: D 
DOCUMENT TITLE:  Project Planning Package 
No.  QP COMMENTS CONTRACTOR RESPONSE

General comment related with P6 integrity:


1. 27 activities out of sequence 1. Noted & Incorporated
1. 2. 5 activities, actual date > data dates
3. 21 activities have invalid relationships
4. 1 activity with schedule loop
5. And the others, please see your schedule log created from P6.
2. Att 1.1, overall s curve. S curve still showing timeline till Feb 2019, please
revise. 2. Noted & Incorporated
PP item 10, page 7 of 12
detailed Tie-in schedule shall be submit at least 4 months before SD 3. CPECC submit detailed Tie-in Schedule for JALM along Rev-D Planning
3.
Package & for FAHM, FAHN & FAHS in last week ofDec-18.
See Attachment 3

Construction planned to be completed in July 2019, but the manpower 4. Until May-18 only construction activities including Commissioning are
4. histogram assign manpower until May planned & As Built and Final Dossier are planned from 23-May-19 to 22-July-
2019. Please clarify? 19.
Page 3 of 12, item 1.0 5. Noted & Incorporated.
1. Qatar diplomatic crisis is not a valid reason for the delay, since SD for
Khatiyah sector has been completed and the rest can be planned accordingly.
This issue shall be removed from Planning package.
2. Weather condition shall be removed from planning package. High humidity
5. during summer is annual event in
Qatar, Contractor shall plan accordingly for this matter. This issue shall be
removed from planning package.
3. Clashes with underground facilities. It's contractor scope to do UG Survey
as per App A, 4.2.1.1.1 of the
contract. The statement that said this is beyond CPECC shall be removed from
Planning package.
 
6. Put triangle with rev. no/letter on the content that has been change from the 6. Noted & Incorporated
previous revision
Precomm and comm weightage has been change from the previous rev 7. Progress & weightage for Pre commissioning and commissioning retained
7. (indvidual and phase). Please clarify? same as per actual on 25-10-18

In the previous revision, Precomm and commissioning has actual progress 8. Refer Sr. No. 7 response 
from the documents (Preparation of plan and procedures for
8.
recommissioning). Why the weightage for those documents has been removed
in the rev.C.
Please clarify?
Activity ID A3100-5, Jaleha shutdown windows is 2 to 23 March 2019. 9.  Refer Sr. No. 3 response 
9. CPECC planned to have it in the last week
(18 to 23 March 2019)? Please clarify? If any unexpecting event occur, we
don't have any buffer time.
Piping Fabrication for Jaleha and Fahahil seem not as main priority? Jaleha . 10. Currently Piping fabrication for Jaleha & Fahahil degassing station in
and Fahahil, especially piping for Shutdown tie in shall be assign as main progress at Medgulf & Dopet facility in Qatar for CS pipes & FBE coated pipes
10. priority to avoid delay during SD time. at Kuwait. CPECC continuing expediting the fabrication progress for Jaleha &
Fahahil in order to deliver the material at site before Shutdown avoid the delay
during SD time ongoing . 

Submit native CRS along with the revised document/drawing.  
PROJECT / CONTRACT REF.: 3963 / GC16101100
CONTRACT TITLE: -

EPIC FOR REPLACEMENT OF OLD 3-PHASE


TEST SEPARATORS AT ALL DEGASSING
STATIONS IN DUKHAN

Project Planning Package

China Petroleum Engineering & Construction Corporation

th Ding
4 DEC 2018 D RE-ISSUED FOR CONSTRUCTION Vivek / Taimoor Zafar/WDH
Guiping
th Ding
4 Nov 2018 C RE-ISSUED FOR CONSTRUCTION Vivek / Taimoor Zafar/WDH
Guiping
th
29 July 2018 B RE-ISSUED FOR CONSTRUCTION Vivek Zafar/WDH Wang Xilin
th
26 Mar 2018 A APPROVED FOR CONSTRUCTION Vivek Zafar/WDH Wang Xilin

10th Aug 2 RE-ISSUED FOR APPROVAL Vivek Zafar/WDH Wang Xilin


th
7 May 1 ISSUED FOR APPROVAL Vivek Wang Danghui Wang Xilin
th
16 Mar 0 ISSUED FOR COMMENTS Li Xiuwang Zafar Wang Xilin
APPD.
DATE REV. NO REASON FOR REVISION PREPARED CHECKED APPD.
QP

DOCUMENT NUMBER: 3963-DGEN-0-04-0001 SHT. 001 OF 008 REV. D

Page 1 of 170
PROJECT PLANNING PACKAGE

TABLE OF CONTENT

1.0 INTRODUCTION: ......................................................................................................................................................3

2.0 INTEGRATED PLANNING NETWORK ........................................................................................................................3

2.1 WEIGHTAGE SYSTEM & S-CURVES: .........................................................................................................................4

3.0 MANPOWER DEPLOYMENT: ....................................................................................................................................4

4.0 PROGRESS MEASUREMENT SYSTEM .......................................................................................................................4

4.1 DETAILED ENGINEERING: ........................................................................................................................................4

4.2 PROCUREMENT: ......................................................................................................................................................5

5.0 EGINEERING DESIGN DRAWING REGISTER (EDDR): ................................................................................................5

6.0 PROCUREMENT REGISTER & PROJECT DOCUMENT REGISTER: ..............................................................................6

7.0 CONSTRUCTION CONTROL REGISTER: .....................................................................................................................6

8.0 EQUIPMENT DEPLOYMENT PLAN: ...........................................................................................................................6

9.0 PROGRESS REPORTING (Monthly, Weekly & Daily): ...............................................................................................6

10.0 Shown Tie-in break down: .....................................................................................................................................7

11.0 Project Execution:..................................................................................................................................................7

11.1 Execution Policy .....................................................................................................................................................7

11.2 Engineering Execution Plan: ..................................................................................................................................7

11.3 Procurement:.........................................................................................................................................................8

11.4 Construction & Commissioning Management: .....................................................................................................9

11.5 Construction Works Execution: .............................................................................................................................9

11.6 Civil works:.......................................................................................................................................................... 10

11.7 Piping Works:...................................................................................................................................................... 10

11.8 Electrical & Instrumentation: ............................................................................................................................. 10

11.9 Pre-commissioning and Commissioning: ........................................................................................................... 10

11.10 Quality Plan: ..................................................................................................................................................... 11

12.0 ATTACHMENTS: .................................................................................................................................................. 11

2|Page
Page 2 of 170
PROJECT PLANNING PACKAGE

1.0 INTRODUCTION:

CPECC hereby is submitting revised project schedule, incorporating QP letter


QP/PND/GC16101100/CP/F/034 for the revised commencement date of the
demolishing for Existing Test Separator in FAHM and shutdown tie-in window and
FAHM, FAHS, FAHN and JAHM.

Commissioning Completion dates for the stations are as follow:


 KAHS : 26th Jan 2019.
 KAHM – 27th Jan 2019.
 KAHN: 29th Jan 2019.
 JALM – 6th April 2019
 FAHN – 9th May 2019
Rev-D
 FAHS – 20th May 2019
 FAHM – 22th May 2019
Milestone completion dates are as follow:
 MS1 – 22th May 2019
 MS-2 (Handover final dossier) – 22 July 2019

Apart from the impact on the Project Schedule due to shutdown tie-ins dates and
commencement date for FAHM demolishing of existing test separator, following events
have also impacted the Project schedule, which are beyond CPECC’s control:

• Less Quantity of Piping Bulk Items - Due to less quantity of piping material, we were
constrained to choose stockiest in UAE to supply material with 3.1 certification plus test
and re-routed from UAE to Qatar from different countries.

• Authority prolong approval for various lifting documents and certificates and personals

• Delay due to ambiguities/discrepancies/conflicting information in FEED documents.

• Substantially increased in FEED quantities in the range of 40% to 200% for steel
structural, piping, valves, electrical cable, and instrumentation cable.

• Reschedule of Khatiyah stations shutdown from Oct-Nov 2018 to Jan-Feb 2018


In view of above, CPECC further requests QP to approve the revised Project schedule.
CPECC hereby commencing weekly and monthly report.

2.0 INTEGRATED PLANNING NETWORK

Planning & scheduling is developed using Primavera Project Planner Version 6 R8.2

3|Page
Page 3 of 170
PROJECT PLANNING PACKAGE

Manpower estimated for completion of each construction based on productivity, which in


detailed define in productivity sheet, attachment-11, which define to manpower require
for the scope of work. Progress for Engineering is based on man-hours required to
produce Engineering deliverables detailed in register. Procurement is based on cost of
the item of procurement detailed in the procurement register. The schedule proposed to
be updated weekly and utilized for calculation of earned values for S-Curves . Detailed
schedule with planned early start, early finish and original duration is enclosed under
Attachment-1.

2.1 WEIGHTAGE SYSTEM & S-CURVES:

Cost based Lev-1 weightage, which define as below, further to fulfill the requirement of
appendix D for minimum % weightage of Pre-Commissioning & Handover Dossier,
CPECC proposed Lev-1 weightage as below for QP approval.

LEV-1 COST ADJUSTMENT to accommodate 10% Commissionning


Contract Price 10% for comm adjust amount Revised price Cost %

Preliminaries General Matters for monitorting

Engineering 1,602,400.00 112,168.00 1,490,232.00 3.98%

Procurement 26,216,183.00 1,835,132.81 24,326,918.00 65.02%

Const & Inst 8,446,834.00 591,278.38 7,855,555.62 21.00%

Pre-Comm & Comm 1,148,701.00 3,741,411.80 2,592,710.80 3,741,411.80 10.00%

Final Handover Dossier

37,414,118.00 3,741,411.80 37,414,117.42 100.00%

The Lev-2 Progress table, weightage factors, Cost distribution details and S-Curves are
enclosed under attachment-2.

3.0 MANPOWER DEPLOYMENT:

Manpower deployment is developed based on estimated manpower required for


completion of all EPC phases. Detailed matrix of trade wise manpower estimated is
enclosed under attachment 5.0.

4.0 PROGRESS MEASUREMENT SYSTEM


4.1 DETAILED ENGINEERING:

Cumulative scales of progress should be compiled using controllable steps of physical


work achievements for each generic type of document. Actual progress shall be
calculated from the document status register.

4|Page
Page 4 of 170
PROJECT PLANNING PACKAGE

 Start on Drawing Board in a logical sequence - 5%


 Issue for QP review, (IFC) - 40%
 Issued for QP approval, (IFA) - 65%
 Issued as Approved for Construction, ( AFC with hold ) - 85%
 Issued Approved for Construction (AFC without hold) - 95%
 Issue As built - 100%

4.2 PROCUREMENT:

For procurement, cumulative scales of progress shall be established to monitor each


item from the inquiry stage up to the delivery and acceptance at Site. Actual progress
shall be calculated from the procurement status register.
Two different scales shall apply for Equipment and bulk supply.
The progress scale for each package shall be:
 Issue MR for QP approval - 5%
 Issue RFQ to Vendors - 10%
 Issue Purchase Order - 15%
 Vendor Drawing Approval - 30%
 Receipt of filled SPIR - 40%
 Inspection cleared and factory tested - 60%
 Ex-Works Delivery and FOB Complete - 70%
 Material received and inspected at Construction site - 85%
 QP inspected and cleared material at site - 90%
 All spare parts rec’d and SPIR completed -100%

Bulk Material for Progress tracking only (If deemed necessary by QP)
The progress scale for each Purchase Order or Sub-contract shall be:

 Issue RFQ to Vendors - 5%


 Place order for Bulk material – 15%
 Material Delivery Ex-works (50% of estimated quantity) - 30%
 Material Delivery Ex-works (90% of estimated quantity) - 40%
 Material received at Const. Site(50% of estimated qty) - 50%
 90% Material received at Construction Site - 80%
 All Material received and purchase order closed - 100%

5.0 EGINEERING DESIGN DRAWING REGISTER (EDDR):

Project document register developed based on execution schedule, scope of work in


consultation with Engineering team and Discipline Engineers. Project Document
Registers are enclosed under attachment 6.0

5|Page
Page 5 of 170
PROJECT PLANNING PACKAGE

6.0 PROCUREMENT REGISTER & PROJECT DOCUMENT REGISTER:

Procurement register developed based on Execution schedule, scope of work in


consultation with Engineering and Discipline Project Engineers. Procurement enclosed
under attachment 7.0.

7.0 CONSTRUCTION CONTROL REGISTER:

Construction Control Register is developed based on Execution schedule, scope of


work based on quantity and productivity. Construction register format enclosed under
attachment 8.0.

8.0 EQUIPMENT DEPLOYMENT PLAN:

Equipment deployment plan is prepared in consultation with the project execution team.
The plan is issued at the start of the project according to the equipment identified in the
bid/budget of the job. Equipment deployment plan is enclosed under attachment 9.0

9.0 PROGRESS REPORTING (Monthly, Weekly & Daily):

A weekly progress report with Thursday of the week as cut off shall be submitted
to QP on every Sunday early.
(Weekly progress reporting formats are enclosed under attachment 10.0

The Monthly Progress Report (MPR) shall be submitted under a cover of transmittal
sheet, during the entire duration of the CONTRACT, with last Thursday in a
calendar month as cut-of. The report shall be submitted to QP on Sunday and is
treated as monthly cut-off, unless otherwise agreed. Monthly Progress Reporting
formats are enclosed under attachment 11.0

During Construction Phase Daily Report shall be submitted each morning a daily
progress from the previous day, This includes Split trade manpower, machinery
deployment (including subcontractor) material received at site, achieved quantities
for the major activities. Detailed format and content for the report is finalized in
consultation with QP REPRESENTATIVE.

Critical Path:

Total float less than or equal to 5 days considered as critical activities in revised
schedule.
There are two critical paths in the current schedule.
1. Driven from procurement, installation pre-commissioning and commissioning of
Deluge Skid.

6|Page
Page 6 of 170
PROJECT PLANNING PACKAGE

2. Driven from release for demolition of Existing Test Separator in Fahahil Main,
construction for new foundation, installation of New Test Separator associate pipping,
instrumentation, pre-commissioning and commissioning.

10.0 Shown Tie-in break down:

CPECC will submit detailed Tie-in schedule during shutdown works 4 month before the
start for shutdown.

11.0 Project Execution:

11.1 Execution Policy

To ensure the success of the Project, CPECC shall made the following commitment in
undertaking the Engineering, Procurement, Construction and Commissioning of the
Facility:

CPECC will carry out the Works in accordance with the requirement given in the
CONTRACT.

Higher priority will be given to HSE issues throughout every phase of the Project.
CPECC will strictly enforce our Corporate Safety Policy which is “Zero-Accident” and to
promote the highest standard of safety in the industry.

Throughout the execution of the Project, CPECC will maintain the Quality Standard
embodied within the Project requirements for world-class facility.
CPECC will draw maximum synergies from the utilization of our technical and
operational specialties, while optimizing proficiency from standardization of activities.
Majority of the scope of WORK for engineering, procurement, construction and
commissioning are planned to self-perform by CPECC. Minor works like Site
investigation & survey, TPI, temporary facilities works, etc. will be subcontracted to
others.

Early Tie-in works for Khatiya Stations are critically planned & executed for early
engineering, procurement at early phase of the project.

11.2 Engineering Execution Plan:

Design and detail engineering activities will be carried out at our Engineering Office in
Dubai. The full engineering scope shall maximized the synergies arising from the best
utilization of available technical excellence and qualified resources our engineering
organization.

The Dubai Office will be responsible for the overall project areas as follows:
 Detailed Engineering
 Procurement Management

7|Page
Page 7 of 170
PROJECT PLANNING PACKAGE

 Expediting Material
 Third Party Studies and Design Review.

First main step will be definition of the Technical Design Basis and Early Tie-in package,
which cover early tie-in philosophy, data sheets and specification for early tie-in
materials, in liaison with the COMPANY and follow by the preparation of general
technical specifications, procedures and documentation, common throughout the whole
project. These preliminary activities will be executed from Dubai office, where
COMPANY’s reviews will take place through online ASSAI system
The project engineering office in Dubai coordinates further to Qatar Site Office,
according to well established Corporate Procedures and Work Practices.
Proper coordination and contribution from Qatar Site will be ensured through the in-
charge Field Construction team and/or specific assignments of concerned Specialists
Sub Contractor (e.g. Site Investigation Sub Contractor).
As Company instruction, detailed engineering will prepare early tie-in package, which
allows for early procurement of valves pipes and fittings to accommodate Khatiya
Shutdown plans in Jan and Feb 2018.

11.3 Procurement:

Procurement activities for early tie-in materials are planned at early phase of project
follow by project remaining materials.

Project Procurement will be managed as to ensure that the following main objectives
are reached: Procurement of fit for purpose materials from project approved Vendors
only, and in compliance with the project’s technical, quality and safety requirements;
Procurement in compliance with project schedule requirements, with timely delivery of
information from vendors to engineering and materials to Construction;
Procurement against the budget and Contract requirements.

Relevant main drivers will be:

Overall coordination of procurement activities to ensure consistency and homogeneous


implementation of common principles and procedures throughout the whole project,
under the responsibility of Project Management Team, from Qatar Home Office, as well
as support Qatar Site office for local procurement, whenever needed; Tried and tested
execution systems; Maximization of materials standardization, and early spare parts
definition and purchasing, in coordination with COMPANY;

Special care will be devoted to procurement of long lead items on schedule and out of
the critical path. In this respect, CPECC will Early issue of purchased orders (as
practical as possible), based on material requisitions developed during the bidding
phase; Implement close expediting and control of vendor data Operate a high level of
surveillance at vendors’ workshops to monitor the progress of manufacturing; With
regard to critical items. CPECC intends at maximum possible extent to manage their
purchased Order by placing blanket purchased orders based initially on preliminary
MTO and the piping classes’ specifications developed by CPECC from those available
in ITT documentations.

8|Page
Page 8 of 170
PROJECT PLANNING PACKAGE

Details on Procurement organization, vendor’s qualification, expediting and inspection


procedures and traffic & logistics plans as well as on material management systems are
further given within the Procurement Plan and associated procedures.

11.4 Construction & Commissioning Management:

The Project Manager is mobilized to Qatar Site to take the overall management of the
project from the Site. A team of appointed staffs mainly the Construction Manager and
construction supervisory staffs from CPECC corporate resources will carry out Site
Construction Management.

At Dubai Office, construction will be carried-out during planning stage. The early
involvement of Construction as well as Commissioning personnel is to familiarize with
the project and assist in the development of the project plans and to provide input and
direction to the overall project team.

The organization Site Management Head will define the requirements for the Project,
will monitor the implementation of the same and will interface the COMPANY.
This team will coordinate the Construction Supervision Organization of CPECC that will
be tailored for the follow-up of Works on field according to discipline and physical areas.
Activities of the construction management team will start early after effective date,
integrating with Dubai Office and Qatar Site Office, as needed to fully and smoothly
prepare and plan in advance all construction activities and the issue and delivery to site
of all needed deliverables, documents and materials, within the planned schedule.

11.5 Construction Works Execution:

This will be carried out through a majority of self-performance by CPECC, a balanced


mix of subcontracts (mainly civil works), as to maximize works execution efficiency and
quality under the supervision of CPECC’s Site Management Team. This joint team will
coordinate the Field supervision groups in charge for the different Site Areas.
A single system of Site procedures and method statements will be followed in the
execution of works across the whole site and close liaison with the Engineering
Organization will be maintained in order to ensure the most effective transfer of
information from engineering to construction.

Fabrication and laydown area is planned in Dukhan field, however to ensure early tie-in
timely completion. Local sub-contractor for fabrication and painting of early tie-in works
also under evaluation.

The revised plan schedule mechanical, instrumentation works are driven by material
deliveries, fabrication and delivery to site. However, civil works are carried out
independently.

9|Page
Page 9 of 170
PROJECT PLANNING PACKAGE

Calendar :

• For construction and pre-commissioning is consider 6days/ week.


• For commissioning is consider 7 days/ week
• Eid holidays consider only one day off, remaining days continue will be working.

11.6 Civil works:

Equipment foundations are most ready in all station stations except Fahahil Main.

Pipe support foundations are in progress at Fahahil and Jaleha stations. Due to clashes
with existing foundation. CPECC Civil Engineer spent two weeks at site in the month of
July to resolve the site clashed. Revised pipe support drawings are AFC by End Aug,
hence the pipe support is planned accordingly. However, as lesson learn from
excavation low productivity. CPECC adding more manpower for the excavation of pipe
supports, & remaining civil works.

Steel Structure Fabrication is in progress with sub-contractor in Doha and closely


monitored to achieve the deliveries for smooth execution of erection and installation
activity.

11.7 Piping Works:


Piping fabrication also planned in two shifts, in order to mitigate the late delivery of
materials.

For Non FBE coated pipes. The pipes will be fabricated in Qatar in Med gulf & Dopet
fabrication facility, which are performing as Sub-Contractor for CPECC for Piping
fabrication work.

For FBE coated pipes. The pipes will be fabricated in Kuwait with the same fabricator,
who will do the FBE coating.
11.8 Electrical & Instrumentation:

CPECC has awarded subcontract for E&I works to IMCO for 3 Khatiyah degassing
station & remaining 4 station shall be executed by CPECC E&I team as per the revised
schedule.

11.9 Pre-commissioning and Commissioning:

A team from CPECC will organize and supervise the activity that will be physically
carried out by manpower from CPECC with vendor site support. CPECC will lead the
management side (system breakdowns, turnover procedures and the like) CPECC will
arrange Vendors’ assistance as required, supported by timely planning of activities to
ensure coping with project completion schedule.

Preparatory activities relevant to Pre-commissioning and Commissioning management


will start timely after effective date in the Home Office, in order to define and plan in

10 | P a g e
Page 10 of 170
PROJECT PLANNING PACKAGE

advance all systems and units commissioning activities in coordination with and driving
the construction plans, as well as instructing specific commissioning requirements to the
Engineering specialists.

11.10 Quality Plan:

CPECC’s management system utilizes certified ISO 9001:2000 Quality Systems as a


basis, supported by project specific plans and procedures to ensure that systemic
auditable controls are in place and expectations are being met.

WPS and PQR will be developed at early phase of project to facilitate early tie-in
fabrication works.

CPECC will develop a comprehensive Quality Plan in order to ensure that all HSE,
Quality and Technical Integrity issues relating to the satisfactory execution of the works
in full compliance with all applicable codes, standards, specifications and COMPANY
expectations are identified and satisfactorily managed. This Quality Plan will also
address in a systematic manner the major actions required to satisfactorily complete all
Project phases, detailing process and procedures to be followed by the Engineering,
Procurement, Construction and Commissioning Resources to achieve the COMPANY
HSE, Quality and Technical Integrity Expectations.

A Quality Assurance/ Quality Control Manager is appointed on the Project with the
responsibility to maintain a high-level overview and audit function to ensure that
measures are taken to grant compliance with the Assurance Plan at all levels of
CPECC’s organization.

12.0 ATTACHMENTS:

Attachment -1 Updated Revised Baseline Schedule

Attachment -2 Critical path

Attachment -3 Jaleha Shutdown Schedule

Attachment – 4 Progress table, weightage factors lev-2

Attachment – 5 S-Curves

Attachment - 6 Manpower Histogram

Attachment - 7 EDDR

Attachment - 8 Procurement Register

11 | P a g e
Page 11 of 170
PROJECT PLANNING PACKAGE

Attachment - 9 Construction Control Register

Attachment - 10 Construction Equipment Deployment Register

Attachment - 11 Weekly Report format

Attachment - 12 Monthly Report Format

Attachment - 13 Productivity Calculation

Attachment - 14 Invoice Format

12 | P a g e
Page 12 of 170
PROJECT PLANNING PACKAGE

Attachment 1

UPDATED REVISED BASELINE SCHEDULE

Page 13 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 1 of32 29-Nov-18 17:45
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

Rev-D by TA E
EPIC for Replacement of Old 3-Phase Test Separators at A 07-Feb-17 18-Feb-19 785 290 06-Feb-17 A 22-Jul-19 0

Milestone 07-Feb-17 18-Feb-19 785 276 06-Feb-17 A 22-Jul-19 0


A1000 CONTRACT AWARD 07-Feb-17 0 100% 0 06-Feb-17 A
DE1000 EFFECTIVE DATE 19-Feb-17 0 100% 0 19-Feb-17 A
DE3380 ALL WORKS COMPLETE - MS1 18-Dec-18 0 0% 0 22-May-19* 0
DE1010 ACHIEVED - SCHEDULE COMPLETE 18-Feb-19 0 0% 0 22-Jul-19* 0
Detailed Engineering
Enginee 01-Apr-17 20-Sep-17 124 0 20-Apr-17 A 31-Dec-18 145
DE3320 ISSUE SHUTDOWN VALVE MTO/ DATASHEETS/ SPECIFICATION 01-Apr-17 0 100% 0 20-Apr-17 A
DE3330 ISSUE SHUTDOWN PIPING AND BULK MTO 27-Apr-17 0 100% 0 08-May-17 A
DE3260 ISSUE DESIGN BASE MEMORANDUM 08-May-17 0 100% 0 29-Jun-17 A
DE3270 ISSUE MR FOR TEST SEPARATORS 13-May-17 0 100% 0 28-May-17 A
DE3280 ISSUE MR FOR METERING 13-May-17 0 100% 0 12-Jul-17 A
DE3310 ISSUE SHUTDOWN PHILOSOPHY 15-May-17 0 100% 0 13-Jul-17 A
DE1020 HAZOP STUDY WORKSHOP 24-May-17 0 100% 0 08-Nov-17 A
DE3300 MR FOR DCS MODIFICATION 28-Jun-17 0 100% 0 10-Aug-17 A
DE3290 ISSUE MR FOR DELUGE 19-Jul-17 0 100% 0 25-Jul-17 A
DE1030 EQUIPMENT FOUNDATIONS AFC 03-Sep-17 0 100% 0 28-Jun-18 A
DE1040 DETAILED ENGINEERING COMPLETE 20-Sep-17 0 0% 0 31-Dec-18 145
Procurement 08-May-17 14-Jul-18 452 75 11-May-17 A 31-Jan-19 119
DE3340 PO ISSUE SHUTDOWN VALVE FOR THREE STATIONS 08-May-17 0 100% 0 11-May-17 A
DE3350 PO ISSUE SHUTDOWN PIPING/ FITTING & BULK FOR THREE STATIONS 28-May-17 0 100% 0 17-Jul-17 A
DE3200 PO ISSUE FOR TEST SEPARATOR 19-Jul-17 0 100% 0 10-Sep-17 A
DE3370 DELIVERY OF PIPING AND FITTINGS FOR KS SHUTDOWN 16-Aug-17 0 100% 0 02-Nov-17 A
DE3240 PO FOR DCS MODIFICATION 05-Sep-17 0 100% 0 28-Dec-17 A
DE3220 PO ISSUE OF DELUGE SKID 27-Sep-17 0 100% 0 22-Feb-18 A
DE3360 DELIVERY OF VALVES KS FOR SHUTDOWN 30-Sep-17 0 100% 0 31-Oct-17 A
DE3250 DELIVERY OF DCS MODIFICATION SITE-EARLY TIE-IN 03-May-18 0 100% 0 20-Jan-18 A
DE3210 DELIVERY OF TEST SEPARATOR AT SITE (Last Batch) 14-Jul-18 0 100% 0 25-Aug-18 A
DE7260 DELIVERY OF DCS MODIFICATION WORK 0 0% 0 13-Dec-18 11
DE7280 DELIVERY OF DELUGE SKID SITE - 1st batch 0 0% 0 31-Dec-18 55
DE7290 DELIVERY OF FBE COATED PIPE AT SITE FROM KUWAIT 0 0% 0 01-Jan-19 36
DE7300 DELIVERY OF GGC VALVE 0 100% 0 11-Jul-18 A
DE7310 DELIVERY OF BALL VALVES 0 100% 0 13-Sep-18 A
DE7320 DELIVERY OF CONTROL VALVES 0 100% 0 28-Aug-18 A
DE7330 DELIVERY OF FLOW METERS 0 0% 0 10-Dec-18 19
DE7340 DELIVERY OF BS&W 0 100% 0 27-Sep-18 A
DE7350 DELIVERY OF INSTRUMENT CALBES 0 0% 0 22-Nov-18 22
DE7360 DELIVERY OF LEVEL GUAGE GLASS TYPE 0 0% 0 10-Dec-18 22
DE7370 DELIVERY OF MAGNETIC TYPES GUAGES 0 0% 0 10-Dec-18 15
DE7380 DELIVERY OF GUAGES PG / TG 0 0% 0 10-Dec-18 14
DE7390 DELIVERY OF 1ST BATCH OF PIPING 0 100% 0 30-Jul-18 A
DE7400 DELIVERY OF LAST BATCH OF PIPING 0 100% 0 27-Sep-18 A
DE7410 DELIVERY OF SDV/BDV 0 0% 0 20-Dec-18 11
DE7420 DDELIVERY OF DELUGE SKID 2ND BATCH 0 0% 0 31-Jan-19 9
Construction 03-Oct-17 08-Dec-18 368 169 10-Dec-17 A 22-May-19 0
A1050 KAHM START WORKS 03-Oct-17 0 100% 0 10-Dec-17 A
A1060 KAHN START WORKS 29-Nov-17 0 100% 0 16-Dec-17 A
A1070 KAHS START WORKS 10-Jan-18 0 100% 0 25-Dec-17 A
A1080 JALM START WORKS 20-Feb-18 0 100% 0 05-Jun-18 A

Primary Baseline 3963-Rev-D.-1 Page 1 of 32 U-3963_REV-D


Date Revision Checked Approved
Actual Work
CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION 29-Nov-18 Rev-D Revised schedule
Remaining Work
06-Nov-18 Rev-C Revised schedule
Critical Remaining Work Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in
Baseline Milestone Dukhan
Milestone
U3963- Updated Revised Baseline Schedule.

Page 14 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 2 of32 29-Nov-18 17:45
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A1090 FAHS START WORKS 28-Apr-18 0 100% 0 08-Apr-18 A
A1190 FAHM START WORKS - ISOLATION OF EXISTING SEPARATOR 09-May-18 0 0% 0 07-Nov-18 44
A1180 FAHN START WORKS 19-Jun-18 0 100% 0 05-May-18 A
A1020 START OF 1ST INSTALLATION OF TEST SEPARATOR 15-Jul-18 0 100% 0 09-Aug-18 A
Shutdown Tie-in for Khatiyah North 24-Oct-17 06-Dec-17 38 0 07-Jan-18 A 14-Feb-18 A
A1100 SHUTDOWN START 24-Oct-17 0 100% 0 07-Jan-18 A
A1170 SHUTDOWN COMPLETE 06-Dec-17 0 100% 0 14-Feb-18 A
Shutdown Tie-in for Khatiyah Main 06-Nov-17 23-Dec-17 39 0 11-Jan-18 A 14-Feb-18 A
A1110 SHUTDOWN START 06-Nov-17 0 100% 0 11-Jan-18 A
A1200 SHUTDOWN COMPLETE 23-Dec-17 0 100% 0 14-Feb-18 A
Shutdown Tie-in for Khatiyah South 07-Nov-17 23-Dec-17 38 0 06-Feb-18 A 17-Feb-18 A
A1120 SHUTDOWN START 07-Nov-17 0 100% 0 06-Feb-18 A
A1210 SHUTDOWN COMPLETE 23-Dec-17 0 100% 0 17-Feb-18 A
JALM Tie-ins 08-Oct-18 08-Oct-18 0 12 28-Feb-19 16-Mar-19 19
A1220 FLARE HEADER HOT TAPPING COMPLETE 08-Oct-18 0 0% 0 28-Feb-19 31
A1330 SHUTDOWN TIE-IN 0 0% 0 16-Mar-19 9
Fahahil South Tie
Tie-ins 25-Oct-18 25-Oct-18 0 0 22-Apr-19 22-Apr-19 24
A1230 FLARE HEADER HOT TAPPING COMPLETE 25-Oct-18 0 0% 0 22-Apr-19 24
A1340 SHUTDOWN TIE-INS 0 0% 0 22-Apr-19 15
Fahahil North Tie
Tie-ins 29-Oct-18 17-Nov-18 16 0 22-Apr-19 22-Apr-19 15
A1150 FLARE HEADER HOT TAPPING COMPLETE 29-Oct-18 0 0% 0 22-Apr-19 15
A1160 SHUTDOWN TIE-INS 17-Nov-18 0 0% 0 22-Apr-19 15
Fahahil Main Tie-ins
Tie 29-Nov-18 29-Nov-18 0 15 06-Apr-19 22-Apr-19 26
A1240 FLARE HEADER HOT TAPPING COMPLETE 29-Nov-18 0 0% 0 06-Apr-19 41
A1460 SHUTDOWN TIE-INS 0 0% 0 22-Apr-19 0
Commissioninng 08-Oct-18 08-Dec-18 52 100 26-Jan-19 22-May-19 0
A1260 COMPLETE OF COMMISSIONING AT KHATIYAH MAIN 08-Oct-18 0 0% 0 27-Jan-19* 0
A1270 COMPLETE OF COMMISSIONING AT KHATIYAH NORTH 30-Oct-18 0 0% 0 29-Jan-19* 0
A1280 COMPLETE OF COMMISSIONING AT KHATIYAH SOUTH 10-Nov-18 0 0% 0 26-Jan-19* 0
A1290 COMPLETE OF COMMISSIONING AT JALM 17-Nov-18 0 0% 0 06-Apr-19* 0
A1300 COMPLETE OF COMMISSIONING AT FAHAHIL SOUTH 26-Nov-18 0 0% 0 20-May-19* 0
A1320 COMPLETE OF COMMISSIONING AT FAHAHIL MAIN 26-Nov-18 0 0% 0 22-May-19* 0
A1310 COMPLETE OF COMMISSIONING AT FAHAHIL NORTH 08-Dec-18 0 0% 0 09-May-19* 0
Final documentation
documenta & As Built / Handover 18-Feb-19 18-Feb-19 0 0 22-Jul-19 22-Jul-19 0
A1250 FINAL DOCUMENTATION / HANDOVER DOSSIER 18-Feb-19 0 0% 0 22-Jul-19 0
Detail Engineering 19-Feb-17 20-Sep-17 154 48 19-Feb-17 A 31-Dec-18 145
General & Common
Comm 19-Feb-17 20-Sep-17 154 48 19-Feb-17 A 31-Dec-18 145
General 19-Feb-17 30-May-17 73 0 19-Feb-17 A 14-Dec-17 A
DE3760 DESIGN BASIS MEMORANDUM 19-Feb-17 07-May-17 63 100% 0 15-Mar-17 A 07-Dec-17 A
DE3390 PLANNING PACKAGE IFR 19-Feb-17 30-Apr-17 57 100% 0 16-Mar-17 A 27-Sep-17 A
DE3400 FEED VALIDATION 19-Feb-17 14-Mar-17 20 100% 0 19-Feb-17 A 14-Mar-17 A
DE3770 EDDR 13-Mar-17 29-May-17 63 100% 0 12-Mar-17 A 03-Aug-17 A
DE6770 SITE VISIT REPORT 14-Mar-17 30-May-17 63 100% 0 15-Mar-17 A 14-Dec-17 A
DE3780 ENGINEERING EXECUTION PLAN 14-Mar-17 30-May-17 63 100% 0 15-Mar-17 A 10-May-17 A
DE7250 HAZOP/HAZID WORKSHOP 18-May-17 24-May-17 5 100% 0 05-Nov-17 A 08-Nov-17 A
Process 19-Feb-17 18-Sep-17 152 48 02-Apr-17 A 31-Dec-18 145
DE3430 PROCESS EQUIPMENT LIST (DGEN) 19-Feb-17 07-May-17 63 100% 0 11-May-17 A 18-Jan-18 A
DE3750 PROCESS UTILITY CONSUMPTION SUMMARY (DGEN) 20-Feb-17 08-May-17 62 100% 0 25-May-17 A 27-Sep-17 A
DE3440 PROCESS OTHER REPORTS (DGEN) 27-Feb-17 20-Jun-17 92 100% 0 22-Jun-17 A 22-Feb-18 A
DE3460 PROCESS SIMULATION & H&MB REPORT (DGEN) 02-Apr-17 15-Jun-17 62 100% 0 10-Apr-17 A 18-Jul-17 A
DE3420 PROCESS DESIGN CALCULATIONS (DGEN) 11-Apr-17 18-Sep-17 129 100% 0 02-Apr-17 A 12-Oct-17 A
DE3410 PROCESS LEGEND, SYMBOLS & DRAWING INDEX (DGEN) 17-Apr-17 03-Jul-17 62 100% 0 18-Apr-17 A 02-Oct-17 A
DE6780 PROCESS DESCRIPTION 03-May-17 19-Jul-17 62 100% 0 04-May-17 A 28-Sep-17 A
DE3470 PROCESS PHILOSOPHIES (DGEN) 18-May-17 11-Sep-17 92 100% 0 28-Jun-17 A 24-Sep-18 A
DE3450 PROCESS OPERATING MANUALS (DGEN) 25-Jul-17 14-Sep-17 42 70% 48 25-May-17 A 31-Dec-18 145
Piping 02-Mar-17 20-Sep-17 144 0 15-Mar-17 A 01-Feb-18 A
DE3620 PIPING DATA SHEETS (DGEN) 02-Mar-17 24-Jul-17 116 100% 0 15-Mar-17 A 05-Oct-17 A

Page 15 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 3 of32 29-Nov-18 17:45
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DE6860 PIPING EARLY TIE-IN PACKAGE (DGEN) 02-Mar-17 14-May-17 59 100% 0 15-Mar-17 A 30-Nov-17 A
DE6970 PIPING TBES FOR EARLY TIE-IN BALL VALVES (DGEN) 23-Mar-17 08-Jun-17 63 100% 0 15-Mar-17 A 25-Jul-17 A
DE3630 PIPING SPECIFICATIONS (DGEN) 29-Mar-17 29-Jun-17 75 100% 0 29-Mar-17 A 08-Oct-17 A
DE3640 PIPING MRS (DGEN) 21-May-17 21-Aug-17 75 100% 0 21-Mar-17 A 21-Dec-17 A
DE3650 PIPE SUPPORT DETAILS (DGEN) 20-Jul-17 11-Sep-17 43 100% 0 27-Jul-17 A 01-Feb-18 A
DE3660 PIPING TBES (DGEN) 26-Jul-17 20-Sep-17 45 100% 0 20-Jul-17 A 29-Jan-18 A
Mechanical 15-Mar-17 12-Sep-17 130 0 05-Apr-17 A 01-Oct-17 A
DE7000 MECHANICAL SPECIFICATIONS (SEPARATOR) 15-Mar-17 20-Jun-17 79 100% 0 05-Apr-17 A 03-Aug-17 A
DE6990 MECHANICAL DATA SHEETS (SEPARATOR) 27-Mar-17 12-Jun-17 63 100% 0 27-Apr-17 A 03-Aug-17 A
DE3480 MECHANICAL MRS (SEPARATOR) 03-Apr-17 09-Jul-17 79 100% 0 11-May-17 A 31-Jul-17 A
DE3490 MECHANICAL TBES (DGEN) 24-Jul-17 12-Sep-17 42 100% 0 03-Aug-17 A 01-Oct-17 A
Electrical 16-Mar-17 20-Jun-17 69 0 15-Mar-17 A 23-May-17 A
DE3500 ELECTRICAL DATA SHEETS (DGEN) 16-Mar-17 31-May-17 62 100% 0 15-Mar-17 A 07-May-17 A
DE3520 ELECTRICAL SPECIFICATIONS (DGEN) 16-Mar-17 08-Jun-17 69 100% 0 15-Mar-17 A 23-May-17 A
DE3510 ELECTRICAL TYPICAL INSTALLATION DETAILS (DGEN) 29-Mar-17 20-Jun-17 68 100% 0 02-Apr-17 A 07-May-17 A
Civil 14-Mar-17 03-Sep-17 123 0 14-Mar-17 A 02-May-18 A
DE3590 CIVIL SPECIFICATIONS (DGEN) 14-Mar-17 06-Jun-17 69 100% 0 14-Mar-17 A 18-May-17 A
DE3600 CIVIL GENERAL NOTES (DGEN) 14-Mar-17 30-May-17 63 100% 0 16-Mar-17 A 24-May-17 A
DE3790 CIVIL TYPICAL DETAILS (DGEN) 21-Mar-17 03-Sep-17 133 100% 0 14-Mar-17 A 28-Mar-18 A
DE3580 CIVIL DESIGN BASIS (DGEN) 13-Apr-17 02-Jul-17 63 100% 0 21-Mar-17 A 01-Jun-17 A
DE3570 CIVIL MTOS (DGEN) 25-May-17 10-Aug-17 62 100% 0 25-May-17 A 12-Oct-17 A
DE3560 CIVIL DEMOLITION DRAWINGS (DGEN) 30-May-17 15-Aug-17 62 100% 0 31-May-17 A 23-Nov-17 A
DE3610 CIVIL DESIGN CALCULATIONS (DGEN) 13-Jun-17 29-Aug-17 62 100% 0 08-Jul-17 A 02-May-18 A
Safety 23-Mar-17 20-Sep-17 129 0 26-Mar-17 A 09-Sep-18 A
DE3730 FIRE & SAFETY STUDIES (DGEN) 23-Mar-17 08-Jun-17 63 100% 0 29-Mar-17 A 20-Jun-17 A
DE3680 HSE PLAN (DGEN) 30-Mar-17 15-Jun-17 62 100% 0 26-Mar-17 A 08-Jun-17 A
DE3670 HSE SPECIFICATIONS (DGEN) 09-Apr-17 05-Jul-17 71 100% 0 05-Apr-17 A 03-Jan-18 A
DE3700 HSE REPORTS (DGEN) 19-Apr-17 19-Sep-17 124 100% 0 05-Apr-17 A 20-Mar-18 A
DE7120 HSE CALCULATIONS (DGEN) 24-Apr-17 10-Jul-17 62 100% 0 05-Apr-17 A 23-Jan-18 A
DE3710 HSE REGISTER (DGEN) 04-May-17 20-Sep-17 111 100% 0 25-May-17 A 09-Sep-18 A
DE7110 HAZARDOUS AREA CLASSIFICATION PHILOSOPHY AND SCHEDULE (DGEN) 14-May-17 30-Jul-17 62 100% 0 03-Apr-17 A 18-Jul-17 A
DE3740 HSE STUDIES (DGEN) 20-Jun-17 05-Sep-17 62 100% 0 05-Apr-17 A 28-Jul-18 A
DE3690 HSE MRS (DGEN) 04-Jul-17 19-Sep-17 62 100% 0 04-Jul-17 A 09-Jan-18 A
DE3720 HSE TBES (DGEN) 07-Aug-17 14-Sep-17 32 100% 0 19-Oct-17 A 28-Mar-18 A
Instrument 03-Apr-17 20-Sep-17 123 0 14-Mar-17 A 26-May-18 A
DE6980 INSTRUMENTS SPECIFICATIONS (DGEN) 03-Apr-17 09-Jul-17 79 100% 0 14-Mar-17 A 14-Sep-17 A
DE3530 INSTRUMENTS MRS (DGEN) 29-May-17 14-Sep-17 89 100% 0 14-Mar-17 A 19-Oct-17 A
DE3540 INSTRUMENTS SCOPE OF WORK (DGEN) 06-Jun-17 22-Aug-17 63 100% 0 08-Jun-17 A 25-Sep-17 A
DE3550 INSTRUMENTSTBES (DGEN) 20-Jul-17 20-Sep-17 51 100% 0 15-Mar-17 A 26-May-18 A
DE3800 INSTRUMENTS DIAGRAMS (DGEN) 01-Aug-17 18-Sep-17 39 100% 0 01-Aug-17 A 13-Nov-17 A
DE3810 INSTALLATION DETAILS (DGEN) 15-Aug-17 20-Sep-17 30 100% 0 01-Aug-17 A 19-Oct-17 A
Khatiyah North 07-Mar-17 20-Sep-17 142 0 12-Mar-17 A 26-Aug-18 A
Process 23-Mar-17 28-Aug-17 112 0 02-Apr-17 A 11-Mar-18 A
DE6350 PROCESS PFDS (KAHN) 23-Mar-17 15-Jun-17 68 100% 0 04-Apr-17 A 04-Dec-17 A
DE6360 PROCESS P&IDS (KAHN) 17-Apr-17 03-Jul-17 62 100% 0 02-Apr-17 A 11-Mar-18 A
DE6370 PROCESS P&IDS (DEMOLITION) (KAHN) 17-Apr-17 03-Jul-17 62 100% 0 02-Apr-17 A 03-Jan-18 A
DE6790 PFD FOR FIRE WATER NETWORK (KAHN) 19-Apr-17 05-Jul-17 62 100% 0 19-Apr-17 A 04-Dec-17 A
DE6340 PROCESS LINE DESIGNATION TABLES (KAHN) 12-Jun-17 28-Aug-17 62 100% 0 11-Jul-17 A 24-Jan-18 A
Piping 07-Mar-17 20-Sep-17 142 0 12-Mar-17 A 13-Apr-18 A
DE6870 EARLY TIE-IN VALVE LIST (KAHN) 07-Mar-17 22-May-17 62 100% 0 15-Mar-17 A 12-Jun-17 A
DE6960 PIPING EQUIPMENT LOCATION PLAN (KAHN) 29-Mar-17 13-Jun-17 62 100% 0 09-Apr-17 A 21-Jan-18 A
DE6490 PIPING PLOT PLANS (KAHN) 29-Mar-17 14-Jun-17 63 100% 0 12-Mar-17 A 21-Jan-18 A
DE6620 PIPING VALVE & PIPING SPECIALITY ITEMS LISTS (KAHN) 16-May-17 10-Aug-17 71 100% 0 25-May-17 A 02-Nov-17 A
DE6640 PIPING STRESS ANALYSIS REPORT (KAHN) 05-Jun-17 20-Aug-17 62 100% 0 07-Jun-17 A 21-Jan-18 A
DE6660 PIPING MTOS (KAHN) 11-Jun-17 27-Aug-17 63 100% 0 11-Jul-17 A 10-Jan-18 A
DE6670 PIPING CRITICAL LINE LIST (KAHN) 21-Jun-17 06-Sep-17 63 100% 0 21-Jun-17 A 29-Aug-17 A
DE6520 PLOT PLANS (DEMOLITION) (KAHN) 25-Jun-17 10-Sep-17 63 100% 0 29-Jun-17 A 18-Oct-17 A

Page 16 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 4 of32 29-Nov-18 17:45
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DE6650 PIPING KEY PLANS (KAHN) 29-Jun-17 14-Sep-17 63 100% 0 06-Jul-17 A 28-Nov-17 A
DE6510 PIPING G.A (KAHN) 13-Jul-17 19-Sep-17 55 100% 0 15-Jul-17 A 21-Feb-18 A
DE6680 PIPING MTOS (DEMOLITION) (KAHN) 16-Jul-17 17-Aug-17 28 100% 0 05-May-17 A 10-Jan-18 A
DE6500 PIPING TIE-IN PACKAGES & SCHEDULES (KAHN) 18-Jul-17 11-Sep-17 45 100% 0 15-Jul-17 A 13-Apr-18 A
DE6610 PIPE SUPPORT LIST (KAHN) 27-Jul-17 18-Sep-17 43 100% 0 14-Oct-17 A 21-Jan-18 A
DE6530 PIPING G.A (DEMOLITION) (KAHN) 03-Aug-17 20-Sep-17 39 100% 0 20-Aug-17 A 19-Nov-17 A
DE6630 PIPING ISOMETRICS (KAHN) 09-Aug-17 14-Sep-17 30 100% 0 29-Dec-17 A 01-Apr-18 A
Electrical 13-Apr-17 07-Sep-17 105 0 14-Apr-17 A 26-Feb-18 A
DE6690 ELECTRICAL CALCULATIONS (KAHN) 13-Apr-17 10-Aug-17 96 100% 0 14-Apr-17 A 05-Oct-17 A
DE6380 TIE-IN, CABLES & INTERCONNECTION SCHEDULES (KAHN) 25-May-17 07-Sep-17 84 100% 0 04-May-17 A 25-Sep-17 A
DE6400 ELECTRICAL ADEQUACY REORTS (KAHN) 29-May-17 14-Aug-17 62 100% 0 01-Jun-17 A 24-Sep-17 A
DE6390 SINGLE LINE DIAGRAMS (KAHN) 15-Jun-17 31-Aug-17 62 100% 0 07-May-17 A 25-Sep-17 A
DE6700 LIGHTING LAYOUT (KAHN) 15-Jun-17 22-Aug-17 55 100% 0 22-May-17 A 03-Aug-17 A
DE6720 EARTHING & CABLE ROUTING LAYOUTS (KAHN) 15-Jun-17 31-Aug-17 62 100% 0 17-Jun-17 A 29-Oct-17 A
DE6710 ELECTRICAL MTOS (KAHN) 09-Jul-17 10-Aug-17 27 100% 0 04-Jul-17 A 26-Feb-18 A
Civil 18-Apr-17 15-Aug-17 86 0 21-Mar-17 A 07-Mar-18 A
DE7180 DRAINAGE LAYOUTS & DETAILS (KAHN) 18-Apr-17 04-Jul-17 63 100% 0 22-Mar-17 A 04-Feb-18 A
DE6450 GRADING & ROAD LAYOUTS & DETAILS (KAHN) 18-Apr-17 04-Jul-17 63 100% 0 21-Mar-17 A 07-Feb-18 A
DE6460 PLATFORMS STRUCTURAL DETAILS (KAHN) 16-May-17 01-Aug-17 63 100% 0 25-May-17 A 05-Feb-18 A
DE6470 FOUNDATIONS GA, PLANS & DETAILS (KAHN) 16-May-17 15-Aug-17 74 100% 0 25-May-17 A 07-Mar-18 A
DE6480 PIPE SUPPORT LAYOUTS & SCHEDULES (KAHN) 16-May-17 01-Aug-17 63 100% 0 28-Nov-17 A 13-Dec-17 A
Safety 18-May-17 21-Aug-17 67 0 03-May-17 A 26-Aug-18 A
DE6540 HAZARDOUS AREA SCHEDULES (KAHN) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Mar-18 A
DE6560 HSE LAYOUTS (DEMOLITION) (KAHN) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 26-Aug-18 A
DE6570 F&G AND PROCESS CAUSE & EFFECT CHARTS (KAHN) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 08-Apr-18 A
DE6550 HSE LAYOUTS (KAHN) 24-May-17 08-Aug-17 61 100% 0 25-May-17 A 26-Aug-18 A
DE6580 HSE DATA SHEETS (KAHN) 24-May-17 21-Aug-17 71 100% 0 03-May-17 A 24-Jan-18 A
DE6590 HSE P&IDS (KAHN) 24-May-17 10-Aug-17 63 100% 0 03-May-17 A 11-Jan-18 A
DE7130 DEMOLITION PROCESS CAUSE & EFFECT CHARTS (KAHN) 29-May-17 14-Aug-17 62 100% 0 08-Jul-17 A 23-Aug-17 A
Instrument 20-Apr-17 20-Sep-17 110 0 14-Mar-17 A 26-Feb-18 A
DE7060 INSTRUMENTS F&G LOCATIONS & CABLE ROUTING LAYOUTS (KAHN) 20-Apr-17 15-Aug-17 95 100% 0 11-May-17 A 25-Jan-18 A
DE6600 INSTRUMENTS LOCATIONS & CABLE ROUTING LAYOUTS (KAHN) 27-Apr-17 10-Aug-17 86 100% 0 18-May-17 A 12-Oct-17 A
DE6410 INPUT/OUTPUT LISTS (DEMOLITION) (KAHN) 27-Apr-17 13-Jul-17 63 100% 0 14-Mar-17 A 26-Jul-17 A
DE6730 INSTRUMENTS DATA SHEETS (KAHN) 01-May-17 08-Aug-17 81 100% 0 04-Apr-17 A 21-Dec-17 A
DE6430 INSTRUMENTS DIAGRAMS (KAHN) 04-May-17 20-Sep-17 113 100% 0 25-May-17 A 26-Feb-18 A
DE6420 INSTRUMENTS INDEX (KAHN) 30-May-17 14-Aug-17 62 100% 0 31-May-17 A 19-Oct-17 A
DE6740 INPUT/OUTPUT AND ALARM & TRIP LISTS (KAHN) 04-Jun-17 03-Sep-17 74 100% 0 07-Jun-17 A 10-Dec-17 A
DE6440 INSTRUMENTS SCOPE OF WORK (KAHN) 13-Jun-17 29-Aug-17 63 100% 0 11-Jul-17 A 19-Oct-17 A
DE6750 INSTRUMENTS CABLES & JUNCTION BOXES SCHEDULES (KAHN) 25-Jun-17 12-Sep-17 65 100% 0 28-Jun-17 A 19-Oct-17 A
DE6760 INSTRUMENTS MTO (KAHN) 09-Aug-17 12-Sep-17 28 100% 0 28-Sep-17 A 14-Dec-17 A
Khatiyah Main 07-Mar-17 20-Sep-17 142 0 15-Mar-17 A 11-Jul-18 A
Process 23-Mar-17 28-Aug-17 112 0 02-Apr-17 A 11-Mar-18 A
DE3830 PROCESS PFDS (KAHM) 23-Mar-17 08-Jun-17 62 100% 0 04-Apr-17 A 04-Dec-17 A
DE3840 PROCESS P&IDS (KAHM) 17-Apr-17 03-Jul-17 62 100% 0 02-Apr-17 A 11-Mar-18 A
DE3850 PROCESS P&IDS (DEMOLITION) (KAHM) 17-Apr-17 03-Jul-17 62 100% 0 02-Apr-17 A 02-Jan-18 A
DE6800 PFD FOR FIRE WATER NETWORK (KAHM) 19-Apr-17 05-Jul-17 62 100% 0 19-Apr-17 A 04-Dec-17 A
DE3820 PROCESS LINE DESIGNATION TABLES (KAHM) 11-Jun-17 28-Aug-17 63 100% 0 08-Jul-17 A 24-Jan-18 A
Piping 07-Mar-17 18-Sep-17 140 0 15-Mar-17 A 13-Apr-18 A
DE6880 EARLY TIE-IN VALVE LIST (KAHM) 07-Mar-17 22-May-17 62 100% 0 15-Mar-17 A 12-Jun-17 A
DE6950 PIPING EQUIPMENT LOCATION PLAN (KAHM) 29-Mar-17 13-Jun-17 62 100% 0 09-Apr-17 A 06-Mar-18 A
DE3970 PIPING PLOT PLANS (KAHM) 29-Mar-17 14-Jun-17 63 100% 0 15-Mar-17 A 21-Jan-18 A
DE4090 PIPING VALVE & PIPING SPECIALITY ITEMS LISTS (KAHM) 14-May-17 03-Aug-17 68 100% 0 25-May-17 A 14-Nov-17 A
DE4120 PIPING KEY PLANS (KAHM) 25-May-17 10-Aug-17 63 100% 0 01-Jun-17 A 26-Nov-17 A
DE3990 PIPING G.A (KAHM) 30-May-17 15-Aug-17 63 100% 0 31-May-17 A 22-Mar-18 A
DE4110 PIPING STRESS ANALYSIS REPORT (KAHM) 30-May-17 15-Aug-17 63 100% 0 01-Jun-17 A 21-Jan-18 A
DE4000 PLOT PLANS (DEMOLITION) (KAHM) 04-Jun-17 21-Aug-17 64 100% 0 07-Jun-17 A 18-Oct-17 A
DE4130 PIPING MTOS (KAHM) 08-Jun-17 24-Aug-17 63 100% 0 08-Jul-17 A 10-Jan-18 A

Page 17 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 5 of32 29-Nov-18 17:45
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DE3980 PIPING TIE-IN PACKAGES & SCHEDULES (KAHM) 15-Jun-17 14-Aug-17 48 100% 0 20-Jul-17 A 13-Apr-18 A
DE4140 PIPING CRITICAL LINE LIST (KAHM) 21-Jun-17 06-Sep-17 63 100% 0 21-Jun-17 A 29-Aug-17 A
DE4150 PIPING MTOS (DEMOLITION) (KAHM) 04-Jul-17 07-Aug-17 28 100% 0 05-May-17 A 10-Jan-18 A
DE4010 PIPING G.A (DEMOLITION) (KAHM) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 23-Nov-17 A
DE4080 PIPE SUPPORT LIST (KAHM) 27-Jul-17 18-Sep-17 43 100% 0 02-Oct-17 A 23-Jan-18 A
DE4100 PIPING ISOMETRICS (KAHM) 03-Aug-17 05-Sep-17 27 100% 0 31-Dec-17 A 01-Apr-18 A
Electrical 06-Apr-17 17-Sep-17 115 0 14-Apr-17 A 26-Feb-18 A
DE4160 ELECTRICAL CALCULATIONS (KAHM) 06-Apr-17 02-Aug-17 95 100% 0 14-Apr-17 A 05-Oct-17 A
DE3860 TIE-IN, CABLES & INTERCONNECTION SCHEDULES (KAHM) 14-May-17 17-Sep-17 101 100% 0 06-May-17 A 04-Dec-17 A
DE3880 ELECTRICAL ADEQUACY REORTS (KAHM) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Nov-17 A
DE3870 SINGLE LINE DIAGRAMS (KAHM) 07-Jun-17 23-Aug-17 62 100% 0 07-May-17 A 24-Sep-17 A
DE4170 LIGHTING LAYOUT (KAHM) 29-Jun-17 14-Sep-17 62 100% 0 27-May-17 A 03-Aug-17 A
DE4190 EARTHING & CABLE ROUTING LAYOUTS (KAHM) 29-Jun-17 14-Sep-17 62 100% 0 17-Jun-17 A 02-Nov-17 A
DE4180 ELECTRICAL MTOS (KAHM) 09-Jul-17 10-Aug-17 27 100% 0 04-Jul-17 A 26-Feb-18 A
Civil 26-Apr-17 15-Aug-17 80 0 05-Apr-17 A 15-Apr-18 A
DE3930 GRADING & ROAD LAYOUTS & DETAILS (KAHM) 26-Apr-17 13-Jul-17 64 100% 0 05-Apr-17 A 12-Feb-18 A
DE7190 DRAINAGE LAYOUTS & DETAILS (KAHM) 27-Apr-17 13-Jul-17 62 100% 0 05-Apr-17 A 12-Feb-18 A
DE3940 PLATFORMS STRUCTURAL DETAILS (KAHM) 22-May-17 08-Aug-17 64 100% 0 01-Jun-17 A 08-Feb-18 A
DE3950 FOUNDATIONS GA, PLANS & DETAILS (KAHM) 22-May-17 15-Aug-17 70 100% 0 25-May-17 A 15-Apr-18 A
DE3960 PIPE SUPPORT LAYOUTS & SCHEDULES (KAHM) 22-May-17 31-Jul-17 57 100% 0 28-Nov-17 A 19-Dec-17 A
Safety 18-May-17 15-Aug-17 63 0 03-May-17 A 11-Jul-18 A
DE4020 HAZARDOUS AREA SCHEDULES (KAHM) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Mar-18 A
DE4030 HSE LAYOUTS (KAHM) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 11-Jul-18 A
DE4040 F&G AND PROCESS CAUSE & EFFECT CHARTS (KAHM) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 05-May-18 A
DE4050 HSE DATA SHEETS (KAHM) 18-May-17 15-Aug-17 71 100% 0 03-May-17 A 24-Jan-18 A
DE4060 HSE P&IDS (KAHM) 18-May-17 06-Aug-17 63 100% 0 04-May-17 A 11-Jan-18 A
DE7140 DEMOLITION PROCESS CAUSE & EFFECT CHARTS (KAHM) 29-May-17 14-Aug-17 62 100% 0 11-Jul-17 A 23-Aug-17 A
Instrument 20-Apr-17 20-Sep-17 110 0 15-Mar-17 A 22-Feb-18 A
DE7050 INSTRUMENTS F&G LOCATIONS & CABLE ROUTING LAYOUTS (KAHM) 20-Apr-17 15-Aug-17 95 100% 0 11-May-17 A 25-Jan-18 A
DE3890 INPUT/OUTPUT LISTS (DEMOLITION) (KAHM) 27-Apr-17 13-Jul-17 63 100% 0 15-Mar-17 A 26-Jul-17 A
DE4070 INSTRUMENTS LOCATIONS & CABLE ROUTING LAYOUTS (KAHM) 27-Apr-17 10-Aug-17 86 100% 0 18-May-17 A 12-Oct-17 A
DE4200 INSTRUMENTS DATA SHEETS (KAHM) 01-May-17 08-Aug-17 81 100% 0 04-Apr-17 A 21-Dec-17 A
DE3910 INSTRUMENTS DIAGRAMS (KAHM) 04-May-17 20-Sep-17 113 100% 0 25-May-17 A 22-Feb-18 A
DE3900 INSTRUMENTS INDEX (KAHM) 30-May-17 15-Aug-17 62 100% 0 31-May-17 A 19-Oct-17 A
DE4210 INPUT/OUTPUT AND ALARM & TRIP LISTS (KAHM) 04-Jun-17 03-Sep-17 74 100% 0 07-Jun-17 A 10-Dec-17 A
DE3920 INSTRUMENTS SCOPE OF WORK (KAHM) 13-Jun-17 29-Aug-17 63 100% 0 08-Jul-17 A 19-Oct-17 A
DE4220 INSTRUMENTS CABLES & JUNCTION BOXES SCHEDULES (KAHM) 22-Jun-17 12-Sep-17 65 100% 0 28-Jun-17 A 19-Oct-17 A
DE4230 INSTRUMENTS MTO (KAHM) 09-Aug-17 12-Sep-17 28 100% 0 28-Sep-17 A 14-Dec-17 A
Khatiyah South 07-Mar-17 20-Sep-17 142 0 14-Mar-17 A 11-Jul-18 A
Process 23-Mar-17 29-Aug-17 113 0 02-Apr-17 A 30-Jan-18 A
DE4250 PROCESS PFDS (KAHS) 23-Mar-17 08-Jun-17 62 100% 0 04-Apr-17 A 04-Dec-17 A
DE6810 PFD FOR FIRE WATER NETWORK (KAHS) 19-Apr-17 05-Jul-17 62 100% 0 19-Apr-17 A 04-Dec-17 A
DE4260 PROCESS P&IDS (KAHS) 20-Apr-17 06-Jul-17 62 100% 0 02-Apr-17 A 30-Jan-18 A
DE4270 PROCESS P&IDS (DEMOLITION) (KAHS) 20-Apr-17 06-Jul-17 62 100% 0 02-Apr-17 A 29-Nov-17 A
DE4240 PROCESS LINE DESIGNATION TABLES (KAHS) 13-Jun-17 29-Aug-17 62 100% 0 08-Jul-17 A 24-Jan-18 A
Piping 07-Mar-17 20-Sep-17 142 0 14-Mar-17 A 13-Apr-18 A
DE6890 EARLY TIE-IN VALVE LIST (KAHS) 07-Mar-17 22-May-17 62 100% 0 15-Mar-17 A 12-Jun-17 A
DE6940 PIPING EQUIPMENT LOCATION PLAN (KAHS) 29-Mar-17 13-Jun-17 62 100% 0 09-Apr-17 A 21-Jan-18 A
DE4390 PIPING PLOT PLANS (KAHS) 02-Apr-17 15-Jun-17 62 100% 0 14-Mar-17 A 21-Jan-18 A
DE4510 PIPING VALVE & PIPING SPECIALITY ITEMS LISTS (KAHS) 15-May-17 08-Aug-17 70 100% 0 25-May-17 A 24-Jan-18 A
DE4560 PIPING CRITICAL LINE LIST (KAHS) 22-May-17 07-Aug-17 63 100% 0 25-May-17 A 29-Aug-17 A
DE4530 PIPING STRESS ANALYSIS REPORT (KAHS) 08-Jun-17 24-Aug-17 63 100% 0 08-Jul-17 A 31-Jan-18 A
DE4550 PIPING MTOS (KAHS) 14-Jun-17 30-Aug-17 63 100% 0 08-Jul-17 A 10-Jan-18 A
DE4540 PIPING KEY PLANS (KAHS) 19-Jun-17 04-Sep-17 63 100% 0 22-Jun-17 A 28-Nov-17 A
DE4410 PIPING G.A (KAHS) 22-Jun-17 07-Sep-17 63 100% 0 28-Jun-17 A 18-Mar-18 A
DE4420 PLOT PLANS (DEMOLITION) (KAHS) 27-Jun-17 13-Sep-17 64 100% 0 28-Jun-17 A 03-Aug-17 A
DE4570 PIPING MTOS (DEMOLITION) (KAHS) 09-Jul-17 10-Aug-17 28 100% 0 05-May-17 A 10-Jan-18 A

Page 18 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 6 of32 29-Nov-18 17:45
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DE4400 PIPING TIE-IN PACKAGES & SCHEDULES (KAHS) 20-Jul-17 13-Sep-17 45 100% 0 27-Jul-17 A 13-Apr-18 A
DE4430 PIPING G.A (DEMOLITION) (KAHS) 27-Jul-17 20-Sep-17 45 100% 0 16-Aug-17 A 05-Dec-17 A
DE4500 PIPE SUPPORT LIST (KAHS) 27-Jul-17 18-Sep-17 43 100% 0 14-Oct-17 A 11-Jan-18 A
DE4520 PIPING ISOMETRICS (KAHS) 06-Aug-17 10-Sep-17 29 100% 0 02-Jan-18 A 01-Apr-18 A
Electrical 06-Apr-17 19-Sep-17 118 0 14-Apr-17 A 26-Feb-18 A
DE4580 ELECTRICAL CALCULATIONS (KAHS) 06-Apr-17 27-Jul-17 89 100% 0 14-Apr-17 A 28-Sep-17 A
DE4300 ELECTRICAL ADEQUACY REORTS (KAHS) 20-Apr-17 09-Jul-17 63 100% 0 25-May-17 A 20-Sep-17 A
DE4290 SINGLE LINE DIAGRAMS (KAHS) 04-Jun-17 17-Sep-17 84 100% 0 07-May-17 A 20-Sep-17 A
DE4280 TIE-IN, CABLES & INTERCONNECTION SCHEDULES (KAHS) 14-Jun-17 14-Sep-17 74 100% 0 04-May-17 A 25-Sep-17 A
DE4610 EARTHING & CABLE ROUTING LAYOUTS (KAHS) 22-Jun-17 19-Sep-17 71 100% 0 17-Jun-17 A 08-Nov-17 A
DE4590 LIGHTING LAYOUT (KAHS) 29-Jun-17 14-Sep-17 62 100% 0 25-May-17 A 03-Aug-17 A
DE4600 ELECTRICAL MTOS (KAHS) 09-Jul-17 10-Aug-17 27 100% 0 04-Jul-17 A 26-Feb-18 A
Civil 03-May-17 29-Aug-17 85 0 22-Mar-17 A 12-Mar-18 A
DE4350 GRADING & ROAD LAYOUTS & DETAILS (KAHS) 03-May-17 20-Jul-17 64 100% 0 22-Mar-17 A 20-Jan-18 A
DE7200 DRAINAGE LAYOUTS & DETAILS (KAHS) 03-May-17 20-Jul-17 64 100% 0 22-Mar-17 A 04-Feb-18 A
DE4360 PLATFORMS STRUCTURAL DETAILS (KAHS) 13-Jun-17 29-Aug-17 63 100% 0 08-Jul-17 A 12-Feb-18 A
DE4370 FOUNDATIONS GA, PLANS & DETAILS (KAHS) 13-Jun-17 29-Aug-17 63 100% 0 08-Jul-17 A 12-Mar-18 A
DE4380 PIPE SUPPORT LAYOUTS & SCHEDULES (KAHS) 13-Jun-17 29-Aug-17 63 100% 0 28-Nov-17 A 19-Dec-17 A
Safety 18-May-17 20-Aug-17 66 0 03-May-17 A 11-Jul-18 A
DE4440 HAZARDOUS AREA SCHEDULES (KAHS) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Mar-18 A
DE4460 F&G AND PROCESS CAUSE & EFFECT CHARTS (KAHS) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 05-May-18 A
DE4450 HSE LAYOUTS (KAHS) 23-May-17 08-Aug-17 62 100% 0 25-May-17 A 11-Jul-18 A
DE4470 HSE DATA SHEETS (KAHS) 23-May-17 20-Aug-17 71 100% 0 03-May-17 A 24-Jan-18 A
DE4480 HSE P&IDS (KAHS) 23-May-17 09-Aug-17 63 100% 0 04-May-17 A 11-Jan-18 A
Instrument 20-Apr-17 20-Sep-17 110 0 21-Mar-17 A 26-Feb-18 A
DE7070 INSTRUMENTS F&G LOCATIONS & CABLE ROUTING LAYOUTS (KAHS) 20-Apr-17 15-Aug-17 95 100% 0 11-May-17 A 25-Jan-18 A
DE4490 INSTRUMENTS LOCATIONS & CABLE ROUTING LAYOUTS (KAHS) 27-Apr-17 10-Aug-17 86 100% 0 18-May-17 A 19-Oct-17 A
DE4310 INPUT/OUTPUT LISTS (DEMOLITION) (KAHS) 27-Apr-17 13-Jul-17 63 100% 0 21-Mar-17 A 20-Jun-17 A
DE4620 INSTRUMENTS DATA SHEETS (KAHS) 01-May-17 08-Aug-17 81 100% 0 04-Apr-17 A 21-Dec-17 A
DE4330 INSTRUMENTS DIAGRAMS (KAHS) 04-May-17 20-Sep-17 113 100% 0 25-May-17 A 26-Feb-18 A
DE4320 INSTRUMENTS INDEX (KAHS) 30-May-17 14-Aug-17 62 100% 0 31-May-17 A 19-Oct-17 A
DE4630 INPUT/OUTPUT AND ALARM & TRIP LISTS (KAHS) 04-Jun-17 03-Sep-17 74 100% 0 07-Jun-17 A 10-Dec-17 A
DE4340 INSTRUMENTS SCOPE OF WORK (KAHS) 13-Jun-17 29-Aug-17 63 100% 0 08-Jul-17 A 19-Oct-17 A
DE4640 INSTRUMENTS CABLES & JUNCTION BOXES SCHEDULES (KAHS) 25-Jun-17 12-Sep-17 65 100% 0 28-Jun-17 A 19-Oct-17 A
DE4650 INSTRUMENTS MTO (KAHS) 09-Aug-17 12-Sep-17 28 100% 0 28-Sep-17 A 13-Dec-17 A
Fahahil North 23-Mar-17 20-Sep-17 130 27 15-Mar-17 A 02-Dec-18 166
Process 23-Mar-17 20-Aug-17 106 0 02-Apr-17 A 11-Mar-18 A
DE4670 PROCESS PFDS (FAHN) 23-Mar-17 08-Jun-17 62 100% 0 04-Apr-17 A 14-Dec-17 A
DE6820 PFD FOR FIRE WATER NETWORK (FAHN) 19-Apr-17 05-Jul-17 62 100% 0 05-Apr-17 A 14-Dec-17 A
DE4690 PROCESS P&IDS (DEMOLITION) (FAHN) 27-Apr-17 13-Jul-17 62 100% 0 03-May-17 A 03-Jan-18 A
DE4680 PROCESS P&IDS (FAHN) 27-Apr-17 13-Jul-17 62 100% 0 02-Apr-17 A 11-Mar-18 A
DE4660 PROCESS LINE DESIGNATION TABLES (FAHN) 04-Jun-17 20-Aug-17 62 100% 0 07-Jun-17 A 24-Jan-18 A
Piping 23-Mar-17 20-Sep-17 130 27 29-Mar-17 A 02-Dec-18 166
DE4810 PIPING PLOT PLANS (FAHN) 23-Mar-17 08-Jun-17 63 100% 0 29-Mar-17 A 21-Jan-18 A
DE6930 PIPING EQUIPMENT LOCATION PLAN (FAHN) 29-Mar-17 13-Jun-17 62 100% 0 09-Apr-17 A 21-Jan-18 A
DE4930 PIPING VALVE & PIPING SPECIALITY ITEMS LISTS (FAHN) 22-May-17 15-Aug-17 70 100% 0 25-May-17 A 05-Nov-17 A
DE4840 PLOT PLANS (DEMOLITION) (FAHN) 29-May-17 14-Aug-17 63 100% 0 01-Jun-17 A 18-Oct-17 A
DE4970 PIPING MTOS (FAHN) 30-May-17 15-Aug-17 63 100% 0 01-Jun-17 A 10-Jan-18 A
DE4950 PIPING STRESS ANALYSIS REPORT (FAHN) 15-Jun-17 19-Jul-17 28 100% 0 21-Jun-17 A 07-Feb-18 A
DE4980 PIPING CRITICAL LINE LIST (FAHN) 15-Jun-17 11-Sep-17 71 100% 0 21-Jun-17 A 29-Aug-17 A
DE4990 PIPING MTOS (DEMOLITION) (FAHN) 26-Jun-17 30-Jul-17 28 100% 0 01-Jun-17 A 10-Jan-18 A
DE4850 PIPING G.A (DEMOLITION) (FAHN) 16-Jul-17 19-Sep-17 54 100% 0 15-Jul-17 A 16-Oct-17 A
DE4920 PIPE SUPPORT LIST (FAHN) 17-Jul-17 10-Sep-17 45 100% 0 15-Jul-17 A 21-Jan-18 A
DE4960 PIPING KEY PLANS (FAHN) 20-Jul-17 13-Sep-17 45 100% 0 27-Jul-17 A 21-Jan-18 A
DE4820 PIPING TIE-IN PACKAGES & SCHEDULES (FAHN) 20-Jul-17 17-Sep-17 47 95% 27 27-Jul-17 A 02-Dec-18 166
DE4830 PIPING G.A (FAHN) 03-Aug-17 20-Sep-17 39 100% 0 19-Oct-17 A 18-Mar-18 A
DE4940 PIPING ISOMETRICS (FAHN) 10-Aug-17 19-Sep-17 33 100% 0 18-Jan-18 A 01-Apr-18 A

Page 19 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 7 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Electrical 23-Apr-17 17-Aug-17 84 0 14-Apr-17 A 07-Dec-17 A
DE5000 ELECTRICAL CALCULATIONS (FAHN) 23-Apr-17 10-Aug-17 89 100% 0 14-Apr-17 A 28-Sep-17 A
DE4700 TIE-IN, CABLES & INTERCONNECTION SCHEDULES (FAHN) 23-Apr-17 24-Jul-17 74 100% 0 25-Apr-17 A 07-Dec-17 A
DE5010 LIGHTING LAYOUT (FAHN) 02-May-17 19-Jul-17 63 100% 0 22-May-17 A 03-Aug-17 A
DE4720 ELECTRICAL ADEQUACY REORTS (FAHN) 07-May-17 23-Jul-17 62 100% 0 25-May-17 A 19-Oct-17 A
DE4710 SINGLE LINE DIAGRAMS (FAHN) 09-May-17 26-Jul-17 63 100% 0 07-May-17 A 24-Sep-17 A
DE5030 EARTHING & CABLE ROUTING LAYOUTS (FAHN) 01-Jun-17 17-Aug-17 62 100% 0 07-Jun-17 A 04-Dec-17 A
DE5020 ELECTRICAL MTOS (FAHN) 09-Jul-17 10-Aug-17 27 100% 0 04-Jul-17 A 01-Oct-17 A
Civil 11-May-17 05-Sep-17 84 0 25-May-17 A 19-Mar-18 A
DE7210 DRAINAGE LAYOUTS & DETAILS (FAHN) 11-May-17 27-Jul-17 63 100% 0 25-May-17 A 05-Mar-18 A
DE4770 GRADING & ROAD LAYOUTS & DETAILS (FAHN) 11-May-17 27-Jul-17 63 100% 0 25-May-17 A 18-Feb-18 A
DE4780 PLATFORMS STRUCTURAL DETAILS (FAHN) 20-Jun-17 05-Sep-17 63 100% 0 21-Jun-17 A 18-Mar-18 A
DE4790 FOUNDATIONS GA, PLANS & DETAILS (FAHN) 20-Jun-17 05-Sep-17 63 100% 0 21-Jun-17 A 19-Mar-18 A
DE4800 PIPE SUPPORT LAYOUTS & SCHEDULES (FAHN) 20-Jun-17 05-Sep-17 63 100% 0 21-Jun-17 A 05-Mar-18 A
Safety 18-May-17 15-Aug-17 63 0 03-May-17 A 08-Jul-18 A
DE4860 HAZARDOUS AREA SCHEDULES (FAHN) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Mar-18 A
DE4870 HSE LAYOUTS (FAHN) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 08-Jul-18 A
DE4880 F&G AND PROCESS CAUSE & EFFECT CHARTS (FAHN) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 05-May-18 A
DE4890 HSE DATA SHEETS (FAHN) 18-May-17 15-Aug-17 71 100% 0 03-May-17 A 24-Jan-18 A
DE4900 HSE P&IDS (FAHN) 18-May-17 06-Aug-17 63 100% 0 03-May-17 A 11-Jan-18 A
DE7150 DEMOLITION PROCESS CAUSE & EFFECT CHARTS (FAHN) 29-May-17 14-Aug-17 62 100% 0 11-Jul-17 A 23-Aug-17 A
Instrument 20-Apr-17 20-Sep-17 110 0 15-Mar-17 A 12-Mar-18 A
DE7020 INSTRUMENTS F&G LOCATIONS & CABLE ROUTING LAYOUTS (FAHN) 20-Apr-17 15-Aug-17 95 100% 0 11-May-17 A 25-Jan-18 A
DE4910 INSTRUMENTS LOCATIONS & CABLE ROUTING LAYOUTS (FAHN) 27-Apr-17 10-Aug-17 86 100% 0 18-May-17 A 10-Oct-17 A
DE5040 INSTRUMENTS DATA SHEETS (FAHN) 01-May-17 08-Aug-17 81 100% 0 04-Apr-17 A 26-Dec-17 A
DE4750 INSTRUMENTS DIAGRAMS (FAHN) 04-May-17 20-Sep-17 113 100% 0 25-May-17 A 12-Mar-18 A
DE7080 INSTRUMENTS BUILDING LAYOUT (FAHN) 16-May-17 01-Aug-17 63 100% 0 17-May-17 A 25-Jul-17 A
DE4740 INSTRUMENTS INDEX (FAHN) 30-May-17 14-Aug-17 62 100% 0 31-May-17 A 20-Nov-17 A
DE5050 INPUT/OUTPUT AND ALARM & TRIP LISTS (FAHN) 04-Jun-17 03-Sep-17 74 100% 0 08-Jun-17 A 10-Dec-17 A
DE4760 INSTRUMENTS SCOPE OF WORK (FAHN) 13-Jun-17 29-Aug-17 63 100% 0 08-Jul-17 A 19-Oct-17 A
DE4730 INPUT/OUTPUT LISTS (DEMOLITION) (FAHN) 15-Jun-17 14-Aug-17 48 100% 0 15-Mar-17 A 26-Jul-17 A
DE5060 INSTRUMENTS CABLES & JUNCTION BOXES SCHEDULES (FAHN) 25-Jun-17 12-Sep-17 65 100% 0 28-Jun-17 A 19-Oct-17 A
DE5070 INSTRUMENTS MTO (FAHN) 09-Aug-17 12-Sep-17 28 100% 0 28-Sep-17 A 14-Dec-17 A
Fahahil Main 23-Mar-17 20-Sep-17 130 27 15-Mar-17 A 02-Dec-18 166
Process 23-Mar-17 16-Aug-17 104 0 02-Apr-17 A 11-Mar-18 A
DE5930 PROCESS PFDS (FAHM) 23-Mar-17 08-Jun-17 62 100% 0 04-Apr-17 A 04-Dec-17 A
DE6830 PFD FOR FIRE WATER NETWORK (FAHM) 19-Apr-17 05-Jul-17 62 100% 0 19-Apr-17 A 04-Dec-17 A
DE5940 PROCESS P&IDS (FAHM) 20-Apr-17 06-Jul-17 62 100% 0 02-Apr-17 A 11-Mar-18 A
DE5950 PROCESS P&IDS (DEMOLITION) (FAHM) 20-Apr-17 06-Jul-17 62 100% 0 27-Apr-17 A 02-Jan-18 A
DE5920 PROCESS LINE DESIGNATION TABLES (FAHM) 30-May-17 16-Aug-17 63 100% 0 31-May-17 A 24-Jan-18 A
Piping 29-Mar-17 20-Sep-17 126 27 15-Mar-17 A 02-Dec-18 166
DE6920 PIPING EQUIPMENT LOCATION PLAN (FAHM) 29-Mar-17 13-Jun-17 62 100% 0 09-Apr-17 A 25-Jan-18 A
DE6070 PIPING PLOT PLANS (FAHM) 29-Mar-17 14-Jun-17 63 100% 0 29-Mar-17 A 25-Jan-18 A
DE6190 PIPING VALVE & PIPING SPECIALITY ITEMS LISTS (FAHM) 18-May-17 20-Sep-17 101 100% 0 25-May-17 A 26-Oct-17 A
DE6100 PLOT PLANS (DEMOLITION) (FAHM) 21-May-17 03-Aug-17 62 100% 0 25-May-17 A 18-Oct-17 A
DE6230 PIPING MTOS (FAHM) 15-Jun-17 19-Jul-17 28 100% 0 22-Jun-17 A 10-Jan-18 A
DE6240 PIPING CRITICAL LINE LIST (FAHM) 15-Jun-17 31-Aug-17 63 100% 0 22-Jun-17 A 14-Sep-17 A
DE6220 PIPING KEY PLANS (FAHM) 19-Jun-17 04-Sep-17 63 100% 0 15-Mar-17 A 21-Jan-18 A
DE6090 PIPING G.A (FAHM) 20-Jun-17 29-Aug-17 57 100% 0 19-Oct-17 A 18-Mar-18 A
DE6210 PIPING STRESS ANALYSIS REPORT (FAHM) 29-Jun-17 02-Aug-17 28 100% 0 03-Jul-17 A 29-Jan-18 A
DE6250 PIPING MTOS (DEMOLITION) (FAHM) 29-Jun-17 02-Aug-17 28 100% 0 22-Jul-17 A 10-Jan-18 A
DE6110 PIPING G.A (DEMOLITION) (FAHM) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 13-Nov-17 A
DE6080 PIPING TIE-IN PACKAGES & SCHEDULES (FAHM) 25-Jul-17 17-Sep-17 44 90% 27 15-Jul-17 A 02-Dec-18 166
DE6180 PIPE SUPPORT LIST (FAHM) 27-Jul-17 18-Sep-17 43 100% 0 02-Oct-17 A 21-Jan-18 A
DE6200 PIPING ISOMETRICS (FAHM) 14-Aug-17 17-Sep-17 28 100% 0 18-Jan-18 A 01-Apr-18 A
Electrical 13-Apr-17 10-Aug-17 85 0 14-Apr-17 A 09-Jan-18 A
DE5960 TIE-IN, CABLES & INTERCONNECTION SCHEDULES (FAHM) 13-Apr-17 17-Jul-17 77 100% 0 19-Apr-17 A 20-Sep-17 A

Page 20 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 8 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DE6260 ELECTRICAL CALCULATIONS (FAHM) 16-Apr-17 09-Jul-17 68 100% 0 14-Apr-17 A 19-Sep-17 A
DE5980 ELECTRICAL ADEQUACY REORTS (FAHM) 19-Apr-17 28-Jun-17 57 100% 0 25-May-17 A 24-Sep-17 A
DE5970 SINGLE LINE DIAGRAMS (FAHM) 02-May-17 18-Jul-17 63 100% 0 07-May-17 A 20-Sep-17 A
DE6270 LIGHTING LAYOUT (FAHM) 02-May-17 18-Jul-17 62 100% 0 21-May-17 A 03-Aug-17 A
DE6290 EARTHING & CABLE ROUTING LAYOUTS (FAHM) 02-May-17 18-Jul-17 62 100% 0 25-May-17 A 09-Jan-18 A
DE6280 ELECTRICAL MTOS (FAHM) 09-Jul-17 10-Aug-17 27 100% 0 04-Jul-17 A 28-Sep-17 A
Civil 16-May-17 19-Sep-17 91 0 25-May-17 A 29-Apr-18 A
DE7220 DRAINAGE LAYOUTS & DETAILS (FAHM) 16-May-17 01-Aug-17 63 100% 0 25-May-17 A 05-Mar-18 A
DE6030 GRADING & ROAD LAYOUTS & DETAILS (FAHM) 16-May-17 01-Aug-17 63 100% 0 25-May-17 A 21-Feb-18 A
DE6050 FOUNDATIONS GA, PLANS & DETAILS (FAHM) 04-Jul-17 19-Sep-17 63 100% 0 03-Jul-17 A 05-Apr-18 A
DE6060 PIPE SUPPORT LAYOUTS & SCHEDULES (FAHM) 04-Jul-17 19-Sep-17 63 100% 0 04-Jul-17 A 05-Mar-18 A
DE6040 PLATFORMS STRUCTURAL DETAILS (FAHM) 04-Jul-17 19-Sep-17 63 100% 0 04-Jul-17 A 29-Apr-18 A
Safety 18-May-17 20-Aug-17 66 0 03-May-17 A 05-May-18 A
DE6120 HAZARDOUS AREA SCHEDULES (FAHM) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Mar-18 A
DE6140 F&G AND PROCESS CAUSE & EFFECT CHARTS (FAHM) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 05-May-18 A
DE6130 HSE LAYOUTS (FAHM) 23-May-17 08-Aug-17 62 100% 0 25-May-17 A 31-Jan-18 A
DE6150 HSE DATA SHEETS (FAHM) 23-May-17 20-Aug-17 71 100% 0 03-May-17 A 24-Jan-18 A
DE6160 HSE P&IDS (FAHM) 23-May-17 09-Aug-17 63 100% 0 03-May-17 A 11-Jan-18 A
DE7160 DEMOLITION PROCESS CAUSE & EFFECT CHARTS (FAHM) 29-May-17 14-Aug-17 62 100% 0 11-Jul-17 A 23-Aug-17 A
Instrument 20-Apr-17 20-Sep-17 110 0 22-Mar-17 A 22-Mar-18 A
DE7010 INSTRUMENTS F&G LOCATIONS & CABLE ROUTING LAYOUTS (FAHM) 20-Apr-17 15-Aug-17 95 100% 0 11-May-17 A 25-Jan-18 A
DE5990 INPUT/OUTPUT LISTS (DEMOLITION) (FAHM) 27-Apr-17 13-Jul-17 63 100% 0 22-Mar-17 A 14-Jun-17 A
DE6170 INSTRUMENTS LOCATIONS & CABLE ROUTING LAYOUTS (FAHM) 27-Apr-17 10-Aug-17 86 100% 0 18-May-17 A 12-Oct-17 A
DE6300 INSTRUMENTS DATA SHEETS (FAHM) 01-May-17 08-Aug-17 81 100% 0 04-Apr-17 A 26-Dec-17 A
DE6010 INSTRUMENTS DIAGRAMS (FAHM) 04-May-17 20-Sep-17 113 100% 0 25-May-17 A 22-Mar-18 A
DE7090 INSTRUMENTS BUILDING LAYOUT (FAHM) 16-May-17 01-Aug-17 63 100% 0 15-May-17 A 25-Jul-17 A
DE6000 INSTRUMENTS INDEX (FAHM) 30-May-17 14-Aug-17 62 100% 0 31-May-17 A 05-Oct-17 A
DE6310 INPUT/OUTPUT AND ALARM & TRIP LISTS (FAHM) 04-Jun-17 03-Sep-17 74 100% 0 08-Jun-17 A 10-Dec-17 A
DE6020 INSTRUMENTS SCOPE OF WORK (FAHM) 13-Jun-17 29-Aug-17 63 100% 0 11-Jul-17 A 19-Oct-17 A
DE6320 INSTRUMENTS CABLES & JUNCTION BOXES SCHEDULES (FAHM) 25-Jun-17 12-Sep-17 65 100% 0 28-Jun-17 A 29-Nov-17 A
DE6330 INSTRUMENTS MTO (FAHM) 09-Aug-17 12-Sep-17 28 100% 0 28-Sep-17 A 14-Dec-17 A
Fahahil South 23-Mar-17 20-Sep-17 130 27 21-Mar-17 A 02-Dec-18 166
Process 23-Mar-17 16-Aug-17 104 0 04-Apr-17 A 11-Mar-18 A
DE5510 PROCESS PFDS (FAHS) 23-Mar-17 08-Jun-17 62 100% 0 04-Apr-17 A 04-Dec-17 A
DE6840 PFD FOR FIRE WATER NETWORK (FAHS) 19-Apr-17 05-Jul-17 62 100% 0 19-Apr-17 A 04-Dec-17 A
DE5520 PROCESS P&IDS (FAHS) 27-Apr-17 13-Jul-17 62 100% 0 03-May-17 A 11-Mar-18 A
DE5530 PROCESS P&IDS (DEMOLITION) (FAHS) 27-Apr-17 13-Jul-17 62 100% 0 03-May-17 A 05-Oct-17 A
DE5500 PROCESS LINE DESIGNATION TABLES (FAHS) 30-May-17 16-Aug-17 63 100% 0 01-Jun-17 A 24-Jan-18 A
Piping 29-Mar-17 19-Sep-17 125 27 29-Mar-17 A 02-Dec-18 166
DE6910 PIPING EQUIPMENT LOCATION PLAN (FAHS) 29-Mar-17 13-Jun-17 62 100% 0 09-Apr-17 A 21-Jan-18 A
DE5650 PIPING PLOT PLANS (FAHS) 29-Mar-17 14-Jun-17 63 100% 0 29-Mar-17 A 21-Jan-18 A
DE5770 PIPING VALVE & PIPING SPECIALITY ITEMS LISTS (FAHS) 18-May-17 10-Aug-17 69 100% 0 25-May-17 A 29-Aug-17 A
DE5810 PIPING MTOS (FAHS) 01-Jun-17 17-Aug-17 63 100% 0 07-Jun-17 A 10-Jan-18 A
DE5680 PLOT PLANS (DEMOLITION) (FAHS) 11-Jun-17 27-Aug-17 63 100% 0 08-Jul-17 A 18-Oct-17 A
DE5820 PIPING CRITICAL LINE LIST (FAHS) 14-Jun-17 31-Aug-17 64 100% 0 21-Jun-17 A 14-Sep-17 A
DE5790 PIPING STRESS ANALYSIS REPORT (FAHS) 22-Jun-17 27-Jul-17 29 100% 0 29-Jun-17 A 14-Feb-18 A
DE5830 PIPING MTOS (DEMOLITION) (FAHS) 02-Jul-17 03-Aug-17 28 100% 0 07-Jun-17 A 10-Jan-18 A
DE5690 PIPING G.A (DEMOLITION) (FAHS) 20-Jul-17 13-Sep-17 45 100% 0 27-Jul-17 A 18-Oct-17 A
DE5760 PIPE SUPPORT LIST (FAHS) 20-Jul-17 13-Sep-17 45 100% 0 27-Jul-17 A 11-Jan-18 A
DE5800 PIPING KEY PLANS (FAHS) 20-Jul-17 13-Sep-17 45 100% 0 27-Jul-17 A 26-Nov-17 A
DE5660 PIPING TIE-IN PACKAGES & SCHEDULES (FAHS) 23-Jul-17 14-Sep-17 45 90% 27 16-Jul-17 A 02-Dec-18 166
DE5670 PIPING G.A (FAHS) 30-Jul-17 14-Sep-17 39 100% 0 12-Oct-17 A 18-Mar-18 A
DE5780 PIPING ISOMETRICS (FAHS) 16-Aug-17 19-Sep-17 28 100% 0 18-Jan-18 A 08-Apr-18 A
Electrical 30-Apr-17 24-Aug-17 84 0 14-Apr-17 A 07-Dec-17 A
DE5540 TIE-IN, CABLES & INTERCONNECTION SCHEDULES (FAHS) 30-Apr-17 02-Aug-17 77 100% 0 25-Apr-17 A 07-Dec-17 A
DE5840 ELECTRICAL CALCULATIONS (FAHS) 30-Apr-17 23-Jul-17 68 100% 0 14-Apr-17 A 28-Sep-17 A
DE5560 ELECTRICAL ADEQUACY REORTS (FAHS) 14-May-17 30-Jul-17 62 100% 0 25-May-17 A 07-Dec-17 A

Page 21 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 9 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DE5550 SINGLE LINE DIAGRAMS (FAHS) 17-May-17 02-Aug-17 62 100% 0 07-May-17 A 24-Sep-17 A
DE5850 LIGHTING LAYOUT (FAHS) 08-Jun-17 24-Aug-17 62 100% 0 27-May-17 A 03-Aug-17 A
DE5870 EARTHING & CABLE ROUTING LAYOUTS (FAHS) 08-Jun-17 24-Aug-17 62 100% 0 17-Jun-17 A 08-Nov-17 A
DE5860 ELECTRICAL MTOS (FAHS) 09-Jul-17 10-Aug-17 27 100% 0 04-Jul-17 A 02-Oct-17 A
Civil 24-May-17 18-Sep-17 84 0 25-May-17 A 23-Apr-18 A
DE7230 DRAINAGE LAYOUTS & DETAILS (FAHS) 24-May-17 08-Aug-17 62 100% 0 25-May-17 A 11-Apr-18 A
DE5610 GRADING & ROAD LAYOUTS & DETAILS (FAHS) 24-May-17 08-Aug-17 62 100% 0 25-May-17 A 05-Apr-18 A
DE5620 PLATFORMS STRUCTURAL DETAILS (FAHS) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 13-Mar-18 A
DE5630 FOUNDATIONS GA, PLANS & DETAILS (FAHS) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 23-Apr-18 A
DE5640 PIPE SUPPORT LAYOUTS & SCHEDULES (FAHS) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 11-Apr-18 A
Safety 18-May-17 15-Aug-17 63 0 03-May-17 A 12-Jul-18 A
DE5700 HAZARDOUS AREA SCHEDULES (FAHS) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Mar-18 A
DE5710 HSE LAYOUTS (FAHS) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 12-Jul-18 A
DE5720 F&G AND PROCESS CAUSE & EFFECT CHARTS (FAHS) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 05-May-18 A
DE5730 HSE DATA SHEETS (FAHS) 18-May-17 15-Aug-17 71 100% 0 03-May-17 A 24-Jan-18 A
DE5740 HSE P&IDS (FAHS) 18-May-17 06-Aug-17 63 100% 0 04-May-17 A 11-Jan-18 A
Instrument 20-Apr-17 20-Sep-17 110 0 21-Mar-17 A 18-Mar-18 A
DE7030 INSTRUMENTS F&G LOCATIONS & CABLE ROUTING LAYOUTS (FAHS) 20-Apr-17 15-Aug-17 95 100% 0 11-May-17 A 25-Jan-18 A
DE5570 INPUT/OUTPUT LISTS (DEMOLITION) (FAHS) 27-Apr-17 13-Jul-17 63 100% 0 21-Mar-17 A 26-Jul-17 A
DE5750 INSTRUMENTS LOCATIONS & CABLE ROUTING LAYOUTS (FAHS) 27-Apr-17 10-Aug-17 86 100% 0 18-May-17 A 10-Oct-17 A
DE5880 INSTRUMENTS DATA SHEETS (FAHS) 01-May-17 08-Aug-17 81 100% 0 04-Apr-17 A 26-Dec-17 A
DE5590 INSTRUMENTS DIAGRAMS (FAHS) 04-May-17 20-Sep-17 113 100% 0 25-May-17 A 18-Mar-18 A
DE7100 INSTRUMENTS BUILDING LAYOUT (FAHS) 16-May-17 01-Aug-17 63 100% 0 15-May-17 A 25-Jul-17 A
DE5580 INSTRUMENTS INDEX (FAHS) 30-May-17 14-Aug-17 62 100% 0 31-May-17 A 19-Oct-17 A
DE5890 INPUT/OUTPUT AND ALARM & TRIP LISTS (FAHS) 04-Jun-17 03-Sep-17 74 100% 0 08-Jun-17 A 10-Dec-17 A
DE5600 INSTRUMENTS SCOPE OF WORK (FAHS) 13-Jun-17 29-Aug-17 63 100% 0 13-Jul-17 A 19-Oct-17 A
DE5900 INSTRUMENTS CABLES & JUNCTION BOXES SCHEDULES (FAHS) 25-Jun-17 12-Sep-17 65 100% 0 29-Jun-17 A 19-Oct-17 A
DE5910 INSTRUMENTS MTO (FAHS) 09-Aug-17 12-Sep-17 28 100% 0 28-Sep-17 A 13-Dec-17 A
Jaleha Main 23-Mar-17 20-Sep-17 130 27 15-Mar-17 A 02-Dec-18 166
Process 23-Mar-17 20-Aug-17 106 0 04-Apr-17 A 11-Mar-18 A
DE5090 PROCESS PFDS (JALM) 23-Mar-17 08-Jun-17 62 100% 0 04-Apr-17 A 04-Dec-17 A
DE6850 PFD FOR FIRE WATER NETWORK (JALM) 19-Apr-17 05-Jul-17 62 100% 0 19-Apr-17 A 04-Dec-17 A
DE5100 PROCESS P&IDS (JALM) 27-Apr-17 13-Jul-17 62 100% 0 03-May-17 A 11-Mar-18 A
DE5110 PROCESS P&IDS (DEMOLITION) (JALM) 27-Apr-17 13-Jul-17 62 100% 0 03-May-17 A 02-Jan-18 A
DE5080 PROCESS LINE DESIGNATION TABLES (JALM) 04-Jun-17 20-Aug-17 62 100% 0 07-Jun-17 A 24-Jan-18 A
Piping 29-Mar-17 20-Sep-17 126 27 05-Apr-17 A 02-Dec-18 166
DE6900 PIPING EQUIPMENT LOCATION PLAN (JALM) 29-Mar-17 13-Jun-17 62 100% 0 09-Apr-17 A 04-Mar-18 A
DE5230 PIPING PLOT PLANS (JALM) 02-Apr-17 15-Jun-17 62 100% 0 05-Apr-17 A 04-Mar-18 A
DE5350 PIPING VALVE & PIPING SPECIALITY ITEMS LISTS (JALM) 21-May-17 20-Aug-17 74 100% 0 25-May-17 A 02-Nov-17 A
DE5390 PIPING MTOS (JALM) 05-Jun-17 20-Aug-17 62 100% 0 07-Jun-17 A 10-Jan-18 A
DE5400 PIPING CRITICAL LINE LIST (JALM) 14-Jun-17 31-Aug-17 64 100% 0 21-Jun-17 A 14-Sep-17 A
DE5260 PLOT PLANS (DEMOLITION) (JALM) 18-Jun-17 03-Sep-17 63 100% 0 22-Jun-17 A 18-Oct-17 A
DE5370 PIPING STRESS ANALYSIS REPORT (JALM) 04-Jul-17 07-Aug-17 28 100% 0 03-Jul-17 A 26-Feb-18 A
DE5250 PIPING G.A (JALM) 10-Jul-17 20-Sep-17 60 100% 0 08-Jul-17 A 22-Mar-18 A
DE5410 PIPING MTOS (DEMOLITION) (JALM) 12-Jul-17 15-Aug-17 28 100% 0 07-Jun-17 A 10-Jan-18 A
DE5270 PIPING G.A (DEMOLITION) (JALM) 24-Jul-17 17-Sep-17 44 100% 0 27-Jul-17 A 09-Nov-17 A
DE5340 PIPE SUPPORT LIST (JALM) 24-Jul-17 14-Sep-17 43 100% 0 27-Jul-17 A 22-Jan-18 A
DE5240 PIPING TIE-IN PACKAGES & SCHEDULES (JALM) 30-Jul-17 19-Sep-17 43 85% 27 04-Aug-17 A 02-Dec-18 166
DE5380 PIPING KEY PLANS (JALM) 30-Jul-17 14-Sep-17 39 100% 0 01-Aug-17 A 26-Nov-17 A
DE5360 PIPING ISOMETRICS (JALM) 20-Aug-17 20-Sep-17 27 100% 0 18-Jan-18 A 22-Feb-18 A
Electrical 30-Mar-17 13-Sep-17 119 0 14-Apr-17 A 26-Feb-18 A
DE5420 ELECTRICAL CALCULATIONS (JALM) 30-Mar-17 24-Jul-17 92 100% 0 14-Apr-17 A 01-Oct-17 A
DE5120 TIE-IN, CABLES & INTERCONNECTION SCHEDULES (JALM) 07-May-17 13-Sep-17 105 100% 0 04-May-17 A 25-Sep-17 A
DE5140 ELECTRICAL ADEQUACY REORTS (JALM) 14-May-17 30-Jul-17 62 100% 0 25-May-17 A 24-Sep-17 A
DE5130 SINGLE LINE DIAGRAMS (JALM) 24-May-17 09-Aug-17 62 100% 0 07-May-17 A 19-Sep-17 A
DE5430 LIGHTING LAYOUT (JALM) 15-Jun-17 31-Aug-17 62 100% 0 21-May-17 A 03-Aug-17 A
DE5450 EARTHING & CABLE ROUTING LAYOUTS (JALM) 18-Jun-17 03-Sep-17 62 100% 0 18-Jun-17 A 08-Nov-17 A

Page 22 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 10 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DE5440 ELECTRICAL MTOS (JALM) 09-Jul-17 10-Aug-17 27 100% 0 04-Jul-17 A 26-Feb-18 A
Civil 06-Jun-17 18-Sep-17 75 0 07-Jun-17 A 24-Sep-18 A
DE7240 DRAINAGE LAYOUTS & DETAILS (JALM) 06-Jun-17 22-Aug-17 63 100% 0 07-Jun-17 A 24-Sep-18 A
DE5190 GRADING & ROAD LAYOUTS & DETAILS (JALM) 06-Jun-17 22-Aug-17 63 100% 0 07-Jun-17 A 24-Sep-18 A
DE5200 PLATFORMS STRUCTURAL DETAILS (JALM) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 01-May-18 A
DE5210 FOUNDATIONS GA, PLANS & DETAILS (JALM) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 28-Jun-18 A
DE5220 PIPE SUPPORT LAYOUTS & SCHEDULES (JALM) 09-Jul-17 18-Sep-17 59 100% 0 08-Jul-17 A 24-Sep-18 A
Safety 18-May-17 15-Aug-17 63 0 03-May-17 A 11-Jul-18 A
DE5280 HAZARDOUS AREA SCHEDULES (JALM) 18-May-17 03-Aug-17 62 100% 0 25-May-17 A 22-Mar-18 A
DE5290 HSE LAYOUTS (JALM) 18-May-17 08-Aug-17 65 100% 0 25-May-17 A 11-Jul-18 A
DE5300 F&G AND PROCESS CAUSE & EFFECT CHARTS (JALM) 18-May-17 08-Aug-17 65 100% 0 15-May-17 A 17-Jun-18 A
DE5310 HSE DATA SHEETS (JALM) 18-May-17 15-Aug-17 71 100% 0 03-May-17 A 24-Jan-18 A
DE5320 HSE P&IDS (JALM) 18-May-17 06-Aug-17 63 100% 0 04-May-17 A 11-Jan-18 A
DE7170 DEMOLITION PROCESS CAUSE & EFFECT CHARTS (JALM) 29-May-17 14-Aug-17 62 100% 0 08-Jul-17 A 23-Aug-17 A
Instrument 20-Apr-17 20-Sep-17 110 0 15-Mar-17 A 26-Feb-18 A
DE7040 INSTRUMENTS F&G LOCATIONS & CABLE ROUTING LAYOUTS (JALM) 20-Apr-17 15-Aug-17 95 100% 0 22-Mar-17 A 25-Jan-18 A
DE5150 INPUT/OUTPUT LISTS (DEMOLITION) (JALM) 27-Apr-17 13-Jul-17 63 100% 0 15-Mar-17 A 26-Jul-17 A
DE5330 INSTRUMENTS LOCATIONS & CABLE ROUTING LAYOUTS (JALM) 27-Apr-17 10-Aug-17 86 100% 0 18-May-17 A 10-Oct-17 A
DE5460 INSTRUMENTS DATA SHEETS (JALM) 01-May-17 08-Aug-17 81 100% 0 04-Apr-17 A 21-Dec-17 A
DE5170 INSTRUMENTS DIAGRAMS (JALM) 04-May-17 20-Sep-17 113 100% 0 25-May-17 A 26-Feb-18 A
DE5160 INSTRUMENTS INDEX (JALM) 30-May-17 14-Aug-17 62 100% 0 31-May-17 A 19-Oct-17 A
DE5470 INPUT/OUTPUT AND ALARM & TRIP LISTS (JALM) 04-Jun-17 03-Sep-17 74 100% 0 08-Jun-17 A 10-Dec-17 A
DE5180 INSTRUMENTS SCOPE OF WORK (JALM) 13-Jun-17 29-Aug-17 63 100% 0 13-Jul-17 A 19-Oct-17 A
DE5480 INSTRUMENTS CABLES & JUNCTION BOXES SCHEDULES (JALM) 25-Jun-17 12-Sep-17 65 100% 0 29-Jun-17 A 19-Oct-17 A
DE5490 INSTRUMENTS MTO (JALM) 09-Aug-17 12-Sep-17 28 100% 0 28-Sep-17 A 14-Dec-17 A
Procurement 01-Apr-17 27-Jul-18 507 106 03-Apr-17 A 31-Jan-19 9
EQUIPMENTS 01-Apr-17 27-Jul-18 507 106 03-Apr-17 A 31-Jan-19 9
Mechanical 01-Apr-17 27-Jul-18 507 0 03-Apr-17 A 27-Sep-18 A
Three Phase Test
Te Separator 13-May-17 27-Jul-18 462 0 28-May-17 A 25-Aug-18 A
PC1000 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- TEST SEPARATOR 13-May-17 19-Jul-17 56 100% 0 28-May-17 A 10-Sep-17 A
PC1030 PREPARE VENDOR DOCUMENT REVIEW & APPROVAL 20-Jul-17 10-Sep-17 45 100% 0 12-Sep-17 A 26-Oct-17 A
PC1010 MANUFACTURING ( PROCUREMENT / MANUFAC, SHIP) - TEST SEPARATOR 11-Sep-17 27-Jul-18 320 100% 0 28-Nov-17 A 01-Aug-18 A
PC1190 DELIVERED AT AT SITE - TEST SEPARATOR - FIRST BATCH - 2 NOS 28-Jun-18 0 100% 0 23-Jul-18 A
PC1020 DELIVERED AT AT SITE - TEST SEPARATOR 2ND BATCH - 2 NOS 13-Jul-18 0 100% 0 12-Aug-18 A
PC1200 DELIVERED AT AT SITE - TEST SEPARATOR - 3RD BATCH 3NOS 27-Jul-18 0 100% 0 25-Aug-18 A
BS&W Meter 01-Jun-17 06-Apr-18 321 0 12-Jul-17 A 27-Sep-18 A
PC1070 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL - METERING SKID 01-Jun-17 09-Aug-17 56 100% 0 12-Jul-17 A 18-Jan-18 A
PC1080 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- METERING SKID 09-Aug-17 06-Apr-18 300 100% 0 19-Jan-18 A 20-Sep-18 A
PC1090 DELIVERED AT SITE- METERING SKID 06-Apr-18 0 100% 0 27-Sep-18 A
Piping 01-Apr-17 30-Sep-17 186 0 03-Apr-17 A 02-Nov-17 A
Procurment (Early
(Ea Tie-in ) for all Khatiya Station 01-Apr-17 30-Sep-17 186 0 03-Apr-17 A 02-Nov-17 A
BALL VALVES (1.5 inch to 10 inch) 01-Apr-17 30-Sep-17 186 0 03-Apr-17 A 31-Oct-17 A
SDPR00 ENQUIRY FLOATED/ RECIEVE BIDS 01-Apr-17 13-Apr-17 12 100% 0 03-Apr-17 A 20-Apr-17 A
SDPR10 BID EVALUATION - TBE ISSUE TO QP 15-Apr-17 30-Apr-17 14 100% 0 21-Apr-17 A 04-May-17 A
SDPR20 TBE APPROVAL - QP 01-May-17 06-May-17 5 100% 0 05-May-17 A 09-May-17 A
SDPR30 PO ISSUE VALVES 07-May-17 08-May-17 2 100% 0 10-May-17 A 11-May-17 A
SDPR40 MANUFACURING PERIOD / SHIPMENT & PORT CLEARENACE 08-May-17 29-Sep-17 180 100% 0 14-May-17 A 31-Oct-17 A
SDPR70 DELIVERY TO SITE 30-Sep-17 0 100% 0 31-Oct-17 A
Piping and Fittings
Fit / Flanges 13-Apr-17 16-Aug-17 131 0 20-Apr-17 A 02-Nov-17 A
SDPR100 ENQUIRY FLOATED/ RECIEVE BIDS 13-Apr-17 26-Apr-17 12 100% 0 20-Apr-17 A 16-May-17 A
SDPR010 BID EVALUATION - TBE ISSUE TO QP 27-Apr-17 17-May-17 18 100% 0 17-May-17 A 03-Jul-17 A
SDPR020 TBE APPROVAL - QP 18-May-17 23-May-17 5 100% 0 17-Jul-17 A 17-Jul-17 A
SDPR030 PO ISSUE PIPING 24-May-17 28-May-17 4 100% 0 15-Jul-17 A 17-Jul-17 A
SDPR040 MANUFACURING PERIOD & TRANSPORTATION 28-May-17 08-Aug-17 90 100% 0 18-Jul-17 A 26-Oct-17 A
SDPR050 SHIPMENT AND CLAREANCE 09-Aug-17 16-Aug-17 7 100% 0 27-Oct-17 A 02-Nov-17 A
SDPR070 DELIVERY AT SITE 16-Aug-17 0 100% 0 02-Nov-17 A
Piping Valves 05-Jun-17 06-Apr-18 317 0 29-Jun-17 A 13-Sep-18 A

Page 23 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 11 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Ball Valves 12-Jun-17 06-Apr-18 310 0 29-Jun-17 A 13-Sep-18 A
PR1020 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-ALL VALVES 12-Jun-17 09-Aug-17 48 100% 0 29-Jun-17 A 28-Dec-17 A
PR1000 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-ALL VALVES 09-Aug-17 06-Apr-18 300 100% 0 29-Dec-17 A 13-Sep-18 A
PR1010 DELIVERED AT SITE-ALL VALVES 06-Apr-18 0 100% 0 13-Sep-18 A
Gate, Globe an
and Check Valve 05-Jun-17 30-Mar-18 310 0 25-Jul-17 A 11-Jul-18 A
PC1390 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- GGC VALVES 05-Jun-17 02-Aug-17 48 100% 0 25-Jul-17 A 21-Dec-17 A
PC1370 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- GCC VALVES 02-Aug-17 30-Mar-18 300 100% 0 22-Dec-17 A 11-Jul-18 A
PC1380 DELIVERED AT SITE-GGC VALVES 30-Mar-18 0 100% 0 11-Jul-18 A
Butter Fly Valves
Valve - DELETED 0 0 27-Jul-17 A 29-Mar-18 A
PC1580 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- BUTTER FLY VALV 0 100% 0 25-Dec-17 A 29-Mar-18 A
PC1590 DELIVERED AT SITE-BUTTER FLY VALVES 0 100% 0 29-Mar-18 A
PC1600 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- BUTTER FLY VALVES 0 100% 0 27-Jul-17 A 24-Aug-17 A
Instrumentation & Control 12-Jun-17 03-May-18 339 61 19-Jun-17 A 20-Dec-18 13
Field Instrumentation
Instrumen 09-Aug-17 11-Mar-18 223 50 13-Jul-17 A 10-Dec-18 24
ELECTRONIC INSTRUMENTS
I (PT/TT) 09-Aug-17 11-Mar-18 223 50 19-Jul-17 A 10-Dec-18 15
PC1550 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- ELECTRONIC INSTRUM 09-Aug-17 18-Oct-17 56 100% 0 19-Jul-17 A 18-Jan-18 A
PC1560 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- ELECTRONIC INS 18-Oct-17 11-Mar-18 180 95% 47 18-Jan-18 A 10-Dec-18 14
PC1570 DELIVERED AT SITE- ELECTRONIC INSTRUMENTS (PT/TT) 11-Mar-18 0 0% 0 10-Dec-18 14
LEVEL GAUGES
GAUGE (MAGNETIC) 0 50 24-Jul-17 A 10-Dec-18 15
PC1610 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- LEVEL GAUGES (MAG 0 100% 0 24-Jul-17 A 12-Dec-17 A
PC1620 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- LEVEL GAUGES ( 0 95% 47 13-Dec-17 A 10-Dec-18 14
PC1630 DELIVERED AT SITE- LEVEL GAUGES (MAGNETIC) 0 0% 0 10-Dec-18 14
GAUGES (PG/TG)
(PG/T 0 50 20-Jul-17 A 10-Dec-18 15
PC1640 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-GAUGES (PG/TG) 0 100% 0 20-Jul-17 A 30-Jan-18 A
PC1650 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-GAUGES (PG/TG) 0 95% 47 31-Jan-18 A 10-Dec-18 14
PC1660 DELIVERED AT SITE- GAUGES (PG/TG) 0 0% 0 10-Dec-18 14
LEVEL GAUGES
GAUGE (GLASS TYPE) 0 50 24-Jul-17 A 10-Dec-18 16
PC1670 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- LEVEL GAUGES (GLAS 0 100% 0 24-Jul-17 A 15-Feb-18 A
PC1680 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-LEVEL GAUGES (G 0 80% 47 16-Feb-18 A 10-Dec-18 15
PC1690 DELIVERED AT SITE- LEVEL GAUGES (GLASS TYPE) 0 0% 0 10-Dec-18 15
LEVEL TRANSMITTERS
TRANSM (DISPLACER) 0 50 25-Jul-17 A 10-Dec-18 24
PC1700 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- LEVEL TRANSMITTERS 0 100% 0 25-Jul-17 A 28-Dec-17 A
PC1710 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-LEVEL TRANSMIT 0 80% 47 29-Dec-17 A 10-Dec-18 22
PC1720 DELIVERED AT SITE- LEVEL TRANSMITTERS (DISPLACER) 0 0% 0 10-Dec-18 22
LEVEL TRANSMITTERS
TRANSM (RADAR) 0 50 25-Jul-17 A 10-Dec-18 13
PC1730 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- LEVEL TRANSMITTER 0 100% 0 25-Jul-17 A 30-Jan-18 A
PC1740 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- LEVEL TRANSMIT 0 80% 47 01-Feb-18 A 10-Dec-18 12
PC1750 DELIVERED AT SITE- LEVEL TRANSMITTERS (RADAR) 0 0% 0 10-Dec-18 12
FLOW TRANSMITTERS
TRANSM 0 50 13-Jul-17 A 10-Dec-18 10
PC1760 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- FLOW TRANSMITTERS 0 100% 0 13-Jul-17 A 18-Jan-18 A
PC1770 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-FLOW TRANSMITT 0 70% 47 18-Jan-18 A 10-Dec-18 9
PC1780 DELIVERED AT SITE- FLOW TRANSMITTERS 0 0% 0 10-Dec-18 9
Modifcation Control
Con System (Honey Well, Emerson,Yokgawa) 28-Jun-17 03-May-18 322 54 27-Jul-17 A 13-Dec-18 12
Modifcation Control
Co System (Yokgawa) 28-Jun-17 03-May-18 322 50 27-Jul-17 A 10-Dec-18 15
PC1160 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- DCS 28-Jun-17 05-Sep-17 56 100% 0 27-Jul-17 A 21-Dec-17 A
PC1170 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-DCS 05-Sep-17 03-May-18 300 65% 47 22-Dec-17 A 10-Dec-18 14
PC1180 DELIVERED AT SITE- DCS (HARDWARE AND SOFTWARE)- EARLY TIE-IN WO 03-May-18 0 100% 0 20-Jan-18 A
PC1850 DELIVERED AT SITE- DCS (HARDWARE AND SOFTWARE)-JALEHA 0 0% 0 10-Dec-18 14
Modifcation Control
Co System (Honey Well) 0 54 03-Aug-17 A 13-Dec-18 11
PC1790 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- DCS 0 100% 0 03-Aug-17 A 28-Dec-17 A
PC1800 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-DCS 0 60% 50 29-Dec-17 A 13-Dec-18 11
PC1810 DELIVERED AT SITE- DCS (HARDWARE AND SOFTWARE) 0 0% 0 13-Dec-18 11
Modifcation Control
Co System (Emerson) 0 0 10-Aug-17 A 27-Sep-18 A
PC1820 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- DCS 0 100% 0 10-Aug-17 A 28-Dec-17 A
PC1830 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-DCS 0 100% 0 29-Dec-17 A 27-Sep-18 A
PC1840 DELIVERED AT SITE- DCS (HARDWARE AND SOFTWARE) 0 100% 0 27-Sep-18 A
Intrumentation & Control Valves 12-Jun-17 19-Apr-18 324 61 19-Jun-17 A 20-Dec-18 11
Control Valves 14-Jun-17 19-Apr-18 322 0 03-Aug-17 A 28-Aug-18 A

Page 24 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 12 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
PC1100 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- CONTROL VALVES 14-Jun-17 22-Aug-17 56 100% 0 03-Aug-17 A 19-Nov-17 A
PC1110 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- CONTROL VALVE 22-Aug-17 19-Apr-18 300 100% 0 20-Nov-17 A 28-Aug-18 A
PC1120 DELIVERED AT SITE- CONTROL VALVE 19-Apr-18 0 100% 0 28-Aug-18 A
SDV / BDV Valve
Valv 12-Jun-17 17-Apr-18 322 61 19-Jun-17 A 20-Dec-18 11
PC1460 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- SD / BD VALVE 12-Jun-17 20-Aug-17 56 100% 0 19-Jun-17 A 05-Apr-18 A
PC1470 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- SD/ BD VALVE 20-Aug-17 17-Apr-18 300 80% 57 06-Apr-18 A 20-Dec-18 11
PC1480 DELIVERED AT SITE- SD/ BD VALVE 17-Apr-18 0 0% 0 20-Dec-18 11
RESTRICTION ORIFICE 0 0 02-Aug-17 A 02-Aug-18 A
PC1860 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- RESTRICTION ORIFICE 0 100% 0 02-Aug-17 A 15-Feb-18 A
PC1870 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- RESTRICTION OR 0 100% 0 16-Feb-18 A 02-Aug-18 A
PC1880 DELIVERED AT SITE- RESTRICTION ORIFICE 0 100% 0 02-Aug-18 A
Pressure Relief
Relie Valve 0 50 19-Jun-17 A 10-Dec-18 10
PC1890 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- PRESSURE RELIEF VA 0 100% 0 19-Jun-17 A 04-Jan-18 A
PC1900 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- PRESSURE REL 0 90% 47 05-Jan-18 A 10-Dec-18 9
PC1910 DELIVERED AT SITE- PRESSURE RELIEF VALVES 0 0% 0 10-Dec-18 9
Safety 10-Jul-17 09-May-18 319 106 23-Jul-17 A 31-Jan-19 9
Fire and Gas Detectors
De 10-Jul-17 01-Apr-18 279 50 23-Jul-17 A 10-Dec-18 23
PC1130 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-FIRE & GAS DEVICES 10-Jul-17 21-Sep-17 60 100% 0 23-Jul-17 A 25-Jan-18 A
PC1140 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-FIRE & GAS DEV 21-Sep-17 01-Apr-18 240 50% 47 26-Jan-18 A 10-Dec-18 21
PC1150 DELIVERED AT SITE-FIRE & GAS DEVICES 01-Apr-18 0 0% 0 10-Dec-18 21
Fire Fighting Equipments
Eq 19-Jul-17 22-Mar-18 258 69 25-Jul-17 A 27-Dec-18 4
PC1490 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- FIRE FIGHTING EQUIP 19-Jul-17 27-Sep-17 56 100% 0 25-Jul-17 A 29-Mar-18 A
PC1500 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-FIRE FIGHTING EQ 27-Sep-17 22-Mar-18 220 90% 64 01-Apr-18 A 27-Dec-18 4
PC1510 DELIVERED AT SITE- FIRE FIGHTING EQUIPMENTS 22-Mar-18 0 0% 0 27-Dec-18 4
Deludge Skid 19-Jul-17 09-May-18 309 106 25-Jul-17 A 31-Jan-19 9
PC1040 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- DELUDGE SKID 19-Jul-17 27-Sep-17 56 100% 0 25-Jul-17 A 22-Feb-18 A
PC1050 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-DELUDGE SKID 27-Sep-17 09-May-18 280 55% 99 23-Feb-18 A 31-Jan-19 0
PC1060 DELIVERED AT SITE-DELUDGE SKID -1st LOT (Khatiya Stations) 09-May-18 0 0% 0 31-Dec-18 0
PC1950 DELIVERED AT SITE-DELUDGE SKID - 2nd LOT Remaining Stations 0 0% 0 31-Jan-19 9
Bulk Material 29-Jun-17 27-Jan-18 217 31 30-Jul-17 A 22-Nov-18 17
Electrical Bulks 09-Jul-17 15-Jan-18 198 31 30-Jul-17 A 22-Nov-18 8
Power & Control
Contro Cables 09-Jul-17 15-Jan-18 198 31 30-Jul-17 A 22-Nov-18 8
PC1250 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-POWER & CONT CABLE 09-Jul-17 17-Sep-17 56 100% 0 30-Jul-17 A 06-Mar-18 A
PC1260 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-POWER & CONT C 17-Sep-17 15-Jan-18 150 65% 29 07-Mar-18 A 22-Nov-18 8
PC1270 DELIVERED AT SITE-POWER & CONT CABLES 15-Jan-18 0 0% 0 22-Nov-18 8
Electrical Bulk Material
M 09-Jul-17 22-Dec-17 172 0 30-Jul-17 A 15-Aug-18 A
PC1220 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-ELECTRIC BULK 09-Jul-17 17-Sep-17 56 100% 0 30-Jul-17 A 06-Mar-18 A
PC1230 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-ELECTRIC BULK 17-Sep-17 22-Dec-17 120 100% 0 07-Mar-18 A 15-Aug-18 A
PC1240 DELIVERED AT SITE-ELECTRIC BULK 22-Dec-17 0 100% 0 15-Aug-18 A
Instrumentation 24-Aug-17 27-Jan-18 161 31 10-Aug-17 A 22-Nov-18 1
Instrumentation Bulk Material 24-Aug-17 17-Jan-18 151 0 10-Aug-17 A 18-Aug-18 A
PC1400 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-INSTRUMENTATION BU 24-Aug-17 06-Nov-17 60 100% 0 10-Aug-17 A 06-Mar-18 A
PC1410 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-INSTRUMENTATIO 06-Nov-17 17-Jan-18 90 100% 0 06-Mar-18 A 18-Aug-18 A
PC1420 DELIVERED AT SITE-INSTRUMENTATION BULK 17-Jan-18 0 100% 0 18-Aug-18 A
Instrument Cables
Cabl 24-Aug-17 27-Jan-18 161 31 10-Aug-17 A 22-Nov-18 1
PC1430 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-INSTRUMENT CABLES 24-Aug-17 23-Oct-17 48 100% 0 10-Aug-17 A 06-Mar-18 A
PC1440 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-INSTRUMENT CAB 23-Oct-17 27-Jan-18 120 95% 29 06-Mar-18 A 22-Nov-18 2
PC1450 DELIVERED AT SITE-INSTRUMENT CABLES 27-Jan-18 0 0% 0 22-Nov-18 2
Piping Bulk 29-Jun-17 25-Dec-17 182 29 03-Aug-17 A 20-Nov-18 19
Pipes / Fittings & Flanges 29-Jun-17 25-Dec-17 182 0 13-Aug-17 A 27-Sep-18 A
PC1310 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-PIPES 29-Jun-17 27-Aug-17 48 100% 0 13-Aug-17 A 18-Jan-18 A
PC1320 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-PIPES / FITTINGS 27-Aug-17 25-Dec-17 150 100% 0 19-Jan-18 A 05-Jul-18 A
PC1990 DELIVERED AT FABRICATION FACILITY / SITE -PIPES / FITTINGS & FLANGE 0 100% 0 30-Jul-18 A
PC2000 DELIVERED AT FABRICATION FACILITY / SITE -PIPES / FITTINGS & FLANGE 0 100% 0 30-Jul-18 A
PC2010 DELIVERED AT FABRICATION FACILITY / SITE -PIPES / FITTINGS & FLANGE 0 100% 0 20-Sep-18 A
PC2020 DELIVERED AT FABRICATION FACILITY / SITE -PIPES / FITTINGS & FLANGE 0 100% 0 27-Sep-18 A
PROJECT FITTINGS
FITTIN 0 0 03-Aug-17 A 27-Sep-18 A
PC1920 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-PROJECT FITTINGS (Y-T 0 100% 0 03-Aug-17 A 18-Jan-18 A

Page 25 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 13 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
PC1930 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)- (Y-TYPE STRAINE 0 100% 0 19-Jan-18 A 27-Sep-18 A
PC1940 DELIVERED AT SITE- (Y-TYPE STRAINER/CC PROBES) 0 100% 0 27-Sep-18 A
Gaskets and Bolts
Bo 29-Jun-17 25-Dec-17 182 29 10-Aug-17 A 20-Nov-18 19
PC1340 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)-GASKETS AND BOLTS 29-Jun-17 27-Aug-17 48 100% 0 10-Aug-17 A 18-Jan-18 A
PC1350 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-GASKETS AND BO 27-Aug-17 25-Dec-17 150 90% 27 19-Jan-18 A 20-Nov-18 18
PC1360 DELIVERED AT SITE-GASKETS AND BOLTS 25-Dec-17 0 0% 0 20-Nov-18 18
Civil 05-Aug-17 14-Dec-17 137 0 07-Aug-17 A 25-Jan-18 A
Steel Structure 05-Aug-17 14-Dec-17 137 0 07-Aug-17 A 25-Jan-18 A
PR1030 P.O ISSUANCE (MR, INQUIRY, BIDS, QP APPROVAL)- STEEL STRUCTURE 05-Aug-17 03-Oct-17 48 100% 0 07-Aug-17 A 19-Dec-17 A
PR1040 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-STEEL STRUCTUR 03-Oct-17 14-Dec-17 90 100% 0 20-Dec-17 A 25-Jan-18 A
PR1050 DELIVERED AT SITE-STEEL STRUCURE 14-Dec-17 0 100% 0 25-Jan-18 A
Sub-Contract Packages
Pac 04-May-17 21-Aug-17 91 0 04-Jun-17 A 14-Nov-17 A
HSE Studies 04-May-17 20-Jun-17 40 0 04-Jun-17 A 08-Oct-17 A
PC1520 PACKAGE ENQUIRY FLOATED FOR HSE WORKS 04-May-17 10-May-17 5 100% 0 04-Jun-17 A 10-Jun-17 A
PC1530 RECEIVE BIDS, EVALUATION, COMPANY APPROVAL 10-May-17 14-Jun-17 30 100% 0 10-Jun-17 A 03-Oct-17 A
PC1540 ISSUE PO 14-Jun-17 20-Jun-17 5 100% 0 04-Oct-17 A 08-Oct-17 A
NDT 15-Jun-17 21-Aug-17 55 0 01-Jul-17 A 14-Nov-17 A
PS1000 PACKAGE ENQUIRY FLOATED FOR NDT WORKS 15-Jun-17 20-Jun-17 5 100% 0 01-Jul-17 A 05-Jul-17 A
PS1010 RECEIVE BIDS, EVALUATION, COMPANY APPROVAL 21-Jun-17 15-Aug-17 45 100% 0 06-Jul-17 A 12-Nov-17 A
PS1020 ISSUE PO NDT 16-Aug-17 21-Aug-17 5 100% 0 13-Nov-17 A 14-Nov-17 A
Pre-construction Prepartation
P 19-Feb-17 02-Oct-17 187 0 16-Mar-17 A 21-Jan-18 A
Mobilization Plan 23-May-17 02-Oct-17 107 0 10-Aug-17 A 21-Jan-18 A
A1390 MANPOWER MOBILIZATION FOR TCF SET-UP 23-May-17 24-Aug-17 78 100% 0 10-Aug-17 A 09-Jan-18 A
A1400 EQUIPMENT MOBILIZATION FOR TCF SET-UP 23-May-17 24-Aug-17 78 100% 0 10-Sep-17 A 09-Jan-18 A
A1410 MANPOWER MOBILIZATION FOR PLANT CONSTRUCTION 24-Jul-17 02-Oct-17 57 100% 0 15-Oct-17 A 21-Jan-18 A
A1420 EQUIPMENT MOBILIZATION FOR PLANT CONSTRUCTION 24-Jul-17 02-Oct-17 57 100% 0 05-Oct-17 A 21-Jan-18 A
Documents Prepatation
Prep 19-Feb-17 03-Aug-17 140 0 16-Mar-17 A 27-Sep-17 A
A1350 PLANNING PACKAGE APPROVED BY QP 19-Feb-17 22-May-17 80 100% 0 16-Mar-17 A 27-Sep-17 A
A1360 H&S PLAN APPROVED BY QP 23-May-17 03-Aug-17 60 100% 0 27-Mar-17 A 10-Aug-17 A
A1370 QA/QC PLAN APPROVED BY QP 23-May-17 03-Aug-17 60 100% 0 25-Mar-17 A 04-Jul-17 A
A1380 CEMP APPROVED BY QP 23-May-17 03-Aug-17 60 100% 0 16-Apr-17 A 27-Aug-17 A
TCF Set-up 23-May-17 24-Aug-17 78 0 02-Sep-17 A 11-Jan-18 A
A1430 TCF SET-UP 23-May-17 24-Aug-17 78 100% 0 02-Sep-17 A 11-Jan-18 A
CONSTRUCTION WORKS 03-Jun-17 24-Dec-18 601 267 09-Jun-17 A 01-Jul-19 23
Early Tie-in (3 Degassing
De Station) 03-Jun-17 23-Oct-17 116 0 09-Jun-17 A 18-Jan-18 A
Welder Qualification
Qualifica (Shutdown Tie-in ) for KM /KN/KS 03-Jun-17 23-Oct-17 116 0 09-Jun-17 A 18-Jan-18 A
SDCN110 METHOD STATEMENTS / WPS / PQR 03-Jun-17 27-Jul-17 45 100% 0 09-Jun-17 A 11-Jan-18 A
SDCN90 WELDER QUALIFICATION 17-Aug-17 25-Sep-17 30 100% 0 28-Oct-17 A 30-Dec-17 A
SDCN100 SPOOL FABRICATION 02-Sep-17 16-Oct-17 35 100% 0 19-Dec-17 A 18-Jan-18 A
SDCN120 READY FOR SHUTDOWN 23-Oct-17 0 100% 0 30-Dec-17 A
KAHS 07-Nov-17 21-Nov-18 325 117 25-Dec-17 A 10-Mar-19 62
FABRICATION 25-Feb-18 29-Mar-18 29 43 06-Feb-18 A 13-Dec-18 9
Structural Steel Fabrication 26-Feb-18 22-Mar-18 22 14 06-Feb-18 A 10-Nov-18 33
TEST SEPERATOR
SEPERAT 26-Feb-18 11-Mar-18 12 10 16-Aug-18 A 05-Nov-18 0
F220 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CR 26-Feb-18 11-Mar-18 12 95% 10 16-Aug-18 A 05-Nov-18 0
METERING SKID
SK 19-Mar-18 22-Mar-18 4 0 19-Jun-18 A 26-Aug-18 A
F250 FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS. TRANSFE 19-Mar-18 22-Mar-18 4 100% 0 19-Jun-18 A 26-Aug-18 A
PSV 15-Mar-18 18-Mar-18 3 10 06-Feb-18 A 05-Nov-18 21
F240 FAB. OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTURE TRANSF 15-Mar-18 18-Mar-18 3 95% 10 06-Feb-18 A 05-Nov-18 21
PIPE SUPPORT 12-Mar-18 14-Mar-18 3 14 06-Feb-18 A 10-Nov-18 33
F230 FAB. OF PIPESUPPORT STRUCTURE TRANSFER TO SITE FOR INSTALLATI 12-Mar-18 14-Mar-18 3 98% 14 06-Feb-18 A 10-Nov-18 3
F260-1 FABRICATION OF INSTRUMENT STANCHION SUPPORTS 0 100% 0 02-Sep-18 A 16-Sep-18 A
Piping Fabrication
Fabricati 25-Feb-18 29-Mar-18 29 43 27-Sep-18 A 13-Dec-18 9
FBE PIPING (AT KUWAIT) 25-Feb-18 29-Mar-18 29 43 27-Sep-18 A 13-Dec-18 0
F290 PIPING FABRICATION & FBE COATING AT KUWAIT 25-Feb-18 29-Mar-18 29 0% 34 08-Oct-18 A 03-Dec-18 0
F320-2 FBE PIPING BULK DELIVER AT SITE 0 0% 9 04-Dec-18 13-Dec-18 0
F290-00 PIPE DELIVER AT KUWAIT 0 100% 0 27-Sep-18 A
REMAINING PIPING
PI (NON - FBE) 0 33 27-Sep-18 A 02-Dec-18 19

Page 26 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 14 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
F290-1 COMPLETE PIPING FABRICATION INCL. HYDROTEST/ PAINTING & COATING 0 0% 26 21-Oct-18 A 24-Nov-18 3
F320-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 13 18-Nov-18 02-Dec-18 19
F290-4 PIPE DELIVER AT FAB FACILITY 0 100% 0 27-Sep-18 A
INSTALLATION 07-Nov-17 19-Nov-18 323 70 25-Dec-17 A 14-Jan-19 10
Civil Works 10-Jan-18 19-Nov-18 269 70 25-Dec-17 A 14-Jan-19 6
COMMON 10-Jan-18 19-Nov-18 269 70 10-Feb-18 A 14-Jan-19 6
A1710 GRADING 10-Jan-18 15-Jan-18 5 100% 0 10-Feb-18 A 31-May-18 A
A1770 ROADSND PAVING(INCLUDING MODIFICATIONS) 10-Oct-18 25-Oct-18 14 0% 13 31-Dec-18 14-Jan-19 6
A1790 DRAINAGE PIPE CULVERTS 27-Oct-18 11-Nov-18 14 0% 20 08-Dec-18 30-Dec-18 5
A1800 ROAD SAFETY CRASH BARRIERS AND BOLLARD 27-Oct-18 29-Oct-18 3 0% 13 31-Dec-18 14-Jan-19 6
A1780 UTILITY ROAD CROSSINGS 27-Oct-18 19-Nov-18 21 0% 26 11-Dec-18 09-Jan-19 5
A1780-2 CABLE TRENCHES 0 35% 25 24-Sep-18 A 22-Nov-18 2
A1710-1 PROTECTION OF UNDERGROUND CABLES 0 90% 25 14-Sep-18 A 22-Nov-18 5
A1715-6 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPL 0 98% 8 06-Aug-18 A 03-Nov-18 2
A1800-1 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) 0 0% 13 30-Dec-18 13-Jan-19 7
TEST SEPERATOR
SEPERAT 10-Jan-18 19-Feb-18 35 0 10-Feb-18 A 08-Aug-18 A
A1715 EXCAVATION FOR THE MAIN FOUNDATIONS 10-Jan-18 17-Jan-18 7 100% 0 10-Feb-18 A 01-Mar-18 A
A1720 FOUNDATION WORK (STEEL FIXING) 18-Jan-18 19-Feb-18 28 100% 0 07-Apr-18 A 12-Apr-18 A
A1720-1 FOUNDATION WORK (CONCRETE) 0 100% 0 07-Apr-18 A 26-Apr-18 A
A1720-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 17-May-18 A 08-Aug-18 A
TEST SEPERAT
SEPERATOR PLATFORM 0 0 10-Feb-18 A 08-Aug-18 A
A1715-1 EXCAVATION FOR THE MAIN FOUNDATIONS 0 100% 0 10-Feb-18 A 01-Mar-18 A
A1720-3 FOUNDATION WORK (STEEL FIXING) 0 100% 0 07-Apr-18 A 12-Apr-18 A
A1720-4 FOUNDATION WORK (CONCRETE) 0 100% 0 07-Apr-18 A 26-Apr-18 A
A1720-5 CURING / WATERPROOFING / BACK FILLING 0 100% 0 17-May-18 A 08-Aug-18 A
METERING SKID
SK 17-Mar-18 24-Mar-18 7 0 10-Feb-18 A 08-Aug-18 A
A1760 FOUNDATION WORK (CONCRETE) 17-Mar-18 24-Mar-18 7 100% 0 18-Mar-18 A 24-May-18 A
A1715-2 EXCAVATION 0 100% 0 10-Feb-18 A 24-Mar-18 A
A1760-1 FOUNDATION WORK (STEEL FIXING) 0 100% 0 22-Mar-18 A 12-Apr-18 A
A1760-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 15-May-18 A 08-Aug-18 A
PIPE SUPPORT 20-Feb-18 15-Mar-18 21 0 25-Dec-17 A 25-Oct-18 A
A1740 FOUNDATION WORK (STEEL FIXING) 20-Feb-18 15-Mar-18 21 100% 0 25-Dec-17 A 08-Aug-18 A
A1715-3 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 100% 0 25-Dec-17 A 19-Jul-18 A
A1740-1 FOUNDATION WORK (CONCRETE) 0 100% 0 25-Dec-17 A 14-Aug-18 A
A1740-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 25-Dec-17 A 25-Oct-18 A
PSV 0 0 05-Mar-18 A 06-Aug-18 A
A1715-4 EXCAVATION (INCLUDING AREA LIGHTING POLES) 0 100% 0 05-Mar-18 A 31-May-18 A
A1760-5 FOUNDATION WORK (STEEL FIXING) 0 100% 0 25-Mar-18 A 17-May-18 A
A1760-3 FOUNDATION WORK (CONCRETE) 0 100% 0 18-Mar-18 A 21-Jun-18 A
A1760-4 CURING / WATERPROOFING / BACK FILLING 0 100% 0 18-Mar-18 A 06-Aug-18 A
Structural Steel 20-Aug-18 08-Sep-18 17 31 27-Sep-18 A 29-Nov-18 21
TEST SEPERATOR
SEPERAT 20-Aug-18 04-Sep-18 14 24 27-Sep-18 A 21-Nov-18 10
A2480 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PL 20-Aug-18 27-Aug-18 7 10% 24 27-Sep-18 A 21-Nov-18 0
A2510 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 02-Sep-18 04-Sep-18 3 0% 9 12-Nov-18 21-Nov-18 10
METERING SKID
SK 23-Aug-18 28-Aug-18 5 0 13-Oct-18 A 23-Oct-18 A
A2490 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK W 23-Aug-18 28-Aug-18 5 100% 0 13-Oct-18 A 23-Oct-18 A
PSV 27-Aug-18 01-Sep-18 5 19 17-Oct-18 A 15-Nov-18 21
A2500 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 27-Aug-18 01-Sep-18 5 0% 19 17-Oct-18 A 15-Nov-18 21
PIPE SUPPORT 05-Sep-18 08-Sep-18 3 29 10-Oct-18 A 27-Nov-18 21
A2520 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS 05-Sep-18 08-Sep-18 3 0% 29 10-Oct-18 A 27-Nov-18 21
FIELD INSTRUMENT
INSTRUM 0 5 25-Nov-18 29-Nov-18 21
A2520-1 INSTALLATION OF INSTRUMENT STANCHION 0 0% 5 25-Nov-18 29-Nov-18 21
Mechanical 02-Aug-18 19-Aug-18 15 0 09-Aug-18 A 09-Aug-18 A
A2815 INSTALLATION OF NEW TEST SEPARATOR 02-Aug-18 19-Aug-18 15 100% 0 09-Aug-18 A 09-Aug-18 A
Piping 07-Nov-17 17-Sep-18 269 22 31-Dec-17 A 09-Jan-19 14
EARLY SHUTDOWN
SHUTDO WORKS - Pre Shutdown and Plant Shutdown Tie-in 07-Nov-17 22-Dec-17 38 0 31-Dec-17 A 17-Feb-18 A
A3061 MOBILIZATION OF OF TEAM APPLY PTW 07-Nov-17 07-Nov-17 1 100% 0 31-Dec-17 A 31-Dec-17 A
A3071 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 08-Nov-17 30-Nov-17 20 100% 0 31-Dec-17 A 05-Jan-18 A

Page 27 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 15 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A3081 PIPING TIE-IN / NDT 06-Dec-17 20-Dec-17 12 100% 0 09-Feb-18 A 14-Feb-18 A
A3091 TIE-IN COMPLETE / REMOVE SCAFFOLD 21-Dec-17 22-Dec-17 2 100% 0 06-Feb-18 A 17-Feb-18 A
STATION PIPING
PIPIN 09-Aug-18 17-Sep-18 34 22 16-Dec-18 09-Jan-19 4
A3020 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 09-Aug-18 01-Sep-18 20 0% 18 16-Dec-18 05-Jan-19 0
A3030 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 20-Aug-18 26-Aug-18 6 0% 4 06-Jan-19 09-Jan-19 4
A3040 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 02-Sep-18 05-Sep-18 4 0% 12 24-Dec-18 06-Jan-19 3
A3050 TIE-IN 06-Sep-18 17-Sep-18 10 0% 4 06-Jan-19 09-Jan-19 0
A3020-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 24-Dec-18 02-Jan-19 0
A3051-1 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 07-Jan-19 09-Jan-19 3
Electrical 16-Jan-18 13-Oct-18 232 52 08-Nov-18 07-Jan-19 5
A3450 CABLE GLANDING AND TERMINATION 16-Jan-18 31-Jan-18 14 0% 7 22-Dec-18 29-Dec-18 9
A3460 U/G CABLE LAYING 01-Feb-18 08-Feb-18 7 0% 5 29-Nov-18 04-Dec-18 5
A3470 CABLE TRAY INSTALLATION 28-Aug-18 12-Sep-18 14 0% 8 22-Nov-18 01-Dec-18 0
A3480 ELECTRICAL EQUIPMENTS INSTALLATION 13-Sep-18 20-Sep-18 7 0% 10 09-Dec-18 19-Dec-18 5
A3490 CABLE LAYING 22-Sep-18 29-Sep-18 7 0% 8 02-Dec-18 10-Dec-18 5
A3500 LIGHTING FIXTURE AND DB INSTALLATION 22-Sep-18 29-Sep-18 7 0% 8 16-Dec-18 24-Dec-18 5
A3510 ELECTRICAL TIE-INS 30-Sep-18 07-Oct-18 7 0% 2 03-Jan-19 05-Jan-19 5
A3520 ENERGIZATION 08-Oct-18 13-Oct-18 5 0% 3 05-Jan-19 07-Jan-19 5
A3460-1 BACK FILLING OF CABLE TRENCH 0 0% 9 02-Dec-18 11-Dec-18 5
A3510-1 HOOK UP 0 0% 4 25-Dec-18 29-Dec-18 5
A3530 EARTH PIT DRILLING 0 0% 4 08-Nov-18 12-Nov-18 0
Instrument & Control
Co 20-Aug-18 17-Nov-18 77 49 13-Nov-18 08-Jan-19 0
A4090 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 20-Aug-18 02-Sep-18 12 0% 10 25-Dec-18 05-Jan-19 0
A4050 CABLE TRAY AND SUPPORTS INSTALLATION 01-Sep-18 16-Sep-18 14 0% 17 13-Nov-18 02-Dec-18 0
A4060 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TESTING 17-Sep-18 24-Sep-18 7 0% 4 05-Jan-19 08-Jan-19 0
A4070 INSTRUMENT EQUIPEMNT INSTALLATION (RO, SDV, RELIEF VALVE & CONT 25-Sep-18 02-Oct-18 7 0% 6 20-Dec-18 26-Dec-18 0
A4080 SS TUBING AND LEAK TEST 03-Oct-18 08-Oct-18 5 0% 4 01-Jan-19 05-Jan-19 0
A5300 INSTALLATION OF DELUGE 09-Oct-18 16-Oct-18 7 0% 7 01-Jan-19 08-Jan-19 0
A4640 JB SUPPORT INSTALLATION 21-Oct-18 23-Oct-18 3 0% 4 02-Dec-18 05-Dec-18 0
A4740 JB INSTALLATION 14-Nov-18 17-Nov-18 3 0% 3 04-Dec-18 06-Dec-18 0
A4090-2 INSTALLATION OF INSTRUMENT VALVE 0 0% 3 23-Dec-18 25-Dec-18 8
A4080-2 FIELD INSTRUMENT INSTALLATION (GAUGES & TRANSMITTERS) 0 0% 7 16-Dec-18 23-Dec-18 9
A4090-1 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 2 25-Dec-18 26-Dec-18 7
A4080-1 INSTRUMENT CABLE LAYING 0 0% 17 05-Dec-18 24-Dec-18 0
A4080-11 CABLE GLANDS AND TERMINATION (ALONG JBs) 0 0% 10 24-Dec-18 03-Jan-19 0
A4080-21 CABLE GLANDS AND TERMINATION (ALONG INSTRUMENTS) 0 0% 5 20-Dec-18 25-Dec-18 9
F&G System 0 33 28-Nov-18 05-Jan-19 7
A5910 F&G CABLE INSTALLATION 0 0% 9 05-Dec-18 15-Dec-18 25
A5920 F&G SUPPORTS INSTALLATION 0 0% 4 28-Nov-18 02-Dec-18 30
A5930 F&G DEVICES INSTALLATION 0 0% 5 11-Dec-18 16-Dec-18 24
A5940 F&G JB SUPPORT INSTALLATION 0 0% 2 05-Dec-18 06-Dec-18 32
A5950 F&G JB INSTALLATION 0 0% 3 06-Dec-18 09-Dec-18 30
A5960 F&G CABLE GLANDING AND TERMINATION 0 0% 5 20-Dec-18 25-Dec-18 9
A5970 F&G LOOP PREPARATION 0 0% 3 25-Dec-18 27-Dec-18 9
A5980 F&G LOOP TESTING 0 0% 5 31-Dec-18 05-Jan-19 7
Painting & Fireproofing
Firep 28-Aug-18 13-Sep-18 15 20 15-Dec-18 06-Jan-19 4
A4360 STRUCTURAL STEEL PAINTING AND TOUCH-UP 28-Aug-18 04-Sep-18 7 0% 12 15-Dec-18 27-Dec-18 4
A4380 FIREPROOFING FOR STRUCTURAL STEEL 05-Sep-18 12-Sep-18 7 0% 16 19-Dec-18 06-Jan-19 4
A4370 PIPING PAINTING AND TOUCH-UP 06-Sep-18 13-Sep-18 7 0% 4 24-Dec-18 27-Dec-18 4
Pre-commisionin
Pre-commisioning 06-Sep-18 25-Oct-18 43 73 09-Sep-18 A 17-Jan-19 1
A3051 INST LOOP AND FUNCTIONAL TEST 06-Sep-18 09-Sep-18 3 0% 3 06-Jan-19 08-Jan-19 0
A4610 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 02-Oct-18 09-Oct-18 7 17% 58 09-Sep-18 A 31-Dec-18 10
A4650 DELUGE SKID FUNCTIONAL TESTING 02-Oct-18 25-Oct-18 21 0% 5 09-Jan-19 14-Jan-19 4
A4620 ELECTRICAL LIGHITING TEST 06-Oct-18 08-Oct-18 3 0% 5 08-Jan-19 13-Jan-19 0
A4630 PUNCHLIST 17-Oct-18 20-Oct-18 3 0% 4 14-Jan-19 17-Jan-19 0
A4620-1 LEAK TEST FOR PIPING AND SEPARATOR 0 0% 5 08-Jan-19 13-Jan-19 0
Commissioning 01-Nov-18 09-Nov-18 7 8 17-Jan-19 26-Jan-19 0

Page 28 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 16 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A5010 START OF PRODUCTION 01-Nov-18 3 0% 0 17-Jan-19 0
A5020 COMMISSIONING AND STARTUP 01-Nov-18 04-Nov-18 3 0% 4 17-Jan-19 21-Jan-19 0
A5030 PERFORMANCE TESTS 04-Nov-18 09-Nov-18 7 0% 4 22-Jan-19 26-Jan-19 0
Demolition Works
Work 03-Nov-18 21-Nov-18 16 45 17-Jan-19 10-Mar-19 62
DM1070 WORK PERMIT APPROVED FOR DEMOLITION 03-Nov-18 06-Nov-18 3 0% 3 17-Jan-19 20-Jan-19 67
DM1080 DEPRESSURIZATION / ISOLATION (PIPING & INSTRUMENTATION) 06-Nov-18 08-Nov-18 2 0% 2 27-Jan-19 28-Jan-19 62
DM1100 APPLY ANTI RUST TO FOUNDATION BOTLS 08-Nov-18 10-Nov-18 1 0% 3 28-Jan-19 30-Jan-19 80
DM1090 COLD CUTTING INLET AND OUTLET PIPING REMOVAL 10-Nov-18 13-Nov-18 3 0% 21 28-Jan-19 20-Feb-19 62
DM1110 UNBOLD & REMOVE EXISTING SEPARATOR 13-Nov-18 15-Nov-18 2 0% 4 20-Feb-19 24-Feb-19 62
DM1120 REMOVE CONCRETE FOUNDATION / GRADE THE AREA 15-Nov-18 21-Nov-18 5 0% 13 24-Feb-19 10-Mar-19 62
DM1130 DEMOLITION WORKS COMPLETE 21-Nov-18 0 0% 0 10-Mar-19 62
KAHN 03-Oct-17 18-Dec-18 378 120 10-Dec-17 A 13-Mar-19 59
FABRICATION 24-Jan-18 11-Mar-18 40 44 09-May-18 A 15-Dec-18 33
Structural Steel Fabrication 24-Jan-18 25-Feb-18 28 17 09-May-18 A 13-Nov-18 29
TEST SEPERATOR
SEPERAT 24-Jan-18 10-Feb-18 15 17 19-Sep-18 A 13-Nov-18 3
F110 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CR 24-Jan-18 10-Feb-18 15 90% 17 19-Sep-18 A 13-Nov-18 3
METERING SKID
SK 20-Feb-18 25-Feb-18 5 0 28-May-18 A 16-Aug-18 A
F140 FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS. TRANSFE 20-Feb-18 25-Feb-18 5 100% 0 28-May-18 A 16-Aug-18 A
PSV 15-Feb-18 19-Feb-18 4 0 17-May-18 A 21-Aug-18 A
F130 FAB. OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTURE TO SITE 15-Feb-18 19-Feb-18 4 100% 0 17-May-18 A 21-Aug-18 A
PIPE SUPPORT 11-Feb-18 14-Feb-18 4 17 09-May-18 A 13-Nov-18 29
F120 COMPLETE FAB. OF PIPESUPPORT STRUCTURE TRANSFER TO SITE FOR 11-Feb-18 14-Feb-18 4 99% 17 09-May-18 A 13-Nov-18 0
F120-1 FABRICATION OF INSTRUMENT STANCHION SUPPORTS 0 100% 0 15-Aug-18 A 16-Sep-18 A
Piping Fabrication
Fabricati 25-Jan-18 11-Mar-18 39 44 27-Sep-18 A 15-Dec-18 33
FBE PIPING (AT KUWAIT) 25-Jan-18 11-Mar-18 39 44 27-Sep-18 A 15-Dec-18 33
F180 PIPING FABRICATION & FBE COATING AT KUWAIT 25-Jan-18 24-Feb-18 26 0% 34 08-Oct-18 A 03-Dec-18 43
F210 FBE PIPING BULK DELIVER AT SITE 22-Feb-18 11-Mar-18 15 0% 13 01-Dec-18 15-Dec-18 12
F180-2 PIPE DELIVER AT KUWAIT 0 100% 0 27-Sep-18 A
REMAINING PIPING
PI ( NON FBE) 0 37 27-Sep-18 A 08-Dec-18 3
F180-1 COMPLETE PIPING FABRICATION . HYDROTEST/ PAINTING & COATING 0 0% 33 27-Oct-18 03-Dec-18 3
F210-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 13 24-Nov-18 08-Dec-18 3
F180-3 PIPE DELIVER AT FAB FACILITY 0 100% 0 27-Sep-18 A
INSTALLATION 03-Oct-17 18-Dec-18 378 72 10-Dec-17 A 16-Jan-19 11
Civil Works 03-Oct-17 06-Oct-18 315 72 10-Dec-17 A 16-Jan-19 6
COMMOMN 03-Oct-17 06-Oct-18 315 72 10-Feb-18 A 16-Jan-19 6
A1440 GRADING 03-Oct-17 26-Oct-17 21 100% 0 10-Feb-18 A 31-May-18 A
A1510 CABLE TRENCHES AND UTILITY ROAD CROSSINGS 28-Oct-17 20-Nov-17 21 35% 24 25-Aug-18 A 21-Nov-18 9
A1520 DRAINAGE PIPE CULVERTS 12-Sep-18 27-Sep-18 14 100% 0 30-Sep-18 A 16-Oct-18 A
A1530 ROAD SAFETY CRASH BARRIERS AND BOLLARD 12-Sep-18 06-Oct-18 21 0% 13 02-Jan-19 16-Jan-19 6
A1500 ROADS AND PAVING(INCLUDING MODIFICATIONS) 12-Sep-18 27-Sep-18 14 0% 13 02-Jan-19 16-Jan-19 6
A1440-1 PROTECTION OF UNDERGROUND CABLES 0 90% 24 05-Sep-18 A 21-Nov-18 13
A1445-6 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPL 0 90% 20 14-Aug-18 A 17-Nov-18 13
A1530-1 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) 0 0% 13 02-Jan-19 16-Jan-19 6
TEST SEPERATOR
SEPERAT 16-Oct-17 28-Nov-17 38 0 09-Feb-18 A 11-Aug-18 A
A1445 EXCAVATION FOR THE MAIN FOUNDATIONS 16-Oct-17 26-Oct-17 10 100% 0 09-Feb-18 A 29-Mar-18 A
A1450 FOUNDATION WORK (STEEL FIXING) 28-Oct-17 28-Nov-17 28 100% 0 01-Apr-18 A 12-Apr-18 A
A1450-1 FOUNDATION WORK (CONCRETE) 0 100% 0 01-Apr-18 A 26-Apr-18 A
A1450-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 24-May-18 A 11-Aug-18 A
TEST SEPERAT
SEPERATOR PLATFORM 0 0 09-Feb-18 A 11-Aug-18 A
A1445-1 EXCAVATION FOR THE MAIN FOUNDATIONS 0 100% 0 09-Feb-18 A 29-Mar-18 A
A1450-3 FOUNDATION WORK (STEEL FIXING) 0 100% 0 01-Apr-18 A 16-Jul-18 A
A1450-4 FOUNDATION WORK (CONCRETE) 0 100% 0 01-Apr-18 A 26-Jul-18 A
A1450-5 CURING / WATERPROOFING / BACK FILLING 0 100% 0 27-May-18 A 11-Aug-18 A
METERING SKID
SK 25-Dec-17 01-Jan-18 7 0 06-Mar-18 A 11-Aug-18 A
A1490 FOUNDATION WORK (STEEL FIXING) 25-Dec-17 01-Jan-18 7 100% 0 01-Apr-18 A 12-Apr-18 A
A1445-2 EXCAVATION 0 100% 0 06-Mar-18 A 29-Mar-18 A
A1490-1 FOUNDATION WORK (CONCRETE) 0 100% 0 01-Apr-18 A 26-Apr-18 A
A1490-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 28-May-18 A 11-Aug-18 A

Page 29 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 17 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
PIPE SUPPORT 29-Nov-17 24-Dec-17 21 0 10-Dec-17 A 23-Aug-18 A
A1470 FOUNDATION WORK (STEEL FIXING) 29-Nov-17 24-Dec-17 21 100% 0 10-Dec-17 A 18-Aug-18 A
A1445-3 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 100% 0 22-Mar-18 A 06-Aug-18 A
A1470-1 FOUNDATION WORK (CONCRETE) 0 100% 0 10-Dec-17 A 18-Aug-18 A
A1470-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 10-Dec-17 A 23-Aug-18 A
PSV 0 0 24-Mar-18 A 11-Aug-18 A
A1445-4 EXCAVATION (INCLUDING AREA LIGHTING POLES) 0 100% 0 24-Mar-18 A 05-Jul-18 A
A1490-3 FOUNDATION WORK (STEEL FIXING) 0 100% 0 15-Apr-18 A 08-Aug-18 A
A1490-5 FOUNDATION WORK (CONCRETE) 0 100% 0 22-Apr-18 A 08-Aug-18 A
A1490-6 CURING / WATERPROOFING / BACK FILLING 0 100% 0 04-Jun-18 A 11-Aug-18 A
Structural Steel 16-Jul-18 04-Aug-18 17 47 02-Oct-18 A 18-Dec-18 12
TEST SEPERATOR
SEPERAT 16-Jul-18 04-Aug-18 17 34 02-Oct-18 A 03-Dec-18 15
A2360 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PL 16-Jul-18 23-Jul-18 7 15% 34 02-Oct-18 A 03-Dec-18 3
A2400 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 01-Aug-18 04-Aug-18 3 0% 17 14-Nov-18 03-Dec-18 15
METERING SKID
SK 0 37 04-Oct-18 A 06-Dec-18 3
A2360-1 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK W 0 15% 37 04-Oct-18 A 06-Dec-18 3
PSV 23-Jul-18 28-Jul-18 5 37 10-Oct-18 A 06-Dec-18 22
A2380 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 23-Jul-18 28-Jul-18 5 0% 37 10-Oct-18 A 06-Dec-18 22
PIPE SUPPORT 19-Jul-18 24-Jul-18 5 47 11-Oct-18 A 18-Dec-18 0
A2370 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS 19-Jul-18 24-Jul-18 5 0% 47 11-Oct-18 A 18-Dec-18 0
FIELD INSTRUMENT
INSTRUM 0 4 15-Dec-18 18-Dec-18 3
A2370-1 INSTALLATION OF INSTRUMENT STANCHION 0 0% 4 15-Dec-18 18-Dec-18 3
Mechanical 28-Jun-18 15-Jul-18 15 0 05-Sep-18 A 06-Sep-18 A
A2775 INSTALLATION OF NEW TEST SEPARATOR 28-Jun-18 15-Jul-18 15 100% 0 05-Sep-18 A 06-Sep-18 A
Piping 07-Jul-18 21-Aug-18 40 24 31-Dec-17 A 06-Jan-19 20
EARLY SHUTDOWN
SHUTDO WORKS - Pre Shutdown and Plant Shutdown Tie-in 0 0 31-Dec-17 A 17-Feb-18 A
A5550 MOBILIZATION OF OF TEAM APPLY PTW 0 100% 0 31-Dec-17 A 31-Dec-17 A
A5560 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 100% 0 31-Dec-17 A 05-Jan-18 A
A5570 PIPING TIE-IN / NDT 0 100% 0 09-Feb-18 A 14-Feb-18 A
A5580 TIE-IN COMPLETE / REMOVE SCAFFOLD 0 100% 0 06-Feb-18 A 17-Feb-18 A
PIPING -REMAINING
-REMA 07-Jul-18 21-Aug-18 40 24 10-Dec-18 06-Jan-19 5
A2920 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 07-Jul-18 09-Aug-18 30 0% 17 10-Dec-18 29-Dec-18 0
A2940 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 11-Aug-18 13-Aug-18 3 0% 7 26-Dec-18 02-Jan-19 8
A2930 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 14-Aug-18 19-Aug-18 5 0% 4 02-Jan-19 06-Jan-19 0
A2950 TIE-IN 14-Aug-18 21-Aug-18 7 0% 4 02-Jan-19 06-Jan-19 0
A2920-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 8 19-Dec-18 27-Dec-18 0
A2951-1 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 03-Jan-19 06-Jan-19 4
Electrical 30-Jun-18 08-Sep-18 61 68 25-Aug-18 A 12-Jan-19 3
A3270 CABLE GLANDING AND TERMINATION 30-Jun-18 15-Jul-18 14 0% 12 18-Dec-18 31-Dec-18 6
A3280 U/G CABLE LAYING 16-Jul-18 23-Jul-18 7 0% 13 06-Dec-18 20-Dec-18 3
A3290 CABLE TRAY INSTALLATION 24-Jul-18 08-Aug-18 14 0% 8 06-Dec-18 15-Dec-18 3
A3300 ELECTRICAL EQUIPMENTS INSTALLATION 09-Aug-18 16-Aug-18 7 0% 12 18-Dec-18 31-Dec-18 3
A3310 CABLE LAYING 18-Aug-18 25-Aug-18 7 0% 17 09-Dec-18 27-Dec-18 3
A3320 LIGHTING FIXTURE AND DB INSTALLATION 18-Aug-18 25-Aug-18 7 0% 6 25-Dec-18 31-Dec-18 3
A3330 ELECTRICAL TIE-INS 26-Aug-18 02-Sep-18 7 0% 5 05-Jan-19 09-Jan-19 3
A3340 ENERGIZATION 03-Sep-18 08-Sep-18 5 0% 3 09-Jan-19 12-Jan-19 3
A3280-2 BACK FILLING OF CABLE TRENCH 0 0% 13 09-Dec-18 23-Dec-18 17
A3310-1 HOOK UP 0 0% 5 31-Dec-18 05-Jan-19 3
A5990 CABLE TRENCHES 0 25% 24 25-Aug-18 A 21-Nov-18 9
A6000 EARTH PIT DRILLING 0 0% 4 13-Nov-18 17-Nov-18 5
Instrument & Control
Co 28-Jul-18 18-Dec-18 124 40 22-Nov-18 07-Jan-19 7
A3950 CABLE TRAY AND SUPPORTS INSTALLATION 28-Jul-18 12-Aug-18 14 0% 18 22-Nov-18 12-Dec-18 3
A3960 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TESTING 13-Aug-18 20-Aug-18 7 0% 4 02-Jan-19 06-Jan-19 3
A3990 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 14-Aug-18 20-Aug-18 6 0% 9 29-Dec-18 07-Jan-19 3
A3970 INSTRUMENT EQUIPEMNT INSTALLATION (RO, SDV, PRV & CONTROL VALV 21-Aug-18 28-Aug-18 7 0% 7 26-Dec-18 02-Jan-19 3
A3980 INSTRUMENT CABLE LAYING 29-Aug-18 03-Sep-18 5 0% 18 11-Dec-18 31-Dec-18 3
A4860 INSTALLATION OF DELUGE 04-Sep-18 11-Sep-18 7 0% 4 01-Jan-19 05-Jan-19 9

Page 30 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 18 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A4870 JB INSTALLATION 27-Sep-18 30-Sep-18 3 0% 3 11-Dec-18 13-Dec-18 3
A4790 JB SUPPORT INSTALLATION 16-Dec-18 18-Dec-18 3 0% 3 09-Dec-18 11-Dec-18 3
A3980-2 SS TUBE AND LEAK TEST 0 0% 4 30-Dec-18 02-Jan-19 6
A3970-3 INSTALLATION OF INSTRUMENT VALVE 0 0% 3 26-Dec-18 29-Dec-18 6
A3970-1 FIELD INSTRUMENT INSTALLATION (GAUGES / TRANSMITTERS) 0 0% 6 24-Dec-18 30-Dec-18 3
A3970-2 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 3 29-Dec-18 31-Dec-18 4
A3970-11 CABLE GLAND AND TERMINATION (ALONG JBs) 0 0% 4 25-Dec-18 29-Dec-18 3
A3970-21 CABLE GLAND AND TERMINTATION (ALONG INSTRUMENTS) 0 0% 5 27-Dec-18 01-Jan-19 3
F&G System 0 26 09-Dec-18 07-Jan-19 3
A6030 F&G CABLE INSTALLATION 0 0% 9 11-Dec-18 20-Dec-18 18
A6010 F&G SUPPORTS INSTALLATION 0 0% 4 09-Dec-18 12-Dec-18 23
A6020 F&G DEVICES INSTALLATION 0 0% 4 11-Dec-18 15-Dec-18 23
A6040 F&G JB SUPPORT INSTALLATION 0 0% 3 11-Dec-18 13-Dec-18 23
A6050 F&G JB INSTALLATION 0 0% 3 12-Dec-18 15-Dec-18 23
A6060 F&G CABLE GLANDING AND TERMINATION 0 0% 5 27-Dec-18 01-Jan-19 3
A6070 F&G LOOP PREPARATION 0 0% 2 01-Jan-19 02-Jan-19 3
A6080 F&G LOOP TESTING 0 0% 4 03-Jan-19 07-Jan-19 3
Painting & Fireproofing
Firep 24-Jul-18 21-Aug-18 25 20 15-Dec-18 06-Jan-19 11
A4300 STRUCTURAL STEEL PAINTING AND TOUCH-UP 24-Jul-18 31-Jul-18 7 0% 9 15-Dec-18 24-Dec-18 19
A4320 FIREPROOFING FOR STRUCTURAL STEEL 01-Aug-18 08-Aug-18 7 0% 12 15-Dec-18 27-Dec-18 19
A4310 PIPING PAINTING AND TOUCH-UP 14-Aug-18 21-Aug-18 7 0% 8 29-Dec-18 06-Jan-19 8
Pre-commisionin
Pre-commisioning 14-Aug-18 16-Oct-18 55 75 09-Sep-18 A 20-Jan-19 0
A2951 INST LOOP AND FUNCTIONAL TEST 14-Aug-18 16-Aug-18 3 0% 4 02-Jan-19 06-Jan-19 3
A4560 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 23-Sep-18 30-Sep-18 7 17% 58 09-Sep-18 A 31-Dec-18 4
A4600 ELECTRICAL LIGHTING TEST 23-Sep-18 16-Oct-18 21 0% 5 06-Jan-19 10-Jan-19 0
A4570 LEAK TEST FOR PIPING AND SEPARATOR 30-Sep-18 02-Oct-18 3 0% 4 12-Jan-19 15-Jan-19 0
A4580 PUNCHLIST 03-Oct-18 06-Oct-18 3 0% 4 16-Jan-19 20-Jan-19 0
A4570-1 DELUGE SKID FUNCTIONAL TESTING 0 0% 3 09-Jan-19 12-Jan-19 0
Commissioning 17-Oct-18 30-Oct-18 11 9 20-Jan-19 29-Jan-19 0
A4950 START OF PRODUCTION 17-Oct-18 20-Oct-18 3 0% 1 20-Jan-19 20-Jan-19 0
A4960 COMMISSIONING AND STARTUP 22-Oct-18 24-Oct-18 3 0% 5 20-Jan-19 24-Jan-19 0
A4970 PERFORMANCE TESTS 24-Oct-18 30-Oct-18 7 0% 5 24-Jan-19 29-Jan-19 0
Demolition Works
Work 02-Oct-18 22-Oct-18 17 41 26-Jan-19 13-Mar-19 59
D0000 WORK PERMIT APPROVED FOR DEMOLITION 02-Oct-18 04-Oct-18 3 0% 4 26-Jan-19 29-Jan-19 59
D0010 DEPRESSURIZATION / ISOLATION (PIPING & INSTRUMENTATION) 06-Oct-18 07-Oct-18 2 0% 2 29-Jan-19 30-Jan-19 59
D0030 APPLY ANTI RUST TO FOUNDATION BOTLS 08-Oct-18 09-Oct-18 1 0% 3 30-Jan-19 02-Feb-19 59
D0020 COLD CUTTING INLET AND OUTLET PIPING 09-Oct-18 13-Oct-18 3 0% 21 02-Feb-19 25-Feb-19 59
D0040 UNBOLD & REMOVE EXISTING SEPARATOR 13-Oct-18 16-Oct-18 3 0% 3 25-Feb-19 27-Feb-19 59
D0050 REMOVE CONCRETE FOUNDATION / GRADE THE AREA 16-Oct-18 22-Oct-18 5 0% 12 28-Feb-19 13-Mar-19 59
D0060 DEMOLITION WORKS COMPLETE 22-Oct-18 0 0% 0 13-Mar-19 59
KAHM 29-Nov-17 08-Nov-18 294 117 03-Dec-17 A 10-Mar-19 62
FABRICATION 26-Dec-17 08-Feb-18 39 44 07-Jun-18 A 15-Dec-18 14
Structural Steel Fabrication 30-Dec-17 23-Jan-18 22 23 07-Jun-18 A 20-Nov-18 22
TEST SEPERATOR
SEPERAT 30-Dec-17 11-Jan-18 12 23 06-Sep-18 A 20-Nov-18 0
F0010 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CR 30-Dec-17 11-Jan-18 12 98% 23 06-Sep-18 A 20-Nov-18 0
METERING SKID
SK 20-Jan-18 23-Jan-18 4 0 08-Aug-18 A 15-Oct-18 A
F0040 FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS TRANSFER 20-Jan-18 23-Jan-18 4 100% 0 08-Aug-18 A 15-Oct-18 A
PSV 16-Jan-18 18-Jan-18 3 0 09-Aug-18 A 23-Oct-18 A
F0030 FAB. OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTURE TRANSFE 16-Jan-18 18-Jan-18 3 100% 0 09-Aug-18 A 23-Oct-18 A
PIPE SUPPORT 13-Jan-18 15-Jan-18 3 16 07-Jun-18 A 12-Nov-18 29
F0020 FAB. OF PIPESUPPORT STRUCTURE SHIFT TO SITE 13-Jan-18 15-Jan-18 3 99% 16 07-Jun-18 A 12-Nov-18 29
F0020-1 FABRICATION OF INSTRUMENT STANCHION SUPPORTS 0 100% 0 13-Aug-18 A 03-Sep-18 A
Piping Fabrication
Fabricati 26-Dec-17 08-Feb-18 39 44 27-Sep-18 A 15-Dec-18 14
FBE PIPING (AT KUWAIT) 26-Dec-17 08-Feb-18 39 44 27-Sep-18 A 15-Dec-18 14
F0080 PIPING FABRICATION & FBE COATING AT KUWAIT 26-Dec-17 24-Jan-18 26 0% 40 08-Oct-18 A 10-Dec-18 14
F0110 FBE PIPING BULK DELIVER AT SITE 23-Jan-18 08-Feb-18 15 0% 9 05-Dec-18 15-Dec-18 14
F0080-00 PIPE DELIVER AT KUWAIT 0 100% 0 27-Sep-18 A

Page 31 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 19 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
REMANING PIPING
PIP (NON FBE) 0 42 27-Sep-18 A 12-Dec-18 8
F0080-000 PIPE DELIVER AT FAB FACILITY 0 100% 0 27-Sep-18 A
F0080-1 COMPLETE PIPING FABRICATION INCL. HYDROTEST/ PAINTING & COATIN 0 0% 38 24-Oct-18 A 08-Dec-18 8
F0110-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 13 28-Nov-18 12-Dec-18 8
INSTALLATION 29-Nov-17 01-Nov-18 289 70 03-Dec-17 A 14-Jan-19 20
Civil Works 29-Nov-17 01-Nov-18 289 70 03-Dec-17 A 14-Jan-19 6
COMMOMN 29-Nov-17 01-Nov-18 289 70 17-Feb-18 A 14-Jan-19 6
A1580 GRADING 29-Nov-17 04-Dec-17 5 100% 0 17-Feb-18 A 02-Apr-18 A
A1650 CABLE TRENCHES AND UTILITY ROAD CROSSINGS 08-Feb-18 05-Mar-18 21 10% 24 25-Sep-18 A 21-Nov-18 7
A1700 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPL 05-Mar-18 08-Mar-18 3 95% 10 04-Aug-18 A 05-Nov-18 7
A1660 DRAINAGE PIPE CULVERTS 01-Oct-18 16-Oct-18 14 0% 36 16-Oct-18 A 05-Dec-18 30
A1670 ROAD SAFETY CRASH BARRIERS AND BOLLARD 01-Oct-18 24-Oct-18 21 0% 9 05-Jan-19 14-Jan-19 6
A1690 PAVING&GRADING(GRAVEL FILL) 14-Oct-18 16-Oct-18 3 0% 9 05-Jan-19 14-Jan-19 6
A1640 ROADS AND PAVING(INCLUDING MODIFICATIONS) 17-Oct-18 01-Nov-18 14 0% 10 03-Jan-19 14-Jan-19 6
A1580-1 PROTECTION OF UNDERGROUND CABLES 0 50% 24 23-Sep-18 A 21-Nov-18 7
TEST SEPERATOR
SEPERAT 29-Nov-17 09-Jan-18 35 0 17-Feb-18 A 18-Aug-18 A
A1585 EXCAVATION FOR THE MAIN FOUNDATIONS 29-Nov-17 06-Dec-17 7 100% 0 17-Feb-18 A 02-Apr-18 A
A1590 FOUNDATION WORK (STEEL FIXING) 07-Dec-17 09-Jan-18 28 100% 0 19-May-18 A 18-Jul-18 A
A1590-1 FOUNDATION WORK (CONCRETE) 0 100% 0 01-Apr-18 A 04-Aug-18 A
A1590-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 09-Jul-18 A 18-Aug-18 A
TEST SEPERAT
SEPERATOR PLATFORM 0 0 17-Feb-18 A 20-Sep-18 A
A1590-3 FOUNDATION WORK (STEEL FIXING) 0 100% 0 19-May-18 A 18-Jul-18 A
A1590-4 FOUNDATION WORK (CONCRETE) 0 100% 0 01-Apr-18 A 04-Aug-18 A
A1590-5 CURING / WATERPROOFING / BACK FILLING 0 100% 0 09-Jul-18 A 20-Sep-18 A
A1585-1 EXCAVATION FOR THE MAIN FOUNDATIONS 0 100% 0 17-Feb-18 A 02-Apr-18 A
METERING SKID
SK 04-Feb-18 11-Feb-18 7 0 03-Mar-18 A 18-Sep-18 A
A1630 FOUNDATION WORK (STEEL FIXING) 04-Feb-18 11-Feb-18 7 100% 0 19-May-18 A 18-Jul-18 A
A1585-2 EXCAVATION 0 100% 0 03-Mar-18 A 01-Apr-18 A
A1630-1 FOUNDATION WORK (CONCRETE) 0 100% 0 01-Apr-18 A 02-Aug-18 A
A1630-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 01-Jul-18 A 18-Sep-18 A
PIPE SUPPORT 10-Jan-18 03-Feb-18 21 0 03-Dec-17 A 29-Aug-18 A
A1610 FOUNDATION WORK (STEEL FIXING) 10-Jan-18 03-Feb-18 21 100% 0 16-Dec-17 A 25-Aug-18 A
A1610-1 FOUNDATION WORK (CONCRETE) 0 100% 0 16-Dec-17 A 27-Aug-18 A
A1610-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 16-Dec-17 A 29-Aug-18 A
A1585-3 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 100% 0 03-Dec-17 A 18-Jul-18 A
PSV 0 0 17-Feb-18 A 13-Sep-18 A
A1630-3 FOUNDATION WORK (STEEL FIXING) 0 100% 0 20-May-18 A 25-Aug-18 A
A1630-4 FOUNDATION WORK (CONCRETE) 0 100% 0 20-May-18 A 26-Aug-18 A
A1630-5 CURING / WATERPROOFING / BACK FILLING 0 100% 0 02-Jul-18 A 13-Sep-18 A
A1585-4 EXCAVATION (INCLUDING AREA LIGHTING POLES) 0 100% 0 17-Feb-18 A 21-Jun-18 A
Structural Steel 02-Aug-18 21-Aug-18 17 32 04-Oct-18 A 01-Dec-18 21
TEST SEPERATOR
SEPERAT 02-Aug-18 21-Aug-18 17 31 14-Oct-18 A 29-Nov-18 22
A2420 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PL 02-Aug-18 09-Aug-18 7 15% 31 14-Oct-18 A 29-Nov-18 22
A2460 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 19-Aug-18 21-Aug-18 3 0% 9 20-Nov-18 29-Nov-18 0
METERING SKID
SK 06-Aug-18 11-Aug-18 5 10 04-Oct-18 A 12-Nov-18 19
A2430 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK W 06-Aug-18 11-Aug-18 5 10% 10 04-Oct-18 A 12-Nov-18 19
PSV 09-Aug-18 14-Aug-18 5 8 08-Nov-18 17-Nov-18 13
A2440 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 09-Aug-18 14-Aug-18 5 0% 8 08-Nov-18 17-Nov-18 13
PIPE SUPPORT 15-Aug-18 18-Aug-18 3 16 13-Nov-18 01-Dec-18 13
A2450 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS 15-Aug-18 18-Aug-18 3 0% 16 13-Nov-18 01-Dec-18 13
FIELD INSTRUMENT
INSTRUM 0 6 25-Nov-18 01-Dec-18 13
A2450-1 INSTALLATION OF INSTRUMENT STANCHION 0 0% 6 25-Nov-18 01-Dec-18 13
Mechanical 16-Jul-18 01-Aug-18 15 0 16-Oct-18 A 18-Oct-18 A
A2795 INSTALLATION OF NEW TEST SEPARATOR 16-Jul-18 01-Aug-18 15 100% 0 16-Oct-18 A 18-Oct-18 A
Piping 02-Aug-18 17-Sep-18 40 27 31-Dec-17 A 30-Dec-18 24
EARLY SHUTDOWN
SHUTDO WORKS - Pre Shutdown and Plant Shutdown Tie-in 0 0 31-Dec-17 A 17-Feb-18 A
A5590 MOBILIZATION OF OF TEAM APPLY PTW 0 100% 0 31-Dec-17 A 31-Dec-17 A
A5600 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 100% 0 31-Dec-17 A 05-Jan-18 A

Page 32 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 20 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A5610 PIPING TIE-IN / NDT 0 100% 0 09-Feb-18 A 14-Feb-18 A
A5620 TIE-IN COMPLETE / REMOVE SCAFFOLD 0 100% 0 06-Feb-18 A 17-Feb-18 A
PIPING -REMAINING
-REMA 02-Aug-18 17-Sep-18 40 27 29-Nov-18 30-Dec-18 13
A2980 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 02-Aug-18 08-Aug-18 6 0% 4 26-Dec-18 30-Dec-18 8
A2970 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 11-Aug-18 02-Sep-18 20 0% 20 29-Nov-18 22-Dec-18 8
A2990 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 03-Sep-18 05-Sep-18 3 0% 9 17-Dec-18 26-Dec-18 8
A3000 TIE-IN 06-Sep-18 17-Sep-18 10 0% 4 26-Dec-18 30-Dec-18 8
A2970-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 11-Dec-18 20-Dec-18 21
A3001-1 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 27-Dec-18 30-Dec-18 9
Electrical 15-Jan-18 25-Sep-18 218 47 17-Nov-18 09-Jan-19 2
A3360 CABLE GLANDING AND TERMINATION 15-Jan-18 31-Jan-18 14 0% 12 15-Dec-18 27-Dec-18 6
A3370 U/G CABLE LAYING 31-Jan-18 08-Feb-18 7 0% 14 28-Nov-18 13-Dec-18 2
A3380 CABLE TRAY INSTALLATION 11-Aug-18 26-Aug-18 14 0% 9 25-Nov-18 04-Dec-18 0
A3390 ELECTRICAL EQUIPMENTS INSTALLATION 27-Aug-18 03-Sep-18 7 0% 12 15-Dec-18 27-Dec-18 2
A3400 CABLE LAYING 04-Sep-18 11-Sep-18 7 0% 15 10-Dec-18 26-Dec-18 2
A3410 LIGHTING FIXTURES AND DB INSTALLATION 04-Sep-18 11-Sep-18 7 0% 6 22-Dec-18 27-Dec-18 2
A3420 ELECTRICAL TIE-INS 12-Sep-18 19-Sep-18 7 0% 4 02-Jan-19 06-Jan-19 2
A3430 ENERGIZATION 20-Sep-18 25-Sep-18 5 0% 3 07-Jan-19 09-Jan-19 2
A3370-1 BACK FILLING OF CABLE TRENCH 0 0% 12 15-Dec-18 27-Dec-18 10
A3400-1 HOOK UP 0 0% 4 29-Dec-18 01-Jan-19 2
A3440 EARTH PIT DRILLING 0 0% 4 17-Nov-18 20-Nov-18 5
Instrument & Control
Co 02-Aug-18 09-Oct-18 59 40 26-Nov-18 10-Jan-19 3
A4040 MODIFICATION OF EXISTING DCS SYSTEMS BY VENDOR 02-Aug-18 15-Aug-18 12 0% 9 23-Dec-18 01-Jan-19 4
A4000 CABLE TRAY AND SUPPORT INSTALLATION 14-Aug-18 29-Aug-18 14 0% 16 26-Nov-18 13-Dec-18 0
A4010 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TESTING 30-Aug-18 06-Sep-18 7 0% 4 07-Jan-19 10-Jan-19 0
A4020 INSTRUMENT EQUIPEMNT INSTALLATION (RO, SDV, PRV AND CONTROL VA 08-Sep-18 15-Sep-18 7 0% 7 25-Dec-18 01-Jan-19 0
A4030 INSTRUMENT CABLE LAYING 16-Sep-18 20-Sep-18 5 0% 18 05-Dec-18 25-Dec-18 0
A5280 INSTALLATION OF DELUGE 22-Sep-18 29-Sep-18 7 0% 6 01-Jan-19 07-Jan-19 6
A4590 JB SUPPORT INSTALLATION 07-Oct-18 09-Oct-18 3 0% 3 11-Dec-18 13-Dec-18 23
A4030-1 SS TUBE INSTALLATION AND LEAK TEST 0 0% 4 02-Jan-19 06-Jan-19 0
A4020-3 INSTALLATION OF INSTRUMENT VALVE 0 0% 4 01-Jan-19 05-Jan-19 1
A4020-1 FIELD INSTRUMENT INSTALLATION (GAUGES & TRANSMITTERS) 0 0% 7 25-Dec-18 01-Jan-19 0
A4020-2 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 3 30-Dec-18 01-Jan-19 4
A5350 JB INSTALLATION 0 0% 3 15-Dec-18 17-Dec-18 23
A4020-11 CABLE GLAND TERMINATION (ALONG INSRUMENT) 0 0% 6 30-Dec-18 05-Jan-19 3
A4020-21 CABLE GLAND TERMINATION (ALONG JBs) 0 0% 7 30-Dec-18 06-Jan-19 0
F&G System 0 28 10-Dec-18 10-Jan-19 3
A6100 F&G SUPPORT INSTALLATION 0 0% 4 10-Dec-18 13-Dec-18 25
A6110 F&G DEVICES INSTALLATION 0 0% 4 12-Dec-18 16-Dec-18 25
A6120 F&G CABLE INSTALLATION 0 0% 9 16-Dec-18 25-Dec-18 17
A6130 F&G JB SUPPORT INSTALLATION 0 0% 2 15-Dec-18 16-Dec-18 25
A6140 F&G JB INSTALLATION 0 0% 2 17-Dec-18 18-Dec-18 23
A6150 F&G CABLE GLANDING AND TERMINATION 0 0% 5 31-Dec-18 05-Jan-19 3
A6160 F&G LOOP PREPARATION 0 0% 2 05-Jan-19 06-Jan-19 3
A6170 F&G LOOP TESTING 0 0% 4 07-Jan-19 10-Jan-19 3
Painting & Fireproofing
Firep 11-Aug-18 13-Sep-18 30 27 28-Nov-18 29-Dec-18 34
A4330 STRUCTURAL STEEL PAINTING AND TOUCH-UP 11-Aug-18 18-Aug-18 7 0% 9 28-Nov-18 08-Dec-18 41
A4350 FIREPROOFING FOR STRUCTURAL STEEL 19-Aug-18 26-Aug-18 7 0% 17 02-Dec-18 20-Dec-18 41
A4340 PIPING PAINTING AND TOUCH-UP 06-Sep-18 13-Sep-18 7 0% 7 22-Dec-18 29-Dec-18 17
Pre-commisionin
Pre-commisioning 22-Aug-18 27-Sep-18 32 74 09-Sep-18 A 19-Jan-19 0
A4510 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 22-Aug-18 29-Aug-18 7 17% 58 09-Sep-18 A 31-Dec-18 6
A3001 INST LOOP AND FUNCITONAL TEST 06-Sep-18 09-Sep-18 3 0% 4 07-Jan-19 10-Jan-19 0
A4520 DELUGE SKID FUNCTIONAL TEST 12-Sep-18 15-Sep-18 3 0% 3 12-Jan-19 14-Jan-19 0
A4550 ELECTRICAL LIGHITING TEST 12-Sep-18 27-Sep-18 14 0% 5 09-Jan-19 14-Jan-19 0
A4530 PUNCHLIST 16-Sep-18 18-Sep-18 3 0% 4 15-Jan-19 19-Jan-19 0
A4520-1 LEAK TEST FOR SEPARATOR AND PIPING 0 0% 5 10-Jan-19 15-Jan-19 0
Commissioning 29-Sep-18 08-Oct-18 8 8 19-Jan-19 27-Jan-19 0

Page 33 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 21 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A4890 START OF PRODUCTION 29-Sep-18 01-Oct-18 3 0% 2 19-Jan-19 20-Jan-19 0
A4900 COMMISSIONING AND STARTUP 30-Sep-18 02-Oct-18 3 0% 4 19-Jan-19 22-Jan-19 0
A4910 PERFORMANCE TESTS 02-Oct-18 08-Oct-18 7 0% 5 22-Jan-19 27-Jan-19 0
Demolition Works
Work 20-Oct-18 08-Nov-18 17 39 24-Jan-19 10-Mar-19 62
DM1000 WORK PERMIT APPROVED FOR DEMOLITION 20-Oct-18 22-Oct-18 3 0% 3 24-Jan-19 27-Jan-19 62
DM1010 DEPRESSURIZATION / ISOLATION (PIPING & INSTRUMENTATION) 23-Oct-18 24-Oct-18 2 0% 3 27-Jan-19 29-Jan-19 62
DM1030 APPLY ANTI RUST TO FOUNDATION BOTLS 25-Oct-18 27-Oct-18 1 0% 2 29-Jan-19 30-Jan-19 62
DM1020 COLD CUTTING INLET AND OUTLET PIPING 27-Oct-18 30-Oct-18 3 0% 21 30-Jan-19 23-Feb-19 62
DM1040 UNBOLD & REMOVE EXISTING SEPARATOR 30-Oct-18 03-Nov-18 3 0% 2 23-Feb-19 24-Feb-19 62
DM1050 REMOVE CONCRETE FOUNDATION / GRADE THE AREA 03-Nov-18 08-Nov-18 5 0% 13 24-Feb-19 10-Mar-19 62
DM1060 DEMOLITION WORKS COMPLETE 08-Nov-18 0 0% 0 10-Mar-19 62
JALM 20-Feb-18 28-Nov-18 302 229 05-Jun-18 A 26-May-19 61
FABRICATION 24-Mar-18 14-May-18 45 64 02-Sep-18 A 09-Jan-19 44
Structural Steel Fabrication 24-Mar-18 17-Apr-18 22 56 02-Sep-18 A 31-Dec-18 52
TEST SEPERATOR
SEPERAT 24-Mar-18 05-Apr-18 12 48 11-Sep-18 A 22-Dec-18 0
F330 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CR 24-Mar-18 05-Apr-18 12 40% 48 11-Sep-18 A 22-Dec-18 0
METERING SKID
SK 07-Apr-18 09-Apr-18 3 48 11-Sep-18 A 22-Dec-18 0
F340 FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS. TRANSFER 07-Apr-18 09-Apr-18 3 80% 48 11-Sep-18 A 22-Dec-18 0
PSV 10-Apr-18 12-Apr-18 3 48 12-Sep-18 A 22-Dec-18 0
F350 FAB. OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTURE TRANSFE 10-Apr-18 12-Apr-18 3 20% 48 12-Sep-18 A 22-Dec-18 0
PIPE SUPPORT 10-Apr-18 17-Apr-18 7 56 02-Sep-18 A 31-Dec-18 52
F370 FABRICATION OF INSTRUMENT STANCHION SUPPORTS 10-Apr-18 17-Apr-18 7 100% 0 02-Sep-18 A 16-Sep-18 A
F360 FAB. OF PIPESUPPORT STRUCTURE TRANSFER TO SITE FOR INSTALLATI 14-Apr-18 17-Apr-18 4 30% 56 20-Sep-18 A 31-Dec-18 52
Piping Fabrication
Fabricati 31-Mar-18 14-May-18 39 45 27-Sep-18 A 09-Jan-19 0
FBE PIPING (AT KUWAIT) 31-Mar-18 14-May-18 39 38 27-Sep-18 A 01-Jan-19 0
F400 PIPING FABRICATION & FBE COATING AT KUWAIT 31-Mar-18 30-Apr-18 27 0% 29 11-Oct-18 A 22-Dec-18 0
F430 FBE PIPING BULK DELIVER AT SITE 28-Apr-18 14-May-18 15 0% 9 23-Dec-18 01-Jan-19 0
F400-00 PIPE DELIVER AT KUWAIT 0 100% 0 27-Sep-18 A
REMAINING PIPING
PI (NON FBE0 0 37 06-Oct-18 A 09-Jan-19 0
F400-1 COMPLETE PIPING FABRICATION HYDROTEST/ PAINTING & COATING 0 0% 33 28-Nov-18 05-Jan-19 0
F430-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 13 26-Dec-18 09-Jan-19 0
F400-000 PIPE DELIVER AT FAB FACILITY 0 100% 0 06-Oct-18 A
INSTALLATION 20-Feb-18 26-Nov-18 300 169 05-Jun-18 A 31-Mar-19 15
Civil Works 20-Feb-18 26-Nov-18 240 135 05-Jun-18 A 31-Mar-19 12
COMMOMN 20-Feb-18 26-Nov-18 240 135 05-Jun-18 A 31-Mar-19 12
A1840 GRADING 20-Feb-18 25-Feb-18 5 100% 0 05-Jun-18 A 12-Jun-18 A
A1910 CABLE TRENCHES AND UTILITY ROAD CROSSINGS 03-Apr-18 26-Apr-18 21 0% 51 18-Oct-18 A 23-Dec-18 17
A1920 DRAINAGE PIPE CULVERTS 03-Nov-18 18-Nov-18 14 0% 11 09-Dec-18 20-Dec-18 80
A1930 ROAD SAFETY CRASH BARRIERS AND BOLLARD 03-Nov-18 26-Nov-18 21 0% 13 17-Mar-19 31-Mar-19 12
A1935 NEW RETAINING WALLS 05-Nov-18 12-Nov-18 7 0% 14 13-Mar-19 28-Mar-19 10
A1936 RE-INSTATEMENT OF EXISTING ASPHALT ROAD 13-Nov-18 20-Nov-18 7 0% 14 13-Mar-19 28-Mar-19 10
A1938 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) 21-Nov-18 24-Nov-18 3 0% 13 17-Mar-19 31-Mar-19 12
A1937 CONCRETE KERB 21-Nov-18 24-Nov-18 3 0% 14 13-Mar-19 28-Mar-19 10
A1840-1 PROTECTION OF UNDERGROUND CABLES 0 0% 5 04-Dec-18 09-Dec-18 27
A1845-6 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPL 0 70% 24 23-Aug-18 A 21-Nov-18 5
TEST SEPERATOR
SEPERAT 26-Feb-18 07-Apr-18 35 0 12-Jun-18 A 08-Oct-18 A
A1845 EXCAVATION FOR THE MAIN FOUNDATIONS 26-Feb-18 05-Mar-18 7 100% 0 12-Jun-18 A 09-Aug-18 A
A1850 FOUNDATION WORK (STEEL FIXING) 06-Mar-18 07-Apr-18 28 100% 0 10-Jul-18 A 19-Aug-18 A
A1850-1 FOUNDATION WORK (CONCRETE) 0 100% 0 13-Aug-18 A 23-Aug-18 A
A1850-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 26-Aug-18 A 08-Oct-18 A
TEST SEPERAT
SEPERATOR PLATFORM 0 0 27-Jul-18 A 25-Sep-18 A
A1845-1 EXCAVATION FOR THE MAIN FOUNDATIONS 0 100% 0 27-Jul-18 A 11-Aug-18 A
A1850-3 FOUNDATION WORK (STEEL FIXING) 0 100% 0 12-Aug-18 A 03-Sep-18 A
A1850-4 FOUNDATION WORK (CONCRETE) 0 100% 0 03-Sep-18 A 22-Sep-18 A
A1850-5 CURING / WATERPROOFING / BACK FILLING 0 100% 0 11-Sep-18 A 25-Sep-18 A
METERING SKID
SK 19-Apr-18 26-Apr-18 7 0 12-Jun-18 A 27-Sep-18 A
A1890 FOUNDATION WORK (STEEL FIXING) 19-Apr-18 26-Apr-18 7 100% 0 03-Jul-18 A 31-Jul-18 A
A1890-1 FOUNDATION WORK (CONCRETE) 0 100% 0 09-Jul-18 A 05-Aug-18 A

Page 34 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 22 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A1845-2 EXCAVATION / Blinidng 0 100% 0 12-Jun-18 A 05-Jul-18 A
A1890-3 CURING / WATERPROOFING / BACK FILLING 0 100% 0 08-Aug-18 A 27-Sep-18 A
PIPE SUPPORT 0 53 09-Jul-18 A 25-Dec-18 0
A1845-3 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 98% 25 03-Aug-18 A 22-Nov-18 0
A1870-1 FOUNDATION WORK (STEEL FIXING) 0 92% 37 09-Jul-18 A 06-Dec-18 0
A1870-2 FOUNDATION WORK (CONCRETE) 0 75% 45 10-Sep-18 A 16-Dec-18 0
A1870-3 CURING / WATERPROOFING / BACK FILLING 0 60% 53 20-Sep-18 A 25-Dec-18 0
PSV 0 0 05-Jun-18 A 03-Oct-18 A
A1845-4 EXCAVATION 0 100% 0 05-Jun-18 A 06-Sep-18 A
A1890-4 FOUNDATION WORK (STEEL FIXING) 0 100% 0 09-Jul-18 A 13-Sep-18 A
A1890-5 FOUNDATION WORK (CONCRETE) 0 100% 0 16-Aug-18 A 16-Sep-18 A
A1890-6 CURING / WATERPROOFING / BACK FILLING 0 100% 0 03-Sep-18 A 03-Oct-18 A
Structural Steel 06-Sep-18 25-Sep-18 17 68 07-Oct-18 A 14-Jan-19 14
TEST SEPERATOR
SEPERAT 06-Sep-18 25-Sep-18 17 64 07-Oct-18 A 09-Jan-19 2
A2540 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PL 06-Sep-18 13-Sep-18 7 0% 64 07-Oct-18 A 09-Jan-19 2
A2580 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 23-Sep-18 25-Sep-18 3 0% 8 01-Jan-19 09-Jan-19 2
METERING SKID
SK 10-Sep-18 15-Sep-18 5 12 01-Jan-19 14-Jan-19 2
A2550 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK W 10-Sep-18 15-Sep-18 5 0% 12 01-Jan-19 14-Jan-19 2
PSV 13-Sep-18 18-Sep-18 5 12 01-Jan-19 14-Jan-19 0
A2560 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 13-Sep-18 18-Sep-18 5 0% 12 01-Jan-19 14-Jan-19 0
PIPE SUPPORT 19-Sep-18 22-Sep-18 3 16 27-Dec-18 14-Jan-19 0
A2570 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS 19-Sep-18 22-Sep-18 3 0% 16 27-Dec-18 14-Jan-19 0
FIELD INSTRUMENT
INSTRUM 0 4 10-Jan-19 14-Jan-19 14
A2570-1 INSTALLATION OF INSTRUMENT STANCHION 0 0% 4 10-Jan-19 14-Jan-19 14
Mechanical 20-Aug-18 05-Sep-18 15 0 10-Sep-18 A 14-Oct-18 A
A2835 INSTALLATION OF NEW TEST SEPARATOR 20-Aug-18 05-Sep-18 15 100% 0 10-Sep-18 A 14-Oct-18 A
Piping 27-Aug-18 08-Oct-18 46 79 01-Jan-19 15-Mar-19 14
PIPING -REMAINING
-REMA 27-Aug-18 27-Sep-18 28 60 01-Jan-19 11-Mar-19 14
A3070 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 27-Aug-18 18-Sep-18 20 0% 32 01-Jan-19 06-Feb-19 0
A3080 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 06-Sep-18 12-Sep-18 6 0% 5 06-Mar-19 11-Mar-19 11
A3090 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 13-Sep-18 16-Sep-18 3 0% 12 07-Feb-19 20-Feb-19 30
A3100 TIE-IN 17-Sep-18 27-Sep-18 10 0% 6 05-Mar-19 11-Mar-19 8
A3070-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 27-Jan-19 05-Feb-19 5
A3101-1 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 09-Mar-19 11-Mar-19 8
HOT TAPPING 18-Sep-18 08-Oct-18 18 17 10-Feb-19 28-Feb-19 1
HT1080 MOBILIZATION OF HOT TAPPING SUB CONTRACTOR 18-Sep-18 20-Sep-18 3 0% 3 10-Feb-19 12-Feb-19 1
HT1090 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 22-Sep-18 02-Oct-18 10 0% 7 12-Feb-19 19-Feb-19 1
HT1100 FLARE TAPPING / NDT 03-Oct-18 06-Oct-18 3 0% 9 19-Feb-19 28-Feb-19 1
HT1110 FLARE TAPPING COMPLETE / REMOVE SCAFFOLD 07-Oct-18 08-Oct-18 2 0% 5 24-Feb-19 28-Feb-19 1
Pre Shutdown and Plant Shutdown Tie-in 0 24 21-Feb-19 15-Mar-19 0
A3100-2 MOBILIZATION OF OF TEAM APPLY PTW 0 0% 2 04-Mar-19 05-Mar-19 0
A3100-3 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 0% 6 05-Mar-19 11-Mar-19 0
A3100-4 PIPING TIE-IN / NDT PRE SHUT DOWN 0 0% 7 21-Feb-19 28-Feb-19 0
A3100-5 PIPING TIE-IN / NDT SHUT DOWN 0 0% 11 05-Mar-19 15-Mar-19 0
Electrical 26-Feb-18 30-Oct-18 212 84 25-Nov-18 02-Mar-19 2
A3540 CABLE GLAND AND TERMINATION 26-Feb-18 13-Mar-18 14 0% 10 05-Feb-19 16-Feb-19 5
A3550 U/G CABLE LAYING 14-Mar-18 21-Mar-18 7 0% 13 12-Jan-19 26-Jan-19 4
A3560 CABLE TRAY INSTALLATION 15-Sep-18 30-Sep-18 14 0% 8 10-Jan-19 19-Jan-19 2
A3570 ELECTRICAL EQUIPMENTS INSTALLATION 01-Oct-18 08-Oct-18 7 0% 12 03-Feb-19 16-Feb-19 2
A3580 CABLE LAYING 09-Oct-18 16-Oct-18 7 0% 20 15-Jan-19 06-Feb-19 2
A3590 LIGHTING FIXTURES AND DB INSTALLATION 09-Oct-18 16-Oct-18 7 0% 6 10-Feb-19 16-Feb-19 2
A3600 ELECTRICAL TIE-INS 17-Oct-18 24-Oct-18 7 0% 6 20-Feb-19 26-Feb-19 2
A3610 ENERGIZATION 25-Oct-18 30-Oct-18 5 0% 4 26-Feb-19 02-Mar-19 2
A3580-1 HOOK UP 0 0% 4 17-Feb-19 20-Feb-19 2
A3550-1 BACK FILLING OF CABLE TRENCH 0 0% 13 26-Jan-19 09-Feb-19 4
A6180 CABLE TRENCHES 0 0% 25 25-Nov-18 23-Dec-18 5
A6190 EARTH PIT DRILLING 0 0% 6 04-Dec-18 10-Dec-18 5
Instrument & Control
Co 06-Sep-18 03-Nov-18 50 55 29-Dec-18 02-Mar-19 0

Page 35 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 23 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A4140 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 06-Sep-18 12-Sep-18 6 0% 5 20-Feb-19 25-Feb-19 4
A4100 CABLE TRAY AND SUPPORTS INSTALLATION 18-Sep-18 03-Oct-18 14 0% 17 29-Dec-18 16-Jan-19 3
A4540 JB SUPPORT INSTALLATION 19-Sep-18 22-Sep-18 3 0% 3 16-Jan-19 19-Jan-19 3
A4880 JB INSTALLATION 28-Sep-18 01-Oct-18 3 0% 3 20-Jan-19 22-Jan-19 3
A4110 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TEST 04-Oct-18 11-Oct-18 7 0% 5 25-Feb-19 02-Mar-19 0
A4120 INSTRUMENT EQUIPEMNT INSTALLATION 13-Oct-18 20-Oct-18 7 0% 20 24-Jan-19 16-Feb-19 4
A4130 INSTRUMENT CABLE LAYING 21-Oct-18 25-Oct-18 5 0% 18 12-Jan-19 31-Jan-19 4
A5310 INSTALLATION OF DELUGE 27-Oct-18 03-Nov-18 7 0% 8 12-Feb-19 20-Feb-19 3
A4130-1 SS TUBE AND LEAK TEST 0 0% 4 21-Feb-19 25-Feb-19 3
A4120-2 INSTALLATION OF INSTRUMENT VALVE 0 0% 5 19-Feb-19 24-Feb-19 0
A4120-1 FIELD INSTRUMENT INSTALLATION (GAUGES / TRANSMITTERS) 0 0% 18 30-Jan-19 19-Feb-19 4
A4120-3 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 2 14-Feb-19 16-Feb-19 7
A4120-11 CABLE GLANDING AND TERMINATION (ALONG JBs) 0 0% 6 31-Jan-19 06-Feb-19 3
A4120-21 CABLE GLANDING AND TERMINATION (ALONG INTSTRUMENTS) 0 0% 6 19-Feb-19 25-Feb-19 4
F&G System 0 43 12-Jan-19 02-Mar-19 16
A6200 F&G SUPPORT INSTALLATION 0 0% 4 13-Jan-19 16-Jan-19 52
A6210 F&G DEVICES INSTALLATION 0 0% 4 15-Jan-19 19-Jan-19 52
A6230 F&G CABLE INSTALLATION 0 0% 9 12-Jan-19 21-Jan-19 50
A6220 F&G JB SUPPORT INSTALLATION 0 0% 2 20-Jan-19 21-Jan-19 50
A6240 F&G JB INSTALLATION 0 0% 2 22-Jan-19 23-Jan-19 48
A6250 F&G CABLE GLANDING AND TERMINATION 0 0% 4 21-Feb-19 25-Feb-19 16
A6260 F&G LOOP PREPARATION 0 0% 2 26-Feb-19 27-Feb-19 16
A6270 F&G LOOP TESTING 0 0% 3 27-Feb-19 02-Mar-19 16
Painting & Fireproofing
Firep 15-Sep-18 30-Sep-18 14 17 06-Feb-19 25-Feb-19 5
A4390 STRUCTURAL STEEL PAINTING AND TOUCH-UP 15-Sep-18 22-Sep-18 7 0% 13 06-Feb-19 20-Feb-19 5
A4400 PIPING PAINTING AND TOUCH-UP 17-Sep-18 24-Sep-18 7 0% 13 06-Feb-19 20-Feb-19 5
A4410 FIREPROOFING FOR STRUCTURAL STEEL 23-Sep-18 30-Sep-18 7 0% 17 06-Feb-19 25-Feb-19 5
Pre-commisionin
Pre-commisioning 17-Sep-18 10-Nov-18 47 130 09-Sep-18 A 25-Mar-19 0
A3101 INST LOOP AND FUNCTIONAL TESTING 17-Sep-18 19-Sep-18 3 0% 3 13-Mar-19 16-Mar-19 0
A4660 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 29-Sep-18 06-Oct-18 7 17% 109 09-Sep-18 A 28-Feb-19 10
A4700 ELECTRICAL LIGHITNG TEST 29-Sep-18 01-Nov-18 30 0% 5 19-Mar-19 24-Mar-19 0
A4670 DELUGE SKID FUNCTIONAL TESTING 02-Oct-18 04-Oct-18 3 0% 5 19-Mar-19 24-Mar-19 0
A4680 LEAK TEST FOR SEPARATOR AND PIPING 04-Nov-18 06-Nov-18 3 0% 3 21-Mar-19 24-Mar-19 0
A4690 PUNCHLIST 07-Nov-18 10-Nov-18 3 0% 4 21-Mar-19 25-Mar-19 0
Commissioning 07-Nov-18 16-Nov-18 8 11 25-Mar-19 06-Apr-19 0
A5070 START OF PRODUCTION 07-Nov-18 3 0% 0 25-Mar-19 0
A5080 COMMISSIONING AND STARTUP 08-Nov-18 10-Nov-18 3 0% 4 26-Mar-19 30-Mar-19 0
A5090 PERFORMANCE TESTS 10-Nov-18 16-Nov-18 7 0% 6 31-Mar-19 06-Apr-19 0
Demolition Works
Work 10-Nov-18 28-Nov-18 16 46 03-Apr-19 26-May-19 49
DM1140 WORK PERMIT APPROVED FOR DEMOLITION 10-Nov-18 12-Nov-18 3 0% 3 03-Apr-19 06-Apr-19 49
DM1150 DEPRESSURIZATION / ISOLATION (PIPING & INSTRUMENTATION) 13-Nov-18 14-Nov-18 2 0% 3 07-Apr-19 09-Apr-19 49
DM1170 APPLY ANTI RUST TO FOUNDATION BOTLS 15-Nov-18 17-Nov-18 1 0% 2 09-Apr-19 10-Apr-19 50
DM1160 COLD CUTTING INLET AND OUTLET PIPING 17-Nov-18 20-Nov-18 3 0% 23 10-Apr-19 06-May-19 49
DM1180 UNBOLD & REMOVE EXISTING SEPARATOR 20-Nov-18 22-Nov-18 2 0% 3 06-May-19 08-May-19 49
DM1190 REMOVE CONCRETE FOUNDATION / GRADE THE AREA 22-Nov-18 28-Nov-18 5 0% 16 08-May-19 26-May-19 49
DM1200 DEMOLITION WORKS COMPLETE 28-Nov-18 0 0% 0 26-May-19 49
FAHS 18-Apr-18 09-Dec-18 202 214 08-Apr-18 A 01-Jul-19 18
FABRICATION 18-Apr-18 14-Jun-18 50 56 03-Sep-18 A 29-Dec-18 29
Structural Steel Fabrication 18-Apr-18 17-May-18 26 56 03-Sep-18 A 29-Dec-18 29
TEST SEPERATOR
SEPERAT 18-Apr-18 03-May-18 14 56 11-Sep-18 A 29-Dec-18 4
F440 COMPLETE FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIR 18-Apr-18 03-May-18 14 50% 56 11-Sep-18 A 29-Dec-18 4
METERING SKID
SK 05-May-18 08-May-18 4 56 09-Sep-18 A 29-Dec-18 4
F450 COMPLETE SS FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/C 05-May-18 08-May-18 4 80% 56 09-Sep-18 A 29-Dec-18 4
PSV 09-May-18 13-May-18 4 40 11-Sep-18 A 10-Dec-18 33
F460 COMPLETE FAB. OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTU 09-May-18 13-May-18 4 40% 40 11-Sep-18 A 10-Dec-18 33
PIPE SUPPORT 10-May-18 17-May-18 7 48 03-Sep-18 A 19-Dec-18 37
F480 FABRICATION OF INSTRUMENT STANCHION SUPPORTS 10-May-18 17-May-18 7 100% 0 03-Sep-18 A 16-Sep-18 A

Page 36 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 24 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
F470 COMPLETE FAB. OF PIPESUPPORT STRUCTURE BY PETROSERV & TRAN 14-May-18 17-May-18 4 40% 48 12-Sep-18 A 19-Dec-18 4
Piping Fabrication
Fabricati 01-May-18 14-Jun-18 39 47 27-Sep-18 A 25-Dec-18 8
FBE PIPING (AT KUWAIT) 01-May-18 14-Jun-18 39 47 27-Sep-18 A 25-Dec-18 3
F510 PIPING FABRICATION & FBE COATING AT KUWAIT 01-May-18 27-May-18 23 0% 39 11-Oct-18 A 16-Dec-18 3
F540 FBE PIPING BULK DELIVER AT SITE 29-May-18 14-Jun-18 15 0% 8 17-Dec-18 25-Dec-18 3
F510-00 PIPE DELIVER AT KUWAIT 0 100% 0 27-Sep-18 A
REMANING PIPING
PIP (NON FBE) 0 41 06-Oct-18 A 22-Dec-18 11
F510-1 COMPLETE PIPING FABRICATION INCL. HYDROTEST/ PAINTING & COATING 0 0% 33 05-Nov-18 12-Dec-18 11
F540-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 16 04-Dec-18 22-Dec-18 11
F510-000 PIPE DELIVER AT FAB FACILITY 0 100% 0 06-Oct-18 A
INSTALLATION 28-Apr-18 18-Nov-18 176 175 08-Apr-18 A 16-May-19 0
Civil Works 28-Apr-18 18-Nov-18 176 175 08-Apr-18 A 16-May-19 0
COMMOMN 28-Apr-18 18-Nov-18 176 175 08-Apr-18 A 16-May-19 0
A1960 GRADING 28-Apr-18 08-May-18 10 100% 0 08-Apr-18 A 14-Apr-18 A
A2030 CABLE TRENCHES AND UTILITY ROAD CROSSINGS 27-Jun-18 21-Jul-18 21 35% 40 10-Sep-18 A 10-Dec-18 0
A2020 ROADS AND PAVING(INCLUDING MODIFICATIONS) 25-Oct-18 10-Nov-18 14 0% 14 04-Apr-19 20-Apr-19 0
A2040 DRAINAGE PIPE CULVERTS 25-Oct-18 10-Nov-18 14 0% 36 11-Dec-18 21-Jan-19 0
A2050 ROAD SAFETY CRASH BARRIERS AND BOLLARD 25-Oct-18 18-Nov-18 21 0% 13 18-Apr-19 02-May-19 0
A2080 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) 07-Nov-18 10-Nov-18 3 0% 13 02-May-19 16-May-19 0
A1960-1 PROTECTION OF UNDERGROUND CABLES 0 90% 4 10-Sep-18 A 10-Dec-18 0
A1965-5 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPL 0 55% 40 05-Sep-18 A 10-Dec-18 0
TEST SEPERATOR
SEPERAT 09-May-18 18-Jun-18 35 0 08-Apr-18 A 13-Sep-18 A
A1965 EXCAVATION FOR THE MAIN FOUNDATIONS 09-May-18 16-May-18 7 100% 0 08-Apr-18 A 04-May-18 A
A1970 FOUNDATION WORK (STEEL FIXING) 17-May-18 18-Jun-18 28 100% 0 02-Jun-18 A 05-Jul-18 A
A1970-1 FOUNDATION WORK (CONCRETE) 0 100% 0 02-Jun-18 A 19-Jul-18 A
A1970-2 CURING / WATERPROOFING / BACK FILLING 0 100% 0 19-Jul-18 A 13-Sep-18 A
TEST SEPERAT
SEPERATOR PLATFORM 0 53 01-Aug-18 A 25-Dec-18 7
A1965-1 EXCAVATION FOR THE MAIN FOUNDATIONS 0 100% 0 01-Aug-18 A 09-Oct-18 A
A1970-3 FOUNDATION WORK (STEEL FIXING) 0 90% 37 22-Aug-18 A 06-Dec-18 7
A1970-4 FOUNDATION WORK (CONCRETE) 0 35% 16 03-Sep-18 A 16-Dec-18 7
A1970-5 CURING / WATERPROOFING / BACK FILLING 0 15% 16 16-Sep-18 A 25-Dec-18 7
METERING SKID
SK 14-Jul-18 21-Jul-18 7 32 14-Apr-18 A 01-Dec-18 29
A2010 FOUNDATION WORK (STEEL FIXING) 14-Jul-18 21-Jul-18 7 100% 0 09-Jul-18 A 10-Sep-18 A
A1965-2 EXCAVATION 0 100% 0 14-Apr-18 A 21-Jul-18 A
A2010-1 FOUNDATION WORK (CONCRETE) 0 100% 0 15-Aug-18 A 24-Sep-18 A
A2010-2 CURING / WATERPROOFING / BACK FILLING 0 65% 32 11-Sep-18 A 01-Dec-18 29
PIPE SUPPORT 19-Jun-18 12-Jul-18 21 40 18-Jul-18 A 10-Dec-18 12
A1990 FOUNDATION WORK (STEEL FIXING) 19-Jun-18 12-Jul-18 21 30% 36 14-Sep-18 A 05-Dec-18 12
A1965-3 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 98% 26 18-Jul-18 A 24-Nov-18 12
A1990-1 FOUNDATION WORK (CONCRETE) 0 0% 20 30-Sep-18 A 10-Dec-18 12
A1990-2 CURING / WATER PROOFING / BACKFILL 0 0% 15 03-Oct-18 A 10-Dec-18 12
PSV 0 43 21-May-18 A 13-Dec-18 34
A1965-4 EXCAVATION 0 100% 0 21-May-18 A 08-Aug-18 A
A2010-4 FOUNDATION WORK (CONCRETE) 0 90% 27 08-Jul-18 A 29-Nov-18 34
A2010-3 FOUNDATION WORK (STEEL FIXING) 0 95% 19 05-Jun-18 A 15-Nov-18 34
A2010-5 CURING / WATERPROOFING / BACK FILLING 0 90% 18 08-Sep-18 A 13-Dec-18 34
Structural Steel 24-Sep-18 13-Oct-18 17 42 16-Dec-18 02-Feb-19 4
TEST SEPERATOR
SEPERAT 24-Sep-18 13-Oct-18 17 17 30-Dec-18 17-Jan-19 13
A2600 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PL 24-Sep-18 01-Oct-18 7 0% 17 30-Dec-18 17-Jan-19 7
A2640 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 10-Oct-18 13-Oct-18 3 0% 9 08-Jan-19 17-Jan-19 13
METERING SKID
SK 27-Sep-18 02-Oct-18 5 18 31-Dec-18 20-Jan-19 4
A2610 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK W 27-Sep-18 02-Oct-18 5 0% 18 31-Dec-18 20-Jan-19 4
PSV 01-Oct-18 06-Oct-18 5 8 16-Dec-18 24-Dec-18 33
A2620 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 01-Oct-18 06-Oct-18 5 0% 8 16-Dec-18 24-Dec-18 33
PIPE SUPPORT 07-Oct-18 09-Oct-18 3 28 20-Dec-18 21-Jan-19 4
A2630 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS 07-Oct-18 09-Oct-18 3 0% 28 20-Dec-18 21-Jan-19 4
FIELD INSTRUMENT
INSTRUM 0 5 28-Jan-19 02-Feb-19 4
A2630-1 INSTALLATION OF INSTRUMENT STANCHION 0 0% 5 28-Jan-19 02-Feb-19 4

Page 37 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 25 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Mechanical 06-Sep-18 23-Sep-18 15 0 06-Oct-18 A 08-Oct-18 A
A2855 INSTALLATION OF NEW TEST SEPARATOR 06-Sep-18 23-Sep-18 15 100% 0 06-Oct-18 A 08-Oct-18 A
Piping 15-Sep-18 25-Oct-18 36 104 23-Dec-18 22-Apr-19 11
PIPING -REMAINING
-REMA 15-Sep-18 11-Oct-18 24 45 23-Dec-18 12-Feb-19 70
A3120 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 15-Sep-18 01-Oct-18 15 0% 37 23-Dec-18 03-Feb-19 3
A3130 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 24-Sep-18 30-Sep-18 6 0% 5 29-Jan-19 03-Feb-19 4
A3140 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 01-Oct-18 03-Oct-18 3 0% 13 29-Jan-19 12-Feb-19 4
A3150 TIE-IN 04-Oct-18 11-Oct-18 7 0% 5 29-Jan-19 03-Feb-19 4
A3120-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 15-Jan-19 24-Jan-19 4
A3151-1 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 31-Jan-19 03-Feb-19 78
HOT TAPPING 06-Oct-18 25-Oct-18 18 46 28-Feb-19 22-Apr-19 4
HT1120 MOBILIZATION OF HOT TAPPING SUB CONTRACTOR 06-Oct-18 08-Oct-18 3 0% 3 28-Feb-19 03-Mar-19 4
HT1130 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 09-Oct-18 20-Oct-18 10 0% 9 03-Mar-19 12-Mar-19 4
HT1140 FLARE TIE-IN / NDT 21-Oct-18 23-Oct-18 3 0% 13 13-Mar-19 27-Mar-19 4
HT1150 HOT TIE-IN COMPLETE / REMOVE SCAFFOLD 24-Oct-18 25-Oct-18 2 0% 12 09-Apr-19 22-Apr-19 4
Pre Shutdown and Plant Shutdown Tie-in 0 21 30-Mar-19 22-Apr-19 4
A3150-000 MOBILIZATION OF OF TEAM APPLY PTW 0 0% 1 30-Mar-19 30-Mar-19 4
A3150-00 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 0% 8 31-Mar-19 08-Apr-19 4
A3150-1 PIPING TIE-IN / NDT PRE SHUT DOWN 0 0% 15 30-Mar-19 15-Apr-19 4
A3150-2 PIPING TIE-IN / NDT SHUT DOWN 0 0% 7 15-Apr-19 22-Apr-19 4
Electrical 09-May-18 08-Nov-18 158 81 10-Sep-18 A 27-Jan-19 4
A3630 CABLE GLAND AND TERMINATION 09-May-18 24-May-18 14 0% 12 30-Dec-18 12-Jan-19 5
A3640 U/G CABLE LAYING 26-May-18 02-Jun-18 7 0% 7 03-Jan-19 10-Jan-19 4
A3650 CABLE TRAY INSTALLATION 24-Sep-18 09-Oct-18 14 0% 17 20-Dec-18 08-Jan-19 3
A3660 ELECTRICAL EQUIPMENTS INSTALLATION 10-Oct-18 17-Oct-18 7 0% 12 30-Dec-18 12-Jan-19 3
A3670 CABLE LAYING 18-Oct-18 25-Oct-18 7 0% 15 23-Dec-18 08-Jan-19 3
A3680 LIGHTING FIXTURE AND DB INSTALLATION 18-Oct-18 25-Oct-18 7 0% 7 05-Jan-19 12-Jan-19 3
A3690 ELECTRICAL TIE-INS 27-Oct-18 03-Nov-18 7 0% 2 16-Jan-19 17-Jan-19 3
A3700 ENERGIZATION 04-Nov-18 08-Nov-18 5 0% 4 17-Jan-19 21-Jan-19 3
A3640-1 BACK FILLING OF CABLE TRENCH 0 0% 15 10-Jan-19 27-Jan-19 4
A3670-1 HOOK UP 0 0% 5 12-Jan-19 16-Jan-19 3
A3920 EARTH PIT DRILLING 0 0% 4 20-Dec-18 24-Dec-18 5
A6520 CABLE TRENCHES 0 35% 40 10-Sep-18 A 10-Dec-18 4
Instrument & Control
Co 08-Sep-18 23-Oct-18 40 57 05-Jan-19 11-Mar-19 4
A4150 CABLE TRAY AND SUPPORT INSTALLATION 08-Sep-18 23-Sep-18 14 0% 15 05-Jan-19 21-Jan-19 4
A4160 INSTRUMENT EQUIPMENT CALIBRATION/ LOOP TEST 24-Sep-18 01-Oct-18 7 0% 6 05-Mar-19 11-Mar-19 4
A4190 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 24-Sep-18 07-Oct-18 12 0% 6 24-Feb-19 02-Mar-19 4
A4170 INSTRUMENT EQUIPEMNT INSTALLATION (RO, CONTROL VALVE, PRV, SDV 02-Oct-18 09-Oct-18 7 0% 17 02-Feb-19 20-Feb-19 4
A4180 INSTRUMENT CABLE LAYING 10-Oct-18 15-Oct-18 5 0% 17 17-Jan-19 05-Feb-19 5
A5320 INSTALLATION OF DELUGE 16-Oct-18 23-Oct-18 7 0% 5 16-Feb-19 20-Feb-19 7
A4180-1 SS TUBE AND LEAK TEST 0 0% 4 02-Mar-19 05-Mar-19 7
A4170-1 INSTALLATION OF INSTRUMENT VALVE 0 0% 6 14-Feb-19 20-Feb-19 4
A4170-2 FIELD INSTRUMENT INSTALLATION (GAUGES & TRANSMITTERS) 0 0% 17 02-Feb-19 20-Feb-19 4
A4170-3 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 3 18-Feb-19 20-Feb-19 5
A3710 JB SUPPORT INSTALLATION 0 0% 4 17-Jan-19 21-Jan-19 4
A3810 JB INSTALLATION 0 0% 4 22-Jan-19 26-Jan-19 4
A3900 CABLE GLANDING AND TERMINATION (ALONG JBs) 0 0% 5 27-Jan-19 31-Jan-19 5
A3910 CABLE GLANDING AND TERMINATION (ALONG INSTRUMENTS) 0 0% 5 20-Feb-19 25-Feb-19 4
F&G System 0 41 17-Jan-19 05-Mar-19 44
A6290 F&G SUPPORT INSTALLATION 0 0% 4 17-Jan-19 21-Jan-19 78
A6300 F&G DEVICES INSTALLATION 0 0% 4 21-Jan-19 24-Jan-19 78
A6280 F&G CABLE INSTALLATION 0 0% 9 17-Jan-19 27-Jan-19 76
A6310 F&G JB SUPPORT INSTALLATION 0 0% 2 22-Jan-19 23-Jan-19 79
A6320 F&G JB INSTALLATION 0 0% 2 27-Jan-19 28-Jan-19 75
A6330 F&G CABLE GLANDING AND TERMINATION 0 0% 5 20-Feb-19 25-Feb-19 46
A6340 F&G LOOP PREPARATION 0 0% 3 25-Feb-19 27-Feb-19 46
A6350 F&G LOOP TESTING 0 0% 3 03-Mar-19 05-Mar-19 44

Page 38 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 26 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Painting & Fireproofing
Firep 02-Oct-18 17-Oct-18 14 30 27-Jan-19 02-Mar-19 5
A4420 STRUCTURAL STEEL PAINTING AND TOUCH-UP 02-Oct-18 09-Oct-18 7 0% 12 27-Jan-19 09-Feb-19 5
A4430 PIPING PAINTING AND TOUCH-UP 04-Oct-18 11-Oct-18 7 0% 13 29-Jan-19 12-Feb-19 10
A4440 FIREPROOFING FOR STRUCTURAL STEEL 10-Oct-18 17-Oct-18 7 0% 25 02-Feb-19 02-Mar-19 5
Pre-commisionin
Pre-commisioning 04-Oct-18 13-Nov-18 35 168 09-Sep-18 A 08-May-19 3
A3151 INST LOOP AND FUNCTIONAL TESTING 04-Oct-18 07-Oct-18 3 0% 3 23-Apr-19 25-Apr-19 3
A4710 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 13-Oct-18 20-Oct-18 7 17% 127 09-Sep-18 A 21-Mar-19 18
A4750 ELECTRICAL LIGHTING TEST 13-Oct-18 10-Nov-18 25 0% 5 25-Apr-19 30-Apr-19 3
A4720 DELUGE SKID FUNCTIONAL TESTING 16-Oct-18 18-Oct-18 3 0% 5 30-Apr-19 05-May-19 3
A4730 PUNCHLIST 11-Nov-18 13-Nov-18 3 0% 4 05-May-19 08-May-19 3
A4720-1 LEAK TEST FOR SEPARATOR AND PIPING 0 0% 3 02-May-19 05-May-19 3
Commissioning 17-Nov-18 26-Nov-18 8 10 09-May-19 20-May-19 0
A5130 START OF PRODUCTION 17-Nov-18 20-Nov-18 3 0% 1 09-May-19 09-May-19 3
A5140 COMMISSIONING AND STARTUP 18-Nov-18 21-Nov-18 3 0% 4 09-May-19 13-May-19 3
A5150 PERFORMANCE TESTS 21-Nov-18 26-Nov-18 7 0% 3 18-May-19 20-May-19 0
Demolition Works
Work 20-Nov-18 09-Dec-18 16 39 18-May-19 01-Jul-19 18
DM1210 WORK PERMIT APPROVED FOR DEMOLITION 20-Nov-18 24-Nov-18 3 0% 3 18-May-19 20-May-19 18
DM1220 DEPRESSURIZATION / ISOLATION (PIPING & INSTRUMENTATION) 24-Nov-18 26-Nov-18 2 0% 2 21-May-19 22-May-19 18
DM1240 APPLY ANTI RUST TO FOUNDATION BOTLS 26-Nov-18 27-Nov-18 1 0% 1 22-May-19 23-May-19 18
DM1230 COLD CUTTING INLET AND OUTLET PIPING 27-Nov-18 01-Dec-18 3 0% 21 23-May-19 16-Jun-19 18
DM1250 UNBOLD & REMOVE EXISTING SEPARATOR 01-Dec-18 03-Dec-18 2 0% 2 16-Jun-19 18-Jun-19 18
DM1260 REMOVE CONCRETE FOUNDATION / GRADE THE AREA 03-Dec-18 09-Dec-18 5 0% 12 18-Jun-19 01-Jul-19 18
DM1270 DEMOLITION WORKS COMPLETE 09-Dec-18 0 0% 0 01-Jul-19 18
FAHN 19-May-18 16-Dec-18 182 209 05-May-18 A 25-Jun-19 23
FABRICATION 19-May-18 08-Jul-18 44 62 03-Sep-18 A 05-Jan-19 88
Structural Steel Fabrication 19-May-18 21-Jun-18 30 60 03-Sep-18 A 02-Jan-19 90
TEST SEPERATOR
SEPERAT 19-May-18 05-Jun-18 16 60 10-Sep-18 A 02-Jan-19 0
F550 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CR 19-May-18 05-Jun-18 16 45% 60 10-Sep-18 A 02-Jan-19 0
METERING SKID
SK 06-Jun-18 11-Jun-18 5 60 12-Sep-18 A 02-Jan-19 2
F560 FAB OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS. TRANSFER 06-Jun-18 11-Jun-18 5 80% 60 12-Sep-18 A 02-Jan-19 2
PSV 12-Jun-18 17-Jun-18 5 48 11-Sep-18 A 19-Dec-18 25
F570 FAB OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTURE TRANSFE 12-Jun-18 17-Jun-18 5 50% 48 11-Sep-18 A 19-Dec-18 25
PIPE SUPPORT 14-Jun-18 21-Jun-18 7 60 03-Sep-18 A 02-Jan-19 90
F590 FABRICATION OF INSTRUMENT STANCHION SUPPORTS 14-Jun-18 21-Jun-18 7 100% 0 03-Sep-18 A 11-Oct-18 A
F580 FAB. OF PIPESUPPORT STRUCTURE TRANSFER TO SITE FOR INSTALLATI 18-Jun-18 21-Jun-18 4 45% 60 11-Sep-18 A 02-Jan-19 0
Piping Fabrication
Fabricati 28-May-18 08-Jul-18 36 48 27-Sep-18 A 05-Jan-19 34
FBE PIPING (AT KUWAIT) 28-May-18 08-Jul-18 36 48 27-Sep-18 A 05-Jan-19 34
F620 PIPING FABRICATION & FBE COATING AT KUWAIT 28-May-18 18-Jun-18 19 0% 39 14-Oct-18 A 25-Dec-18 34
F650 FBE PIPING BULK DELIVER AT SITE 25-Jun-18 08-Jul-18 12 0% 9 26-Dec-18 05-Jan-19 34
F620-000 PIPE DELIVER AT KUWAIT 0 100% 0 27-Sep-18 A
REMAINING PIPING
PI (NON FBE) 0 40 06-Oct-18 A 03-Jan-19 20
F620-1 COMPLETE PIPING FABRICATION INCL. HYDROTEST/ PAINTING & COATIN 0 0% 33 19-Nov-18 26-Dec-18 20
F650-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 17 16-Dec-18 03-Jan-19 20
F620-00 PIPE DELIVER AT PETROSERV FACILITY BY CPECC - DRV 0 100% 0 06-Oct-18 A
INSTALLATION 19-Jun-18 16-Dec-18 155 165 05-May-18 A 05-May-19 4
Civil Works 19-Jun-18 16-Dec-18 155 165 05-May-18 A 05-May-19 4
COMMOMN 19-Jun-18 16-Dec-18 155 165 05-May-18 A 05-May-19 4
A2090 GRADING 19-Jun-18 24-Jun-18 5 100% 0 05-May-18 A 10-May-18 A
A2160 UTILITY ROAD CROSSINGS 22-Nov-18 16-Dec-18 21 0% 17 16-Apr-19 05-May-19 4
A2150 ROADS AND PAVING(INCLUDING MODIFICATIONS) 22-Nov-18 08-Dec-18 14 0% 14 13-Apr-19 28-Apr-19 4
A2170 DRAINAGE PIPE CULVERTS 22-Nov-18 08-Dec-18 14 0% 11 25-Dec-18 06-Jan-19 4
A2180 ROAD SAFETY CRASH BARRIERS AND BOLLARD 22-Nov-18 16-Dec-18 21 0% 13 21-Apr-19 05-May-19 4
A2200 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) 05-Dec-18 08-Dec-18 3 0% 14 13-Apr-19 28-Apr-19 4
A2090-1 PROTECTION OF UNDERGROUND CABLES 0 80% 52 13-Aug-18 A 24-Dec-18 9
A2095-00 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPL 0 50% 12 18-Sep-18 A 07-Nov-18 4
A2160-1 CABLE TRENCHES 0 0% 40 08-Nov-18 24-Dec-18 4
TEST SEPERATOR
SEPERAT 25-Jun-18 04-Aug-18 35 0 05-May-18 A 09-Sep-18 A
A2095 EXCAVATION FOR THE MAIN FOUNDATIONS 25-Jun-18 02-Jul-18 7 100% 0 05-May-18 A 04-Aug-18 A

Page 39 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 27 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A2100 FOUNDATION WORK (STEEL FIXING) 03-Jul-18 04-Aug-18 28 100% 0 03-Jul-18 A 16-Aug-18 A
A2100-3 CURING / WATERPROOFING / BACK FILLING 0 100% 0 05-Aug-18 A 09-Sep-18 A
A2100-1 FOUNDATION WORK (CONCRETE) 0 100% 0 17-Jul-18 A 23-Aug-18 A
TEST SEPERAT
SEPERATOR PLATFORM 0 58 28-Aug-18 A 31-Dec-18 8
A2095-1 EXCAVATION FOR THE MAIN FOUNDATIONS 0 40% 28 28-Aug-18 A 26-Nov-18 8
A2100-5 FOUNDATION WORK (CONCRETE) 0 0% 18 22-Nov-18 12-Dec-18 8
A2100-4 FOUNDATION WORK (STEEL FIXING) 0 0% 15 10-Oct-18 A 03-Dec-18 16
A2140-125 CURING / WATER PROOFING / BACKFILL 0 0% 25 03-Dec-18 31-Dec-18 8
METERING SKID
SK 29-Aug-18 05-Sep-18 7 28 05-May-18 A 26-Nov-18 39
A2140 FOUNDATION WORK (STEEL FIXING) 29-Aug-18 05-Sep-18 7 100% 0 04-Jul-18 A 05-Sep-18 A
A2140-2 CURING / WATERPROOFING / BACK FILLING 0 0% 28 08-Oct-18 A 26-Nov-18 39
A2095-2 EXCAVATION 0 100% 0 05-May-18 A 07-Aug-18 A
A2140-1 FOUNDATION WORK (CONCRETE) 0 95% 3 28-Aug-18 A 28-Oct-18 39
PIPE SUPPORT 05-Aug-18 28-Aug-18 21 60 04-Aug-18 A 02-Jan-19 2
A2120 FOUNDATION WORK (STEEL FIXING) 05-Aug-18 28-Aug-18 21 80% 31 08-Sep-18 A 29-Nov-18 12
A2120-2 CURING / WATERPROOFING / BACK FILLING 0 20% 45 16-Sep-18 A 02-Jan-19 2
A2095-3 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 90% 19 04-Aug-18 A 15-Nov-18 17
A2120-1 FOUNDATION WORK (CONCRETE) 0 80% 48 11-Sep-18 A 19-Dec-18 2
PSV 0 56 26-May-18 A 29-Dec-18 34
A2140-5 CURING / WATERPROOFING / BACK FILLING 0 50% 44 18-Sep-18 A 15-Dec-18 34
A2095-4 EXCAVATION 0 100% 0 26-May-18 A 22-Oct-18 A
A2140-3 FOUNDATION WORK (STEEL FIXING) 0 80% 19 09-Jul-18 A 15-Nov-18 34
A2140-4 FOUNDATION WORK (CONCRETE) 0 70% 56 10-Sep-18 A 29-Dec-18 34
Structural Steel 11-Oct-18 30-Oct-18 17 35 26-Dec-18 04-Feb-19 67
TEST SEPERATOR
SEPERAT 11-Oct-18 18-Oct-18 7 18 06-Jan-19 26-Jan-19 4
A2660 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PL 11-Oct-18 18-Oct-18 7 0% 18 06-Jan-19 26-Jan-19 4
A2660-1 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 0 0% 9 16-Jan-19 26-Jan-19 4
METERING SKID
SK 15-Oct-18 20-Oct-18 5 11 09-Jan-19 21-Jan-19 2
A2670 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK W 15-Oct-18 20-Oct-18 5 0% 11 09-Jan-19 21-Jan-19 2
PSV 18-Oct-18 23-Oct-18 5 9 26-Dec-18 05-Jan-19 25
A2680 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 18-Oct-18 23-Oct-18 5 0% 9 26-Dec-18 05-Jan-19 25
PIPE SUPPORT 24-Oct-18 27-Oct-18 3 18 10-Jan-19 30-Jan-19 0
A2690 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS 24-Oct-18 27-Oct-18 3 0% 18 10-Jan-19 30-Jan-19 0
FIELD INSTRUMENT
INSTRUM 28-Oct-18 30-Oct-18 3 5 30-Jan-19 04-Feb-19 67
A2700 INSTALLATION OF INSTRUMENT STANCHION 28-Oct-18 30-Oct-18 3 0% 5 30-Jan-19 04-Feb-19 67
Mechanical 24-Sep-18 10-Oct-18 15 0 05-Sep-18 A 12-Sep-18 A
A2875 INSTALLATION OF NEW TEST SEPARATOR 24-Sep-18 10-Oct-18 15 100% 0 05-Sep-18 A 12-Sep-18 A
Piping 03-Oct-18 29-Oct-18 23 79 21-Jan-19 22-Apr-19 4
PIPING -REMAINING
-REMA 03-Oct-18 29-Oct-18 23 77 21-Jan-19 20-Apr-19 6
A3170 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 03-Oct-18 18-Oct-18 14 0% 21 21-Jan-19 13-Feb-19 0
A3180 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 11-Oct-18 17-Oct-18 6 0% 5 15-Apr-19 20-Apr-19 0
A3190 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 18-Oct-18 21-Oct-18 3 0% 13 02-Feb-19 16-Feb-19 4
A3200 TIE-IN 22-Oct-18 29-Oct-18 7 0% 5 15-Apr-19 20-Apr-19 0
A3170-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 12 29-Jan-19 11-Feb-19 56
A3151-11 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 17-Apr-19 20-Apr-19 6
Pre Shutdown and Plant Shutdown Tie-in 0 26 24-Mar-19 22-Apr-19 4
A3200-2 PIPING TIE-IN / NDT SHUT DOWN 0 0% 7 15-Apr-19 22-Apr-19 4
A3200-b SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 0% 7 24-Mar-19 31-Mar-19 0
A3200-1 PIPING TIE-IN / NDT PRE SHUT DOWN 0 0% 14 31-Mar-19 15-Apr-19 0
A3200-a MOBILIZATION OF OF TEAM APPLY PTW 0 0% 1 24-Mar-19 24-Mar-19 0
Electrical 25-Jun-18 04-Dec-18 140 108 08-Nov-18 13-Mar-19 4
A3720 CABLE GLAND AND TERMINATION 25-Jun-18 10-Jul-18 14 0% 12 16-Feb-19 28-Feb-19 5
A3730 U/G CABLE LAYING 11-Jul-18 18-Jul-18 7 0% 8 30-Dec-18 07-Jan-19 5
A3740 CABLE TRAY INSTALLATION 20-Oct-18 04-Nov-18 14 0% 9 26-Jan-19 04-Feb-19 4
A3750 ELECTRICAL EQUIPMENTS INSTALLATION 05-Nov-18 12-Nov-18 7 0% 12 02-Feb-19 14-Feb-19 4
A3760 CABLE LAYING 13-Nov-18 20-Nov-18 7 0% 17 30-Jan-19 18-Feb-19 4
A3770 LIGHTING FIXTURE AND DB INSTALLATION 13-Nov-18 20-Nov-18 7 0% 9 21-Feb-19 03-Mar-19 4
A3780 ELECTRICAL TIE-INS 21-Nov-18 28-Nov-18 7 0% 2 07-Mar-19 09-Mar-19 4

Page 40 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 28 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A3790 ENERGIZATION 29-Nov-18 04-Dec-18 5 0% 4 10-Mar-19 13-Mar-19 4
A3730-1 BACK FILLING OF CABLE TRENCH 0 0% 12 06-Jan-19 19-Jan-19 5
A3760-1 HOOK UP 0 0% 5 03-Mar-19 07-Mar-19 4
A2160-11 CABLE TRENCHES 0 0% 40 08-Nov-18 24-Dec-18 5
A3930 EARTH PIT DRILLING 0 0% 5 31-Dec-18 05-Jan-19 5
Instrument & Control
Co 11-Oct-18 08-Dec-18 50 40 16-Jan-19 03-Mar-19 2
A4240 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 11-Oct-18 17-Oct-18 6 0% 9 12-Feb-19 21-Feb-19 4
A4930 JB INSTALLATION 16-Oct-18 19-Oct-18 3 0% 3 30-Jan-19 02-Feb-19 4
A4940 JB SUPPORT INSTALLATION 16-Oct-18 19-Oct-18 3 0% 4 27-Jan-19 30-Jan-19 4
A4200 CABLE TRAY AND SUPPORTS INSTALLATION 23-Oct-18 07-Nov-18 14 0% 13 16-Jan-19 30-Jan-19 2
A4990 CABLE GLAND AND TERMINATION (ALONG INSTRUMENTS) 30-Oct-18 01-Nov-18 3 0% 7 16-Feb-19 23-Feb-19 2
A4210 INSTRUMENT EQUIPMENT CALIBRATION 08-Nov-18 15-Nov-18 7 0% 6 25-Feb-19 03-Mar-19 2
A4220 INSTRUMENT EQUIPEMNT INSTALLATION (RO, CONTROL VALVE, PRV, SDV 17-Nov-18 24-Nov-18 7 0% 18 23-Jan-19 12-Feb-19 2
A4230 INSTRUMENT CABLE LAYING 25-Nov-18 29-Nov-18 5 0% 16 22-Jan-19 09-Feb-19 2
A5330 INSTALLATION OF DELUGE 01-Dec-18 08-Dec-18 7 0% 7 05-Feb-19 12-Feb-19 4
A4230-1 SS TUBE AND LEAK TEST 0 0% 4 23-Feb-19 26-Feb-19 2
A4220-1 INSTALLATION OF INSTRUMENT VALVE 0 0% 3 10-Feb-19 12-Feb-19 15
A4220-2 FIELD INSTRUMENT INSTALLATION (GAUGES & TRANSMITTERS) 0 0% 23 23-Jan-19 18-Feb-19 2
A4220-3 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 3 10-Feb-19 12-Feb-19 4
A3800 FIELD INSTRUMENT INSTALLATION 0 0% 17 09-Feb-19 27-Feb-19 4
A4980 CABLE GLAND AND TERMINATION (ALONG JBs) 0 0% 10 10-Feb-19 20-Feb-19 4
F&G System 0 32 22-Jan-19 27-Feb-19 40
A6370 F&G SUPPORT INSTALLATION 0 0% 4 27-Jan-19 30-Jan-19 62
A6380 F&G DEVICES INSTALLATION 0 0% 4 29-Jan-19 02-Feb-19 62
A6360 F&G CABLE INSTALLATION 0 0% 8 22-Jan-19 30-Jan-19 64
A6390 F&G JB SUPPORT INSTALLATION 0 0% 2 30-Jan-19 31-Jan-19 63
A6400 F&G JB INSTALLATION 0 0% 3 02-Feb-19 04-Feb-19 60
A6410 F&G CABLE GLANDING AND TERMINATION 0 0% 5 18-Feb-19 23-Feb-19 18
A6420 F&G LOOP PREPARATION 0 0% 2 23-Feb-19 24-Feb-19 18
A6430 F&G LOOP TESTING 0 0% 4 24-Feb-19 27-Feb-19 18
Painting & Fireproofing
Firep 20-Oct-18 04-Nov-18 14 25 04-Feb-19 04-Mar-19 4
A4450 STRUCTURAL STEEL PAINTING AND TOUCH-UP 20-Oct-18 27-Oct-18 7 0% 13 04-Feb-19 18-Feb-19 4
A4460 PIPING PAINTING AND TOUCH-UP 22-Oct-18 29-Oct-18 7 0% 13 04-Feb-19 18-Feb-19 4
A4470 FIREPROOFING FOR STRUCTURAL STEEL 28-Oct-18 04-Nov-18 7 0% 20 10-Feb-19 04-Mar-19 4
Pre-commisionin
Pre-commisioning 22-Oct-18 15-Dec-18 47 162 09-Sep-18 A 01-May-19 1
A3201 INST LOOP AND FUNCTIONAL TESTING 22-Oct-18 24-Oct-18 3 0% 3 16-Apr-19 18-Apr-19 0
A4760 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 30-Oct-18 06-Nov-18 7 17% 127 09-Sep-18 A 21-Mar-19 18
A4800 ELECTRICAL LIGHITNG TESTING 30-Oct-18 26-Nov-18 24 0% 5 20-Apr-19 24-Apr-19 0
A4770 DELUGE SKID FUNCTIONAL TESTING 09-Dec-18 11-Dec-18 3 0% 3 24-Apr-19 27-Apr-19 0
A4780 PUNCH LIST 12-Dec-18 15-Dec-18 3 0% 4 28-Apr-19 01-May-19 0
A4770-1 LEAK TEST FOR SEPARATOR AND PIPING 0 0% 5 23-Apr-19 28-Apr-19 4
Commissioning 28-Nov-18 07-Dec-18 8 8 01-May-19 09-May-19 0
A5190 START OF PRODUCTION 28-Nov-18 30-Nov-18 3 0% 2 01-May-19 02-May-19 0
A5200 COMMISSIONING AND STARTUP 29-Nov-18 01-Dec-18 3 0% 3 02-May-19 05-May-19 0
A5210 PERFORMANCE TESTS 01-Dec-18 07-Dec-18 7 0% 4 06-May-19 09-May-19 0
Demolition Works
Work 27-Nov-18 16-Dec-18 16 43 07-May-19 25-Jun-19 23
DM1280 WORK PERMIT APPROVED FOR DEMOLITION 27-Nov-18 29-Nov-18 3 0% 3 07-May-19 09-May-19 23
DM1290 DEPRESSURIZATION / ISOLATION (PIPING & INSTRUMENTATION) 01-Dec-18 02-Dec-18 2 0% 2 11-May-19 12-May-19 23
DM1310 APPLY ANTI RUST TO FOUNDATION BOTLS 03-Dec-18 04-Dec-18 1 0% 2 12-May-19 13-May-19 23
DM1300 COLD CUTTING INLET AND OUTLET PIPING 04-Dec-18 08-Dec-18 3 0% 21 13-May-19 05-Jun-19 23
DM1320 UNBOLD & REMOVE EXISTING SEPARATOR 08-Dec-18 10-Dec-18 2 0% 2 05-Jun-19 06-Jun-19 23
DM1330 REMOVE CONCRETE FOUNDATION / GRADE THE AREA 10-Dec-18 16-Dec-18 5 0% 16 08-Jun-19 25-Jun-19 23
DM1340 DEMOLITION WORKS COMPLETE 16-Dec-18 0 0% 0 25-Jun-19 23
FAHM 09-May-18 24-Dec-18 197 183 24-Jun-18 A 26-May-19 10
FABRICATION 19-Jun-18 01-Aug-18 38 79 03-Sep-18 A 24-Jan-19 64
Structural Steel Fabrication 23-Jun-18 17-Jul-18 22 79 03-Sep-18 A 24-Jan-19 64
TEST SEPERATOR
SEPERAT 23-Jun-18 05-Jul-18 12 79 13-Sep-18 A 24-Jan-19 9

Page 41 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 29 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
F660 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CR 23-Jun-18 05-Jul-18 12 30% 79 13-Sep-18 A 24-Jan-19 9
METERING SKID
SK 07-Jul-18 09-Jul-18 3 79 13-Sep-18 A 24-Jan-19 9
F670 FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS TRANSFER 07-Jul-18 09-Jul-18 3 30% 79 13-Sep-18 A 24-Jan-19 9
PSV 10-Jul-18 12-Jul-18 3 66 13-Sep-18 A 09-Jan-19 77
F680 FAB.OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTURE TRANSFE 10-Jul-18 12-Jul-18 3 30% 66 13-Sep-18 A 09-Jan-19 77
PIPE SUPPORT 10-Jul-18 17-Jul-18 7 62 03-Sep-18 A 05-Jan-19 58
F700 FABRICATION OF INSTRUMENT STANCHION SUPPORTS 10-Jul-18 17-Jul-18 7 100% 0 03-Sep-18 A 16-Sep-18 A
F690 FAB. OF PIPESUPPORT STRUCTURE TRANSFER TO SITE FOR INSTALLATI 14-Jul-18 17-Jul-18 4 67% 62 12-Sep-18 A 05-Jan-19 51
Piping Fabrication
Fabricati 19-Jun-18 01-Aug-18 38 72 27-Sep-18 A 16-Jan-19 28
FBE PIPING (AT KUWAIT) 19-Jun-18 01-Aug-18 38 67 27-Sep-18 A 10-Jan-19 22
F730 PIPING FABRICATION & FBE COATING AT KUWAIT 19-Jun-18 11-Jul-18 20 0% 58 18-Oct-18 A 31-Dec-18 22
F760 FBE PIPING BULK DELIVER AT SITE 17-Jul-18 01-Aug-18 14 0% 9 01-Jan-19 10-Jan-19 22
F730-000 PIPE DELIVER AT KUWAIT 0 100% 0 27-Sep-18 A
REMAINING PIPING
PI (NON FBE) 0 42 06-Oct-18 A 16-Jan-19 28
F730-1 COMPLETE PIPING FABRICATION INCL. HYDROTEST/ PAINTING & COATIN 0 0% 40 29-Nov-18 14-Jan-19 28
F760-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 17 29-Dec-18 16-Jan-19 28
F730-00 PIPE DELIVER AT FACILITY BY CPECC 0 100% 0 06-Oct-18 A
ISOLATION AND DEMOLITION WORKS 0 43 24-Jun-18 A 20-Dec-18 37
FM-DEM-1000 ISSUE METHOD STATEMENT FOR ISOLATION & DEMOLTION WORK OF SE 0 100% 0 24-Jun-18 A
FM-DEM-1010 METHOD STATEMENT RE SUBMISSION & APPROVED BY QP 0 100% 0 24-Jun-18 A 19-Sep-18 A
FM-DEM-1020 OPERATION CLEARANCE & VESSEL DEPRESSURIZATION BY QP OPERATIO 0 0% 5 01-Nov-18 06-Nov-18 3
FM-DEM-1030 PURGING / SYSTEM ISOLATE SEPERATOR FROM EXISTING SYSTEM 0 0% 7 07-Nov-18 14-Nov-18 32
FM-DEM-1040 COMPLETE DEMO WORK OF SEPARATOR & METERING SKID FOUNDATIO 0 0% 30 15-Nov-18 19-Dec-18 37
ISOLATION WORKS
WOR 0 7 07-Nov-18 14-Nov-18 3
PIPING ISOLATION
ISOLAT 0 5 07-Nov-18 12-Nov-18 3
A5630 ISOLATION OF EXISTING VALVES 0 0% 5 07-Nov-18 12-Nov-18 3
INSTRUMENT ISOLATION
I 0 2 11-Nov-18 12-Nov-18 4
A5640 ISOLATION OF ASSOCIATED INTRUMENTS 0 0% 2 11-Nov-18 12-Nov-18 4
ELECTRICAL ISOLATION
IS 0 2 13-Nov-18 14-Nov-18 3
A5650 ISOLATION OF ASSOCIATED ELECTRICAL ITEMS 0 0% 2 13-Nov-18 14-Nov-18 3
DEMOLITION WORKS
W 0 32 14-Nov-18 20-Dec-18 37
DEMOLITION O
OF EXISTING PIPING 0 7 14-Nov-18 21-Nov-18 3
A5660 REMOVAL OF EXISITNG PIPING WITH SEPARATOR 0 0% 7 14-Nov-18 21-Nov-18 3
DEMOLITION O
OF EXISTING INSTRUMENTATION 0 6 19-Nov-18 25-Nov-18 7
A5670 REMOVAL OF EXISITNG INTRUMENTS AND CABLES WITH SEPARATOR 0 0% 3 19-Nov-18 21-Nov-18 3
A5680 REMOVAL OF SEPARTOR FROM EXISTING LOGIC 0 0% 5 20-Nov-18 25-Nov-18 7
DISMANTLING OF EXISTING SEPARATOR 0 4 25-Nov-18 28-Nov-18 4
A5690 APPLICATION OF ANTI-RUST PAINT/COATING 0 0% 2 25-Nov-18 26-Nov-18 3
A5700 UNBOLTING OF SEPARATOR FROM FOUNDATION 0 0% 2 25-Nov-18 26-Nov-18 4
A5710 LIFITNG AND REMOVAL FROM FOUNDATION 0 0% 2 27-Nov-18 28-Nov-18 4
DISMANTLING OF EXISTING SEPARATOR PLATFORM 0 5 26-Nov-18 01-Dec-18 3
A5750 APPLICATION OF ANTI-RUST PAINT/COATING 0 0% 1 26-Nov-18 26-Nov-18 3
A5760 UNBOLTING OF PLATFORM FROM FOUNDATION 0 0% 2 26-Nov-18 27-Nov-18 3
A5770 LIFTING AND REMOVAL FROM FOUNDATION 0 0% 4 27-Nov-18 01-Dec-18 3
DISMANTLING OF EXISTING METERING SKID 0 5 27-Nov-18 02-Dec-18 16
A5720 APPLICATION OF ANTI-RUST PAINT/COATING 0 0% 1 27-Nov-18 27-Nov-18 16
A5730 UNBOLTING FROM FOUNDATION 0 0% 2 27-Nov-18 28-Nov-18 16
A5740 LIFTING AND REMOVAL FROM FOUNDATION 0 0% 2 01-Dec-18 02-Dec-18 16
DISMANTLING OF EXISTING METERING SKID PLATFORM 0 8 27-Nov-18 05-Dec-18 16
A5780 APPLICATION OF ANTI-RUST PAINT/COATING 0 0% 2 27-Nov-18 28-Nov-18 17
A5790 UNBOLTING OF PLATFORM FROM FOUNDATION 0 0% 3 27-Nov-18 29-Nov-18 17
A5800 LIFTING AND REMOVAL FROM FOUNDATION 0 0% 4 02-Dec-18 05-Dec-18 16
DISMANTLING OF EXISTING PSV PLATFORM 0 8 27-Nov-18 05-Dec-18 43
A5810 APPLICATION OF ANTI-RUST PAINT/COATING 0 0% 2 27-Nov-18 28-Nov-18 46
A5820 UNBOLTING OF PLATFORM FROM FOUNDATION 0 0% 3 27-Nov-18 29-Nov-18 46
A5830 LIFTING AND REMOVAL FROM FOUNDATION 0 0% 2 04-Dec-18 05-Dec-18 43
DEMOLITION OF
O EXISITNG SEPARATOR FOUNDATION 0 17 02-Dec-18 20-Dec-18 3
A5840 EXISTING SEPARATOR FOUNDATION DEMOLITION 0 0% 17 02-Dec-18 20-Dec-18 3

Page 42 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 30 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DEMOLITION OF
O EXISTING METERING SKID FOUNDATION 0 8 06-Dec-18 15-Dec-18 16
A5850 EXISTING FOUNDATION DEMOLITION 0 0% 8 06-Dec-18 15-Dec-18 16
DEMOLITION O
OF EXISTING PSV FOUNDATION 0 7 06-Dec-18 13-Dec-18 43
A5860 EXISTING FOUNDATION DEMOLITION 0 0% 7 06-Dec-18 13-Dec-18 43
INSTALLATION 09-May-18 24-Dec-18 197 183 04-Aug-18 A 26-May-19 10
Civil Works 09-May-18 24-Dec-18 197 183 04-Aug-18 A 26-May-19 10
COMMOMN 09-May-18 24-Dec-18 197 169 14-Sep-18 A 26-May-19 10
A2230 GRADING 09-May-18 20-May-18 10 0% 5 14-Sep-18 A 15-Nov-18 10
A2300 CABLE TRENCHES AND UTILITY ROAD CROSSINGS 09-Jul-18 01-Aug-18 21 0% 25 04-Dec-18 01-Jan-19 29
A2290 ROADS AND PAVING(INCLUDING MODIFICATIONS) 22-Nov-18 08-Dec-18 14 0% 16 18-Apr-19 07-May-19 10
A2310 DRAINAGE PIPE CULVERTS 22-Nov-18 08-Dec-18 14 0% 25 22-Jan-19 19-Feb-19 10
A2320 ROAD SAFETY CRASH BARRIERS AND BOLLARD 22-Nov-18 16-Dec-18 21 0% 16 07-May-19 26-May-19 10
A2350 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) 17-Dec-18 24-Dec-18 7 0% 16 07-May-19 26-May-19 10
A2230-1 PROTECTION OF UNDERGROUND CABLES 0 0% 14 26-Dec-18 10-Jan-19 10
A2280-3 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPL 0 0% 21 25-Nov-18 18-Dec-18 107
TEST SEPERATOR
SEPERAT 29-May-18 30-Jun-18 28 47 20-Dec-18 12-Feb-19 3
A2240 EXCAVATION 29-May-18 30-Jun-18 28 0% 15 20-Dec-18 06-Jan-19 3
A2240-2 CURING 0 0% 8 26-Jan-19 03-Feb-19 3
A2240-1 FOUNDATION (STEEL FIXING) 0 0% 15 06-Jan-19 22-Jan-19 3
A2240-11 FOUNDATION (CONCRETE) 0 0% 11 19-Jan-19 30-Jan-19 3
A2250 BLINDING 0 0% 6 02-Jan-19 08-Jan-19 3
A2270 FORMWORK FOR FOUNDATION 0 0% 8 14-Jan-19 22-Jan-19 3
A2240-22 WATER PROOFING (BITUMEN COATING) 0 0% 9 29-Jan-19 07-Feb-19 3
A2240-32 BACKFILL 0 0% 9 03-Feb-19 12-Feb-19 3
TEST SEPERAT
SEPERATOR PLATFORM 0 48 01-Jan-19 25-Feb-19 27
A5900 EXCAVATION 0 0% 22 01-Jan-19 26-Jan-19 27
A2240-82 CURING 0 0% 7 11-Feb-19 18-Feb-19 27
A2240-62 FOUNDATION (STEEL FIXING) 0 0% 15 22-Jan-19 07-Feb-19 27
A2240-72 FOUNDATION (CONCRETE) 0 0% 9 06-Feb-19 16-Feb-19 27
A5880 BLINDING 0 0% 9 22-Jan-19 31-Jan-19 27
A5890 FORMWORK FOR FOUNDATION 0 0% 7 31-Jan-19 07-Feb-19 27
A2240-42 WATER PROOFING (BITUMEN COATING) 0 0% 7 16-Feb-19 23-Feb-19 27
A2240-52 BACKFILL 0 0% 7 18-Feb-19 25-Feb-19 27
METERING SKID
SK 0 34 30-Dec-18 06-Feb-19 4
A2240-12 EXCAVATION 0 0% 12 30-Dec-18 12-Jan-19 4
A2240-92 BLINDING 0 0% 7 01-Jan-19 08-Jan-19 4
A2240-102 FOUNDATION (STEEL FIXING) 0 0% 9 05-Jan-19 14-Jan-19 4
A2240-112 FOUNDATION (CONCRETE) 0 0% 9 12-Jan-19 21-Jan-19 4
A2240-122 FORMWORK FOR FOUNDATION 0 0% 5 09-Jan-19 14-Jan-19 4
A2240-132 CURING 0 0% 7 21-Jan-19 28-Jan-19 4
A2240-142 WATERPROOFING (BITUMEN COATING) 0 0% 3 28-Jan-19 30-Jan-19 4
A2240-152 BACKFILL 0 0% 7 30-Jan-19 06-Feb-19 4
PIPE SUPPORT 01-Jul-18 24-Jul-18 21 64 04-Aug-18 A 07-Jan-19 7
A2260 FOUNDATION WORK (STEEL FIXING) 01-Jul-18 24-Jul-18 21 0% 26 13-Nov-18 12-Dec-18 0
A2235-4 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 60% 26 04-Aug-18 A 24-Nov-18 0
A2260-1 FOUNDATION WORK (CONCRETE) 0 0% 26 21-Nov-18 20-Dec-18 0
A2260-2 CURING 0 0% 26 24-Nov-18 23-Dec-18 0
A2260-3 BLINDING CONCRETE FOR PS FOUNDATIONS 0 0% 25 07-Nov-18 05-Dec-18 0
A2260-4 FORMWORK FOR FOR PS FOUNDAITON 0 0% 20 20-Nov-18 12-Dec-18 0
A2260-5 WATER PROOFING (BITUMENT COATING) 0 0% 20 09-Dec-18 31-Dec-18 7
A2260-6 BACKFILLING 0 0% 20 16-Dec-18 07-Jan-19 7
PSV 25-Jul-18 01-Aug-18 7 55 20-Dec-18 21-Feb-19 38
A2280 FOUNDATION WORK (STEEL FIXING) 25-Jul-18 01-Aug-18 7 0% 15 06-Jan-19 22-Jan-19 38
A2235-5 EXCAVATION (INCLUDING AREA LIGHTING POLES) 0 0% 15 20-Dec-18 06-Jan-19 38
A2280-1 FOUNDATION WORK (CONCRETE) 0 0% 15 22-Jan-19 07-Feb-19 38
A2280-2 CURING / WATERPROOFING / BACK FILLING 0 0% 13 07-Feb-19 21-Feb-19 38
Structural Steel 29-Oct-18 17-Nov-18 17 76 24-Dec-18 21-Mar-19 44

Page 43 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 31 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
TEST SEPERATOR
SEPERAT 29-Oct-18 05-Nov-18 7 21 26-Feb-19 21-Mar-19 27
A2730 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PL 29-Oct-18 05-Nov-18 7 0% 21 26-Feb-19 21-Mar-19 27
A2730-1 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 0 0% 21 26-Feb-19 21-Mar-19 27
METERING SKID
SK 01-Nov-18 06-Nov-18 5 12 04-Feb-19 17-Feb-19 4
A2740 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK W 01-Nov-18 06-Nov-18 5 0% 12 04-Feb-19 17-Feb-19 4
PSV 05-Nov-18 10-Nov-18 5 11 25-Feb-19 09-Mar-19 38
A2750 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 05-Nov-18 10-Nov-18 5 0% 11 25-Feb-19 09-Mar-19 38
PIPE SUPPORT 11-Nov-18 13-Nov-18 3 28 24-Dec-18 24-Jan-19 92
A2760 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS 11-Nov-18 13-Nov-18 3 0% 28 24-Dec-18 24-Jan-19 0
A2760-1 MODIFICATIONS OF EXISTING PIPE SUPORT / ACCESS PLATFORMS 0 0% 15 24-Dec-18 09-Jan-19 105
FIELD INSTRUMENT
INSTRUM 14-Nov-18 17-Nov-18 3 5 26-Jan-19 30-Jan-19 41
A2770 INSTALLATION OF INSTRUMENT STANCHION 14-Nov-18 17-Nov-18 3 0% 5 26-Jan-19 30-Jan-19 41
Mechanical 11-Oct-18 28-Oct-18 15 4 07-Feb-19 11-Feb-19 3
A2900 INSTALLATION OF NEW TEST SEPARATOR 11-Oct-18 28-Oct-18 15 0% 4 07-Feb-19 11-Feb-19 3
Piping 02-Oct-18 29-Nov-18 51 69 02-Feb-19 22-Apr-19 0
PIPE INSTALATION
INSTALAT & Pre Shutdown WORKS 02-Oct-18 17-Nov-18 40 62 02-Feb-19 14-Apr-19 1
A3230 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 02-Oct-18 17-Oct-18 14 0% 20 02-Feb-19 24-Feb-19 0
A3240 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 29-Oct-18 05-Nov-18 7 0% 6 06-Apr-19 11-Apr-19 3
A3250 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 06-Nov-18 08-Nov-18 3 0% 11 25-Mar-19 06-Apr-19 0
A3260 PIPING TIE-IN / NDT PRE SHUT DOWN 10-Nov-18 17-Nov-18 7 0% 6 08-Apr-19 14-Apr-19 0
A3260-a MOBILIZATION OF OF TEAM APPLY PTW 0 0% 1 06-Apr-19 06-Apr-19 0
A3260-b SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 0% 7 06-Apr-19 13-Apr-19 0
A3230-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 07-Feb-19 17-Feb-19 48
HOT TAPPING 10-Nov-18 29-Nov-18 18 23 11-Mar-19 06-Apr-19 1
HT1160 MOBILIZATION OF HOT TAPPING SUB CONTRACTOR 10-Nov-18 12-Nov-18 3 0% 3 11-Mar-19 13-Mar-19 1
HT1170 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 13-Nov-18 24-Nov-18 10 0% 8 14-Mar-19 23-Mar-19 1
HT1180 HOT TAPPING / NDT 25-Nov-18 27-Nov-18 3 0% 6 24-Mar-19 30-Mar-19 1
HT1190 HOT TAPPING COMPLETE / REMOVE SCAFFOLD 28-Nov-18 29-Nov-18 2 0% 3 03-Apr-19 06-Apr-19 1
Plant Shutdown Tie-in 10-Nov-18 12-Nov-18 3 7 15-Apr-19 22-Apr-19 0
A3261 REPLACE THE SHUTVALVE AT POINT OF OIL-IN TIE-IN / INSTALL SDV 10-Nov-18 12-Nov-18 3 0% 2 21-Apr-19 22-Apr-19 0
A3260-1 PIPING TIE-IN / NDT SHUT DOWN 0 0% 7 15-Apr-19 22-Apr-19 0
Electrical 21-May-18 19-Nov-18 157 93 03-Dec-18 20-Mar-19 4
A3820 CABLE GLANDING AND TERMINATION 21-May-18 05-Jun-18 14 0% 9 21-Feb-19 03-Mar-19 5
A3840 CABLE TRAY INSTALLATION 29-May-18 13-Jun-18 14 0% 13 17-Feb-19 03-Mar-19 4
A3830 U/G CABLE LAYING 06-Jun-18 13-Jun-18 7 0% 9 13-Feb-19 23-Feb-19 5
A3850 ELECTRICAL EQUIPMENTS INSTALLATION 21-Oct-18 28-Oct-18 7 0% 17 21-Feb-19 12-Mar-19 4
A3860 CABLE LAYING 29-Oct-18 05-Nov-18 7 0% 10 20-Feb-19 03-Mar-19 4
A3870 LIGHTING INSTALLATION 29-Oct-18 05-Nov-18 7 0% 7 05-Mar-19 12-Mar-19 4
A3880 ELECTRICAL TIE-INS 06-Nov-18 13-Nov-18 7 0% 3 14-Mar-19 17-Mar-19 4
A3890 ENERGIZATION 14-Nov-18 19-Nov-18 5 0% 4 17-Mar-19 20-Mar-19 4
A3830-1 BACK FILLING OF CABLE TRENCH 0 0% 8 23-Feb-19 03-Mar-19 5
A3890-1 HOOK UP 0 0% 3 12-Mar-19 14-Mar-19 4
A3940 EARTH PIT DRILLING 0 0% 5 19-Jan-19 23-Jan-19 5
A6530 CABLE TRENCHES 0 0% 21 03-Dec-18 26-Dec-18 10
Instrument & Control
Co 13-Oct-18 27-Nov-18 40 40 16-Feb-19 02-Apr-19 2
A4260 CABLE TRAY AND SUPPORT INSTALLATION 13-Oct-18 28-Oct-18 14 0% 16 16-Feb-19 05-Mar-19 2
A4270 INSTRUMENT EQUIPMENT CALIBRATION/ LOOP TEST 29-Oct-18 05-Nov-18 7 0% 4 30-Mar-19 02-Apr-19 2
A4920 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 29-Oct-18 11-Nov-18 12 0% 10 19-Mar-19 30-Mar-19 2
A5000 JB SUPPORT INSTALLATION 31-Oct-18 02-Nov-18 3 0% 3 03-Mar-19 05-Mar-19 2
A5050 CABLE GLANDING AND TERMINATION (ALONG JBs) 04-Nov-18 06-Nov-18 3 0% 10 09-Mar-19 19-Mar-19 2
A4280 INSTRUMENT EQUIPEMNT INSTALLATION (RO, CONTROL VALVE, PRV, SDV 06-Nov-18 13-Nov-18 7 0% 9 11-Mar-19 20-Mar-19 2
A5060 CABLE GLAND AND TERMINATION (ALONG INSTRUMENTS) 06-Nov-18 09-Nov-18 3 0% 6 18-Mar-19 24-Mar-19 4
A4290 INSTRUMENT CABLE LAYING 14-Nov-18 19-Nov-18 5 0% 17 28-Feb-19 19-Mar-19 2
A5340 INSTALLATION OF DELUGE 20-Nov-18 27-Nov-18 7 0% 9 11-Mar-19 20-Mar-19 5
A4290-1 SS TUBE AND LEAK TEST 0 0% 3 19-Mar-19 21-Mar-19 5
A4280-1 INSTALLATION OF INSTRUMENT VALVE 0 0% 3 16-Mar-19 18-Mar-19 3
A4280-2 FIELD INSTRUMENT INSTALLATION (GAUGES & TRANSMITTERS) 0 0% 7 11-Mar-19 18-Mar-19 3

Page 44 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Updated Revised Baseline Schedule. Page 32 of32 29-Nov-18 17:46
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A4280-3 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 3 16-Mar-19 18-Mar-19 3
A5040 JB INSTALLATION 0 0% 3 06-Mar-19 09-Mar-19 2
F&G System 0 25 28-Feb-19 28-Mar-19 21
A6450 F&G SUPPORT INSTALLATION 0 0% 4 02-Mar-19 05-Mar-19 38
A6460 F&G DEVICES INSTALLATION 0 0% 4 05-Mar-19 09-Mar-19 38
A6440 F&G CABLE INSTALLATION 0 0% 9 28-Feb-19 10-Mar-19 37
A6470 F&G JB SUPPORT INSTALLATION 0 0% 2 06-Mar-19 07-Mar-19 39
A6480 F&G JB INSTALLATION 0 0% 2 09-Mar-19 10-Mar-19 37
A6490 F&G CABLE GLANDING AND TERMINATION 0 0% 5 19-Mar-19 24-Mar-19 21
A6500 F&G LOOP PREPARATION 0 0% 2 24-Mar-19 25-Mar-19 21
A6510 F&G LOOP TESTING 0 0% 4 25-Mar-19 28-Mar-19 21
Painting & Fireproofing
Firep 10-Nov-18 03-Dec-18 21 18 19-Mar-19 08-Apr-19 3
A4490 PIPING PAINTING AND TOUCH-UP 10-Nov-18 17-Nov-18 7 0% 9 27-Mar-19 06-Apr-19 4
A4480 STRUCTURAL STEEL PAINTING AND TOUCH-UP 18-Nov-18 25-Nov-18 7 0% 10 19-Mar-19 30-Mar-19 3
A4500 FIREPROOFING FOR STRUCTURAL STEEL 26-Nov-18 03-Dec-18 7 0% 13 25-Mar-19 08-Apr-19 3
Pre-commisionin
Pre-commisioning 10-Nov-18 08-Dec-18 25 173 27-Sep-18 A 14-May-19 0
A4810 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 10-Nov-18 17-Nov-18 7 17% 135 27-Sep-18 A 31-Mar-19 18
A4850 INST LOOP AND FUNCITONAL TESTING 10-Nov-18 08-Dec-18 25 0% 4 23-Apr-19 27-Apr-19 0
A4820 ELECTRICAL LIGHITING TEST 13-Nov-18 15-Nov-18 3 0% 5 28-Apr-19 02-May-19 0
A4830 LEAK TEST FOR SEPARATOR AND PIPING 28-Nov-18 01-Dec-18 3 0% 4 06-May-19 11-May-19 0
A4840 PUNCHLIST 02-Dec-18 04-Dec-18 3 0% 2 12-May-19 14-May-19 0
A4820-1 DELUGE SKID FUNCTIONAL TESTING 0 0% 2 04-May-19 05-May-19 0
Commissioning 08-Dec-18 17-Dec-18 8 7 15-May-19 22-May-19 0
A5250 START OF PRODUCTION 08-Dec-18 3 0% 0 15-May-19 0
A5260 COMMISSIONING AND STARTUP 09-Dec-18 12-Dec-18 3 0% 3 15-May-19 18-May-19 0
A5270 PERFORMANCE TESTS 12-Dec-18 17-Dec-18 7 0% 3 19-May-19 22-May-19 0
As Built and Final Dossier 17-Dec-18 18-Feb-19 54 53 22-May-19 22-Jul-19 0
A5290 FINAL PUNCH LIST AND CLOSE OUT DOCUMENTATION 17-Dec-18 18-Feb-19 54 0% 53 22-May-19 22-Jul-19 0

Page 45 of 170
PROJECT PLANNING PACKAGE

Attachment 2

CRITICAL PATH

Page 46 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Critical Activities TF>5 Page 1 of11 29-Nov-18 17:49
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

Rev-D by TA E
EPIC for Replacement of Old 3-Phase Test Separators at All 27-Sep-17 18-Feb-19 544 290 06-Feb-18 A 22-Jul-19 0

Milestone 08-Oct-18 18-Feb-19 115 152 26-Jan-19 22-Jul-19 0


DE3380 ALL WORKS COMPLETE - MS1 18-Dec-18 0 0% 0 22-May-19* 0
DE1010 ACHIEVED - SCHEDULE COMPLETE 18-Feb-19 0 0% 0 22-Jul-19* 0
Construction 08-Oct-18 08-Dec-18 52 100 26-Jan-19 22-May-19 0
Fahahil Main Tie-ins
Tie 0 0 22-Apr-19 22-Apr-19 0
A1460 SHUTDOWN TIE-INS 0 0% 0 22-Apr-19 0
Commissioninng 08-Oct-18 08-Dec-18 52 100 26-Jan-19 22-May-19 0
A1260 COMPLETE OF COMMISSIONING AT KHATIYAH MAIN 08-Oct-18 0 0% 0 27-Jan-19* 0
A1270 COMPLETE OF COMMISSIONING AT KHATIYAH NORTH 30-Oct-18 0 0% 0 29-Jan-19* 0
A1280 COMPLETE OF COMMISSIONING AT KHATIYAH SOUTH 10-Nov-18 0 0% 0 26-Jan-19* 0
A1290 COMPLETE OF COMMISSIONING AT JALM 17-Nov-18 0 0% 0 06-Apr-19* 0
A1300 COMPLETE OF COMMISSIONING AT FAHAHIL SOUTH 26-Nov-18 0 0% 0 20-May-19* 0
A1320 COMPLETE OF COMMISSIONING AT FAHAHIL MAIN 26-Nov-18 0 0% 0 22-May-19* 0
A1310 COMPLETE OF COMMISSIONING AT FAHAHIL NORTH 08-Dec-18 0 0% 0 09-May-19* 0
Final documentation
documenta & As Built / Handover 18-Feb-19 18-Feb-19 0 0 22-Jul-19 22-Jul-19 0
A1250 FINAL DOCUMENTATION / HANDOVER DOSSIER 18-Feb-19 0 0% 0 22-Jul-19 0
Procurement 27-Sep-17 09-May-18 224 99 23-Feb-18 A 31-Jan-19 0
EQUIPMENTS 27-Sep-17 09-May-18 224 99 23-Feb-18 A 31-Jan-19 0
Safety 27-Sep-17 09-May-18 224 99 23-Feb-18 A 31-Jan-19 0
Fire Fighting Equipments
Eq 27-Sep-17 22-Mar-18 176 64 01-Apr-18 A 27-Dec-18 4
PC1500 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-FIRE FIGHTING EQUIP 27-Sep-17 22-Mar-18 220 90% 64 01-Apr-18 A 27-Dec-18 4
PC1510 DELIVERED AT SITE- FIRE FIGHTING EQUIPMENTS 22-Mar-18 0 0% 0 27-Dec-18 4
Deludge Skid 27-Sep-17 09-May-18 224 99 23-Feb-18 A 31-Jan-19 0
PC1050 MANUFACTURING ( VENDOR DOC, PIM, MANUFAC, SHIP)-DELUDGE SKID 27-Sep-17 09-May-18 280 55% 99 23-Feb-18 A 31-Jan-19 0
PC1060 DELIVERED AT SITE-DELUDGE SKID -1st LOT (Khatiya Stations) 09-May-18 0 0% 0 31-Dec-18 0
CONSTRUCTION WORKS 30-Dec-17 18-Dec-18 380 225 06-Feb-18 A 22-May-19 0
KAHS 01-Feb-18 19-Nov-18 250 80 06-Feb-18 A 26-Jan-19 0
FABRICATION 25-Feb-18 29-Mar-18 29 43 06-Feb-18 A 13-Dec-18 0
Structural Steel Fabrication 26-Feb-18 14-Mar-18 15 14 06-Feb-18 A 10-Nov-18 3
TEST SEPERATOR
SEPERAT 26-Feb-18 11-Mar-18 12 10 16-Aug-18 A 05-Nov-18 0
F220 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CROS 26-Feb-18 11-Mar-18 12 95% 10 16-Aug-18 A 05-Nov-18 0
PIPE SUPPORT 12-Mar-18 14-Mar-18 3 14 06-Feb-18 A 10-Nov-18 3
F230 FAB. OF PIPESUPPORT STRUCTURE TRANSFER TO SITE FOR INSTALLATION 12-Mar-18 14-Mar-18 3 98% 14 06-Feb-18 A 10-Nov-18 3
Piping Fabrication
Fabricati 25-Feb-18 29-Mar-18 29 43 08-Oct-18 A 13-Dec-18 0
FBE PIPING (AT KUWAIT) 25-Feb-18 29-Mar-18 29 43 08-Oct-18 A 13-Dec-18 0
F290 PIPING FABRICATION & FBE COATING AT KUWAIT 25-Feb-18 29-Mar-18 29 0% 34 08-Oct-18 A 03-Dec-18 0
F320-2 FBE PIPING BULK DELIVER AT SITE 0 0% 9 04-Dec-18 13-Dec-18 0
REMAINING PIPING
PI (NON - FBE) 0 26 21-Oct-18 A 24-Nov-18 3
F290-1 COMPLETE PIPING FABRICATION INCL. HYDROTEST/ PAINTING & COATING 0 0% 26 21-Oct-18 A 24-Nov-18 3
INSTALLATION 01-Feb-18 19-Nov-18 250 66 06-Aug-18 A 09-Jan-19 5
Civil Works 27-Oct-18 19-Nov-18 21 66 06-Aug-18 A 09-Jan-19 5
COMMON 27-Oct-18 19-Nov-18 21 66 06-Aug-18 A 09-Jan-19 5
A1790 DRAINAGE PIPE CULVERTS 27-Oct-18 11-Nov-18 14 0% 20 08-Dec-18 30-Dec-18 5
A1780 UTILITY ROAD CROSSINGS 27-Oct-18 19-Nov-18 21 0% 26 11-Dec-18 09-Jan-19 5
A1780-2 CABLE TRENCHES 0 35% 25 24-Sep-18 A 22-Nov-18 2
A1710-1 PROTECTION OF UNDERGROUND CABLES 0 90% 25 14-Sep-18 A 22-Nov-18 5
A1715-6 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPLICAB 0 98% 8 06-Aug-18 A 03-Nov-18 2
Structural Steel 20-Aug-18 27-Aug-18 7 24 27-Sep-18 A 21-Nov-18 0
TEST SEPERATOR
SEPERAT 20-Aug-18 27-Aug-18 7 24 27-Sep-18 A 21-Nov-18 0
A2480 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PLATF 20-Aug-18 27-Aug-18 7 10% 24 27-Sep-18 A 21-Nov-18 0

Primary Baseline 3963-Rev-D.-1 Page 1 of 11 U-3963_REV-D


Date Revision Checked Approved
Actual Work
CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION 29-Nov-18 Critical Path
Remaining Work
Critical Remaining Work Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in
Baseline Milestone Dukhan
Milestone
U3963- Critical Activities TF>5

Page 47 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Critical Activities TF>5 Page 2 of11 29-Nov-18 17:49
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Piping 09-Aug-18 17-Sep-18 34 22 16-Dec-18 09-Jan-19 4
STATION PIPING
PIPIN 09-Aug-18 17-Sep-18 34 22 16-Dec-18 09-Jan-19 4
A3020 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 09-Aug-18 01-Sep-18 20 0% 18 16-Dec-18 05-Jan-19 0
A3030 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 20-Aug-18 26-Aug-18 6 0% 4 06-Jan-19 09-Jan-19 4
A3040 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 02-Sep-18 05-Sep-18 4 0% 12 24-Dec-18 06-Jan-19 3
A3050 TIE-IN 06-Sep-18 17-Sep-18 10 0% 4 06-Jan-19 09-Jan-19 0
A3020-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 24-Dec-18 02-Jan-19 0
A3051-1 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 07-Jan-19 09-Jan-19 3
Electrical 01-Feb-18 13-Oct-18 218 52 08-Nov-18 07-Jan-19 5
A3460 U/G CABLE LAYING 01-Feb-18 08-Feb-18 7 0% 5 29-Nov-18 04-Dec-18 5
A3470 CABLE TRAY INSTALLATION 28-Aug-18 12-Sep-18 14 0% 8 22-Nov-18 01-Dec-18 0
A3480 ELECTRICAL EQUIPMENTS INSTALLATION 13-Sep-18 20-Sep-18 7 0% 10 09-Dec-18 19-Dec-18 5
A3490 CABLE LAYING 22-Sep-18 29-Sep-18 7 0% 8 02-Dec-18 10-Dec-18 5
A3500 LIGHTING FIXTURE AND DB INSTALLATION 22-Sep-18 29-Sep-18 7 0% 8 16-Dec-18 24-Dec-18 5
A3510 ELECTRICAL TIE-INS 30-Sep-18 07-Oct-18 7 0% 2 03-Jan-19 05-Jan-19 5
A3520 ENERGIZATION 08-Oct-18 13-Oct-18 5 0% 3 05-Jan-19 07-Jan-19 5
A3460-1 BACK FILLING OF CABLE TRENCH 0 0% 9 02-Dec-18 11-Dec-18 5
A3510-1 HOOK UP 0 0% 4 25-Dec-18 29-Dec-18 5
A3530 EARTH PIT DRILLING 0 0% 4 08-Nov-18 12-Nov-18 0
Instrument & Control
Co 20-Aug-18 17-Nov-18 77 49 13-Nov-18 08-Jan-19 0
A4090 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 20-Aug-18 02-Sep-18 12 0% 10 25-Dec-18 05-Jan-19 0
A4050 CABLE TRAY AND SUPPORTS INSTALLATION 01-Sep-18 16-Sep-18 14 0% 17 13-Nov-18 02-Dec-18 0
A4060 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TESTING 17-Sep-18 24-Sep-18 7 0% 4 05-Jan-19 08-Jan-19 0
A4070 INSTRUMENT EQUIPEMNT INSTALLATION (RO, SDV, RELIEF VALVE & CONTROL 25-Sep-18 02-Oct-18 7 0% 6 20-Dec-18 26-Dec-18 0
A4080 SS TUBING AND LEAK TEST 03-Oct-18 08-Oct-18 5 0% 4 01-Jan-19 05-Jan-19 0
A5300 INSTALLATION OF DELUGE 09-Oct-18 16-Oct-18 7 0% 7 01-Jan-19 08-Jan-19 0
A4640 JB SUPPORT INSTALLATION 21-Oct-18 23-Oct-18 3 0% 4 02-Dec-18 05-Dec-18 0
A4740 JB INSTALLATION 14-Nov-18 17-Nov-18 3 0% 3 04-Dec-18 06-Dec-18 0
A4080-1 INSTRUMENT CABLE LAYING 0 0% 17 05-Dec-18 24-Dec-18 0
A4080-11 CABLE GLANDS AND TERMINATION (ALONG JBs) 0 0% 10 24-Dec-18 03-Jan-19 0
Painting & Fireproofing
Firep 28-Aug-18 13-Sep-18 15 20 15-Dec-18 06-Jan-19 4
A4360 STRUCTURAL STEEL PAINTING AND TOUCH-UP 28-Aug-18 04-Sep-18 7 0% 12 15-Dec-18 27-Dec-18 4
A4380 FIREPROOFING FOR STRUCTURAL STEEL 05-Sep-18 12-Sep-18 7 0% 16 19-Dec-18 06-Jan-19 4
A4370 PIPING PAINTING AND TOUCH-UP 06-Sep-18 13-Sep-18 7 0% 4 24-Dec-18 27-Dec-18 4
Pre-commisionin
Pre-commisioning 06-Sep-18 25-Oct-18 43 11 06-Jan-19 17-Jan-19 1
A3051 INST LOOP AND FUNCTIONAL TEST 06-Sep-18 09-Sep-18 3 0% 3 06-Jan-19 08-Jan-19 0
A4650 DELUGE SKID FUNCTIONAL TESTING 02-Oct-18 25-Oct-18 21 0% 5 09-Jan-19 14-Jan-19 4
A4620 ELECTRICAL LIGHITING TEST 06-Oct-18 08-Oct-18 3 0% 5 08-Jan-19 13-Jan-19 0
A4630 PUNCHLIST 17-Oct-18 20-Oct-18 3 0% 4 14-Jan-19 17-Jan-19 0
A4620-1 LEAK TEST FOR PIPING AND SEPARATOR 0 0% 5 08-Jan-19 13-Jan-19 0
Commissioning 01-Nov-18 09-Nov-18 7 8 17-Jan-19 26-Jan-19 0
A5010 START OF PRODUCTION 01-Nov-18 3 0% 0 17-Jan-19 0
A5020 COMMISSIONING AND STARTUP 01-Nov-18 04-Nov-18 3 0% 4 17-Jan-19 21-Jan-19 0
A5030 PERFORMANCE TESTS 04-Nov-18 09-Nov-18 7 0% 4 22-Jan-19 26-Jan-19 0
KAHN 24-Jan-18 18-Dec-18 282 83 09-May-18 A 29-Jan-19 0
FABRICATION 24-Jan-18 14-Feb-18 19 38 09-May-18 A 08-Dec-18 3
Structural Steel Fabrication 24-Jan-18 14-Feb-18 19 17 09-May-18 A 13-Nov-18 3
TEST SEPERATOR
SEPERAT 24-Jan-18 10-Feb-18 15 17 19-Sep-18 A 13-Nov-18 3
F110 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CROS 24-Jan-18 10-Feb-18 15 90% 17 19-Sep-18 A 13-Nov-18 3
PIPE SUPPORT 11-Feb-18 14-Feb-18 4 17 09-May-18 A 13-Nov-18 0
F120 COMPLETE FAB. OF PIPESUPPORT STRUCTURE TRANSFER TO SITE FOR INS 11-Feb-18 14-Feb-18 4 99% 17 09-May-18 A 13-Nov-18 0
Piping Fabrication
Fabricati 0 37 27-Oct-18 08-Dec-18 3
REMAINING PIPING
PI ( NON FBE) 0 37 27-Oct-18 08-Dec-18 3
F180-1 COMPLETE PIPING FABRICATION . HYDROTEST/ PAINTING & COATING 0 0% 33 27-Oct-18 03-Dec-18 3
F210-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 13 24-Nov-18 08-Dec-18 3
INSTALLATION 07-Jul-18 18-Dec-18 142 68 02-Oct-18 A 12-Jan-19 3
Structural Steel 16-Jul-18 24-Jul-18 8 47 02-Oct-18 A 18-Dec-18 3
TEST SEPERATOR
SEPERAT 16-Jul-18 23-Jul-18 7 34 02-Oct-18 A 03-Dec-18 3

Page 48 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Critical Activities TF>5 Page 3 of11 29-Nov-18 17:49
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A2360 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PLATF 16-Jul-18 23-Jul-18 7 15% 34 02-Oct-18 A 03-Dec-18 3
METERING SKID
SK 0 37 04-Oct-18 A 06-Dec-18 3
A2360-1 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK WAY O 0 15% 37 04-Oct-18 A 06-Dec-18 3
PIPE SUPPORT 19-Jul-18 24-Jul-18 5 47 11-Oct-18 A 18-Dec-18 0
A2370 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS OF 19-Jul-18 24-Jul-18 5 0% 47 11-Oct-18 A 18-Dec-18 0
FIELD INSTRUMENT
INSTRUM 0 4 15-Dec-18 18-Dec-18 3
A2370-1 INSTALLATION OF INSTRUMENT STANCHION 0 0% 4 15-Dec-18 18-Dec-18 3
Piping 07-Jul-18 21-Aug-18 40 24 10-Dec-18 06-Jan-19 4
PIPING -REMAINING
-REMA 07-Jul-18 21-Aug-18 40 24 10-Dec-18 06-Jan-19 4
A2920 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 07-Jul-18 09-Aug-18 30 0% 17 10-Dec-18 29-Dec-18 0
A2930 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 14-Aug-18 19-Aug-18 5 0% 4 02-Jan-19 06-Jan-19 0
A2950 TIE-IN 14-Aug-18 21-Aug-18 7 0% 4 02-Jan-19 06-Jan-19 0
A2920-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 8 19-Dec-18 27-Dec-18 0
A2951-1 REPLACE THE SHUTVALVET POINT OF OIL-IN TIE-IN / INSTALL SDV 0 0% 3 03-Jan-19 06-Jan-19 4
Electrical 16-Jul-18 08-Sep-18 47 52 13-Nov-18 12-Jan-19 3
A3280 U/G CABLE LAYING 16-Jul-18 23-Jul-18 7 0% 13 06-Dec-18 20-Dec-18 3
A3290 CABLE TRAY INSTALLATION 24-Jul-18 08-Aug-18 14 0% 8 06-Dec-18 15-Dec-18 3
A3300 ELECTRICAL EQUIPMENTS INSTALLATION 09-Aug-18 16-Aug-18 7 0% 12 18-Dec-18 31-Dec-18 3
A3310 CABLE LAYING 18-Aug-18 25-Aug-18 7 0% 17 09-Dec-18 27-Dec-18 3
A3320 LIGHTING FIXTURE AND DB INSTALLATION 18-Aug-18 25-Aug-18 7 0% 6 25-Dec-18 31-Dec-18 3
A3330 ELECTRICAL TIE-INS 26-Aug-18 02-Sep-18 7 0% 5 05-Jan-19 09-Jan-19 3
A3340 ENERGIZATION 03-Sep-18 08-Sep-18 5 0% 3 09-Jan-19 12-Jan-19 3
A3310-1 HOOK UP 0 0% 5 31-Dec-18 05-Jan-19 3
A6000 EARTH PIT DRILLING 0 0% 4 13-Nov-18 17-Nov-18 5
Instrument & Control
Co 28-Jul-18 18-Dec-18 124 40 22-Nov-18 07-Jan-19 3
A3950 CABLE TRAY AND SUPPORTS INSTALLATION 28-Jul-18 12-Aug-18 14 0% 18 22-Nov-18 12-Dec-18 3
A3960 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TESTING 13-Aug-18 20-Aug-18 7 0% 4 02-Jan-19 06-Jan-19 3
A3990 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 14-Aug-18 20-Aug-18 6 0% 9 29-Dec-18 07-Jan-19 3
A3970 INSTRUMENT EQUIPEMNT INSTALLATION (RO, SDV, PRV & CONTROL VALVE) 21-Aug-18 28-Aug-18 7 0% 7 26-Dec-18 02-Jan-19 3
A3980 INSTRUMENT CABLE LAYING 29-Aug-18 03-Sep-18 5 0% 18 11-Dec-18 31-Dec-18 3
A4870 JB INSTALLATION 27-Sep-18 30-Sep-18 3 0% 3 11-Dec-18 13-Dec-18 3
A4790 JB SUPPORT INSTALLATION 16-Dec-18 18-Dec-18 3 0% 3 09-Dec-18 11-Dec-18 3
A3970-1 FIELD INSTRUMENT INSTALLATION (GAUGES / TRANSMITTERS) 0 0% 6 24-Dec-18 30-Dec-18 3
A3970-2 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 3 29-Dec-18 31-Dec-18 4
A3970-11 CABLE GLAND AND TERMINATION (ALONG JBs) 0 0% 4 25-Dec-18 29-Dec-18 3
A3970-21 CABLE GLAND AND TERMINTATION (ALONG INSTRUMENTS) 0 0% 5 27-Dec-18 01-Jan-19 3
F&G System 0 10 27-Dec-18 07-Jan-19 3
A6060 F&G CABLE GLANDING AND TERMINATION 0 0% 5 27-Dec-18 01-Jan-19 3
A6070 F&G LOOP PREPARATION 0 0% 2 01-Jan-19 02-Jan-19 3
A6080 F&G LOOP TESTING 0 0% 4 03-Jan-19 07-Jan-19 3
Pre-commisionin
Pre-commisioning 14-Aug-18 16-Oct-18 55 75 09-Sep-18 A 20-Jan-19 0
A2951 INST LOOP AND FUNCTIONAL TEST 14-Aug-18 16-Aug-18 3 0% 4 02-Jan-19 06-Jan-19 3
A4560 PREPARATION OF PLANS AND PROCEDURES FOR PRECOMMISSIONING 23-Sep-18 30-Sep-18 7 17% 58 09-Sep-18 A 31-Dec-18 4
A4600 ELECTRICAL LIGHTING TEST 23-Sep-18 16-Oct-18 21 0% 5 06-Jan-19 10-Jan-19 0
A4570 LEAK TEST FOR PIPING AND SEPARATOR 30-Sep-18 02-Oct-18 3 0% 4 12-Jan-19 15-Jan-19 0
A4580 PUNCHLIST 03-Oct-18 06-Oct-18 3 0% 4 16-Jan-19 20-Jan-19 0
A4570-1 DELUGE SKID FUNCTIONAL TESTING 0 0% 3 09-Jan-19 12-Jan-19 0
Commissioning 17-Oct-18 30-Oct-18 11 9 20-Jan-19 29-Jan-19 0
A4950 START OF PRODUCTION 17-Oct-18 20-Oct-18 3 0% 1 20-Jan-19 20-Jan-19 0
A4960 COMMISSIONING AND STARTUP 22-Oct-18 24-Oct-18 3 0% 5 20-Jan-19 24-Jan-19 0
A4970 PERFORMANCE TESTS 24-Oct-18 30-Oct-18 7 0% 5 24-Jan-19 29-Jan-19 0
KAHM 30-Dec-17 08-Oct-18 242 81 06-Sep-18 A 27-Jan-19 0
FABRICATION 30-Dec-17 11-Jan-18 12 23 06-Sep-18 A 20-Nov-18 0
Structural Steel Fabrication 30-Dec-17 11-Jan-18 12 23 06-Sep-18 A 20-Nov-18 0
TEST SEPERATOR
SEPERAT 30-Dec-17 11-Jan-18 12 23 06-Sep-18 A 20-Nov-18 0
F0010 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CROS 30-Dec-17 11-Jan-18 12 98% 23 06-Sep-18 A 20-Nov-18 0
INSTALLATION 31-Jan-18 25-Sep-18 204 48 17-Nov-18 10-Jan-19 3
Structural Steel 19-Aug-18 21-Aug-18 3 9 20-Nov-18 29-Nov-18 0

Page 49 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Critical Activities TF>5 Page 4 of11 29-Nov-18 17:49
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
TEST SEPERATOR
SEPERAT 19-Aug-18 21-Aug-18 3 9 20-Nov-18 29-Nov-18 0
A2460 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 19-Aug-18 21-Aug-18 3 0% 9 20-Nov-18 29-Nov-18 0
Electrical 31-Jan-18 25-Sep-18 204 47 17-Nov-18 09-Jan-19 2
A3370 U/G CABLE LAYING 31-Jan-18 08-Feb-18 7 0% 14 28-Nov-18 13-Dec-18 2
A3380 CABLE TRAY INSTALLATION 11-Aug-18 26-Aug-18 14 0% 9 25-Nov-18 04-Dec-18 0
A3390 ELECTRICAL EQUIPMENTS INSTALLATION 27-Aug-18 03-Sep-18 7 0% 12 15-Dec-18 27-Dec-18 2
A3400 CABLE LAYING 04-Sep-18 11-Sep-18 7 0% 15 10-Dec-18 26-Dec-18 2
A3410 LIGHTING FIXTURES AND DB INSTALLATION 04-Sep-18 11-Sep-18 7 0% 6 22-Dec-18 27-Dec-18 2
A3420 ELECTRICAL TIE-INS 12-Sep-18 19-Sep-18 7 0% 4 02-Jan-19 06-Jan-19 2
A3430 ENERGIZATION 20-Sep-18 25-Sep-18 5 0% 3 07-Jan-19 09-Jan-19 2
A3400-1 HOOK UP 0 0% 4 29-Dec-18 01-Jan-19 2
A3440 EARTH PIT DRILLING 0 0% 4 17-Nov-18 20-Nov-18 5
Instrument & Control
Co 02-Aug-18 20-Sep-18 43 40 26-Nov-18 10-Jan-19 0
A4040 MODIFICATION OF EXISTING DCS SYSTEMS BY VENDOR 02-Aug-18 15-Aug-18 12 0% 9 23-Dec-18 01-Jan-19 4
A4000 CABLE TRAY AND SUPPORT INSTALLATION 14-Aug-18 29-Aug-18 14 0% 16 26-Nov-18 13-Dec-18 0
A4010 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TESTING 30-Aug-18 06-Sep-18 7 0% 4 07-Jan-19 10-Jan-19 0
A4020 INSTRUMENT EQUIPEMNT INSTALLATION (RO, SDV, PRV AND CONTROL VALVE 08-Sep-18 15-Sep-18 7 0% 7 25-Dec-18 01-Jan-19 0
A4030 INSTRUMENT CABLE LAYING 16-Sep-18 20-Sep-18 5 0% 18 05-Dec-18 25-Dec-18 0
A4030-1 SS TUBE INSTALLATION AND LEAK TEST 0 0% 4 02-Jan-19 06-Jan-19 0
A4020-3 INSTALLATION OF INSTRUMENT VALVE 0 0% 4 01-Jan-19 05-Jan-19 1
A4020-1 FIELD INSTRUMENT INSTALLATION (GAUGES & TRANSMITTERS) 0 0% 7 25-Dec-18 01-Jan-19 0
A4020-2 INSTALLATION OF BS & W ANALYZERS ON METERING SKID 0 0% 3 30-Dec-18 01-Jan-19 4
A4020-11 CABLE GLAND TERMINATION (ALONG INSRUMENT) 0 0% 6 30-Dec-18 05-Jan-19 3
A4020-21 CABLE GLAND TERMINATION (ALONG JBs) 0 0% 7 30-Dec-18 06-Jan-19 0
F&G System 0 10 31-Dec-18 10-Jan-19 3
A6150 F&G CABLE GLANDING AND TERMINATION 0 0% 5 31-Dec-18 05-Jan-19 3
A6160 F&G LOOP PREPARATION 0 0% 2 05-Jan-19 06-Jan-19 3
A6170 F&G LOOP TESTING 0 0% 4 07-Jan-19 10-Jan-19 3
Pre-commisionin
Pre-commisioning 06-Sep-18 27-Sep-18 19 11 07-Jan-19 19-Jan-19 0
A3001 INST LOOP AND FUNCITONAL TEST 06-Sep-18 09-Sep-18 3 0% 4 07-Jan-19 10-Jan-19 0
A4520 DELUGE SKID FUNCTIONAL TEST 12-Sep-18 15-Sep-18 3 0% 3 12-Jan-19 14-Jan-19 0
A4550 ELECTRICAL LIGHITING TEST 12-Sep-18 27-Sep-18 14 0% 5 09-Jan-19 14-Jan-19 0
A4530 PUNCHLIST 16-Sep-18 18-Sep-18 3 0% 4 15-Jan-19 19-Jan-19 0
A4520-1 LEAK TEST FOR SEPARATOR AND PIPING 0 0% 5 10-Jan-19 15-Jan-19 0
Commissioning 29-Sep-18 08-Oct-18 8 8 19-Jan-19 27-Jan-19 0
A4890 START OF PRODUCTION 29-Sep-18 01-Oct-18 3 0% 2 19-Jan-19 20-Jan-19 0
A4900 COMMISSIONING AND STARTUP 30-Sep-18 02-Oct-18 3 0% 4 19-Jan-19 22-Jan-19 0
A4910 PERFORMANCE TESTS 02-Oct-18 08-Oct-18 7 0% 5 22-Jan-19 27-Jan-19 0
JALM 26-Feb-18 16-Nov-18 282 175 09-Jul-18 A 06-Apr-19 0
FABRICATION 24-Mar-18 14-May-18 45 64 11-Sep-18 A 09-Jan-19 0
Structural Steel Fabrication 24-Mar-18 12-Apr-18 18 48 11-Sep-18 A 22-Dec-18 0
TEST SEPERATOR
SEPERAT 24-Mar-18 05-Apr-18 12 48 11-Sep-18 A 22-Dec-18 0
F330 FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/HR/WW/CROS 24-Mar-18 05-Apr-18 12 40% 48 11-Sep-18 A 22-Dec-18 0
METERING SKID
SK 07-Apr-18 09-Apr-18 3 48 11-Sep-18 A 22-Dec-18 0
F340 FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS. TRANSFER TO 07-Apr-18 09-Apr-18 3 80% 48 11-Sep-18 A 22-Dec-18 0
PSV 10-Apr-18 12-Apr-18 3 48 12-Sep-18 A 22-Dec-18 0
F350 FAB. OF PSV INCL.LADDERS/STAIRS/HR/WW/CROS. STRUCTURE TRANSFER T 10-Apr-18 12-Apr-18 3 20% 48 12-Sep-18 A 22-Dec-18 0
Piping Fabrication
Fabricati 31-Mar-18 14-May-18 39 45 11-Oct-18 A 09-Jan-19 0
FBE PIPING (AT KUWAIT) 31-Mar-18 14-May-18 39 38 11-Oct-18 A 01-Jan-19 0
F400 PIPING FABRICATION & FBE COATING AT KUWAIT 31-Mar-18 30-Apr-18 27 0% 29 11-Oct-18 A 22-Dec-18 0
F430 FBE PIPING BULK DELIVER AT SITE 28-Apr-18 14-May-18 15 0% 9 23-Dec-18 01-Jan-19 0
REMAINING PIPING
PI (NON FBE0 0 37 28-Nov-18 09-Jan-19 0
F400-1 COMPLETE PIPING FABRICATION HYDROTEST/ PAINTING & COATING 0 0% 33 28-Nov-18 05-Jan-19 0
F430-1 FABRICATION SPOOLS DELIVER TO SITE 0 0% 13 26-Dec-18 09-Jan-19 0
INSTALLATION 26-Feb-18 03-Nov-18 269 151 09-Jul-18 A 15-Mar-19 0
Civil Works 0 53 09-Jul-18 A 25-Dec-18 0
COMMOMN 0 24 23-Aug-18 A 21-Nov-18 5
A1845-6 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPLICAB 0 70% 24 23-Aug-18 A 21-Nov-18 5

Page 50 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Critical Activities TF>5 Page 5 of11 29-Nov-18 17:49
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
PIPE SUPPORT 0 53 09-Jul-18 A 25-Dec-18 0
A1845-3 EXCAVATION FOR STRUCTURAL STEEL PIPE SUPPORTS 0 98% 25 03-Aug-18 A 22-Nov-18 0
A1870-1 FOUNDATION WORK (STEEL FIXING) 0 92% 37 09-Jul-18 A 06-Dec-18 0
A1870-2 FOUNDATION WORK (CONCRETE) 0 75% 45 10-Sep-18 A 16-Dec-18 0
A1870-3 CURING / WATERPROOFING / BACK FILLING 0 60% 53 20-Sep-18 A 25-Dec-18 0
Structural Steel 06-Sep-18 25-Sep-18 17 68 07-Oct-18 A 14-Jan-19 2
TEST SEPERATOR
SEPERAT 06-Sep-18 25-Sep-18 17 64 07-Oct-18 A 09-Jan-19 2
A2540 INSTALLATION OF STRUCTURAL STEELWORK OPERATING AND ACCESS PLATF 06-Sep-18 13-Sep-18 7 0% 64 07-Oct-18 A 09-Jan-19 2
A2580 INSTALLATION OF LADDERS, STAIRS, HANDRAILS 23-Sep-18 25-Sep-18 3 0% 8 01-Jan-19 09-Jan-19 2
METERING SKID
SK 10-Sep-18 15-Sep-18 5 12 01-Jan-19 14-Jan-19 2
A2550 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK WAY O 10-Sep-18 15-Sep-18 5 0% 12 01-Jan-19 14-Jan-19 2
PSV 13-Sep-18 18-Sep-18 5 12 01-Jan-19 14-Jan-19 0
A2560 INSTALLATION OF PSV VALVES ACCESS PLATFORMS 13-Sep-18 18-Sep-18 5 0% 12 01-Jan-19 14-Jan-19 0
PIPE SUPPORT 19-Sep-18 22-Sep-18 3 16 27-Dec-18 14-Jan-19 0
A2570 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS OF 19-Sep-18 22-Sep-18 3 0% 16 27-Dec-18 14-Jan-19 0
Piping 27-Aug-18 08-Oct-18 46 79 01-Jan-19 15-Mar-19 0
PIPING -REMAINING
-REMA 27-Aug-18 18-Sep-18 20 32 01-Jan-19 06-Feb-19 4
A3070 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 27-Aug-18 18-Sep-18 20 0% 32 01-Jan-19 06-Feb-19 0
A3070-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 27-Jan-19 05-Feb-19 5
HOT TAPPING 18-Sep-18 08-Oct-18 18 17 10-Feb-19 28-Feb-19 1
HT1080 MOBILIZATION OF HOT TAPPING SUB CONTRACTOR 18-Sep-18 20-Sep-18 3 0% 3 10-Feb-19 12-Feb-19 1
HT1090 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 22-Sep-18 02-Oct-18 10 0% 7 12-Feb-19 19-Feb-19 1
HT1100 FLARE TAPPING / NDT 03-Oct-18 06-Oct-18 3 0% 9 19-Feb-19 28-Feb-19 1
HT1110 FLARE TAPPING COMPLETE / REMOVE SCAFFOLD 07-Oct-18 08-Oct-18 2 0% 5 24-Feb-19 28-Feb-19 1
Pre Shutdown and Plant Shutdown Tie-in 0 24 21-Feb-19 15-Mar-19 0
A3100-2 MOBILIZATION OF OF TEAM APPLY PTW 0 0% 2 04-Mar-19 05-Mar-19 0
A3100-3 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 0% 6 05-Mar-19 11-Mar-19 0
A3100-4 PIPING TIE-IN / NDT PRE SHUT DOWN 0 0% 7 21-Feb-19 28-Feb-19 0
A3100-5 PIPING TIE-IN / NDT SHUT DOWN 0 0% 11 05-Mar-19 15-Mar-19 0
Electrical 26-Feb-18 30-Oct-18 212 84 25-Nov-18 02-Mar-19 2
A3540 CABLE GLAND AND TERMINATION 26-Feb-18 13-Mar-18 14 0% 10 05-Feb-19 16-Feb-19 5
A3550 U/G CABLE LAYING 14-Mar-18 21-Mar-18 7 0% 13 12-Jan-19 26-Jan-19 4
A3560 CABLE TRAY INSTALLATION 15-Sep-18 30-Sep-18 14 0% 8 10-Jan-19 19-Jan-19 2
A3570 ELECTRICAL EQUIPMENTS INSTALLATION 01-Oct-18 08-Oct-18 7 0% 12 03-Feb-19 16-Feb-19 2
A3580 CABLE LAYING 09-Oct-18 16-Oct-18 7 0% 20 15-Jan-19 06-Feb-19 2
A3590 LIGHTING FIXTURES AND DB INSTALLATION 09-Oct-18 16-Oct-18 7 0% 6 10-Feb-19 16-Feb-19 2
A3600 ELECTRICAL TIE-INS 17-Oct-18 24-Oct-18 7 0% 6 20-Feb-19 26-Feb-19 2
A3610 ENERGIZATION 25-Oct-18 30-Oct-18 5 0% 4 26-Feb-19 02-Mar-19 2
A3580-1 HOOK UP 0 0% 4 17-Feb-19 20-Feb-19 2
A3550-1 BACK FILLING OF CABLE TRENCH 0 0% 13 26-Jan-19 09-Feb-19 4
A6180 CABLE TRENCHES 0 0% 25 25-Nov-18 23-Dec-18 5
A6190 EARTH PIT DRILLING 0 0% 6 04-Dec-18 10-Dec-18 5
Instrument & Control
Co 06-Sep-18 03-Nov-18 50 55 29-Dec-18 02-Mar-19 0
A4140 DCS MODIFICATION IN CONTROL ROOM BY VENDOR 06-Sep-18 12-Sep-18 6 0% 5 20-Feb-19 25-Feb-19 4
A4100 CABLE TRAY AND SUPPORTS INSTALLATION 18-Sep-18 03-Oct-18 14 0% 17 29-Dec-18 16-Jan-19 3
A4540 JB SUPPORT INSTALLATION 19-Sep-18 22-Sep-18 3 0% 3 16-Jan-19 19-Jan-19 3
A4880 JB INSTALLATION 28-Sep-18 01-Oct-18 3 0% 3 20-Jan-19 22-Jan-19 3
A4110 INSTRUMENT EQUIPMENT CALIBRATION / LOOP TEST 04-Oct-18 11-Oct-18 7 0% 5 25-Feb-19 02-Mar-19 0
A4120 INSTRUMENT EQUIPEMNT INSTALLATION 13-Oct-18 20-Oct-18 7 0% 20 24-Jan-19 16-Feb-19 4
A4130 INSTRUMENT CABLE LAYING 21-Oct-18 25-Oct-18 5 0% 18 12-Jan-19 31-Jan-19 4
A5310 INSTALLATION OF DELUGE 27-Oct-18 03-Nov-18 7 0% 8 12-Feb-19 20-Feb-19 3
A4130-1 SS TUBE AND LEAK TEST 0 0% 4 21-Feb-19 25-Feb-19 3
A4120-2 INSTALLATION OF INSTRUMENT VALVE 0 0% 5 19-Feb-19 24-Feb-19 0
A4120-1 FIELD INSTRUMENT INSTALLATION (GAUGES / TRANSMITTERS) 0 0% 18 30-Jan-19 19-Feb-19 4
A4120-11 CABLE GLANDING AND TERMINATION (ALONG JBs) 0 0% 6 31-Jan-19 06-Feb-19 3
A4120-21 CABLE GLANDING AND TERMINATION (ALONG INTSTRUMENTS) 0 0% 6 19-Feb-19 25-Feb-19 4
Painting & Fireproofing
Firep 15-Sep-18 30-Sep-18 14 17 06-Feb-19 25-Feb-19 5

Page 51 of 170
Rev-D by TA EPIC for Replacement of Old 3-Phase Test Separators at All Degassing Stations in Dukhan U3963- Critical Activities TF>5 Page 6 of11 29-Nov-18 17:49
Activity ID Activity Name BL1 Start BL1 Finish BL1 Duration Phy. % Com. OD Act.Start / F-C Start Act. Fin / F-C Fin TF 2017 2018 2019
F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
A4390 STRUCTURAL STEEL PAINTING AND TOUCH-UP 15-Sep-18 22-Sep-18 7 0% 13 06-Feb-19 20-Feb-19 5
A4400 PIPING PAINTING AND TOUCH-UP 17-Sep-18 24-Sep-18 7 0% 13 06-Feb-19 20-Feb-19 5
A4410 FIREPROOFING FOR STRUCTURAL STEEL 23-Sep-18 30-Sep-18 7 0% 17 06-Feb-19 25-Feb-19 5
Pre-commisionin
Pre-commisioning 17-Sep-18 10-Nov-18 47 11 13-Mar-19 25-Mar-19 0
A3101 INST LOOP AND FUNCTIONAL TESTING 17-Sep-18 19-Sep-18 3 0% 3 13-Mar-19 16-Mar-19 0
A4700 ELECTRICAL LIGHITNG TEST 29-Sep-18 01-Nov-18 30 0% 5 19-Mar-19 24-Mar-19 0
A4670 DELUGE SKID FUNCTIONAL TESTING 02-Oct-18 04-Oct-18 3 0% 5 19-Mar-19 24-Mar-19 0
A4680 LEAK TEST FOR SEPARATOR AND PIPING 04-Nov-18 06-Nov-18 3 0% 3 21-Mar-19 24-Mar-19 0
A4690 PUNCHLIST 07-Nov-18 10-Nov-18 3 0% 4 21-Mar-19 25-Mar-19 0
Commissioning 07-Nov-18 16-Nov-18 8 11 25-Mar-19 06-Apr-19 0
A5070 START OF PRODUCTION 07-Nov-18 3 0% 0 25-Mar-19 0
A5080 COMMISSIONING AND STARTUP 08-Nov-18 10-Nov-18 3 0% 4 26-Mar-19 30-Mar-19 0
A5090 PERFORMANCE TESTS 10-Nov-18 16-Nov-18 7 0% 6 31-Mar-19 06-Apr-19 0
FAHS 18-Apr-18 26-Nov-18 191 178 05-Sep-18 A 20-May-19 0
FABRICATION 18-Apr-18 14-Jun-18 50 56 09-Sep-18 A 29-Dec-18 4
Structural Steel Fabrication 18-Apr-18 17-May-18 26 56 09-Sep-18 A 29-Dec-18 4
TEST SEPERATOR
SEPERAT 18-Apr-18 03-May-18 14 56 11-Sep-18 A 29-Dec-18 4
F440 COMPLETE FAB. OF SEPERATOR & PLATFORM STR. INCL.LADDERS/STAIRS/H 18-Apr-18 03-May-18 14 50% 56 11-Sep-18 A 29-Dec-18 4
METERING SKID
SK 05-May-18 08-May-18 4 56 09-Sep-18 A 29-Dec-18 4
F450 COMPLETE SS FAB. OF METERING SKID INCL.LADDERS/STAIRS/HR/WW/CROS 05-May-18 08-May-18 4 80% 56 09-Sep-18 A 29-Dec-18 4
PIPE SUPPORT 14-May-18 17-May-18 4 48 12-Sep-18 A 19-Dec-18 4
F470 COMPLETE FAB. OF PIPESUPPORT STRUCTURE BY PETROSERV & TRANSFE 14-May-18 17-May-18 4 40% 48 12-Sep-18 A 19-Dec-18 4
Piping Fabrication
Fabricati 01-May-18 14-Jun-18 39 47 11-Oct-18 A 25-Dec-18 3
FBE PIPING (AT KUWAIT) 01-May-18 14-Jun-18 39 47 11-Oct-18 A 25-Dec-18 3
F510 PIPING FABRICATION & FBE COATING AT KUWAIT 01-May-18 27-May-18 23 0% 39 11-Oct-18 A 16-Dec-18 3
F540 FBE PIPING BULK DELIVER AT SITE 29-May-18 14-Jun-18 15 0% 8 17-Dec-18 25-Dec-18 3
INSTALLATION 09-May-18 18-Nov-18 166 175 05-Sep-18 A 16-May-19 0
Civil Works 27-Jun-18 18-Nov-18 124 175 05-Sep-18 A 16-May-19 0
COMMOMN 27-Jun-18 18-Nov-18 124 175 05-Sep-18 A 16-May-19 0
A2030 CABLE TRENCHES AND UTILITY ROAD CROSSINGS 27-Jun-18 21-Jul-18 21 35% 40 10-Sep-18 A 10-Dec-18 0
A2020 ROADS AND PAVING(INCLUDING MODIFICATIONS) 25-Oct-18 10-Nov-18 14 0% 14 04-Apr-19 20-Apr-19 0
A2040 DRAINAGE PIPE CULVERTS 25-Oct-18 10-Nov-18 14 0% 36 11-Dec-18 21-Jan-19 0
A2050 ROAD SAFETY CRASH BARRIERS AND BOLLARD 25-Oct-18 18-Nov-18 21 0% 13 18-Apr-19 02-May-19 0
A2080 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) 07-Nov-18 10-Nov-18 3 0% 13 02-May-19 16-May-19 0
A1960-1 PROTECTION OF UNDERGROUND CABLES 0 90% 4 10-Sep-18 A 10-Dec-18 0
A1965-5 SOAKWAY PIT EXCAVATION & INSTALLATION INCL. DEMOLITION - IF APPLICAB 0 55% 40 05-Sep-18 A 10-Dec-18 0
Structural Steel 27-Sep-18 09-Oct-18 11 38 20-Dec-18 02-Feb-19 4
METERING SKID
SK 27-Sep-18 02-Oct-18 5 18 31-Dec-18 20-Jan-19 4
A2610 INSTALLATION OF STRUCTURAL STEEL OF METERING SKID INCL. WALK WAY O 27-Sep-18 02-Oct-18 5 0% 18 31-Dec-18 20-Jan-19 4
PIPE SUPPORT 07-Oct-18 09-Oct-18 3 28 20-Dec-18 21-Jan-19 4
A2630 INSTALLATION OF STRUCTURAL STEEL PIPE SUPPORTS & MODIFICATIONS OF 07-Oct-18 09-Oct-18 3 0% 28 20-Dec-18 21-Jan-19 4
FIELD INSTRUMENT
INSTRUM 0 5 28-Jan-19 02-Feb-19 4
A2630-1 INSTALLATION OF INSTRUMENT STANCHION 0 0% 5 28-Jan-19 02-Feb-19 4
Piping 15-Sep-18 25-Oct-18 36 104 23-Dec-18 22-Apr-19 4
PIPING -REMAINING
-REMA 15-Sep-18 11-Oct-18 24 45 23-Dec-18 12-Feb-19 4
A3120 PIPING INSTALLATION ON PIPE SUPPORT,PIERACK & AROUND EQUIPMENT 15-Sep-18 01-Oct-18 15 0% 37 23-Dec-18 03-Feb-19 3
A3130 INLET PIPING TIE-IN TO SEPARATOR (PARTIAL SHUTDOWN TIE-IN) 24-Sep-18 30-Sep-18 6 0% 5 29-Jan-19 03-Feb-19 4
A3140 HYDRO-TESTING, FLUSHING, DRAINING AND PURGING 01-Oct-18 03-Oct-18 3 0% 13 29-Jan-19 12-Feb-19 4
A3150 TIE-IN 04-Oct-18 11-Oct-18 7 0% 5 29-Jan-19 03-Feb-19 4
A3120-1 INSTALLATION OF BALL VALVE & GGC VALVE 0 0% 9 15-Jan-19 24-Jan-19 4
HOT TAPPING 06-Oct-18 25-Oct-18 18 46 28-Feb-19 22-Apr-19 4
HT1120 MOBILIZATION OF HOT TAPPING SUB CONTRACTOR 06-Oct-18 08-Oct-18 3 0% 3 28-Feb-19 03-Mar-19 4
HT1130 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 09-Oct-18 20-Oct-18 10 0% 9 03-Mar-19 12-Mar-19 4
HT1140 FLARE TIE-IN / NDT 21-Oct-18 23-Oct-18 3 0% 13 13-Mar-19 27-Mar-19 4
HT1150 HOT TIE-IN COMPLETE / REMOVE SCAFFOLD 24-Oct-18 25-Oct-18 2 0% 12 09-Apr-19 22-Apr-19 4
Pre Shutdown and Plant Shutdown Tie-in 0 21 30-Mar-19 22-Apr-19 4
A3150-000 MOBILIZATION OF OF TEAM APPLY PTW 0 0% 1 30-Mar-19 30-Mar-19 4
A3150-00 SCAFFOLDING / PLATE FORM / WORK PERMIT ISSUE 0 0% 8 31-Mar-19 08-Apr-19 4

Page 52 of 170
PROJECT PLANNING PACKAGE

Attachment 3

JALEHA SHUTDOWN SCHEDULE

Page 53 of 170
TIE-IN SCHEDULE - (JALM) TIE-IN SCHEDULE - (JALM) Page 1 of5 29-Nov-18 13:39
Activity ID Activity Name OD Act. Fin / F-C Fin Act.Start / F-C Start 2017 2018 2019
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

TIE-IN SCHEDULE
SCHED - (JALM) 537.00 20-Mar-19 08:00 14-Feb-19 17:00

JALM - 19 TIE-IN 537.00 20-Mar-19 08:00 14-Feb-19 17:00


PRE-SHUTDOWN TIE-IN - 07 TIE-IN 250.00 02-Mar-19 09:00 14-Feb-19 17:00
COMMON 96.00 20-Feb-19 17:00 14-Feb-19 17:00
SD-JL-10021 CO-ORDINATE LEVEL CHECK FOR PIPING SUPPORT & SPOOLS 0.00 14-Feb-19 17:00*
SD-JL-10001 THICKNESS / LAMINATION CHECK FOR TIE-IN POINTS 40.00 20-Feb-19 17:00 17-Feb-19 07:00
JM01-6"-P12134
JM01-6"-P12134-CS1-900-4 PSD (01 JOINT) 50.00 23-Feb-19 21:00 20-Feb-19 17:00
SD-JL-34030 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 20-Feb-19 19:00 20-Feb-19 17:00
SD-JL-34040 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 21-Feb-19 01:00 20-Feb-19 19:00
SD-JL-33960 FLUSHING & PURGING 6.00 21-Feb-19 07:00 21-Feb-19 01:00
SD-JL-33970 PIPE CUTTING AND INSPECTION BY QC 8.00 21-Feb-19 15:00 21-Feb-19 07:00
SD-JL-33980 FITUP, WELDING PIPING SPOOL & PWHT 20.00 22-Feb-19 11:00 21-Feb-19 15:00
SD-JL-33990 NDT - APPROVED 4.00 22-Feb-19 15:00 22-Feb-19 11:00
SD-JL-34050 VALVE INSTALLATION 10.00 23-Feb-19 05:00 22-Feb-19 15:00
SD-JL-34060 DE-BLINDING 6.00 23-Feb-19 15:00 23-Feb-19 05:00
SD-JL-34020 FINAL TOUCH UP AND QC INSPECTION 6.00 23-Feb-19 21:00 23-Feb-19 15:00
SD-JL-34110 HANDOVER TO OPERATION 0.00 23-Feb-19 21:00
JM02-31-0875-3"
JM02-31-0875-3"-OD-CS1-300-4 PSD (02 JOINTS) 57.00 25-Feb-19 03:00 21-Feb-19 13:00
SD-JL-34140 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 21-Feb-19 15:00 21-Feb-19 13:00
SD-JL-34150 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 21-Feb-19 21:00 21-Feb-19 15:00
SD-JL-34070 FLUSHING & PURGING 6.00 22-Feb-19 03:00 21-Feb-19 21:00
SD-JL-34080 PIPE CUTTING AND INSPECTION BY QC 8.00 22-Feb-19 11:00 22-Feb-19 03:00
SD-JL-34090 FITUP, WELDING PIPING SPOOL & PWHT 20.00 23-Feb-19 07:00 22-Feb-19 11:00
SD-JL-34100 NDT - APPROVED 14.00 23-Feb-19 21:00 23-Feb-19 07:00
SD-JL-35960 VALVE INSTALLATION 10.00 24-Feb-19 11:00 23-Feb-19 21:00
SD-JL-35970 DE-BLINDING 6.00 24-Feb-19 21:00 24-Feb-19 11:00
SD-JL-35980 FINAL TOUCH UP AND QC INSPECTION 6.00 25-Feb-19 03:00 24-Feb-19 21:00
SD-JL-35990 HANDOVER TO OPERATION 0.00 25-Feb-19 03:00
JM02A-31-0330-3
JM02A-31-0330-3"-OD-L3-300-1 PSD (01 JOINT) 58.00 25-Feb-19 23:00 22-Feb-19 09:00
SD-JL-34340 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 22-Feb-19 11:00 22-Feb-19 09:00
SD-JL-34350 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 22-Feb-19 17:00 22-Feb-19 11:00
SD-JL-34270 FLUSHING & PURGING 6.00 22-Feb-19 23:00 22-Feb-19 17:00
SD-JL-34280 PIPE CUTTING AND INSPECTION BY QC 8.00 23-Feb-19 07:00 22-Feb-19 23:00
SD-JL-34290 FITUP, WELDING PIPING SPOOL & PWHT 20.00 24-Feb-19 03:00 23-Feb-19 07:00
SD-JL-34300 NDT - APPROVED 14.00 24-Feb-19 17:00 24-Feb-19 03:00
SD-JL-36000 VALVE INSTALLATION 10.00 25-Feb-19 09:00 24-Feb-19 17:00
SD-JL-36010 DE-BLINDING 6.00 25-Feb-19 17:00 25-Feb-19 09:00
SD-JL-36020 FINAL TOUCH UP AND QC INSPECTION 6.00 25-Feb-19 23:00 25-Feb-19 17:00
SD-JL-36030 HANDOVER TO OPERATION 0.00 25-Feb-19 23:00
JM16A-2"-A1101
JM16A-2"-A11016-CS1-150-4 PSD (THD JOINT) 49.00 26-Feb-19 10:00 23-Feb-19 09:00
SD-JL-35640 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 23-Feb-19 11:00 23-Feb-19 09:00
SD-JL-35650 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 5.00 23-Feb-19 16:00 23-Feb-19 11:00
SD-JL-35580 PIPE, CUTTING AND INSPECTION BY QC 6.00 24-Feb-19 03:00 23-Feb-19 21:00
SD-JL-35590 THREADED JOINT AND SEAL 22.00 25-Feb-19 01:00 24-Feb-19 03:00
SD-JL-35600 QC INSPECTION 3.00 25-Feb-19 04:00 25-Feb-19 01:00
SD-JL-36040 VALVE INSTALLATION 10.00 25-Feb-19 18:00 25-Feb-19 04:00
SD-JL-36060 FINAL TOUCH UP AND QC INSPECTION 6.00 26-Feb-19 10:00 26-Feb-19 04:00
SD-JL-36070 HANDOVER TO OPERATION 0.00 26-Feb-19 10:00
JM16B-2"-A1101
JM16B-2"-A11016-CS1-150-4 PSD (THD JOINT) 48.00 27-Feb-19 08:00 24-Feb-19 07:00
SD-JL-35740 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 24-Feb-19 09:00 24-Feb-19 07:00

Remaining Work P3963-JMT Page 1 of 5 Rev-D


Date Revision Checked Approved
Critical Remaining Work
CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION 29-Nov-18 Jaleha Shutdown Schedule for QP aprro
Milestone
TIE-IN SCHEDULE - (JALM)

TIE-IN SCHEDULE - (JALM)

Page 54 of 170
TIE-IN SCHEDULE - (JALM) TIE-IN SCHEDULE - (JALM) Page 2 of5 29-Nov-18 13:39
Activity ID Activity Name OD Act. Fin / F-C Fin Act.Start / F-C Start 2017 2018 2019
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
SD-JL-35750 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 5.00 24-Feb-19 14:00 24-Feb-19 09:00
SD-JL-35680 PIPE CUTTING AND INSPECTION BY QC 6.00 25-Feb-19 01:00 24-Feb-19 19:00
SD-JL-35690 THREADED JOINT AND SEAL 22.00 25-Feb-19 23:00 25-Feb-19 01:00
SD-JL-35700 QC INSPECTION 3.00 26-Feb-19 02:00 25-Feb-19 23:00
SD-JL-36080 VALVE INSTALLATION 10.00 26-Feb-19 16:00 26-Feb-19 02:00
SD-JL-36100 FINAL TOUCH UP AND QC INSPECTION 6.00 27-Feb-19 08:00 27-Feb-19 02:00
SD-JL-36110 HANDOVER TO OPERATION 0.00 27-Feb-19 08:00
JM17A/B-6"-P121
JM17A/B-6"-P12134-CS1-900-4X PSD (SD VALVE REPLACEMENT) 43.00 28-Feb-19 11:00 25-Feb-19 19:00
SD-JL-35840 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 25-Feb-19 21:00 25-Feb-19 19:00
SD-JL-35850 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 26-Feb-19 03:00 25-Feb-19 21:00
SD-JL-35770 CABLE ISOLATION AND REMOVAL OF CABLE 6.00 26-Feb-19 09:00 26-Feb-19 03:00
SD-JL-35780 EXISTING VALVE REMOVAL 12.00 26-Feb-19 21:00 26-Feb-19 09:00
SD-JL-35790 VALVE INSTALLATION 18.00 27-Feb-19 15:00 26-Feb-19 21:00
SD-JL-35800 QC INSPECTION 6.00 27-Feb-19 21:00 27-Feb-19 15:00
SD-JL-36130 GLANDING AND TERMINATION OF CABLE 6.00 28-Feb-19 05:00 27-Feb-19 21:00
SD-JL-36140 LOOP TESTING 6.00 28-Feb-19 11:00 28-Feb-19 05:00
SD-JL-36150 HANDOVER TO OPERATION 0.00 28-Feb-19 11:00
JM18-6"-WF-31-0
JM18-6"-WF-31-0774-CS1-150-4 PSD (02 JOINTS) 50.00 02-Mar-19 09:00 27-Feb-19 05:00
SD-JL-35940 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 27-Feb-19 07:00 27-Feb-19 05:00
SD-JL-35950 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 27-Feb-19 13:00 27-Feb-19 07:00
SD-JL-35870 FLUSHING & PURGING 6.00 27-Feb-19 19:00 27-Feb-19 13:00
SD-JL-35880 PIPE CUTTING AND INSPECTION BY QC 8.00 28-Feb-19 03:00 27-Feb-19 19:00
SD-JL-35890 FITUP, WELDING PIPING SPOOL & PWHT 18.00 28-Feb-19 21:00 28-Feb-19 03:00
SD-JL-35900 NDT - APPROVED 6.00 01-Mar-19 03:00 28-Feb-19 21:00
SD-JL-36160 VALVE INSTALLATION 10.00 01-Mar-19 17:00 01-Mar-19 03:00
SD-JL-36170 DE-BLINDING 6.00 02-Mar-19 03:00 01-Mar-19 17:00
SD-JL-36180 FINAL TOUCH UP AND QC INSPECTION 6.00 02-Mar-19 09:00 02-Mar-19 03:00
SD-JL-36190 HANDOVER TO OPERATION 0.00 02-Mar-19 09:00
SHUTDOWN TIE-IN
TIE - 12 TIE-IN 199.00 15-Mar-19 14:00 03-Mar-19 03:00
PLANT SHUTDOWN
SHUTDOW 30.00 04-Mar-19 23:00 03-Mar-19 03:00
SD-JL-10000 PLANT SHUTDOWN AND DE-CONTAMINATION 30.00 04-Mar-19 23:00 03-Mar-19 03:00
TIE-INS 164.00 15-Mar-19 14:00 05-Mar-19 06:00
JM03-3"-WD-31-0244-CS1-900-8 (01 JOINT)
JM03-3"-WD-31 43.00 08-Mar-19 01:00 05-Mar-19 06:00
SD-JL-34440 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 05-Mar-19 08:00 05-Mar-19 06:00*
SD-JL-34450 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 8.00 05-Mar-19 16:00 05-Mar-19 08:00
SD-JL-34370 FLUSHING & PURGING 6.00 05-Mar-19 22:00 05-Mar-19 16:00
SD-JL-34380 PIPE CUTTING AND INSPECTION BY QC 10.00 06-Mar-19 08:00 05-Mar-19 22:00
SD-JL-34390 FITUP, WELDING PIPING SPOOL & PWHT 12.00 06-Mar-19 10:00 05-Mar-19 22:00
SD-JL-34400 NDT - APPROVED 6.00 06-Mar-19 16:00 06-Mar-19 10:00
SD-JL-36200 VALVE INSTALLATION 12.00 07-Mar-19 10:00 06-Mar-19 16:00
SD-JL-36210 DE-BLINDING 6.00 07-Mar-19 18:00 07-Mar-19 10:00
SD-JL-36220 FINAL TOUCH UP AND QC INSPECTION 6.00 08-Mar-19 00:00 07-Mar-19 18:00
SD-JL-36230 HANDOVER TO OPERATION 0.00 08-Mar-19 01:00
JM06A/B-16"-W
JM06A/B-16"-WD-31-0636-L3-300-1 (02 JOINTS) 74.00 09-Mar-19 22:00 05-Mar-19 08:00
SD-JL-34840 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 05-Mar-19 10:00 05-Mar-19 08:00
SD-JL-34850 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 24.00 06-Mar-19 10:00 05-Mar-19 10:00
SD-JL-34770 FLUSHING & PURGING 10.00 06-Mar-19 20:00 06-Mar-19 10:00
SD-JL-34780 PIPE CUTTING AND INSPECTION BY QC 14.00 07-Mar-19 10:00 06-Mar-19 20:00
SD-JL-34790 FITUP, WELDING PIPING SPOOL & PWHT 18.00 08-Mar-19 04:00 07-Mar-19 10:00
SD-JL-34800 NDT - APPROVED 10.00 08-Mar-19 14:00 08-Mar-19 04:00
SD-JL-36280 VALVE INSTALLATION 10.00 09-Mar-19 04:00 08-Mar-19 14:00
SD-JL-36290 DE-BLINDING 8.00 09-Mar-19 16:00 09-Mar-19 04:00
SD-JL-36300 FINAL TOUCH UP AND QC INSPECTION 6.00 09-Mar-19 22:00 09-Mar-19 16:00
SD-JL-36310 HANDOVER TO OPERATION 0.00 09-Mar-19 22:00
JM12A-8"-GV-31
JM12A-8"-GV-31-1409-CS1-150-8 (01 JOINT) 66.00 11-Mar-19 16:00 07-Mar-19 14:00
SD-JL-34240 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 07-Mar-19 16:00 07-Mar-19 14:00
SD-JL-34250 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 12.00 08-Mar-19 04:00 07-Mar-19 16:00

Page 55 of 170
TIE-IN SCHEDULE - (JALM) TIE-IN SCHEDULE - (JALM) Page 3 of5 29-Nov-18 13:39
Activity ID Activity Name OD Act. Fin / F-C Fin Act.Start / F-C Start 2017 2018 2019
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
SD-JL-34170 FLUSHING & PURGING 8.00 08-Mar-19 12:00 08-Mar-19 04:00
SD-JL-34180 PIPE CUTTING AND INSPECTION BY QC 16.00 09-Mar-19 04:00 08-Mar-19 12:00
SD-JL-34190 FITUP, WELDING PIPING SPOOL & PWHT 18.00 09-Mar-19 22:00 09-Mar-19 04:00
SD-JL-34200 NDT - APPROVED 8.00 10-Mar-19 06:00 09-Mar-19 22:00
SD-JL-36320 VALVE INSTALLATION 12.00 11-Mar-19 02:00 10-Mar-19 08:00
SD-JL-36330 DE-BLINDING 6.00 11-Mar-19 10:00 11-Mar-19 02:00
SD-JL-36340 FINAL TOUCH UP AND QC INSPECTION 6.00 11-Mar-19 16:00 11-Mar-19 10:00
SD-JL-36350 HANDOVER TO OPERATION 0.00 11-Mar-19 16:00
JM12B-30"-GV-3
JM12B-30"-GV-31-1400-CS1-150-8 (02 JOINTS) 132.00 15-Mar-19 14:00 07-Mar-19 06:00
SD-JL-35440 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 07-Mar-19 08:00 07-Mar-19 06:00
SD-JL-35450 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 34.00 08-Mar-19 18:00 07-Mar-19 08:00
SD-JL-35370 FLUSHING & PURGING 16.00 09-Mar-19 10:00 08-Mar-19 18:00
SD-JL-35380 PIPE CUTTING AND INSPECTION BY QC 36.00 10-Mar-19 22:00 09-Mar-19 10:00
SD-JL-35390 FITUP WELDING PIPING SPOOL & PWHT 48.00 12-Mar-19 22:00 10-Mar-19 22:00
SD-JL-35400 NDT - APPROVED 12.00 13-Mar-19 10:00 12-Mar-19 22:00
SD-JL-36360 VALVE INSTALLATION 18.00 14-Mar-19 12:00 13-Mar-19 10:00
SD-JL-36370 DE-BLINDING 12.00 15-Mar-19 06:00 14-Mar-19 14:00
SD-JL-36380 FINAL TOUCH UP AND QC INSPECTION 8.00 15-Mar-19 14:00 15-Mar-19 06:00
SD-JL-36390 HANDOVER TO OPERATION 0.00 15-Mar-19 14:00
JM04-3"-OC-31-
JM04-3"-OC-31-0266-CS1-900-8 (01 JOINT) 47.00 08-Mar-19 05:00 05-Mar-19 06:00
SD-JL-34540 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 05-Mar-19 08:00 05-Mar-19 06:00*
SD-JL-34550 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 8.00 05-Mar-19 16:00 05-Mar-19 08:00
SD-JL-34470 FLUSHING & PURGING 6.00 05-Mar-19 22:00 05-Mar-19 16:00
SD-JL-34480 PIPE CUTTING AND INSPECTION BY QC 10.00 06-Mar-19 08:00 05-Mar-19 22:00
SD-JL-34490 FITUP, WELDING PIPING SPOOL & PWHT 12.00 06-Mar-19 20:00 06-Mar-19 08:00
SD-JL-34500 NDT - APPROVED 3.00 06-Mar-19 23:00 06-Mar-19 20:00
SD-JL-36240 VALVE INSTALLATION 10.00 07-Mar-19 15:00 07-Mar-19 01:00
SD-JL-36250 DE-BLINDING 6.00 07-Mar-19 23:00 07-Mar-19 15:00
SD-JL-36260 FINAL TOUCH UP AND QC INSPECTION 6.00 08-Mar-19 05:00 07-Mar-19 23:00
SD-JL-36270 HANDOVER TO OPERATION 0.00 08-Mar-19 05:00
JM05A-4"-P1102
JM05A-4"-P11021-CS1-300-4 (01 JOINT) 50.00 09-Mar-19 18:00 06-Mar-19 16:00
SD-JL-34640 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 06-Mar-19 18:00 06-Mar-19 16:00
SD-JL-34650 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 10.00 07-Mar-19 04:00 06-Mar-19 18:00
SD-JL-34570 FLUSHING & PURGING 6.00 07-Mar-19 10:00 07-Mar-19 04:00
SD-JL-34580 PIPE CUTTING AND INSPECTION BY QC 10.00 07-Mar-19 20:00 07-Mar-19 10:00
SD-JL-34590 FITUP, WELDING PIPING SPOOL & PWHT 12.00 08-Mar-19 08:00 07-Mar-19 20:00
SD-JL-34600 NDT - APPROVED 4.00 08-Mar-19 12:00 08-Mar-19 08:00
SD-JL-36560 VALVE INSTALLATION 10.00 09-Mar-19 04:00 08-Mar-19 14:00
SD-JL-36570 DE-BLINDING 6.00 09-Mar-19 12:00 09-Mar-19 04:00
SD-JL-36580 FINAL TOUCH UP AND QC INSPECTION 6.00 09-Mar-19 18:00 09-Mar-19 12:00
SD-JL-36590 HANDOVER TO OPERATION 0.00 09-Mar-19 18:00
JM05B-16"-OC-3
JM05B-16"-OC-31-0218-CS1-300-4 (02 JOINTS) 66.00 11-Mar-19 22:00 07-Mar-19 18:00
SD-JL-34740 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 07-Mar-19 20:00 07-Mar-19 18:00
SD-JL-34750 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 14.00 08-Mar-19 10:00 07-Mar-19 20:00
SD-JL-34670 FLUSHING & PURGING 10.00 08-Mar-19 20:00 08-Mar-19 10:00
SD-JL-34680 PIPE CUTTING AND INSPECTION BY QC 12.00 09-Mar-19 08:00 08-Mar-19 20:00
SD-JL-34690 FITUP, WELDING PIPING SPOOL & PWHT 18.00 10-Mar-19 02:00 09-Mar-19 08:00
SD-JL-34700 NDT - APPROVED 8.00 10-Mar-19 10:00 10-Mar-19 02:00
SD-JL-36600 VALVE INSTALLATION 14.00 11-Mar-19 06:00 10-Mar-19 10:00
SD-JL-36610 DE-BLINDING 6.00 11-Mar-19 16:00 11-Mar-19 08:00
SD-JL-36620 FINAL TOUCH UP AND QC INSPECTION 6.00 11-Mar-19 22:00 11-Mar-19 16:00
SD-JL-36630 HANDOVER TO OPERATION 0.00 11-Mar-19 22:00
JM13-14"-GP-31
JM13-14"-GP-31-9008-CS1-300-4 (02 JOINTS) 60.00 13-Mar-19 12:00 09-Mar-19 18:00
SD-JL-35540 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 09-Mar-19 20:00 09-Mar-19 18:00
SD-JL-35550 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 10.00 10-Mar-19 06:00 09-Mar-19 20:00
SD-JL-35470 FLUSHING & PURGING 8.00 10-Mar-19 14:00 10-Mar-19 06:00

Page 56 of 170
TIE-IN SCHEDULE - (JALM) TIE-IN SCHEDULE - (JALM) Page 4 of5 29-Nov-18 13:39
Activity ID Activity Name OD Act. Fin / F-C Fin Act.Start / F-C Start 2017 2018 2019
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
SD-JL-35480 PIPE CUTTING AND INSPECTION BY QC 12.00 11-Mar-19 02:00 10-Mar-19 14:00
SD-JL-35490 FITUP, WELDING PIPING SPOOL & PWHT 18.00 11-Mar-19 20:00 11-Mar-19 02:00
SD-JL-35500 NDT - APPROVED 8.00 12-Mar-19 04:00 11-Mar-19 20:00
SD-JL-36640 VALVE INSTALLATION 12.00 12-Mar-19 22:00 12-Mar-19 04:00
SD-JL-36650 DE-BLINDING 6.00 13-Mar-19 06:00 12-Mar-19 22:00
SD-JL-36660 FINAL TOUCH UP AND QC INSPECTION 6.00 13-Mar-19 12:00 13-Mar-19 06:00
SD-JL-36670 HANDOVER TO OPERATION 0.00 13-Mar-19 12:00
JM07-3"-WD-31
JM07-3"-WD-31-0699-L3-300-1 (FLANGED CONNECTION) 43.00 08-Mar-19 01:00 05-Mar-19 06:00
SD-JL-34940 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 05-Mar-19 08:00 05-Mar-19 06:00
SD-JL-34950 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 05-Mar-19 14:00 05-Mar-19 08:00
SD-JL-34870 FLUSHING & PURGING 6.00 05-Mar-19 20:00 05-Mar-19 14:00
SD-JL-34880 UNBOLTING, REMOVAL OF EXISTING JOINT AND INSPECTION BY QC 8.00 06-Mar-19 04:00 05-Mar-19 20:00
SD-JL-34890 INSTALLATION OF NEW BOLT JOINT 12.00 06-Mar-19 16:00 06-Mar-19 04:00
SD-JL-34900 LEAKAGE INSPECTION 3.00 06-Mar-19 19:00 06-Mar-19 16:00
SD-JL-36400 VALVE INSTALLATION 10.00 07-Mar-19 10:00 06-Mar-19 20:00
SD-JL-36410 DE-BLINDING 6.00 07-Mar-19 18:00 07-Mar-19 10:00
SD-JL-36420 FINAL TOUCH UP AND QC INSPECTION 6.00 08-Mar-19 00:00 07-Mar-19 18:00
SD-JL-36430 HANDOVER TO OPERATION 0.00 08-Mar-19 01:00
JM09A-4"-GL-31
JM09A-4"-GL-31-9017-CS1-150-8 (01 JOINT) 44.00 09-Mar-19 12:00 06-Mar-19 18:00
SD-JL-35140 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 06-Mar-19 20:00 06-Mar-19 18:00
SD-JL-35150 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 07-Mar-19 02:00 06-Mar-19 20:00
SD-JL-35070 FLUSHING & PURGING 6.00 07-Mar-19 08:00 07-Mar-19 02:00
SD-JL-35080 PIPE CUTTING AND INSPECTION BY QC 8.00 07-Mar-19 16:00 07-Mar-19 08:00
SD-JL-35090 FITUP, WELDING PIPING SPOOL & PWHT 12.00 08-Mar-19 04:00 07-Mar-19 16:00
SD-JL-35100 NDT - APPROVED 4.00 08-Mar-19 08:00 08-Mar-19 04:00
SD-JL-36440 VALVE INSTALLATION 10.00 08-Mar-19 22:00 08-Mar-19 08:00
SD-JL-36450 DE-BLINDING 6.00 09-Mar-19 06:00 08-Mar-19 22:00
SD-JL-36460 FINAL TOUCH UP AND QC INSPECTION 6.00 09-Mar-19 12:00 09-Mar-19 06:00
SD-JL-36470 HANDOVER TO OPERATION 0.00 09-Mar-19 12:00
JM09B-16"-GL-3
JM09B-16"-GL-31-9015-CS1-150-8 (02 JOINTS) 70.00 11-Mar-19 18:00 07-Mar-19 10:00
SD-JL-35240 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 07-Mar-19 12:00 07-Mar-19 10:00
SD-JL-35250 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 12.00 08-Mar-19 00:00 07-Mar-19 12:00
SD-JL-35170 FLUSHING & PURGING 10.00 08-Mar-19 10:00 08-Mar-19 00:00
SD-JL-35180 PIEP CUTTING AND INSPECTION BY QC 18.00 09-Mar-19 04:00 08-Mar-19 10:00
SD-JL-35190 FITUP, WELDING PIPING SPOOL & PWHT 18.00 09-Mar-19 22:00 09-Mar-19 04:00
SD-JL-35200 NDT - APPROVED 8.00 10-Mar-19 06:00 09-Mar-19 22:00
SD-JL-36480 VALVE INSTALLATION 12.00 11-Mar-19 02:00 10-Mar-19 08:00
SD-JL-36490 DE-BLINDING 8.00 11-Mar-19 12:00 11-Mar-19 02:00
SD-JL-36500 FINAL TOUCH UP AND QC INSPECTION 6.00 11-Mar-19 18:00 11-Mar-19 12:00
SD-JL-36510 HANDOVER TO OPERATION 0.00 11-Mar-19 18:00
JM10-1"-D11042
JM10-1"-D11042-CS1-300-4 (01 JOINT) 44.00 12-Mar-19 16:00 09-Mar-19 22:00
SD-JL-35340 PTW SIGNED AND RECEIVED CLEAN PIPE FROM QP 2.00 10-Mar-19 00:00 09-Mar-19 22:00
SD-JL-35350 APPLY BLINDING / SLIP PLATE / SYSTEM ISOLATION 6.00 10-Mar-19 06:00 10-Mar-19 00:00
SD-JL-35270 FLUSHING & PURGING 6.00 10-Mar-19 12:00 10-Mar-19 06:00
SD-JL-35280 PIPE CUTTING AND INSPECTION BY QC 10.00 10-Mar-19 22:00 10-Mar-19 12:00
SD-JL-35290 FITUP, WELDING PIPING SPOOL & PWHT 12.00 11-Mar-19 10:00 10-Mar-19 22:00
SD-JL-35300 NDT - APPROVED 6.00 11-Mar-19 16:00 11-Mar-19 10:00
SD-JL-36520 VALVE INSTALLATION 8.00 12-Mar-19 04:00 11-Mar-19 16:00
SD-JL-36530 DE-BLINDING 6.00 12-Mar-19 12:00 12-Mar-19 04:00
SD-JL-36540 FINAL TOUCH UP AND QC INSPECTION 4.00 12-Mar-19 16:00 12-Mar-19 12:00
SD-JL-36550 HANDOVER TO OPERATION 0.00 12-Mar-19 16:00
POST-SHUTDOWN
POST-SHUTDOW 0.00 20-Mar-19 08:00 20-Mar-19 08:00
LEAK TEST 0.00 20-Mar-19 08:00 20-Mar-19 08:00
SD-JL-2000 LEAK TEST (JOINTLY WITH QP OPERATION) 0.00 20-Mar-19 08:00*
SYSTEM MODIFICATIONS
MODIFI 124.00 14-Mar-19 02:00 06-Mar-19 08:00
ESD / DCS MARSHALLING
MARS CABINET 18.00 07-Mar-19 10:00 06-Mar-19 08:00
JM-MOD-001 ISOLATE 24V DC DISTRIBUTION 2.00 06-Mar-19 10:00 06-Mar-19 08:00*

Page 57 of 170
TIE-IN SCHEDULE - (JALM) TIE-IN SCHEDULE - (JALM) Page 5 of5 29-Nov-18 13:39
Activity ID Activity Name OD Act. Fin / F-C Fin Act.Start / F-C Start 2017 2018 2019
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
JM-MOD-002 INSTALLATION OF FF CARD AND BARRIOR FOR AI SIGNAL 4.00 06-Mar-19 16:00 06-Mar-19 10:00
JM-MOD-003 INSTALL AI, DI, DO CARDS 4.00 06-Mar-19 22:00 06-Mar-19 16:00
JM-MOD-004 INTERNAL WIRING FOR COMPONENTS 6.00 07-Mar-19 06:00 06-Mar-19 22:00
JM-MOD-005 CONTINUITY CHECK FOR NEW WIRING 2.00 07-Mar-19 10:00 07-Mar-19 08:00
F&G MARSHALLING
MARSHALLI CABINET 18.00 08-Mar-19 12:00 07-Mar-19 10:00
JM-MOD-006 ISOLATE 24V DC DISTRIBUTION 2.00 07-Mar-19 12:00 07-Mar-19 10:00
JM-MOD-007 INSTAL FF CARD AND BARRIOR FOR AI SIGNAL 4.00 07-Mar-19 18:00 07-Mar-19 14:00
JM-MOD-008 INSTALL AI, DI, DO CARDS 4.00 08-Mar-19 02:00 07-Mar-19 20:00
JM-MOD-009 INTERNAL WIRING FOR COMPONENTS 6.00 08-Mar-19 10:00 08-Mar-19 02:00
JM-MOD-010 CONTINUITY CHECK FOR NEW WIRING 2.00 08-Mar-19 12:00 08-Mar-19 10:00
ESD / DCS AUX CONSOLE
C 20.00 09-Mar-19 04:00 07-Mar-19 22:00
JM-MOD-011 HOLE PROVISION FOR NEW ESD PUSH BUTTON 2.00 08-Mar-19 02:00 07-Mar-19 22:00
JM-MOD-012 INSTALLATION OF NEW BUTTON AND MAINTENANCE OVERRIDE 4.00 08-Mar-19 06:00 08-Mar-19 02:00
JM-MOD-013 INSTALLATION OF NEW TB 4.00 08-Mar-19 12:00 08-Mar-19 08:00
JM-MOD-014 INTERNAL WIRING FROM NEW SWITCH TO NEW TB 8.00 09-Mar-19 02:00 08-Mar-19 14:00
JM-MOD-015 CONTINUITY TEST 2.00 09-Mar-19 04:00 09-Mar-19 02:00
F&G AUX CONSOLE
CONSO 18.00 10-Mar-19 06:00 09-Mar-19 04:00
JM-MOD-016 HOLE PROVISION FOR NEW ESD PUSH BUTTON 2.00 09-Mar-19 06:00 09-Mar-19 04:00
JM-MOD-017 INSTALLATION OF NEW BUTTON AND MAINTENANCE OVERRIDE 4.00 09-Mar-19 12:00 09-Mar-19 08:00
JM-MOD-018 INSTALLATION OF NEW TB 4.00 09-Mar-19 18:00 09-Mar-19 14:00
JM-MOD-019 INTERNAL WIRING FROM NEW SWITCH TO NEW TB 6.00 10-Mar-19 04:00 09-Mar-19 20:00
JM-MOD-020 CONTINUITY TEST 2.00 10-Mar-19 06:00 10-Mar-19 04:00
SOFTWARE MODIFICATION
MOD 24.00 11-Mar-19 18:00 10-Mar-19 08:00
JM-MOD-021 SOFTWARE MODIFICATION FOR DCS / ESD / F&G 24.00 11-Mar-19 18:00 10-Mar-19 08:00
PUNCHLIST 36.00 14-Mar-19 02:00 11-Mar-19 20:00
JM-MOD-022 FINAL CHECK AND PUNCH LIST 36.00 14-Mar-19 02:00 11-Mar-19 20:00

Page 58 of 170
PROJECT PLANNING PACKAGE

Attachment 4

PROGRESS TABLE – WEIGHTAGE FACTOR LEV - II

Page 59 of 170
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS"

PROJECT No. 3963 REV-D

JOB TITLE : "EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS"

CLIENT : QATAR PETROLEUM 25-Oct-18

BASELINE PLAN REVISED PLAN

OVERALL PROJECT
PREVIOUS WEEK CURRENT WEEK UP TO DATE PREVIOUS WEEK CURRENT WEEK UP TO DATE

S.
DESCRIPTION REL. WT. % PLANNED ACTUAL DEV. PLANNED ACTUAL DEV. PLANNED ACTUAL DEV. PLANNED ACTUAL DEV. PLANNED ACTUAL DEV. PLANNED ACTUAL DEV.
No.

ENGINEERING
1 3.98% 95.00% 94.64% -0.36% 0.00% 0.00% 0.00% 95.00% 94.64% -0.36% 94.64% 94.64% 0.00% 0.00% 0.00% 0.00% 94.64% 94.64% 0.00%
PHASE

PROCUREMENT
2 65.02% 100.00% 89.55% -10.45% 0.00% 0.00% 0.00% 100.00% 89.55% -10.45% 89.55% 89.55% 0.00% 0.00% 0.00% 0.00% 89.55% 89.55% 0.00%
PHASE

CONSTRUCTION
3 21.00% 82.78% 24.94% -57.84% 3.79% 0.02% -3.78% 86.57% 24.96% -61.61% 24.94% 24.94% 0.00% 0.02% 0.02% 0.00% 24.96% 24.96% 0.00%
PHASE
PRE-
4 COMMISSIONING & 8.00% 30.87% 0.21% -30.66% 6.35% 0.09% -6.26% 37.22% 0.30% -36.92% 0.21% 0.21% 0.00% 0.09% 0.09% 0.00% 0.30% 0.30% 0.00%
COMMISSIONING
CLOSE-OUT
5 2.00% 2.70% 0.00% -2.70% 1.89% 0.00% -1.89% 4.59% 0.00% -4.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
DOCUMENTS

Overall Project 100.00% 88.71% 67.24% -21.46% 1.34% 0.01% -1.33% 90.05% 67.26% -22.80% 67.24% 67.24% 0.00% 0.01% 0.01% 0.00% 67.26% 67.26% 0.00%

Page 60 of 170
PROJECT PLANNING PACKAGE

Attachment 5

S-CURVES

Page 61 of 170
Plan
WEEK

Cum Actual
B/L Weekly

Cum. Plan

Cum. Actual
Overall Project

Weekly Plan
B/L Cum. Plan

Weekly Actual

Weekly Actual

Rev. Recovery
Rev. Recovery
Rev. Recovery

Rev. Recovery
1
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2-Mar-17

0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%

2
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9-Mar-17 2‐Mar‐17

9‐Mar‐17

3
0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 16-Mar-17

16‐Mar‐17

4
0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.01% 0.00% 23-Mar-17

23‐Mar‐17

5
0.05% 0.03% 0.05% 0.03% 0.05% 0.03% 0.05% 0.04% 30-Mar-17

30‐Mar‐17

6
0.08% 0.03% 0.08% 0.03% 0.08% 0.03% 0.16% 0.11% 6-Apr-17

6‐Apr‐17

7
0.11% 0.03% 0.11% 0.03% 0.11% 0.03% 0.19% 0.03% 13-Apr-17

13‐Apr‐17

8
20-Apr-17

QATAR BRANCH
0.14% 0.02% 0.14% 0.02% 0.14% 0.02% 0.28% 0.10%

20‐Apr‐17

9
0.19% 0.05% 0.19% 0.05% 0.19% 0.05% 0.30% 0.02% 27-Apr-17

27‐Apr‐17
0.45% 0.27% 0.45% 0.27% 0.45% 0.27% 0.39% 0.09% 4-May-17

10
4‐May‐17
0.60% 0.15% 0.60% 0.15% 0.60% 0.15% 0.55% 0.16% 11-May-17

11
11‐May‐17
0.67% 0.07% 0.67% 0.07% 0.67% 0.07% 1.56% 1.01% 18-May-17

12
18‐May‐17

CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION


0.75% 0.08% 0.75% 0.08% 0.75% 0.08% 1.65% 0.09% 25-May-17

13
25‐May‐17
1.27% 0.52% 1.27% 0.52% 1.27% 0.52% 2.24% 0.59% 1-Jun-17

14
1‐Jun‐17
1.37% 0.10% 1.37% 0.10% 1.37% 0.10% 2.42% 0.18% 8-Jun-17

15
8‐Jun‐17
1.89% 0.52% 1.89% 0.52% 1.89% 0.52% 3.71% 1.30% 15-Jun-17

16
15‐Jun‐17
2.51% 0.63% 2.51% 0.63% 2.51% 0.63% 3.82% 0.10% 22-Jun-17

17
22‐Jun‐17
2.53% 0.02% 2.53% 0.02% 2.53% 0.02% 5.39% 1.57% 29-Jun-17

18
29‐Jun‐17
2.70% 0.17% 2.70% 0.17% 2.70% 0.17% 5.69% 0.30% 6-Jul-17

19
6‐Jul‐17
2.86% 0.16% 2.86% 0.16% 2.86% 0.16% 6.12% 0.43% 20 13-Jul-17

13‐Jul‐17
3.08% 0.22% 3.08% 0.22% 3.08% 0.22% 7.53% 1.42% 20-Jul-17
21

20‐Jul‐17
4.12% 1.04% 4.12% 1.04% 4.12% 1.04% 7.73% 0.20% 27-Jul-17
22

27‐Jul‐17

6.27% 2.15% 6.27% 2.15% 6.27% 2.15% 7.98% 0.25% 3-Aug-17


23

3‐Aug‐17

7.22% 0.95% 7.22% 0.95% 7.22% 0.95% 9.85% 1.87% 10-Aug-17


24

10‐Aug‐17

7.58% 0.36% 7.58% 0.36% 7.58% 0.36% 10.35% 0.50% 17-Aug-17


25

17‐Aug‐17

7.81% 0.23% 7.81% 0.23% 7.81% 0.23% 10.87% 0.52% 24-Aug-17


26

24‐Aug‐17

7.86% 0.05% 7.86% 0.05% 7.86% 0.05% 11.60% 0.72% 31-Aug-17


27

31‐Aug‐17

8.07% 0.21% 8.07% 0.21% 8.07% 0.21% 12.58% 0.98% 7-Sep-17


28

7‐Sep‐17

8.56% 0.49% 8.56% 0.49% 8.56% 0.49% 14.28% 1.70% 14-Sep-17


29

14‐Sep‐17

8.75% 0.19% 8.75% 0.19% 8.75% 0.19% 14.66% 0.38% 21-Sep-17


30

21‐Sep‐17

8.97% 0.22% 8.97% 0.22% 8.97% 0.22% 15.20% 0.54% 28-Sep-17


31

28‐Sep‐17

9.07% 0.10% 9.07% 0.10% 9.07% 0.10% 16.09% 0.89% 5-Oct-17


32

5‐Oct‐17

9.18% 0.11% 9.18% 0.11% 9.18% 0.11% 17.52% 1.43% 12-Oct-17


33

12‐Oct‐17

9.28% 0.10% 9.28% 0.10% 9.28% 0.10% 18.05% 0.53% 19-Oct-17


34

19‐Oct‐17

10.51% 1.23% 10.51% 1.23% 10.51% 1.23% 20.97% 2.92% 26-Oct-17


35

26‐Oct‐17

11.40% 0.89% 11.40% 0.89% 11.40% 0.89% 21.26% 0.29% 2-Nov-17


36

2‐Nov‐17

11.47% 0.08% 11.47% 0.08% 11.47% 0.08% 21.74% 0.48% 9-Nov-17


37

9‐Nov‐17

11.79% 0.32% 11.79% 0.32% 11.79% 0.32% 23.87% 2.13% 16-Nov-17


38

16‐Nov‐17

11.93% 0.14% 11.93% 0.14% 11.93% 0.14% 24.14% 0.27% 23-Nov-17


39

23‐Nov‐17

12.16% 0.23% 12.16% 0.23% 12.16% 0.23% 25.47% 1.33% 30-Nov-17


40

30‐Nov‐17

12.22% 0.06% 12.22% 0.06% 12.22% 0.06% 28.75% 3.28% 7-Dec-17


41

7‐Dec‐17

12.43% 0.21% 12.43% 0.21% 12.43% 0.21% 29.94% 1.19% 14-Dec-17


42

14‐Dec‐17
S-Curve

14.44% 2.00% 14.44% 2.00% 14.44% 2.00% 31.22% 1.28% 21-Dec-17 21‐Dec‐17
43

16.21% 1.77% 16.21% 1.77% 16.21% 1.77% 32.60% 1.38% 28-Dec-17 28‐Dec‐17
44

Overall Project Progress

16.78% 0.58% 16.78% 0.58% 16.78% 0.58% 33.55% 0.95% 4-Jan-18 4‐Jan‐18
45

18.29% 1.50% 18.29% 1.50% 18.29% 1.50% 35.94% 2.39% 11-Jan-18 11‐Jan‐18
46

20.85% 2.56% 20.85% 2.56% 20.85% 2.56% 36.40% 0.45% 18-Jan-18 18‐Jan‐18
47

21.08% 0.23% 21.08% 0.23% 21.08% 0.23% 38.89% 2.50% 25-Jan-18 25‐Jan‐18
48

21.86% 0.78% 21.86% 0.78% 21.86% 0.78% 39.73% 0.83% 1-Feb-18 1‐Feb‐18
49

22.37% 0.51% 22.37% 0.51% 22.37% 0.51% 42.05% 2.32% 8-Feb-18 8‐Feb‐18
50

22.86% 0.49% 22.86% 0.49% 22.86% 0.49% 42.87% 0.82% 15-Feb-18 15‐Feb‐18
51

23.41% 0.55% 23.41% 0.55% 23.41% 0.55% 43.88% 1.01% 22-Feb-18 22‐Feb‐18
52

23.510% 0.10% 23.51% 0.10% 23.51% 0.10% 46.13% 2.25% 1-Mar-18 1‐Mar‐18
53

26.69% 3.18% 26.69% 3.18% 26.69% 3.18% 47.32% 1.19% 8-Mar-18 8‐Mar‐18
54

26.97% 0.28% 26.97% 0.28% 26.97% 0.28% 49.60% 2.27% 15-Mar-18 15‐Mar‐18
55

22-Mar-18 22‐Mar‐18
27.28% 0.31% 27.28% 0.31% 27.28% 0.31% 50.04% 0.45%
56

29‐Mar‐18
27.97% 0.69% 27.97% 0.69% 27.97% 0.69% 53.10% 3.06% 29-Mar-18
57

5‐Apr‐18
28.13% 0.16% 28.13% 0.16% 28.13% 0.16% 57.44% 4.34% 5-Apr-18
58

12‐Apr‐18
28.31% 0.19% 28.31% 0.19% 28.31% 0.19% 59.87% 2.43% 12-Apr-18
59

19‐Apr‐18
28.36% 0.05% 28.36% 0.05% 28.36% 0.05% 63.01% 3.15% 19-Apr-18
60

26‐Apr‐18
28.95% 0.59% 28.95% 0.59% 28.95% 0.59% 63.27% 0.26% 26-Apr-18
61

3‐May‐18
29.16% 0.21% 29.16% 0.21% 29.16% 0.21% 65.48% 2.21% 3-May-18
62

10‐May‐18
31.44% 2.28% 31.44% 2.28% 31.44% 2.28% 69.81% 4.33% 10-May-18
63

17‐May‐18
34.21% 2.76% 34.21% 2.76% 34.21% 2.76% 70.20% 0.39% 17-May-18
64

24‐May‐18
36.25% 2.04% 36.25% 2.04% 36.25% 2.04% 70.56% 0.37% 24-May-18
65
Overall Progress "S" curve

31‐May‐18
37.30% 1.05% 37.30% 1.05% 37.30% 1.05% 70.94% 0.37% 31-May-18
66

7‐Jun‐18
38.64% 1.34% 38.64% 1.34% 38.64% 1.34% 71.26% 0.33% 7-Jun-18
67

14‐Jun‐18
41.47% 2.84% 41.47% 2.84% 41.47% 2.84% 71.54% 0.28% 14-Jun-18
68

21‐Jun‐18
41.58% 0.11% 41.58% 0.11% 41.58% 0.11% 71.93% 0.39% 21-Jun-18
69

28‐Jun‐18
42.28% 0.69% 42.28% 0.69% 42.28% 0.69% 72.47% 0.54% 28-Jun-18
70

5‐Jul‐18
44.23% 1.96% 44.23% 1.96% 44.23% 1.96% 74.68% 2.21% 5-Jul-18
71

12‐Jul‐18
46.85% 2.61% 46.85% 2.61% 46.85% 2.61% 75.94% 1.27% 12-Jul-18
72

19‐Jul‐18
48.61% 1.76% 48.61% 1.76% 48.61% 1.76% 76.41% 0.46% 19-Jul-18
73

26‐Jul‐18
48.99% 0.38% 48.99% 0.38% 48.99% 0.38% 78.07% 1.66% 26-Jul-18
74

2‐Aug‐18
48.99% 0.00% 48.99% 0.00% 48.99% 0.00% 79.65% 1.58% 2-Aug-18
75

9‐Aug‐18
49.58% 0.59% 49.58% 0.59% 49.58% 0.59% 80.01% 0.35% 9-Aug-18
76

16‐Aug‐18
50.07% 0.49% 50.07% 0.49% 50.07% 0.49% 80.37% 0.36% 16-Aug-18
77

23‐Aug‐18
50.59% 0.52% 50.59% 0.52% 50.59% 0.52% 81.02% 0.65% 23-Aug-18
78

PROJECT No. 3963 "

30‐Aug‐18
54.63% 4.03% 54.63% 4.03% 54.63% 4.03% 81.43% 0.42% 30-Aug-18
79

6‐Sep‐18

55.89% 1.27% 55.89% 1.27% 55.89% 1.27% 81.97% 0.54% 6-Sep-18


80

13‐Sep‐18

60.30% 4.40% 60.30% 4.40% 60.30% 4.40% 82.95% 0.98% 13-Sep-18


81

20‐Sep‐18

62.21% 1.91% 62.21% 1.91% 62.21% 1.91% 84.02% 1.07% 20-Sep-18


82

27‐Sep‐18

63.94% 1.73% 63.94% 1.73% 63.94% 1.73% 84.88% 0.87% 27-Sep-18


83

4‐Oct‐18

66.87% 2.92% 66.87% 2.92% 66.87% 2.92% 86.20% 1.32% 4-Oct-18


84

11‐Oct‐18
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS

67.06% 0.19% 67.06% 0.19% 67.06% 0.19% 87.54% 1.34% 11-Oct-18


85

18‐Oct‐18

67.24% 0.19% 67.24% 0.19% 67.24% 0.19% 88.71% 1.17% 18-Oct-18


86

25‐Oct‐18

67.26% 0.01% 67.26% 0.01% 67.26% 0.01% 90.05% 1.34% 25-Oct-18


87

1‐Nov‐18

67.48% 0.23% 91.24% 1.19% 1-Nov-18


88

8‐Nov‐18

67.98% 0.50% 92.77% 1.53% 8-Nov-18


89

15‐Nov‐18

68.55% 0.57% 94.00% 1.23% 15-Nov-18


90

22‐Nov‐18

69.14% 0.60% 95.30% 1.31% 22-Nov-18


91

29‐Nov‐18

70.47% 1.32% 96.45% 1.15% 29-Nov-18


92

6‐Dec‐18

71.41% 0.94% 97.20% 0.75% 6-Dec-18


93

13‐Dec‐18

75.03% 3.63% 98.08% 0.88% 13-Dec-18


94

20‐Dec‐18

76.29% 1.26% 98.53% 0.44% 20-Dec-18


95

27‐Dec‐18

77.76% 1.46% 98.70% 0.18% 27-Dec-18


96

3‐Jan‐19

80.13% 2.37% 98.87% 0.16% 3-Jan-19


97

10‐Jan‐19

82.34% 2.21% 99.03% 0.16% 10-Jan-19


98

17‐Jan‐19

84.57% 2.23% 99.19% 0.16% 17-Jan-19 24‐Jan‐19


DATE:

86.12% 1.55% 99.37% 0.17% 24-Jan-19


31‐Jan‐19

88.22% 2.10% 99.55% 0.18% 31-Jan-19


7‐Feb‐19

88.76% 0.54% 99.72% 0.18% 7-Feb-19


14‐Feb‐19

89.46% 0.69% 99.90% 0.18% 14-Feb-19


21‐Feb‐19
25-Oct-18

90.07% 0.62% 100.00% 0.10% 21-Feb-19


28‐Feb‐19

90.74% 0.66% 100.00% 0.00% 28-Feb-19


7‐Mar‐19

91.16% 0.42% 100.00% 0.00% 7-Mar-19


14‐Mar‐19

91.59% 0.43% 100.00% 0.00% 14-Mar-19


21‐Mar‐19

92.19% 0.59% 100.00% 0.00% 21-Mar-19


28‐Mar‐19

92.79% 0.61% 100.00% 0.00% 28-Mar-19


4‐Apr‐19

93.40% 0.61% 100.00% 0.00% 4-Apr-19 11‐Apr‐19

93.77% 0.37% 100.00% 0.00% 11-Apr-19 18‐Apr‐19

94.09% 0.32% 100.00% 0.00% 18-Apr-19 25‐Apr‐19

94.62% 0.53% 100.00% 0.00% 25-Apr-19 2‐May‐19

95.25% 0.63% 100.00% 0.00% 2-May-19 9‐May‐19

96.28% 1.03% 100.00% 0.00% 9-May-19 16‐May‐19

96.78% 0.50% 100.00% 0.00% 16-May-19 23‐May‐19

97.65% 0.87% 100.00% 0.00% 23-May-19 30‐May‐19

97.90% 0.24% 100.00% 0.00% 30-May-19 6‐Jun‐19

98.16% 0.26% 100.00% 0.00% 6-Jun-19 13‐Jun‐19

98.40% 0.24% 100.00% 0.00% 13-Jun-19 20‐Jun‐19


Page 62 of 170
B/L Cum. Plan

98.67% 0.27% 100.00% 0.00% 20-Jun-19 27‐Jun‐19


Rev. Recovery Cum. Plan

Rev. Recovery Cum. Actual

98.92% 0.25% 100.00% 0.00% 27-Jun-19 4‐Jul‐19

99.16% 0.23% 100.00% 0.00% 4-Jul-19 11‐Jul‐19

99.38% 0.23% 100.00% 0.00% 11-Jul-19 18‐Jul‐19

99.61% 0.23% 100.00% 0.00% 18-Jul-19 25‐Jul‐19

100.00% 0.39% 100.00% 0.00% 25-Jul-19


99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126
Plan
Plan
WEEK

Actual
Actual
Rev. Cum.
Cum Actual

Rev. Cum.
Overall Project

Rev. Weekly
Rev. Weekly
B/L Cum. Plan

Weekly Actual
B/L Weekly Plan
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%

0.00%
2‐Mar‐17

1
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2-Mar-17

9‐Mar‐17

2
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.02% 0.02% 9-Mar-17

16‐Mar‐17

3
0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.20% 0.23% 16-Mar-17
23‐Mar‐17

4
0.45% 0.58% 0.45% 0.58% 0.45% 0.58% 0.10% 0.32% 23-Mar-17
30‐Mar‐17

5
0.80% 1.38% 0.80% 1.38% 0.80% 1.38% 0.94% 1.26% 30-Mar-17 6‐Apr‐17

13‐Apr‐17

6
0.70% 2.08% 0.70% 2.08% 0.68% 2.08% 0.28% 1.54% 6-Apr-17

20‐Apr‐17

7
0.80% 2.88% 0.80% 2.88% 0.81% 2.88% 0.65% 2.19% 13-Apr-17

27‐Apr‐17

QATAR BRANCH
0.62% 3.50% 0.62% 3.50% 0.62% 3.50% 1.05% 3.24% 20-Apr-17
4‐May‐17

9
0.85% 4.35% 0.85% 4.35% 0.85% 4.35% 0.59% 3.83% 27-Apr-17
11‐May‐17

1.76% 6.11% 1.76% 6.11% 1.76% 6.11% 2.19% 6.02% 4-May-17 18‐May‐17

10
11-May-17 25‐May‐17
2.49% 8.60% 2.49% 8.60% 2.50% 8.60% 2.74% 8.76%

11
1‐Jun‐17
1.85% 10.45% 1.85% 10.45% 1.85% 10.45% 3.10% 11.85% 18-May-17

12
8‐Jun‐17

CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION


2.08% 12.54% 2.08% 12.54% 2.08% 12.54% 2.23% 14.09% 25-May-17

13
15‐Jun‐17

1.84% 14.37% 1.84% 14.37% 1.84% 14.37% 2.75% 16.84% 1-Jun-17

14
22‐Jun‐17

1.28% 15.65% 1.28% 15.65% 1.28% 15.65% 4.50% 21.34% 8-Jun-17 29‐Jun‐17

15
6‐Jul‐17
1.89% 17.55% 1.89% 17.55% 1.89% 17.55% 4.13% 25.47% 15-Jun-17

16
13‐Jul‐17
2.28% 19.83% 2.28% 19.83% 2.28% 19.83% 2.54% 28.01% 22-Jun-17

17
20‐Jul‐17
0.42% 20.25% 0.42% 20.25% 0.42% 20.25% 4.04% 32.04% 29-Jun-17

18
27‐Jul‐17

1.74% 21.99% 1.74% 21.99% 1.74% 21.99% 5.24% 37.29% 6-Jul-17

19
3‐Aug‐17

1.33% 23.32% 1.33% 23.32% 1.33% 23.32% 3.61% 40.90% 13-Jul-17 10‐Aug‐17

20 17‐Aug‐17
4.06% 27.38% 4.06% 27.38% 4.06% 27.38% 4.45% 45.35% 20-Jul-17
21

24‐Aug‐17

2.07% 29.45% 2.07% 29.45% 2.07% 29.45% 4.97% 50.32% 27-Jul-17


22

31‐Aug‐17

3.74% 33.20% 3.74% 33.20% 3.74% 33.20% 4.36% 54.68% 3-Aug-17


23

7‐Sep‐17

2.05% 35.25% 2.05% 35.25% 2.05% 35.25% 4.69% 59.37% 10-Aug-17 14‐Sep‐17
24

21‐Sep‐17
1.48% 36.74% 1.48% 36.74% 1.48% 36.74% 4.06% 63.43% 17-Aug-17
25

28‐Sep‐17
1.69% 38.42% 1.69% 38.42% 1.69% 38.42% 4.58% 68.01% 24-Aug-17
26

5‐Oct‐17

1.24% 39.66% 1.24% 39.66% 1.24% 39.66% 6.60% 74.60% 31-Aug-17


27

12‐Oct‐17

0.38% 40.04% 0.38% 40.04% 0.38% 40.04% 5.63% 80.23% 7-Sep-17 19‐Oct‐17
28

1.06% 41.09% 1.06% 41.09% 1.06% 41.09% 7.40% 87.64% 14-Sep-17 26‐Oct‐17
29

2‐Nov‐17
2.30% 43.39% 2.30% 43.39% 2.30% 43.39% 7.36% 95.00% 21-Sep-17
30

9‐Nov‐17
2.79% 46.18% 2.79% 46.18% 2.79% 46.18% 0.00% 95.00% 28-Sep-17
31

16‐Nov‐17

2.59% 48.78% 2.59% 48.78% 2.59% 48.78% 0.00% 95.00% 5-Oct-17


32

23‐Nov‐17

2.76% 51.54% 2.76% 51.54% 2.76% 51.54% 0.00% 95.00% 12-Oct-17 30‐Nov‐17
33

19-Oct-17 7‐Dec‐17
2.44% 53.98% 2.44% 53.98% 2.44% 53.98% 0.00% 95.00%
34

14‐Dec‐17
2.89% 56.87% 2.89% 56.87% 2.89% 56.87% 0.00% 95.00% 26-Oct-17
35

21‐Dec‐17
2.22% 59.09% 2.22% 59.09% 2.22% 59.09% 0.00% 95.00% 2-Nov-17
36

28‐Dec‐17

1.90% 60.99% 1.90% 60.99% 1.90% 60.99% 0.00% 95.00% 9-Nov-17


37

4‐Jan‐18

2.67% 63.65% 2.67% 63.65% 2.67% 63.65% 0.00% 95.00% 16-Nov-17 11‐Jan‐18
38

23-Nov-17 18‐Jan‐18
1.84% 65.49% 1.84% 65.49% 1.84% 65.49% 0.00% 95.00%
39

25‐Jan‐18
2.12% 67.61% 2.12% 67.61% 2.12% 67.61% 0.00% 95.00% 30-Nov-17
40

1‐Feb‐18
1.44% 69.05% 1.44% 69.05% 1.44% 69.05% 0.00% 95.00% 7-Dec-17
41

8‐Feb‐18

1.00% 70.05% 1.00% 70.05% 1.00% 70.05% 0.00% 95.00% 14-Dec-17


42

15‐Feb‐18
S-Curve

1.78% 71.83% 1.78% 71.83% 1.78% 71.83% 0.00% 95.00% 21-Dec-17 22‐Feb‐18
43

1‐Mar‐18
0.64% 72.47% 0.64% 72.47% 0.64% 72.47% 0.00% 95.00% 28-Dec-17
44

Overall Engineering Progress

8‐Mar‐18
0.97% 73.44% 0.97% 73.44% 0.97% 73.44% 0.00% 95.00% 4-Jan-18
45

15‐Mar‐18
1.69% 75.14% 1.69% 75.14% 1.69% 75.14% 0.00% 95.00% 11-Jan-18
46

22‐Mar‐18

1.19% 76.32% 1.19% 76.32% 1.19% 76.32% 0.00% 95.00% 18-Jan-18


47

29‐Mar‐18

2.71% 79.03% 2.71% 79.03% 2.71% 79.03% 0.00% 95.00% 25-Jan-18 5‐Apr‐18
48

12‐Apr‐18
1.85% 80.89% 1.85% 80.89% 1.85% 80.89% 0.00% 95.00% 1-Feb-18
49

19‐Apr‐18
1.45% 82.34% 1.45% 82.34% 1.45% 82.34% 0.00% 95.00% 8-Feb-18
50

26‐Apr‐18

0.75% 83.08% 0.75% 83.08% 0.75% 83.08% 0.00% 95.00% 15-Feb-18


51

3‐May‐18

4.21% 87.29% 4.21% 87.29% 4.21% 87.29% 0.00% 95.00% 22-Feb-18


52

10‐May‐18

1.09% 88.375% 1.09% 88.38% 1.09% 88.38% 0.00% 95.00% 1-Mar-18 17‐May‐18
53

24‐May‐18
0.45% 88.82% 0.45% 88.82% 0.45% 88.82% 0.00% 95.00% 8-Mar-18
54

31‐May‐18
Overall Engineering Progress "S" curve

0.69% 89.52% 0.69% 89.52% 0.69% 89.52% 0.00% 95.00% 15-Mar-18


55

7‐Jun‐18

1.38% 90.90% 1.38% 90.90% 1.38% 90.90% 0.00% 95.00% 22-Mar-18


56

14‐Jun‐18

0.12% 91.01% 0.12% 91.01% 0.12% 91.01% 0.00% 95.00% 29-Mar-18 21‐Jun‐18
57

0.79% 91.80% 0.79% 91.80% 0.79% 91.80% 0.00% 95.00% 5-Apr-18 28‐Jun‐18
58

5‐Jul‐18
0.25% 92.05% 0.25% 92.05% 0.25% 92.05% 5.00% 95.00% 12-Apr-18
59

12‐Jul‐18
0.27% 92.32% 0.27% 92.32% 0.27% 92.32% 0.00% 95.00% 19-Apr-18
60

19‐Jul‐18

0.15% 92.47% 0.15% 92.47% 0.15% 92.47% 0.00% 95.00% 26-Apr-18


61

26‐Jul‐18

0.17% 92.64% 0.17% 92.64% 0.17% 92.64% 0.00% 95.00% 3-May-18 2‐Aug‐18
62

10-May-18 9‐Aug‐18
0.20% 92.84% 0.20% 92.84% 0.20% 92.84% 0.00% 95.00%
63

16‐Aug‐18
0.50% 93.34% 0.50% 93.34% 0.50% 93.34% 0.00% 95.00% 17-May-18
64

23‐Aug‐18
0.00% 93.34% 0.00% 93.34% 0.00% 93.34% 0.00% 95.00% 24-May-18
65

30‐Aug‐18

0.37% 93.70% 0.37% 93.70% 0.37% 93.70% 0.00% 95.00% 31-May-18


66

6‐Sep‐18

0.00% 93.70% 0.00% 93.70% 0.00% 93.70% 0.00% 95.00% 7-Jun-18 13‐Sep‐18
67

14-Jun-18 20‐Sep‐18
0.05% 93.76% 0.05% 93.76% 0.05% 93.76% 0.00% 95.00%
68

27‐Sep‐18
0.00% 93.76% 0.00% 93.76% 0.00% 93.76% 0.00% 95.00% 21-Jun-18
69

4‐Oct‐18
0.08% 93.84% 0.08% 93.84% 0.08% 93.84% 0.00% 95.00% 28-Jun-18
70

11‐Oct‐18

0.00% 93.84% 0.00% 93.84% 0.00% 93.84% 0.00% 95.00% 5-Jul-18


71

18‐Oct‐18

0.08% 93.92% 0.08% 93.92% 0.08% 93.92% 0.00% 95.00% 12-Jul-18 25‐Oct‐18
72

1‐Nov‐18
0.00% 93.92% 0.00% 93.92% 0.00% 93.92% 0.00% 95.00% 19-Jul-18
73

8‐Nov‐18
0.20% 94.12% 0.20% 94.12% 0.20% 94.12% 0.00% 95.00% 26-Jul-18
74

15‐Nov‐18
0.00% 94.12% 0.00% 94.12% 0.00% 94.12% 0.00% 95.00% 2-Aug-18
75

22‐Nov‐18

0.03% 94.15% 0.03% 94.15% 0.03% 94.15% 0.00% 95.00% 9-Aug-18


76

29‐Nov‐18

0.00% 94.15% 0.00% 94.15% 0.00% 94.15% 0.00% 95.00% 16-Aug-18 6‐Dec‐18
77

13‐Dec‐18
0.00% 94.15% 0.00% 94.15% 0.00% 94.15% 0.00% 95.00% 23-Aug-18
78

PROJECT No. 3963 "

20‐Dec‐18
0.02% 94.17% 0.02% 94.17% 0.02% 94.17% 0.00% 95.00% 30-Aug-18
79

27‐Dec‐18

0.19% 94.36% 0.19% 94.36% 0.19% 94.36% 0.00% 95.00% 6-Sep-18


80

3‐Jan‐19

0.12% 94.48% 0.12% 94.48% 0.12% 94.48% 0.00% 95.00% 13-Sep-18


81

10‐Jan‐19

0.04% 94.53% 0.04% 94.53% 0.04% 94.53% 0.00% 95.00% 20-Sep-18 17‐Jan‐19
82

24‐Jan‐19
0.05% 94.58% 0.05% 94.58% 0.05% 94.58% 0.00% 95.00% 27-Sep-18
83

31‐Jan‐19
0.00% 94.58% 0.00% 94.58% 0.00% 94.58% 0.00% 95.00% 4-Oct-18
84

7‐Feb‐19
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS

0.07% 94.64% 0.07% 94.64% 0.07% 94.64% 0.00% 95.00% 11-Oct-18


85

14‐Feb‐19

0.00% 94.64% 0.00% 94.64% 0.00% 94.64% 0.00% 95.00% 18-Oct-18


86

21‐Feb‐19

0.00% 94.64% 0.00% 94.64% 0.00% 94.64% 0.00% 95.00% 25-Oct-18 28‐Feb‐19
87

7‐Mar‐19
0.00% 94.64% 0.00% 95.00% 1-Nov-18
88

14‐Mar‐19
0.00% 94.64% 0.00% 95.00% 8-Nov-18
89

21‐Mar‐19

0.00% 94.64% 0.00% 95.00% 15-Nov-18


90

28‐Mar‐19

0.00% 94.64% 0.00% 95.00% 22-Nov-18 4‐Apr‐19


91

0.00% 94.64% 0.00% 95.00% 29-Nov-18 11‐Apr‐19


92

18‐Apr‐19
0.24% 94.88% 0.00% 95.00% 6-Dec-18
93

25‐Apr‐19
0.00% 94.88% 0.00% 95.00% 13-Dec-18
94

2‐May‐19

0.00% 94.88% 0.00% 95.00% 20-Dec-18


95

9‐May‐19

0.06% 94.93% 0.00% 95.00% 27-Dec-18 16‐May‐19


96

3-Jan-19 23‐May‐19
0.07% 95.00% 0.00% 95.00%
97

30‐May‐19
0.00% 95.00% 0.00% 95.00% 10-Jan-19
98

6‐Jun‐19
DATE:

0.00% 95.00% 0.00% 95.00% 17-Jan-19


99

Page 63 of 170

13‐Jun‐19

0.00% 95.00% 0.00% 95.00% 24-Jan-19


20‐Jun‐19
100
Cum Actual
B/L Cum. Plan

0.00% 95.00% 0.00% 95.00% 31-Jan-19 27‐Jun‐19


3-Nov-18
Rev. Cum. Actual
Rev. Cum. Plan

4‐Jul‐19
5.00% 100.00% 0.00% 95.00% 11-Jul-19

11‐Jul‐19
0.00% 100.00% 0.00% 95.00% 18-Jul-19
18‐Jul‐19

0.00% 100.00% 0.00% 95.00% 25-Jul-19


101 124 125 126

25‐Jul‐19
WEEK

Cum. Plan
Cum Actual
Overall Project

Cum. Actual
Weekly Plan
B/L Cum. Plan

Weekly Actual

Rev. Recovery
Rev. Recovery
Rev. Recovery
Rev. Recovery

Weekly Actual
B/L Weekly Plan
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%

2‐Mar‐17

1
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2-Mar-17

9‐Mar‐17

2
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9-Mar-17

16‐Mar‐17

3
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 16-Mar-17

23‐Mar‐17

4
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 23-Mar-17

30‐Mar‐17

5
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 30-Mar-17

6‐Apr‐17

6
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 0.15% 6-Apr-17

13‐Apr‐17

7
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.15% 13-Apr-17

20‐Apr‐17

QATAR BRANCH
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.08% 0.23% 20-Apr-17

27‐Apr‐17

9
0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.00% 0.23% 27-Apr-17

0.30% 0.32% 0.30% 0.32% 0.30% 0.32% 0.00% 0.23% 4-May-17 4‐May‐17

10
0.07% 0.39% 0.07% 0.39% 0.07% 0.39% 0.08% 0.31% 11-May-17 11‐May‐17

11
0.00% 0.39% 0.00% 0.39% 0.00% 0.39% 1.36% 1.67% 18-May-17 18‐May‐17

12

CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION


0.00% 0.39% 0.00% 0.39% 0.00% 0.39% 0.00% 1.67% 25-May-17 25‐May‐17

13
0.68% 1.08% 0.68% 1.08% 0.68% 1.08% 0.74% 2.41% 1-Jun-17 1‐Jun‐17

14
0.08% 1.15% 0.08% 1.15% 0.08% 1.15% 0.00% 2.41% 8-Jun-17 8‐Jun‐17

15
0.68% 1.83% 0.68% 1.83% 0.68% 1.83% 1.75% 4.15% 15-Jun-17 15‐Jun‐17

16
0.82% 2.65% 0.82% 2.65% 0.82% 2.65% 0.00% 4.15% 22-Jun-17 22‐Jun‐17

17
0.00% 2.65% 0.00% 2.65% 0.00% 2.65% 2.17% 6.32% 29-Jun-17 29‐Jun‐17

18
0.15% 2.81% 0.15% 2.81% 0.15% 2.81% 0.15% 6.47% 6-Jul-17 6‐Jul‐17

19
0.17% 2.98% 0.17% 2.98% 0.17% 2.98% 0.43% 6.90% 13-Jul-17 13‐Jul‐17
20

0.08% 3.06% 0.08% 3.06% 0.08% 3.06% 1.91% 8.81% 20-Jul-17 20‐Jul‐17
21

27‐Jul‐17
1.48% 4.54% 1.48% 4.54% 1.48% 4.54% 0.00% 8.81% 27-Jul-17
22

3‐Aug‐17
3.08% 7.62% 3.08% 7.62% 3.08% 7.62% 0.11% 8.92% 3-Aug-17
23

10‐Aug‐17
1.33% 8.95% 1.33% 8.95% 1.33% 8.95% 2.59% 11.51% 10-Aug-17
24

17‐Aug‐17
0.46% 9.41% 0.46% 9.41% 0.46% 9.41% 0.52% 12.04% 17-Aug-17
25

24‐Aug‐17
0.25% 9.66% 0.25% 9.66% 0.25% 9.66% 0.52% 12.56% 24-Aug-17
26

31‐Aug‐17
0.00% 9.66% 0.00% 9.66% 0.00% 9.66% 0.71% 13.27% 31-Aug-17
27

7‐Sep‐17
0.30% 9.96% 0.30% 9.96% 0.30% 9.96% 1.17% 14.44% 7-Sep-17
28

14‐Sep‐17
0.68% 10.64% 0.68% 10.64% 0.68% 10.64% 2.16% 16.60% 14-Sep-17
29

21‐Sep‐17
0.15% 10.80% 0.15% 10.80% 0.15% 10.80% 0.12% 16.72% 21-Sep-17
30

28‐Sep‐17
0.17% 10.96% 0.17% 10.96% 0.17% 10.96% 0.77% 17.49% 28-Sep-17
31

5‐Oct‐17
0.00% 10.96% 0.00% 10.96% 0.00% 10.96% 1.31% 18.80% 5-Oct-17
32

12‐Oct‐17
0.00% 10.96% 0.00% 10.96% 0.00% 10.96% 2.14% 20.94% 12-Oct-17
33

19‐Oct‐17
0.00% 10.96% 0.00% 10.96% 0.00% 10.96% 0.66% 21.60% 19-Oct-17
34

26‐Oct‐17
1.72% 12.68% 1.72% 12.68% 1.72% 12.68% 4.28% 25.88% 26-Oct-17
35

2‐Nov‐17
1.23% 13.91% 1.23% 13.91% 1.23% 13.91% 0.38% 26.26% 2-Nov-17
36

9-Nov-17
9‐Nov‐17
0.00% 13.91% 0.00% 13.91% 0.00% 13.91% 0.65% 26.91%
37

16-Nov-17
16‐Nov‐17
0.32% 14.24% 0.32% 14.24% 0.32% 14.24% 3.18% 30.09%
38

23-Nov-17
23‐Nov‐17
0.10% 14.34% 0.10% 14.34% 0.10% 14.34% 0.32% 30.41%
39

30-Nov-17
30‐Nov‐17
0.23% 14.57% 0.23% 14.57% 0.23% 14.57% 1.88% 32.29%
40

7-Dec-17
7‐Dec‐17
0.00% 14.57% 0.00% 14.57% 0.00% 14.57% 4.78% 37.07%
41

1.76% 14-Dec-17 14‐Dec‐17


0.26% 14.82% 0.26% 14.82% 0.26% 14.82% 38.83%
42

S-Curve

1.90% 21-Dec-17 21‐Dec‐17


2.95% 17.78% 2.95% 17.78% 2.95% 17.78% 40.73%
43

2.01% 28-Dec-17 28‐Dec‐17


2.56% 20.34% 2.56% 20.34% 2.56% 20.34% 42.74%
44

Overall Procurement Progress

1.23% 4-Jan-18 4‐Jan‐18


0.70% 21.04% 0.70% 21.04% 0.70% 21.04% 43.96%
45

3.37% 47.34% 11-Jan-18 11‐Jan‐18


2.18% 23.22% 2.18% 23.22% 2.18% 23.22%
46

0.20% 47.54% 18-Jan-18 18‐Jan‐18


3.85% 27.07% 3.85% 27.07% 3.85% 27.07%
47

3.26% 50.80% 25-Jan-18 25‐Jan‐18


0.16% 27.23% 0.16% 27.23% 0.16% 27.23%
48

0.84% 51.63% 1-Feb-18 1‐Feb‐18


1.09% 28.31% 1.09% 28.31% 1.09% 28.31%
49

3.19% 54.82% 8-Feb-18 8‐Feb‐18


0.54% 28.85% 0.54% 28.85% 0.54% 28.85%
50

0.66% 29.51% 0.66% 29.51% 0.66% 29.51% 0.96% 55.79% 15-Feb-18 15‐Feb‐18
51

0.57% 30.08% 0.57% 30.08% 0.57% 30.08% 1.08% 56.87% 22-Feb-18 22‐Feb‐18
52

0.07% 30.151% 0.07% 30.15% 0.07% 30.15% 2.73% 59.60% 1-Mar-18 1‐Mar‐18
53

4.81% 34.96% 4.81% 34.96% 4.81% 34.96% 1.37% 60.97% 8-Mar-18 8‐Mar‐18
54
Overall Procurement Progress "S" curve

0.35% 35.31% 0.35% 35.31% 0.35% 35.31% 3.19% 64.16% 15-Mar-18 15‐Mar‐18
55

0.21% 35.52% 0.21% 35.52% 0.21% 35.52% 0.21% 64.37% 22-Mar-18 22‐Mar‐18
56

0.87% 36.39% 0.87% 36.39% 0.87% 36.39% 4.21% 68.58% 29-Mar-18 29‐Mar‐18
57

0.10% 36.49% 0.10% 36.49% 0.10% 36.49% 6.25% 74.83% 5-Apr-18 5‐Apr‐18
58

0.00% 36.49% 0.00% 36.49% 0.00% 36.49% 3.40% 78.23% 12-Apr-18 12‐Apr‐18
59

0.00% 36.49% 0.00% 36.49% 0.00% 36.49% 4.3% 82.6% 19-Apr-18 19‐Apr‐18
60

0.83% 37.32% 0.83% 37.32% 0.83% 37.32% 0.0% 82.6% 26-Apr-18 26‐Apr‐18
61

0.27% 37.59% 0.27% 37.59% 0.27% 37.59% 3.0% 85.6% 3-May-18 3‐May‐18
62

3.43% 41.03% 3.43% 41.03% 3.43% 41.03% 6.3% 91.8% 10-May-18 10‐May‐18
63

4.17% 45.19% 4.17% 45.19% 4.17% 45.19% 0.0% 91.8% 17-May-18 17‐May‐18
64

3.06% 48.25% 3.06% 48.25% 3.06% 48.25% 0.0% 91.8% 24-May-18 24‐May‐18
65

1.37% 49.62% 1.37% 49.62% 1.37% 49.62% 0.0% 91.8% 31-May-18 31‐May‐18
66

1.63% 51.25% 1.63% 51.25% 1.63% 51.25% 0.0% 91.82% 7-Jun-18 7‐Jun‐18
67

4.09% 55.34% 4.09% 55.34% 4.09% 55.34% 0.00% 91.82% 14-Jun-18 14‐Jun‐18
68

0.00% 55.34% 0.00% 55.34% 0.00% 55.34% 0.00% 91.82% 21-Jun-18 21‐Jun‐18
69

0.93% 56.27% 0.93% 56.27% 0.93% 56.27% 0.00% 91.82% 28-Jun-18 28‐Jun‐18
70

2.87% 59.14% 2.87% 59.14% 2.87% 59.14% 2.73% 94.55% 5-Jul-18 5‐Jul‐18
71

3.81% 62.95% 3.81% 62.95% 3.81% 62.95% 1.36% 95.91% 12-Jul-18 12‐Jul‐18
72

2.47% 65.42% 2.47% 65.42% 2.47% 65.42% 0.00% 95.91% 19-Jul-18 19‐Jul‐18
73

0.31% 65.73% 0.31% 65.73% 0.31% 65.73% 2.04% 97.96% 26-Jul-18 26‐Jul‐18
74

0.00% 65.73% 0.00% 65.73% 0.00% 65.73% 2.04% 100.00% 2-Aug-18 2‐Aug‐18
75

0.00% 65.73% 0.00% 65.73% 0.00% 65.73% 0.00% 100.00% 9-Aug-18 9‐Aug‐18
76

0.56% 66.29% 0.56% 66.29% 0.56% 66.29% 0.00% 100.00% 16-Aug-18 16‐Aug‐18
77

0.54% 66.83% 0.54% 66.83% 0.54% 66.83% 0.00% 100.00% 23-Aug-18 23‐Aug‐18
78

PROJECT No. 3963 "

5.96% 72.79% 5.96% 72.79% 5.96% 72.79% 0.00% 100.00% 30-Aug-18 30‐Aug‐18
79

1.42% 74.21% 1.42% 74.21% 1.42% 74.21% 0.00% 100.00% 6-Sep-18 6‐Sep‐18
80

6.15% 80.36% 6.15% 80.36% 6.15% 80.36% 0.00% 100.00% 13-Sep-18 13‐Sep‐18
81

2.38% 82.74% 2.38% 82.74% 2.38% 82.74% 0.00% 100.00% 20-Sep-18 20‐Sep‐18
82

2.46% 85.20% 2.46% 85.20% 2.46% 85.20% 0.00% 100.00% 27-Sep-18 27‐Sep‐18
83

4.35% 89.55% 4.35% 89.55% 4.35% 89.55% 0.00% 100.00% 4-Oct-18 4‐Oct‐18
84

"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS

0.00% 89.55% 0.00% 89.55% 0.00% 89.55% 0.00% 100.00% 11-Oct-18 11‐Oct‐18
85

0.00% 89.55% 0.00% 89.55% 0.00% 89.55% 0.00% 100.00% 18-Oct-18 18‐Oct‐18
86

0.00% 89.55% 0.00% 89.55% 0.00% 89.55% 0.00% 100.00% 25-Oct-18 25‐Oct‐18
87

0.02% 89.57% 0.00% 100.00% 1-Nov-18 1‐Nov‐18


88

0.00% 89.57% 0.00% 100.00% 8-Nov-18 8‐Nov‐18


89

0.00% 89.57% 0.00% 100.00% 15-Nov-18 15‐Nov‐18


90

0.00% 89.57% 0.00% 100.00% 22-Nov-18 22‐Nov‐18


91

0.93% 90.50% 0.00% 100.00% 29-Nov-18 29‐Nov‐18


92

0.05% 90.55% 0.00% 100.00% 6-Dec-18 6‐Dec‐18


93

4.27% 94.82% 0.00% 100.00% 13-Dec-18 13‐Dec‐18


94

0.63% 95.45% 0.00% 100.00% 20-Dec-18 20‐Dec‐18


95

0.21% 95.66% 0.00% 100.00% 27-Dec-18 27‐Dec‐18


96

1.09% 96.74% 0.00% 100.00% 3-Jan-19 3‐Jan‐19


97

0.00% 96.74% 0.00% 100.00% 10-Jan-19 10‐Jan‐19


98

DATE:

17-Jan-19 17‐Jan‐19
Cum Actual

1.63% 98.37% 0.00% 100.00%


99

Page 64 of 170
B/L Cum. Plan

0.00% 98.37% 0.00% 100.00% 24-Jan-19 24‐Jan‐19

1.63% 100.00% 0.00% 100.00% 31-Jan-19


31‐Jan‐19
25-Oct-18

7-Feb-19
Rev. Recovery Cum. Plan

0.00% 100.00% 0.00% 100.00%


Rev. Recovery Cum. Actual

7‐Feb‐19

0.00% 100.00% 0.00% 100.00% 14-Feb-19


14‐Feb‐19

0.00% 100.00% 0.00% 100.00% 21-Feb-19


## 101 102 103 104

21‐Feb‐19

0.00% 100.00%
Plan
WEEK

Cum Actual
B/L Weekly

Cum. Plan

Cum. Actual
Overall Project

Weekly Plan
B/L Cum. Plan

Weekly Actual

Weekly Actual
Rev. Recovery
Rev. Recovery
Rev. Recovery
Rev. Recovery
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%

1
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2-Mar-17
2‐Mar‐17

2
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9-Mar-17
9‐Mar‐17

3
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 16-Mar-17
16‐Mar‐17

4
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 23-Mar-17
23‐Mar‐17

5
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 30-Mar-17
30‐Mar‐17

6
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6-Apr-17
6‐Apr‐17

7
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 13-Apr-17
13‐Apr‐17

8
20-Apr-17

QATAR BRANCH
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20‐Apr‐17

9
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 27-Apr-17
27‐Apr‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4-May-17

10
4‐May‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11-May-17

11
11‐May‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 18-May-17

12
18‐May‐17

CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION


0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25-May-17

13
25‐May‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1-Jun-17

14
1‐Jun‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8-Jun-17

15
8‐Jun‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 15-Jun-17

16
15‐Jun‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 22-Jun-17

17
22‐Jun‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 29-Jun-17


18
29‐Jun‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6-Jul-17


19
6‐Jul‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 13-Jul-17


20

13‐Jul‐17

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 20-Jul-17 20‐Jul‐17
21

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 27-Jul-17 27‐Jul‐17
22

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3-Aug-17 3‐Aug‐17
23

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10-Aug-17 10‐Aug‐17
24

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 17-Aug-17 17‐Aug‐17
25

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 24-Aug-17 24‐Aug‐17
26

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 31-Aug-17 31‐Aug‐17
27

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7-Sep-17 7‐Sep‐17
28

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 14-Sep-17 14‐Sep‐17
29

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.05% 0.05% 21-Sep-17 21‐Sep‐17
30

28-Sep-17
28‐Sep‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.22% 0.17%
31

5‐Oct‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.39% 0.18% 5-Oct-17
32

12‐Oct‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.59% 0.20% 12-Oct-17
33

19‐Oct‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.07% 0.48% 19-Oct-17
34

26‐Oct‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.74% 0.67% 26-Oct-17
35

2‐Nov‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.95% 0.21% 2-Nov-17
36

9‐Nov‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.21% 0.26% 9-Nov-17
37

16‐Nov‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.51% 0.30% 16-Nov-17
38

23‐Nov‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.79% 0.28% 23-Nov-17
39

30‐Nov‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.30% 0.51% 30-Nov-17
40

7‐Dec‐17
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.11% 0.81% 7-Dec-17
41

14‐Dec‐17
0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 4.32% 0.21% 14-Dec-17
42

S-Curve

21‐Dec‐17
0.05% 0.09% 0.05% 0.09% 0.09% 0.05% 4.53% 0.21% 21-Dec-17
43

28‐Dec‐17
0.38% 0.47% 0.38% 0.47% 0.47% 0.38% 4.91% 0.37% 28-Dec-17
44

4‐Jan‐18
Overall Construction Progress

0.38% 0.84% 0.38% 0.84% 0.84% 0.38% 5.65% 0.74% 4-Jan-18


45

11‐Jan‐18
0.08% 0.93% 0.08% 0.93% 0.93% 0.08% 6.58% 0.93% 11-Jan-18
46

18‐Jan‐18
0.07% 1.00% 0.07% 1.00% 1.00% 0.07% 8.11% 1.53% 18-Jan-18
47

25‐Jan‐18
0.08% 1.08% 0.08% 1.08% 1.08% 0.08% 9.92% 1.81% 25-Jan-18
48

1‐Feb‐18
0.01% 1.09% 0.01% 1.09% 1.09% 0.01% 11.30% 1.38% 1-Feb-18
49

8‐Feb‐18
0.50% 1.60% 0.50% 1.60% 1.60% 0.50% 12.50% 1.19% 8-Feb-18
50

15‐Feb‐18
0.14% 1.73% 0.14% 1.73% 1.73% 0.14% 13.41% 0.91% 15-Feb-18
51

22‐Feb‐18
0.04% 1.78% 0.04% 1.78% 1.78% 0.04% 14.88% 1.47% 22-Feb-18
52

1‐Mar‐18
0.07% 1.849% 0.07% 1.85% 1.85% 0.07% 17.14% 2.26% 1-Mar-18
53

8‐Mar‐18
0.14% 1.99% 0.14% 1.99% 1.99% 0.14% 18.59% 1.44% 8-Mar-18
54

15‐Mar‐18
0.15% 2.14% 0.15% 2.14% 2.14% 0.15% 19.54% 0.95% 15-Mar-18
55

22‐Mar‐18
0.57% 2.72% 0.57% 2.72% 2.72% 0.57% 21.01% 1.47% 22-Mar-18
56

29‐Mar‐18
0.56% 3.28% 0.56% 3.28% 3.28% 0.56% 22.54% 1.53% 29-Mar-18
57

5‐Apr‐18
0.28% 3.55% 0.28% 3.55% 3.55% 0.28% 23.84% 1.30% 5-Apr-18
58

12‐Apr‐18
0.85% 4.40% 0.85% 4.40% 4.40% 0.85% 24.86% 1.03% 12-Apr-18
59

19‐Apr‐18
0.18% 4.57% 0.18% 4.57% 4.57% 0.18% 26.4% 1.6% 19-Apr-18
60

26‐Apr‐18
0.21% 4.78% 0.21% 4.78% 4.78% 0.21% 27.7% 1.2% 26-Apr-18
61

3‐May‐18
0.12% 4.91% 0.12% 4.91% 4.91% 0.12% 28.9% 1.2% 3-May-18
62

10‐May‐18
0.20% 5.10% 0.20% 5.10% 5.10% 0.20% 30.1% 1.2% 10-May-18
63

17‐May‐18
0.17% 5.28% 0.17% 5.28% 5.28% 0.17% 32.0% 1.9% 17-May-18
64

24‐May‐18
0.25% 5.53% 0.25% 5.53% 5.53% 0.25% 33.7% 1.7% 24-May-18
65

31‐May‐18
0.69% 6.22% 0.69% 6.22% 6.22% 0.69% 35.5% 1.8% 31-May-18
66

7‐Jun‐18
1.33% 7.56% 1.33% 7.56% 7.56% 1.33% 37.05% 1.6% 7-Jun-18
67

14‐Jun‐18
0.83% 8.39% 0.83% 8.39% 8.39% 0.83% 38.37% 1.33% 14-Jun-18
68

21‐Jun‐18
0.52% 8.91% 0.52% 8.91% 8.91% 0.52% 40.22% 1.84% 21-Jun-18
69

28‐Jun‐18
0.42% 9.33% 0.42% 9.33% 9.33% 0.42% 42.78% 2.56% 28-Jun-18
70

5‐Jul‐18

0.42% 9.75% 0.42% 9.75% 9.75% 0.42% 44.87% 2.09% 5-Jul-18


71

12‐Jul‐18

0.64% 10.38% 0.64% 10.38% 10.38% 0.64% 46.68% 1.81% 12-Jul-18


72

19‐Jul‐18

0.75% 11.14% 0.75% 11.14% 11.14% 0.75% 48.88% 2.20% 19-Jul-18


73

26‐Jul‐18

0.80% 11.94% 0.80% 11.94% 11.94% 0.80% 50.47% 1.59% 26-Jul-18


74

2‐Aug‐18

0.00% 11.94% 0.00% 11.94% 11.94% 0.00% 51.67% 1.20% 2-Aug-18


75

9‐Aug‐18

1.53% 13.46% 1.53% 13.46% 13.46% 1.53% 53.36% 1.69% 9-Aug-18


76

16‐Aug‐18

1.34% 14.80% 1.34% 14.80% 14.80% 1.34% 55.09% 1.73% 16-Aug-18


77

23‐Aug‐18

1.36% 16.16% 1.36% 16.16% 16.16% 1.36% 58.15% 3.06% 23-Aug-18


78

30‐Aug‐18

0.75% 16.90% 0.75% 16.90% 16.90% 0.75% 60.08% 1.93% 30-Aug-18


79

6‐Sep‐18

1.59% 18.49% 1.59% 18.49% 18.49% 1.59% 62.64% 2.56% 6-Sep-18


80

13‐Sep‐18

2.45% 20.94% 2.45% 20.94% 20.94% 2.45% 66.90% 4.26% 13-Sep-18


81

20‐Sep‐18

1.14% 22.08% 1.14% 22.08% 22.08% 1.14% 70.76% 3.86% 20-Sep-18


82

27‐Sep‐18
PROJECT No. 3963 "

0.63% 22.71% 0.63% 22.71% 22.71% 0.63% 73.97% 3.21% 27-Sep-18


83

4‐Oct‐18

0.45% 23.17% 0.45% 23.17% 23.17% 0.45% 76.11% 2.14% 4-Oct-18


84

11‐Oct‐18

0.88% 24.05% 0.88% 24.05% 24.05% 0.88% 79.96% 3.85% 11-Oct-18


85

18‐Oct‐18

0.90% 24.94% 0.90% 24.94% 24.94% 0.90% 82.78% 2.82% 18-Oct-18


86

25‐Oct‐18

0.02% 24.96% 0.02% 24.96% 24.96% 0.02% 86.57% 3.79% 25-Oct-18


87

1‐Nov‐18
Overall Construction Progress "S" curve

1.00% 25.96% 89.38% 2.81% 1-Nov-18


88

8‐Nov‐18
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS

2.39% 28.35% 91.17% 1.79% 8-Nov-18


89

15‐Nov‐18

2.70% 31.05% 93.38% 2.21% 15-Nov-18


90

22‐Nov‐18

2.83% 33.88% 96.04% 2.67% 22-Nov-18


91

29‐Nov‐18

3.42% 37.30% 98.34% 2.30% 29-Nov-18


92

6‐Dec‐18

4.28% 41.59% 99.22% 0.88% 6-Dec-18


93

13‐Dec‐18

4.03% 45.62% 99.77% 0.55% 13-Dec-18


94

20‐Dec‐18

4.06% 49.68% 99.94% 0.17% 20-Dec-18


95

27‐Dec‐18

6.31% 55.99% 100.00% 0.06% 27-Dec-18


96

3‐Jan‐19

7.49% 63.48% 100.00% 0.00% 3-Jan-19


97

10‐Jan‐19

7.44% 70.92% 100.00% 0.00% 10-Jan-19


98

17‐Jan‐19

1.82% 72.75% 100.00% 0.00% 17-Jan-19 24‐Jan‐19

1.39% 74.14% 100.00% 0.00% 24-Jan-19


31‐Jan‐19

1.95% 76.08% 100.00% 0.00% 31-Jan-19


7‐Feb‐19

2.59% 78.68% 100.00% 0.00% 7-Feb-19


14‐Feb‐19

3.29% 81.97% 100.00% 0.00% 14-Feb-19


21‐Feb‐19

2.93% 84.90% 100.00% 0.00% 21-Feb-19


28‐Feb‐19

3.11% 88.01% 100.00% 0.00% 28-Feb-19


7‐Mar‐19

2.02% 90.03% 100.00% 0.00% 7-Mar-19


14‐Mar‐19
DATE:

1.73% 91.76% 100.00% 0.00% 14-Mar-19


21‐Mar‐19

1.77% 93.53% 100.00% 0.00% 21-Mar-19


28‐Mar‐19

0.89% 94.42% 100.00% 0.00% 28-Mar-19


4‐Apr‐19
25-Oct-18

1.24% 95.67% 100.00% 0.00% 4-Apr-19


11‐Apr‐19

1.27% 96.94% 100.00% 0.00% 11-Apr-19


18‐Apr‐19

0.84% 97.78% 100.00% 0.00% 18-Apr-19 25‐Apr‐19

0.58% 98.37% 100.00% 0.00% 25-Apr-19 2‐May‐19

0.15% 98.52% 100.00% 0.00% 2-May-19 9‐May‐19

0.34% 98.85% 100.00% 0.00% 9-May-19 16‐May‐19

0.23% 99.08% 100.00% 0.00% 16-May-19 23‐May‐19


Cum Actual

0.22% 99.30% 100.00% 0.00% 23-May-19 30‐May‐19


B/L Cum. Plan

0.09% 99.39% 100.00% 0.00% 30-May-19 6‐Jun‐19


Page 65 of 170

0.16% 99.55% 100.00% 0.00% 6-Jun-19 13‐Jun‐19


Rev. Recovery Cum. Plan
Rev. Recovery Cum. Actual

0.07% 99.62% 100.00% 0.00% 13-Jun-19 20‐Jun‐19

0.22% 99.84% 100.00% 0.00% 20-Jun-19 27‐Jun‐19

0.12% 99.96% 100.00% 0.00% 27-Jun-19 4‐Jul‐19

0.04% 100.00% 100.00% 0.00% 4-Jul-19


99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
100.00%

0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%

2‐Aug‐18

Week

Cum Actual
Weekly Actual
B/L Cum. Plan
B/L Weekly Plan

Revised Weekly Plan

Revised Weekly Actual


Overall Construction

Revised Cumulative Plan

Revised Cumulative Actual


9‐Aug‐18

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2-Aug-18 16‐Aug‐18

W-75
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9-Aug-18 23‐Aug‐18

W-76

Doha, Qatar
0.00% 30‐Aug‐18
Cum Actual

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 16-Aug-18

QATAR BRANCH
W-77
B/L Cum. Plan

0.00% 6‐Sep‐18
0.00% 0.00% 0.00% 0.00% 0.00% 0.05% 0.05% 23-Aug-18

CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION


W-78
Revised Cumulative Plan

Revised Cumulative Actual

13‐Sep‐18
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.19% 0.14% 30-Aug-18

W-79
20‐Sep‐18
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.19% 0.00% 6-Sep-18

W-80
27‐Sep‐18
0.17% 0.17% 0.17% 0.17% 0.17% 0.17% 1.30% 1.10% 13-Sep-18

W-81
4‐Oct‐18
0.00% 0.17% 0.00% 0.17% 0.17% 0.00% 4.45% 3.15% 20-Sep-18

W-82
11‐Oct‐18

0.00% 0.17% 0.00% 0.17% 0.17% 0.00% 6.68% 2.23% 27-Sep-18


W-83

18‐Oct‐18

0.00% 0.17% 0.00% 0.17% 0.17% 0.00% 17.34% ##### 4-Oct-18


W-84

25‐Oct‐18

0.00% 0.17% 0.00% 0.17% 0.17% 0.00% 23.87% 6.53% 11-Oct-18


W-85

1‐Nov‐18

0.04% 0.21% 0.04% 0.21% 0.21% 0.04% 30.87% 7.00% 18-Oct-18


W-86

8‐Nov‐18

0.09% 0.30% 0.09% 0.30% 0.30% 0.09% 37.22% 6.35% 25-Oct-18


W-87

15‐Nov‐18

0.00% 0.30% 0.00% -0.30% 44.24% 7.03% 1-Nov-18


W-88

22‐Nov‐18

0.00% 0.30% 0.00% 0.00% 55.66% ##### 8-Nov-18


W-89

29‐Nov‐18

0.00% 0.30% 64.76% 9.10% 15-Nov-18

S-Curve
W-90

6‐Dec‐18

0.00% 0.30% 73.46% 8.70% 22-Nov-18


13‐Dec‐18
W-91

0.00% 0.30% 81.01% 7.55% 29-Nov-18 20‐Dec‐18


Pre-Commisioning & Commissioning Progress
W-92

0.00% 0.30% 87.25% 6.24% 6-Dec-18 27‐Dec‐18


W-93
Pre‐Commisioning & Commisioning Progress "S" Curve

3‐Jan‐19
0.00% 0.30% 96.05% 8.80% 13-Dec-18
W-94

10‐Jan‐19

0.00% 0.30% 100.00% 3.95% 20-Dec-18


W-95

17‐Jan‐19

0.00% 0.30% 100.00% 0.00% 27-Dec-18


W-96

24‐Jan‐19

1.11% 1.40% 100.00% 0.00% 3-Jan-19


W-97

31‐Jan‐19

8.11% 9.52% 100.00% 0.00% 10-Jan-19


W-98

7‐Feb‐19
9.89% 19.41% 100.00% 0.00% 17-Jan-19

14‐Feb‐19
##### 35.08% 100.00% 0.00% 24-Jan-19

7.95% 43.03% 100.00% 0.00% 31-Jan-19 21‐Feb‐19

0.00% 43.03% 100.00% 0.00% 7-Feb-19 28‐Feb‐19

0.00% 43.03% 100.00% 0.00% 14-Feb-19


7‐Mar‐19

0.00% 43.03% 100.00% 0.00% 21-Feb-19


14‐Mar‐19

0.13% 43.16% 100.00% 0.00% 28-Feb-19


21‐Mar‐19

0.00% 43.16% 100.00% 0.00% 7-Mar-19


PROJECT No. 3963 "

28‐Mar‐19
0.88% 44.04% 100.00% 0.00% 14-Mar-19

4‐Apr‐19
2.74% 46.78% 100.00% 0.00% 21-Mar-19

5.26% 52.04% 100.00% 0.00% 28-Mar-19 11‐Apr‐19

4.33% 56.36% 100.00% 0.00% 4-Apr-19 18‐Apr‐19


"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS

1.31% 57.67% 100.00% 0.00% 11-Apr-19


25‐Apr‐19

1.76% 59.44% 100.00% 0.00% 18-Apr-19


2‐May‐19

5.10% 64.54% 100.00% 0.00% 25-Apr-19

9‐May‐19

7.44% 71.98% 100.00% 0.00% 2-May-19

16‐May‐19
##### 84.03% 100.00% 0.00% 9-May-19
Page 66 of 170

23‐May‐19
5.66% 89.68% 100.00% 0.00% 16-May-19
DATE: 25-Oct-18

##### 100.00% 100.00% 0.00% 23-May-19


W-99 W-100 W-101 W-102 W-103 W-104 W-105 W-106 W-107 W-108 W-109 W-110 W-111 W-112 W-113 W-114 W-115 W-116 W-117
Week

Cum Act
Week Act
Cum. Plan
Week Plan
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%

Overall Project C
0.00% 0.00% 0.00% 0.00% 22-Jan-19

100
0.00% 0.00% 0.00% 0.00% 29-Jan-19

101

Doha, Qatar
QATAR BRANCH
0.00% 0.00% 0.00% 0.00% 5-Feb-19

102
0.00% 0.00% 0.00% 0.00% 12-Feb-19

103
0.00% 0.00% 0.00% 0.00% 19-Feb-19

104

CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION


0.00% 0.00% 0.00% 0.00% 26-Feb-19

0.00% 0.00% 0.00% 0.00% 105


106 5-Mar-19

0.00% 0.00% 0.00% 0.00% 12-Mar-19


107

0.00% 0.00% 0.00% 0.00% 19-Mar-19


108

0.00% 0.00% 0.00% 0.00% 26-Mar-19


109

0.00% 0.00% 0.00% 0.00% 2-Apr-19


110

0.00% 0.00% 0.00% 0.00% 9-Apr-19


111

0.00% 0.00% 0.00% 0.00% 16-Apr-19


112

0.00% 0.00% 0.00% 0.00% 23-Apr-19


113

S-Curve

0.00% 0.00% 0.00% 0.00% 30-Apr-19


114

Overall Project Close-Out


Close‐Out "S"Curve

0.00% 0.00% 0.00% 0.00% 7-May-19


115

0.00% 0.00% 0.00% 0.00% 14-May-19


116

0.00% 0.00% 0.00% 0.00% 21-May-19


117

0.00% 0.00% 11.29% 11.29% 28-May-19


118

0.00% 0.00% 22.58% 11.29% 4-Jun-19


119

0.00% 0.00% 33.87% 11.29% 11-Jun-19


120

0.00% 0.00% 45.16% 11.29% 18-Jun-19


121

SEPARATORS IN ALL DEGASSING STATIONS


EPIC OF REPLACMENT OF THREE PHASE TEST

0.00% 0.00% 56.45% 11.29% 25-Jun-19


122

DATE:

0.00% 0.00% 67.74% 11.29% 2-Jul-19


123

0.00% 0.00% 79.03% 11.29% 9-Jul-19


25-Oct-18
124

0.00% 0.00% 90.32% 11.29% 16-Jul-19


125
Cum Act

0.00% 0.00% 100.00% 9.68% 23-Jul-19


Week Act

126
Cum. Plan

Page 67 of 170

0.00% 0.00% 100.00% 0.00% 30-Jul-19


127
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%

0.00% 0.00% 100.00% 0.00% 6-Aug-19


128
PROJECT PLANNING PACKAGE

Attachment 6

MANPOWER HISTOGRAM

Page 68 of 170
Sr.No. DESCRIPTION PEAK MAN Project Timeline (Monthwise)
QTY MONTH
Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
A ALL KHATIYA STATIONS
1 CIVIL TEAM 40 95 40 35 20

2 INSTRUMENT TEAM 40 82 12 40 30

3 ELECTRICAL TEAM 24 48 24 24
4 PIPING TEAM 24 60 12 24 24
B JELAHA STATION - -
1 CIVIL TEAM 30 107 20 30 25 20 12

2 INSTRUMENT TEAM 24 96 24 24 24 12 12

3 ELECTRICAL TEAM 16 66 14 16 16 10 10
4 PIPING TEAM 20 66 14 20 20 12

C FAHAHIL SOUTH - -
1 CIVIL TEAM 22 102 18 22 17 15 12 10 8
2 INSTRUMENT TEAM 20 94 14 20 20 20 20
3 ELECTRICAL TEAM 12 56 12 12 12 10 10
4 PIPING TEAM 12 70 10 12 12 12 12 12
D FAHAHIL NORTH - -
1 CIVIL TEAM 25 109 22 25 22 20 10 10

2 INSTRUMENT TEAM 16 72 12 16 16 16 12
3 ELECTRICAL TEAM 12 64 6 12 12 12 12 10

4 PIPING TEAM 12 60 12 12 12 12 12

E FAHAHIL MAIN - -

1 CIVIL TEAM 22 130 16 22 22 20 20 15 15

2 INSTRUMENT TEAM 20 72 20 20 20 12

3 ELECTRICAL TEAM 12 64 6 12 12 12 12 10
4 PIPING TEAM 20 88 8 8 20 20 20 12

TOTAL 332 1,601 140 290 332 271 232 203 133 - - - - -
-
-
-
- REPLACEMENT THREE PHASE TEST SEPARATOR
-
00 ISSUED FOR APPROVAL 1-Nov-18 VS
REV NO DETAIL DATE BY

Page 69 of 170
Sr.No. DESCRIPTION PEAK MAN Project Timeline (Monthwise)
QTY MONTHS
Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19
1 CONTRACT REPRESENTATIVE 1 9 1 1 1 1 1 1 1 1 1
2 DPEPUTY PROJECT MANAGER 1 9 1 1 1 1 1 1 1 1 1
2 CONSTRUCTION MANAGER 1 9 1 1 1 1 1 1 1 1 1
3 QA/QC MANAGER 1 9 1 1 1 1 1 1 1 1 1

4 HSE MANAGER 1 9 1 1 1 1 1 1 1 1 1

5 COMMISSIONG MANANGER 1 9 1 1 1 1 1 1 1 1 1
6 SR. PLANNING/COORDINATOR 1 9 1 1 1 1 1 1 1 1 1
7 SR. PLANNING ENGINEER 1 9 1 1 1 1 1 1 1 1 1
8 SITE PLANNING ENGINEER 1 9 1 1 1 1 1 1 1 1 1

9 LEAD HSE OFFICER 1 9 1 1 1 1 1 1 1 1 1

10 HSE OFFICERS 14 104 12 14 14 14 14 14 10 6 6


11 MECHANICAL ENGINEER 1 9 1 1 1 1 1 1 1 1 1
12 INSTRUMENT ENGINEER 1 9 1 1 1 1 1 1 1 1 1

13 ELETRICAL ENGINEER 1 9 1 1 1 1 1 1 1 1 1
14 QA/QC ENGINEER 1 9 1 1 1 1 1 1 1 1 1
15 QA /QC INSPECTOR 6 54 6 6 6 6 6 6 6 6 6
16 CIVIL ENGINEER 1 9 1 1 1 1 1 1 1 1 1
17 COMMISSIONG ENGINEER 1 6 1 1 1 1 1 1
18 ADMIN TEAM 6 54 6 6 6 6 6 6 6 6 6
19 PRO OFFICCER 1 9 1 1 1 1 1 1 1 1 1
20 PTW - COORDINATOR 1 9 1 1 1 1 1 1 1 1 1
21 SITE SUPERVISORS - PTW 20 164 20 20 20 20 20 20 20 12 12

- -

TOTAL 64 535 61 64 64 63 63 64 60 48 48 - - - -
- -
- DIRECT MANPOWER DEPLOYMENT SCHEDULE
- CIVIL, MECHANICAL AND E&I WORKS
- - TITLE: FOR
- REPLACEMENT THREE PHASE TEST SEPARATOR
00 ISSUED FOR APPROVAL 1-Nov-18 VS AT DUKHAN, QATAR
REV NO DETAIL DATE BY

Page 70 of 170
PROJECT PLANNING PACKAGE

Attachment 7

ENGINEERING DOCUMENT DELIVERABLE REGISTER

Page 71 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS

1 1 GENERAL 3963‐DGEN‐0‐00‐0002 OT ENGINEERING DOCUMENT & DELIVERABLES REGISTER (EDDR) 1 A 0.417% 14‐Mar‐17 24‐Mar‐17 29‐Mar‐17 14‐May‐17 4‐Jun‐17 14‐Jun‐17 31‐Oct‐18 12‐Mar‐17 20‐Mar‐17 29‐Mar‐17 3‐Aug‐17 3‐Aug‐17 3‐Aug‐17 22‐Jul‐19 12‐Mar‐17 20‐Mar‐17 29‐Mar‐17 3‐Aug‐17 3‐Aug‐17 3‐Aug‐17 95% 95% 0% 0.396% 0.396%
2 1 GENERAL 3963‐DGEN‐0‐29‐0001 OT DESIGN BASIS MEMORANDUM 1 A 0.222% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 15‐Mar‐17 29‐Mar‐17 29‐Mar‐17 29‐Jun‐17 26‐Jul‐17 7‐Dec‐17 22‐Jul‐19 15‐Mar‐17 29‐Mar‐17 29‐Mar‐17 29‐Jun‐17 26‐Jul‐17 7‐Dec‐17 95% 95% 0% 0.211% 0.211%
3 1 GENERAL 3963‐DGEN‐0‐04‐0003 OT ENGINEERING EXECUTION PLAN 1 A 0.278% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 10‐May‐17 10‐May‐17 10‐May‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 10‐May‐17 10‐May‐17 10‐May‐17 95% 95% 0% 0.264% 0.264%
4 1 GENERAL 3963‐DGEN‐0‐17‐0001 OT SITE VISIT (1) ‐ REPORT 1 A 0.972% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 29‐Mar‐17 25‐May‐17 21‐Jun‐17 21‐Jun‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 29‐Mar‐17 25‐May‐17 21‐Jun‐17 21‐Jun‐17 95% 95% 0% 0.924% 0.924%
5 1 GENERAL 3963‐DGEN‐0‐17‐0002 OT SITE VISIT (2) ‐ REPORT 1 A 0.417% 29‐Apr‐17 1‐May‐17 4‐May‐17 25‐May‐17 15‐Jun‐17 25‐Jun‐17 31‐Oct‐18 2‐May‐17 4‐May‐17 4‐May‐17 1‐Jun‐17 17‐Jul‐17 18‐Jul‐17 22‐Jul‐19 2‐May‐17 4‐May‐17 4‐May‐17 1‐Jun‐17 17‐Jul‐17 18‐Jul‐17 95% 95% 0% 0.396% 0.396%
6 1 GENERAL 3963‐DGEN‐0‐17‐0003 OT SITE VISIT‐3 REPORT BY SYSTEM OEM (YOKOGAWA) FOR KAHM / KAHN / KAHS / JALM 1 A 0.056% 30‐Jul‐17 7‐Aug‐17 10‐Aug‐17 31‐Aug‐17 14‐Sep‐17 21‐Sep‐17 31‐Oct‐18 22‐Sep‐17 23‐Sep‐17 25‐Sep‐17 19‐Oct‐17 19‐Oct‐17 14‐Dec‐17 22‐Jul‐19 22‐Sep‐17 23‐Sep‐17 25‐Sep‐17 19‐Oct‐17 19‐Oct‐17 14‐Dec‐17 95% 95% 0% 0.053% 0.053%
7 1 GENERAL 3963‐DGEN‐0‐17‐0004 OT SITE VISIT‐4 REPORT BY SYSTEM OEM (EMERSON) FOR FAHM / FAHN / FAHS 1 A 0.042% 30‐Jul‐17 7‐Aug‐17 10‐Aug‐17 31‐Aug‐17 14‐Sep‐17 21‐Sep‐17 31‐Oct‐18 27‐Jul‐17 30‐Jul‐17 31‐Jul‐17 5‐Oct‐17 8‐Oct‐17 8‐Oct‐17 22‐Jul‐19 27‐Jul‐17 30‐Jul‐17 31‐Jul‐17 5‐Oct‐17 8‐Oct‐17 8‐Oct‐17 95% 95% 0% 0.040% 0.040%
8 7 GENERAL 3963‐DGEN‐0‐00‐0001 OT MISCELLANEOUS ‐ GENERAL 0 0.042% 16‐Aug‐17 16‐Aug‐17 16‐Aug‐17 23‐Aug‐17 23‐Aug‐17 30‐Aug‐17 31‐Oct‐18 12‐Jan‐18 15‐Jan‐18 18‐Jan‐18 21‐Jan‐18 26‐Jan‐18 27‐Jan‐18 22‐Jul‐19 12‐Jan‐18 15‐Jan‐18 18‐Jan‐18 21‐Jan‐18 26‐Jan‐18 27‐Jan‐18 95% 95% 0% 0.040% 0.040%
9 7 PROCESS 3963‐FAHM‐6‐52‐0001 OT DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION GENERAL , PROCESS FLOW DIAGRAM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
10 7 PROCESS 3963‐FAHM‐6‐52‐0002 OT PFD FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ FIRST STAGE SEPARATOR & PWT 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 5‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 5‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
11 7 PROCESS 3963‐FAHM‐6‐52‐0003 OT PFD FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ SEPARATORS SYSTEM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
12 7 PROCESS 3963‐FAHN‐6‐52‐0001 OT PFD FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐ FIRST STAGE SEPARATOR & PWI 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 14‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 14‐Dec‐17 95% 95% 0% 0.053% 0.053%
13 7 PROCESS 3963‐FAHS‐6‐52‐0001 OT PFD FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ FIRST STAGE SEPARATOR & PWT 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
14 7 PROCESS 3963‐JALM‐6‐52‐0001 OT DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ GENERAL, PROCESS FLOW DIAGRAM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
15 7 PROCESS 3963‐JALM‐6‐52‐0002 OT PFD FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ JALEHA/DIYAB PROD. & FLOW LINES 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
16 7 PROCESS 3963‐JALM‐6‐52‐0003 OT PFD FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ FIRST STAGE SEPARATORS & PWT 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
17 7 PROCESS 3963‐JALM‐6‐52‐0004 OT PFD FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ SEPARATION TRAIN 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
18 7 PROCESS 3963‐KAHM‐6‐52‐0001 OT DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ GENERAL, PROCESS FLOW DIAGRAM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
19 7 PROCESS 3963‐KAHM‐6‐52‐0002 OT PFD FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ FIRST STAGE SEPARATORS 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
20 7 PROCESS 3963‐KAHM‐6‐52‐0003 OT PFD FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ PRODUCED WATER TREATMENT 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
21 7 PROCESS 3963‐KAHN‐6‐52‐0001 OT DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ GENERAL PROCESS FLOW DIAGRAM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
22 7 PROCESS 3963‐KAHS‐6‐52‐0001 OT DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ GENERAL PROCESS FLOW DIAGRAM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
23 7 PROCESS 3963‐KAHS‐6‐52‐0002 OT DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ GENERAL PROCESS FLOW DIAGRAM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
24 7 PROCESS 3963‐FAHM‐6‐52‐0004 OT PFD FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION 3 PHASE TEST SEPERATOR, SEPARATOR SYSTEM 1 A 0.069% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.066% 0.066%
25 7 PROCESS 3963‐DGEN‐6‐17‐0001 OT PROCESS SIMULATION & H&MB REPORT 1 A 0.111% 1‐Apr‐17 11‐Apr‐17 16‐Apr‐17 17‐May‐17 7‐Jun‐17 17‐Jun‐17 31‐Oct‐18 10‐Apr‐17 11‐Apr‐17 12‐Apr‐17 21‐Jun‐17 13‐Jul‐17 18‐Jul‐17 22‐Jul‐19 10‐Apr‐17 11‐Apr‐17 12‐Apr‐17 21‐Jun‐17 13‐Jul‐17 18‐Jul‐17 95% 95% 0% 0.106% 0.106%
26 7 PROCESS 3963‐DGEN‐6‐12‐0001 OT 3 ‐ PHASE TEST SEPARATOR SIZING CALCULATION  1 B 0.097% 12‐Apr‐17 22‐Apr‐17 27‐Apr‐17 28‐May‐17 18‐Jun‐17 28‐Jun‐17 31‐Oct‐18 18‐Apr‐17 12‐Jun‐17 13‐Jun‐17 27‐Aug‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 18‐Apr‐17 12‐Jun‐17 13‐Jun‐17 27‐Aug‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
27 7 PROCESS 3963‐DGEN‐6‐00‐0001 OT PROJECT DRAWING INDEX (PROCESS) 1 1 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 4‐Jun‐17 4‐Jun‐17 2‐Oct‐17 2‐Oct‐17 2‐Oct‐17 22‐Jul‐19 18‐Apr‐17 4‐Jun‐17 4‐Jun‐17 2‐Oct‐17 2‐Oct‐17 2‐Oct‐17 95% 95% 0% 0.053% 0.053%
28 7 PROCESS 3963‐DGEN‐6‐50‐0001 OT LEGEND, SYMBOLS & ABBREVIATIONS (2 SHEETS) 1 B 0.097% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 4‐May‐17 4‐May‐17 19‐Jun‐17 21‐Aug‐17 21‐Aug‐17 22‐Jul‐19 18‐Apr‐17 4‐May‐17 4‐May‐17 19‐Jun‐17 21‐Aug‐17 21‐Aug‐17 95% 95% 0% 0.092% 0.092%
29 7 PROCESS 3963‐KAHM‐6‐50‐0001 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐MANIFOLD SHUTDOWN VALVES 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 3‐Jan‐18 22‐Jul‐19 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
30 7 PROCESS 3963‐KAHM‐6‐50‐0002 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 24‐V‐XXX1 1 A 0.083% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 3‐Jan‐18 22‐Jul‐19 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 3‐Jan‐18 95% 95% 0% 0.079% 0.079%
31 7 PROCESS 3963‐KAHM‐6‐50‐0003 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐NEW 3 PHASE TEST SEPARATOR 24‐V‐XXX1 1 A 0.083% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 21‐Jan‐18 22‐Jul‐19 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 21‐Jan‐18 95% 95% 0% 0.079% 0.079%
32 7 PROCESS 3963‐KAHM‐6‐50‐0005 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ DEGASSING VESSEL 24‐V‐4005 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 3‐Jan‐18 22‐Jul‐19 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
33 7 PROCESS 3963‐KAHM‐6‐50‐0006 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ GAS GATHERING STATION  1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 3‐Jan‐18 22‐Jul‐19 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
34 7 PROCESS 3963‐KAHM‐6‐50‐0007 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ CRUDE OIL FROM KHATIYAH NORTH 1 B 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 3‐May‐17 15‐Jun‐17 11‐Sep‐17 12‐Sep‐17 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 3‐May‐17 15‐Jun‐17 11‐Sep‐17 12‐Sep‐17 95% 95% 0% 0.053% 0.053%
35 7 PROCESS 3963‐KAHM‐6‐50‐0008 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ CRUDE OIL FROM KHATIYAH SOUTH 1 B 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 18‐May‐17 15‐Jun‐17 11‐Sep‐17 12‐Sep‐17 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 18‐May‐17 15‐Jun‐17 11‐Sep‐17 12‐Sep‐17 95% 95% 0% 0.053% 0.053%
36 7 PROCESS 3963‐KAHM‐6‐51‐0001 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ DRAIN COLLECTION  1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 5‐Oct‐17 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 5‐Oct‐17 95% 95% 0% 0.053% 0.053%
37 7 PROCESS 3963‐KAHM‐6‐51‐0002 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐PROCESS FLARE COLLECTION  1 B 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 5‐Oct‐17 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 5‐Oct‐17 95% 95% 0% 0.053% 0.053%
38 7 PROCESS 3963‐KAHM‐6‐51‐0003 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐INSTRUMENT AIR DISTRIBUTION 1 B 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 5‐Oct‐17 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 5‐Oct‐17 95% 95% 0% 0.053% 0.053%
39 7 PROCESS 3963‐KAHN‐6‐50‐0001 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ NEW 3 PHASE TEST SEPARATOR 22‐V‐XXX1 1 A 0.083% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 9‐Jul‐17 26‐Sep‐17 21‐Jan‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 9‐Jul‐17 26‐Sep‐17 21‐Jan‐18 95% 95% 0% 0.079% 0.079%
40 7 PROCESS 3963‐KAHN‐6‐50‐0003 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR CONT. SKID 22‐V‐ 1 A 0.083% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
41 7 PROCESS 3963‐KAHN‐6‐50‐0004 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ PROD WATER DEGASSING VESSEL 22‐V‐7490 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
42 7 PROCESS 3963‐KAHN‐6‐50‐0005 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ PROD WATER DEGASSING VESSEL 22‐V‐7495 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
43 7 PROCESS 3963‐KAHN‐6‐50‐0006 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ WET LIFT GAS KO DRUM 22‐V‐4601 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
44 7 PROCESS 3963‐KAHN‐6‐50‐0007 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ PIG LAUNCHER 22‐Z‐7020 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
45 7 PROCESS 3963‐KAHN‐6‐50‐0008 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ 3 PHASE TEST SEP. CONT. SKID 22‐V‐4002 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
46 7 PROCESS 3963‐KAHN‐6‐50‐0009 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ FIRST STAGE 3 PHASE SEP. 22‐V‐7480 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
47 7 PROCESS 3963‐KAHN‐6‐50‐0010 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ MANIFOLD SHUTDOWN VALVES 1 B 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
48 7 PROCESS 3963‐KAHN‐6‐51‐0001 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ INSTRUMENT AIR DISTRIBUTION 1 A 0.056% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.053% 0.053%
49 7 PROCESS 3963‐KAHN‐6‐52‐0002 OT DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ SEPARATORS SYSTEM PROCESS FLOW DIAGRAM 1 A 0.056% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 20‐Jul‐17 10‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.053% 0.053%
50 7 PROCESS DEM‐3963‐KAHM‐6‐50‐0001 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐MANIFOLD SHUTDOWN VALVES ,P&ID (DEMO 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 2‐Jan‐18 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 2‐Jan‐18 95% 95% 0% 0.040% 0.040%
51 7 PROCESS DEM‐3963‐KAHM‐6‐50‐0002 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 24‐V‐7900,P&ID (D 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 2‐Jan‐18 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 2‐Jan‐18 95% 95% 0% 0.040% 0.040%
52 7 PROCESS DEM‐3963‐KAHM‐6‐50‐0003 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 24‐V7900 CTRL SKI 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 2‐Jan‐18 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 2‐Jan‐18 95% 95% 0% 0.040% 0.040%
53 7 PROCESS DEM‐3963‐KAHM‐6‐50‐0004 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ DEGASSING VESSEL 24‐V‐4005,P&ID (DEMOLI 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 2‐Jan‐18 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 15‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.040% 0.040%
54 7 PROCESS DEM‐3963‐KAHM‐6‐51‐0003 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ IA DISTRIBUTION P&ID (DEMOLITION) 1 B 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 24‐Sep‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 24‐Sep‐17 95% 95% 0% 0.040% 0.040%
55 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0001 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 22‐V‐7400 (DEMO 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 24‐Aug‐17 4‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 24‐Aug‐17 4‐Oct‐17 95% 95% 0% 0.040% 0.040%
56 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0002 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR CONT. SKID 22‐V‐ 1 B 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
57 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0003 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐3 PHASE TEST SEPARATOR CONT. SKID 22‐V‐7 1 B 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
58 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0004 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ PROD WATER DEGASSING VESSEL 22‐V‐7490 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.040% 0.040%
59 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0005 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ PROD WATER DEGASSING VESSEL 22‐V‐7495 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.040% 0.040%
60 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0006 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ WET LIFT GAS KO DRUM 22‐V‐4601 (DEMOL 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
61 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0007 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ PIG LAUNCHER 22‐Z‐7020 (DEMOLITION) 1 B 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
62 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0008 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ 3 PHASE TEST SEP. CONT SKID 22‐V‐4002 (D 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
63 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0009 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ FIRST STAGE PHASE SEP. 22‐V‐7480 (DEMOL 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
64 7 PROCESS DEM‐3963‐KAHN‐6‐50‐0010 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ MANIFOLD SHUTDOWN VALVES (DEMOLITIO 1 B 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 19‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
65 7 PROCESS DEM‐3963‐KAHN‐6‐51‐0001 DEM P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ INSTRUMENT AIR DISTRIBUTION (DEMOLITI 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 3‐May‐17 22‐Jun‐17 22‐Jun‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
66 7 PROCESS 3963‐FAHM‐6‐50‐0001 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ NEW 3 PHASE TEST SEPARATOR 14‐V‐XXX1 1 A 0.083% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 21‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.079% 0.079%
67 7 PROCESS 3963‐FAHM‐6‐50‐0003 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ HYDROCYCLONE & DEGASSER SKID SHT.2 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 2‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
68 7 PROCESS 3963‐FAHM‐6‐50‐0004 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ GAS & OIL DISTRIBUTION 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 95% 95% 0% 0.053% 0.053%
69 7 PROCESS 3963‐FAHM‐6‐50‐0005 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ 3RD STAGE SUCTION KO DRUM 14‐V‐5205, 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 95% 95% 0% 0.053% 0.053%
70 7 PROCESS 3963‐FAHM‐6‐50‐0006 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ 3‐PHASE SEPARATOR 14‐V‐4001 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 95% 95% 0% 0.053% 0.053%
71 7 PROCESS 3963‐FAHM‐6‐50‐0007 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ S.D.V & R.V. STATION & DIST. MANIFOLD 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 14‐Jan‐18 95% 95% 0% 0.053% 0.053%
72 7 PROCESS 3963‐FAHM‐6‐51‐0001 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ DRAIN COLLECTION 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 2‐Jan‐18 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
73 7 PROCESS 3963‐FAHM‐6‐51‐0002 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ TANK FLARE COLLECTION 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 2‐Jan‐18 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
74 7 PROCESS 3963‐FAHM‐6‐51‐0003 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ INSTRUMENT AIR DISTRIBUTION 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 2‐Jan‐18 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
75 7 PROCESS 3963‐KAHS‐6‐50‐0001 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ NEW 3 PHASE TEST SEPARATOR 23‐V‐XXX1 1 A 0.083% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 21‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.079% 0.079%
76 7 PROCESS 3963‐KAHS‐6‐50‐0003 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ 3 PHASE SEPARATION HEADERS 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 22‐Jul‐19 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
77 7 PROCESS 3963‐KAHS‐6‐50‐0004 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ DEGASSING VESSEL 23‐V‐7280 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 22‐Jul‐19 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
78 7 PROCESS 3963‐KAHS‐6‐50‐0005 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ HYDROCARBON CONDENSATE LINES 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
79 7 PROCESS 3963‐KAHS‐6‐50‐0006 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ MANIFOLD SHUTDOWN VALVES 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
80 7 PROCESS 3963‐KAHS‐6‐51‐0001 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ DRAIN SYSTEM 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 2‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
81 7 PROCESS 3963‐KAHS‐6‐51‐0002 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ FLARE COLLECTION 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
82 7 PROCESS 3963‐KAHS‐6‐51‐0003 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ INSTRUMENT AIR DISTRIBUTION 1 A 0.056% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 22‐Jul‐19 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
83 7 PROCESS DEM‐3963‐FAHM‐6‐50‐0001 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐3 PHASE TEST SEPARATOR 14‐V‐1900 (DEMOLIT 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.040% 0.040%
84 7 PROCESS DEM‐3963‐FAHM‐6‐50‐0002 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐3 PHASE TEST SEPARATOR 14‐V‐1900 CTRL SKID 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.040% 0.040%
85 7 PROCESS DEM‐3963‐FAHM‐6‐50‐0003 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐HYDROCYCLONE & DEGASSER SKID SHT.2 (DEM 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
86 7 PROCESS DEM‐3963‐FAHM‐6‐50‐0004 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐GAS & OIL DISTRIBUTION (DEMOLITION) 1 B 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 5‐Oct‐17 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
87 7 PROCESS DEM‐3963‐FAHM‐6‐50‐0005 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ S.D.V & R.V. STATION & DIST. MANIFOLD (DEM 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 5‐Oct‐17 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
88 7 PROCESS DEM‐3963‐FAHM‐6‐51‐0001 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ DRAIN COLLECTION (DEMOLITION) 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 4‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 4‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.040% 0.040%
89 7 PROCESS DEM‐3963‐FAHM‐6‐51‐0004 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐FLARE COLLECTION (DEMOLITION) 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 27‐Jun‐17 2‐Jul‐17 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 27‐Jun‐17 2‐Jul‐17 95% 95% 0% 0.040% 0.040%
90 7 PROCESS DEM‐3963‐FAHM‐6‐51‐0002 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ TANK FLARE COLLECTION (DEMOLITION) 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 27‐Apr‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.040% 0.040%
91 7 PROCESS DEM‐3963‐FAHM‐6‐51‐0003 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐INSTRUMENT AIR DISTRIBUTION (DEMOLITION) 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 27‐Sep‐17 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 27‐Sep‐17 95% 95% 0% 0.040% 0.040%
92 7 PROCESS DEM‐3963‐KAHS‐6‐51‐0001 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐DRAIN SYSTEM (DEMOLITION) 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.040% 0.040%
93 7 PROCESS DEM‐3963‐KAHS‐6‐51‐0003 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐INSTRUMENT AIR DISTRIBUTION (DEMOLITIO 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 17‐Jun‐17 22‐Jun‐17 22‐Jul‐19 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 17‐Jun‐17 22‐Jun‐17 95% 95% 0% 0.040% 0.040%
94 7 PROCESS 3963‐FAHM‐6‐51‐0004 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ FLARE COLLECTION 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.040% 0.040%
95 7 PROCESS 3963‐FAHN‐6‐50‐0001 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐ MANIFOLD SHUTDOWN VALVES 1 B 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.053% 0.053%
96 7 PROCESS 3963‐FAHN‐6‐50‐0002 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐NEW 3 PHASE TEST SEPARATOR 12‐V‐XXX1 1 A 0.083% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 21‐Jan‐18 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 21‐Jan‐18 95% 95% 0% 0.079% 0.079%
97 7 PROCESS 3963‐FAHN‐6‐50‐0004 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐ HYDROCYCLONE & DEGASSER SKID SHT.2 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
98 7 PROCESS 3963‐FAHN‐6‐50‐0005 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐PIG LAUNCHER 12‐Z‐0810 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
99 7 PROCESS 3963‐FAHN‐6‐51‐0001 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐DRAIN SYSTEM 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
100 7 PROCESS 3963‐FAHN‐6‐51‐0002 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐PROCESS FLARE K.O DRUM 12‐V‐4017 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
101 7 PROCESS 3963‐FAHN‐6‐51‐0003 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐INSTRUMENT AIR DISTRIBUTION 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 25‐Sep‐17 2‐Jan‐18 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 25‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
102 7 PROCESS 3963‐FAHS‐6‐50‐0001 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ MANIFOLD SHUTDOWN VALVES 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
103 7 PROCESS 3963‐FAHS‐6‐50‐0002 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ NEW 3 PHASE TEST SEPARATOR 13‐V‐XXX1 CT 1 A 0.083% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 21‐Jan‐18 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 21‐Jan‐18 95% 95% 0% 0.079% 0.079%
104 7 PROCESS 3963‐FAHS‐6‐50‐0004 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ HYDROCYCLONE & DEGASSER SKID SHT. 2 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
105 7 PROCESS 3963‐FAHS‐6‐50‐0005 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ PIG LAUNCHER 13‐Z‐0403 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
106 7 PROCESS 3963‐FAHS‐6‐51‐0001 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐DRAIN SYSTEM 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
107 7 PROCESS 3963‐FAHS‐6‐51‐0002 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐PROCESS FLARE K.O DRUM 13‐V‐4043 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
108 7 PROCESS 3963‐FAHS‐6‐51‐0003 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ INSTRUMENT AIR DISTRIBUTION SYSTEM 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 13‐May‐17 15‐May‐17 18‐May‐17 28‐Sep‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 13‐May‐17 15‐May‐17 18‐May‐17 28‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.053% 0.053%
109 7 PROCESS DEM‐3963‐FAHN‐6‐50‐0001 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐MANIFOLD SHUTDOWN VALVES (DEMOLITION 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
110 7 PROCESS DEM‐3963‐FAHN‐6‐50‐0002 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐3 PHASE TEST SEPARATOR 12‐V‐0800 (DEMOL 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
111 7 PROCESS DEM‐3963‐FAHN‐6‐50‐0003 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐3 PHASE TEST SEPARATOR 12‐V‐0800 CTRL SKI 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
112 7 PROCESS DEM‐3963‐FAHN‐6‐50‐0004 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐HYDROCYCLONE & DEGASSER SKID SHT 2 (DEM 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
113 7 PROCESS DEM‐3963‐FAHN‐6‐50‐0005 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐ PIG LAUNCHER 12‐Z‐0810 (DEMOLITION) 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 5‐Oct‐17 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 5‐Oct‐17 95% 95% 0% 0.053% 0.053%
114 7 PROCESS DEM‐3963‐FAHN‐6‐51‐0001 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐ DRAIN SYSTEM (DEMOLITION) 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
115 7 PROCESS DEM‐3963‐FAHN‐6‐51‐0002 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐PROCESS FLARE K.O DRUM 12‐V‐4017 (DEMO 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 3‐Jan‐18 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 2‐Jul‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
116 7 PROCESS DEM‐3963‐FAHN‐6‐51‐0003 DEM P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐INSTRUMENT AIR DISTRIBUTION (DEMOLITION 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
117 7 PROCESS DEM‐3963‐FAHS‐6‐50‐0001 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐MANIFOLD SHUTDOWN VALVES (DEMOLITION 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
118 7 PROCESS DEM‐3963‐FAHS‐6‐50‐0002 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 13‐V‐400 (DEMOLIT 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
119 7 PROCESS DEM‐3963‐FAHS‐6‐50‐0003 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ 3 PHASE TEST SEP. 13‐V‐400 CTRL SKID (DEMO 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
120 7 PROCESS DEM‐3963‐FAHS‐6‐50‐0004 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ HYDROCYCLONE & DEGASSER SKID SHT 2 (DEM 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
121 7 PROCESS DEM‐3963‐FAHS‐6‐50‐0005 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ PIG LAUNCHER 13‐Z‐0403 (DEMOLITION) 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 11‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.053% 0.053%
122 7 PROCESS DEM‐3963‐FAHS‐6‐51‐0001 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ DRAIN SYSTEM (DEMOLITION) 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.053% 0.053%
123 7 PROCESS DEM‐3963‐FAHS‐6‐51‐0002 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ PROCESS FLARE K.O DRUM 13‐V‐4043 (DEMO 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.053% 0.053%

Page 1 of 13
Page 72 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
124 7 PROCESS DEM‐3963‐FAHS‐6‐51‐0003 DEM P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ INSTRUMENT AIR DISTRIBUTION SYSTEM (DEM 1 A 0.056% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.053% 0.053%
125 7 PROCESS 3963‐JALM‐6‐50‐0003 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ MANIFOLD SHUTDOWN VALVES 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
126 7 PROCESS 3963‐JALM‐6‐50‐0004 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ OIL STABILIZATION HEAT EXCH. 31‐E‐4002 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
127 7 PROCESS 3963‐JALM‐6‐50‐0005 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ DEGASSER VESSEL 31‐V‐4009 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
128 7 PROCESS 3963‐JALM‐6‐50‐0006 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ PRODUCED GAS K.O. POT 31‐V‐5020 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
129 7 PROCESS 3963‐JALM‐6‐50‐0007 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ WET LIFTGAS KO DRUM 31‐V‐4901 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
130 7 PROCESS 3963‐JALM‐6‐50‐0008 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ GAS GATHERING STATION 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
131 7 PROCESS 3963‐JALM‐6‐50‐0009 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR MANIFOLD SHUTDOW 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
132 7 PROCESS 3963‐JALM‐6‐51‐0001 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ DRAIN COLLECTION 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
133 7 PROCESS 3963‐JALM‐6‐51‐0002 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐FLARE COLLECTION 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
134 7 PROCESS 3963‐JALM‐6‐51‐0003 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐INSTRUMENT AIR DISTRIBUTION 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 11‐Oct‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 11‐Oct‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
135 7 PROCESS DEM‐3963‐JALM‐6‐50‐0001 DEM P&ID FOR DUKHAN ‐ JALEHA MAIN DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 31‐V‐42 (DEMOLITION 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 22‐Jul‐19 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 95% 95% 0% 0.079% 0.079%
136 7 PROCESS DEM‐3963‐JALM‐6‐50‐0002 DEM P&ID FOR DUKHAN ‐ JALEHA MAIN DEGASSING STATION ‐3 PHASE TEST SEPARATOR 31‐V‐42, CONR. SKID ( 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 27‐Sep‐17 27‐Sep‐17 22‐Jul‐19 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 27‐Sep‐17 27‐Sep‐17 95% 95% 0% 0.079% 0.079%
137 7 PROCESS DEM‐3963‐JALM‐6‐50‐0003 DEM P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐MANIFOLD SHUTDOWN VALVES (DEMOLITION) 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 22‐Jul‐19 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 95% 95% 0% 0.079% 0.079%
138 7 PROCESS DEM‐3963‐JALM‐6‐50‐0004 DEM P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐OIL STABILIZATION HEAT EXCH. 31‐E‐4002 (DEMO 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 22‐Jul‐19 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 95% 95% 0% 0.079% 0.079%
139 7 PROCESS DEM‐3963‐JALM‐6‐50‐0005 DEM P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐DEGASSER VESSEL 31‐V4009 (DEMOLITION) 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 22‐Jul‐19 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 95% 95% 0% 0.079% 0.079%
140 7 PROCESS DEM‐3963‐JALM‐6‐50‐0006 DEM P&ID FOR DUKHAN ‐ JALEHA MAIN DEGASSING STATION ‐PRODUCED GAS KO POT 31‐V5020 (DEMOLITION 1 A 0.056% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 22‐Jul‐19 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 95% 95% 0% 0.053% 0.053%
141 7 PROCESS DEM‐3963‐JALM‐6‐50‐0007 DEM P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐WET LIFTGAS KO DRUM 31‐V‐4901 (DEMOLITION 1 A 0.056% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 22‐Jul‐19 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 23‐Jul‐17 24‐Jul‐17 95% 95% 0% 0.053% 0.053%
142 7 PROCESS DEM‐3963‐JALM‐6‐50‐0008 DEM P&ID FOR DUKHAN ‐ JALEHA MAIN DEGASSING STATION ‐GAS GATHERING STATION (DEMOLITION) 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 28‐Sep‐17 2‐Jan‐18 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 28‐Sep‐17 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
143 7 PROCESS DEM‐3963‐JALM‐6‐50‐0009 DEM P&ID FOR DUKHAN ‐ JALEHA MAIN DEGASSING STATION ‐3 PHASE TEST SEPARATOR MANIFOLD SHUT DOW 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 28‐Sep‐17 19‐Oct‐17 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 28‐Sep‐17 19‐Oct‐17 95% 95% 0% 0.079% 0.079%
144 7 PROCESS DEM‐3963‐JALM‐6‐51‐0003 DEM P&ID FOR DUKHAN ‐ JALEHA MAIN DEGASSING STATION ‐ INSTRUMENT AIR DISTRIBUTION (DEMOLITION) 1 A 0.056% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 26‐Jul‐17 27‐Jul‐17 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 26‐Jul‐17 27‐Jul‐17 95% 95% 0% 0.053% 0.053%
145 7 PROCESS 3963‐JALM‐6‐50‐0001 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐NEW 3 PHASE TEST SEPARATOR 31‐V‐XXX1 1 A 0.056% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 21‐Jan‐18 22‐Jul‐19 11‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
146 7 PROCESS 3963‐DGEN‐6‐05‐0001 OT PROCESS DESCRIPTION 1 A 0.111% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 4‐May‐17 10‐Jun‐17 11‐Jun‐17 18‐Sep‐17 28‐Sep‐17 28‐Sep‐17 22‐Jul‐19 4‐May‐17 10‐Jun‐17 11‐Jun‐17 18‐Sep‐17 28‐Sep‐17 28‐Sep‐17 95% 95% 0% 0.106% 0.106%
147 7 PROCESS 3963‐DGEN‐6‐17‐0002 OT UTILITY ADEQUACY REPORT 1 A 0.069% 12‐May‐17 22‐May‐17 27‐May‐17 27‐Jun‐17 18‐Jul‐17 28‐Jul‐17 31‐Oct‐18 25‐May‐17 29‐Aug‐17 30‐Aug‐17 27‐Sep‐17 27‐Sep‐17 27‐Sep‐17 22‐Jul‐19 25‐May‐17 29‐Aug‐17 30‐Aug‐17 27‐Sep‐17 27‐Sep‐17 27‐Sep‐17 95% 95% 0% 0.066% 0.066%
148 7 PROCESS 3963‐DGEN‐6‐03‐0001 OT OPERATING CONTROL & SAFEGUARDING & SHUTDOWN PHILOSOPHY 1 B 0.139% 21‐May‐17 31‐May‐17 5‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 25‐May‐17 11‐Jul‐17 12‐Jul‐17 3‐Oct‐17 29‐Oct‐17 29‐Oct‐17 22‐Jul‐19 25‐May‐17 11‐Jul‐17 12‐Jul‐17 3‐Oct‐17 29‐Oct‐17 29‐Oct‐17 95% 95% 0% 0.132% 0.132%
149 7 PROCESS 3963‐DGEN‐6‐03‐0003 OT SHUTDOWN AND CHANGEOVER PHILOSOPHY 1 A 0.111% 13‐Jul‐17 25‐Jul‐17 30‐Jul‐17 27‐Aug‐17 11‐Sep‐17 18‐Sep‐17 31‐Oct‐18 8‐Jul‐17 25‐Oct‐17 26‐Oct‐17 26‐Nov‐17 4‐Dec‐17 4‐Dec‐17 22‐Jul‐19 8‐Jul‐17 25‐Oct‐17 26‐Oct‐17 26‐Nov‐17 4‐Dec‐17 4‐Dec‐17 95% 95% 0% 0.106% 0.106%
150 7 PROCESS 3963‐DGEN‐6‐12‐0002 OT RELIEF VALVE SIZING CALCULATION 3 A 0.111% 13‐Jun‐17 23‐Jun‐17 28‐Jun‐17 29‐Jul‐17 19‐Aug‐17 29‐Aug‐17 31‐Oct‐18 9‐Jul‐17 7‐Aug‐17 9‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 9‐Jul‐17 7‐Aug‐17 9‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.106% 0.106%
151 7 PROCESS 3963‐DGEN‐6‐12‐0003 OT BLOWDOWN CALCULATION 1 A 0.097% 3‐Jul‐17 13‐Jul‐17 18‐Jul‐17 18‐Aug‐17 8‐Sep‐17 18‐Sep‐17 31‐Oct‐18 3‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 12‐Oct‐17 12‐Oct‐17 22‐Jul‐19 3‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 12‐Oct‐17 12‐Oct‐17 95% 95% 0% 0.092% 0.092%
152 7 PROCESS 3963‐DGEN‐6‐17‐0004 OT HYDRAULIC ANALYSIS /LINE SIZING CALCULATION REPORT 3 A 0.111% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 2‐Apr‐17 10‐Jun‐17 11‐Jun‐17 17‐Aug‐17 17‐Aug‐17 17‐Aug‐17 22‐Jul‐19 2‐Apr‐17 10‐Jun‐17 11‐Jun‐17 17‐Aug‐17 17‐Aug‐17 17‐Aug‐17 95% 95% 0% 0.106% 0.106%
153 7 PROCESS 3963‐DGEN‐6‐22‐0001 OT STARTUP, SHUTDOWN & OPERATING MANUALS 1 A 0.222% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 20‐Aug‐18 1‐Sep‐18 24‐Dec‐18 31‐Dec‐18 31‐Dec‐18 22‐Jul‐19 27‐Jul‐17 20‐Aug‐18 1‐Sep‐18 40% 40% 0% 0.089% 0.089%
154 7 PROCESS DEM‐3963‐FAHM‐6‐50‐0006 DEM P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION – THREE PHASE SEPARATOR 14‐V‐4001  (DEMOL 1 A 0.083% 20‐Sep‐17 25‐Sep‐17 30‐Sep‐17 15‐Oct‐17 9‐Nov‐17 29‐Nov‐17 31‐Oct‐18 17‐Sep‐17 18‐Sep‐17 20‐Sep‐17 18‐Dec‐17 2‐Jan‐18 2‐Jan‐18 22‐Jul‐19 17‐Sep‐17 18‐Sep‐17 20‐Sep‐17 18‐Dec‐17 2‐Jan‐18 2‐Jan‐18 95% 95% 0% 0.079% 0.079%
155 7 PROCESS DEM‐3963‐KAHN‐6‐51‐0002 DEM P&ID FOR DUKHAN – KHATIYAH NORTH DEGASSING STATION – INSTRUMENT AIR RECEIVER 22‐V‐7330  (DE 1 A 0.083% 20‐Sep‐17 25‐Sep‐17 30‐Sep‐17 15‐Oct‐17 9‐Nov‐17 29‐Nov‐17 31‐Oct‐18 17‐Sep‐17 18‐Sep‐17 20‐Sep‐17 17‐Dec‐17 3‐Jan‐18 3‐Jan‐18 22‐Jul‐19 17‐Sep‐17 18‐Sep‐17 20‐Sep‐17 17‐Dec‐17 3‐Jan‐18 3‐Jan‐18 95% 95% 0% 0.079% 0.079%
156 8 PROCESS 3963‐DGEN‐6‐00‐0002 OT MISCELLANEOUS ‐ PROCESS 0 0.111% 31‐Aug‐17 6‐Sep‐17 7‐Sep‐17 14‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 12‐Jan‐18 12‐Jan‐18 15‐Jan‐18 8‐Feb‐18 8‐Mar‐18 8‐Mar‐18 22‐Jul‐19 12‐Jan‐18 12‐Jan‐18 15‐Jan‐18 8‐Feb‐18 8‐Mar‐18 8‐Mar‐18 95% 95% 0% 0.106% 0.106%
157 7 PROCESS 3963‐DGEN‐6‐03‐0002 OT PRE‐COMMISSIONING, COMMISSIONING PHILOSOPHY 1 0 0.139% 27‐Jun‐17 7‐Jul‐17 12‐Jul‐17 12‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 28‐Jun‐17 22‐Jan‐18 24‐Jan‐18 6‐Aug‐18 24‐Sep‐18 24‐Sep‐18 22‐Jul‐19 28‐Jun‐17 22‐Jan‐18 24‐Jan‐18 6‐Aug‐18 24‐Sep‐18 24‐Sep‐18 95% 95% 0% 0.132% 0.132%
158 7 PROCESS 3963‐DGEN‐6‐17‐0003 OT FLARE ADEQUACY REPORT 1 A 0.111% 18‐Jun‐17 28‐Jun‐17 3‐Jul‐17 3‐Aug‐17 24‐Aug‐17 3‐Sep‐17 31‐Oct‐18 22‐Jun‐17 16‐Oct‐17 17‐Oct‐17 22‐Jan‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 22‐Jun‐17 16‐Oct‐17 17‐Oct‐17 22‐Jan‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.106% 0.106%
159 7 PROCESS 3963‐KAHM‐6‐50‐0004 OT P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ 3 PHASE TEST SEP.24‐V‐XX1 CTRL SKID 1 B 0.083% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 11‐Mar‐18 22‐Jul‐19 18‐Apr‐17 3‐May‐17 3‐May‐17 15‐Jun‐17 26‐Sep‐17 11‐Mar‐18 95% 95% 0% 0.079% 0.079%
160 7 PROCESS 3963‐KAHN‐6‐50‐0002 OT P&ID FOR DUKHAN ‐ KHATIYAH NORTH DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 22‐V‐XXX1 CTRL S 1 B 0.083% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 11‐Mar‐18 22‐Jul‐19 18‐Apr‐17 30‐Apr‐17 3‐May‐17 22‐Jun‐17 26‐Sep‐17 11‐Mar‐18 95% 95% 0% 0.079% 0.079%
161 7 PROCESS 3963‐FAHM‐6‐50‐0002 OT P&ID FOR DUKHAN ‐ FAHAHIL MAIN DEGASSING STATION ‐ NEW 3 PHASE TEST SEPARATOR 14‐V‐XXX1, CTR 1 B 0.083% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 11‐Mar‐18 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 18‐May‐17 2‐Jul‐17 5‐Oct‐17 11‐Mar‐18 95% 95% 0% 0.079% 0.079%
162 7 PROCESS 3963‐KAHS‐6‐50‐0002 OT P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ NEW 3 PHASE TEST SEPARATOR 23‐V‐XXX1 C 1 B 0.083% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 30‐Jan‐18 22‐Jul‐19 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 11‐Oct‐17 30‐Jan‐18 95% 95% 0% 0.079% 0.079%
163 7 PROCESS 3963‐FAHN‐6‐50‐0003 OT P&ID FOR DUKHAN ‐ FAHAHIL NORTH DEGASSING STATION ‐ 3 PHASE TEST SEP. 12‐V‐XXX1 CTRL SKID 1 B 0.083% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 11‐Mar‐18 22‐Jul‐19 4‐May‐17 14‐May‐17 18‐May‐17 2‐Jul‐17 26‐Sep‐17 11‐Mar‐18 95% 95% 0% 0.079% 0.079%
164 7 PROCESS 3963‐FAHS‐6‐33‐0001 OT LINE DESIGNATION TABLE ‐ FAHAHIL SOUTH DEGASSING STATION 1 A 0.056% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 22‐Jul‐19 1‐Jun‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
165 7 PROCESS 3963‐FAHS‐6‐50‐0003 OT P&ID FOR DUKHAN ‐ FAHAHIL SOUTH DEGASSING STATION ‐ 3 PHASE TEST SEP. 13‐V‐XXX1 CTRL SKID 1 B 0.083% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 11‐Mar‐18 22‐Jul‐19 3‐May‐17 14‐May‐17 18‐May‐17 3‐Jul‐17 28‐Sep‐17 11‐Mar‐18 95% 95% 0% 0.079% 0.079%
166 7 PROCESS 3963‐JALM‐6‐50‐0002 OT P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐ NEW 3 PHASE TEST SEPARATOR 31‐V‐XXX1, CTRL 1 B 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 11‐Mar‐18 22‐Jul‐19 3‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 9‐Jul‐17 11‐Mar‐18 95% 95% 0% 0.079% 0.079%
167 7 PROCESS 3963‐DGEN‐6‐30‐0001 OT EQUIPMENT LIST 1 A 0.097% 6‐May‐17 16‐May‐17 21‐May‐17 21‐Jun‐17 12‐Jul‐17 22‐Jul‐17 31‐Oct‐18 11‐May‐17 4‐Jun‐17 4‐Jun‐17 27‐Jul‐17 28‐Sep‐17 18‐Jan‐18 22‐Jul‐19 11‐May‐17 4‐Jun‐17 4‐Jun‐17 27‐Jul‐17 28‐Sep‐17 18‐Jan‐18 95% 95% 0% 0.092% 0.092%
168 7 PROCESS 3963‐FAHM‐6‐33‐0001 OT LINE DESIGNATION TABLE ‐ FAHAHIL MAIN DEGASSING STATION  1 A 0.111% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 22‐Jul‐19 31‐May‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 95% 95% 0% 0.106% 0.106%
169 7 PROCESS 3963‐FAHN‐6‐33‐0001 OT LINE DESIGNATION TABLE ‐ FAHAHIL NORTH DEGASSING STATION  1 A 0.069% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 7‐Jun‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 22‐Jul‐19 7‐Jun‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 95% 95% 0% 0.066% 0.066%
170 7 PROCESS 3963‐JALM‐6‐33‐0001 OT LINE DESIGNATION TABLE ‐ JALEHA MAIN DEGASSING STATION 1 A 0.056% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 7‐Jun‐17 26‐Sep‐17 28‐Sep‐17 14‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 7‐Jun‐17 26‐Sep‐17 28‐Sep‐17 14‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
171 7 PROCESS 3963‐KAHM‐6‐33‐0001 OT LINE DESIGNATION TABLE ‐ KHATIYAH MAIN DEGASSING STATION  1 A 0.056% 13‐Jun‐17 23‐Jun‐17 28‐Jun‐17 29‐Jul‐17 19‐Aug‐17 29‐Aug‐17 31‐Oct‐18 8‐Jul‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 22‐Jul‐19 8‐Jul‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
172 7 PROCESS 3963‐KAHN‐6‐33‐0001 OT LINE DESIGNATION TABLE ‐ KHATIYAH NORTH DEGASSING STATION  1 A 0.056% 13‐Jun‐17 23‐Jun‐17 28‐Jun‐17 29‐Jul‐17 19‐Aug‐17 29‐Aug‐17 31‐Oct‐18 11‐Jul‐17 26‐Sep‐17 28‐Sep‐17 14‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 11‐Jul‐17 26‐Sep‐17 28‐Sep‐17 14‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
173 7 PROCESS 3963‐KAHS‐6‐33‐0001 OT LINE DESIGNATION TABLE ‐ KHATIYAH SOUTH DEGASSING STATION  1 A 0.056% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 22‐Jul‐19 8‐Jul‐17 26‐Sep‐17 28‐Sep‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
174 7 PROCESS DEM‐3963‐KAHM‐6‐50‐0005 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ GAS GATHERING STATION, P&ID (DEMOLITIO 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
175 7 PROCESS DEM‐3963‐KAHM‐6‐50‐0006 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR CRUDE OIL FROM K 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
176 7 PROCESS DEM‐3963‐KAHM‐6‐51‐0001 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ DRAIN COLLECTION, P&ID (DEMOLITION) 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
177 7 PROCESS DEM‐3963‐KAHM‐6‐51‐0002 DEM P&ID FOR DUKHAN ‐ KHATIYAH MAIN DEGASSING STATION ‐ PROCESS FLARE COLLECTION, P&ID (DEMOLIT 1 A 0.042% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 15‐Jun‐17 24‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
178 7 PROCESS DEM‐3963‐KAHS‐6‐50‐0001 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR 23‐V‐7200 (DEMO 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 22‐Jul‐19 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 95% 95% 0% 0.040% 0.040%
179 7 PROCESS DEM‐3963‐KAHS‐6‐50‐0002 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐ 3 PHASE TEST SEPARATOR CONTROL SKID 23 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 22‐Jul‐19 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 95% 95% 0% 0.040% 0.040%
180 7 PROCESS DEM‐3963‐KAHS‐6‐50‐0003 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐3 PHASE TEST SEPARATOR HEADERS (DEMOL 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 95% 95% 0% 0.040% 0.040%
181 7 PROCESS DEM‐3963‐KAHS‐6‐50‐0004 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐DEGASSING VESSEL 23‐V‐7280 (DEMOLITION 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 2‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 22‐Jul‐19 2‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 95% 95% 0% 0.040% 0.040%
182 7 PROCESS DEM‐3963‐KAHS‐6‐50‐0005 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐HYDROCARBON CONDENSATE LINES (DEMOL 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 22‐Jul‐19 27‐Apr‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 95% 95% 0% 0.040% 0.040%
183 7 PROCESS DEM‐3963‐KAHS‐6‐50‐0006 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐MANIFOLD SHUTDOWN VALVES (DEMOLITIO 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 22‐Jul‐19 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 22‐Jun‐17 29‐Nov‐17 95% 95% 0% 0.040% 0.040%
184 7 PROCESS DEM‐3963‐KAHS‐6‐51‐0002 DEM P&ID FOR DUKHAN ‐ KHATIYAH SOUTH DEGASSING STATION ‐FLARE COLLECTION (DEMOLITION) 1 A 0.042% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 24‐Aug‐17 29‐Nov‐17 22‐Jul‐19 4‐May‐17 9‐May‐17 10‐May‐17 22‐Jun‐17 24‐Aug‐17 29‐Nov‐17 95% 95% 0% 0.040% 0.040%
185 7 PROCESS DEM‐3963‐JALM‐6‐51‐0001 DEM P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐DRAIN COLLECTION (DEMOLITION) 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 15‐Oct‐17 29‐Nov‐17 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 15‐Oct‐17 29‐Nov‐17 95% 95% 0% 0.079% 0.079%
186 7 PROCESS DEM‐3963‐JALM‐6‐51‐0002 DEM P&ID FOR DUKHAN ‐JALEHA MAIN DEGASSING STATION ‐FLARE COLLECTION (DEMOLITION) 1 A 0.083% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 15‐Oct‐17 29‐Nov‐17 22‐Jul‐19 4‐May‐17 20‐May‐17 22‐May‐17 9‐Jul‐17 15‐Oct‐17 29‐Nov‐17 95% 95% 0% 0.079% 0.079%
187 8 PIPING 3963‐DGEN‐5‐14‐0001 OT DUKHAN FIELD; PIPING MATERIAL SPECIFICATIONS 1 A 0.140% 13‐Apr‐17 23‐Apr‐17 28‐Apr‐17 29‐May‐17 19‐Jun‐17 29‐Jun‐17 31‐Oct‐18 19‐Apr‐17 27‐May‐17 28‐May‐17 20‐Aug‐17 30‐Aug‐17 8‐Oct‐17 22‐Jul‐19 19‐Apr‐17 27‐May‐17 28‐May‐17 20‐Aug‐17 30‐Aug‐17 8‐Oct‐17 95% 95% 0% 0.133% 0.133%
188 8 PIPING 3963‐DGEN‐5‐14‐0002 OT DUKHAN FIELD; TECHNICAL SPECIFICATION FOR PIPING STRESS ANALYSIS 1 A 0.084% 10‐Apr‐17 20‐Apr‐17 25‐Apr‐17 26‐May‐17 16‐Jun‐17 26‐Jun‐17 31‐Oct‐18 29‐Mar‐17 29‐Mar‐17 19‐Apr‐17 25‐May‐17 11‐Jun‐17 11‐Jun‐17 22‐Jul‐19 29‐Mar‐17 29‐Mar‐17 19‐Apr‐17 25‐May‐17 11‐Jun‐17 11‐Jun‐17 95% 95% 0% 0.080% 0.080%
189 8 PIPING 3963‐DGEN‐5‐14‐0004 OT DUKHAN FIELD; TECHNICAL SPECIFICATION FOR PIPES 1 A 0.084% 5‐Apr‐17 15‐Apr‐17 20‐Apr‐17 21‐May‐17 11‐Jun‐17 21‐Jun‐17 31‐Oct‐18 5‐Apr‐17 24‐Apr‐17 27‐Apr‐17 11‐Jul‐17 12‐Jul‐17 13‐Jul‐17 22‐Jul‐19 5‐Apr‐17 24‐Apr‐17 27‐Apr‐17 11‐Jul‐17 12‐Jul‐17 13‐Jul‐17 95% 95% 0% 0.080% 0.080%
190 8 PIPING 3963‐DGEN‐5‐14‐0005 OT DUKHAN FIELD; TECHNICAL SPECIFICATION FOR FITTINGS & FLANGES 1 A 0.084% 5‐Apr‐17 15‐Apr‐17 20‐Apr‐17 21‐May‐17 11‐Jun‐17 21‐Jun‐17 31‐Oct‐18 29‐Mar‐17 24‐Apr‐17 27‐Apr‐17 20‐Jun‐17 20‐Jun‐17 20‐Jun‐17 22‐Jul‐19 29‐Mar‐17 24‐Apr‐17 27‐Apr‐17 20‐Jun‐17 20‐Jun‐17 20‐Jun‐17 95% 95% 0% 0.080% 0.080%
191 8 PIPING 3963‐DGEN‐5‐14‐0006 OT DUKHAN FIELD; TECHNICAL SPECIFICATION FOR MANUAL VALVES  1 B 0.084% 1‐Apr‐17 11‐Apr‐17 16‐Apr‐17 17‐May‐17 7‐Jun‐17 17‐Jun‐17 31‐Oct‐18 5‐Apr‐17 16‐Apr‐17 19‐Apr‐17 13‐Jun‐17 13‐Jun‐17 13‐Jun‐17 22‐Jul‐19 5‐Apr‐17 16‐Apr‐17 19‐Apr‐17 13‐Jun‐17 13‐Jun‐17 13‐Jun‐17 95% 95% 0% 0.080% 0.080%
192 8 PIPING 3963‐DGEN‐5‐13‐0001 OT DUKHAN FIELD; DATA SHEETS FOR BALL VALVES 1 B 0.168% 5‐Mar‐17 10‐Mar‐17 14‐Mar‐17 14‐Apr‐17 5‐May‐17 15‐May‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 1‐May‐17 7‐Jun‐17 7‐Jun‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 1‐May‐17 7‐Jun‐17 7‐Jun‐17 95% 95% 0% 0.160% 0.160%
193 8 PIPING 3963‐DGEN‐5‐13‐0002 OT DUKHAN FIELD; DATA SHEET FOR GATE VALVES 1 A 0.112% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 20‐Apr‐17 16‐May‐17 16‐May‐17 5‐Jun‐17 21‐Jun‐17 21‐Jun‐17 22‐Jul‐19 20‐Apr‐17 16‐May‐17 16‐May‐17 5‐Jun‐17 21‐Jun‐17 21‐Jun‐17 95% 95% 0% 0.106% 0.106%
194 8 PIPING 3963‐DGEN‐5‐13‐0003 OT DUKHAN FIELD; DATA SHEET FOR GLOBE VALVES 1 A 0.112% 20‐Apr‐17 30‐Apr‐17 5‐May‐17 5‐Jun‐17 26‐Jun‐17 6‐Jul‐17 31‐Oct‐18 19‐Apr‐17 19‐May‐17 21‐May‐17 13‐Jun‐17 11‐Jul‐17 12‐Jul‐17 22‐Jul‐19 19‐Apr‐17 19‐May‐17 21‐May‐17 13‐Jun‐17 11‐Jul‐17 12‐Jul‐17 95% 95% 0% 0.106% 0.106%
195 8 PIPING 3963‐DGEN‐5‐13‐0004 OT DUKHAN FIELD; DATA SHEET FOR CHECK VALVES 1 B 0.112% 25‐Apr‐17 5‐May‐17 10‐May‐17 10‐Jun‐17 1‐Jul‐17 11‐Jul‐17 31‐Oct‐18 20‐Apr‐17 19‐May‐17 21‐May‐17 13‐Jun‐17 22‐Jul‐17 23‐Jul‐17 22‐Jul‐19 20‐Apr‐17 19‐May‐17 21‐May‐17 13‐Jun‐17 22‐Jul‐17 23‐Jul‐17 95% 95% 0% 0.106% 0.106%
196 8 PIPING 3963‐DGEN‐5‐13‐0005 OT DUKHAN FIELD; DATA SHEET FOR NEEDLE VALVES 1 A 0.084% 30‐Apr‐17 10‐May‐17 15‐May‐17 15‐Jun‐17 6‐Jul‐17 16‐Jul‐17 31‐Oct‐18 5‐Apr‐17 30‐May‐17 31‐May‐17 21‐Jun‐17 12‐Jul‐17 13‐Jul‐17 22‐Jul‐19 5‐Apr‐17 30‐May‐17 31‐May‐17 21‐Jun‐17 12‐Jul‐17 13‐Jul‐17 95% 95% 0% 0.080% 0.080%
197 8 PIPING 3963‐DGEN‐5‐13‐0006 OT DUKHAN FIELD; DATASHEET FOR CORROSION COUPON & CORROSION PROBES 1 A 0.112% 10‐May‐17 20‐May‐17 25‐May‐17 25‐Jun‐17 16‐Jul‐17 26‐Jul‐17 31‐Oct‐18 11‐May‐17 8‐Jun‐17 8‐Jun‐17 25‐Jul‐17 25‐Jul‐17 14‐Sep‐17 22‐Jul‐19 11‐May‐17 8‐Jun‐17 8‐Jun‐17 25‐Jul‐17 25‐Jul‐17 14‐Sep‐17 95% 95% 0% 0.106% 0.106%
198 8 PIPING 3963‐DGEN‐5‐15‐0001 OT DUKHAN FIELD; MATERIAL REQUISITION FOR MANUAL VALVES (GATE, GLOBE & CHECK) 1 A 0.070% 22‐May‐17 1‐Jun‐17 6‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 25‐May‐17 6‐Jun‐17 6‐Jun‐17 11‐Jul‐17 15‐Jul‐17 20‐Jul‐17 22‐Jul‐19 25‐May‐17 6‐Jun‐17 6‐Jun‐17 11‐Jul‐17 15‐Jul‐17 20‐Jul‐17 95% 95% 0% 0.067% 0.067%
199 8 PIPING 3963‐DGEN‐5‐15‐0002 OT DUKHAN FIELD; MATERIAL REQUISITION FOR PIPING BULK ITEMS  1 A 0.070% 3‐Jun‐17 13‐Jun‐17 18‐Jun‐17 19‐Jul‐17 9‐Aug‐17 19‐Aug‐17 31‐Oct‐18 7‐Jun‐17 12‐Jul‐17 13‐Jul‐17 1‐Aug‐17 10‐Aug‐17 10‐Aug‐17 22‐Jul‐19 7‐Jun‐17 12‐Jul‐17 13‐Jul‐17 1‐Aug‐17 10‐Aug‐17 10‐Aug‐17 95% 95% 0% 0.067% 0.067%
200 8 PIPING 3963‐DGEN‐5‐15‐0003 OT DUKHAN FIELD; MATERIAL REQUISITIONS FOR BALL VALVES 1 A 0.070% 26‐May‐17 5‐Jun‐17 10‐Jun‐17 11‐Jul‐17 1‐Aug‐17 11‐Aug‐17 31‐Oct‐18 31‐May‐17 6‐Jun‐17 6‐Jun‐17 11‐Jul‐17 15‐Jul‐17 20‐Jul‐17 22‐Jul‐19 31‐May‐17 6‐Jun‐17 6‐Jun‐17 11‐Jul‐17 15‐Jul‐17 20‐Jul‐17 95% 95% 0% 0.067% 0.067%
201 8 PIPING 3963‐DGEN‐5‐15‐0004 OT DUKHAN FIELD; MATERIAL REQUISITION FOR PIPING SPECIALTY ITEMS (STRAINERS, SAMPLING, CORROSIO 1 A 0.070% 29‐May‐17 8‐Jun‐17 13‐Jun‐17 14‐Jul‐17 4‐Aug‐17 14‐Aug‐17 31‐Oct‐18 31‐May‐17 30‐Jul‐17 31‐Jul‐17 2‐Oct‐17 18‐Oct‐17 19‐Oct‐17 22‐Jul‐19 31‐May‐17 30‐Jul‐17 31‐Jul‐17 2‐Oct‐17 18‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.067% 0.067%
202 8 PIPING 3963‐DGEN‐5‐17‐0001 OT DUKHAN FIELD; TECHNICAL BID EVALUATION FOR MANUAL VALVES (GATE, GLOBE & CHECK) 1 A 0.252% 17‐Jul‐17 27‐Jul‐17 1‐Aug‐17 18‐Aug‐17 28‐Aug‐17 6‐Sep‐17 31‐Oct‐18 20‐Jul‐17 24‐Oct‐17 26‐Oct‐17 19‐Nov‐17 28‐Nov‐17 28‐Nov‐17 22‐Jul‐19 20‐Jul‐17 24‐Oct‐17 26‐Oct‐17 19‐Nov‐17 28‐Nov‐17 28‐Nov‐17 95% 95% 0% 0.240% 0.240%
203 8 PIPING 3963‐DGEN‐5‐17‐0003 OT DUKHAN FIELD; TECHNICAL BID EVALUATION FOR BALL VALVES 1 A 0.224% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 24‐Oct‐17 26‐Oct‐17 21‐Nov‐17 5‐Dec‐17 5‐Dec‐17 22‐Jul‐19 27‐Jul‐17 24‐Oct‐17 26‐Oct‐17 21‐Nov‐17 5‐Dec‐17 5‐Dec‐17 95% 95% 0% 0.213% 0.213%
204 8 PIPING 3963‐DGEN‐5‐17‐0004 OT DUKHAN FIELD; TECHNICAL BID EVALUATION FOR PIPING SPECIALTY ITEMS (STRAINERS, SAMPLING, CORR 1 A 0.224% 10‐Aug‐17 20‐Aug‐17 25‐Aug‐17 12‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 21‐Oct‐17 23‐Oct‐17 23‐Nov‐17 7‐Dec‐17 3‐Dec‐17 22‐Jul‐19 19‐Oct‐17 21‐Oct‐17 23‐Oct‐17 23‐Nov‐17 7‐Dec‐17 3‐Dec‐17 95% 95% 0% 0.213% 0.213%
205 8 PIPING 3963‐DGEN‐5‐36‐0001 ET DUKHAN FIELD; EARLY TIE‐IN PACKAGE 1 C Y 0.070% 5‐Mar‐17 10‐Mar‐17 14‐Mar‐17 14‐Apr‐17 5‐May‐17 15‐May‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 15‐Jun‐17 12‐Jul‐17 13‐Jul‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 15‐Jun‐17 12‐Jul‐17 13‐Jul‐17 95% 95% 0% 0.067% 0.067%
206 8 PIPING 3963‐FAHN‐5‐33‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; CRITICAL LINE LIST 1 A 0.042% 16‐Jun‐17 26‐Jun‐17 1‐Jul‐17 1‐Aug‐17 22‐Aug‐17 1‐Sep‐17 31‐Oct‐18 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.040% 0.040%
207 8 PIPING 3963‐FAHN‐5‐32‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING SPECIALTY ITEM LIST 1 A 0.028% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.027% 0.027%
208 8 PIPING 3963‐FAHN‐5‐21‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; TIE‐IN ENGINEERING PACKAGE 3 0 0.168% 15‐Aug‐17 25‐Aug‐17 30‐Aug‐17 13‐Sep‐17 18‐Sep‐17 18‐Sep‐17 31‐Oct‐18 19‐Oct‐17 12‐Mar‐18 14‐Mar‐18 8‐Sep‐18 2‐Dec‐18 2‐Dec‐18 22‐Jul‐19 19‐Oct‐17 12‐Mar‐18 14‐Mar‐18 8‐Sep‐18 65% 65% 0% 0.109% 0.109%
209 8 PIPING 3963‐FAHN‐5‐31‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS 3 A 0.280% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 22‐Jul‐19 1‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 95% 95% 0% 0.266% 0.266%
210 8 PIPING 3963‐FAHN‐5‐17‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING STRESS ANALYSIS REPORT 3 A 0.420% 16‐Jun‐17 26‐Jun‐17 1‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Jul‐17 31‐Oct‐18 21‐Jun‐17 25‐Sep‐17 27‐Sep‐17 16‐Oct‐17 29‐Oct‐17 7‐Feb‐18 22‐Jul‐19 21‐Jun‐17 25‐Sep‐17 27‐Sep‐17 16‐Oct‐17 29‐Oct‐17 7‐Feb‐18 95% 95% 0% 0.399% 0.399%
211 8 PIPING 3963‐FAHN‐5‐52‐0003 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.3 PIPING GA EL.21.600 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 8‐Dec‐17 10‐Dec‐17 12‐Feb‐18 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 19‐Oct‐17 8‐Dec‐17 10‐Dec‐17 12‐Feb‐18 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.093% 0.093%
212 8 PIPING 3963‐FAHN‐5‐52‐0004 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.4 PIPING GA EL.21.600 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.093% 0.093%
213 8 PIPING 3963‐FAHN‐5‐52‐0005 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.5 PIPING GA EL.21.600 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.093% 0.093%
214 8 PIPING 3963‐FAHN‐5‐52‐0006 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.6 PIPING GA EL.22.620 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.093% 0.093%
215 8 PIPING 3963‐FAHN‐5‐52‐0007 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.7 PIPING GA EL.22.620 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 11‐Feb‐18 11‐Feb‐18 22‐Jul‐19 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 11‐Feb‐18 11‐Feb‐18 95% 95% 0% 0.093% 0.093%
216 8 PIPING 3963‐FAHN‐5‐52‐0008 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.8 PIPING GA EL.22.620 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 11‐Feb‐18 11‐Feb‐18 22‐Jul‐19 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 11‐Feb‐18 11‐Feb‐18 95% 95% 0% 0.093% 0.093%
217 8 PIPING 3963‐FAHN‐5‐52‐0009 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.9 PIPING GA EL.22.620 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 11‐Feb‐18 11‐Feb‐18 22‐Jul‐19 19‐Oct‐17 30‐Oct‐17 31‐Oct‐17 15‐Nov‐17 11‐Feb‐18 11‐Feb‐18 95% 95% 0% 0.093% 0.093%
218 8 PIPING 3963‐FAHN‐5‐52‐0010 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.10 PIPING GA EL.22.620 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 20‐Nov‐17 11‐Feb‐18 11‐Feb‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 20‐Nov‐17 11‐Feb‐18 11‐Feb‐18 95% 95% 0% 0.093% 0.093%
219 8 PIPING 3963‐FAHN‐5‐52‐0011 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.11 PIPING GA EL.22.620 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 16‐Nov‐17 16‐Nov‐17 20‐Nov‐17 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 16‐Nov‐17 16‐Nov‐17 20‐Nov‐17 95% 95% 0% 0.093% 0.093%
220 8 PIPING 3963‐FAHS‐5‐33‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; CRITICAL LINE LIST  1 B 0.042% 16‐Jun‐17 26‐Jun‐17 1‐Jul‐17 1‐Aug‐17 22‐Aug‐17 1‐Sep‐17 31‐Oct‐18 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 13‐Sep‐17 14‐Sep‐17 22‐Jul‐19 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 13‐Sep‐17 14‐Sep‐17 95% 95% 0% 0.040% 0.040%
221 8 PIPING 3963‐FAHS‐5‐32‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING SPECIALTY ITEM LIST  1 A 0.028% 28‐May‐17 7‐Jun‐17 12‐Jun‐17 13‐Jul‐17 3‐Aug‐17 13‐Aug‐17 31‐Oct‐18 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.027% 0.027%
222 8 PIPING 3963‐FAHS‐5‐36‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING TIE‐IN SCHEDULE  1 A 0.056% 24‐Jul‐17 3‐Aug‐17 8‐Aug‐17 26‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 16‐Jul‐17 17‐Jul‐17 18‐Jul‐17 14‐Nov‐17 28‐Nov‐17 28‐Nov‐17 22‐Jul‐19 16‐Jul‐17 17‐Jul‐17 18‐Jul‐17 14‐Nov‐17 28‐Nov‐17 28‐Nov‐17 95% 95% 0% 0.053% 0.053%
223 8 PIPING 3963‐FAHS‐5‐21‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; TIE‐IN ENGINEERING PACKAGE  3 A 0.168% 10‐Aug‐17 20‐Aug‐17 25‐Aug‐17 8‐Sep‐17 13‐Sep‐17 13‐Sep‐17 31‐Oct‐18 19‐Oct‐17 20‐Mar‐18 22‐Mar‐18 30‐Aug‐18 2‐Dec‐18 2‐Dec‐18 22‐Jul‐19 19‐Oct‐17 20‐Mar‐18 22‐Mar‐18 30‐Aug‐18 65% 65% 0% 0.109% 0.109%
224 8 PIPING 3963‐FAHS‐5‐31‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS 3 A 0.336% 2‐Jun‐17 12‐Jun‐17 17‐Jun‐17 18‐Jul‐17 8‐Aug‐17 18‐Aug‐17 31‐Oct‐18 7‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 22‐Jul‐19 7‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 95% 95% 0% 0.319% 0.319%
225 8 PIPING 3963‐FAHS‐5‐17‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING STRESS ANALYSIS REPORT 3 A 0.420% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 24‐Jul‐17 29‐Jul‐17 29‐Jul‐17 31‐Oct‐18 29‐Jun‐17 3‐Oct‐17 5‐Oct‐17 23‐Oct‐17 23‐Oct‐17 14‐Feb‐18 22‐Jul‐19 29‐Jun‐17 3‐Oct‐17 5‐Oct‐17 23‐Oct‐17 23‐Oct‐17 14‐Feb‐18 95% 95% 0% 0.399% 0.399%
226 8 PIPING 3963‐FAHS‐5‐50‐0002 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; KEY PLAN 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 26‐Nov‐17 22‐Jul‐19 27‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 26‐Nov‐17 95% 95% 0% 0.040% 0.040%
227 8 PIPING 3963‐FAHS‐5‐52‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.1 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 2‐Nov‐17 2‐Nov‐17 2‐Nov‐17 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 2‐Nov‐17 2‐Nov‐17 2‐Nov‐17 95% 95% 0% 0.093% 0.093%
228 8 PIPING 3963‐FAHS‐5‐52‐0002 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.2 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Oct‐17 1‐Nov‐17 1‐Nov‐17 1‐Nov‐17 20‐Nov‐17 22‐Jul‐19 19‐Oct‐17 30‐Oct‐17 1‐Nov‐17 1‐Nov‐17 1‐Nov‐17 20‐Nov‐17 95% 95% 0% 0.093% 0.093%
229 8 PIPING 3963‐FAHS‐5‐52‐0003 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.3 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 2‐Nov‐17 2‐Nov‐17 2‐Nov‐17 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 2‐Nov‐17 2‐Nov‐17 2‐Nov‐17 95% 95% 0% 0.093% 0.093%
230 8 PIPING 3963‐FAHS‐5‐52‐0004 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.4 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 18‐Feb‐18 18‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 18‐Feb‐18 18‐Feb‐18 95% 95% 0% 0.093% 0.093%
231 8 PIPING 3963‐FAHS‐5‐52‐0005 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.5 EL. 54.700 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 19‐Feb‐18 19‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 19‐Feb‐18 19‐Feb‐18 95% 95% 0% 0.093% 0.093%
232 8 PIPING 3963‐FAHS‐5‐52‐0006 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.6 EL. 54.700 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 30‐Oct‐17 30‐Oct‐17 18‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 30‐Oct‐17 30‐Oct‐17 18‐Feb‐18 95% 95% 0% 0.093% 0.093%
233 8 PIPING 3963‐FAHS‐5‐52‐0007 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.7 EL. 54.470 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 18‐Feb‐18 18‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 18‐Feb‐18 18‐Feb‐18 95% 95% 0% 0.093% 0.093%
234 8 PIPING 3963‐FAHS‐5‐52‐0008 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.8 EL. 54.470 & ABOVE  1 1 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 19‐Oct‐17 15‐Dec‐17 17‐Dec‐17 25‐Feb‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 19‐Oct‐17 15‐Dec‐17 17‐Dec‐17 25‐Feb‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.093% 0.093%
235 8 PIPING 3963‐FAHS‐5‐52‐0009 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.9 EL. 54.470 TO 58.470  1 1 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 19‐Oct‐17 18‐Dec‐17 21‐Dec‐17 18‐Feb‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 19‐Oct‐17 18‐Dec‐17 21‐Dec‐17 18‐Feb‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.093% 0.093%
236 8 PIPING 3963‐FAHS‐5‐52‐0010 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.10 EL. 54.364 & ABOVE  1 1 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 19‐Oct‐17 18‐Dec‐17 20‐Dec‐17 21‐Feb‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 19‐Oct‐17 18‐Dec‐17 20‐Dec‐17 21‐Feb‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.093% 0.093%
237 8 PIPING 3963‐FAHS‐5‐52‐0011 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.11 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 95% 95% 0% 0.093% 0.093%
238 8 PIPING 3963‐FAHS‐5‐52‐0012 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.12 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 95% 95% 0% 0.093% 0.093%
239 8 PIPING 3963‐FAHS‐5‐52‐0013 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.13 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 95% 95% 0% 0.093% 0.093%
240 8 PIPING 3963‐FAHS‐5‐52‐0014 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING G.A AREA 701,SHT.14 EL. 54.364 & ABOVE  1 A 0.098% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 22‐Jul‐19 12‐Oct‐17 15‐Oct‐17 16‐Oct‐17 19‐Nov‐17 25‐Feb‐18 25‐Feb‐18 95% 95% 0% 0.093% 0.093%
241 8 PIPING 3963‐JALM‐5‐33‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; CRITICAL LINE LIST 1 B 0.042% 16‐Jun‐17 26‐Jun‐17 1‐Jul‐17 1‐Aug‐17 22‐Aug‐17 1‐Sep‐17 31‐Oct‐18 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 13‐Sep‐17 14‐Sep‐17 22‐Jul‐19 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 13‐Sep‐17 14‐Sep‐17 95% 95% 0% 0.040% 0.040%
242 8 PIPING 3963‐JALM‐5‐32‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING SPECIALTY ITEM LIST 1 A 0.028% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 7‐Jun‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 7‐Jun‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.027% 0.027%
243 8 PIPING 3963‐JALM‐5‐36‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING TIE‐IN SCHEDULE 1 A 0.056% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 4‐Aug‐17 6‐Aug‐17 8‐Aug‐17 28‐Nov‐17 10‐Dec‐17 10‐Dec‐17 22‐Jul‐19 4‐Aug‐17 6‐Aug‐17 8‐Aug‐17 28‐Nov‐17 10‐Dec‐17 10‐Dec‐17 95% 95% 0% 0.053% 0.053%
244 8 PIPING 3963‐JALM‐5‐21‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; TIE‐IN ENGINEERING PACKAGE 3 A 0.168% 15‐Aug‐17 25‐Aug‐17 30‐Aug‐17 13‐Sep‐17 18‐Sep‐17 18‐Sep‐17 31‐Oct‐18 19‐Oct‐17 20‐Mar‐18 22‐Mar‐18 8‐Sep‐18 2‐Dec‐18 2‐Dec‐18 22‐Jul‐19 19‐Oct‐17 20‐Mar‐18 22‐Mar‐18 8‐Sep‐18 65% 65% 0% 0.109% 0.109%
245 8 PIPING 3963‐JALM‐5‐31‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS 3 A 0.336% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 7‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 22‐Jul‐19 7‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 95% 95% 0% 0.319% 0.319%
246 8 PIPING 3963‐JALM‐5‐17‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING STRESS ANALYSIS REPORT 3 A 0.420% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 3‐Aug‐17 8‐Aug‐17 8‐Aug‐17 31‐Oct‐18 3‐Jul‐17 11‐Oct‐17 12‐Oct‐17 2‐Jan‐18 26‐Feb‐18 26‐Feb‐18 22‐Jul‐19 3‐Jul‐17 11‐Oct‐17 12‐Oct‐17 2‐Jan‐18 26‐Feb‐18 26‐Feb‐18 95% 95% 0% 0.399% 0.399%
247 8 PIPING 3963‐JALM‐5‐50‐0002 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; KEY PLAN 1 A 0.042% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 1‐Aug‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 26‐Nov‐17 22‐Jul‐19 1‐Aug‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 26‐Nov‐17 95% 95% 0% 0.040% 0.040%

Page 2 of 13
Page 73 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
248 8 PIPING 3963‐JALM‐5‐52‐0003 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 803, SHT.3 EL.63.000 & ABOVE  1 1 0.140% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 5‐Jan‐18 7‐Jan‐18 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 8‐Jul‐17 5‐Jan‐18 7‐Jan‐18 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.133% 0.133%
249 8 PIPING 3963‐JALM‐5‐52‐0004 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 803, SHT.4 EL.63.000 & ABOVE  1 1 0.084% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 11‐Jul‐17 26‐Dec‐17 28‐Dec‐17 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 11‐Jul‐17 26‐Dec‐17 28‐Dec‐17 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.080% 0.080%
250 8 PIPING 3963‐JALM‐5‐52‐0005 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.5 EL.63.000 & ABOVE  1 1 0.140% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 26‐Dec‐17 28‐Dec‐17 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 8‐Jul‐17 26‐Dec‐17 28‐Dec‐17 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.133% 0.133%
251 8 PIPING 3963‐JALM‐5‐52‐0006 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.6 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
252 8 PIPING 3963‐JALM‐5‐52‐0007 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.7 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
253 8 PIPING 3963‐JALM‐5‐52‐0008 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.8 EL.63000 & ABOVE  1 A 0.112% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.106% 0.106%
254 8 PIPING 3963‐JALM‐5‐52‐0009 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.9 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
255 8 PIPING 3963‐JALM‐5‐52‐0010 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.10 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
256 8 PIPING 3963‐JALM‐5‐52‐0011 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.11 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 11‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 11‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
257 8 PIPING 3963‐JALM‐5‐52‐0012 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.12 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
258 8 PIPING 3963‐JALM‐5‐52‐0013 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.13 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 4‐Dec‐17 4‐Dec‐17 22‐Jul‐19 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 4‐Dec‐17 4‐Dec‐17 95% 95% 0% 0.067% 0.067%
259 8 PIPING 3963‐JALM‐5‐52‐0014 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.14 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
260 8 PIPING 3963‐JALM‐5‐52‐0015 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.15 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 13‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
261 8 PIPING 3963‐JALM‐5‐52‐0016 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.16 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
262 8 PIPING 3963‐JALM‐5‐52‐0017 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.17 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
263 8 PIPING 3963‐JALM‐5‐52‐0018 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.18 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
264 8 PIPING 3963‐JALM‐5‐52‐0019 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 805, SHT.19 EL.63.000 & ABOVE  1 A 0.070% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 8‐Jul‐17 30‐Oct‐17 31‐Oct‐17 23‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.067% 0.067%
265 8 PIPING 3963‐KAHM‐5‐33‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; CRITICAL LINE LIST 1 A 0.042% 22‐Jun‐17 2‐Jul‐17 7‐Jul‐17 7‐Aug‐17 28‐Aug‐17 7‐Sep‐17 31‐Oct‐18 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.040% 0.040%
266 8 PIPING 3963‐KAHM‐5‐32‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING SPECIALTY ITEM LIST 1 A 0.028% 21‐May‐17 31‐May‐17 5‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 25‐May‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 25‐May‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.027% 0.027%
267 8 PIPING 3963‐KAHM‐5‐21‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; TIE‐IN ENGINEERING PACKAGE 3 A 0.168% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 5‐Sep‐17 15‐Sep‐17 15‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Mar‐18 1‐Apr‐18 7‐May‐18 27‐May‐18 27‐May‐18 22‐Jul‐19 19‐Oct‐17 30‐Mar‐18 1‐Apr‐18 7‐May‐18 27‐May‐18 27‐May‐18 95% 95% 0% 0.160% 0.160%
268 8 PIPING 3963‐KAHM‐5‐31‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS 3 A 0.336% 10‐Jun‐17 20‐Jun‐17 25‐Jun‐17 26‐Jul‐17 16‐Aug‐17 26‐Aug‐17 31‐Oct‐18 8‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 22‐Jul‐19 8‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 95% 95% 0% 0.319% 0.319%
269 8 PIPING 3963‐KAHM‐5‐31‐0002 ET DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS (EARLY T 3 A Y 0.084% 7‐May‐17 11‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 5‐May‐17 7‐May‐17 8‐May‐17 30‐Jul‐17 29‐Jul‐17 30‐Jul‐17 22‐Jul‐19 5‐May‐17 7‐May‐17 8‐May‐17 30‐Jul‐17 29‐Jul‐17 30‐Jul‐17 95% 95% 0% 0.080% 0.080%
270 8 PIPING 3963‐KAHM‐5‐50‐0002 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; KEY PLAN 1 A 0.042% 26‐May‐17 5‐Jun‐17 10‐Jun‐17 11‐Jul‐17 1‐Aug‐17 11‐Aug‐17 31‐Oct‐18 1‐Jun‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 26‐Nov‐17 22‐Jul‐19 1‐Jun‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 26‐Nov‐17 95% 95% 0% 0.040% 0.040%
271 8 PIPING 3963‐KAHM‐5‐52‐0002 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.2 EL. 99.143 & ABOVE  1 A 0.060% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 29‐Nov‐17 22‐Jul‐19 31‐May‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 29‐Nov‐17 95% 95% 0% 0.057% 0.057%
272 8 PIPING 3963‐KAHM‐5‐52‐0004 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.4 EL. 99.143 & ABOVE  1 A 0.075% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 29‐Nov‐17 22‐Jul‐19 31‐May‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 29‐Nov‐17 95% 95% 0% 0.072% 0.072%
273 8 PIPING 3963‐KAHM‐5‐52‐0006 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.6 EL. 98.973 & ABOVE  1 A 0.090% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 2‐Aug‐17 3‐Aug‐17 29‐Oct‐17 29‐Oct‐17 29‐Nov‐17 22‐Jul‐19 31‐May‐17 2‐Aug‐17 3‐Aug‐17 29‐Oct‐17 29‐Oct‐17 29‐Nov‐17 95% 95% 0% 0.086% 0.086%
274 8 PIPING 3963‐KAHM‐5‐52‐0007 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA‐255 SHT.7 EL.99.743 & ABOVE  1 A 0.090% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 22‐Jul‐19 1‐Jun‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 95% 95% 0% 0.086% 0.086%
275 8 PIPING 3963‐KAHM‐5‐52‐0010 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.10 EL. 99.443 & ABOVE  1 A 0.075% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 22‐Jul‐19 1‐Jun‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 95% 95% 0% 0.072% 0.072%
276 8 PIPING 3963‐KAHM‐5‐52‐0011 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A. AREA‐255, SHT.11 EL.99.9943 & ABOV 1 A 0.075% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 28‐Dec‐17 22‐Jul‐19 31‐May‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 28‐Dec‐17 95% 95% 0% 0.072% 0.072%
277 8 PIPING 3963‐KAHM‐5‐71‐0002 ET DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING ISOMETRICS FOR EARLY TIE‐IN 3 A Y 0.132% 6‐Jul‐17 16‐Jul‐17 20‐Jul‐17 30‐Jul‐17 9‐Aug‐17 19‐Aug‐17 31‐Oct‐18 18‐Jul‐17 19‐Jul‐17 20‐Jul‐17 7‐Sep‐17 7‐Sep‐17 30‐Nov‐17 22‐Jul‐19 18‐Jul‐17 19‐Jul‐17 20‐Jul‐17 7‐Sep‐17 7‐Sep‐17 30‐Nov‐17 95% 95% 0% 0.126% 0.126%
278 8 PIPING 3963‐KAHN‐5‐33‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; CRITICAL LINE LIST 1 A 0.042% 22‐Jun‐17 2‐Jul‐17 7‐Jul‐17 7‐Aug‐17 28‐Aug‐17 7‐Sep‐17 31‐Oct‐18 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 21‐Jun‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.040% 0.040%
279 8 PIPING 3963‐KAHN‐5‐32‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING SPECIALTY ITEM LIST 1 A 0.028% 26‐May‐17 5‐Jun‐17 10‐Jun‐17 11‐Jul‐17 1‐Aug‐17 11‐Aug‐17 31‐Oct‐18 31‐May‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 31‐May‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.027% 0.027%
280 8 PIPING 3963‐KAHN‐5‐21‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; TIE‐IN ENGINEERING PACKAGE 3 A 0.224% 8‐Aug‐17 18‐Aug‐17 23‐Aug‐17 6‐Sep‐17 11‐Sep‐17 11‐Sep‐17 31‐Oct‐18 19‐Oct‐17 30‐Mar‐18 1‐Apr‐18 5‐May‐18 31‐May‐18 31‐May‐18 22‐Jul‐19 19‐Oct‐17 30‐Mar‐18 1‐Apr‐18 5‐May‐18 31‐May‐18 31‐May‐18 95% 95% 0% 0.213% 0.213%
281 8 PIPING 3963‐KAHN‐5‐31‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS 3 A 0.336% 12‐Jun‐17 22‐Jun‐17 27‐Jun‐17 28‐Jul‐17 18‐Aug‐17 28‐Aug‐17 31‐Oct‐18 11‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 22‐Jul‐19 11‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 95% 95% 0% 0.319% 0.319%
282 8 PIPING 3963‐KAHN‐5‐31‐0002 ET DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS (EARLY 3 A Y 0.084% 7‐May‐17 11‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 5‐May‐17 7‐May‐17 8‐May‐17 18‐Jul‐17 7‐Sep‐17 7‐Sep‐17 22‐Jul‐19 5‐May‐17 7‐May‐17 8‐May‐17 18‐Jul‐17 7‐Sep‐17 7‐Sep‐17 95% 95% 0% 0.080% 0.080%
283 8 PIPING 3963‐KAHN‐5‐50‐0002 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; KEY PLAN 1 A 0.042% 30‐Jun‐17 10‐Jul‐17 15‐Jul‐17 15‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 6‐Jul‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 22‐Jul‐19 6‐Jul‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 95% 95% 0% 0.040% 0.040%
284 8 PIPING 3963‐KAHN‐5‐52‐0006 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.6 EL.103.590 & ABOVE 1 A 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 19‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.067% 0.067%
285 8 PIPING 3963‐KAHN‐5‐52‐0008 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.8 EL.103.590 & ABOVE 1 B 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 20‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.067% 0.067%
286 8 PIPING 3963‐KAHN‐5‐52‐0009 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.9 EL.103.590 & ABOVE 1 A 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 20‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.067% 0.067%
287 8 PIPING 3963‐KAHN‐5‐52‐0011 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.11 EL.103.590 & ABOV 1 A 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.067% 0.067%
288 8 PIPING 3963‐KAHN‐5‐52‐0012 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.12 EL.103.590 & ABOV 1 A 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.067% 0.067%
289 8 PIPING 3963‐KAHN‐5‐71‐0002 ET DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING ISOMETRICS FOR EARLY TIE‐IN 3 A Y 0.112% 6‐Jul‐17 16‐Jul‐17 20‐Jul‐17 30‐Jul‐17 9‐Aug‐17 19‐Aug‐17 31‐Oct‐18 18‐Jul‐17 19‐Jul‐17 20‐Jul‐17 7‐Sep‐17 7‐Sep‐17 30‐Nov‐17 22‐Jul‐19 18‐Jul‐17 19‐Jul‐17 20‐Jul‐17 7‐Sep‐17 7‐Sep‐17 30‐Nov‐17 95% 95% 0% 0.106% 0.106%
290 8 PIPING 3963‐KAHS‐5‐33‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; CRITICAL LINE LIST 1 A 0.042% 23‐May‐17 2‐Jun‐17 7‐Jun‐17 8‐Jul‐17 29‐Jul‐17 8‐Aug‐17 31‐Oct‐18 25‐May‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 25‐May‐17 19‐Jul‐17 20‐Jul‐17 20‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.040% 0.040%
291 8 PIPING 3963‐KAHS‐5‐32‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING SPECIALTY ITEM LIST 1 A 0.028% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 25‐May‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.027% 0.027%
292 8 PIPING 3963‐KAHS‐5‐21‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; TIE‐IN ENGINEERING PACKAGE 3 A 0.280% 10‐Aug‐17 20‐Aug‐17 25‐Aug‐17 8‐Sep‐17 13‐Sep‐17 13‐Sep‐17 31‐Oct‐18 19‐Oct‐17 6‐Apr‐18 8‐Apr‐18 7‐May‐18 31‐May‐18 31‐May‐18 22‐Jul‐19 19‐Oct‐17 6‐Apr‐18 8‐Apr‐18 7‐May‐18 31‐May‐18 31‐May‐18 95% 95% 0% 0.266% 0.266%
293 8 PIPING 3963‐KAHS‐5‐31‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS 3 A 0.336% 15‐Jun‐17 25‐Jun‐17 30‐Jun‐17 31‐Jul‐17 21‐Aug‐17 31‐Aug‐17 31‐Oct‐18 8‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 22‐Jul‐19 8‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 95% 95% 0% 0.319% 0.319%
294 8 PIPING 3963‐KAHS‐5‐31‐0002 ET DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS (EARLY 3 A Y 0.084% 7‐May‐17 11‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 5‐May‐17 7‐May‐17 8‐May‐17 18‐Jul‐17 7‐Sep‐17 7‐Sep‐17 22‐Jul‐19 5‐May‐17 7‐May‐17 8‐May‐17 18‐Jul‐17 7‐Sep‐17 7‐Sep‐17 95% 95% 0% 0.080% 0.080%
295 8 PIPING 3963‐KAHS‐5‐50‐0002 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; KEY PLAN 1 A 0.042% 20‐Jun‐17 30‐Jun‐17 5‐Jul‐17 5‐Aug‐17 26‐Aug‐17 5‐Sep‐17 31‐Oct‐18 22‐Jun‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 22‐Jul‐19 22‐Jun‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 28‐Nov‐17 95% 95% 0% 0.040% 0.040%
296 8 PIPING 3963‐KAHS‐5‐52‐0004 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.4 EL.26.000 TO 28.600 1 A 0.084% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.080% 0.080%
297 8 PIPING 3963‐KAHS‐5‐52‐0005 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.5 EL.28.600 & ABOVE 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
298 8 PIPING 3963‐KAHS‐5‐52‐0006 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.6 EL.26.000 TO 28.600 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
299 8 PIPING 3963‐KAHS‐5‐52‐0007 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.7 EL.26.000 TO 28.600 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
300 8 PIPING 3963‐KAHS‐5‐52‐0008 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.8 EL.26.000 TO 28.600 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
301 8 PIPING 3963‐KAHS‐5‐52‐0009 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.9 EL.26.000 & ABOVE 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 28‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
302 8 PIPING 3963‐KAHS‐5‐52‐0010 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.10 EL.26.000 & ABOVE 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
303 8 PIPING 3963‐KAHS‐5‐52‐0011 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.11 EL.26.000 & ABOVE 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
304 8 PIPING 3963‐KAHS‐5‐52‐0012 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.12 EL.26.000 & ABOVE 1 A 0.070% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 22‐Jul‐19 29‐Jun‐17 21‐Oct‐17 23‐Oct‐17 7‐Nov‐17 7‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.067% 0.067%
305 8 PIPING 3963‐KAHS‐5‐71‐0002 ET DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING ISOMETRICS FOR EARLY TIE‐IN 3 A Y 0.132% 6‐Jul‐17 16‐Jul‐17 20‐Jul‐17 30‐Jul‐17 9‐Aug‐17 19‐Aug‐17 31‐Oct‐18 18‐Jul‐17 19‐Jul‐17 20‐Jul‐17 20‐Jul‐17 20‐Jul‐17 30‐Nov‐17 22‐Jul‐19 18‐Jul‐17 19‐Jul‐17 20‐Jul‐17 20‐Jul‐17 20‐Jul‐17 30‐Nov‐17 95% 95% 0% 0.126% 0.126%
306 8 PIPING 3963‐FAHM‐5‐33‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; CRITICAL LINE LIST 1 B 0.028% 16‐Jun‐17 26‐Jun‐17 1‐Jul‐17 1‐Aug‐17 22‐Aug‐17 1‐Sep‐17 31‐Oct‐18 22‐Jun‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 13‐Sep‐17 14‐Sep‐17 22‐Jul‐19 22‐Jun‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 13‐Sep‐17 14‐Sep‐17 95% 95% 0% 0.027% 0.027%
307 8 PIPING 3963‐FAHM‐5‐32‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING SPECIALTY ITEM LIST 1 A 0.028% 30‐Jul‐17 9‐Aug‐17 14‐Aug‐17 1‐Sep‐17 11‐Sep‐17 21‐Sep‐17 31‐Oct‐18 29‐Jul‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 29‐Jul‐17 30‐Jul‐17 31‐Jul‐17 18‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.027% 0.027%
308 8 PIPING 3963‐FAHM‐5‐21‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; TIE‐IN ENGINEERING PACKAGE 3 A 0.280% 15‐Aug‐17 25‐Aug‐17 30‐Aug‐17 13‐Sep‐17 18‐Sep‐17 18‐Sep‐17 31‐Oct‐18 19‐Oct‐17 20‐Mar‐18 13‐Aug‐18 30‐Aug‐18 2‐Dec‐18 2‐Dec‐18 22‐Jul‐19 19‐Oct‐17 20‐Mar‐18 13‐Aug‐18 30‐Aug‐18 65% 65% 0% 0.182% 0.182%
309 8 PIPING 3963‐FAHM‐5‐31‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; MATERIAL TAKE OFF ‐ PIPING BULK ITEMS 3 A 0.336% 16‐Jun‐17 26‐Jun‐17 1‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Jul‐17 31‐Oct‐18 22‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 22‐Jul‐19 22‐Jun‐17 6‐Nov‐17 13‐Nov‐17 21‐Dec‐17 10‐Jan‐18 10‐Jan‐18 95% 95% 0% 0.319% 0.319%
310 8 PIPING 3963‐FAHM‐5‐17‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING STRESS ANALYSIS REPORT 3 A 0.420% 30‐Jun‐17 10‐Jul‐17 15‐Jul‐17 29‐Jul‐17 3‐Aug‐17 3‐Aug‐17 31‐Oct‐18 3‐Jul‐17 19‐Sep‐17 20‐Sep‐17 9‐Oct‐17 25‐Oct‐17 29‐Jan‐18 22‐Jul‐19 3‐Jul‐17 19‐Sep‐17 20‐Sep‐17 9‐Oct‐17 25‐Oct‐17 29‐Jan‐18 95% 95% 0% 0.399% 0.399%
311 8 PIPING 3963‐FAHM‐5‐52‐0003 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.3 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 28‐Nov‐17 30‐Nov‐17 1‐Feb‐18 4‐Mar‐18 4‐Mar‐18 22‐Jul‐19 19‐Oct‐17 28‐Nov‐17 30‐Nov‐17 1‐Feb‐18 4‐Mar‐18 4‐Mar‐18 95% 95% 0% 0.093% 0.093%
312 8 PIPING 3963‐FAHM‐5‐52‐0004 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.4 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 31‐Jan‐18 4‐Mar‐18 4‐Mar‐18 22‐Jul‐19 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 31‐Jan‐18 4‐Mar‐18 4‐Mar‐18 95% 95% 0% 0.093% 0.093%
313 8 PIPING 3963‐FAHM‐5‐52‐0005 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.5 EL.60.000 & ABOVE  1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 31‐Jan‐18 4‐Mar‐18 4‐Mar‐18 22‐Jul‐19 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 31‐Jan‐18 4‐Mar‐18 4‐Mar‐18 95% 95% 0% 0.093% 0.093%
314 8 PIPING 3963‐FAHM‐5‐52‐0006 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.6 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 31‐Jan‐18 4‐Mar‐18 4‐Mar‐18 22‐Jul‐19 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 31‐Jan‐18 4‐Mar‐18 4‐Mar‐18 95% 95% 0% 0.093% 0.093%
315 8 PIPING 3963‐FAHM‐5‐52‐0007 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.7 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 4‐Feb‐18 4‐Mar‐18 4‐Mar‐18 22‐Jul‐19 19‐Oct‐17 6‐Nov‐17 8‐Nov‐17 4‐Feb‐18 4‐Mar‐18 4‐Mar‐18 95% 95% 0% 0.093% 0.093%
316 8 PIPING 3963‐FAHM‐5‐52‐0008 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.8 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 12‐Nov‐17 12‐Nov‐17 11‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 12‐Nov‐17 12‐Nov‐17 11‐Jan‐18 95% 95% 0% 0.093% 0.093%
317 8 PIPING 3963‐FAHM‐5‐52‐0009 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.9 EL.60.600 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.093% 0.093%
318 8 PIPING 3963‐FAHM‐5‐52‐0010 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.10 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
319 8 PIPING 3963‐FAHM‐5‐52‐0011 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.11 EL.60.700 & ABOVE  1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
320 8 PIPING 3963‐FAHM‐5‐52‐0012 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐655 SHT.12 EL.60.450 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
321 8 PIPING 3963‐FAHM‐5‐52‐0013 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐655 SHT.13 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
322 8 PIPING 3963‐FAHM‐5‐52‐0014 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐655 SHT.14 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
323 8 PIPING 3963‐FAHM‐5‐52‐0015 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐655 SHT.15 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
324 8 PIPING 3963‐FAHM‐5‐52‐0016 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐ 655 SHT.16 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
325 8 PIPING 3963‐FAHM‐5‐52‐0017 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐ 655 SHT.17 EL.60.000 & ABOVE  1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
326 8 PIPING 3963‐FAHM‐5‐52‐0018 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐ 655 SHT.18 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
327 8 PIPING 3963‐FAHM‐5‐52‐0019 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐ 655 SHT.19 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
328 8 PIPING 3963‐FAHM‐5‐52‐0020 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐ 655 SHT.20 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.093% 0.093%
329 8 PIPING 3963‐FAHM‐5‐52‐0021 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA‐ 655 SHT.21 EL.60.000 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 2‐Nov‐17 23‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.093% 0.093%
330 8 PIPING DEM‐3963‐FAHM‐5‐50‐0001 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PLOT PLAN 1 A 0.056% 22‐May‐17 1‐Jun‐17 6‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 25‐May‐17 25‐Jul‐17 26‐Jul‐17 24‐Aug‐17 14‐Sep‐17 18‐Oct‐17 22‐Jul‐19 25‐May‐17 25‐Jul‐17 26‐Jul‐17 24‐Aug‐17 14‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.053% 0.053%
331 8 PIPING DEM‐3963‐FAHM‐5‐52‐0001 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.1 EL.60.000 & ABOVE (DEM 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 95% 95% 0% 0.027% 0.027%
332 8 PIPING DEM‐3963‐FAHM‐5‐52‐0002 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.2 EL.60.000 & ABOVE (DEM 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 22‐Jul‐19 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 95% 95% 0% 0.040% 0.040%
333 8 PIPING DEM‐3963‐FAHM‐5‐52‐0003 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.3 EL.60.000 & ABOVE (DEM 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 22‐Jul‐19 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 95% 95% 0% 0.040% 0.040%
334 8 PIPING DEM‐3963‐FAHM‐5‐52‐0004 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.4 EL.60.000 & ABOVE (DEM 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 22‐Jul‐19 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 95% 95% 0% 0.027% 0.027%
335 8 PIPING DEM‐3963‐FAHM‐5‐52‐0005 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.5 EL.60.000 & ABOVE (DEM 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 24‐Aug‐17 14‐Sep‐17 17‐Oct‐17 95% 95% 0% 0.027% 0.027%
336 8 PIPING DEM‐3963‐FAHM‐5‐52‐0006 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.6 EL.60.000 & ABOVE (DEM 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 17‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 17‐Oct‐17 95% 95% 0% 0.027% 0.027%
337 8 PIPING DEM‐3963‐FAHM‐5‐52‐0007 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.7 EL.60.000 & ABOVE (DEM 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 17‐Oct‐17 22‐Jul‐19 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 17‐Oct‐17 95% 95% 0% 0.027% 0.027%
338 8 PIPING DEM‐3963‐FAHM‐5‐52‐0008 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.8 EL.60.000 & ABOVE (DEM 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
339 8 PIPING DEM‐3963‐FAHM‐5‐52‐0009 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.9 EL.60.700 & ABOVE (DEM 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
340 8 PIPING DEM‐3963‐FAHM‐5‐52‐0010 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.10 EL.60.450 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
341 8 PIPING DEM‐3963‐FAHM‐5‐52‐0011 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.11 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 22‐Jul‐19 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Aug‐17 5‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
342 8 PIPING DEM‐3963‐FAHM‐5‐52‐0012 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.12 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 29‐Aug‐17 17‐Oct‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 29‐Aug‐17 17‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
343 8 PIPING DEM‐3963‐FAHM‐5‐52‐0013 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.13 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 31‐Aug‐17 20‐Sep‐17 18‐Oct‐17 22‐Jul‐19 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 31‐Aug‐17 20‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
344 8 PIPING DEM‐3963‐FAHM‐5‐52‐0014 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.14 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 31‐Aug‐17 20‐Sep‐17 18‐Oct‐17 22‐Jul‐19 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 31‐Aug‐17 20‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
345 8 PIPING DEM‐3963‐FAHM‐5‐52‐0015 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.15 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 31‐Aug‐17 20‐Sep‐17 18‐Oct‐17 22‐Jul‐19 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 31‐Aug‐17 20‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
346 8 PIPING DEM‐3963‐FAHM‐5‐52‐0016 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.16 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 29‐Aug‐17 17‐Oct‐17 18‐Oct‐17 22‐Jul‐19 13‐Jul‐17 6‐Aug‐17 8‐Aug‐17 29‐Aug‐17 17‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
347 8 PIPING DEM‐3963‐FAHM‐5‐52‐0017 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.17 EL.60.200 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 6‐Aug‐17 8‐Aug‐17 29‐Aug‐17 17‐Oct‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 6‐Aug‐17 8‐Aug‐17 29‐Aug‐17 17‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.027% 0.027%
348 8 PIPING DEM‐3963‐FAHM‐5‐52‐0018 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.18 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 10‐Sep‐17 11‐Sep‐17 26‐Sep‐17 26‐Sep‐17 26‐Sep‐17 22‐Jul‐19 8‐Jul‐17 10‐Sep‐17 11‐Sep‐17 26‐Sep‐17 26‐Sep‐17 26‐Sep‐17 95% 95% 0% 0.027% 0.027%
349 8 PIPING DEM‐3963‐FAHM‐5‐52‐0019 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.19 EL.60.000 & ABOVE (DE 1 A 0.028% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 10‐Sep‐17 11‐Sep‐17 26‐Sep‐17 26‐Sep‐17 26‐Sep‐17 22‐Jul‐19 8‐Jul‐17 10‐Sep‐17 11‐Sep‐17 26‐Sep‐17 26‐Sep‐17 26‐Sep‐17 95% 95% 0% 0.027% 0.027%
350 8 PIPING DEM‐3963‐FAHM‐5‐52‐0020 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.23 EL.60.000 & ABOVE (DE 1 A 0.056% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 20‐Oct‐17 22‐Oct‐17 24‐Oct‐17 13‐Nov‐17 13‐Nov‐17 13‐Nov‐17 22‐Jul‐19 20‐Oct‐17 22‐Oct‐17 24‐Oct‐17 13‐Nov‐17 13‐Nov‐17 13‐Nov‐17 95% 95% 0% 0.053% 0.053%
351 8 PIPING DEM‐3963‐FAHM‐5‐52‐0021 DEM DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.25 EL.60.000 & ABOVE (DE 1 A 0.056% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 20‐Oct‐17 22‐Oct‐17 24‐Oct‐17 13‐Nov‐17 13‐Nov‐17 13‐Nov‐17 22‐Jul‐19 20‐Oct‐17 22‐Oct‐17 24‐Oct‐17 13‐Nov‐17 13‐Nov‐17 13‐Nov‐17 95% 95% 0% 0.053% 0.053%
352 8 PIPING DEM‐3963‐FAHN‐5‐50‐0001 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PLOT PLAN (DEMOLITION) 1 A 0.056% 29‐May‐17 8‐Jun‐17 13‐Jun‐17 14‐Jul‐17 4‐Aug‐17 14‐Aug‐17 31‐Oct‐18 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 27‐Aug‐17 14‐Sep‐17 18‐Oct‐17 22‐Jul‐19 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 27‐Aug‐17 14‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.053% 0.053%
353 8 PIPING DEM‐3963‐FAHN‐5‐52‐0001 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.1 EL.21.600 TO 24.050  1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 22‐Jul‐19 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
354 8 PIPING DEM‐3963‐FAHN‐5‐52‐0002 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 400, SHT.2 EL.21.600 & ABOVE (D 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
355 8 PIPING DEM‐3963‐FAHN‐5‐52‐0003 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.3 EL. 21.600 & ABOVE ( 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
356 8 PIPING DEM‐3963‐FAHN‐5‐52‐0004 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.4 EL.21.600 & ABOVE (D 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 2‐Oct‐17 15‐Oct‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 2‐Oct‐17 15‐Oct‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
357 8 PIPING DEM‐3963‐FAHN‐5‐52‐0005 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.5 EL. 21.600 & ABOVE ( 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
358 8 PIPING DEM‐3963‐FAHN‐5‐52‐0006 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.6 EL. 21.600 & ABOVE ( 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
359 8 PIPING DEM‐3963‐FAHN‐5‐52‐0007 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.7 EL. 22.620 & ABOVE ( 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 20‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
360 8 PIPING DEM‐3963‐FAHN‐5‐52‐0008 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.8 EL. 22.620 & ABOVE ( 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
361 8 PIPING DEM‐3963‐FAHN‐5‐52‐0009 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.9 EL. 22.620 & ABOVE ( 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 19‐Jul‐17 8‐Aug‐17 10‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
362 8 PIPING DEM‐3963‐FAHN‐5‐52‐0010 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.10 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
363 8 PIPING DEM‐3963‐FAHN‐5‐52‐0011 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.11 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
364 8 PIPING DEM‐3963‐FAHN‐5‐52‐0012 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.12 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 22‐Jul‐19 19‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
365 8 PIPING DEM‐3963‐FAHN‐5‐52‐0013 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.13 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
366 8 PIPING DEM‐3963‐FAHN‐5‐52‐0014 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.14 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
367 8 PIPING DEM‐3963‐FAHN‐5‐52‐0015 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.15 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 22‐Jul‐19 15‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 28‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
368 8 PIPING DEM‐3963‐FAHN‐5‐52‐0016 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.16 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 20‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
369 8 PIPING DEM‐3963‐FAHN‐5‐52‐0017 DEM DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING GA, AREA 401, SHT.17 EL. 22.620 & ABOVE 1 A 0.042% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 22‐Jul‐19 20‐Jul‐17 11‐Aug‐17 13‐Aug‐17 17‐Sep‐17 25‐Sep‐17 16‐Oct‐17 95% 95% 0% 0.040% 0.040%
370 8 PIPING DEM‐3963‐FAHS‐5‐50‐0001 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PLOT PLAN (DEMOLITION) 1 A 0.056% 12‐Jun‐17 22‐Jun‐17 27‐Jun‐17 28‐Jul‐17 18‐Aug‐17 28‐Aug‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 14‐Sep‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 14‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.053% 0.053%
371 8 PIPING DEM‐3963‐FAHS‐5‐52‐0001 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.1 EL. 54.364 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 24‐Sep‐17 17‐Oct‐17 18‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 24‐Sep‐17 17‐Oct‐17 18‐Oct‐17 95% 95% 0% 0.040% 0.040%

Page 3 of 13
Page 74 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
372 8 PIPING DEM‐3963‐FAHS‐5‐52‐0002 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.2 EL. 54.364 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 95% 95% 0% 0.040% 0.040%
373 8 PIPING DEM‐3963‐FAHS‐5‐52‐0003 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.3 EL. 54.364 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 95% 95% 0% 0.040% 0.040%
374 8 PIPING DEM‐3963‐FAHS‐5‐52‐0004 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.4 EL. 54.364 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 95% 95% 0% 0.040% 0.040%
375 8 PIPING DEM‐3963‐FAHS‐5‐52‐0005 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.5 EL. 54.364 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 95% 95% 0% 0.040% 0.040%
376 8 PIPING DEM‐3963‐FAHS‐5‐52‐0006 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.6 EL. 54.700 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 95% 95% 0% 0.040% 0.040%
377 8 PIPING DEM‐3963‐FAHS‐5‐52‐0007 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.7 EL. 54.700 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 3‐Oct‐17 3‐Oct‐17 3‐Oct‐17 95% 95% 0% 0.040% 0.040%
378 8 PIPING DEM‐3963‐FAHS‐5‐52‐0008 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.8 EL. 54.364 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 14‐Aug‐17 15‐Aug‐17 16‐Aug‐17 17‐Aug‐17 18‐Aug‐17 22‐Jul‐19 27‐Jul‐17 14‐Aug‐17 15‐Aug‐17 16‐Aug‐17 17‐Aug‐17 18‐Aug‐17 95% 95% 0% 0.040% 0.040%
379 8 PIPING DEM‐3963‐FAHS‐5‐52‐0009 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.9 EL. 54.364 & ABOVE ( 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
380 8 PIPING DEM‐3963‐FAHS‐5‐52‐0010 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.10 EL. 54.364 & ABOVE 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
381 8 PIPING DEM‐3963‐FAHS‐5‐52‐0011 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.11 EL. 54.664 & ABOVE 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
382 8 PIPING DEM‐3963‐FAHS‐5‐52‐0012 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.12 EL. 54.364 & ABOVE 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
383 8 PIPING DEM‐3963‐FAHS‐5‐52‐0013 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.13 EL. 54.364 & ABOVE 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
384 8 PIPING DEM‐3963‐FAHS‐5‐52‐0014 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.14 EL. 54.364 & ABOVE 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
385 8 PIPING DEM‐3963‐FAHS‐5‐52‐0015 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.15 EL. 54.364 & ABOVE 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
386 8 PIPING DEM‐3963‐FAHS‐5‐52‐0016 DEM DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPING GA, AREA 701, SHT.16 EL. 54.364 & ABOVE 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 27‐Jul‐17 15‐Aug‐17 17‐Aug‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.040% 0.040%
387 8 PIPING DEM‐3963‐JALM‐5‐50‐0001 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PLOT PLAN (DEMOLITION) 1 A 0.056% 19‐Jun‐17 29‐Jun‐17 4‐Jul‐17 4‐Aug‐17 25‐Aug‐17 4‐Sep‐17 31‐Oct‐18 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 20‐Sep‐17 18‐Oct‐17 22‐Jul‐19 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 20‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.053% 0.053%
388 8 PIPING DEM‐3963‐JALM‐5‐52‐0001 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 803, SHT.1 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 95% 95% 0% 0.040% 0.040%
389 8 PIPING DEM‐3963‐JALM‐5‐52‐0002 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 803, SHT.2 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 95% 95% 0% 0.040% 0.040%
390 8 PIPING DEM‐3963‐JALM‐5‐52‐0003 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.3 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 95% 95% 0% 0.040% 0.040%
391 8 PIPING DEM‐3963‐JALM‐5‐52‐0004 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.4 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 95% 95% 0% 0.040% 0.040%
392 8 PIPING DEM‐3963‐JALM‐5‐52‐0005 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.5 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 95% 95% 0% 0.040% 0.040%
393 8 PIPING DEM‐3963‐JALM‐5‐52‐0006 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.6 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 95% 95% 0% 0.040% 0.040%
394 8 PIPING DEM‐3963‐JALM‐5‐52‐0007 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.7 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 95% 95% 0% 0.040% 0.040%
395 8 PIPING DEM‐3963‐JALM‐5‐52‐0008 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.8 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 95% 95% 0% 0.040% 0.040%
396 8 PIPING DEM‐3963‐JALM‐5‐52‐0009 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.9 EL. 63.000 & ABOVE (DE 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 95% 95% 0% 0.040% 0.040%
397 8 PIPING DEM‐3963‐JALM‐5‐52‐0010 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.10 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 95% 95% 0% 0.040% 0.040%
398 8 PIPING DEM‐3963‐JALM‐5‐52‐0011 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.11 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 22‐Jul‐19 27‐Jul‐17 17‐Aug‐17 20‐Aug‐17 9‐Nov‐17 9‐Nov‐17 9‐Nov‐17 95% 95% 0% 0.040% 0.040%
399 8 PIPING DEM‐3963‐JALM‐5‐52‐0012 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.12 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 5‐Oct‐17 9‐Oct‐17 9‐Oct‐17 95% 95% 0% 0.040% 0.040%
400 8 PIPING DEM‐3963‐JALM‐5‐52‐0013 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.13 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
401 8 PIPING DEM‐3963‐JALM‐5‐52‐0014 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.14 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
402 8 PIPING DEM‐3963‐JALM‐5‐52‐0015 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.15 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
403 8 PIPING DEM‐3963‐JALM‐5‐52‐0016 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.16 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 22‐Jul‐19 27‐Jul‐17 18‐Aug‐17 21‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
404 8 PIPING DEM‐3963‐JALM‐5‐52‐0017 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.17 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 22‐Jul‐19 27‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
405 8 PIPING DEM‐3963‐JALM‐5‐52‐0018 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.18 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 22‐Jul‐19 27‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
406 8 PIPING DEM‐3963‐JALM‐5‐52‐0019 DEM DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING GA, AREA 805, SHT.19 EL. 63.000 & ABOVE (D 1 A 0.042% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 27‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 22‐Jul‐19 27‐Jul‐17 19‐Aug‐17 22‐Aug‐17 27‐Sep‐17 11‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
407 8 PIPING DEM‐3963‐KAHM‐5‐50‐0001 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PLOT PLAN (DEMOLITION) 1 A 0.056% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 7‐Jun‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 20‐Sep‐17 18‐Oct‐17 22‐Jul‐19 7‐Jun‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 20‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.053% 0.053%
408 8 PIPING DEM‐3963‐KAHM‐5‐52‐0001 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.1 EL.98.973 & ABOVE (D 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 11‐Jul‐17 17‐Oct‐17 18‐Oct‐17 6‐Nov‐17 6‐Nov‐17 23‐Nov‐17 22‐Jul‐19 11‐Jul‐17 17‐Oct‐17 18‐Oct‐17 6‐Nov‐17 6‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.040% 0.040%
409 8 PIPING DEM‐3963‐KAHM‐5‐52‐0002 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.2 EL. 99.143 & ABOVE ( 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.040% 0.040%
410 8 PIPING DEM‐3963‐KAHM‐5‐52‐0003 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.3 EL.99.143 & ABOVE (D 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.040% 0.040%
411 8 PIPING DEM‐3963‐KAHM‐5‐52‐0004 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.4 EL. 99.143 & ABOVE ( 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 22‐Jul‐19 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.040% 0.040%
412 8 PIPING DEM‐3963‐KAHM‐5‐52‐0005 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.5 EL. 99.743 & ABOVE ( 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 6‐Nov‐17 6‐Nov‐17 23‐Nov‐17 22‐Jul‐19 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 6‐Nov‐17 6‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.040% 0.040%
413 8 PIPING DEM‐3963‐KAHM‐5‐52‐0006 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.6 EL. 98.973 & ABOVE ( 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 22‐Jul‐19 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.040% 0.040%
414 8 PIPING DEM‐3963‐KAHM‐5‐52‐0007 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.7 EL. 99.863 & ABOVE ( 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 6‐Nov‐17 6‐Nov‐17 23‐Nov‐17 22‐Jul‐19 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 6‐Nov‐17 6‐Nov‐17 23‐Nov‐17 95% 95% 0% 0.040% 0.040%
415 8 PIPING DEM‐3963‐KAHM‐5‐52‐0008 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.8 SH24 EL.99.743 & AB 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 22‐Jul‐19 13‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.040% 0.040%
416 8 PIPING DEM‐3963‐KAHM‐5‐52‐0009 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255, SHT.9 EL.99.443 & ABOVE (D 1 A 0.042% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 22‐Jul‐19 8‐Jul‐17 2‐Aug‐17 3‐Aug‐17 18‐Sep‐17 25‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.040% 0.040%
417 8 PIPING DEM‐3963‐KAHN‐5‐50‐0001 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PLOT PLAN (DEMOLITION) 1 A 0.056% 26‐Jun‐17 6‐Jul‐17 11‐Jul‐17 11‐Aug‐17 1‐Sep‐17 11‐Sep‐17 31‐Oct‐18 29‐Jun‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 20‐Sep‐17 18‐Oct‐17 22‐Jul‐19 29‐Jun‐17 2‐Aug‐17 3‐Aug‐17 27‐Aug‐17 20‐Sep‐17 18‐Oct‐17 95% 95% 0% 0.053% 0.053%
418 8 PIPING DEM‐3963‐KAHN‐5‐52‐0001 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151, SHT.1 EL.103.590 & ABOVE 1 A 0.042% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 22‐Jul‐19 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 95% 95% 0% 0.040% 0.040%
419 8 PIPING DEM‐3963‐KAHN‐5‐52‐0002 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151, SHT.2 EL.103.590 & ABOVE 1 A 0.042% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 22‐Jul‐19 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 95% 95% 0% 0.040% 0.040%
420 8 PIPING DEM‐3963‐KAHN‐5‐52‐0003 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151, SHT.3 EL.103.590 & ABOVE 1 A 0.042% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 22‐Jul‐19 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 95% 95% 0% 0.040% 0.040%
421 8 PIPING DEM‐3963‐KAHN‐5‐52‐0004 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151, SHT.4 EL.103.590 & ABOVE 1 A 0.042% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 22‐Jul‐19 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 95% 95% 0% 0.040% 0.040%
422 8 PIPING DEM‐3963‐KAHN‐5‐52‐0005 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151, SHT.5 EL.103.590 & ABOVE 1 A 0.042% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 22‐Jul‐19 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 95% 95% 0% 0.040% 0.040%
423 8 PIPING DEM‐3963‐KAHN‐5‐52‐0006 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151, SHT.6 EL.103.590 & ABOVE 1 A 0.042% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 22‐Jul‐19 20‐Aug‐17 17‐Aug‐17 20‐Aug‐17 19‐Oct‐17 30‐Oct‐17 19‐Nov‐17 95% 95% 0% 0.040% 0.040%
424 8 PIPING DEM‐3963‐KAHS‐5‐50‐0001 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PLOT PLAN (DEMOLITION) 1 A 0.056% 29‐Jun‐17 9‐Jul‐17 14‐Jul‐17 14‐Aug‐17 4‐Sep‐17 14‐Sep‐17 31‐Oct‐18 28‐Jun‐17 2‐Aug‐17 3‐Aug‐17 3‐Aug‐17 3‐Aug‐17 3‐Aug‐17 22‐Jul‐19 28‐Jun‐17 2‐Aug‐17 3‐Aug‐17 3‐Aug‐17 3‐Aug‐17 3‐Aug‐17 95% 95% 0% 0.053% 0.053%
425 8 PIPING DEM‐3963‐KAHS‐5‐52‐0001 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300, SHT.1 EL.26.000 TO 28.600 1 A 0.042% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 25‐Sep‐17 14‐Nov‐17 22‐Jul‐19 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 25‐Sep‐17 14‐Nov‐17 95% 95% 0% 0.040% 0.040%
426 8 PIPING DEM‐3963‐KAHS‐5‐52‐0002 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300, SHT.2 EL.28.600 & ABOVE  1 A 0.042% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 22‐Jul‐19 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 95% 95% 0% 0.040% 0.040%
427 8 PIPING DEM‐3963‐KAHS‐5‐52‐0003 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300, SHT.3 EL.26.000 TO 28.600 1 A 0.042% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 22‐Jul‐19 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 95% 95% 0% 0.040% 0.040%
428 8 PIPING DEM‐3963‐KAHS‐5‐52‐0004 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300, SHT.4 EL.26.000 &ABOVE ( 1 A 0.042% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 22‐Jul‐19 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 95% 95% 0% 0.040% 0.040%
429 8 PIPING DEM‐3963‐KAHS‐5‐52‐0005 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300, SHT.5 EL.26.000 & ABOVE  1 A 0.042% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 22‐Jul‐19 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 28‐Sep‐17 14‐Nov‐17 95% 95% 0% 0.040% 0.040%
430 8 PIPING DEM‐3963‐KAHS‐5‐52‐0006 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300, SHT.6 EL.26.000 & ABOVE  1 A 0.042% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 25‐Sep‐17 14‐Nov‐17 22‐Jul‐19 16‐Aug‐17 18‐Aug‐17 21‐Aug‐17 18‐Sep‐17 25‐Sep‐17 14‐Nov‐17 95% 95% 0% 0.040% 0.040%
431 8 PIPING DEM‐3963‐KAHS‐5‐52‐0007 DEM DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300, SHT.7 EL.26.000 & ABOVE  1 A 0.084% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 19‐Oct‐17 19‐Nov‐17 21‐Nov‐17 5‐Dec‐17 5‐Dec‐17 5‐Dec‐17 22‐Jul‐19 19‐Oct‐17 19‐Nov‐17 21‐Nov‐17 5‐Dec‐17 5‐Dec‐17 5‐Dec‐17 95% 95% 0% 0.080% 0.080%
432 8 PIPING 3963‐FAHM‐5‐32‐0002 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; VALVE LIST 1 A 0.140% 19‐May‐17 29‐May‐17 3‐Jun‐17 4‐Jul‐17 25‐Jul‐17 4‐Aug‐17 31‐Oct‐18 25‐May‐17 22‐Jul‐17 23‐Jul‐17 10‐Aug‐17 20‐Aug‐17 26‐Oct‐17 22‐Jul‐19 25‐May‐17 22‐Jul‐17 23‐Jul‐17 10‐Aug‐17 20‐Aug‐17 26‐Oct‐17 95% 95% 0% 0.133% 0.133%
433 8 PIPING 3963‐FAHS‐5‐32‐0002 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; VALVE LIST 1 B 0.168% 21‐May‐17 31‐May‐17 5‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 25‐May‐17 22‐Jul‐17 23‐Jul‐17 10‐Aug‐17 23‐Aug‐17 24‐Aug‐17 22‐Jul‐19 25‐May‐17 22‐Jul‐17 23‐Jul‐17 10‐Aug‐17 23‐Aug‐17 24‐Aug‐17 95% 95% 0% 0.160% 0.160%
434 8 PIPING 3963‐FAHN‐5‐32‐0002 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; VALVE LIST 1 A 0.140% 23‐May‐17 2‐Jun‐17 7‐Jun‐17 8‐Jul‐17 29‐Jul‐17 8‐Aug‐17 31‐Oct‐18 25‐May‐17 22‐Jul‐17 23‐Jul‐17 10‐Aug‐17 20‐Aug‐17 5‐Nov‐17 22‐Jul‐19 25‐May‐17 22‐Jul‐17 23‐Jul‐17 10‐Aug‐17 20‐Aug‐17 5‐Nov‐17 95% 95% 0% 0.133% 0.133%
435 8 PIPING 3963‐KAHM‐5‐32‐0002 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; VALVE LIST 1 A 0.070% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 25‐May‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 14‐Sep‐17 14‐Nov‐17 22‐Jul‐19 25‐May‐17 19‐Jul‐17 20‐Jul‐17 23‐Aug‐17 14‐Sep‐17 14‐Nov‐17 95% 95% 0% 0.067% 0.067%
436 8 PIPING 3963‐KAHS‐5‐32‐0002 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; VALVE LIST 1 A 0.070% 16‐May‐17 26‐May‐17 31‐May‐17 1‐Jul‐17 22‐Jul‐17 1‐Aug‐17 31‐Oct‐18 25‐May‐17 24‐Jul‐17 25‐Jul‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 22‐Jul‐19 25‐May‐17 24‐Jul‐17 25‐Jul‐17 2‐Nov‐17 2‐Nov‐17 24‐Jan‐18 95% 95% 0% 0.067% 0.067%
437 8 PIPING 3963‐KAHN‐5‐32‐0002 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; VALVE LIST 1 A 0.070% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 24‐Jul‐17 25‐Jul‐17 23‐Aug‐17 14‐Sep‐17 2‐Nov‐17 22‐Jul‐19 25‐May‐17 24‐Jul‐17 25‐Jul‐17 23‐Aug‐17 14‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.067% 0.067%
438 8 PIPING 3963‐JALM‐5‐32‐0002 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; VALVE LIST 1 A 0.140% 22‐May‐17 1‐Jun‐17 6‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 25‐May‐17 24‐Jul‐17 25‐Jul‐17 23‐Aug‐17 14‐Sep‐17 2‐Nov‐17 22‐Jul‐19 25‐May‐17 24‐Jul‐17 25‐Jul‐17 23‐Aug‐17 14‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.133% 0.133%
439 8 PIPING 3963‐KAHM‐5‐32‐0015 ET DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; VALVE LIST (EARLY TIE‐IN) 1 A Y 0.070% 8‐Mar‐17 18‐Mar‐17 23‐Mar‐17 23‐Apr‐17 14‐May‐17 24‐May‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 30‐May‐17 12‐Jun‐17 12‐Jun‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 30‐May‐17 12‐Jun‐17 12‐Jun‐17 95% 95% 0% 0.067% 0.067%
440 8 PIPING 3963‐KAHN‐5‐32‐0016 ET DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; VALVE LIST (EARLY TIE‐IN) 1 A Y 0.070% 8‐Mar‐17 18‐Mar‐17 23‐Mar‐17 23‐Apr‐17 14‐May‐17 24‐May‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 30‐May‐17 12‐Jun‐17 12‐Jun‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 30‐May‐17 12‐Jun‐17 12‐Jun‐17 95% 95% 0% 0.067% 0.067%
441 8 PIPING 3963‐KAHS‐5‐32‐0017 ET DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; VALVE LIST (EARLY TIE‐IN) 1 A Y 0.070% 8‐Mar‐17 18‐Mar‐17 23‐Mar‐17 23‐Apr‐17 14‐May‐17 24‐May‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 30‐May‐17 12‐Jun‐17 12‐Jun‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 30‐May‐17 12‐Jun‐17 12‐Jun‐17 95% 95% 0% 0.067% 0.067%
442 8 PIPING 3963‐DGEN‐5‐17‐0006 ET DUKHAN FIELD; TECHNICAL BID EVALUATION FOR BALL VALVES (EARLY TIE‐INS) 1 A Y 0.056% 26‐Mar‐17 5‐Apr‐17 10‐Apr‐17 11‐May‐17 1‐Jun‐17 11‐Jun‐17 31‐Oct‐18 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 5‐Jun‐17 24‐Jul‐17 25‐Jul‐17 22‐Jul‐19 15‐Mar‐17 17‐Mar‐17 20‐Mar‐17 5‐Jun‐17 24‐Jul‐17 25‐Jul‐17 95% 95% 0% 0.053% 0.053%
443 8 PIPING 3963‐DGEN‐5‐31‐0001 OT DUKHAN FIELD ‐MTO FOR BALL VALVES 1 A 0.196% 24‐Jul‐17 26‐Jul‐17 28‐Jul‐17 9‐Aug‐17 21‐Aug‐17 2‐Sep‐17 31‐Oct‐18 21‐Mar‐17 30‐Jul‐17 31‐Jul‐17 9‐Dec‐17 21‐Dec‐17 21‐Dec‐17 22‐Jul‐19 21‐Mar‐17 30‐Jul‐17 31‐Jul‐17 9‐Dec‐17 21‐Dec‐17 21‐Dec‐17 95% 95% 0% 0.186% 0.186%
444 8 PIPING 3963‐DGEN‐5‐31‐0002 OT DUKHAN FIELD ‐ MTO FOR MANUAL VALVES (GATE, GLOBE, NEEDLE & CHECK) 1 A 0.191% 24‐Jul‐17 26‐Jul‐17 28‐Jul‐17 9‐Aug‐17 21‐Aug‐17 2‐Sep‐17 31‐Oct‐18 27‐Jul‐17 30‐Jul‐17 31‐Jul‐17 25‐Oct‐17 25‐Oct‐17 4‐Dec‐17 22‐Jul‐19 27‐Jul‐17 30‐Jul‐17 31‐Jul‐17 25‐Oct‐17 25‐Oct‐17 4‐Dec‐17 95% 95% 0% 0.181% 0.181%
445 8 PIPING 3963‐DGEN‐5‐13‐0008 OT DUKHAN FIELD ‐DATASHEET FOR BUTTERFLY VALVES 1 A 0.090% 1‐Aug‐17 6‐Aug‐17 11‐Aug‐17 21‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jul‐17 1‐Aug‐17 3‐Aug‐17 17‐Aug‐17 30‐Aug‐17 5‐Oct‐17 22‐Jul‐19 28‐Jul‐17 1‐Aug‐17 3‐Aug‐17 17‐Aug‐17 30‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.085% 0.085%
446 8 PIPING 3963‐DGEN‐5‐13‐0009 OT DUKHAN FIELD ‐ DATASHEET FOR STRAINERS 1 A 0.168% 1‐Aug‐17 6‐Aug‐17 11‐Aug‐17 21‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jul‐17 1‐Aug‐17 3‐Aug‐17 17‐Aug‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 28‐Jul‐17 1‐Aug‐17 3‐Aug‐17 17‐Aug‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.160% 0.160%
447 8 PIPING 3963‐DGEN‐5‐15‐0007 OT DUKHAN FIELD – MATERIAL REQUISITION FOR BUTTERFLY VALVES 1 A 0.084% 1‐Aug‐17 6‐Aug‐17 11‐Aug‐17 21‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jul‐17 1‐Aug‐17 3‐Aug‐17 17‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 28‐Jul‐17 1‐Aug‐17 3‐Aug‐17 17‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.080% 0.080%
448 6 PIPING 3963‐DGEN‐5‐00‐0001 OT MISCELLANEOUS ‐ PIPING 0 0.000% 31‐Aug‐17 6‐Sep‐17 7‐Sep‐17 14‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 1‐Feb‐18 6‐Feb‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 22‐Jul‐19 1‐Feb‐18 6‐Feb‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 95% 95% 0% 0.000% 0.000%
449 8 PIPING 3963‐FAHM‐7780‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:14‐7780‐6"‐OC‐CS1‐900‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
450 8 PIPING 3963‐FAHM‐7775‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:14‐7775‐6''‐OC‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
451 8 PIPING 3963‐FAHM‐7776‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:14‐7776‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
452 8 PIPING 3963‐FAHM‐1222‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐1222‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
453 8 PIPING 3963‐FAHM‐7790‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7790‐6''‐WD‐L5‐300‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
454 8 PIPING 3963‐FAHM‐7811‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7811‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
455 8 PIPING 3963‐FAHM‐7822‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7822‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
456 8 PIPING 3963‐FAHM‐7807‐3‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7807‐3''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
457 8 PIPING 3963‐FAHM‐7808‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7808‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
458 8 PIPING 3963‐FAHM‐7809‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7809‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
459 8 PIPING 3963‐FAHM‐7810‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7810‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
460 8 PIPING 3963‐FAHM‐8008‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8008‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
461 8 PIPING 3963‐FAHM‐8009‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8009‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
462 8 PIPING 3963‐FAHM‐8010‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8010‐3''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
463 8 PIPING 3963‐FAHM‐8011‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8011‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
464 8 PIPING 3963‐FAHM‐8013‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8013‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
465 8 PIPING 3963‐FAHM‐8012‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8012‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
466 8 PIPING 3963‐FAHM‐7777‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:14‐7777‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
467 8 PIPING 3963‐FAHM‐7778‐4‐OC OT PIPING ISOMETRICS ‐ LINE NO.:14‐7778‐4''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
468 8 PIPING 3963‐FAHM‐7779‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:14‐7779‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
469 8 PIPING 3963‐FAHM‐7791‐4‐WD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7791‐4"‐WD‐L5‐300‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
470 8 PIPING 3963‐FAHM‐7792‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7792‐6''‐WD‐L5‐300‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
471 8 PIPING 3963‐FAHM‐8015‐8‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8015‐8''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
472 8 PIPING 3963‐FAHM‐8014‐4‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8014‐4''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
473 8 PIPING 3963‐FAHM‐1224‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐1224‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
474 8 PIPING 3963‐FAHM‐1223‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐1223‐8"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
475 8 PIPING 3963‐FAHM‐1225‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐1225‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
476 8 PIPING 3963‐FAHM‐1227‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐1227‐8''‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
477 8 PIPING 3963‐FAHM‐1228‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐1228‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
478 8 PIPING 3963‐FAHM‐8017‐2‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐8017‐2"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
479 8 PIPING 3963‐FAHM‐8016‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:14‐8016‐3"‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
480 8 PIPING 3963‐FAHM‐1226‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:14‐1226‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
481 8 PIPING 3963‐FAHM‐7818‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7818‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
482 8 PIPING 3963‐FAHM‐7823‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7823‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
483 8 PIPING 3963‐FAHM‐7824‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7824‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
484 8 PIPING 3963‐FAHM‐7816‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7816‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
485 8 PIPING 3963‐FAHM‐7815‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7815‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
486 8 PIPING 3963‐FAHM‐7820‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7820‐2"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
487 8 PIPING 3963‐FAHM‐7817‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7817‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
488 8 PIPING 3963‐FAHM‐7821‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7821‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
489 8 PIPING 3963‐FAHM‐7819‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7819‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
490 8 PIPING 3963‐FAHM‐7812‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7812‐1"‐OD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
491 8 PIPING 3963‐FAHM‐7813‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:14‐7813‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
492 8 PIPING 3963‐FAHM‐8012‐2‐AI OT PIPING ISOMETRICS ‐ LINE NO.:14‐8012‐2"‐AI‐CS1‐150‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 14‐Mar‐18 14‐Mar‐18 14‐Mar‐18 14‐Mar‐18 14‐Mar‐18 22‐Jul‐19 18‐Jan‐18 14‐Mar‐18 14‐Mar‐18 14‐Mar‐18 14‐Mar‐18 14‐Mar‐18 95% 95% 0% 0.019% 0.019%
493 8 PIPING 3963‐FAHM‐7805‐4‐WF OT PIPING ISOMETRICS ‐ LINE NO.:14‐7805‐4"‐WF‐L5‐150‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
494 8 PIPING 3963‐FAHM‐7807‐2‐WF OT PIPING ISOMETRICS ‐ LINE NO.:14‐7807‐2"‐WF‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
495 8 PIPING 3963‐FAHN‐4304‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:12‐4304‐6"‐OC‐CS1‐900‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%

Page 4 of 13
Page 75 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
496 8 PIPING 3963‐FAHN‐4299‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:12‐4299‐6''‐OC‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
497 8 PIPING 3963‐FAHN‐4300‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:12‐4300‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
498 8 PIPING 3963‐FAHN‐4315‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4315‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
499 8 PIPING 3963‐FAHN‐4299‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4299‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
500 8 PIPING 3963‐FAHN‐4302‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4302‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
501 8 PIPING 3963‐FAHN‐4303‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4303‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
502 8 PIPING 3963‐FAHN‐4299‐3‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4299‐3''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
503 8 PIPING 3963‐FAHN‐4314‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4314‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
504 8 PIPING 3963‐FAHN‐4300‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4300‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
505 8 PIPING 3963‐FAHN‐4301‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4301‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
506 8 PIPING 3963‐FAHN‐4340‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4340‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
507 8 PIPING 3963‐FAHN‐4339‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4339‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
508 8 PIPING 3963‐FAHN‐4338‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4338‐3''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
509 8 PIPING 3963‐FAHN‐4335‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4335‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
510 8 PIPING 3963‐FAHN‐4337‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4337‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
511 8 PIPING 3963‐FAHN‐4336‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4336‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
512 8 PIPING 3963‐FAHN‐4303‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:12‐4303‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
513 8 PIPING 3963‐FAHN‐4301‐4‐OC OT PIPING ISOMETRICS ‐ LINE NO.:12‐4301‐4''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
514 8 PIPING 3963‐FAHN‐4302‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:12‐4302‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
515 8 PIPING 3963‐FAHN‐4301‐4‐WD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4301‐4"‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
516 8 PIPING 3963‐FAHN‐4300‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4300‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
517 8 PIPING 3963‐FAHN‐4333‐8‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4333‐8''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
518 8 PIPING 3963‐FAHN‐4334‐4‐GV OT PIPING ISOMETRICS ‐ LINE NO.:12‐4334‐4''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
519 8 PIPING 3963‐FAHN‐4321‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4321‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
520 8 PIPING 3963‐FAHN‐4332‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4332‐8"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 27‐Feb‐18 1‐Mar‐18 1‐Mar‐18 1‐Mar‐18 1‐Mar‐18 22‐Jul‐19 18‐Jan‐18 27‐Feb‐18 1‐Mar‐18 1‐Mar‐18 1‐Mar‐18 1‐Mar‐18 95% 95% 0% 0.019% 0.019%
521 8 PIPING 3963‐FAHN‐4317‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4317‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
522 8 PIPING 3963‐FAHN‐4318‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4318‐8''‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
523 8 PIPING 3963‐FAHN‐4320‐2‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4320‐2"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
524 8 PIPING 3963‐FAHN‐4319‐3‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4319‐3"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
525 8 PIPING 3963‐FAHN‐4316‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:12‐4316‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
526 8 PIPING 3963‐FAHN‐4310‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4310‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
527 8 PIPING 3963‐FAHN‐4313‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4313‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
528 8 PIPING 3963‐FAHN‐4307‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4307‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
529 8 PIPING 3963‐FAHN‐4306‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4306‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
530 8 PIPING 3963‐FAHN‐4308‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4308‐2"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 18‐Jan‐18 6‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.019% 0.019%
531 8 PIPING 3963‐FAHN‐4311‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4311‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
532 8 PIPING 3963‐FAHN‐4312‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4312‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
533 8 PIPING 3963‐FAHN‐4315‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4315‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
534 8 PIPING 3963‐FAHN‐4309‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4309‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
535 8 PIPING 3963‐FAHN‐4304‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4304‐1"‐OD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
536 8 PIPING 3963‐FAHN‐4305‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:12‐4305‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 18‐Jan‐18 4‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.019% 0.019%
537 8 PIPING 3963‐FAHN‐4343‐2‐AI OT PIPING ISOMETRICS ‐ LINE NO.:12‐4343‐2"‐AI‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.019% 0.019%
538 8 PIPING 3963‐FAHN‐4304‐4‐WF OT PIPING ISOMETRICS ‐ LINE NO.:12‐4304‐4"‐WF‐L5‐150‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
539 8 PIPING 3963‐FAHN‐4306‐2‐WF OT PIPING ISOMETRICS ‐ LINE NO.:12‐4305‐2"‐WF‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
540 8 PIPING 3963‐FAHS‐6006‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:13‐6006‐6"‐OC‐CS1‐900‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
541 8 PIPING 3963‐FAHS‐6001‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:13‐6001‐6''‐OC‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
542 8 PIPING 3963‐FAHS‐6002‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:13‐6002‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
543 8 PIPING 3963‐FAHS‐6278‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6278‐8''‐GP‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 22‐Jul‐19 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 95% 95% 0% 0.019% 0.019%
544 8 PIPING 3963‐FAHS‐6228‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6228‐6''‐WD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 22‐Jul‐19 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 95% 95% 0% 0.019% 0.019%
545 8 PIPING 3963‐FAHS‐6005‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6005‐2''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
546 8 PIPING 3963‐FAHS‐6004‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6004‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
547 8 PIPING 3963‐FAHS‐6006‐3‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6006‐3''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
548 8 PIPING 3963‐FAHS‐6001‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6001‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
549 8 PIPING 3963‐FAHS‐6002‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6002‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
550 8 PIPING 3963‐FAHS‐6003‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6003‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
551 8 PIPING 3963‐FAHS‐6295‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6295‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
552 8 PIPING 3963‐FAHS‐6299‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6299‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
553 8 PIPING 3963‐FAHS‐6297‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6297‐3''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
554 8 PIPING 3963‐FAHS‐6300‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6300‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
555 8 PIPING 3963‐FAHS‐6298‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6298‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
556 8 PIPING 3963‐FAHS‐6296‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6296‐10''‐GV‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
557 8 PIPING 3963‐FAHS‐6004‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:13‐6004‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
558 8 PIPING 3963‐FAHS‐6005‐4‐OC OT PIPING ISOMETRICS ‐ LINE NO.:13‐6005‐4''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
559 8 PIPING 3963‐FAHS‐6017‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:13‐6017‐6''‐OC‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
560 8 PIPING 3963‐FAHS‐6230‐4‐WD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6230‐4"‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
561 8 PIPING 3963‐FAHS‐6229‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6229‐6''‐WD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
562 8 PIPING 3963‐FAHS‐6302‐8‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6302‐8''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
563 8 PIPING 3963‐FAHS‐6303‐4‐GV OT PIPING ISOMETRICS ‐ LINE NO.:13‐6303‐4''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 22‐Jul‐19 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 95% 95% 0% 0.019% 0.019%
564 8 PIPING 3963‐FAHS‐6284‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6284‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
565 8 PIPING 3963‐FAHS‐6301‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6301‐8"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 8‐Apr‐18 8‐Apr‐18 8‐Apr‐18 8‐Apr‐18 8‐Apr‐18 22‐Jul‐19 18‐Jan‐18 8‐Apr‐18 8‐Apr‐18 8‐Apr‐18 8‐Apr‐18 8‐Apr‐18 95% 95% 0% 0.019% 0.019%
566 8 PIPING 3963‐FAHS‐6279‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6279‐8''‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 22‐Jul‐19 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 95% 95% 0% 0.019% 0.019%
567 8 PIPING 3963‐FAHS‐6283‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6283‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
568 8 PIPING 3963‐FAHS‐6281‐2‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6281‐2"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
569 8 PIPING 3963‐FAHS‐6280‐3‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6280‐3"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 22‐Jul‐19 18‐Jan‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 14‐Feb‐18 95% 95% 0% 0.019% 0.019%
570 8 PIPING 3963‐FAHS‐6282‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:13‐6282‐6"‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
571 8 PIPING 3963‐FAHS‐6012‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6012‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
572 8 PIPING 3963‐FAHS‐6285‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6285‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
573 8 PIPING 3963‐FAHS‐6010‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6010‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
574 8 PIPING 3963‐FAHS‐6009‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6009‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
575 8 PIPING 3963‐FAHS‐6015‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6015‐2"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
576 8 PIPING 3963‐FAHS‐6016‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6016‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
577 8 PIPING 3963‐FAHS‐6011‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6011‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
578 8 PIPING 3963‐FAHS‐6014‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6014‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
579 8 PIPING 3963‐FAHS‐6013‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6013‐1"‐OD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
580 8 PIPING 3963‐FAHS‐6007‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6007‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
581 8 PIPING 3963‐FAHS‐6008‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:13‐6008‐1"‐OD‐CS1‐150‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 18‐Jan‐18 13‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.019% 0.019%
582 8 PIPING 3963‐FAHS‐6306‐2‐AI OT PIPING ISOMETRICS ‐ LINE NO.:13‐6306‐2"‐AI‐ 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 15‐Mar‐18 15‐Mar‐18 15‐Mar‐18 15‐Mar‐18 15‐Mar‐18 22‐Jul‐19 18‐Jan‐18 15‐Mar‐18 15‐Mar‐18 15‐Mar‐18 15‐Mar‐18 15‐Mar‐18 95% 95% 0% 0.019% 0.019%
583 8 PIPING 3963‐FAHS‐6233‐4‐WF OT PIPING ISOMETRICS ‐ LINE NO.:13‐6233‐4"‐WF‐L5‐150‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
584 8 PIPING 3963‐FAHS‐6235‐2‐WF OT PIPING ISOMETRICS ‐ LINE NO.:13‐6235‐2"‐WF‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
585 8 PIPING 3963‐KAHM‐1345‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:24‐1345‐6"‐OC‐CS1‐900‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
586 8 PIPING 3963‐KAHM‐1346‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:24‐1346‐6''‐OC‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.019% 0.019%
587 8 PIPING 3963‐KAHM‐1348‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:24‐1348‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.019% 0.019%
588 8 PIPING 3963‐KAHM‐8601‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8601‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
589 8 PIPING 3963‐KAHM‐8098‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8098‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.019% 0.019%
590 8 PIPING 3963‐KAHM‐8083‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8083‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
591 8 PIPING 3963‐KAHM‐8081‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8081‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
592 8 PIPING 3963‐KAHM‐8084‐3‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8084‐3''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
593 8 PIPING 3963‐KAHM‐8080‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8080‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
594 8 PIPING 3963‐KAHM‐8082‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8082‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
595 8 PIPING 3963‐KAHM‐8621‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8621‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
596 8 PIPING 3963‐KAHM‐8620‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8620‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
597 8 PIPING 3963‐KAHM‐8622‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8622‐3''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
598 8 PIPING 3963‐KAHM‐8623‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8623‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
599 8 PIPING 3963‐KAHM‐8624‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8624‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
600 8 PIPING 3963‐KAHM‐8625‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8625‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
601 8 PIPING 3963‐KAHM‐1349‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:24‐1349‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
602 8 PIPING 3963‐KAHM‐1350‐4‐OC OT PIPING ISOMETRICS ‐ LINE NO.:24‐1350‐4''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
603 8 PIPING 3963‐KAHM‐1351‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:24‐1351‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
604 8 PIPING 3963‐KAHM‐8100‐4‐WD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8100‐4"‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.019% 0.019%
605 8 PIPING 3963‐KAHM‐8099‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8099‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 18‐Jan‐18 23‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.019% 0.019%
606 8 PIPING 3963‐KAHM‐8626‐8‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8626‐8''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
607 8 PIPING 3963‐KAHM‐8627‐4‐GV OT PIPING ISOMETRICS ‐ LINE NO.:24‐8627‐4''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
608 8 PIPING 3963‐KAHM‐8605‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8605‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
609 8 PIPING 3963‐KAHM‐8604‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8604‐8"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
610 8 PIPING 3963‐KAHM‐8602‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8602‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
611 8 PIPING 3963‐KAHM‐8603‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8603‐8''‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
612 8 PIPING 3963‐KAHM‐8608‐2‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8608‐2"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
613 8 PIPING 3963‐KAHM‐8607‐3‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8607‐3"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
614 8 PIPING 3963‐KAHM‐8606‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:24‐8606‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 18‐Jan‐18 20‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.019% 0.019%
615 8 PIPING 3963‐KAHM‐8091‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8091‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
616 8 PIPING 3963‐KAHM‐8093‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8093‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
617 8 PIPING 3963‐KAHM‐8092‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8092‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
618 8 PIPING 3963‐KAHM‐8090‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8090‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
619 8 PIPING 3963‐KAHM‐8089‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8089‐2"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%

Page 5 of 13
Page 76 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
620 8 PIPING 3963‐KAHM‐8088‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8088‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
621 8 PIPING 3963‐KAHM‐8094‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8094‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
622 8 PIPING 3963‐KAHM‐8096‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8096‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
623 8 PIPING 3963‐KAHM‐8087‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8087‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
624 8 PIPING 3963‐KAHM‐8085‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8085‐1"‐OD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
625 8 PIPING 3963‐KAHM‐8086‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8086‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
626 8 PIPING 3963‐KAHM‐8095‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:24‐8095‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
627 8 PIPING 3963‐KAHM‐8629‐2‐AI OT PIPING ISOMETRICS ‐ LINE NO.:24‐8629‐2"‐AI‐CS1‐150‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
628 8 PIPING 3963‐KAHM‐8176‐4‐WF OT PIPING ISOMETRICS ‐ LINE NO.:24‐8176‐4"‐WF‐L5‐150‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
629 8 PIPING 3963‐KAHM‐8178‐2‐WF OT PIPING ISOMETRICS ‐ LINE NO.:24‐8178‐2"‐WF‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
630 8 PIPING 3963‐KAHN‐0170‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:22‐170‐6"‐OC‐CS1‐900‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
631 8 PIPING 3963‐KAHN‐0162‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:22‐162‐6''‐OC‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
632 8 PIPING 3963‐KAHN‐0163‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:22‐163‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
633 8 PIPING 3963‐KAHN‐7615‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7615‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
634 8 PIPING 3963‐KAHN‐0360‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:22‐360‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
635 8 PIPING 3963‐KAHN‐0185‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐185‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
636 8 PIPING 3963‐KAHN‐0186‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐186‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
637 8 PIPING 3963‐KAHN‐0179‐3‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐179‐3''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
638 8 PIPING 3963‐KAHN‐0182‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐182‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
639 8 PIPING 3963‐KAHN‐0183‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐183‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
640 8 PIPING 3963‐KAHN‐0184‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐184‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
641 8 PIPING 3963‐KAHN‐0172‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐172‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
642 8 PIPING 3963‐KAHN‐0175‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐175‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
643 8 PIPING 3963‐KAHN‐0173‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐173‐3''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
644 8 PIPING 3963‐KAHN‐0176‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐176‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
645 8 PIPING 3963‐KAHN‐0174‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐174‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
646 8 PIPING 3963‐KAHN‐0177‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐177‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
647 8 PIPING 3963‐KAHN‐0164‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:22‐164‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
648 8 PIPING 3963‐KAHN‐0165‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:22‐165‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
649 8 PIPING 3963‐KAHN‐0168‐4‐OC OT PIPING ISOMETRICS ‐ LINE NO.:22‐168‐4''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
650 8 PIPING 3963‐KAHN‐0167‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:22‐167‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
651 8 PIPING 3963‐KAHN‐0361‐4‐WD OT PIPING ISOMETRICS ‐ LINE NO.:22‐361‐4"‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
652 8 PIPING 3963‐KAHN‐0363‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:22‐363‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
653 8 PIPING 3963‐KAHN‐0364‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:22‐364‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
654 8 PIPING 3963‐KAHN‐0179‐8‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐179‐8''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
655 8 PIPING 3963‐KAHN‐0178‐4‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐178‐4''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
656 8 PIPING 3963‐KAHN‐7621‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7621‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
657 8 PIPING 3963‐KAHN‐7622‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7622‐8"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
658 8 PIPING 3963‐KAHN‐7917‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7917‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
659 8 PIPING 3963‐KAHN‐7619‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7619‐8''‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
660 8 PIPING 3963‐KAHN‐7616‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7616‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
661 8 PIPING 3963‐KAHN‐0180‐2‐GV OT PIPING ISOMETRICS ‐ LINE NO.:22‐180‐2"‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
662 8 PIPING 3963‐KAHN‐7618‐3‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7618‐3"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
663 8 PIPING 3963‐KAHN‐7620‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:22‐7620‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 18‐Jan‐18 21‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.019% 0.019%
664 8 PIPING 3963‐KAHN‐0362‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐362‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
665 8 PIPING 3963‐KAHN‐0180‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐180‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
666 8 PIPING 3963‐KAHN‐0177‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐177‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
667 8 PIPING 3963‐KAHN‐0175‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐175‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
668 8 PIPING 3963‐KAHN‐0187‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐187‐2"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
669 8 PIPING 3963‐KAHN‐0169‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐169‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
670 8 PIPING 3963‐KAHN‐0178‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐178‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
671 8 PIPING 3963‐KAHN‐0188‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐188‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
672 8 PIPING 3963‐KAHN‐0176‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐176‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
673 8 PIPING 3963‐KAHN‐0174‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐174‐1"‐OD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
674 8 PIPING 3963‐KAHN‐0173‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐173‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
675 8 PIPING 3963‐KAHN‐0181‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:22‐181‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 18‐Jan‐18 22‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.019% 0.019%
676 8 PIPING 3963‐KAHN‐0484‐2‐AI OT PIPING ISOMETRICS ‐ LINE NO.:22‐484‐2"‐AI‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.019% 0.019%
677 8 PIPING 3963‐KAHN‐5001‐4‐WF OT PIPING ISOMETRICS ‐ LINE NO.:22‐5001‐4"‐WF‐L5‐150‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
678 8 PIPING 3963‐KAHN‐5003‐2‐WF OT PIPING ISOMETRICS ‐ LINE NO.:22‐5003‐2"‐WF‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
679 8 PIPING 3963‐KAHS‐0106‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:23‐106‐6"‐OC‐CS1‐900‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
680 8 PIPING 3963‐KAHS‐0101‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:23‐101‐6''‐OC‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
681 8 PIPING 3963‐KAHS‐0102‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:23‐102‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
682 8 PIPING 3963‐KAHS‐9775‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:23‐9775‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
683 8 PIPING 3963‐KAHS‐9776‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9776‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 3‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 18‐Jan‐18 3‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.019% 0.019%
684 8 PIPING 3963‐KAHS‐9888‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9888‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
685 8 PIPING 3963‐KAHS‐9889‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9889‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
686 8 PIPING 3963‐KAHS‐9884‐3‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9884‐3''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
687 8 PIPING 3963‐KAHS‐9885‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9885‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
688 8 PIPING 3963‐KAHS‐9886‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9886‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
689 8 PIPING 3963‐KAHS‐9887‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9887‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 95% 95% 0% 0.019% 0.019%
690 8 PIPING 3963‐KAHS‐9886‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:23‐9886‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 27‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 22‐Jul‐19 18‐Jan‐18 27‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 95% 95% 0% 0.019% 0.019%
691 8 PIPING 3963‐KAHS‐9889‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:23‐9889‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
692 8 PIPING 3963‐KAHS‐9887‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:23‐9887‐3''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
693 8 PIPING 3963‐KAHS‐9890‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:23‐9890‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
694 8 PIPING 3963‐KAHS‐9888‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:23‐9888‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
695 8 PIPING 3963‐KAHS‐9885‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:23‐9885‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
696 8 PIPING 3963‐KAHS‐0104‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:23‐104‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
697 8 PIPING 3963‐KAHS‐0103‐4‐OC OT PIPING ISOMETRICS ‐ LINE NO.:23‐103‐4''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
698 8 PIPING 3963‐KAHS‐0105‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:23‐105‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
699 8 PIPING 3963‐KAHS‐9777‐4‐WD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9777‐4"‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 3‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 18‐Jan‐18 3‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.019% 0.019%
700 8 PIPING 3963‐KAHS‐9778‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9778‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 3‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 18‐Jan‐18 3‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.019% 0.019%
701 8 PIPING 3963‐KAHS‐9884‐8‐GV OT PIPING ISOMETRICS ‐ LINE NO.:23‐9884‐8''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
702 8 PIPING 3963‐KAHS‐9777‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:23‐9777‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
703 8 PIPING 3963‐KAHS‐9776‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:23‐9776‐8"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
704 8 PIPING 3963‐KAHS‐9778‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:23‐9778‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
705 8 PIPING 3963‐KAHS‐9779‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:23‐9779‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
706 8 PIPING 3963‐KAHS‐9893‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9893‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
707 8 PIPING 3963‐KAHS‐9895‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9895‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
708 8 PIPING 3963‐KAHS‐9896‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9896‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
709 8 PIPING 3963‐KAHS‐9892‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9892‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
710 8 PIPING 3963‐KAHS‐9899‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9899‐2"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 95% 95% 0% 0.019% 0.019%
711 8 PIPING 3963‐KAHS‐9898‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9898‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
712 8 PIPING 3963‐KAHS‐9897‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9897‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
713 8 PIPING 3963‐KAHS‐9900‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9900‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 27‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 22‐Jul‐19 18‐Jan‐18 27‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 28‐Jan‐18 95% 95% 0% 0.019% 0.019%
714 8 PIPING 3963‐KAHS‐9894‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9894‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 95% 95% 0% 0.019% 0.019%
715 8 PIPING 3963‐KAHS‐9890‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9890‐1"‐OD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
716 8 PIPING 3963‐KAHS‐9891‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9891‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 30‐Jan‐18 95% 95% 0% 0.019% 0.019%
717 8 PIPING 3963‐KAHS‐9899‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:23‐9899‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 18‐Jan‐18 28‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.019% 0.019%
718 8 PIPING 3963‐KAHS‐9871‐2‐AI OT PIPING ISOMETRICS ‐ LINE NO.:23‐9871‐2"‐AI‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.019% 0.019%
719 8 PIPING 3963‐KAHS‐3083‐4‐WF OT PIPING ISOMETRICS ‐ LINE NO.:23‐3083‐4"‐WF‐L5‐150‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
720 8 PIPING 3963‐KAHS‐3087‐2‐WF OT PIPING ISOMETRICS ‐ LINE NO.:23‐3087‐2"‐WF‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
721 8 PIPING 3963‐JALM‐2090‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:31‐2090‐6"‐OC‐CS1‐900‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 20‐Feb‐18 20‐Feb‐18 20‐Feb‐18 20‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 20‐Feb‐18 20‐Feb‐18 20‐Feb‐18 20‐Feb‐18 95% 95% 0% 0.019% 0.019%
722 8 PIPING 3963‐JALM‐2037‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:31‐2037‐6''‐OC‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
723 8 PIPING 3963‐JALM‐2035‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:31‐2035‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
724 8 PIPING 3963‐JALM‐5201‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5201‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
725 8 PIPING 3963‐JALM‐2032‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2032‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
726 8 PIPING 3963‐JALM‐2083‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2083‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
727 8 PIPING 3963‐JALM‐2084‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2084‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
728 8 PIPING 3963‐JALM‐2079‐3‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2079‐3''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
729 8 PIPING 3963‐JALM‐2080‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2080‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
730 8 PIPING 3963‐JALM‐2081‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2081‐1"‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
731 8 PIPING 3963‐JALM‐2082‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2082‐2''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
732 8 PIPING 3963‐JALM‐5210‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5210‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
733 8 PIPING 3963‐JALM‐5213‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5213‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
734 8 PIPING 3963‐JALM‐5211‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5211‐3''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
735 8 PIPING 3963‐JALM‐5214‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5214‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
736 8 PIPING 3963‐JALM‐5212‐6‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5212‐6''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
737 8 PIPING 3963‐JALM‐5215‐10‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5215‐10''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
738 8 PIPING 3963‐JALM‐2086‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:31‐2086‐6"‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
739 8 PIPING 3963‐JALM‐2033‐4‐OC OT PIPING ISOMETRICS ‐ LINE NO.:31‐2033‐4''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
740 8 PIPING 3963‐JALM‐2089‐6‐OC OT PIPING ISOMETRICS ‐ LINE NO.:31‐2089‐6''‐OC‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
741 8 PIPING 3963‐JALM‐2088‐4‐WD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2088‐4"‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
742 8 PIPING 3963‐JALM‐2034‐6‐WD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2034‐6''‐WD‐L5‐300‐1X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
743 8 PIPING 3963‐JALM‐5217‐8‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5217‐8''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%

Page 6 of 13
Page 77 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
744 8 PIPING 3963‐JALM‐5216‐4‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5216‐4''‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
745 8 PIPING 3963‐JALM‐5204‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5204‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
746 8 PIPING 3963‐JALM‐5203‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5203‐8"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
747 8 PIPING 3963‐JALM‐5205‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5205‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
748 8 PIPING 3963‐JALM‐5202‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5202‐8''‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
749 8 PIPING 3963‐JALM‐5207‐8‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5207‐8''‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
750 8 PIPING 3963‐JALM‐5208‐2‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5208‐2"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
751 8 PIPING 3963‐JALM‐5206‐2‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5206‐2"‐GP‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
752 8 PIPING 3963‐JALM‐5218‐3‐GV OT PIPING ISOMETRICS ‐ LINE NO.:31‐5218‐3"‐GV‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
753 8 PIPING 3963‐JALM‐5209‐6‐GP OT PIPING ISOMETRICS ‐ LINE NO.:31‐5209‐6"‐GP‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
754 8 PIPING 3963‐JALM‐2089‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2089‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
755 8 PIPING 3963‐JALM‐2092‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2092‐1''‐OD‐CS1‐150‐8X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
756 8 PIPING 3963‐JALM‐2087‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2087‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
757 8 PIPING 3963‐JALM‐2086‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2086‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
758 8 PIPING 3963‐JALM‐2093‐2‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2093‐2"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
759 8 PIPING 3963‐JALM‐2094‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2094‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
760 8 PIPING 3963‐JALM‐2088‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2088‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
761 8 PIPING 3963‐JALM‐2091‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2091‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
762 8 PIPING 3963‐JALM‐2090‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2090‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 19‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 18‐Jan‐18 19‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.019% 0.019%
763 8 PIPING 3963‐JALM‐2084‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2084‐1''‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
764 8 PIPING 3963‐JALM‐2085‐1‐OD OT PIPING ISOMETRICS ‐ LINE NO.:31‐2085‐1"‐OD‐CS1‐300‐4X 3 0 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 18‐Jan‐18 20‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.019% 0.019%
765 8 PIPING 3963‐JALM‐5212‐2‐AI OT PIPING ISOMETRICS ‐ LINE NO.:31‐5212‐2"‐AI‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 18‐Jan‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.019% 0.019%
766 8 PIPING 3963‐JALM‐2086‐4‐WF OT PIPING ISOMETRICS ‐ LINE NO.:31‐2086‐4"‐WF‐L5‐150‐1X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
767 8 PIPING 3963‐JALM‐2087‐2‐WF OT PIPING ISOMETRICS ‐ LINE NO.:31‐2087‐2"‐WF‐CS1‐150‐4X 3 A 0.020% 21‐Aug‐17 31‐Aug‐17 5‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 22‐Jul‐19 18‐Jan‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 1‐Apr‐18 95% 95% 0% 0.019% 0.019%
768 8 PIPING 3963‐KAHN‐5‐52‐0013 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING G.A. AREA 151 SH13 EL.103.590 & ABOVE 1 A 0.028% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 2‐Jan‐18 1‐Jan‐18 2‐Jan‐18 22‐Jan‐18 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 2‐Jan‐18 1‐Jan‐18 2‐Jan‐18 22‐Jan‐18 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.026% 0.026%
769 8 PIPING 3963‐KAHN‐5‐52‐0014 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING G.A. AREA 151 SH14 EL.103.590 & ABOVE 1 A 0.028% 24‐Jul‐17 26‐Jul‐17 28‐Jul‐17 9‐Aug‐17 21‐Aug‐17 2‐Sep‐17 31‐Oct‐18 29‐Dec‐17 1‐Jan‐18 2‐Jan‐18 22‐Jan‐18 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 29‐Dec‐17 1‐Jan‐18 2‐Jan‐18 22‐Jan‐18 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.026% 0.026%
770 8 PIPING 3963‐KAHN‐5‐52‐0015 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING G.A AREA 151 SH14 MANIFOLD SHUTDOW 1 A 0.028% 24‐Jul‐17 26‐Jul‐17 28‐Jul‐17 9‐Aug‐17 21‐Aug‐17 2‐Sep‐17 31‐Oct‐18 30‐Dec‐17 31‐Dec‐17 2‐Jan‐18 23‐Jan‐18 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 30‐Dec‐17 31‐Dec‐17 2‐Jan‐18 23‐Jan‐18 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.026% 0.026%
771 8 PIPING 3963‐KAHS‐5‐52‐0013 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A MANIFOLD SHUTDOWN VALVES (23‐S 1 A 0.028% 1‐Aug‐17 6‐Aug‐17 11‐Aug‐17 21‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 2‐Jan‐18 2‐Jan‐18 2‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 2‐Jan‐18 2‐Jan‐18 2‐Jan‐18 29‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.026% 0.026%
772 8 PIPING DEM‐3963‐KAHN‐5‐52‐0007 DEM DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING G.A MANIFOLD SHUTDOWN VALVES (22‐S 1 A 0.014% 1‐Aug‐17 6‐Aug‐17 11‐Aug‐17 21‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 7‐Jan‐18 8‐Jan‐18 9‐Jan‐18 25‐Jan‐18 12‐Feb‐18 12‐Feb‐18 22‐Jul‐19 7‐Jan‐18 8‐Jan‐18 9‐Jan‐18 25‐Jan‐18 12‐Feb‐18 12‐Feb‐18 95% 95% 0% 0.013% 0.013%
773 8 PIPING DEM‐3963‐KAHM‐5‐52‐0010 DEM DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A MANIFOLD SHUTDOWN VALVES (24‐SD 1 A 0.014% 1‐Aug‐17 6‐Aug‐17 11‐Aug‐17 21‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 31‐Dec‐17 7‐Jan‐18 9‐Jan‐18 25‐Jan‐18 12‐Feb‐18 12‐Feb‐18 22‐Jul‐19 31‐Dec‐17 7‐Jan‐18 9‐Jan‐18 25‐Jan‐18 12‐Feb‐18 12‐Feb‐18 95% 95% 0% 0.013% 0.013%
774 8 PIPING 3963‐FAHN‐5‐36‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPING TIE‐IN SCHEDULE 1 A 0.056% 23‐Jul‐17 2‐Aug‐17 7‐Aug‐17 25‐Aug‐17 4‐Sep‐17 14‐Sep‐17 31‐Oct‐18 27‐Jul‐17 2‐Aug‐17 3‐Aug‐17 29‐Oct‐17 29‐Oct‐17 11‐Jan‐18 22‐Jul‐19 27‐Jul‐17 2‐Aug‐17 3‐Aug‐17 29‐Oct‐17 29‐Oct‐17 11‐Jan‐18 95% 95% 0% 0.053% 0.053%
775 8 PIPING 3963‐FAHN‐5‐57‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PIPE SUPPORT LIST 1 A 0.056% 18‐Jul‐17 28‐Jul‐17 2‐Aug‐17 20‐Aug‐17 30‐Aug‐17 9‐Sep‐17 31‐Oct‐18 15‐Jul‐17 15‐Oct‐17 16‐Oct‐17 4‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 15‐Jul‐17 15‐Oct‐17 16‐Oct‐17 4‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
776 8 PIPING 3963‐FAHN‐5‐50‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; PLOT PLAN 1 C 0.112% 26‐Mar‐17 5‐Apr‐17 10‐Apr‐17 11‐May‐17 1‐Jun‐17 11‐Jun‐17 31‐Oct‐18 29‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 3‐Sep‐18 22‐Jul‐19 29‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 3‐Sep‐18 95% 95% 0% 0.106% 0.106%
777 8 PIPING 3963‐FAHN‐5‐50‐0002 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; KEY PLAN 1 A 0.042% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 21‐Jan‐18 22‐Jul‐19 27‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Oct‐17 26‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.040% 0.040%
778 8 PIPING 3963‐FAHS‐5‐57‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PIPE SUPPORT LIST  1 A 0.056% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 8‐Oct‐17 10‐Oct‐17 3‐Jan‐18 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 27‐Jul‐17 8‐Oct‐17 10‐Oct‐17 3‐Jan‐18 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.053% 0.053%
779 8 PIPING 3963‐FAHS‐5‐50‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; PLOT PLAN 1 C 0.112% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 29‐Mar‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 3‐Sep‐18 22‐Jul‐19 29‐Mar‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 3‐Sep‐18 95% 95% 0% 0.106% 0.106%
780 8 PIPING 3963‐JALM‐5‐57‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPE SUPPORT LIST 1 A 0.056% 24‐Jul‐17 3‐Aug‐17 8‐Aug‐17 26‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 27‐Jul‐17 15‐Oct‐17 16‐Oct‐17 10‐Jan‐18 22‐Jan‐18 22‐Jan‐18 22‐Jul‐19 27‐Jul‐17 15‐Oct‐17 16‐Oct‐17 10‐Jan‐18 22‐Jan‐18 22‐Jan‐18 95% 95% 0% 0.053% 0.053%
781 8 PIPING 3963‐JALM‐5‐50‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PLOT PLAN 1 C 0.112% 1‐Apr‐17 11‐Apr‐17 16‐Apr‐17 17‐May‐17 7‐Jun‐17 17‐Jun‐17 31‐Oct‐18 5‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 3‐Sep‐18 22‐Jul‐19 5‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 3‐Sep‐18 95% 95% 0% 0.106% 0.106%
782 8 PIPING 3963‐KAHM‐5‐36‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING TIE‐IN SCHEDULE 1 A 0.056% 18‐Jul‐17 28‐Jul‐17 2‐Aug‐17 20‐Aug‐17 30‐Aug‐17 9‐Sep‐17 31‐Oct‐18 20‐Jul‐17 17‐Sep‐17 18‐Sep‐17 10‐Dec‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 20‐Jul‐17 17‐Sep‐17 18‐Sep‐17 10‐Dec‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.053% 0.053%
783 8 PIPING 3963‐KAHM‐5‐57‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPE SUPPORT LIST 1 A 0.112% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 2‐Oct‐17 3‐Oct‐17 5‐Oct‐17 10‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 2‐Oct‐17 3‐Oct‐17 5‐Oct‐17 10‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.106% 0.106%
784 8 PIPING 3963‐KAHM‐5‐17‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING STRESS ANALYSIS REPORT 3 A 0.336% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 25‐Sep‐17 27‐Sep‐17 16‐Oct‐17 29‐Oct‐17 21‐Jan‐18 22‐Jul‐19 1‐Jun‐17 25‐Sep‐17 27‐Sep‐17 16‐Oct‐17 29‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.319% 0.319%
785 8 PIPING 3963‐KAHM‐5‐50‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PLOT PLAN 1 A 0.112% 30‐Mar‐17 9‐Apr‐17 14‐Apr‐17 15‐May‐17 5‐Jun‐17 15‐Jun‐17 31‐Oct‐18 15‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 2‐Nov‐17 3‐Sep‐18 22‐Jul‐19 15‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 2‐Nov‐17 3‐Sep‐18 95% 95% 0% 0.106% 0.106%
786 8 PIPING 3963‐KAHN‐5‐36‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING TIE‐IN SCHEDULE 1 A 0.056% 19‐Jul‐17 29‐Jul‐17 3‐Aug‐17 21‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 15‐Jul‐17 22‐Sep‐17 24‐Sep‐17 7‐Dec‐17 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 15‐Jul‐17 22‐Sep‐17 24‐Sep‐17 7‐Dec‐17 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 0.053% 0.053%
787 8 PIPING 3963‐KAHN‐5‐57‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPE SUPPORT LIST 1 A 0.056% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 14‐Oct‐17 15‐Oct‐17 16‐Oct‐17 8‐Jan‐18 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 14‐Oct‐17 15‐Oct‐17 16‐Oct‐17 8‐Jan‐18 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
788 8 PIPING 3963‐KAHN‐5‐17‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING STRESS ANALYSIS REPORT 3 A 0.420% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 7‐Jun‐17 19‐Sep‐17 20‐Sep‐17 9‐Oct‐17 9‐Oct‐17 21‐Jan‐18 22‐Jul‐19 7‐Jun‐17 19‐Sep‐17 20‐Sep‐17 9‐Oct‐17 9‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.399% 0.399%
789 8 PIPING 3963‐KAHN‐5‐50‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PLOT PLAN 1 A 0.112% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 12‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 2‐Nov‐17 21‐Jan‐18 22‐Jul‐19 12‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 2‐Nov‐17 21‐Jan‐18 95% 95% 0% 0.106% 0.106%
790 8 PIPING 3963‐KAHN‐5‐52‐0005 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.5 EL.103.590 & ABOVE 1 A 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.067% 0.067%
791 8 PIPING 3963‐KAHN‐5‐52‐0007 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.7 EL.103.590 & ABOVE 1 A 0.084% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 15‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.080% 0.080%
792 8 PIPING 3963‐KAHN‐5‐52‐0010 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 151 SHT.10 EL.103.590 & ABOV 1 A 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 19‐Jul‐17 9‐Oct‐17 11‐Oct‐17 19‐Nov‐17 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.067% 0.067%
793 8 PIPING 3963‐KAHS‐5‐36‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING TIE‐IN SCHEDULE 1 A 0.056% 22‐Jul‐17 1‐Aug‐17 6‐Aug‐17 24‐Aug‐17 3‐Sep‐17 13‐Sep‐17 31‐Oct‐18 27‐Jul‐17 17‐Sep‐17 18‐Sep‐17 11‐Dec‐17 17‐Jan‐18 17‐Jan‐18 22‐Jul‐19 27‐Jul‐17 17‐Sep‐17 18‐Sep‐17 11‐Dec‐17 17‐Jan‐18 17‐Jan‐18 95% 95% 0% 0.053% 0.053%
794 8 PIPING 3963‐KAHS‐5‐57‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPE SUPPORT LIST 1 A 0.056% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 14‐Oct‐17 15‐Oct‐17 16‐Oct‐17 3‐Jan‐18 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 14‐Oct‐17 15‐Oct‐17 16‐Oct‐17 3‐Jan‐18 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.053% 0.053%
795 8 PIPING 3963‐KAHS‐5‐17‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING STRESS ANALYSIS REPORT 3 A 0.420% 10‐Jun‐17 20‐Jun‐17 25‐Jun‐17 26‐Jul‐17 16‐Aug‐17 26‐Aug‐17 31‐Oct‐18 8‐Jul‐17 3‐Oct‐17 5‐Oct‐17 23‐Oct‐17 23‐Oct‐17 31‐Jan‐18 22‐Jul‐19 8‐Jul‐17 3‐Oct‐17 5‐Oct‐17 23‐Oct‐17 23‐Oct‐17 31‐Jan‐18 95% 95% 0% 0.399% 0.399%
796 8 PIPING 3963‐KAHS‐5‐50‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PLOT PLAN 1 A 0.112% 1‐Apr‐17 11‐Apr‐17 16‐Apr‐17 17‐May‐17 7‐Jun‐17 17‐Jun‐17 31‐Oct‐18 14‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 2‐Nov‐17 21‐Jan‐18 22‐Jul‐19 14‐Mar‐17 5‐Apr‐17 13‐Apr‐17 23‐Oct‐17 2‐Nov‐17 21‐Jan‐18 95% 95% 0% 0.106% 0.106%
797 8 PIPING 3963‐FAHM‐5‐36‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING TIE‐IN SCHEDULE 1 A 0.056% 26‐Jul‐17 5‐Aug‐17 10‐Aug‐17 28‐Aug‐17 7‐Sep‐17 17‐Sep‐17 31‐Oct‐18 15‐Jul‐17 16‐Jul‐17 17‐Jul‐17 13‐Nov‐17 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 15‐Jul‐17 16‐Jul‐17 17‐Jul‐17 13‐Nov‐17 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
798 8 PIPING 3963‐FAHM‐5‐57‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPE SUPPORT LIST 1 A 0.084% 28‐Jul‐17 7‐Aug‐17 12‐Aug‐17 30‐Aug‐17 9‐Sep‐17 19‐Sep‐17 31‐Oct‐18 2‐Oct‐17 3‐Oct‐17 5‐Oct‐17 20‐Dec‐17 21‐Jan‐18 21‐Jan‐18 22‐Jul‐19 2‐Oct‐17 3‐Oct‐17 5‐Oct‐17 20‐Dec‐17 21‐Jan‐18 21‐Jan‐18 95% 95% 0% 0.080% 0.080%
799 8 PIPING 3963‐FAHM‐5‐50‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PLOT PLAN 1 A 0.112% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 29‐Mar‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 25‐Jan‐18 22‐Jul‐19 29‐Mar‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 25‐Jan‐18 95% 95% 0% 0.106% 0.106%
800 8 PIPING 3963‐FAHM‐5‐50‐0003 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; KEY PLAN 1 A 0.056% 20‐Jun‐17 30‐Jun‐17 5‐Jul‐17 5‐Aug‐17 26‐Aug‐17 5‐Sep‐17 31‐Oct‐18 15‐Mar‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 21‐Jan‐18 22‐Jul‐19 15‐Mar‐17 15‐Jul‐17 16‐Jul‐17 26‐Oct‐17 26‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
801 8 PIPING 3963‐KAHM‐5‐51‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; EQUIPMENT LOCATION PLAN 1 A 0.056% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 6‐Mar‐18 22‐Jul‐19 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 6‐Mar‐18 95% 95% 0% 0.053% 0.053%
802 8 PIPING 3963‐KAHN‐5‐51‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; EQUIPMENT LOCATION PLAN 1 A 0.056% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 21‐Jan‐18 22‐Jul‐19 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 23‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
803 8 PIPING 3963‐KAHS‐5‐51‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; EQUIPMENT LOCATION PLAN 1 A 0.056% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 1‐Nov‐17 21‐Jan‐18 22‐Jul‐19 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 23‐Oct‐17 1‐Nov‐17 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
804 8 PIPING 3963‐FAHM‐5‐51‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; EQUIPMENT LOCATION PLAN 1 A 0.056% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 25‐Jan‐18 22‐Jul‐19 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 25‐Jan‐18 95% 95% 0% 0.053% 0.053%
805 8 PIPING 3963‐FAHN‐5‐51‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; EQUIPMENT LOCATION PLAN 1 A 0.056% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 21‐Jan‐18 22‐Jul‐19 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
806 8 PIPING 3963‐FAHS‐5‐51‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH DEGASSING STATION; EQUIPMENT LOCATION PLAN 1 A 0.056% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 21‐Jan‐18 22‐Jul‐19 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.053% 0.053%
807 8 PIPING 3963‐JALM‐5‐51‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; EQUIPMENT LOCATION PLAN 1 A 0.056% 31‐Mar‐17 10‐Apr‐17 15‐Apr‐17 16‐May‐17 6‐Jun‐17 16‐Jun‐17 31‐Oct‐18 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 4‐Mar‐18 22‐Jul‐19 9‐Apr‐17 12‐Apr‐17 13‐Apr‐17 24‐Oct‐17 24‐Oct‐17 4‐Mar‐18 95% 95% 0% 0.053% 0.053%
808 8 PIPING 3963‐DGEN‐5‐17‐0002 OT DUKHAN FIELD; TECHNICAL BID EVALUATION FOR PIPING BULK ITEMS 1 A 1.270% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 4‐Dec‐17 6‐Dec‐17 18‐Jan‐18 29‐Jan‐18 29‐Jan‐18 22‐Jul‐19 19‐Oct‐17 4‐Dec‐17 6‐Dec‐17 18‐Jan‐18 29‐Jan‐18 29‐Jan‐18 95% 95% 0% 1.206% 1.206%
809 8 PIPING 3963‐DGEN‐5‐57‐0001 OT DUKHAN FIELD ‐ STANDARD PIPE SUPPORT DETAILS  1 A 0.168% 21‐Jul‐17 31‐Jul‐17 5‐Aug‐17 23‐Aug‐17 2‐Sep‐17 12‐Sep‐17 31‐Oct‐18 27‐Jul‐17 10‐Oct‐17 12‐Oct‐17 21‐Jan‐18 1‐Feb‐18 1‐Feb‐18 22‐Jul‐19 27‐Jul‐17 10‐Oct‐17 12‐Oct‐17 21‐Jan‐18 1‐Feb‐18 1‐Feb‐18 95% 95% 0% 0.160% 0.160%
810 8 PIPING 3963‐FAHN‐5‐52‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.1 PIPING GA EL.21.600 TO 24.050  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 11‐Dec‐17 13‐Dec‐17 7‐Feb‐18 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 19‐Oct‐17 11‐Dec‐17 13‐Dec‐17 7‐Feb‐18 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.093% 0.093%
811 8 PIPING 3963‐FAHN‐5‐52‐0002 OT DUKHAN FIELD ‐ FAHAHIL NORTH DEGASSING STATION; AREA 401, SHT.2 PIPING GA EL.24.050 & ABOVE  1 A 0.098% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 10‐Dec‐17 13‐Dec‐17 12‐Feb‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 19‐Oct‐17 10‐Dec‐17 13‐Dec‐17 12‐Feb‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.093% 0.093%
812 8 PIPING 3963‐JALM‐5‐52‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 803, SHT.1 EL.63.000 TO 67.000  1 1 0.140% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 26‐Dec‐17 28‐Dec‐17 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 8‐Jul‐17 26‐Dec‐17 28‐Dec‐17 4‐Mar‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.133% 0.133%
813 8 PIPING 3963‐JALM‐5‐52‐0002 OT DUKHAN FIELD ‐ JALEHA MAIN DEGASSING STATION; PIPING G.A. AREA 803, SHT.2 EL.67.000 TO OVER  1 1 0.140% 11‐Jul‐17 21‐Jul‐17 26‐Jul‐17 26‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 8‐Jul‐17 30‐Dec‐17 2‐Jan‐18 6‐Mar‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 8‐Jul‐17 30‐Dec‐17 2‐Jan‐18 6‐Mar‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.133% 0.133%
814 8 PIPING 3963‐KAHM‐5‐52‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.1 EL.101.523 & ABOVE  1 1 0.151% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 7‐Dec‐17 9‐Dec‐17 25‐Jan‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 31‐May‐17 7‐Dec‐17 9‐Dec‐17 25‐Jan‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.143% 0.143%
815 8 PIPING 3963‐KAHM‐5‐52‐0003 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.3 EL. 99.143 TO 101.523 1 A 0.151% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 8‐Dec‐17 10‐Dec‐17 21‐Jan‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 31‐May‐17 8‐Dec‐17 10‐Dec‐17 21‐Jan‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.143% 0.143%
816 8 PIPING 3963‐KAHM‐5‐52‐0005 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.5 EL. 99.143 & ABOVE  1 A 0.151% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 7‐Dec‐17 9‐Dec‐17 25‐Jan‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 31‐May‐17 7‐Dec‐17 9‐Dec‐17 25‐Jan‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.143% 0.143%
817 8 PIPING 3963‐KAHM‐5‐52‐0008 OT DUKHAN FIELD ‐ KHATIYAH MAIN DEGASSING STATION; PIPING G.A AREA 255 SHT.8 EL.99.863 & ABOVE  1 A 0.075% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 24‐Oct‐17 26‐Oct‐17 21‐Jan‐18 12‐Feb‐18 12‐Feb‐18 22‐Jul‐19 1‐Jun‐17 24‐Oct‐17 26‐Oct‐17 21‐Jan‐18 12‐Feb‐18 12‐Feb‐18 95% 95% 0% 0.072% 0.072%
818 8 PIPING 3963‐KAHN‐5‐52‐0002 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 103 SHT.2 EL.105.500 & ABOVE 1 A 0.529% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Jul‐17 28‐Nov‐17 30‐Nov‐17 17‐Jan‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 19‐Jul‐17 28‐Nov‐17 30‐Nov‐17 17‐Jan‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.503% 0.503%
819 8 PIPING 3963‐KAHN‐5‐52‐0003 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 103 SHT.3 EL.103.590 TO EL.105 1 A 0.084% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 8‐Dec‐17 10‐Dec‐17 25‐Jan‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 15‐Jul‐17 8‐Dec‐17 10‐Dec‐17 25‐Jan‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.080% 0.080%
820 8 PIPING 3963‐KAHN‐5‐52‐0004 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 103 SHT.4 EL.105.500 & ABOVE 1 A 0.070% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 20‐Jul‐17 28‐Nov‐17 30‐Nov‐17 25‐Jan‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 20‐Jul‐17 28‐Nov‐17 30‐Nov‐17 25‐Jan‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.067% 0.067%
821 8 PIPING 3963‐KAHS‐5‐52‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.1 EL.26.000 TO 28.380 1 1 0.098% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 29‐Jun‐17 12‐Dec‐17 14‐Dec‐17 21‐Jan‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 29‐Jun‐17 12‐Dec‐17 14‐Dec‐17 21‐Jan‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.093% 0.093%
822 8 PIPING 3963‐KAHS‐5‐52‐0002 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.2 EL.26.000 TO 28.380 1 1 0.140% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 29‐Jun‐17 18‐Dec‐17 20‐Dec‐17 21‐Jan‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 29‐Jun‐17 18‐Dec‐17 20‐Dec‐17 21‐Jan‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.133% 0.133%
823 8 PIPING 3963‐KAHS‐5‐52‐0003 OT DUKHAN FIELD ‐ KHATIYAH SOUTH DEGASSING STATION; PIPING G.A AREA 300 SHT.3 EL.28.380 & ABOVE 1 1 0.084% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 29‐Jun‐17 11‐Dec‐17 13‐Dec‐17 21‐Jan‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 29‐Jun‐17 11‐Dec‐17 13‐Dec‐17 21‐Jan‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.080% 0.080%
824 8 PIPING 3963‐FAHM‐5‐52‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.1 EL.60.600 TO 63.050 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 4‐Dec‐17 6‐Dec‐17 1‐Feb‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 19‐Oct‐17 4‐Dec‐17 6‐Dec‐17 1‐Feb‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.093% 0.093%
825 8 PIPING 3963‐FAHM‐5‐52‐0002 OT DUKHAN FIELD ‐ FAHAHIL MAIN DEGASSING STATION; PIPING GA AREA 655 SHT.2 EL.63.050 & ABOVE 1 B 0.098% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 3‐Dec‐17 5‐Dec‐17 5‐Feb‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 19‐Oct‐17 3‐Dec‐17 5‐Dec‐17 5‐Feb‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.093% 0.093%
826 8 PIPING 3963‐KAHN‐5‐52‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH DEGASSING STATION; PIPING GA AREA 103 SHT.1 EL.103.590 TO EL.105 1 A 0.423% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 15‐Jul‐17 28‐Nov‐17 30‐Nov‐17 15‐Jan‐18 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 15‐Jul‐17 28‐Nov‐17 30‐Nov‐17 15‐Jan‐18 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.402% 0.402%
827 6 MECHANICAL 3963‐DGEN‐5‐14‐0007 OT TECHNICAL SPECIFICATION FOR NEW 3 PHASE TEST SEPARATOR 1 A 0.125% 11‐Apr‐17 21‐Apr‐17 26‐Apr‐17 27‐May‐17 17‐Jun‐17 27‐Jun‐17 31‐Oct‐18 5‐Apr‐17 25‐Apr‐17 27‐Apr‐17 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 22‐Jul‐19 5‐Apr‐17 25‐Apr‐17 27‐Apr‐17 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 95% 95% 0% 0.119% 0.119%
828 6 MECHANICAL 3963‐DGEN‐5‐15‐0005 OT MATERIAL REQUISITION FOR SEPARATOR EQUIPMENT 1 A 0.083% 30‐Apr‐17 10‐May‐17 15‐May‐17 15‐Jun‐17 6‐Jul‐17 16‐Jul‐17 31‐Oct‐18 11‐May‐17 24‐May‐17 25‐May‐17 27‐Jun‐17 30‐Jul‐17 31‐Jul‐17 22‐Jul‐19 11‐May‐17 24‐May‐17 25‐May‐17 27‐Jun‐17 30‐Jul‐17 31‐Jul‐17 95% 95% 0% 0.079% 0.079%
829 6 MECHANICAL 3963‐DGEN‐5‐17‐0005 OT TECHNICAL BID EVALUATION FOR SEPARATOR EQUIPMENT 1 A 0.167% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 3‐Aug‐17 8‐Aug‐17 10‐Aug‐17 22‐Aug‐17 1‐Oct‐17 1‐Oct‐17 22‐Jul‐19 3‐Aug‐17 8‐Aug‐17 10‐Aug‐17 22‐Aug‐17 1‐Oct‐17 1‐Oct‐17 95% 95% 0% 0.158% 0.158%
830 6 MECHANICAL 3963‐DGEN‐5‐13‐0007 OT MECHANICAL DATA SHEETS FOR SEPARATOR EQUIPMENT 1 A 0.125% 23‐Apr‐17 3‐May‐17 8‐May‐17 8‐Jun‐17 29‐Jun‐17 9‐Jul‐17 31‐Oct‐18 27‐Apr‐17 23‐May‐17 25‐May‐17 27‐Jun‐17 2‐Aug‐17 3‐Aug‐17 22‐Jul‐19 27‐Apr‐17 23‐May‐17 25‐May‐17 27‐Jun‐17 2‐Aug‐17 3‐Aug‐17 95% 95% 0% 0.119% 0.119%
831 6 MECHANICAL 3963‐DGEN‐5‐14‐0008 OT SPECIFICATION FOR PRESSURE RELIEF VALVES 1 A 0.125% 11‐May‐17 23‐May‐17 28‐May‐17 28‐Jun‐17 19‐Jul‐17 29‐Jul‐17 31‐Oct‐18 24‐Apr‐17 29‐Apr‐17 2‐May‐17 6‐Jun‐17 6‐Jun‐17 14‐Sep‐17 22‐Jul‐19 24‐Apr‐17 29‐Apr‐17 2‐May‐17 6‐Jun‐17 6‐Jun‐17 14‐Sep‐17 95% 95% 0% 0.119% 0.119%
832 6 MECHANICAL 3963‐DGEN‐5‐17‐0007 OT MATERIAL SELECTION REPORT (SEPARATORS) 1 A 0.083% 11‐May‐17 23‐May‐17 28‐May‐17 28‐Jun‐17 19‐Jul‐17 29‐Jul‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 5‐Jun‐17 25‐Jul‐17 26‐Jul‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 5‐Jun‐17 25‐Jul‐17 26‐Jul‐17 95% 95% 0% 0.079% 0.079%
833 6 MECHANICAL 3963‐KAHM‐5‐13‐0001 OT DATA SHEET FOR PRESSURE RELIEF VALVES (KAHM) 1 A 0.125% 6‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 22‐Jul‐19 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.119% 0.119%
834 6 MECHANICAL 3963‐KAHN‐5‐13‐0001 OT DATA SHEET FOR PRESSURE RELIEF VALVES (KAHN) 1 A 0.125% 6‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 22‐Jul‐19 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.119% 0.119%
835 6 MECHANICAL 3963‐KAHS‐5‐13‐0001 OT DATA SHEET FOR PRESSURE RELIEF VALVES (KAHS) 1 A 0.125% 6‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 22‐Jul‐19 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.119% 0.119%
836 6 MECHANICAL 3963‐FAHM‐5‐13‐0001 OT DATA SHEET FOR PRESSURE RELIEF VALVES (FAHM) 1 A 0.125% 6‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 22‐Jul‐19 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.119% 0.119%
837 6 MECHANICAL 3963‐FAHN‐5‐13‐0001 OT DATA SHEET FOR PRESSURE RELIEF VALVES (FAHN) 1 A 0.125% 6‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 22‐Jul‐19 10‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.119% 0.119%
838 6 MECHANICAL 3963‐FAHS‐5‐13‐0001 OT DATA SHEET FOR PRESSURE RELIEF VALVES (FAHS) 1 A 0.125% 6‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 25‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 22‐Jul‐19 25‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.119% 0.119%
839 6 MECHANICAL 3963‐JALM‐5‐13‐0001 OT DATA SHEET FOR PRESSURE RELIEF VALVES (JALM) 1 A 0.125% 6‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 25‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 22‐Jul‐19 25‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Sep‐17 20‐Sep‐17 2‐Nov‐17 95% 95% 0% 0.119% 0.119%
840 6 MECHANICAL 3963‐DGEN‐5‐15‐0006 OT MATERIAL REQUISITION FOR PRESSURE RELIEF VALVES 1 A 0.069% 3‐Jun‐17 13‐Jun‐17 18‐Jun‐17 19‐Jul‐17 9‐Aug‐17 19‐Aug‐17 31‐Oct‐18 8‐Jun‐17 20‐Jun‐17 22‐Jun‐17 18‐Aug‐17 18‐Oct‐17 19‐Oct‐17 22‐Jul‐19 8‐Jun‐17 20‐Jun‐17 22‐Jun‐17 18‐Aug‐17 18‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.066% 0.066%
841 6 MECHANICAL 3963‐DGEN‐5‐17‐0008 OT TECHNICAL BID EVALUATION FOR PRESSURE RELIEF VALVES 1 A 0.242% 5‐Aug‐17 15‐Aug‐17 20‐Aug‐17 9‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 24‐Nov‐17 26‐Nov‐17 26‐Dec‐17 26‐Dec‐17 26‐Dec‐17 22‐Jul‐19 19‐Oct‐17 24‐Nov‐17 26‐Nov‐17 26‐Dec‐17 26‐Dec‐17 26‐Dec‐17 95% 95% 0% 0.230% 0.230%
842 3 MECHANICAL 3963‐DGEN‐5‐00‐0002 OT MISCELLANEOUS ‐ MECHANICAL 0 0.022% 14‐Sep‐17 14‐Sep‐17 14‐Sep‐17 14‐Sep‐17 14‐Sep‐17 14‐Sep‐17 14‐Sep‐17 1‐Feb‐18 6‐Feb‐18 1‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 22‐Jul‐19 1‐Feb‐18 6‐Feb‐18 1‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 95% 95% 0% 0.021% 0.021%
843 3 ELECTRICAL 3963‐DGEN‐2‐14‐0001 OT SPECIFICATION FOR ELECTRICAL POWER, CONTROL CABLES  1 A 0.111% 17‐Mar‐17 27‐Mar‐17 1‐Apr‐17 2‐May‐17 23‐May‐17 2‐Jun‐17 31‐Oct‐18 15‐Mar‐17 4‐Apr‐17 12‐Apr‐17 26‐Apr‐17 23‐May‐17 23‐May‐17 22‐Jul‐19 15‐Mar‐17 4‐Apr‐17 12‐Apr‐17 26‐Apr‐17 23‐May‐17 23‐May‐17 95% 95% 0% 0.106% 0.106%
844 3 ELECTRICAL 3963‐DGEN‐2‐14‐0002 OT SPECIFICATION FOR ELECTRICAL BULK MATERIALS 1 A 0.111% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 29‐Mar‐17 3‐Apr‐17 12‐Apr‐17 26‐Apr‐17 26‐Apr‐17 26‐Apr‐17 22‐Jul‐19 29‐Mar‐17 3‐Apr‐17 12‐Apr‐17 26‐Apr‐17 26‐Apr‐17 26‐Apr‐17 95% 95% 0% 0.106% 0.106%
845 3 ELECTRICAL 3963‐DGEN‐2‐13‐0001 OT DATA SHEET FOR LV CABLES & EARTHING CABLES 1 A 0.097% 17‐Mar‐17 27‐Mar‐17 1‐Apr‐17 2‐May‐17 23‐May‐17 2‐Jun‐17 31‐Oct‐18 15‐Mar‐17 3‐Apr‐17 5‐Apr‐17 26‐Apr‐17 7‐May‐17 7‐May‐17 22‐Jul‐19 15‐Mar‐17 3‐Apr‐17 5‐Apr‐17 26‐Apr‐17 7‐May‐17 7‐May‐17 95% 95% 0% 0.092% 0.092%
846 3 ELECTRICAL 3963‐DGEN‐2‐80‐0001 OT TYPICAL INSTALLATION DETAILS DRAWINGS FOR POWER 1 A 0.153% 29‐Mar‐17 8‐Apr‐17 13‐Apr‐17 14‐May‐17 4‐Jun‐17 14‐Jun‐17 31‐Oct‐18 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 26‐Apr‐17 7‐May‐17 7‐May‐17 22‐Jul‐19 4‐Apr‐17 6‐Apr‐17 9‐Apr‐17 26‐Apr‐17 7‐May‐17 7‐May‐17 95% 95% 0% 0.145% 0.145%
847 3 ELECTRICAL 3963‐DGEN‐2‐80‐0002 OT TYPICAL INSTALLATION DETAILS DRAWINGS FOR EARTHING 1 A 0.153% 29‐Mar‐17 8‐Apr‐17 13‐Apr‐17 14‐May‐17 4‐Jun‐17 14‐Jun‐17 31‐Oct‐18 2‐Apr‐17 5‐Apr‐17 9‐Apr‐17 3‐May‐17 3‐May‐17 3‐May‐17 22‐Jul‐19 2‐Apr‐17 5‐Apr‐17 9‐Apr‐17 3‐May‐17 3‐May‐17 3‐May‐17 95% 95% 0% 0.145% 0.145%
848 3 ELECTRICAL 3963‐DGEN‐2‐80‐0003 OT TYPICAL INSTALLATION DETAILS DRAWINGS FOR LIGHTING 1 A 0.153% 5‐Apr‐17 15‐Apr‐17 20‐Apr‐17 21‐May‐17 11‐Jun‐17 21‐Jun‐17 31‐Oct‐18 5‐Apr‐17 6‐Apr‐17 9‐Apr‐17 3‐May‐17 3‐May‐17 3‐May‐17 22‐Jul‐19 5‐Apr‐17 6‐Apr‐17 9‐Apr‐17 3‐May‐17 3‐May‐17 3‐May‐17 95% 95% 0% 0.145% 0.145%
849 3 ELECTRICAL 3963‐KAHM‐2‐34‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 ELECTRICAL LOAD SCHEDULE 1 B 0.097% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 23‐Aug‐17 10‐Sep‐17 17‐Sep‐17 31‐Oct‐18 6‐May‐17 8‐May‐17 9‐May‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 22‐Jul‐19 6‐May‐17 8‐May‐17 9‐May‐17 5‐Oct‐17 5‐Oct‐17 5‐Oct‐17 95% 95% 0% 0.092% 0.092%
850 3 ELECTRICAL 3963‐KAHM‐2‐36‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 ELECTRICAL TIE‐IN SCHEDULE 1 A 0.083% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 4‐Dec‐17 22‐Jul‐19 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 4‐Dec‐17 95% 95% 0% 0.079% 0.079%
851 3 ELECTRICAL 3963‐KAHM‐2‐37‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 ELECTRICAL CABLE SCHEDULE 1 A 0.097% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 25‐May‐17 29‐May‐17 30‐May‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 22‐Jul‐19 25‐May‐17 29‐May‐17 30‐May‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.092% 0.092%
852 3 ELECTRICAL 3963‐KAHM‐2‐54‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 24MCC‐2601 MOTOR CONTROL CENTER SINGLE LINE DIAGRAM 1 B 0.097% 8‐Jun‐17 18‐Jun‐17 23‐Jun‐17 24‐Jul‐17 14‐Aug‐17 24‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 12‐Jun‐17 24‐Sep‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 12‐Jun‐17 24‐Sep‐17 95% 95% 0% 0.092% 0.092%
853 3 ELECTRICAL 3963‐KAHM‐2‐54‐0002 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 24‐DB‐2604 DISTRIBUTION BOARD SINGLE LINE DIAGRAM‐415V 1 A 0.097% 8‐Jun‐17 18‐Jun‐17 23‐Jun‐17 24‐Jul‐17 14‐Aug‐17 24‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 3‐Aug‐17 22‐Aug‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 3‐Aug‐17 22‐Aug‐17 95% 95% 0% 0.092% 0.092%
854 3 ELECTRICAL 3963‐KAHM‐2‐54‐0003 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 24UPS‐2605(CLASS A UPS) S.L.D INSTRUMENT UPS 240V A.C. 1 A 0.097% 8‐Jun‐17 18‐Jun‐17 23‐Jun‐17 24‐Jul‐17 14‐Aug‐17 24‐Aug‐17 31‐Oct‐18 10‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 24‐Sep‐17 22‐Jul‐19 10‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 24‐Sep‐17 95% 95% 0% 0.092% 0.092%
855 3 ELECTRICAL 3963‐KAHM‐2‐64‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 CABLE ROUTING LAYOUT 1 A 0.111% 30‐Jun‐17 10‐Jul‐17 15‐Jul‐17 15‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 2‐Nov‐17 22‐Jul‐19 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 2‐Nov‐17 95% 95% 0% 0.106% 0.106%
856 3 ELECTRICAL 3963‐KAHM‐2‐65‐0002 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 EARTHING LAYOUT 1 A 0.097% 30‐Jun‐17 10‐Jul‐17 15‐Jul‐17 15‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 2‐Jul‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 22‐Jul‐19 2‐Jul‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
857 3 ELECTRICAL 3963‐KAHM‐2‐67‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 LIGHTING LAYOUT 1 A 0.097% 30‐Jun‐17 10‐Jul‐17 15‐Jul‐17 15‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 27‐May‐17 27‐May‐17 28‐May‐17 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 22‐Jul‐19 27‐May‐17 27‐May‐17 28‐May‐17 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 95% 95% 0% 0.092% 0.092%
858 3 ELECTRICAL 3963‐KAHM‐2‐31‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 MTO FOR ELECTRICAL POWER, CONTROL CABLES & EARTHING C 3 A 0.097% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 2‐Oct‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 2‐Oct‐17 95% 95% 0% 0.092% 0.092%
859 3 ELECTRICAL 3963‐KAHM‐2‐31‐0002 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 MTO FOR ELECTRICAL BULK MATERIALS (LIGHTING, EARTHING,  3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 95% 95% 0% 0.079% 0.079%
860 3 ELECTRICAL 3963‐KAHM‐2‐17‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 POWER ADEQUACY REPORT 1 A 0.153% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 22‐Nov‐17 22‐Jul‐19 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 22‐Nov‐17 95% 95% 0% 0.145% 0.145%
861 3 ELECTRICAL 3963‐KAHM‐2‐12‐0001 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 LV CABLE SIZING CALCULATION 1 B 0.111% 8‐Apr‐17 18‐Apr‐17 23‐Apr‐17 24‐May‐17 14‐Jun‐17 24‐Jun‐17 31‐Oct‐18 19‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 5‐Oct‐17 22‐Jul‐19 19‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 5‐Oct‐17 95% 95% 0% 0.106% 0.106%
862 3 ELECTRICAL 3963‐KAHM‐2‐12‐0002 OT DUKHAN FIELD ‐ KHATIYAH MAIN UNIT 24 LIGHTING CALCULATION 1 B 0.111% 18‐May‐17 28‐May‐17 2‐Jun‐17 3‐Jul‐17 24‐Jul‐17 3‐Aug‐17 31‐Oct‐18 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 19‐Jun‐17 19‐Jun‐17 19‐Jun‐17 22‐Jul‐19 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 19‐Jun‐17 19‐Jun‐17 19‐Jun‐17 95% 95% 0% 0.106% 0.106%
863 3 ELECTRICAL 3963‐KAHN‐2‐34‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 ELECTRICAL LOAD SCHEDULE 1 A 0.097% 18‐Jul‐17 28‐Jul‐17 2‐Aug‐17 20‐Aug‐17 30‐Aug‐17 9‐Sep‐17 31‐Oct‐18 4‐May‐17 3‐May‐17 4‐May‐17 5‐Jul‐17 13‐Jul‐17 18‐Sep‐17 22‐Jul‐19 4‐May‐17 3‐May‐17 4‐May‐17 5‐Jul‐17 13‐Jul‐17 18‐Sep‐17 95% 95% 0% 0.092% 0.092%
864 3 ELECTRICAL 3963‐KAHN‐2‐36‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 ELECTRICAL TIE‐IN SCHEDULE 1 A 0.097% 28‐May‐17 7‐Jun‐17 12‐Jun‐17 13‐Jul‐17 3‐Aug‐17 13‐Aug‐17 31‐Oct‐18 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 25‐Sep‐17 22‐Jul‐19 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 25‐Sep‐17 95% 95% 0% 0.092% 0.092%
865 3 ELECTRICAL 3963‐KAHN‐2‐37‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 ELECTRICAL CABLE SCHEDULE 1 A 0.097% 28‐May‐17 7‐Jun‐17 12‐Jun‐17 13‐Jul‐17 3‐Aug‐17 13‐Aug‐17 31‐Oct‐18 30‐May‐17 30‐May‐17 31‐May‐17 2‐Aug‐17 3‐Aug‐17 19‐Sep‐17 22‐Jul‐19 30‐May‐17 30‐May‐17 31‐May‐17 2‐Aug‐17 3‐Aug‐17 19‐Sep‐17 95% 95% 0% 0.092% 0.092%
866 3 ELECTRICAL 3963‐KAHN‐2‐54‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 22‐DB‐7311/7312 DISTRIBUTION BOARD SINGLE LINE DIAGRAM 1 A 0.097% 18‐Jun‐17 28‐Jun‐17 3‐Jul‐17 3‐Aug‐17 24‐Aug‐17 3‐Sep‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 3‐Aug‐17 17‐Aug‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 3‐Aug‐17 17‐Aug‐17 95% 95% 0% 0.092% 0.092%
867 3 ELECTRICAL 3963‐KAHN‐2‐54‐0002 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 22UPS‐1801 UPS 10KVA SINGLE LINE DIAGRAM‐110/240V AC 1 A 0.097% 18‐Jun‐17 28‐Jun‐17 3‐Jul‐17 3‐Aug‐17 24‐Aug‐17 3‐Sep‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 25‐Sep‐17 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 25‐Sep‐17 95% 95% 0% 0.092% 0.092%

Page 7 of 13
Page 78 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
868 3 ELECTRICAL 3963‐KAHN‐2‐64‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 CABLE ROUTING LAYOUT 1 A 0.153% 18‐Jun‐17 28‐Jun‐17 3‐Jul‐17 3‐Aug‐17 24‐Aug‐17 3‐Sep‐17 31‐Oct‐18 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 29‐Oct‐17 22‐Jul‐19 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 29‐Oct‐17 95% 95% 0% 0.145% 0.145%
869 3 ELECTRICAL 3963‐KAHN‐2‐65‐0002 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 EARTHING LAYOUT 1 A 0.111% 18‐Jul‐17 28‐Jul‐17 2‐Aug‐17 20‐Aug‐17 30‐Aug‐17 9‐Sep‐17 31‐Oct‐18 2‐Jul‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 22‐Jul‐19 2‐Jul‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.106% 0.106%
870 3 ELECTRICAL 3963‐KAHN‐2‐67‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 LIGHTING LAYOUT 1 A 0.097% 18‐Jul‐17 28‐Jul‐17 2‐Aug‐17 20‐Aug‐17 30‐Aug‐17 9‐Sep‐17 31‐Oct‐18 22‐May‐17 23‐May‐17 25‐May‐17 13‐Jun‐17 21‐Jun‐17 3‐Aug‐17 22‐Jul‐19 22‐May‐17 23‐May‐17 25‐May‐17 13‐Jun‐17 21‐Jun‐17 3‐Aug‐17 95% 95% 0% 0.092% 0.092%
871 3 ELECTRICAL 3963‐KAHN‐2‐31‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 MTO FOR ELECTRICAL POWER, CONTROL CABLES & EARTHING 3 A 0.097% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 19‐Oct‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 19‐Oct‐17 95% 95% 0% 0.092% 0.092%
872 3 ELECTRICAL 3963‐KAHN‐2‐31‐0002 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 MTO FOR ELECTRICAL BULK MATERIALS (LIGHTING, EARTHING 3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 95% 95% 0% 0.079% 0.079%
873 3 ELECTRICAL 3963‐KAHN‐2‐17‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 POWER ADEQUACY REPORT 1 A 0.153% 30‐May‐17 9‐Jun‐17 14‐Jun‐17 15‐Jul‐17 5‐Aug‐17 15‐Aug‐17 31‐Oct‐18 1‐Jun‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 24‐Sep‐17 22‐Jul‐19 1‐Jun‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 24‐Sep‐17 95% 95% 0% 0.145% 0.145%
874 3 ELECTRICAL 3963‐KAHN‐2‐12‐0001 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 LV CABLE SIZING CALCULATION 1 A 0.111% 15‐Apr‐17 25‐Apr‐17 30‐Apr‐17 31‐May‐17 21‐Jun‐17 1‐Jul‐17 31‐Oct‐18 19‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 5‐Oct‐17 22‐Jul‐19 19‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 5‐Oct‐17 95% 95% 0% 0.106% 0.106%
875 3 ELECTRICAL 3963‐KAHN‐2‐12‐0002 OT DUKHAN FIELD ‐ KHATIYAH NORTH UNIT 22 LIGHTING CALCULATION 1 A 0.111% 28‐May‐17 7‐Jun‐17 12‐Jun‐17 13‐Jul‐17 3‐Aug‐17 13‐Aug‐17 31‐Oct‐18 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 22‐Jul‐19 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 95% 95% 0% 0.106% 0.106%
876 3 ELECTRICAL 3963‐KAHS‐2‐34‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 ELECTRICAL LOAD SCHEDULE 1 A 0.097% 15‐Jun‐17 25‐Jun‐17 30‐Jun‐17 31‐Jul‐17 21‐Aug‐17 31‐Aug‐17 31‐Oct‐18 4‐May‐17 3‐May‐17 4‐May‐17 5‐Jul‐17 13‐Jul‐17 20‐Sep‐17 22‐Jul‐19 4‐May‐17 3‐May‐17 4‐May‐17 5‐Jul‐17 13‐Jul‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
877 3 ELECTRICAL 3963‐KAHS‐2‐36‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 ELECTRICAL TIE‐IN SCHEDULE 1 A 0.097% 25‐Jul‐17 4‐Aug‐17 9‐Aug‐17 27‐Aug‐17 6‐Sep‐17 16‐Sep‐17 31‐Oct‐18 16‐May‐17 17‐May‐17 17‐May‐17 2‐Aug‐17 3‐Aug‐17 25‐Sep‐17 22‐Jul‐19 16‐May‐17 17‐May‐17 17‐May‐17 2‐Aug‐17 3‐Aug‐17 25‐Sep‐17 95% 95% 0% 0.092% 0.092%
878 3 ELECTRICAL 3963‐KAHS‐2‐37‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 ELECTRICAL CABLE SCHEDULE 1 A 0.097% 25‐Jul‐17 4‐Aug‐17 9‐Aug‐17 27‐Aug‐17 6‐Sep‐17 16‐Sep‐17 31‐Oct‐18 30‐May‐17 30‐May‐17 31‐May‐17 2‐Aug‐17 3‐Aug‐17 19‐Sep‐17 22‐Jul‐19 30‐May‐17 30‐May‐17 31‐May‐17 2‐Aug‐17 3‐Aug‐17 19‐Sep‐17 95% 95% 0% 0.092% 0.092%
879 3 ELECTRICAL 3963‐KAHS‐2‐54‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 23‐SB‐7220 SWITCHBOARD SINGLE LINE DIAGRAM‐415V SYSTE 1 3 0.083% 4‐Jun‐17 14‐Jun‐17 19‐Jun‐17 20‐Jul‐17 10‐Aug‐17 20‐Aug‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 95% 95% 0% 0.079% 0.079%
880 3 ELECTRICAL 3963‐KAHS‐2‐54‐0002 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 23‐DB‐0001/0002‐ DISTRIBUTION BOARD SINGLE LINE DIAGRA 1 A 0.097% 4‐Jun‐17 14‐Jun‐17 19‐Jun‐17 20‐Jul‐17 10‐Aug‐17 20‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 12‐Jun‐17 22‐Aug‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 12‐Jun‐17 22‐Aug‐17 95% 95% 0% 0.092% 0.092%
881 3 ELECTRICAL 3963‐KAHS‐2‐54‐0003 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 23‐UPS‐7701,15KVA SINGLE LINE DIAGRAM‐110/240V AC SYST 1 A 0.097% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 3‐Aug‐17 20‐Sep‐17 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 5‐Jun‐17 3‐Aug‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
882 3 ELECTRICAL 3963‐KAHS‐2‐64‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 CABLE ROUTING LAYOUT 1 A 0.111% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 8‐Nov‐17 22‐Jul‐19 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 8‐Nov‐17 95% 95% 0% 0.106% 0.106%
883 3 ELECTRICAL 3963‐KAHS‐2‐65‐0002 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 EARTHING LAYOUT 1 A 0.097% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 22‐Jul‐19 28‐Jun‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
884 3 ELECTRICAL 3963‐KAHS‐2‐67‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 LIGHTING LAYOUT 1 A 0.097% 30‐Jun‐17 10‐Jul‐17 15‐Jul‐17 15‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 22‐Jun‐17 2‐Aug‐17 3‐Aug‐17 95% 95% 0% 0.092% 0.092%
885 3 ELECTRICAL 3963‐KAHS‐2‐31‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 MTO FOR ELECTRICAL POWER, CONTROL CABLES & EARTHING  3 A 0.097% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 20‐Sep‐17 5‐Oct‐17 19‐Oct‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 20‐Sep‐17 5‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.092% 0.092%
886 3 ELECTRICAL 3963‐KAHS‐2‐31‐0002 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 MTO FOR ELECTRICAL BULK MATERIALS (LIGHTING, EARTHING 3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 8‐Jul‐17 8‐Jul‐17 9‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 22‐Jul‐19 8‐Jul‐17 8‐Jul‐17 9‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 95% 95% 0% 0.079% 0.079%
887 3 ELECTRICAL 3963‐KAHS‐2‐17‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 POWER ADEQUACY REPORT 1 A 0.153% 22‐Apr‐17 2‐May‐17 7‐May‐17 7‐Jun‐17 28‐Jun‐17 8‐Jul‐17 31‐Oct‐18 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 20‐Sep‐17 22‐Jul‐19 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 20‐Sep‐17 95% 95% 0% 0.145% 0.145%
888 3 ELECTRICAL 3963‐KAHS‐2‐12‐0001 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 LV CABLE SIZING CALCULATION 1 A 0.111% 7‐Jul‐17 17‐Jul‐17 22‐Jul‐17 22‐Aug‐17 9‐Sep‐17 16‐Sep‐17 31‐Oct‐18 22‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 28‐Sep‐17 22‐Jul‐19 22‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 28‐Sep‐17 95% 95% 0% 0.106% 0.106%
889 3 ELECTRICAL 3963‐KAHS‐2‐12‐0002 OT DUKHAN FIELD ‐ KHATIYAH SOUTH UNIT 23 LIGHTING CALCULATION 1 A 0.111% 7‐Jul‐17 17‐Jul‐17 22‐Jul‐17 22‐Aug‐17 9‐Sep‐17 16‐Sep‐17 31‐Oct‐18 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 22‐Jul‐19 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 95% 95% 0% 0.106% 0.106%
890 3 ELECTRICAL 3963‐FAHM‐2‐34‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 ELECTRICAL LOAD SCHEDULE 1 A 0.097% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 30‐Apr‐17 3‐May‐17 5‐Jul‐17 3‐Aug‐17 20‐Sep‐17 22‐Jul‐19 19‐Apr‐17 30‐Apr‐17 3‐May‐17 5‐Jul‐17 3‐Aug‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
891 3 ELECTRICAL 3963‐FAHM‐2‐36‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 ELECTRICAL TIE‐IN SCHEDULE 1 B 0.097% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 22‐Jun‐17 22‐Jun‐17 22‐Jul‐19 19‐Apr‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 22‐Jun‐17 22‐Jun‐17 95% 95% 0% 0.092% 0.092%
892 3 ELECTRICAL 3963‐FAHM‐2‐37‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 ELECTRICAL CABLE SCHEDULE 1 A 0.097% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 22‐May‐17 23‐May‐17 25‐May‐17 19‐Jun‐17 27‐Jun‐17 19‐Sep‐17 22‐Jul‐19 22‐May‐17 23‐May‐17 25‐May‐17 19‐Jun‐17 27‐Jun‐17 19‐Sep‐17 95% 95% 0% 0.092% 0.092%
893 3 ELECTRICAL 3963‐FAHM‐2‐54‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 14‐MCC‐2601 MOTOR CONTROL CENTRE SINGLE LINE DIAGRAM‐ 1 3 0.083% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 19‐Sep‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 19‐Sep‐17 95% 95% 0% 0.079% 0.079%
894 3 ELECTRICAL 3963‐FAHM‐2‐54‐0002 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 14‐DB‐2603 ‐ DISTRIBUTION BOARD SINGLE LINE DIAGRAM‐415V  1 B 0.097% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 21‐Jun‐17 21‐Jun‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 21‐Jun‐17 21‐Jun‐17 95% 95% 0% 0.092% 0.092%
895 3 ELECTRICAL 3963‐FAHM‐2‐54‐0003 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 14‐UPS‐2605 UPS,10KVA SINGLE LINE DIAGRAM‐240V AC SYSTEM 1 A 0.097% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 14‐Jun‐17 22‐Jun‐17 20‐Sep‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 14‐Jun‐17 22‐Jun‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
896 3 ELECTRICAL 3963‐FAHM‐2‐64‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 CABLE ROUTING LAYOUT 1 A 0.097% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 25‐May‐17 10‐Jun‐17 11‐Jun‐17 2‐Aug‐17 3‐Aug‐17 9‐Jan‐18 22‐Jul‐19 25‐May‐17 10‐Jun‐17 11‐Jun‐17 2‐Aug‐17 3‐Aug‐17 9‐Jan‐18 95% 95% 0% 0.092% 0.092%
897 3 ELECTRICAL 3963‐FAHM‐2‐65‐0002 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 EARTHING LAYOUT 1 A 0.097% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 25‐May‐17 2‐Jul‐17 3‐Jul‐17 20‐Jul‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 25‐May‐17 2‐Jul‐17 3‐Jul‐17 20‐Jul‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.092% 0.092%
898 3 ELECTRICAL 3963‐FAHM‐2‐67‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 LIGHTING LAYOUT 1 A 0.097% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 21‐May‐17 22‐May‐17 24‐May‐17 13‐Jun‐17 21‐Jun‐17 3‐Aug‐17 22‐Jul‐19 21‐May‐17 22‐May‐17 24‐May‐17 13‐Jun‐17 21‐Jun‐17 3‐Aug‐17 95% 95% 0% 0.092% 0.092%
899 3 ELECTRICAL 3963‐FAHM‐2‐31‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 MTO FOR ELECTRICAL POWER, CONTROL CABLES & EARTHING CA 3 A 0.097% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 6‐Jul‐17 6‐Jul‐17 28‐Sep‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 6‐Jul‐17 6‐Jul‐17 28‐Sep‐17 95% 95% 0% 0.092% 0.092%
900 3 ELECTRICAL 3963‐FAHM‐2‐31‐0002 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 MTO FOR ELECTRICAL BULK MATERIALS (LIGHTING, EARTHING, PO 3 A 0.097% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.092% 0.092%
901 3 ELECTRICAL 3963‐FAHM‐2‐17‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 POWER ADEQUACY REPORT 1 A 0.153% 1‐May‐17 11‐May‐17 16‐May‐17 16‐Jun‐17 7‐Jul‐17 17‐Jul‐17 31‐Oct‐18 25‐May‐17 12‐Jun‐17 13‐Jun‐17 12‐Sep‐17 24‐Sep‐17 24‐Sep‐17 22‐Jul‐19 25‐May‐17 12‐Jun‐17 13‐Jun‐17 12‐Sep‐17 24‐Sep‐17 24‐Sep‐17 95% 95% 0% 0.145% 0.145%
902 3 ELECTRICAL 3963‐FAHM‐2‐12‐0001 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 LV CABLE SIZING CALCULATION 1 A 0.111% 17‐Apr‐17 27‐Apr‐17 2‐May‐17 2‐Jun‐17 23‐Jun‐17 3‐Jul‐17 31‐Oct‐18 19‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 22‐Jun‐17 22‐Jun‐17 22‐Jul‐19 19‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 22‐Jun‐17 22‐Jun‐17 95% 95% 0% 0.106% 0.106%
903 3 ELECTRICAL 3963‐FAHM‐2‐12‐0002 OT DUKHAN FIELD ‐ FAHAHIL MAIN UNIT 14 LIGHTING CALCULATION 1 A 0.111% 24‐Apr‐17 4‐May‐17 9‐May‐17 9‐Jun‐17 30‐Jun‐17 10‐Jul‐17 31‐Oct‐18 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 20‐Jul‐17 18‐Sep‐17 19‐Sep‐17 22‐Jul‐19 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 20‐Jul‐17 18‐Sep‐17 19‐Sep‐17 95% 95% 0% 0.106% 0.106%
904 3 ELECTRICAL 3963‐FAHN‐2‐34‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 ELECTRICAL LOAD SCHEDULE 1 A 0.097% 24‐Apr‐17 4‐May‐17 9‐May‐17 9‐Jun‐17 30‐Jun‐17 10‐Jul‐17 31‐Oct‐18 25‐Apr‐17 30‐Apr‐17 3‐May‐17 5‐Jul‐17 3‐Aug‐17 28‐Sep‐17 22‐Jul‐19 25‐Apr‐17 30‐Apr‐17 3‐May‐17 5‐Jul‐17 3‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.092% 0.092%
905 3 ELECTRICAL 3963‐FAHN‐2‐36‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 ELECTRICAL TIE‐IN SCHEDULE 1 A 0.083% 24‐Apr‐17 4‐May‐17 9‐May‐17 9‐Jun‐17 30‐Jun‐17 10‐Jul‐17 31‐Oct‐18 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 7‐Dec‐17 22‐Jul‐19 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 7‐Dec‐17 95% 95% 0% 0.079% 0.079%
906 3 ELECTRICAL 3963‐FAHN‐2‐37‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 ELECTRICAL CABLE SCHEDULE 1 A 0.097% 10‐May‐17 20‐May‐17 25‐May‐17 25‐Jun‐17 16‐Jul‐17 26‐Jul‐17 31‐Oct‐18 22‐May‐17 23‐May‐17 25‐May‐17 19‐Jun‐17 27‐Jun‐17 28‐Sep‐17 22‐Jul‐19 22‐May‐17 23‐May‐17 25‐May‐17 19‐Jun‐17 27‐Jun‐17 28‐Sep‐17 95% 95% 0% 0.092% 0.092%
907 3 ELECTRICAL 3963‐FAHN‐2‐54‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 12‐SB‐0007‐EXISTING LV SWITCHBOARD SINGLE LINE DIAGRAM‐ 1 B 0.083% 10‐May‐17 20‐May‐17 25‐May‐17 25‐Jun‐17 16‐Jul‐17 26‐Jul‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 24‐Sep‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 24‐Sep‐17 95% 95% 0% 0.079% 0.079%
908 3 ELECTRICAL 3963‐FAHN‐2‐54‐0002 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 12‐DB‐0001/0002 ‐ EXISTING LV DISTRIBUTION BOARD SINGLE L 1 B 0.083% 10‐May‐17 20‐May‐17 25‐May‐17 25‐Jun‐17 16‐Jul‐17 26‐Jul‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 21‐Jun‐17 21‐Jun‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 21‐Jun‐17 21‐Jun‐17 95% 95% 0% 0.079% 0.079%
909 3 ELECTRICAL 3963‐FAHN‐2‐54‐0003 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 12‐UPS‐0007 UPS,5KVA SINGLE LINE DIAGRAM‐110V AC SYSTEM 1 A 0.083% 10‐May‐17 20‐May‐17 25‐May‐17 25‐Jun‐17 16‐Jul‐17 26‐Jul‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 20‐Sep‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
910 3 ELECTRICAL 3963‐FAHN‐2‐64‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 CABLE ROUTING LAYOUT 1 A 0.097% 3‐Jun‐17 13‐Jun‐17 18‐Jun‐17 19‐Jul‐17 9‐Aug‐17 19‐Aug‐17 31‐Oct‐18 7‐Jun‐17 14‐Jun‐17 15‐Jun‐17 2‐Aug‐17 3‐Aug‐17 4‐Dec‐17 22‐Jul‐19 7‐Jun‐17 14‐Jun‐17 15‐Jun‐17 2‐Aug‐17 3‐Aug‐17 4‐Dec‐17 95% 95% 0% 0.092% 0.092%
911 3 ELECTRICAL 3963‐FAHN‐2‐65‐0002 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 EARTHING LAYOUT 1 A 0.083% 3‐Jun‐17 13‐Jun‐17 18‐Jun‐17 19‐Jul‐17 9‐Aug‐17 19‐Aug‐17 31‐Oct‐18 7‐Jun‐17 3‐Jul‐17 4‐Jul‐17 20‐Jul‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 7‐Jun‐17 3‐Jul‐17 4‐Jul‐17 20‐Jul‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
912 3 ELECTRICAL 3963‐FAHN‐2‐67‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 LIGHTING LAYOUT 1 A 0.083% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 22‐May‐17 23‐May‐17 25‐May‐17 21‐Jun‐17 29‐Jun‐17 3‐Aug‐17 22‐Jul‐19 22‐May‐17 23‐May‐17 25‐May‐17 21‐Jun‐17 29‐Jun‐17 3‐Aug‐17 95% 95% 0% 0.079% 0.079%
913 3 ELECTRICAL 3963‐FAHN‐2‐31‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 MTO FOR ELECTRICAL POWER, CONTROL CABLES & EARTHING C 3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.079% 0.079%
914 3 ELECTRICAL 3963‐FAHN‐2‐31‐0002 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 MTO FOR ELECTRICAL BULK MATERIALS (LIGHTING, EARTHING,  3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 1‐Oct‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 1‐Oct‐17 95% 95% 0% 0.079% 0.079%
915 3 ELECTRICAL 3963‐FAHN‐2‐17‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 POWER ADEQUACY REPORT 1 A 0.153% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 19‐Oct‐17 22‐Jul‐19 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 19‐Oct‐17 95% 95% 0% 0.145% 0.145%
916 3 ELECTRICAL 3963‐FAHN‐2‐12‐0001 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 LV CABLE SIZING CALCULATION 1 A 0.111% 24‐Apr‐17 4‐May‐17 9‐May‐17 9‐Jun‐17 30‐Jun‐17 10‐Jul‐17 31‐Oct‐18 22‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 28‐Sep‐17 22‐Jul‐19 22‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 28‐Sep‐17 95% 95% 0% 0.106% 0.106%
917 3 ELECTRICAL 3963‐FAHN‐2‐12‐0002 OT DUKHAN FIELD ‐ FAHAHIL NORTH UNIT 12 LIGHTING CALCULATION 1 B 0.111% 1‐May‐17 11‐May‐17 16‐May‐17 16‐Jun‐17 7‐Jul‐17 17‐Jul‐17 31‐Oct‐18 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 19‐Jun‐17 19‐Jun‐17 19‐Jun‐17 22‐Jul‐19 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 19‐Jun‐17 19‐Jun‐17 19‐Jun‐17 95% 95% 0% 0.106% 0.106%
918 3 ELECTRICAL 3963‐FAHS‐2‐34‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 ELECTRICAL LOAD SCHEDULE 1 B 0.083% 1‐May‐17 11‐May‐17 16‐May‐17 16‐Jun‐17 7‐Jul‐17 17‐Jul‐17 31‐Oct‐18 25‐Apr‐17 30‐Apr‐17 3‐May‐17 5‐Jul‐17 3‐Aug‐17 5‐Oct‐17 22‐Jul‐19 25‐Apr‐17 30‐Apr‐17 3‐May‐17 5‐Jul‐17 3‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.079% 0.079%
919 3 ELECTRICAL 3963‐FAHS‐2‐36‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 ELECTRICAL TIE‐IN SCHEDULE 1 A 0.083% 1‐May‐17 11‐May‐17 16‐May‐17 16‐Jun‐17 7‐Jul‐17 17‐Jul‐17 31‐Oct‐18 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 7‐Dec‐17 22‐Jul‐19 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 7‐Dec‐17 95% 95% 0% 0.079% 0.079%
920 3 ELECTRICAL 3963‐FAHS‐2‐37‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 ELECTRICAL CABLE SCHEDULE 1 A 0.083% 18‐May‐17 28‐May‐17 2‐Jun‐17 3‐Jul‐17 24‐Jul‐17 3‐Aug‐17 31‐Oct‐18 25‐May‐17 29‐May‐17 30‐May‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 22‐Jul‐19 25‐May‐17 29‐May‐17 30‐May‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.079% 0.079%
921 3 ELECTRICAL 3963‐FAHS‐2‐54‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 12‐SB‐0007‐EXISTING LV SWITCHBOARD SINGLE LINE DIAGRAM‐ 1 B 0.083% 18‐May‐17 28‐May‐17 2‐Jun‐17 3‐Jul‐17 24‐Jul‐17 3‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 24‐Sep‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 24‐Sep‐17 95% 95% 0% 0.079% 0.079%
922 3 ELECTRICAL 3963‐FAHS‐2‐54‐0002 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 12‐DB‐0001/0002 ‐ EXISTING LV DISTRIBUTION BOARD SINGLE L 1 B 0.083% 18‐May‐17 28‐May‐17 2‐Jun‐17 3‐Jul‐17 24‐Jul‐17 3‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 21‐Jun‐17 21‐Jun‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 21‐Jun‐17 21‐Jun‐17 95% 95% 0% 0.079% 0.079%
923 3 ELECTRICAL 3963‐FAHS‐2‐54‐0003 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 12‐UPS‐0007 UPS,5KVA SINGLE LINE DIAGRAM‐110V AC SYSTEM 1 A 0.083% 18‐May‐17 28‐May‐17 2‐Jun‐17 3‐Jul‐17 24‐Jul‐17 3‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 20‐Sep‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 9‐Jun‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
924 3 ELECTRICAL 3963‐FAHS‐2‐64‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 CABLE ROUTING LAYOUT 1 A 0.111% 10‐Jun‐17 20‐Jun‐17 25‐Jun‐17 26‐Jul‐17 16‐Aug‐17 26‐Aug‐17 31‐Oct‐18 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 8‐Nov‐17 22‐Jul‐19 17‐Jun‐17 18‐Jun‐17 19‐Jun‐17 2‐Aug‐17 3‐Aug‐17 8‐Nov‐17 95% 95% 0% 0.106% 0.106%
925 3 ELECTRICAL 3963‐FAHS‐2‐65‐0002 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 EARTHING LAYOUT 1 A 0.083% 10‐Jun‐17 20‐Jun‐17 25‐Jun‐17 26‐Jul‐17 16‐Aug‐17 26‐Aug‐17 31‐Oct‐18 2‐Jul‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 2‐Jul‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
926 3 ELECTRICAL 3963‐FAHS‐2‐67‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 LIGHTING LAYOUT 1 A 0.083% 10‐Jun‐17 20‐Jun‐17 25‐Jun‐17 26‐Jul‐17 16‐Aug‐17 26‐Aug‐17 31‐Oct‐18 27‐May‐17 27‐May‐17 28‐May‐17 21‐Jun‐17 29‐Jun‐17 3‐Aug‐17 22‐Jul‐19 27‐May‐17 27‐May‐17 28‐May‐17 21‐Jun‐17 29‐Jun‐17 3‐Aug‐17 95% 95% 0% 0.079% 0.079%
927 3 ELECTRICAL 3963‐FAHS‐2‐31‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 MTO FOR ELECTRICAL POWER, CONTROL CABLES & EARTHING C 3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.079% 0.079%
928 3 ELECTRICAL 3963‐FAHS‐2‐31‐0002 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 MTO FOR ELECTRICAL BULK MATERIALS (LIGHTING, EARTHING, P 3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 2‐Oct‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 2‐Oct‐17 95% 95% 0% 0.079% 0.079%
929 3 ELECTRICAL 3963‐FAHS‐2‐17‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 POWER ADEQUACY REPORT 1 A 0.153% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 22‐Jul‐19 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 95% 95% 0% 0.145% 0.145%
930 3 ELECTRICAL 3963‐FAHS‐2‐12‐0001 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 LV CABLE SIZING CALCULATION 1 A 0.111% 1‐May‐17 11‐May‐17 16‐May‐17 16‐Jun‐17 7‐Jul‐17 17‐Jul‐17 31‐Oct‐18 22‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 28‐Sep‐17 22‐Jul‐19 22‐Apr‐17 22‐Apr‐17 24‐Apr‐17 17‐May‐17 25‐May‐17 28‐Sep‐17 95% 95% 0% 0.106% 0.106%
931 3 ELECTRICAL 3963‐FAHS‐2‐12‐0002 OT DUKHAN FIELD ‐ FAHAHIL SOUTH UNIT 13 LIGHTING CALCULATION 1 A 0.111% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 20‐Jul‐17 18‐Sep‐17 19‐Sep‐17 22‐Jul‐19 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 20‐Jul‐17 18‐Sep‐17 19‐Sep‐17 95% 95% 0% 0.106% 0.106%
932 3 ELECTRICAL 3963‐JALM‐2‐34‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 ELECTRICAL LOAD SCHEDULE 1 A 0.083% 30‐Jun‐17 10‐Jul‐17 15‐Jul‐17 15‐Aug‐17 5‐Sep‐17 15‐Sep‐17 31‐Oct‐18 4‐May‐17 4‐May‐17 4‐May‐17 2‐Jul‐17 10‐Jul‐17 20‐Sep‐17 22‐Jul‐19 4‐May‐17 4‐May‐17 4‐May‐17 2‐Jul‐17 10‐Jul‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
933 3 ELECTRICAL 3963‐JALM‐2‐36‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 ELECTRICAL TIE‐IN SCHEDULE 1 A 0.083% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 25‐Sep‐17 22‐Jul‐19 16‐May‐17 17‐May‐17 17‐May‐17 8‐Jun‐17 16‐Jun‐17 25‐Sep‐17 95% 95% 0% 0.079% 0.079%
934 3 ELECTRICAL 3963‐JALM‐2‐37‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 ELECTRICAL CABLE SCHEDULE 1 A 0.083% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 22‐May‐17 23‐May‐17 25‐May‐17 19‐Jun‐17 27‐Jun‐17 19‐Sep‐17 22‐Jul‐19 22‐May‐17 23‐May‐17 25‐May‐17 19‐Jun‐17 27‐Jun‐17 19‐Sep‐17 95% 95% 0% 0.079% 0.079%
935 3 ELECTRICAL 3963‐JALM‐2‐54‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 31‐MCC‐0001‐415V MOTOR CONTROL CENTER‐SINGLE LINE DIAGR 1 3 0.083% 25‐May‐17 4‐Jun‐17 9‐Jun‐17 10‐Jul‐17 31‐Jul‐17 10‐Aug‐17 31‐Oct‐18 8‐May‐17 10‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 22‐Jul‐19 8‐May‐17 10‐May‐17 11‐May‐17 5‐Jun‐17 13‐Jun‐17 19‐Sep‐17 95% 95% 0% 0.079% 0.079%
936 3 ELECTRICAL 3963‐JALM‐2‐54‐0002 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 31‐DB‐5206B ‐ LIGHTING DISTRIBUTION BOARD SINGLE LINE DIAGR 1 A 0.083% 25‐May‐17 4‐Jun‐17 9‐Jun‐17 10‐Jul‐17 31‐Jul‐17 10‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.079% 0.079%
937 3 ELECTRICAL 3963‐JALM‐2‐54‐0003 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 31‐UPS‐0001 UPS,5KVA SINGLE LINE DIAGRAM‐110V AC INSTRUME 1 A 0.083% 25‐May‐17 4‐Jun‐17 9‐Jun‐17 10‐Jul‐17 31‐Jul‐17 10‐Aug‐17 31‐Oct‐18 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 3‐Aug‐17 23‐Aug‐17 22‐Jul‐19 7‐May‐17 9‐May‐17 10‐May‐17 4‐Jun‐17 3‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.079% 0.079%
938 3 ELECTRICAL 3963‐JALM‐2‐64‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 CABLE ROUTING LAYOUT 1 A 0.111% 17‐Jun‐17 27‐Jun‐17 2‐Jul‐17 2‐Aug‐17 23‐Aug‐17 2‐Sep‐17 31‐Oct‐18 18‐Jun‐17 19‐Jun‐17 20‐Jun‐17 2‐Aug‐17 3‐Aug‐17 8‐Nov‐17 22‐Jul‐19 18‐Jun‐17 19‐Jun‐17 20‐Jun‐17 2‐Aug‐17 3‐Aug‐17 8‐Nov‐17 95% 95% 0% 0.106% 0.106%
939 3 ELECTRICAL 3963‐JALM‐2‐65‐0002 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 EARTHING LAYOUT 1 A 0.083% 17‐Jun‐17 27‐Jun‐17 2‐Jul‐17 2‐Aug‐17 23‐Aug‐17 2‐Sep‐17 31‐Oct‐18 22‐Jun‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 22‐Jul‐19 22‐Jun‐17 3‐Jul‐17 4‐Jul‐17 23‐Jul‐17 20‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
940 3 ELECTRICAL 3963‐JALM‐2‐67‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 LIGHTING LAYOUT 1 A 0.083% 17‐Jun‐17 27‐Jun‐17 2‐Jul‐17 2‐Aug‐17 23‐Aug‐17 2‐Sep‐17 31‐Oct‐18 21‐May‐17 22‐May‐17 24‐May‐17 13‐Jun‐17 21‐Jun‐17 3‐Aug‐17 22‐Jul‐19 21‐May‐17 22‐May‐17 24‐May‐17 13‐Jun‐17 21‐Jun‐17 3‐Aug‐17 95% 95% 0% 0.079% 0.079%
941 3 ELECTRICAL 3963‐JALM‐2‐31‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 MTO FOR ELECTRICAL POWER, CONTROL CABLES & EARTHING CAB 3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 5‐Oct‐17 22‐Jul‐19 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 2‐Aug‐17 3‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.079% 0.079%
942 3 ELECTRICAL 3963‐JALM‐2‐31‐0002 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 MTO FOR ELECTRICAL BULK MATERIALS (LIGHTING, EARTHING, PO 3 A 0.083% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 6‐Aug‐17 11‐Aug‐17 11‐Aug‐17 31‐Oct‐18 8‐Jul‐17 8‐Jul‐17 9‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 22‐Jul‐19 8‐Jul‐17 8‐Jul‐17 9‐Jul‐17 2‐Aug‐17 3‐Aug‐17 26‐Feb‐18 95% 95% 0% 0.079% 0.079%
943 3 ELECTRICAL 3963‐JALM‐2‐17‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 POWER ADEQUACY REPORT 1 A 0.153% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 24‐Sep‐17 22‐Jul‐19 25‐May‐17 12‐Jun‐17 13‐Jun‐17 2‐Aug‐17 3‐Aug‐17 24‐Sep‐17 95% 95% 0% 0.145% 0.145%
944 3 ELECTRICAL 3963‐JALM‐2‐12‐0001 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 LV CABLE SIZING CALCULATION 1 A 0.111% 1‐Apr‐17 11‐Apr‐17 16‐Apr‐17 17‐May‐17 7‐Jun‐17 17‐Jun‐17 31‐Oct‐18 19‐Apr‐17 16‐Apr‐17 19‐Apr‐17 17‐May‐17 25‐May‐17 1‐Oct‐17 22‐Jul‐19 19‐Apr‐17 16‐Apr‐17 19‐Apr‐17 17‐May‐17 25‐May‐17 1‐Oct‐17 95% 95% 0% 0.106% 0.106%
945 3 ELECTRICAL 3963‐JALM‐2‐12‐0002 OT DUKHAN FIELD ‐ JALEHA MAIN UNIT 31 LIGHTING CALCULATION 1 A 0.111% 10‐May‐17 20‐May‐17 25‐May‐17 25‐Jun‐17 16‐Jul‐17 26‐Jul‐17 31‐Oct‐18 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 20‐Jul‐17 18‐Sep‐17 19‐Sep‐17 22‐Jul‐19 14‐Apr‐17 14‐Apr‐17 17‐Apr‐17 20‐Jul‐17 18‐Sep‐17 19‐Sep‐17 95% 95% 0% 0.106% 0.106%
946 3 ELECTRICAL 3963‐DGEN‐2‐00‐0001 OT DRAWING INDEX – ELECTRICAL 1 A 0.139% 18‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 15‐Sep‐17 25‐Sep‐17 31‐Oct‐18 17‐Jul‐17 18‐Jul‐17 19‐Jul‐17 3‐Aug‐17 15‐Aug‐17 15‐Aug‐17 22‐Jul‐19 17‐Jul‐17 18‐Jul‐17 19‐Jul‐17 3‐Aug‐17 15‐Aug‐17 15‐Aug‐17 95% 95% 0% 0.132% 0.132%
947 2 ELECTRICAL 3963‐DGEN‐2‐00‐0010 OT MISCELLANEOUS ‐ ELECTRICAL 0 0.069% 31‐Aug‐17 6‐Sep‐17 7‐Sep‐17 14‐Sep‐17 14‐Sep‐17 21‐Sep‐17 31‐Oct‐18 1‐Feb‐18 6‐Feb‐18 1‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 22‐Jul‐19 1‐Feb‐18 6‐Feb‐18 1‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 95% 95% 0% 0.066% 0.066%
948 2 CIVIL 3963‐DGEN‐1‐14‐0001 OT SPECIFICATION FOR TOPOGRAPHICAL & UG SURVEY WORKS 3 A 0.097% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 16‐Mar‐17 21‐Mar‐17 29‐Mar‐17 24‐Apr‐17 4‐May‐17 4‐May‐17 22‐Jul‐19 16‐Mar‐17 21‐Mar‐17 29‐Mar‐17 24‐Apr‐17 4‐May‐17 4‐May‐17 95% 95% 0% 0.092% 0.092%
949 2 CIVIL 3963‐DGEN‐1‐14‐0002 OT SPECIFICATIONS FOR STRUCTURAL STEEL WORKS 1 A 0.069% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 16‐Mar‐17 27‐Mar‐17 5‐Apr‐17 27‐Apr‐17 27‐Apr‐17 27‐Apr‐17 22‐Jul‐19 16‐Mar‐17 27‐Mar‐17 5‐Apr‐17 27‐Apr‐17 27‐Apr‐17 27‐Apr‐17 95% 95% 0% 0.066% 0.066%
950 2 CIVIL 3963‐DGEN‐1‐14‐0003 OT SPECIFICATIONS FOR CONCRETE WORKS 1 A 0.069% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 21‐Mar‐17 29‐Mar‐17 12‐Apr‐17 4‐May‐17 4‐May‐17 4‐May‐17 22‐Jul‐19 21‐Mar‐17 29‐Mar‐17 12‐Apr‐17 4‐May‐17 4‐May‐17 4‐May‐17 95% 95% 0% 0.066% 0.066%
951 2 CIVIL 3963‐DGEN‐1‐14‐0004 OT SPECIFICATIONS FOR SITE PREPARATION & EARTHWORKS 1 A 0.069% 22‐Mar‐17 1‐Apr‐17 6‐Apr‐17 7‐May‐17 28‐May‐17 7‐Jun‐17 31‐Oct‐18 14‐Mar‐17 29‐Mar‐17 5‐Apr‐17 13‐May‐17 15‐May‐17 18‐May‐17 22‐Jul‐19 14‐Mar‐17 29‐Mar‐17 5‐Apr‐17 13‐May‐17 15‐May‐17 18‐May‐17 95% 95% 0% 0.066% 0.066%
952 2 CIVIL 3963‐DGEN‐1‐14‐0005 OT SPECIFICATIONS FOR ROAD & PAVING WORKS 1 A 0.069% 22‐Mar‐17 1‐Apr‐17 6‐Apr‐17 7‐May‐17 28‐May‐17 7‐Jun‐17 31‐Oct‐18 16‐Mar‐17 29‐Mar‐17 5‐Apr‐17 8‐May‐17 8‐May‐17 8‐May‐17 22‐Jul‐19 16‐Mar‐17 29‐Mar‐17 5‐Apr‐17 8‐May‐17 8‐May‐17 8‐May‐17 95% 95% 0% 0.066% 0.066%
953 2 CIVIL 3963‐DGEN‐1‐29‐0001 OT CIVIL & STRUCTURAL DESIGN CRITERIA 1 A 0.139% 15‐Apr‐17 25‐Apr‐17 30‐Apr‐17 31‐May‐17 21‐Jun‐17 1‐Jul‐17 31‐Oct‐18 21‐Mar‐17 5‐Apr‐17 4‐May‐17 1‐Jun‐17 1‐Jun‐17 1‐Jun‐17 22‐Jul‐19 21‐Mar‐17 5‐Apr‐17 4‐May‐17 1‐Jun‐17 1‐Jun‐17 1‐Jun‐17 95% 95% 0% 0.132% 0.132%
954 2 CIVIL 3963‐DGEN‐1‐87‐0001 OT GENERAL NOTES ‐ CONCRETE WORKS 1 A 0.083% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 21‐Mar‐17 21‐Mar‐17 5‐Apr‐17 3‐May‐17 24‐May‐17 24‐May‐17 22‐Jul‐19 21‐Mar‐17 21‐Mar‐17 5‐Apr‐17 3‐May‐17 24‐May‐17 24‐May‐17 95% 95% 0% 0.079% 0.079%
955 2 CIVIL 3963‐DGEN‐1‐87‐0002 OT GENERAL NOTES ‐ STRUCTURAL STEEL WORKS 1 A 0.083% 15‐Mar‐17 25‐Mar‐17 30‐Mar‐17 30‐Apr‐17 21‐May‐17 31‐May‐17 31‐Oct‐18 16‐Mar‐17 20‐Mar‐17 5‐Apr‐17 2‐May‐17 2‐May‐17 2‐May‐17 22‐Jul‐19 16‐Mar‐17 20‐Mar‐17 5‐Apr‐17 2‐May‐17 2‐May‐17 2‐May‐17 95% 95% 0% 0.079% 0.079%
956 2 CIVIL 3963‐DGEN‐1‐57‐0001 OT TYPICAL DETAILS OF HANDRAIL  1 A 0.083% 12‐Apr‐17 22‐Apr‐17 27‐Apr‐17 28‐May‐17 18‐Jun‐17 28‐Jun‐17 31‐Oct‐18 16‐Mar‐17 29‐Mar‐17 20‐Apr‐17 8‐May‐17 24‐May‐17 24‐May‐17 22‐Jul‐19 16‐Mar‐17 29‐Mar‐17 20‐Apr‐17 8‐May‐17 24‐May‐17 24‐May‐17 95% 95% 0% 0.079% 0.079%
957 2 CIVIL 3963‐DGEN‐1‐57‐0002 OT TYPICAL DETAILS OF STAIRS  1 A 0.083% 5‐Apr‐17 15‐Apr‐17 20‐Apr‐17 21‐May‐17 11‐Jun‐17 21‐Jun‐17 31‐Oct‐18 21‐Mar‐17 23‐Apr‐17 25‐Apr‐17 10‐May‐17 10‐May‐17 10‐May‐17 22‐Jul‐19 21‐Mar‐17 23‐Apr‐17 25‐Apr‐17 10‐May‐17 10‐May‐17 10‐May‐17 95% 95% 0% 0.079% 0.079%
958 2 CIVIL 3963‐DGEN‐1‐57‐0004 OT TYPICAL DETAILS OF FRONT ACCESS LADDER  1 A 0.083% 3‐Apr‐17 15‐Apr‐17 20‐Apr‐17 21‐May‐17 11‐Jun‐17 21‐Jun‐17 31‐Oct‐18 2‐May‐17 4‐May‐17 4‐May‐17 22‐May‐17 24‐May‐17 24‐May‐17 22‐Jul‐19 2‐May‐17 4‐May‐17 4‐May‐17 22‐May‐17 24‐May‐17 24‐May‐17 95% 95% 0% 0.079% 0.079%
959 2 CIVIL 3963‐DGEN‐1‐57‐0006 OT TYPICAL DETAILS OF SIDE ACCESS LADDER  1 A 0.083% 12‐Apr‐17 24‐Apr‐17 29‐Apr‐17 30‐May‐17 20‐Jun‐17 30‐Jun‐17 31‐Oct‐18 4‐May‐17 6‐Jun‐17 6‐Jun‐17 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 22‐Jul‐19 4‐May‐17 6‐Jun‐17 6‐Jun‐17 4‐Jul‐17 5‐Jul‐17 6‐Jul‐17 95% 95% 0% 0.079% 0.079%
960 2 CIVIL 3963‐DGEN‐1‐64‐0001 OT TYPICAL REINFORCED CONCRETE PAVING DETAILS 1 A 0.083% 22‐Mar‐17 1‐Apr‐17 6‐Apr‐17 7‐May‐17 28‐May‐17 7‐Jun‐17 31‐Oct‐18 14‐Mar‐17 2‐Apr‐17 5‐Apr‐17 3‐May‐17 24‐May‐17 24‐May‐17 22‐Jul‐19 14‐Mar‐17 2‐Apr‐17 5‐Apr‐17 3‐May‐17 24‐May‐17 24‐May‐17 95% 95% 0% 0.079% 0.079%
961 2 CIVIL 3963‐DGEN‐1‐57‐0003 OT TYPICAL DETAILS OF GRATING 1 A 0.083% 5‐Apr‐17 15‐Apr‐17 20‐Apr‐17 21‐May‐17 11‐Jun‐17 21‐Jun‐17 31‐Oct‐18 15‐Mar‐17 23‐Apr‐17 25‐Apr‐17 10‐May‐17 10‐May‐17 10‐May‐17 22‐Jul‐19 15‐Mar‐17 23‐Apr‐17 25‐Apr‐17 10‐May‐17 10‐May‐17 10‐May‐17 95% 95% 0% 0.079% 0.079%
962 2 CIVIL 3963‐DGEN‐1‐64‐0002 OT TYPICAL DETAILS FOR ROAD SIGNS & BARRIER 1 A 0.083% 22‐Mar‐17 1‐Apr‐17 6‐Apr‐17 7‐May‐17 28‐May‐17 7‐Jun‐17 31‐Oct‐18 15‐Mar‐17 2‐Apr‐17 5‐Apr‐17 2‐May‐17 2‐May‐17 2‐May‐17 22‐Jul‐19 15‐Mar‐17 2‐Apr‐17 5‐Apr‐17 2‐May‐17 2‐May‐17 2‐May‐17 95% 95% 0% 0.079% 0.079%
963 2 CIVIL 3963‐DGEN‐1‐87‐0003 OT TYPICAL MISC. FOUNDATIONS DETAILS  1 A 0.222% 20‐Jun‐17 30‐Jun‐17 5‐Jul‐17 5‐Aug‐17 26‐Aug‐17 5‐Sep‐17 31‐Oct‐18 22‐Jun‐17 8‐Nov‐17 15‐Nov‐17 4‐Jan‐18 4‐Jan‐18 4‐Jan‐18 22‐Jul‐19 22‐Jun‐17 8‐Nov‐17 15‐Nov‐17 4‐Jan‐18 4‐Jan‐18 4‐Jan‐18 95% 95% 0% 0.211% 0.211%
964 2 CIVIL 3963‐DGEN‐1‐87‐0004 OT TYPICAL STRUCTURAL CONNECTION DETAILS  1 2 0.111% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 18‐May‐17 30‐Sep‐17 2‐Oct‐17 13‐Oct‐17 13‐Oct‐17 13‐Oct‐17 22‐Jul‐19 18‐May‐17 30‐Sep‐17 2‐Oct‐17 13‐Oct‐17 13‐Oct‐17 13‐Oct‐17 95% 95% 0% 0.106% 0.106%
965 2 CIVIL 3963‐DGEN‐1‐87‐0005 OT TYPICAL PIPE SLEEPER FOUNDATION DETAILS  1 A 0.111% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 18‐May‐17 7‐Aug‐17 9‐Aug‐17 20‐Dec‐17 20‐Dec‐17 20‐Dec‐17 22‐Jul‐19 18‐May‐17 7‐Aug‐17 9‐Aug‐17 20‐Dec‐17 20‐Dec‐17 20‐Dec‐17 95% 95% 0% 0.106% 0.106%
966 2 CIVIL 3963‐DGEN‐1‐87‐0006 OT TYPICAL PIPE SUPPORT FOUNDATION DETAILS  1 A 0.111% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 18‐May‐17 12‐Aug‐17 14‐Aug‐17 3‐Sep‐17 20‐Sep‐17 16‐Nov‐17 22‐Jul‐19 18‐May‐17 12‐Aug‐17 14‐Aug‐17 3‐Sep‐17 20‐Sep‐17 16‐Nov‐17 95% 95% 0% 0.106% 0.106%
967 2 CIVIL 3963‐DGEN‐1‐58‐0001 OT TYPICAL PIPE SUPPORT STRUCTURAL DETAILS  1 B 0.111% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 18‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Dec‐17 20‐Dec‐17 20‐Dec‐17 22‐Jul‐19 18‐May‐17 7‐Aug‐17 9‐Aug‐17 10‐Dec‐17 20‐Dec‐17 20‐Dec‐17 95% 95% 0% 0.106% 0.106%
968 2 CIVIL 3963‐DGEN‐1‐87‐0008 OT TYPICAL ROAD CROSS SECTION DETAILS 1 1 0.083% 12‐Apr‐17 22‐Apr‐17 27‐Apr‐17 28‐May‐17 18‐Jun‐17 28‐Jun‐17 31‐Oct‐18 22‐Mar‐17 4‐May‐17 4‐May‐17 15‐Oct‐17 15‐Oct‐17 15‐Oct‐17 22‐Jul‐19 22‐Mar‐17 4‐May‐17 4‐May‐17 15‐Oct‐17 15‐Oct‐17 15‐Oct‐17 95% 95% 0% 0.079% 0.079%
969 2 CIVIL 3963‐DGEN‐1‐87‐0009 OT TYPICAL SOAKAWAY PIT DETAILS 1 0 0.000% 12‐Apr‐17 22‐Apr‐17 27‐Apr‐17 28‐May‐17 18‐Jun‐17 28‐Jun‐17 31‐Oct‐18 28‐Jan‐18 30‐Jan‐18 31‐Jan‐18 22‐Mar‐18 28‐Mar‐18 28‐Mar‐18 22‐Jul‐19 28‐Jan‐18 30‐Jan‐18 31‐Jan‐18 22‐Mar‐18 28‐Mar‐18 28‐Mar‐18 95% 95% 0% 0.000% 0.000%
970 2 CIVIL 3963‐KAHN‐1‐64‐0001 OT KHATIYAH NORTH DEGASSING STATION  SITE GRADING LAYOUT & DETAILS 1 A 0.097% 19‐Apr‐17 29‐Apr‐17 4‐May‐17 4‐Jun‐17 25‐Jun‐17 5‐Jul‐17 31‐Oct‐18 21‐Mar‐17 13‐Jun‐17 14‐Jun‐17 8‐Nov‐17 8‐Nov‐17 7‐Feb‐18 22‐Jul‐19 21‐Mar‐17 13‐Jun‐17 14‐Jun‐17 8‐Nov‐17 8‐Nov‐17 7‐Feb‐18 95% 95% 0% 0.092% 0.092%
971 2 CIVIL 3963‐KAHN‐1‐50‐0001 OT KHATIYAH NORTH DEGASSING STATION  GENERAL ARRANGEMENT CIVIL 1 A 0.097% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 16‐Sep‐17 17‐Sep‐17 31‐Oct‐17 31‐Oct‐17 21‐Feb‐18 22‐Jul‐19 1‐Jun‐17 16‐Sep‐17 17‐Sep‐17 31‐Oct‐17 31‐Oct‐17 21‐Feb‐18 95% 95% 0% 0.092% 0.092%
972 2 CIVIL 3963‐KAHN‐1‐50‐0002 OT KHATIYAH NORTH DEGASSING STATION  DRAINAGE LAYOUT & DETAILS 1 B 0.097% 19‐Apr‐17 29‐Apr‐17 4‐May‐17 4‐Jun‐17 25‐Jun‐17 5‐Jul‐17 31‐Oct‐18 22‐Mar‐17 13‐Jun‐17 14‐Jun‐17 5‐Nov‐17 5‐Nov‐17 4‐Feb‐18 22‐Jul‐19 22‐Mar‐17 13‐Jun‐17 14‐Jun‐17 5‐Nov‐17 5‐Nov‐17 4‐Feb‐18 95% 95% 0% 0.092% 0.092%
973 2 CIVIL 3963‐KAHN‐1‐66‐0002 OT KHATIYAH NORTH DEGASSING STATION  METERING SKID FOUNDATION GA & RC DETAILS  1 A 0.139% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 13‐Sep‐17 14‐Sep‐17 6‐Dec‐17 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 25‐May‐17 13‐Sep‐17 14‐Sep‐17 6‐Dec‐17 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.132% 0.132%
974 2 CIVIL 3963‐KAHN‐1‐66‐0003 OT KHATIYAH NORTH DEGASSING STATION  TEST SEPARATOR PLATFORM FOUNDATION GA & RC DETAILS  1 A 0.139% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 18‐Sep‐17 19‐Sep‐17 25‐Oct‐17 25‐Oct‐17 13‐Feb‐18 22‐Jul‐19 25‐May‐17 18‐Sep‐17 19‐Sep‐17 25‐Oct‐17 25‐Oct‐17 13‐Feb‐18 95% 95% 0% 0.132% 0.132%
975 2 CIVIL 3963‐KAHN‐1‐51‐0001 OT KHATIYAH NORTH DEGASSING STATION  TEST SEPARATOR PLATFORM STRUCTURAL GA & DETAILS  1 A 0.278% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 13‐Sep‐17 14‐Sep‐17 13‐Dec‐17 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 25‐May‐17 13‐Sep‐17 14‐Sep‐17 13‐Dec‐17 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.264% 0.264%
976 2 CIVIL 3963‐KAHN‐1‐51‐0002 OT KHATIYAH NORTH DEGASSING STATION  METERING SKID PLATFORM STRUCTURAL GA & DETAILS  1 A 0.139% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 23‐Sep‐17 25‐Sep‐17 26‐Oct‐17 26‐Oct‐17 30‐Jan‐18 22‐Jul‐19 25‐May‐17 23‐Sep‐17 25‐Sep‐17 26‐Oct‐17 26‐Oct‐17 30‐Jan‐18 95% 95% 0% 0.132% 0.132%
977 2 CIVIL 3963‐KAHN‐1‐50‐0003 OT KHATIYAH NORTH DEGASSING STATION FOUNDATION LOCATION PLAN 1 A 0.278% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 1‐Oct‐17 3‐Oct‐17 14‐Nov‐17 7‐Mar‐18 7‐Mar‐18 22‐Jul‐19 25‐May‐17 1‐Oct‐17 3‐Oct‐17 14‐Nov‐17 7‐Mar‐18 7‐Mar‐18 95% 95% 0% 0.264% 0.264%
978 2 CIVIL 3963‐KAHM‐1‐64‐0001 OT KHATIYAH MAIN DEGASSING STATION  PAVING LAYOUT & DETAILS 1 A 0.069% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 5‐Apr‐17 26‐Jun‐17 28‐Jun‐17 14‐Nov‐17 12‐Feb‐18 12‐Feb‐18 22‐Jul‐19 5‐Apr‐17 26‐Jun‐17 28‐Jun‐17 14‐Nov‐17 12‐Feb‐18 12‐Feb‐18 95% 95% 0% 0.066% 0.066%
979 2 CIVIL 3963‐KAHM‐1‐50‐0001 OT KHATIYAH MAIN DEGASSING STATION  GENERAL ARRANGEMENT CIVIL 1 A 0.069% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 24‐Sep‐17 26‐Sep‐17 5‐Nov‐17 5‐Nov‐17 22‐Feb‐18 22‐Jul‐19 1‐Jun‐17 24‐Sep‐17 26‐Sep‐17 5‐Nov‐17 5‐Nov‐17 22‐Feb‐18 95% 95% 0% 0.066% 0.066%
980 2 CIVIL 3963‐KAHM‐1‐50‐0002 OT KHATIYAH MAIN DEGASSING STATION  DRAINAGE LAYOUT & DETAILS 1 B 0.069% 28‐Apr‐17 8‐May‐17 13‐May‐17 13‐Jun‐17 4‐Jul‐17 14‐Jul‐17 31‐Oct‐18 5‐Apr‐17 25‐Jun‐17 27‐Jun‐17 15‐Nov‐17 12‐Feb‐18 12‐Feb‐18 22‐Jul‐19 5‐Apr‐17 25‐Jun‐17 27‐Jun‐17 15‐Nov‐17 12‐Feb‐18 12‐Feb‐18 95% 95% 0% 0.066% 0.066%
981 2 CIVIL 3963‐KAHM‐1‐66‐0002 OT KHATIYAH MAIN DEGASSING STATION  METERING SKID FOUNDATION GA & RC DETAILS 1 A 0.139% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 18‐Sep‐17 20‐Sep‐17 2‐Nov‐17 2‐Nov‐17 7‐Feb‐18 22‐Jul‐19 25‐May‐17 18‐Sep‐17 20‐Sep‐17 2‐Nov‐17 2‐Nov‐17 7‐Feb‐18 95% 95% 0% 0.132% 0.132%
982 2 CIVIL 3963‐KAHM‐1‐66‐0003 OT KHATIYAH MAIN DEGASSING STATION  TEST SEPARATOR PLATFORM FOUNDATION GA & RC DETAILS  1 A 0.139% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 26‐Sep‐17 28‐Sep‐17 5‐Dec‐17 13‐Feb‐18 13‐Feb‐18 22‐Jul‐19 1‐Jun‐17 26‐Sep‐17 28‐Sep‐17 5‐Dec‐17 13‐Feb‐18 13‐Feb‐18 95% 95% 0% 0.132% 0.132%
983 2 CIVIL 3963‐KAHM‐1‐51‐0001 OT KHATIYAH MAIN DEGASSING STATION  TEST SEPARATOR PLATFORM STRUCTURAL GA & DETAILS  1 A 0.278% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 30‐Sep‐17 2‐Oct‐17 15‐Nov‐17 8‐Feb‐18 8‐Feb‐18 22‐Jul‐19 1‐Jun‐17 30‐Sep‐17 2‐Oct‐17 15‐Nov‐17 8‐Feb‐18 8‐Feb‐18 95% 95% 0% 0.264% 0.264%
984 2 CIVIL 3963‐KAHM‐1‐51‐0002 OT KHATIYAH MAIN DEGASSING STATION  METERING SKID PLATFORM STRUCTURAL GA & DETAILS  1 A 0.139% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 29‐Sep‐17 1‐Oct‐17 2‐Nov‐17 2‐Nov‐17 4‐Feb‐18 22‐Jul‐19 1‐Jun‐17 29‐Sep‐17 1‐Oct‐17 2‐Nov‐17 2‐Nov‐17 4‐Feb‐18 95% 95% 0% 0.132% 0.132%
985 2 CIVIL 3963‐KAHM‐1‐50‐0003 OT KHATIYAH MAIN DEGASSING STATION FOUNDATION LOCATION PLAN 1 A 0.278% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 3‐Oct‐17 5‐Oct‐17 15‐Apr‐18 15‐Apr‐18 15‐Apr‐18 22‐Jul‐19 25‐May‐17 3‐Oct‐17 5‐Oct‐17 15‐Apr‐18 15‐Apr‐18 15‐Apr‐18 95% 95% 0% 0.264% 0.264%
986 2 CIVIL 3963‐KAHS‐1‐64‐0001 OT KHATIYAH SOUTH DEGASSING STATION  PAVING LAYOUT & DETAILS 1 A 0.069% 5‐May‐17 15‐May‐17 20‐May‐17 20‐Jun‐17 11‐Jul‐17 21‐Jul‐17 31‐Oct‐18 22‐Mar‐17 18‐Nov‐17 20‐Nov‐17 18‐Jan‐18 20‐Jan‐18 20‐Jan‐18 22‐Jul‐19 22‐Mar‐17 18‐Nov‐17 20‐Nov‐17 18‐Jan‐18 20‐Jan‐18 20‐Jan‐18 95% 95% 0% 0.066% 0.066%
987 2 CIVIL 3963‐KAHS‐1‐50‐0001 OT KHATIYAH SOUTH DEGASSING STATION  GENERAL ARRANGEMENT CIVIL 1 A 0.069% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 13‐Jul‐17 24‐Sep‐17 26‐Sep‐17 5‐Nov‐17 5‐Nov‐17 25‐Feb‐18 22‐Jul‐19 13‐Jul‐17 24‐Sep‐17 26‐Sep‐17 5‐Nov‐17 5‐Nov‐17 25‐Feb‐18 95% 95% 0% 0.066% 0.066%
988 2 CIVIL 3963‐KAHS‐1‐50‐0002 OT KHATIYAH SOUTH DEGASSING STATION  DRAINAGE LAYOUT & DETAILS 1 B 0.139% 5‐May‐17 15‐May‐17 20‐May‐17 20‐Jun‐17 11‐Jul‐17 21‐Jul‐17 31‐Oct‐18 22‐Mar‐17 25‐Sep‐17 27‐Sep‐17 16‐Nov‐17 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 22‐Mar‐17 25‐Sep‐17 27‐Sep‐17 16‐Nov‐17 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.132% 0.132%
989 2 CIVIL 3963‐KAHS‐1‐66‐0002 OT KHATIYAH SOUTH DEGASSING STATION  METERING SKID FOUNDATION GA & RC DETAILS  1 A 0.139% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 13‐Jul‐17 24‐Sep‐17 26‐Sep‐17 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 13‐Jul‐17 24‐Sep‐17 26‐Sep‐17 5‐Feb‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.132% 0.132%
990 2 CIVIL 3963‐KAHS‐1‐66‐0003 OT KHATIYAH SOUTH DEGASSING STATION  TEST SEPARATOR PLATFORM FOUNDATION GA & RC DETAILS  1 B 0.069% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 13‐Jul‐17 29‐Sep‐17 1‐Oct‐17 6‐Dec‐17 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 13‐Jul‐17 29‐Sep‐17 1‐Oct‐17 6‐Dec‐17 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.066% 0.066%
991 2 CIVIL 3963‐KAHS‐1‐51‐0001 OT KHATIYAH SOUTH DEGASSING STATION  TEST SEPARATOR PLATFORM STRUCTURAL GA & DETAILS  1 B 0.278% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 1‐Oct‐17 3‐Oct‐17 16‐Nov‐17 12‐Feb‐18 12‐Feb‐18 22‐Jul‐19 8‐Jul‐17 1‐Oct‐17 3‐Oct‐17 16‐Nov‐17 12‐Feb‐18 12‐Feb‐18 95% 95% 0% 0.264% 0.264%

Page 8 of 13
Page 79 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
992 2 CIVIL 3963‐KAHS‐1‐51‐0002 OT KHATIYAH SOUTH DEGASSING STATION  METERING SKID PLATFORM STRUCTURAL GA & DETAILS  1 A 0.139% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 3‐Oct‐17 5‐Oct‐17 6‐Dec‐17 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 8‐Jul‐17 3‐Oct‐17 5‐Oct‐17 6‐Dec‐17 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.132% 0.132%
993 2 CIVIL 3963‐KAHS‐1‐50‐0003 OT KHATIYAH SOUTH DEGASSING STATION FOUNDATION LOCATION PLAN 1 A 0.278% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 11‐Oct‐17 12‐Oct‐17 11‐Jan‐18 12‐Mar‐18 12‐Mar‐18 22‐Jul‐19 8‐Jul‐17 11‐Oct‐17 12‐Oct‐17 11‐Jan‐18 12‐Mar‐18 12‐Mar‐18 95% 95% 0% 0.264% 0.264%
994 2 CIVIL 3963‐FAHN‐1‐64‐0001 OT FAHAHIL NORTH DEGASSING STATION  PAVING LAYOUT & DETAILS 1 A 0.069% 12‐May‐17 22‐May‐17 27‐May‐17 27‐Jun‐17 18‐Jul‐17 28‐Jul‐17 31‐Oct‐18 25‐May‐17 18‐Sep‐17 19‐Sep‐17 7‐Nov‐17 7‐Nov‐17 18‐Feb‐18 22‐Jul‐19 25‐May‐17 18‐Sep‐17 19‐Sep‐17 7‐Nov‐17 7‐Nov‐17 18‐Feb‐18 95% 95% 0% 0.066% 0.066%
995 2 CIVIL 3963‐FAHN‐1‐50‐0001 OT FAHAHIL NORTH DEGASSING STATION  GENERAL ARRANGEMENT CIVIL 1 A 0.069% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 22‐Jun‐17 10‐Oct‐17 12‐Oct‐17 6‐Nov‐17 6‐Nov‐17 20‐Nov‐17 22‐Jul‐19 22‐Jun‐17 10‐Oct‐17 12‐Oct‐17 6‐Nov‐17 6‐Nov‐17 20‐Nov‐17 95% 95% 0% 0.066% 0.066%
996 2 CIVIL 3963‐FAHN‐1‐50‐0002 OT FAHAHIL NORTH DEGASSING STATION  DRAINAGE LAYOUT & DETAILS 1 A 0.069% 12‐May‐17 22‐May‐17 27‐May‐17 27‐Jun‐17 18‐Jul‐17 28‐Jul‐17 31‐Oct‐18 25‐May‐17 18‐Sep‐17 19‐Sep‐17 13‐Nov‐17 5‐Mar‐18 5‐Mar‐18 22‐Jul‐19 25‐May‐17 18‐Sep‐17 19‐Sep‐17 13‐Nov‐17 5‐Mar‐18 5‐Mar‐18 95% 95% 0% 0.066% 0.066%
997 2 CIVIL 3963‐FAHN‐1‐66‐0001 OT FAHAHIL NORTH DEGASSING STATION  TEST SEPARATOR FOUNDATION GA & RC DETAILS  1 A 0.139% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 22‐Jun‐17 28‐Aug‐17 29‐Aug‐17 1‐Nov‐17 1‐Nov‐17 29‐Jan‐18 22‐Jul‐19 22‐Jun‐17 28‐Aug‐17 29‐Aug‐17 1‐Nov‐17 1‐Nov‐17 29‐Jan‐18 95% 95% 0% 0.132% 0.132%
998 2 CIVIL 3963‐FAHN‐1‐66‐0002 OT FAHAHIL NORTH DEGASSING STATION  METERING SKID FOUNDATION GA & RC DETAILS  1 A 0.139% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 22‐Jun‐17 3‐Oct‐17 5‐Oct‐17 11‐Dec‐17 15‐Feb‐18 15‐Feb‐18 22‐Jul‐19 22‐Jun‐17 3‐Oct‐17 5‐Oct‐17 11‐Dec‐17 15‐Feb‐18 15‐Feb‐18 95% 95% 0% 0.132% 0.132%
999 2 CIVIL 3963‐FAHN‐1‐66‐0003 OT FAHAHIL NORTH DEGASSING STATION  TEST SEPARATOR PLATFORM FOUNDATION GA & RC DETAILS  1 A 0.111% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 22‐Jun‐17 21‐Aug‐17 24‐Aug‐17 7‐Nov‐17 7‐Nov‐17 1‐Mar‐18 22‐Jul‐19 22‐Jun‐17 21‐Aug‐17 24‐Aug‐17 7‐Nov‐17 7‐Nov‐17 1‐Mar‐18 95% 95% 0% 0.106% 0.106%
1000 2 CIVIL 3963‐FAHN‐1‐51‐0001 OT FAHAHIL NORTH DEGASSING STATION  TEST SEPARATOR PLATFORM STRUCTURAL GA & DETAILS  1 A 0.111% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 21‐Jun‐17 12‐Aug‐17 14‐Aug‐17 6‐Sep‐17 20‐Sep‐17 1‐Mar‐18 22‐Jul‐19 21‐Jun‐17 12‐Aug‐17 14‐Aug‐17 6‐Sep‐17 20‐Sep‐17 1‐Mar‐18 95% 95% 0% 0.106% 0.106%
1001 2 CIVIL 3963‐FAHN‐1‐51‐0002 OT FAHAHIL NORTH DEGASSING STATION  METERING SKID PLATFORM STRUCTURAL GA & DETAILS  1 A 0.333% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 21‐Jun‐17 18‐Oct‐17 19‐Oct‐17 27‐Feb‐18 19‐Mar‐18 19‐Mar‐18 22‐Jul‐19 21‐Jun‐17 18‐Oct‐17 19‐Oct‐17 27‐Feb‐18 19‐Mar‐18 19‐Mar‐18 95% 95% 0% 0.317% 0.317%
1002 2 CIVIL 3963‐FAHN‐1‐50‐0003 OT FAHAHIL NORTH DEGASSING STATION FOUNDATION LOCATION PLAN 1 A 0.278% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 21‐Jun‐17 28‐Oct‐17 29‐Oct‐17 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 22‐Jul‐19 21‐Jun‐17 28‐Oct‐17 29‐Oct‐17 18‐Mar‐18 18‐Mar‐18 18‐Mar‐18 95% 95% 0% 0.264% 0.264%
1003 2 CIVIL 3963‐FAHM‐1‐64‐0001 OT FAHAHIL MAIN DEGASSING STATION  PAVING LAYOUT & DETAILS 1 A 0.069% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 3‐Jul‐17 4‐Jul‐17 6‐Nov‐17 6‐Nov‐17 21‐Feb‐18 22‐Jul‐19 25‐May‐17 3‐Jul‐17 4‐Jul‐17 6‐Nov‐17 6‐Nov‐17 21‐Feb‐18 95% 95% 0% 0.066% 0.066%
1004 2 CIVIL 3963‐FAHM‐1‐50‐0001 OT FAHAHIL MAIN DEGASSING STATION  GENERAL ARRANGEMENT CIVIL 1 A 0.069% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 5‐Jul‐17 10‐Oct‐17 14‐Dec‐17 8‐Apr‐18 25‐Apr‐18 25‐Apr‐18 22‐Jul‐19 5‐Jul‐17 10‐Oct‐17 14‐Dec‐17 8‐Apr‐18 25‐Apr‐18 25‐Apr‐18 95% 95% 0% 0.066% 0.066%
1005 2 CIVIL 3963‐FAHM‐1‐50‐0002 OT FAHAHIL MAIN DEGASSING STATION  DRAINAGE LAYOUT & DETAILS 1 A 0.069% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 3‐Jul‐17 4‐Jul‐17 5‐Mar‐18 5‐Mar‐18 5‐Mar‐18 22‐Jul‐19 25‐May‐17 3‐Jul‐17 4‐Jul‐17 5‐Mar‐18 5‐Mar‐18 5‐Mar‐18 95% 95% 0% 0.066% 0.066%
1006 2 CIVIL 3963‐FAHM‐1‐66‐0001 OT FAHAHIL MAIN DEGASSING STATION  TEST SEPARATOR FOUNDATION GA & RC DETAILS  1 A 0.139% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 3‐Jul‐17 25‐Sep‐17 27‐Sep‐17 1‐Nov‐17 1‐Nov‐17 29‐Jan‐18 22‐Jul‐19 3‐Jul‐17 25‐Sep‐17 27‐Sep‐17 1‐Nov‐17 1‐Nov‐17 29‐Jan‐18 95% 95% 0% 0.132% 0.132%
1007 2 CIVIL 3963‐FAHM‐1‐66‐0002 OT FAHAHIL MAIN DEGASSING STATION  METERING SKID FOUNDATION GA & RC DETAILS  1 A 0.139% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 3‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 15‐Feb‐18 22‐Jul‐19 3‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 15‐Feb‐18 95% 95% 0% 0.132% 0.132%
1008 2 CIVIL 3963‐FAHM‐1‐66‐0003 OT FAHAHIL MAIN DEGASSING STATION  TEST SEPARATOR PLATFORM FOUNDATION GA & RC DETAILS  1 A 0.139% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 3‐Jul‐17 15‐Oct‐17 16‐Oct‐17 7‐Dec‐17 5‐Apr‐18 5‐Apr‐18 22‐Jul‐19 3‐Jul‐17 15‐Oct‐17 16‐Oct‐17 7‐Dec‐17 5‐Apr‐18 5‐Apr‐18 95% 95% 0% 0.132% 0.132%
1009 2 CIVIL 3963‐FAHM‐1‐51‐0001 OT FAHAHIL MAIN DEGASSING STATION  TEST SEPARATOR PLATFORM STRUCTURAL GA & DETAILS 1 A 0.139% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 4‐Jul‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 29‐Apr‐18 29‐Apr‐18 22‐Jul‐19 4‐Jul‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 29‐Apr‐18 29‐Apr‐18 95% 95% 0% 0.132% 0.132%
1010 2 CIVIL 3963‐FAHM‐1‐51‐0002 OT FAHAHIL MAIN DEGASSING STATION  METERING SKID PLATFORM STRUCTURAL GA & DETAILS  1 A 0.278% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 4‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 26‐Feb‐18 22‐Jul‐19 4‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 26‐Feb‐18 95% 95% 0% 0.264% 0.264%
1011 2 CIVIL 3963‐FAHM‐1‐50‐0003 OT FAHAHIL MAIN DEGASSING STATION FOUNDATION LOCATION PLAN 1 0 0.278% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 4‐Jul‐17 22‐Oct‐17 24‐Oct‐17 25‐Mar‐18 2‐Apr‐18 2‐Apr‐18 22‐Jul‐19 4‐Jul‐17 22‐Oct‐17 24‐Oct‐17 25‐Mar‐18 2‐Apr‐18 2‐Apr‐18 95% 95% 0% 0.264% 0.264%
1012 2 CIVIL 3963‐FAHS‐1‐64‐0001 OT FAHAHIL SOUTH DEGASSING STATION  SITE GRADING LAYOUT & DETAILS 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 10‐Oct‐17 12‐Oct‐17 13‐Nov‐17 5‐Apr‐18 5‐Apr‐18 22‐Jul‐19 25‐May‐17 10‐Oct‐17 12‐Oct‐17 13‐Nov‐17 5‐Apr‐18 5‐Apr‐18 95% 95% 0% 0.066% 0.066%
1013 2 CIVIL 3963‐FAHS‐1‐50‐0001 OT FAHAHIL SOUTH DEGASSING STATION  GENERAL ARRANGEMENT CIVIL 1 1 0.069% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 11‐Jul‐17 6‐Oct‐17 20‐Nov‐17 3‐Apr‐18 3‐Apr‐18 3‐Apr‐18 22‐Jul‐19 11‐Jul‐17 6‐Oct‐17 20‐Nov‐17 3‐Apr‐18 3‐Apr‐18 3‐Apr‐18 95% 95% 0% 0.066% 0.066%
1014 2 CIVIL 3963‐FAHS‐1‐50‐0002 OT FAHAHIL SOUTH DEGASSING STATION  DRAINAGE LAYOUT & DETAILS 1 1 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 3‐Oct‐17 5‐Oct‐17 11‐Apr‐18 11‐Apr‐18 11‐Apr‐18 22‐Jul‐19 25‐May‐17 3‐Oct‐17 5‐Oct‐17 11‐Apr‐18 11‐Apr‐18 11‐Apr‐18 95% 95% 0% 0.066% 0.066%
1015 2 CIVIL 3963‐FAHS‐1‐66‐0001 OT FAHAHIL SOUTH DEGASSING STATION  TEST SEPARATOR FOUNDATION GA & RC DETAILS  1 A 0.139% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 10‐Oct‐17 12‐Oct‐17 1‐Nov‐17 1‐Nov‐17 29‐Jan‐18 22‐Jul‐19 8‐Jul‐17 10‐Oct‐17 12‐Oct‐17 1‐Nov‐17 1‐Nov‐17 29‐Jan‐18 95% 95% 0% 0.132% 0.132%
1016 2 CIVIL 3963‐FAHS‐1‐66‐0002 OT FAHAHIL SOUTH DEGASSING STATION  METERING SKID FOUNDATION GA & RC DETAILS 1 A 0.139% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 15‐Feb‐18 22‐Jul‐19 8‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 15‐Feb‐18 95% 95% 0% 0.132% 0.132%
1017 2 CIVIL 3963‐FAHS‐1‐66‐0003 OT FAHAHIL SOUTH DEGASSING STATION  TEST SEPARATOR PLATFORM FOUNDATION GA & RC DETAILS 1 A 0.139% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 23‐Oct‐17 25‐Oct‐17 19‐Nov‐17 14‐Mar‐18 14‐Mar‐18 22‐Jul‐19 8‐Jul‐17 23‐Oct‐17 25‐Oct‐17 19‐Nov‐17 14‐Mar‐18 14‐Mar‐18 95% 95% 0% 0.132% 0.132%
1018 2 CIVIL 3963‐FAHS‐1‐51‐0001 OT FAHAHIL SOUTH DEGASSING STATION  TEST SEPARATOR PLATFORM STRUCTURAL GA & DETAILS 1 A 0.278% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 11‐Jul‐17 25‐Oct‐17 26‐Oct‐17 6‐Dec‐17 13‐Mar‐18 13‐Mar‐18 22‐Jul‐19 11‐Jul‐17 25‐Oct‐17 26‐Oct‐17 6‐Dec‐17 13‐Mar‐18 13‐Mar‐18 95% 95% 0% 0.264% 0.264%
1019 2 CIVIL 3963‐FAHS‐1‐51‐0002 OT FAHAHIL SOUTH DEGASSING STATION  METERING SKID PLATFORM STRUCTURAL GA & DETAILS  1 A 0.139% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 1‐Mar‐18 22‐Jul‐19 8‐Jul‐17 10‐Oct‐17 12‐Oct‐17 2‐Nov‐17 2‐Nov‐17 1‐Mar‐18 95% 95% 0% 0.132% 0.132%
1020 2 CIVIL 3963‐FAHS‐1‐50‐0003 OT FAHAHIL SOUTH DEGASSING STATION FOUNDATION LOCATION PLAN 1 A 0.278% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 20‐Oct‐17 22‐Oct‐17 1‐Apr‐18 23‐Apr‐18 23‐Apr‐18 22‐Jul‐19 8‐Jul‐17 20‐Oct‐17 22‐Oct‐17 1‐Apr‐18 23‐Apr‐18 23‐Apr‐18 95% 95% 0% 0.264% 0.264%
1021 2 CIVIL 3963‐JALM‐1‐64‐0002 OT JALEHA MAIN DEGASSING STATION  ROAD & PAVING LAYOUT & DETAILS 1 0 0.167% 7‐Jun‐17 17‐Jun‐17 22‐Jun‐17 23‐Jul‐17 13‐Aug‐17 23‐Aug‐17 31‐Oct‐18 7‐Jun‐17 1‐Oct‐17 3‐Oct‐17 4‐May‐18 24‐Sep‐18 24‐Sep‐18 22‐Jul‐19 7‐Jun‐17 1‐Oct‐17 3‐Oct‐17 4‐May‐18 24‐Sep‐18 24‐Sep‐18 95% 95% 0% 0.159% 0.159%
1022 2 CIVIL 3963‐JALM‐1‐50‐0001 OT JALEHA MAIN DEGASSING STATION GENERAL ARRANGEMENT CIVIL 1 1 0.097% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 3‐Oct‐17 5‐Oct‐17 24‐Dec‐17 27‐May‐18 27‐May‐18 22‐Jul‐19 8‐Jul‐17 3‐Oct‐17 5‐Oct‐17 24‐Dec‐17 27‐May‐18 27‐May‐18 95% 95% 0% 0.092% 0.092%
1023 2 CIVIL 3963‐JALM‐1‐66‐0001 OT JALEHA MAIN DEGASSING STATION  TEST SEPARATOR FOUNDATION GA & RC DETAILS  1 A 0.139% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 27‐Dec‐17 11‐Mar‐18 11‐Mar‐18 22‐Jul‐19 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 27‐Dec‐17 11‐Mar‐18 11‐Mar‐18 95% 95% 0% 0.132% 0.132%
1024 2 CIVIL 3963‐JALM‐1‐66‐0003 OT JALEHA MAIN DEGASSING STATION  TEST SEPARATOR PLATFORM FOUNDATION GA & RC DETAILS  1 0 0.139% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 17‐Oct‐17 19‐Oct‐17 11‐Apr‐18 11‐Apr‐18 11‐Apr‐18 22‐Jul‐19 13‐Jul‐17 17‐Oct‐17 19‐Oct‐17 11‐Apr‐18 11‐Apr‐18 11‐Apr‐18 95% 95% 0% 0.132% 0.132%
1025 2 CIVIL 3963‐JALM‐1‐51‐0001 OT JALEHA MAIN DEGASSING STATION  TEST SEPARATOR PLATFORM STRUCTURAL GA & DETAILS 1 1 0.10% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 11‐Jul‐17 8‐Nov‐17 15‐Nov‐17 29‐Nov‐17 1‐May‐18 1‐May‐18 22‐Jul‐19 11‐Jul‐17 8‐Nov‐17 15‐Nov‐17 29‐Nov‐17 1‐May‐18 1‐May‐18 95% 95% 0% 0.092% 0.092%
1026 2 CIVIL 3963‐JALM‐1‐51‐0002 OT JALEHA MAIN DEGASSING STATION  METERING SKID PLATFORM STRUCTURAL GA & DETAILS 1 0 0.139% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 18‐Oct‐17 19‐Oct‐17 20‐Mar‐18 29‐Apr‐18 29‐Apr‐18 22‐Jul‐19 8‐Jul‐17 18‐Oct‐17 19‐Oct‐17 20‐Mar‐18 29‐Apr‐18 29‐Apr‐18 95% 95% 0% 0.132% 0.132%
1027 2 CIVIL 3963‐JALM‐1‐50‐0003 OT JALEHA MAIN DEGASSING STATION FOUNDATION LOCATION PLAN 1 0 0.097% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 8‐Jul‐17 6‐Nov‐17 8‐Nov‐17 27‐May‐18 28‐Jun‐18 28‐Jun‐18 22‐Jul‐19 8‐Jul‐17 6‐Nov‐17 8‐Nov‐17 27‐May‐18 28‐Jun‐18 28‐Jun‐18 95% 95% 0% 0.092% 0.092%
1028 2 CIVIL DEM‐3963‐KAHN‐1‐50‐0001 DEM KHATIYAH NORTH DEGASSING STATION EXISTING TEST SEPERATOR ‐STEEL WORK DEMOLITION DRAWING 3 A 0.083% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 19‐Jul‐17 20‐Jul‐17 13‐Aug‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 1‐Jun‐17 19‐Jul‐17 20‐Jul‐17 13‐Aug‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.079% 0.079%
1029 2 CIVIL DEM‐3963‐KAHN‐1‐50‐0002 DEM KHATIYAH NORTH DEGASSING STATION EXISTING TEST SEPERATOR ‐CONCRETE WORK DEMOLITION DRAW 3 A 0.097% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 19‐Jul‐17 20‐Jul‐17 13‐Aug‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 31‐May‐17 19‐Jul‐17 20‐Jul‐17 13‐Aug‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.092% 0.092%
1030 2 CIVIL DEM‐3963‐KAHM‐1‐50‐0001 DEM KHATIYAH MAIN DEGASSING STATION  EXISTING TEST SEPERATOR ‐STEEL WORK DEMOLITION DRAWING 3 A 0.083% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 31‐May‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.079% 0.079%
1031 2 CIVIL DEM‐3963‐KAHM‐1‐50‐0002 DEM KHATIYAH MAIN DEGASSING STATION  EXISTING TEST SEPERATOR ‐CONCRETE WORK DEMOLITION DRAW 3 A 0.083% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 31‐May‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.079% 0.079%
1032 2 CIVIL DEM‐3963‐KAHS‐1‐50‐0001 DEM KHATIYAH SOUTH DEGASSING STATION  EXISTING TEST SEPERATOR ‐STEEL WORK DEMOLITION DRAWING 3 A 0.083% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 19‐Jul‐17 20‐Jul‐17 17‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 31‐May‐17 19‐Jul‐17 20‐Jul‐17 17‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.079% 0.079%
1033 2 CIVIL DEM‐3963‐KAHS‐1‐50‐0002 DEM KHATIYAH SOUTH DEGASSING STATION  EXISTING TEST SEPERATOR ‐CONCRETE WORK DEMOLITION DRAW 3 A 0.083% 31‐May‐17 10‐Jun‐17 15‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 31‐May‐17 19‐Jul‐17 20‐Jul‐17 17‐Aug‐17 27‐Aug‐17 29‐Aug‐17 22‐Jul‐19 31‐May‐17 19‐Jul‐17 20‐Jul‐17 17‐Aug‐17 27‐Aug‐17 29‐Aug‐17 95% 95% 0% 0.079% 0.079%
1034 2 CIVIL DEM‐3963‐FAHN‐1‐50‐0001 DEM FAHAHIL NORTH DEGASSING STATION  EXISTING TEST SEPERATOR ‐STEEL WORK DEMOLITION DRAWING 3 A 0.097% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 24‐Aug‐17 13‐Sep‐17 14‐Sep‐17 22‐Jul‐19 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 24‐Aug‐17 13‐Sep‐17 14‐Sep‐17 95% 95% 0% 0.092% 0.092%
1035 2 CIVIL DEM‐3963‐FAHN‐1‐50‐0002 DEM FAHAHIL NORTH DEGASSING STATION  EXISTING TEST SEPERATOR ‐CONCRETE WORK DEMOLITION DRAW 3 A 0.097% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 24‐Aug‐17 13‐Sep‐17 14‐Sep‐17 22‐Jul‐19 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 24‐Aug‐17 13‐Sep‐17 14‐Sep‐17 95% 95% 0% 0.092% 0.092%
1036 2 CIVIL DEM‐3963‐FAHM‐1‐50‐0001 DEM FAHAHIL MAIN DEGASSING STATION  EXISTING TEST SEPERATOR ‐STEEL WORK DEMOLITION DRAWING 3 A 0.083% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 1‐Jun‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.079% 0.079%
1037 2 CIVIL DEM‐3963‐FAHM‐1‐50‐0002 DEM FAHAHIL MAIN DEGASSING STATION  EXISTING TEST SEPERATOR ‐CONCRETE WORK DEMOLITION DRAWIN 3 A 0.097% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 1‐Jun‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.092% 0.092%
1038 2 CIVIL DEM‐3963‐FAHS‐1‐50‐0001 DEM FAHAHIL SOUTH DEGASSING STATION  EXISTING TEST SEPERATOR ‐STEEL WORK DEMOLITION DRAWING 3 A 0.083% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 3‐Sep‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 3‐Sep‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
1039 2 CIVIL DEM‐3963‐FAHS‐1‐50‐0002 DEM FAHAHIL SOUTH DEGASSING STATION  EXISTING TEST SEPERATOR ‐CONCRETE WORK DEMOLITION DRAWI 3 A 0.083% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 3‐Sep‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 1‐Jun‐17 30‐Jul‐17 31‐Jul‐17 3‐Sep‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.079% 0.079%
1040 2 CIVIL DEM‐3963‐JALM‐1‐50‐0001 DEM JALEHA MAIN DEGASSING STATION  EXISTING TEST SEPERATOR ‐STEEL WORK DEMOLITION DRAWING 3 A 0.083% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 29‐Aug‐17 20‐Sep‐17 21‐Nov‐17 22‐Jul‐19 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 29‐Aug‐17 20‐Sep‐17 21‐Nov‐17 95% 95% 0% 0.079% 0.079%
1041 2 CIVIL DEM‐3963‐JALM‐1‐50‐0002 DEM JALEHA MAIN DEGASSING STATION  EXISTING TEST SEPERATOR ‐CONCRETE WORK DEMOLITION DRAWING 3 A 0.083% 31‐May‐17 10‐Jun‐17 22‐Jun‐17 16‐Jul‐17 6‐Aug‐17 16‐Aug‐17 31‐Oct‐18 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 29‐Aug‐17 3‐Oct‐17 3‐Oct‐17 22‐Jul‐19 1‐Jun‐17 25‐Jul‐17 26‐Jul‐17 29‐Aug‐17 3‐Oct‐17 3‐Oct‐17 95% 95% 0% 0.079% 0.079%
1042 2 CIVIL 3963‐DGEN‐1‐12‐0002 OT DESIGN CALCULATION FOR METERING SKID FOUNDATION 1 A 0.208% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 13‐Jul‐17 25‐Sep‐17 27‐Sep‐17 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 13‐Jul‐17 25‐Sep‐17 27‐Sep‐17 7‐Feb‐18 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.198% 0.198%
1043 2 CIVIL 3963‐DGEN‐1‐12‐0003 OT DESIGN CALCULATION FOR TEST SEPARATOR PLATFORM 1 1 0.994% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 13‐Jul‐17 28‐Aug‐17 29‐Aug‐17 19‐Nov‐17 26‐Apr‐18 26‐Apr‐18 22‐Jul‐19 13‐Jul‐17 28‐Aug‐17 29‐Aug‐17 19‐Nov‐17 26‐Apr‐18 26‐Apr‐18 95% 95% 0% 0.945% 0.945%
1044 2 CIVIL 3963‐DGEN‐1‐12‐0004 OT DESIGN CALCULATION FOR PIPE SLEEPERS 1 1 0.194% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 13‐Jul‐17 28‐Oct‐17 29‐Oct‐17 20‐Dec‐17 15‐Apr‐18 15‐Apr‐18 22‐Jul‐19 13‐Jul‐17 28‐Oct‐17 29‐Oct‐17 20‐Dec‐17 15‐Apr‐18 15‐Apr‐18 95% 95% 0% 0.185% 0.185%
1045 2 CIVIL 3963‐DGEN‐1‐12‐0005 OT DESIGN CALCULATION FOR PIPE SUPPORTS 1 0 0.194% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Apr‐18 2‐May‐18 2‐May‐18 22‐Jul‐19 8‐Jul‐17 6‐Nov‐17 13‐Nov‐17 21‐Apr‐18 2‐May‐18 2‐May‐18 95% 95% 0% 0.185% 0.185%
1046 2 CIVIL 3963‐DGEN‐1‐57‐0005 OT TYPICAL DETAILS OF FIRE PROOFING  1 A 0.111% 3‐May‐17 13‐May‐17 18‐May‐17 18‐Jun‐17 9‐Jul‐17 19‐Jul‐17 31‐Oct‐18 8‐Jun‐17 13‐Jun‐17 14‐Jun‐17 13‐Jul‐17 13‐Jul‐17 18‐Jul‐17 22‐Jul‐19 8‐Jun‐17 13‐Jun‐17 14‐Jun‐17 13‐Jul‐17 13‐Jul‐17 18‐Jul‐17 95% 95% 0% 0.106% 0.106%
1047 2 CIVIL 3963‐KAHN‐1‐66‐0004 OT KHATIYAH NORTH DEGASSING STATION PSV PLATFORM FOUNDATION GA & RC DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 12‐Oct‐17 11‐Oct‐17 12‐Oct‐17 30‐Oct‐17 30‐Oct‐17 29‐Jan‐18 22‐Jul‐19 12‐Oct‐17 11‐Oct‐17 12‐Oct‐17 30‐Oct‐17 30‐Oct‐17 29‐Jan‐18 95% 95% 0% 0.013% 0.013%
1048 2 CIVIL 3963‐KAHM‐1‐66‐0004 OT KHATIYAH MAIN DEGASSING STATION PSV PLATFORM FOUNDATION GA & RC DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 23‐Oct‐17 25‐Oct‐17 21‐Nov‐17 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 19‐Oct‐17 23‐Oct‐17 25‐Oct‐17 21‐Nov‐17 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.013% 0.013%
1049 2 CIVIL 3963‐KAHS‐1‐66‐0004 OT KHATIYAH SOUTH DEGASSING STATION PSV PLATFORM FOUNDATION GA & RC DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 25‐Oct‐17 26‐Oct‐17 4‐Dec‐17 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 19‐Oct‐17 25‐Oct‐17 26‐Oct‐17 4‐Dec‐17 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.013% 0.013%
1050 2 CIVIL 3963‐FAHN‐1‐66‐0004 OT FAHAHIL NORTH DEGASSING STATION PSV PLATFORM FOUNDATION GA & RC DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 20‐Nov‐17 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 20‐Nov‐17 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.013% 0.013%
1051 2 CIVIL 3963‐FAHM‐1‐66‐0004 OT FAHAHIL MAIN DEGASSING STATION PSV PLATFORM FOUNDATION GA & RC DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 21‐Nov‐17 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 21‐Nov‐17 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.013% 0.013%
1052 2 CIVIL 3963‐FAHS‐1‐66‐0004 OT FAHAHIL SOUTH DEGASSING STATION PSV PLATFORM FOUNDATION GA & RC DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 21‐Nov‐17 22‐Feb‐18 22‐Feb‐18 22‐Jul‐19 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 21‐Nov‐17 22‐Feb‐18 22‐Feb‐18 95% 95% 0% 0.013% 0.013%
1053 2 CIVIL 3963‐JALM‐1‐66‐0004 OT JALEHA MAIN DEGASSING STATION PSV PLATFORM FOUNDATION GA & RC DETAILS 1 1 0.046% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 5‐Nov‐17 7‐Nov‐17 27‐Nov‐17 20‐Mar‐18 20‐Mar‐18 22‐Jul‐19 19‐Oct‐17 5‐Nov‐17 7‐Nov‐17 27‐Nov‐17 20‐Mar‐18 20‐Mar‐18 95% 95% 0% 0.044% 0.044%
1054 2 CIVIL 3963‐KAHN‐1‐51‐0003 OT KHATIYAH NORTH DEGASSING STATION PSV PLATFORM STRUCTURAL GA & DETAILS 1 B 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 23‐Sep‐17 24‐Sep‐17 26‐Sep‐17 29‐Oct‐17 29‐Oct‐17 27‐Nov‐17 22‐Jul‐19 23‐Sep‐17 24‐Sep‐17 26‐Sep‐17 29‐Oct‐17 29‐Oct‐17 27‐Nov‐17 95% 95% 0% 0.013% 0.013%
1055 2 CIVIL 3963‐KAHM‐1‐51‐0003 OT KHATIYAH MAIN DEGASSING STATION PSV PLATFORM STRUCTURAL GA & DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 25‐Oct‐17 26‐Oct‐17 4‐Dec‐17 4‐Feb‐18 4‐Feb‐18 22‐Jul‐19 19‐Oct‐17 25‐Oct‐17 26‐Oct‐17 4‐Dec‐17 4‐Feb‐18 4‐Feb‐18 95% 95% 0% 0.013% 0.013%
1056 2 CIVIL 3963‐KAHS‐1‐51‐0003 OT KHATIYAH SOUTH DEGASSING STATION PSV PLATFORM STRUCTURAL GA & DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 26‐Nov‐17 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 26‐Nov‐17 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.013% 0.013%
1057 2 CIVIL 3963‐FAHN‐1‐51‐0003 OT FAHAHIL NORTH DEGASSING STATION PSV PLATFORM STRUCTURAL GA & DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 26‐Nov‐17 26‐Feb‐18 26‐Feb‐18 22‐Jul‐19 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 26‐Nov‐17 26‐Feb‐18 26‐Feb‐18 95% 95% 0% 0.013% 0.013%
1058 2 CIVIL 3963‐FAHM‐1‐51‐0003 OT FAHAHIL MAIN DEGASSING STATION PSV PLATFORM STRUCTURAL GA & DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 26‐Nov‐17 21‐Feb‐18 21‐Feb‐18 22‐Jul‐19 19‐Oct‐17 1‐Nov‐17 2‐Nov‐17 26‐Nov‐17 21‐Feb‐18 21‐Feb‐18 95% 95% 0% 0.013% 0.013%
1059 2 CIVIL 3963‐FAHS‐1‐51‐0003 OT FAHAHIL SOUTH DEGASSING STATION PSV PLATFORM STRUCTURAL GA & DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 26‐Nov‐17 28‐Feb‐18 28‐Feb‐18 22‐Jul‐19 19‐Oct‐17 31‐Oct‐17 1‐Nov‐17 26‐Nov‐17 28‐Feb‐18 28‐Feb‐18 95% 95% 0% 0.013% 0.013%
1060 2 CIVIL 3963‐JALM‐1‐51‐0003 OT JALEHA MAIN DEGASSING STATION PSV PLATFORM STRUCTURAL GA & DETAILS 1 1 0.046% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 19‐Oct‐17 5‐Nov‐17 7‐Nov‐17 26‐Nov‐17 20‐Mar‐18 20‐Mar‐18 22‐Jul‐19 19‐Oct‐17 5‐Nov‐17 7‐Nov‐17 26‐Nov‐17 20‐Mar‐18 20‐Mar‐18 95% 95% 0% 0.044% 0.044%
1061 2 CIVIL 3963‐KAHN‐1‐51‐0004 OT KHATIYAH NORTH EARLY TIE IN PIPE SUPPORTS STRUCTURAL SCHEDULE & DETAILS 1 B 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 13‐Dec‐17 13‐Dec‐17 22‐Jul‐19 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 13‐Dec‐17 13‐Dec‐17 95% 95% 0% 0.013% 0.013%
1062 2 CIVIL 3963‐KAHS‐1‐51‐0004 OT KHATIYAH SOUTH EARLY TIE IN PIPE SUPPORTS STRUCTURAL SCHEDULE & DETAILS 1 A 0.014% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 13‐Dec‐17 13‐Dec‐17 22‐Jul‐19 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 13‐Dec‐17 13‐Dec‐17 95% 95% 0% 0.013% 0.013%
1063 2 CIVIL 3963‐KAHM‐1‐51‐0004 OT KHATIYAH MAIN EARLY TIE IN PIPE SUPPORTS STRUCTURAL SCHEDULE & DETAILS 1 A 0.000% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 11‐Dec‐17 11‐Dec‐17 22‐Jul‐19 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 11‐Dec‐17 11‐Dec‐17 95% 95% 0% 0.000% 0.000%
1064 2 CIVIL 3963‐KAHN‐1‐66‐0005 OT KHATIYAH NORTH EARLY TIE IN PIPE SUPPORTS FOUDATION SCHEDULE & DETAILS 1 B 0.0% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 13‐Dec‐17 13‐Dec‐17 22‐Jul‐19 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 13‐Dec‐17 13‐Dec‐17 95% 95% 0% 0.000% 0.000%
1065 2 CIVIL 3963‐KAHS‐1‐66‐0005 OT KHATIYAH SOUTH EARLY TIE IN PIPE SUPPORTS FOUDATION SCHEDULE & DETAILS 1 B 0.000% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 13‐Dec‐17 19‐Dec‐17 19‐Dec‐17 22‐Jul‐19 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 13‐Dec‐17 19‐Dec‐17 19‐Dec‐17 95% 95% 0% 0.000% 0.000%
1066 2 CIVIL 3963‐KAHM‐1‐66‐0005 OT KHATIYAH MAIN EARLY TIE IN PIPE SUPPORTS FOUDATION SCHEDULE & DETAILS 1 C 0.000% 14‐Jul‐17 26‐Jul‐17 31‐Jul‐17 31‐Aug‐17 21‐Sep‐17 1‐Oct‐17 31‐Oct‐18 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 19‐Dec‐17 19‐Dec‐17 22‐Jul‐19 28‐Nov‐17 28‐Nov‐17 29‐Nov‐17 4‐Dec‐17 19‐Dec‐17 19‐Dec‐17 95% 95% 0% 0.000% 0.000%
1067 4 CIVIL 3963‐DGEN‐1‐00‐0001 OT MISCELLANEOUS ‐ CIVIL 0 0.000% 31‐Aug‐17 6‐Sep‐17 7‐Sep‐17 14‐Sep‐17 14‐Sep‐17 21‐Sep‐17 31‐Oct‐18 1‐Feb‐18 6‐Feb‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 22‐Jul‐19 1‐Feb‐18 6‐Feb‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 95% 95% 0% 0.000% 0.000%
1068 2 CIVIL 3963‐JALM‐1‐66‐0002 OT JALEHA MAIN DEGASSING STATION  METERING SKID FOUNDATION GA & RC DETAILS  1 A 0.171% 10‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 12‐Sep‐17 19‐Sep‐17 31‐Oct‐18 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 27‐Dec‐17 20‐Mar‐18 20‐Mar‐18 22‐Jul‐19 13‐Jul‐17 17‐Oct‐17 18‐Oct‐17 27‐Dec‐17 20‐Mar‐18 20‐Mar‐18 95% 95% 0% 0.163% 0.163%
1069 2 CIVIL 3963‐KAHN‐1‐66‐0001 OT KHATIYAH NORTH DEGASSING STATION  TEST SEPARATOR FOUNDATION GA & RC DETAILS  1 B 0.139% 17‐May‐17 27‐May‐17 1‐Jun‐17 2‐Jul‐17 23‐Jul‐17 2‐Aug‐17 31‐Oct‐18 25‐May‐17 5‐Sep‐17 6‐Sep‐17 25‐Oct‐17 25‐Oct‐17 21‐Jan‐18 22‐Jul‐19 25‐May‐17 5‐Sep‐17 6‐Sep‐17 25‐Oct‐17 25‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.132% 0.132%
1070 2 CIVIL 3963‐KAHM‐1‐66‐0001 OT KHATIYAH MAIN DEGASSING STATION  TEST SEPARATOR FOUNDATION GA & RC DETAILS  1 B 0.139% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 18‐Sep‐17 19‐Sep‐17 30‐Oct‐17 30‐Oct‐17 21‐Jan‐18 22‐Jul‐19 25‐May‐17 18‐Sep‐17 19‐Sep‐17 30‐Oct‐17 30‐Oct‐17 21‐Jan‐18 95% 95% 0% 0.132% 0.132%
1071 2 CIVIL 3963‐KAHS‐1‐66‐0001 OT KHATIYAH SOUTH DEGASSING STATION  TEST SEPARATOR FOUNDATION GA & RC DETAILS  1 B 0.139% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 13‐Jul‐17 18‐Sep‐17 20‐Sep‐17 1‐Nov‐17 1‐Nov‐17 21‐Jan‐18 22‐Jul‐19 13‐Jul‐17 18‐Sep‐17 20‐Sep‐17 1‐Nov‐17 1‐Nov‐17 21‐Jan‐18 95% 95% 0% 0.132% 0.132%
1072 2 CIVIL 3963‐DGEN‐1‐12‐0001 OT DESIGN CALCULATION FOR TEST SEPARATOR FOUNDATION 1 A 0.144% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 6‐Sep‐17 7‐Sep‐17 2‐Nov‐17 2‐Nov‐17 22‐Jan‐18 22‐Jul‐19 8‐Jul‐17 6‐Sep‐17 7‐Sep‐17 2‐Nov‐17 2‐Nov‐17 22‐Jan‐18 95% 95% 0% 0.137% 0.137%
1073 4 SAFETY 3963‐DGEN‐3‐04‐0002 OT PROJECT HSE PLAN 1 A 0.139% 1‐Apr‐17 11‐Apr‐17 16‐Apr‐17 17‐May‐17 7‐Jun‐17 17‐Jun‐17 31‐Oct‐18 26‐Mar‐17 29‐Mar‐17 5‐Apr‐17 5‐Apr‐17 8‐Jun‐17 8‐Jun‐17 22‐Jul‐19 26‐Mar‐17 29‐Mar‐17 5‐Apr‐17 5‐Apr‐17 8‐Jun‐17 8‐Jun‐17 95% 95% 0% 0.132% 0.132%
1074 4 SAFETY 3963‐DGEN‐3‐03‐0001 OT FIRE & SAFETY PHILOSOPHY 1 B 0.139% 25‐Mar‐17 4‐Apr‐17 9‐Apr‐17 10‐May‐17 31‐May‐17 10‐Jun‐17 31‐Oct‐18 29‐Mar‐17 2‐Apr‐17 5‐Apr‐17 4‐May‐17 20‐Jun‐17 20‐Jun‐17 22‐Jul‐19 29‐Mar‐17 2‐Apr‐17 5‐Apr‐17 4‐May‐17 20‐Jun‐17 20‐Jun‐17 95% 95% 0% 0.132% 0.132%
1075 4 SAFETY 3963‐DGEN‐3‐03‐0002 OT HAZARDOUS AREA CLASSIFICATION PHILOSOPHY AND SCHEDULE FOR ALL DEGASSING STATIONS 1 B 0.139% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 3‐Apr‐17 19‐May‐17 21‐May‐17 4‐Jul‐17 13‐Jul‐17 18‐Jul‐17 22‐Jul‐19 3‐Apr‐17 19‐May‐17 21‐May‐17 4‐Jul‐17 13‐Jul‐17 18‐Jul‐17 95% 95% 0% 0.132% 0.132%
1076 4 SAFETY 3963‐DGEN‐3‐17‐0001 L TERMS OF REFERENCE FOR HAZID 1 A 0.125% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 5‐Apr‐17 17‐Jul‐17 18‐Jul‐17 3‐Aug‐17 14‐Aug‐17 14‐Aug‐17 22‐Jul‐19 5‐Apr‐17 17‐Jul‐17 18‐Jul‐17 3‐Aug‐17 14‐Aug‐17 14‐Aug‐17 95% 95% 0% 0.119% 0.119%
1077 4 SAFETY 3963‐DGEN‐3‐17‐0003 L HAZID/ENVID CLOSE OUT REPORT 1 A 0.264% 15‐Jul‐17 25‐Jul‐17 30‐Jul‐17 30‐Aug‐17 13‐Sep‐17 20‐Sep‐17 31‐Oct‐18 14‐Nov‐17 16‐Dec‐17 17‐Dec‐17 22‐Jan‐18 5‐Feb‐18 5‐Feb‐18 22‐Jul‐19 14‐Nov‐17 16‐Dec‐17 17‐Dec‐17 22‐Jan‐18 5‐Feb‐18 5‐Feb‐18 95% 95% 0% 0.251% 0.251%
1078 4 SAFETY 3963‐DGEN‐3‐17‐0004 L TERMS OF REFERENCE FOR HAZOP 1 A 0.069% 15‐May‐17 25‐May‐17 30‐May‐17 30‐Jun‐17 21‐Jul‐17 31‐Jul‐17 31‐Oct‐18 5‐Apr‐17 18‐Oct‐17 19‐Oct‐17 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 22‐Jul‐19 5‐Apr‐17 18‐Oct‐17 19‐Oct‐17 24‐Jan‐18 24‐Jan‐18 24‐Jan‐18 95% 95% 0% 0.066% 0.066%
1079 4 SAFETY 3963‐DGEN‐3‐17‐0005 L HAZOP REPORT 1 A 0.250% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 11‐Nov‐17 19‐Nov‐17 21‐Nov‐17 10‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 11‐Nov‐17 19‐Nov‐17 21‐Nov‐17 10‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.238% 0.238%
1080 4 SAFETY 3963‐DGEN‐3‐17‐0006 L HAZOP CLOSE OUT REPORT 1 A 0.250% 31‐Jul‐17 10‐Aug‐17 15‐Aug‐17 4‐Sep‐17 13‐Sep‐17 16‐Sep‐17 31‐Oct‐18 19‐Oct‐17 16‐Dec‐17 17‐Dec‐17 21‐Jan‐18 12‐Mar‐18 12‐Mar‐18 22‐Jul‐19 19‐Oct‐17 16‐Dec‐17 17‐Dec‐17 21‐Jan‐18 12‐Mar‐18 12‐Mar‐18 95% 95% 0% 0.238% 0.238%
1081 4 SAFETY 3963‐DGEN‐3‐17‐0008 OT QRA ASSUMPTION REGISTER 1 A 0.069% 5‐May‐17 15‐May‐17 20‐May‐17 20‐Jun‐17 11‐Jul‐17 21‐Jul‐17 31‐Oct‐18 25‐May‐17 8‐Aug‐17 10‐Aug‐17 25‐Oct‐17 25‐Oct‐17 22‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Aug‐17 10‐Aug‐17 25‐Oct‐17 25‐Oct‐17 22‐Jan‐18 95% 95% 0% 0.066% 0.066%
1082 4 SAFETY 3963‐DGEN‐3‐17‐0010 OT FRA ASSUMPTION REGISTER 1 A 0.125% 10‐May‐17 20‐May‐17 25‐May‐17 25‐Jun‐17 16‐Jul‐17 26‐Jul‐17 31‐Oct‐18 25‐May‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 21‐Aug‐17 22‐Aug‐17 22‐Jul‐19 25‐May‐17 19‐Jul‐17 20‐Jul‐17 10‐Aug‐17 21‐Aug‐17 22‐Aug‐17 95% 95% 0% 0.119% 0.119%
1083 4 SAFETY 3963‐DGEN‐3‐17‐0011 OT FIRE RISK ASSESSMENT STUDY  1 1 0.285% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 21‐Jun‐17 1‐Jan‐18 3‐Jan‐18 29‐Jan‐18 28‐Jul‐18 28‐Jul‐18 22‐Jul‐19 21‐Jun‐17 1‐Jan‐18 3‐Jan‐18 29‐Jan‐18 28‐Jul‐18 28‐Jul‐18 95% 95% 0% 0.270% 0.270%
1084 4 SAFETY 3963‐DGEN‐3‐17‐0012 OT FIREWATER DEMAND AND AVAILABILITY REPORT 1 A 0.139% 20‐Apr‐17 30‐Apr‐17 5‐May‐17 5‐Jun‐17 26‐Jun‐17 6‐Jul‐17 31‐Oct‐18 5‐Apr‐17 9‐May‐17 10‐May‐17 15‐Jun‐17 15‐Jun‐17 4‐Oct‐17 22‐Jul‐19 5‐Apr‐17 9‐May‐17 10‐May‐17 15‐Jun‐17 15‐Jun‐17 4‐Oct‐17 95% 95% 0% 0.132% 0.132%
1085 4 SAFETY 3963‐DGEN‐3‐17‐0013 OT HSE ACTION TRACKING REGISTER 1 A 0.153% 10‐Aug‐17 20‐Aug‐17 25‐Aug‐17 12‐Sep‐17 18‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 8‐Jun‐18 10‐Jun‐18 10‐Aug‐18 9‐Sep‐18 9‐Sep‐18 22‐Jul‐19 19‐Oct‐17 8‐Jun‐18 10‐Jun‐18 10‐Aug‐18 9‐Sep‐18 9‐Sep‐18 95% 95% 0% 0.145% 0.145%
1086 4 SAFETY 3963‐DGEN‐3‐17‐0015 OT TBE FOR FIRE FIGHINT & SAFETY EQUIPMENT  1 2 0.153% 7‐Aug‐17 17‐Aug‐17 22‐Aug‐17 9‐Sep‐17 15‐Sep‐17 18‐Sep‐17 31‐Oct‐18 19‐Oct‐17 29‐Nov‐17 3‐Dec‐17 6‐Feb‐18 28‐Mar‐18 28‐Mar‐18 22‐Jul‐19 19‐Oct‐17 29‐Nov‐17 3‐Dec‐17 6‐Feb‐18 28‐Mar‐18 28‐Mar‐18 95% 95% 0% 0.145% 0.145%
1087 4 SAFETY 3963‐DGEN‐3‐15‐0001 OT MATERIAL REQUISITION FOR DELUGE SKID 1 A 0.125% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 4‐Jul‐17 24‐Jul‐17 25‐Jul‐17 10‐Aug‐17 30‐Aug‐17 9‐Jan‐18 22‐Jul‐19 4‐Jul‐17 24‐Jul‐17 25‐Jul‐17 10‐Aug‐17 30‐Aug‐17 9‐Jan‐18 95% 95% 0% 0.119% 0.119%
1088 4 SAFETY 3963‐DGEN‐3‐15‐0002 OT MATERIAL REQUISITION FOR FIRE FIGHTING SYSTEM 1 A 0.125% 5‐Jul‐17 15‐Jul‐17 20‐Jul‐17 20‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 4‐Jul‐17 24‐Jul‐17 25‐Jul‐17 10‐Aug‐17 30‐Aug‐17 3‐Jan‐18 22‐Jul‐19 4‐Jul‐17 24‐Jul‐17 25‐Jul‐17 10‐Aug‐17 30‐Aug‐17 3‐Jan‐18 95% 95% 0% 0.119% 0.119%
1089 4 SAFETY 3963‐DGEN‐3‐14‐0001 OT DELUGE SKIDS SPECIFICATION 1 B 0.056% 20‐Apr‐17 30‐Apr‐17 5‐May‐17 5‐Jun‐17 26‐Jun‐17 6‐Jul‐17 31‐Oct‐18 5‐Apr‐17 9‐May‐17 11‐May‐17 9‐Jul‐17 30‐Aug‐17 3‐Jan‐18 22‐Jul‐19 5‐Apr‐17 9‐May‐17 11‐May‐17 9‐Jul‐17 30‐Aug‐17 3‐Jan‐18 95% 95% 0% 0.053% 0.053%
1090 4 SAFETY 3963‐DGEN‐3‐14‐0002 OT FIRE FIGHTING & SAFETY EQUIPMENT SPECIFIFCATION 1 C 0.125% 20‐Apr‐17 30‐Apr‐17 5‐May‐17 5‐Jun‐17 26‐Jun‐17 6‐Jul‐17 31‐Oct‐18 19‐Apr‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 26‐Jul‐17 27‐Jul‐17 22‐Jul‐19 19‐Apr‐17 9‐May‐17 10‐May‐17 1‐Jun‐17 26‐Jul‐17 27‐Jul‐17 95% 95% 0% 0.119% 0.119%
1091 4 SAFETY 3963‐DGEN‐3‐14‐0003 OT PASSIVE FIRE PROTECTION‐SPECIFICATION 1 A 0.125% 9‐Apr‐17 19‐Apr‐17 24‐Apr‐17 25‐May‐17 15‐Jun‐17 25‐Jun‐17 31‐Oct‐18 19‐Apr‐17 24‐Apr‐17 26‐Apr‐17 6‐Jul‐17 12‐Jul‐17 17‐Jul‐17 22‐Jul‐19 19‐Apr‐17 24‐Apr‐17 26‐Apr‐17 6‐Jul‐17 12‐Jul‐17 17‐Jul‐17 95% 95% 0% 0.119% 0.119%
1092 4 SAFETY 3963‐DGEN‐3‐12‐0001 OT DELUGE SYSTEM CALCULATION 1 B 0.125% 25‐Apr‐17 5‐May‐17 10‐May‐17 10‐Jun‐17 1‐Jul‐17 11‐Jul‐17 31‐Oct‐18 5‐Apr‐17 6‐Jun‐17 6‐Jun‐17 12‐Dec‐17 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 5‐Apr‐17 6‐Jun‐17 6‐Jun‐17 12‐Dec‐17 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.119% 0.119%
1093 4 SAFETY 3963‐FAHM‐3‐58‐0001 OT 3 PHASE TEST SEPARATORS SAFETY & FIRE FIGHTING EQUIPMENT LAYOUT (FAHM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1094 4 SAFETY 3963‐FAHN‐3‐58‐0001 OT 3 PHASE TEST SEPARATORS SAFETY & FIRE FIGHTING EQUIPMENT LAYOUT (FAHN) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1095 4 SAFETY 3963‐FAHS‐3‐58‐0001 OT 3 PHASE TEST SEPARATORS SAFETY & FIRE FIGHTING EQUIPMENT LAYOUT (FAHS) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1096 4 SAFETY 3963‐JALM‐3‐58‐0001 OT 3 PHASE TEST SEPARATORS SAFETY & FIRE FIGHTING EQUIPMENT LAYOUT (JALM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1097 4 SAFETY 3963‐KAHM‐3‐58‐0001 OT 3 PHASE TEST SEPARATORS SAFETY & FIRE FIGHTING EQUIPMENT LAYOUT (KAHM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1098 4 SAFETY 3963‐KAHN‐3‐58‐0001 OT 3 PHASE TEST SEPARATORS SAFETY & FIRE FIGHTING EQUIPMENT LAYOUT (KAHN) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1099 4 SAFETY 3963‐KAHS‐3‐58‐0001 OT 3 PHASE TEST SEPARATORS SAFETY & FIRE FIGHTING EQUIPMENT LAYOUT (KAHS) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 14‐Dec‐17 25‐Jan‐18 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1100 4 SAFETY 3963‐FAHM‐3‐60‐0001 OT PASSIVE FIRE PROTECTION LAYOUT (FAHM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1101 4 SAFETY 3963‐FAHN‐3‐60‐0001 OT PASSIVE FIRE PROTECTION LAYOUT (FAHN) 1 2 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 8‐Jul‐18 8‐Jul‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 8‐Jul‐18 8‐Jul‐18 95% 95% 0% 0.066% 0.066%
1102 4 SAFETY 3963‐FAHS‐3‐60‐0001 OT PASSIVE FIRE PROTECTION LAYOUT (FAHS) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 21‐Jul‐18 21‐Jul‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 21‐Jul‐18 21‐Jul‐18 95% 95% 0% 0.066% 0.066%
1103 4 SAFETY 3963‐JALM‐3‐60‐0001 OT PASSIVE FIRE PROTECTION LAYOUT (JALM) 1 2 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 11‐Jul‐18 11‐Jul‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 11‐Jul‐18 11‐Jul‐18 95% 95% 0% 0.066% 0.066%
1104 4 SAFETY 3963‐KAHM‐3‐60‐0001 OT PASSIVE FIRE PROTECTION LAYOUT (KAHM) 1 2 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 11‐Jul‐18 11‐Jul‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 11‐Jul‐18 11‐Jul‐18 95% 95% 0% 0.066% 0.066%
1105 4 SAFETY 3963‐KAHN‐3‐60‐0001 OT PASSIVE FIRE PROTECTION LAYOUT (KAHN) 1 2 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 26‐Aug‐18 26‐Aug‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 26‐Aug‐18 26‐Aug‐18 95% 95% 0% 0.066% 0.066%
1106 4 SAFETY 3963‐KAHS‐3‐60‐0001 OT PASSIVE FIRE PROTECTION LAYOUT (KAHS) 1 2 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 11‐Jul‐18 11‐Jul‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 7‐Jan‐18 11‐Jul‐18 11‐Jul‐18 95% 95% 0% 0.066% 0.066%
1107 4 SAFETY 3963‐FAHM‐3‐54‐0001 OT SAFETY SIGN LAYOUTS (FAHM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 16‐Dec‐17 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 16‐Dec‐17 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1108 4 SAFETY 3963‐FAHN‐3‐54‐0001 OT SAFETY SIGN LAYOUTS (FAHN) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 16‐Dec‐17 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 16‐Dec‐17 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1109 4 SAFETY 3963‐FAHS‐3‐54‐0001 OT SAFETY SIGN LAYOUTS (FAHS) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 16‐Dec‐17 23‐Jan‐18 23‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 16‐Dec‐17 23‐Jan‐18 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1110 4 SAFETY 3963‐JALM‐3‐54‐0001 OT SAFETY SIGN LAYOUTS (JALM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1111 4 SAFETY 3963‐KAHM‐3‐54‐0001 OT SAFETY SIGN LAYOUTS (KAHM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1112 4 SAFETY 3963‐KAHN‐3‐54‐0001 OT SAFETY SIGN LAYOUTS (KAHN) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1113 4 SAFETY 3963‐KAHS‐3‐54‐0001 OT SAFETY SIGN LAYOUTS (KAHS) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 22‐Jul‐19 25‐May‐17 31‐May‐17 1‐Jun‐17 17‐Aug‐17 17‐Aug‐17 23‐Jan‐18 95% 95% 0% 0.066% 0.066%
1114 4 SAFETY 3963‐FAHM‐3‐59‐0001 OT FIREWATER RING MAIN, P&ID (FAHM) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1115 4 SAFETY 3963‐FAHM‐3‐59‐0002 OT FIREWATER DELUGE SYSTEM, P&ID (FAHM) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 9‐Jan‐18 22‐Jul‐19 3‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 9‐Jan‐18 95% 95% 0% 0.079% 0.079%

Page 9 of 13
Page 80 of 170
REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS-DUKHAN FIELD
Engineering Document & Deliverables Register (EDDR)
100.000% REV D
SHUTD Original BL Rev-D 25-Oct-18
DISCSE ITEM DOC CURRENT OWN START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT START DRAFT/IDC IFC IFA IAWH IAFC AS-BUILT Deliverable Milestone
SRN DISCIPLINE DOC NO DOC DESC WV Weight Factor %
Q CODE CLASS REVISION PACKA 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100% 5% 0% 40% 65% 85% 95% 100%
GE Plan Actual Variance
PLANNED PLANNED ACTUAL
ITEM DOC CURRENT SHUTD ACTASBUIL Planned Actual Actual
SRN SEQ DISCIPLINE DOC NO DOC DESC WV PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT PLS PLD PLIFC PLIFA PLIAWH PLIAFC PLASBUILT ACTS ACTD ACTIFC ACTIFA ACTIAWH ACTIAFC Plan WF Actual WF
CODE CLASS REVISION OWN T Deliverable MS Deliverable MS Deliverable MS
1116 4 SAFETY 3963‐FAHN‐3‐59‐0001 OT FIREWATER RING MAIN, P&ID (FAHN) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1117 4 SAFETY 3963‐FAHN‐3‐59‐0002 OT FIREWATER DELUGE SYSTEM, P&ID (FAHN) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 22‐Jul‐19 3‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 95% 95% 0% 0.079% 0.079%
1118 4 SAFETY 3963‐FAHS‐3‐59‐0001 OT FIREWATER RING MAIN, P&ID (FAHS) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1119 4 SAFETY 3963‐FAHS‐3‐59‐0002 OT FIREWATER DELUGE SYSTEM, P&ID (FAHS) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 95% 95% 0% 0.079% 0.079%
1120 4 SAFETY 3963‐JALM‐3‐59‐0001 OT FIREWATER RING MAIN, P&ID (JALM) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 17‐Aug‐17 17‐Aug‐17 11‐Jan‐18 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 17‐Aug‐17 17‐Aug‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1121 4 SAFETY 3963‐JALM‐3‐59‐0002 OT FIREWATER DELUGE SYSTEM, P&ID (JALM) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 95% 95% 0% 0.079% 0.079%
1122 4 SAFETY 3963‐KAHM‐3‐59‐0001 OT FIREWATER RING MAIN, P&ID (KAHM) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1123 4 SAFETY 3963‐KAHM‐3‐59‐0002 OT FIREWATER DELUGE SYSTEM, P&ID (KAHM) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 95% 95% 0% 0.079% 0.079%
1124 4 SAFETY 3963‐KAHN‐3‐59‐0001 OT FIREWATER RING MAIN, P&ID (KAHN) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 9‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 22‐Jul‐19 3‐May‐17 9‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1125 4 SAFETY 3963‐KAHN‐3‐59‐0002 OT FIREWATER DELUGE SYSTEM, P&ID (KAHN) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 11‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1126 4 SAFETY 3963‐KAHS‐3‐59‐0001 OT FIREWATER RING MAIN, P&ID (KAHS) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 11‐May‐17 11‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 22‐Jul‐19 11‐May‐17 11‐May‐17 11‐May‐17 30‐Aug‐17 20‐Sep‐17 11‐Jan‐18 95% 95% 0% 0.079% 0.079%
1127 4 SAFETY 3963‐KAHS‐3‐59‐0002 OT FIREWATER DELUGE SYSTEM, P&ID (KAHS) 1 A 0.083% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 22‐Jul‐19 4‐May‐17 9‐May‐17 11‐May‐17 27‐Aug‐17 20‐Sep‐17 10‐Jan‐18 95% 95% 0% 0.079% 0.079%
1128 4 SAFETY 3963‐FAHM‐3‐13‐0001 OT DATA SHEET FOR FIRE FIGHTING & SAFETY EQUIPMENT(FAHM) 1 A 0.069% 7‐May‐17 17‐May‐17 22‐May‐17 22‐Jun‐17 13‐Jul‐17 23‐Jul‐17 31‐Oct‐18 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 22‐Jul‐19 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 95% 95% 0% 0.066% 0.066%
1129 4 SAFETY 3963‐FAHN‐3‐13‐0001 OT DATA SHEET FOR FIRE FIGHTING & SAFETY EQUIPMENT(FAHN) 1 A 0.069% 7‐May‐17 17‐May‐17 22‐May‐17 22‐Jun‐17 13‐Jul‐17 23‐Jul‐17 31‐Oct‐18 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 22‐Jul‐19 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 95% 95% 0% 0.066% 0.066%
1130 4 SAFETY 3963‐FAHS‐3‐13‐0001 OT DATA SHEET FOR FIRE FIGHTING & SAFETY EQUIPMENT(FAHS) 1 A 0.069% 7‐May‐17 17‐May‐17 22‐May‐17 22‐Jun‐17 13‐Jul‐17 23‐Jul‐17 31‐Oct‐18 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 22‐Jul‐19 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 95% 95% 0% 0.066% 0.066%
1131 4 SAFETY 3963‐JALM‐3‐13‐0001 OT DATA SHEET FOR FIRE FIGHTING & SAFETY EQUIPMENT(JALM) 1 A 0.069% 7‐May‐17 17‐May‐17 22‐May‐17 22‐Jun‐17 13‐Jul‐17 23‐Jul‐17 31‐Oct‐18 21‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 22‐Jul‐19 21‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 95% 95% 0% 0.066% 0.066%
1132 4 SAFETY 3963‐KAHM‐3‐13‐0001 OT DATA SHEET FOR FIRE FIGHTING & SAFETY EQUIPMENT(KAHM) 1 A 0.069% 7‐May‐17 17‐May‐17 22‐May‐17 22‐Jun‐17 13‐Jul‐17 23‐Jul‐17 31‐Oct‐18 21‐May‐17 22‐May‐17 24‐May‐17 18‐Jul‐17 26‐Jul‐17 11‐Jan‐18 22‐Jul‐19 21‐May‐17 22‐May‐17 24‐May‐17 18‐Jul‐17 26‐Jul‐17 11‐Jan‐18 95% 95% 0% 0.066% 0.066%
1133 4 SAFETY 3963‐KAHN‐3‐13‐0001 OT DATA SHEET FOR FIRE FIGHTING & SAFETY EQUIPMENT(KAHN) 1 A 0.069% 7‐May‐17 17‐May‐17 22‐May‐17 22‐Jun‐17 13‐Jul‐17 23‐Jul‐17 31‐Oct‐18 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 22‐Jul‐19 10‐May‐17 22‐May‐17 24‐May‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 95% 95% 0% 0.066% 0.066%
1134 4 SAFETY 3963‐KAHS‐3‐13‐0001 OT DATA SHEET FOR FIRE FIGHTING & SAFETY EQUIPMENT(KAHS) 1 A 0.069% 7‐May‐17 17‐May‐17 22‐May‐17 22‐Jun‐17 13‐Jul‐17 23‐Jul‐17 31‐Oct‐18 10‐May‐17 31‐May‐17 1‐Jun‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 22‐Jul‐19 10‐May‐17 31‐May‐17 1‐Jun‐17 21‐Jun‐17 29‐Jun‐17 11‐Jan‐18 95% 95% 0% 0.066% 0.066%
1135 4 SAFETY 3963‐FAHM‐3‐13‐0002 OT DATA SHEET FOR DELUGE SKIDS (FAHM) 1 B 0.069% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 22‐Jul‐19 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 95% 95% 0% 0.066% 0.066%
1136 4 SAFETY 3963‐FAHN‐3‐13‐0002 OT DATA SHEET FOR DELUGE SKIDS (FAHN) 1 B 0.069% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 22‐Jul‐19 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 95% 95% 0% 0.066% 0.066%
1137 4 SAFETY 3963‐FAHS‐3‐13‐0002 OT DATA SHEET FOR DELUGE SKIDS (FAHS) 1 B 0.069% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 22‐Jul‐19 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 95% 95% 0% 0.066% 0.066%
1138 4 SAFETY 3963‐JALM‐3‐13‐0002 OT DATA SHEET FOR DELUGE SKIDS (JALM) 1 B 0.069% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 22‐Jul‐19 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 7‐Aug‐17 24‐Jan‐18 95% 95% 0% 0.066% 0.066%
1139 4 SAFETY 3963‐KAHM‐3‐13‐0002 OT DATA SHEET FOR DELUGE SKIDS (KAHM) 1 B 0.056% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 10‐Aug‐17 24‐Jan‐18 22‐Jul‐19 3‐May‐17 11‐May‐17 11‐May‐17 19‐Jul‐17 10‐Aug‐17 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
1140 4 SAFETY 3963‐KAHN‐3‐13‐0002 OT DATA SHEET FOR DELUGE SKIDS (KAHN) 1 B 0.056% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 11‐May‐17 11‐May‐17 20‐Jul‐17 10‐Aug‐17 24‐Jan‐18 22‐Jul‐19 3‐May‐17 11‐May‐17 11‐May‐17 20‐Jul‐17 10‐Aug‐17 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
1141 4 SAFETY 3963‐KAHS‐3‐13‐0002 OT DATA SHEET FOR DELUGE SKIDS (KAHS) 1 B 0.056% 26‐Apr‐17 6‐May‐17 11‐May‐17 11‐Jun‐17 2‐Jul‐17 12‐Jul‐17 31‐Oct‐18 3‐May‐17 11‐May‐17 11‐May‐17 20‐Jul‐17 10‐Aug‐17 24‐Jan‐18 22‐Jul‐19 3‐May‐17 11‐May‐17 11‐May‐17 20‐Jul‐17 10‐Aug‐17 24‐Jan‐18 95% 95% 0% 0.053% 0.053%
1142 4 SAFETY 3963‐JALM‐3‐56‐0001 OT CAUSE & EFFECT CHART (F&G) (JALM) 1 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 95% 95% 0% 0.066% 0.066%
1143 4 SAFETY 3963‐KAHS‐3‐56‐0001 OT CAUSE & EFFECT CHART (F&G) (KAHS) 1 A 0.056% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 95% 95% 0% 0.053% 0.053%
1144 4 SAFETY 3963‐FAHM‐3‐56‐0001 OT CAUSE & EFFECT CHART (F&G) (FAHM) 1 A 0.056% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 95% 95% 0% 0.053% 0.053%
1145 4 SAFETY 3963‐FAHN‐3‐56‐0001 OT CAUSE & EFFECT CHART (F&G) (FAHN) 1 A 0.056% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 25‐Sep‐17 25‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 25‐Sep‐17 25‐Jan‐18 95% 95% 0% 0.053% 0.053%
1146 4 SAFETY 3963‐FAHS‐3‐56‐0001 OT CAUSE & EFFECT CHART (F&G) (FAHS) 1 A 0.056% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 95% 95% 0% 0.053% 0.053%
1147 4 SAFETY 3963‐KAHM‐3‐56‐0001 OT CAUSE & EFFECT CHART (F&G) (KAHM) 1 A 0.056% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 95% 95% 0% 0.053% 0.053%
1148 4 SAFETY 3963‐KAHN‐3‐56‐0001 OT CAUSE & EFFECT CHART (F&G) (KAHN) 1 A 0.056% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 22‐Jul‐19 25‐May‐17 8‐Jun‐17 8‐Jun‐17 17‐Jul‐17 30‐Aug‐17 25‐Jan‐18 95% 95% 0% 0.053% 0.053%
1149 4 SAFETY DEM‐3963‐FAHM‐3‐55‐0002 DEM DEMOLITION ‐ CAUSE & EFFECT CHART (PROCESS) (FAHM) 1 A 0.167% 8‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 15‐Sep‐17 25‐Sep‐17 31‐Oct‐18 11‐Jul‐17 11‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 22‐Jul‐19 11‐Jul‐17 11‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 95% 95% 0% 0.158% 0.158%
1150 4 SAFETY DEM‐3963‐FAHN‐3‐55‐0002 DEM DEMOLITION ‐ CAUSE & EFFECT CHART (PROCESS) (FAHN) 1 A 0.167% 8‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 15‐Sep‐17 25‐Sep‐17 31‐Oct‐18 11‐Jul‐17 11‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 22‐Jul‐19 11‐Jul‐17 11‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 95% 95% 0% 0.158% 0.158%
1151 4 SAFETY DEM‐3963‐KAHM‐3‐55‐0002 DEM DEMOLITION ‐ CAUSE & EFFECT CHART (PROCESS) (KAHM) 1 A 0.167% 8‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 15‐Sep‐17 25‐Sep‐17 31‐Oct‐18 11‐Jul‐17 11‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 22‐Jul‐19 11‐Jul‐17 11‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 95% 95% 0% 0.158% 0.158%
1152 4 SAFETY DEM‐3963‐KAHN‐3‐55‐0002 DEM DEMOLITION ‐ CAUSE & EFFECT CHART (PROCESS) (KAHN) 1 A 0.167% 8‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 15‐Sep‐17 25‐Sep‐17 31‐Oct‐18 8‐Jul‐17 8‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 22‐Jul‐19 8‐Jul‐17 8‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 95% 95% 0% 0.158% 0.158%
1153 4 SAFETY DEM‐3963‐JALM‐3‐55‐0002 DEM DEMOLITION ‐ CAUSE & EFFECT CHART (PROCESS) (JALM) 1 A 0.167% 8‐Jul‐17 20‐Jul‐17 25‐Jul‐17 25‐Aug‐17 15‐Sep‐17 25‐Sep‐17 31‐Oct‐18 8‐Jul‐17 8‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 22‐Jul‐19 8‐Jul‐17 8‐Jul‐17 11‐Jul‐17 25‐Jul‐17 25‐Jul‐17 23‐Aug‐17 95% 95% 0% 0.158% 0.158%
1154 4 SAFETY 3963‐DGEN‐3‐62‐0001 OT F&G SCHEMATIC DIAGRAM (TYPICAL) 1 B 0.014% 5‐Sep‐17 21‐Sep‐17 28‐Sep‐17 10‐Oct‐17 20‐Oct‐17 4‐Nov‐17 31‐Oct‐18 5‐Sep‐17 14‐Sep‐17 21‐Sep‐17 4‐Dec‐17 4‐Dec‐17 4‐Dec‐17 22‐Jul‐19 5‐Sep‐17 14‐Sep‐17 21‐Sep‐17 4‐Dec‐17 4‐Dec‐17 4‐Dec‐17 95% 95% 0% 0.013% 0.013%
1155 5 SAFETY 3963‐DGEN‐3‐00‐0001 OT MISCELLANEOUS ‐ SAFETY 0 #N/A 0.056% 31‐Aug‐17 6‐Sep‐17 7‐Sep‐17 14‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 1‐Feb‐18 6‐Feb‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 22‐Jul‐19 1‐Feb‐18 6‐Feb‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 8‐Mar‐18 95% 95% 0% 0.053% 0.053%
1156 4 SAFETY 3963‐FAHM‐3‐50‐0001 OT ESCAPE ROUTE LAYOUT (FAHM) 3 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 25‐May‐17 25‐May‐17 28‐Dec‐17 31‐Jan‐18 31‐Jan‐18 22‐Jul‐19 25‐May‐17 25‐May‐17 25‐May‐17 28‐Dec‐17 31‐Jan‐18 31‐Jan‐18 95% 95% 0% 0.066% 0.066%
1157 4 SAFETY 3963‐FAHN‐3‐50‐0001 OT ESCAPE ROUTE LAYOUT (FAHN) 3 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 31‐Jan‐18 31‐Jan‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 31‐Jan‐18 31‐Jan‐18 95% 95% 0% 0.066% 0.066%
1158 4 SAFETY 3963‐FAHS‐3‐50‐0001 OT ESCAPE ROUTE LAYOUT (FAHS) 3 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 20‐Mar‐18 20‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 20‐Mar‐18 20‐Mar‐18 95% 95% 0% 0.066% 0.066%
1159 4 SAFETY 3963‐JALM‐3‐50‐0001 OT ESCAPE ROUTE LAYOUT (JALM) 3 A 0.083% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 25‐May‐17 25‐May‐17 28‐Dec‐17 14‐Mar‐18 14‐Mar‐18 22‐Jul‐19 25‐May‐17 25‐May‐17 25‐May‐17 28‐Dec‐17 14‐Mar‐18 14‐Mar‐18 95% 95% 0% 0.079% 0.079%
1160 4 SAFETY 3963‐KAHM‐3‐50‐0001 OT ESCAPE ROUTE LAYOUT (KAHM) 3 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 14‐Mar‐18 14‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 14‐Mar‐18 14‐Mar‐18 95% 95% 0% 0.066% 0.066%
1161 4 SAFETY 3963‐KAHN‐3‐50‐0001 OT ESCAPE ROUTE LAYOUT (KAHN) 3 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 14‐Mar‐18 14‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 28‐Dec‐17 14‐Mar‐18 14‐Mar‐18 95% 95% 0% 0.066% 0.066%
1162 4 SAFETY 3963‐KAHS‐3‐50‐0001 OT ESCAPE ROUTE LAYOUT (KAHS) 3 A 0.069% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 2‐Jan‐18 14‐Mar‐18 14‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 2‐Jan‐18 14‐Mar‐18 14‐Mar‐18 95% 95% 0% 0.066% 0.066%
1163 4 SAFETY 3963‐JALM‐3‐55‐0001 OT CAUSE & EFFECT CHART (PROCESS) (JALM) 1 3 0.056% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 15‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 22‐Jul‐19 15‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 95% 95% 0% 0.053% 0.053%
1164 4 SAFETY 3963‐KAHS‐3‐55‐0001 OT CAUSE & EFFECT CHART (PROCESS) (KAHS) 1 3 0.056% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 22‐Jul‐19 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 95% 95% 0% 0.053% 0.053%
1165 4 SAFETY 3963‐FAHM‐3‐55‐0001 OT CAUSE & EFFECT CHART (PROCESS) (FAHM) 1 3 0.056% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 22‐Jul‐19 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 95% 95% 0% 0.053% 0.053%
1166 4 SAFETY 3963‐FAHN‐3‐55‐0001 OT CAUSE & EFFECT CHART (PROCESS) (FAHN) 1 3 0.056% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 22‐Jul‐19 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 95% 95% 0% 0.053% 0.053%
1167 4 SAFETY 3963‐FAHS‐3‐55‐0001 OT CAUSE & EFFECT CHART (PROCESS) (FAHS) 1 3 0.056% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 22‐Jul‐19 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 95% 95% 0% 0.053% 0.053%
1168 4 SAFETY 3963‐KAHM‐3‐55‐0001 OT CAUSE & EFFECT CHART (PROCESS) (KAHM) 1 3 0.056% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 22‐Jul‐19 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 5‐May‐18 95% 95% 0% 0.053% 0.053%
1169 4 SAFETY 3963‐KAHN‐3‐55‐0001 OT CAUSE & EFFECT CHART (PROCESS) (KAHN) 1 3 0.056% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 8‐Apr‐18 22‐Jul‐19 25‐May‐17 10‐Jul‐17 11‐Jul‐17 10‐Aug‐17 30‐Aug‐17 8‐Apr‐18 95% 95% 0% 0.053% 0.053%
1170 4 SAFETY 3963‐KAHM‐3‐51‐0002 OT KHATIYAH MAIN UNIT 24 HAZARDOUS AREA CLASSIFICATION LAYOUT 1 A 0.083% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 95% 95% 0% 0.079% 0.079%
1171 4 SAFETY 3963‐KAHN‐3‐51‐0002 OT KHATIYAH NORTH UNIT 22 HAZARDOUS AREA CLASSIFICATION LAYOUT 1 A 0.083% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 95% 95% 0% 0.079% 0.079%
1172 4 SAFETY 3963‐KAHS‐3‐51‐0002 OT KHATIYAH SOUTH UNIT 23 HAZARDOUS AREA CLASSIFICATION LAYOUT 1 A 0.083% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 95% 95% 0% 0.079% 0.079%
1173 4 SAFETY 3963‐FAHS‐3‐51‐0002 OT FAHAHIL SOUTH UNIT 13 HAZARDOUS AREA CLASSIFICATION LAYOUT 1 2 0.083% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 95% 95% 0% 0.079% 0.079%
1174 4 SAFETY 3963‐JALM‐3‐51‐0002 OT JALEHA MAIN UNIT 31 HAZARDOUS AREA CLASSIFICATION LAYOUT 1 A 0.069% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 22‐Oct‐17 31‐Oct‐17 22‐Mar‐18 95% 95% 0% 0.066% 0.066%
1175 4 SAFETY 3963‐DGEN‐3‐17‐0009 OT QRA STUDY 1 0 0.229% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 21‐Jun‐17 21‐Jan‐18 28‐Jan‐18 27‐May‐18 28‐Jul‐18 28‐Jul‐18 22‐Jul‐19 21‐Jun‐17 21‐Jan‐18 28‐Jan‐18 27‐May‐18 28‐Jul‐18 28‐Jul‐18 95% 95% 0% 0.218% 0.218%
1176 4 SAFETY 3963‐DGEN‐3‐17‐0002 L HAZID/ENVID REPORT 1 1 0.083% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 3‐Nov‐17 19‐Nov‐17 21‐Nov‐17 21‐Jan‐18 20‐Mar‐18 20‐Mar‐18 22‐Jul‐19 3‐Nov‐17 19‐Nov‐17 21‐Nov‐17 21‐Jan‐18 20‐Mar‐18 20‐Mar‐18 95% 95% 0% 0.079% 0.079%
1177 4 SAFETY 3963‐DGEN‐3‐17‐0014 OT TBE FOR DELUGE SKIDS 1 A 0.472% 7‐Aug‐17 17‐Aug‐17 22‐Aug‐17 9‐Sep‐17 15‐Sep‐17 18‐Sep‐17 31‐Oct‐18 19‐Oct‐17 18‐Dec‐17 21‐Dec‐17 18‐Jan‐18 6‐Feb‐18 6‐Feb‐18 22‐Jul‐19 19‐Oct‐17 18‐Dec‐17 21‐Dec‐17 18‐Jan‐18 6‐Feb‐18 6‐Feb‐18 95% 95% 0% 0.449% 0.449%
1178 4 SAFETY 3963‐FAHM‐3‐51‐0001 OT FAHAHIL MAIN UNIT 14 HAZARDOUS AREA CLASSIFICATION LAYOUT 1 1 0.069% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 20‐Oct‐17 22‐Oct‐17 21‐Jan‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 25‐May‐17 20‐Oct‐17 22‐Oct‐17 21‐Jan‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.066% 0.066%
1179 4 SAFETY 3963‐FAHN‐3‐51‐0002 OT FAHAHIL NORTH UNIT 12 HAZARDOUS AREA CLASSIFICATION LAYOUT 1 A 0.083% 20‐May‐17 30‐May‐17 4‐Jun‐17 5‐Jul‐17 26‐Jul‐17 5‐Aug‐17 31‐Oct‐18 25‐May‐17 27‐May‐17 28‐May‐17 21‐Jan‐18 22‐Mar‐18 22‐Mar‐18 22‐Jul‐19 25‐May‐17 27‐May‐17 28‐May‐17 21‐Jan‐18 22‐Mar‐18 22‐Mar‐18 95% 95% 0% 0.079% 0.079%
1180 5 INSTRUMENTA 3963‐DGEN‐4‐45‐0001 OT SCOPE OF WORK FOR DIC SYSTEM MODIFICATION AT DUKHAN 1 A 0.111% 7‐Jun‐17 17‐Jun‐17 22‐Jun‐17 23‐Jul‐17 13‐Aug‐17 23‐Aug‐17 31‐Oct‐18 8‐Jun‐17 2‐Aug‐17 3‐Aug‐17 12‐Sep‐17 25‐Sep‐17 25‐Sep‐17 22‐Jul‐19 8‐Jun‐17 2‐Aug‐17 3‐Aug‐17 12‐Sep‐17 25‐Sep‐17 25‐Sep‐17 95% 95% 0% 0.106% 0.106%
1181 5 INSTRUMENTA 3963‐DGEN‐4‐15‐0001 OT MATERIAL REQUISITION FOR ELECTRONIC INSTRUMENTS (PT/TT) 1 B 0.069% 26‐Jun‐17 6‐Jul‐17 11‐Jul‐17 11‐Aug‐17 1‐Sep‐17 11‐Sep‐17 31‐Oct‐18 29‐Jun‐17 18‐Jul‐17 19‐Jul‐17 2‐Aug‐17 3‐Aug‐17 20‐Sep‐17 22‐Jul‐19 29‐Jun‐17 18‐Jul‐17 19‐Jul‐17 2‐Aug‐17 3‐Aug‐17 20‐Sep‐17 95% 95% 0% 0.066% 0.066%
1182 5 INSTRUMENTA 3963‐DGEN‐4‐15‐0002 OT MATERIAL REQUISITION FOR LEVEL GAUGES (MAGNETIC) 1 B 0.069% 20‐Jun‐17 30‐Jun‐17 5‐Jul‐17 5‐Aug‐17 26‐Aug‐17 5‐Sep‐17 31‐Oct‐18 22‐Jun‐17 19‐Jul‐17 20‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 22‐Jul‐19 22‐Jun‐17 19‐Jul‐17 20‐Jul‐17 2‐Aug‐17 3‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.066% 0.066%
1183 5 INSTRUMENTA 3963‐DGEN‐4‐15‐0003 OT MATERIAL REQUISITION FOR RESTRICTION ORIFICE 1 B 0.069% 28‐Jun‐17 8‐Jul‐17 13‐Jul‐17 13‐Aug‐17 3‐Sep‐17 13‐Sep‐17 31‐Oct‐18 29‐Jun‐17 26‐Jul‐17 27‐Jul‐17 10‐Aug‐17 21‐Aug‐17 22‐Aug‐17 22‐Jul‐19 29‐Jun‐17 26‐Jul‐17 27‐Jul‐17 10‐Aug‐17 21‐Aug‐17 22‐Aug‐17 95% 95% 0% 0.066% 0.066%
1184 5 INSTRUMENTA 3963‐DGEN‐4‐15‐0004 OT MATERIAL REQUISITION FOR SHUTDOWN & BLOWDOWN VALVES 1 B 0.069% 29‐May‐17 8‐Jun‐17 13‐Jun‐17 14‐Jul‐17 4‐Aug‐17 14‐Aug‐17 31‐Oct‐18 31‐May‐17 18‐Jun‐17 19‐Jun‐17 18‐Aug‐17 28‐Sep‐17 28‐Sep‐17 22‐Jul‐19 31‐May‐17 18‐Jun‐17 19‐Jun‐17 18‐Aug‐17 28‐Sep‐17 28‐Sep‐17 95% 95% 0% 0.066% 0.066%
1185 5 INSTRUMENTA 3963‐DGEN‐4‐15‐0006 OT MATERIAL REQUISITION FOR FIRE & GAS DEVICES 1 A 0.069% 24‐Jun‐17 4‐Jul‐17 9‐Jul‐17 9‐Aug‐17 30‐Aug‐17 9‐Sep‐17 31‐Oct‐18 29‐Jun‐17 19‐Jul‐17 20‐Jul‐17 2‐Aug‐17 3‐Aug‐17 1‐Oct‐17 22‐Jul‐19 29‐Jun‐17 19‐Jul‐17 20‐Jul‐17 2‐Aug‐17 3‐Aug‐17 1‐Oct‐17 95% 95% 0% 0.066% 0.066%
1186 5 INSTRUMENTA 3963‐DGEN‐4‐15‐0014 OT MATERIAL REQUISITION FOR EXISTING SYSTEM MODIFICATIONS (HONEYWELL) 1 A 0.097% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 6‐Aug‐17 8‐Aug‐17 1‐Oct‐17 12‐Oct‐17 12‐Oct‐17 22‐Jul‐19 8‐Jul‐17 6‐Aug‐17 8‐Aug‐17 1‐Oct‐17 12‐Oct‐17 12‐Oct‐17 95% 95% 0% 0.092% 0.092%
1187 5 INSTRUMENTA 3963‐DGEN‐4‐17‐0014 OT TECHNICAL BID EVALUATION FOR EXISTING SYSTEM MODIFICATIONS (HONEYWELL) 1 A 0.167% 19‐Aug‐17 29‐Aug‐17 3‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 28‐Nov‐17 30‐Nov‐17 13‐Dec‐17 26‐Dec‐17 26‐Dec‐17 22‐Jul‐19 19‐Oct‐17 28‐Nov‐17 30‐Nov‐17 13‐Dec‐17 26‐Dec‐17 26‐Dec‐17 95% 95% 0% 0.158% 0.158%
1188 5 INSTRUMENTA 3963‐DGEN‐4‐17‐0002 OT TECHNICAL BID EVALUATION FOR ELECTRONIC INSTRUMENTS (PT) 1 B 0.139% 26‐Aug‐17 5‐Sep‐17 10‐Sep‐17 17‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 4‐Nov‐17 6‐Nov‐17 30‐Nov‐17 7‐Feb‐18 7‐Feb‐18 22‐Jul‐19 19‐Oct‐17 4‐Nov‐17 6‐Nov‐17 30‐Nov‐17 7‐Feb‐18 7‐Feb‐18 95% 95% 0% 0.132% 0.132%
1189 5 INSTRUMENTA 3963‐DGEN‐4‐17‐0003 OT TECHNICAL BID EVALUATION FOR LEVEL GAUGES (MAGNETIC) 1 A 0.139% 19‐Aug‐17 29‐Aug‐17 3‐Sep‐17 16‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 4‐Nov‐17 6‐Nov‐17 14‐Nov‐17 14‐Nov‐17 20‐Nov‐17 22‐Jul‐19 19‐Oct‐17 4‐Nov‐17 6‐Nov‐17 14‐Nov‐17 14‐Nov‐17 20‐Nov‐17 95% 95% 0% 0.132% 0.132%
1190 5 INSTRUMENTA 3963‐DGEN‐4‐17‐0004 OT TECHNICAL BID EVALUATION FOR RESTRICTION ORIFICE 1 A 0.139% 30‐Aug‐17 9‐Sep‐17 14‐Sep‐17 21‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 19‐Oct‐17 18‐Dec‐17 10‐Jan‐18 18‐Jan‐18 18‐Jan‐18 18‐Jan‐18 22‐Jul‐19 19‐Oct‐17 18‐Dec‐17 10‐Jan‐18 18‐Jan‐18 18‐Jan‐18 18‐Jan‐18 95% 95% 0% 0.132% 0.132%
1191 5 INSTRUMENTA 3963‐DGEN‐4‐17‐0005 OT TECHNICAL BID EVALUATION FOR SHUTDOWN & BLOWDOWN VALVES 1 2 0.181% 22‐Jul‐17 1‐Aug‐17 6‐Aug‐17 24‐Aug‐17 3‐Sep‐17 13‐Sep‐17 31‐Oct‐18 27‐Jul‐17 27‐Nov‐17 30‐Nov‐17 21‐Dec‐17 26‐May‐18 26‐May‐18 22‐Jul‐19 27‐Jul‐17 27‐Nov‐17 30‐Nov‐17 21‐Dec‐17 26‐May‐18 26‐May‐18 95% 95% 0% 0.172% 0.172%
1192 5 INSTRUMENTA 3963‐DGEN‐4‐74‐0001 OT HOOK‐UP DIAGRAM (PROCESS) 1 A 0.083% 2‐Aug‐17 12‐Aug‐17 17‐Aug‐17 7‐Sep‐17 16‐Sep‐17 19‐Sep‐17 31‐Oct‐18 1‐Aug‐17 2‐Aug‐17 3‐Aug‐17 29‐Aug‐17 18‐Oct‐17 19‐Oct‐17 22‐Jul‐19 1‐Aug‐17 2‐Aug‐17 3‐Aug‐17 29‐Aug‐17 18‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.079% 0.079%
1193 5 INSTRUMENTA 3963‐DGEN‐4‐74‐0002 OT HOOK‐UP DIAGRAM PNEUMATIC) 1 A 0.083% 8‐Aug‐17 18‐Aug‐17 23‐Aug‐17 10‐Sep‐17 16‐Sep‐17 19‐Sep‐17 31‐Oct‐18 1‐Aug‐17 2‐Aug‐17 3‐Aug‐17 29‐Aug‐17 20‐Sep‐17 13‐Nov‐17 22‐Jul‐19 1‐Aug‐17 2‐Aug‐17 3‐Aug‐17 29‐Aug‐17 20‐Sep‐17 13‐Nov‐17 95% 95% 0% 0.079% 0.079%
1194 5 INSTRUMENTA 3963‐DGEN‐4‐78‐0001 OT INSTRUMENT INSTALLATION DETAILS 1 A 0.111% 16‐Aug‐17 26‐Aug‐17 31‐Aug‐17 15‐Sep‐17 21‐Sep‐17 21‐Sep‐17 31‐Oct‐18 1‐Aug‐17 6‐Aug‐17 8‐Aug‐17 5‐Sep‐17 20‐Sep‐17 19‐Oct‐17 22‐Jul‐19 1‐Aug‐17 6‐Aug‐17 8‐Aug‐17 5‐Sep‐17 20‐Sep‐17 19‐Oct‐17 95% 95% 0% 0.106% 0.106%
1195 5 INSTRUMENTA 3963‐FAHM‐4‐45‐0001 OT SCOPE OF WORK FOR EXISTING SYSTEM MODIFICATIONS (FAHM) 1 A 0.028% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 11‐Jul‐17 26‐Jul‐17 27‐Jul‐17 12‐Sep‐17 25‐Sep‐17 19‐Oct‐17 22‐Jul‐19 11‐Jul‐17 26‐Jul‐17 27‐Jul‐17 12‐Sep‐17 25‐Sep‐17 19‐Oct‐17 95% 95% 0% 0.026% 0.026%
1196 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0001 OT DATA SHEET FOR PRESSURE GAUGES (FAHM) 1 B 0.028% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 17‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 22‐Jul‐19 17‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 95% 95% 0% 0.026% 0.026%
1197 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0002 OT DATA SHEET FOR TEMP GAUGES (FAHM) 1 B 0.028% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 17‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 4‐Oct‐17 22‐Jul‐19 17‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 4‐Oct‐17 95% 95% 0% 0.026% 0.026%
1198 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0003 OT DATA SHEET FOR PRESSURE TRANSMITTERS (FAHM) 1 B 0.028% 16‐May‐17 26‐May‐17 31‐May‐17 1‐Jul‐17 22‐Jul‐17 1‐Aug‐17 31‐Oct‐18 17‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 22‐Jul‐19 17‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 95% 95% 0% 0.026% 0.026%
1199 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0004 OT DATA SHEET FOR TEMP TRANSMITTERS (FAHM) 1 B 0.028% 16‐May‐17 26‐May‐17 31‐May‐17 1‐Jul‐17 22‐Jul‐17 1‐Aug‐17 31‐Oct‐18 15‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 22‐Jul‐19 15‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 95% 95% 0% 0.026% 0.026%
1200 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0005 OT DATA SHEET FOR FLOWMETER ‐ CORIOLIS (FAHM) 1 A 0.042% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 25‐May‐17 11‐Jul‐17 12‐Jul‐17 22‐Aug‐17 4‐Oct‐17 4‐Oct‐17 22‐Jul‐19 25‐May‐17 11‐Jul‐17 12‐Jul‐17 22‐Aug‐17 4‐Oct‐17 4‐Oct‐17 95% 95% 0% 0.040% 0.040%
1201 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0006 OT DATA SHEET FOR LEVEL TRANSMITTERS (FAHM) 1 B 0.028% 22‐May‐17 1‐Jun‐17 6‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 15‐May‐17 19‐Jul‐17 20‐Jul‐17 14‐Sep‐17 25‐Sep‐17 14‐Dec‐17 22‐Jul‐19 15‐May‐17 19‐Jul‐17 20‐Jul‐17 14‐Sep‐17 25‐Sep‐17 14‐Dec‐17 95% 95% 0% 0.026% 0.026%
1202 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0007 OT DATA SHEET FOR BS&W ANALYSERS (FAHM) 1 A 0.042% 13‐May‐17 23‐May‐17 28‐May‐17 28‐Jun‐17 19‐Jul‐17 29‐Jul‐17 31‐Oct‐18 25‐May‐17 18‐Jun‐17 19‐Jun‐17 26‐Jul‐17 24‐Sep‐17 24‐Sep‐17 22‐Jul‐19 25‐May‐17 18‐Jun‐17 19‐Jun‐17 26‐Jul‐17 24‐Sep‐17 24‐Sep‐17 95% 95% 0% 0.040% 0.040%
1203 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0008 OT DATA SHEET FOR SHUTDOWN & BLOWDOWN VALVES (FAHM) 1 A 0.042% 2‐May‐17 12‐May‐17 17‐May‐17 17‐Jun‐17 8‐Jul‐17 18‐Jul‐17 31‐Oct‐18 4‐Apr‐17 15‐Aug‐17 17‐Aug‐17 27‐Sep‐17 18‐Oct‐17 26‐Dec‐17 22‐Jul‐19 4‐Apr‐17 15‐Aug‐17 17‐Aug‐17 27‐Sep‐17 18‐Oct‐17 26‐Dec‐17 95% 95% 0% 0.040% 0.040%
1204 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0009 OT DATA SHEET FOR CONTROL VALVES (FAHM) 1 A 0.042% 2‐May‐17 12‐May‐17 17‐May‐17 17‐Jun‐17 8‐Jul‐17 18‐Jul‐17 31‐Oct‐18 4‐May‐17 15‐Aug‐17 17‐Aug‐17 30‐Aug‐17 20‐Sep‐17 19‐Oct‐17 22‐Jul‐19 4‐May‐17 15‐Aug‐17 17‐Aug‐17 30‐Aug‐17 20‐Sep‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
1205 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0010 OT DATA SHEET FOR FLOWMETER ‐ VORTEX (FAHM) 1 A 0.042% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 10‐May‐17 19‐Jun‐17 20‐Jun‐17 22‐Aug‐17 19‐Sep‐17 20‐Sep‐17 22‐Jul‐19 10‐May‐17 19‐Jun‐17 20‐Jun‐17 22‐Aug‐17 19‐Sep‐17 20‐Sep‐17 95% 95% 0% 0.040% 0.040%
1206 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0011 OT DATA SHEET FOR RESTRICTION ORIFICE (FAHM) 1 A 0.028% 13‐May‐17 23‐May‐17 28‐May‐17 28‐Jun‐17 19‐Jul‐17 29‐Jul‐17 31‐Oct‐18 25‐May‐17 19‐Sep‐17 20‐Sep‐17 18‐Oct‐17 8‐Nov‐17 8‐Nov‐17 22‐Jul‐19 25‐May‐17 19‐Sep‐17 20‐Sep‐17 18‐Oct‐17 8‐Nov‐17 8‐Nov‐17 95% 95% 0% 0.026% 0.026%
1207 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0012 OT DATA SHEET FOR FIRE & GAS DEVICES (FAHM) 1 A 0.042% 22‐May‐17 1‐Jun‐17 6‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 15‐May‐17 17‐Jun‐17 18‐Jun‐17 24‐Jul‐17 10‐Aug‐17 28‐Sep‐17 22‐Jul‐19 15‐May‐17 17‐Jun‐17 18‐Jun‐17 24‐Jul‐17 10‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.040% 0.040%
1208 5 INSTRUMENTA 3963‐FAHM‐4‐13‐0013 OT DATA SHEET FOR LEVEL GAUGES (FAHM) 1 B 0.042% 23‐Jun‐17 28‐Jun‐17 1‐Jul‐17 1‐Aug‐17 22‐Aug‐17 1‐Sep‐17 31‐Oct‐18 15‐May‐17 19‐Jul‐17 20‐Jul‐17 20‐Jul‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 15‐May‐17 19‐Jul‐17 20‐Jul‐17 20‐Jul‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.040% 0.040%
1209 5 INSTRUMENTA 3963‐FAHM‐4‐00‐0001 OT INSTRUMENT INDEX (FAHM) 1 A 0.028% 30‐May‐17 9‐Jun‐17 14‐Jun‐17 15‐Jul‐17 5‐Aug‐17 15‐Aug‐17 31‐Oct‐18 31‐May‐17 10‐Jun‐17 11‐Jun‐17 2‐Aug‐17 3‐Aug‐17 5‐Oct‐17 22‐Jul‐19 31‐May‐17 10‐Jun‐17 11‐Jun‐17 2‐Aug‐17 3‐Aug‐17 5‐Oct‐17 95% 95% 0% 0.026% 0.026%
1210 5 INSTRUMENTA 3963‐FAHM‐4‐39‐0001 OT INPUT / OUTPUT LIST ‐ DCS/ESD/F&G (FAHM) 1 A 0.028% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 8‐Jun‐17 10‐Jul‐17 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 22‐Jul‐19 8‐Jun‐17 10‐Jul‐17 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 95% 95% 0% 0.026% 0.026%
1211 5 INSTRUMENTA 3963‐FAHM‐4‐67‐0001 OT ALARM & TRIP LIST (MAJOR INPUT BY PROCESS) (FAHM) 1 A 0.028% 19‐Jun‐17 29‐Jun‐17 4‐Jul‐17 4‐Aug‐17 25‐Aug‐17 4‐Sep‐17 31‐Oct‐18 22‐Jun‐17 30‐Jul‐17 31‐Jul‐17 17‐Sep‐17 25‐Sep‐17 10‐Dec‐17 22‐Jul‐19 22‐Jun‐17 30‐Jul‐17 31‐Jul‐17 17‐Sep‐17 25‐Sep‐17 10‐Dec‐17 95% 95% 0% 0.026% 0.026%
1212 5 INSTRUMENTA 3963‐FAHM‐4‐37‐0001 OT INSTRUMENT CABLE SCHEDULE ‐ DCS/ESD/F&G (FAHM) 1 A 0.028% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 29‐Jul‐17 30‐Jul‐17 4‐Oct‐17 18‐Oct‐17 19‐Oct‐17 22‐Jul‐19 28‐Jun‐17 29‐Jul‐17 30‐Jul‐17 4‐Oct‐17 18‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.026% 0.026%
1213 5 INSTRUMENTA 3963‐FAHM‐4‐30‐0002 OT INSTRUMENT JUNCTION BOX SCHEDULE (FAHM) 1 A 0.028% 28‐Jun‐17 8‐Jul‐17 13‐Jul‐17 13‐Aug‐17 3‐Sep‐17 13‐Sep‐17 31‐Oct‐18 28‐Jun‐17 2‐Aug‐17 3‐Aug‐17 4‐Oct‐17 16‐Oct‐17 29‐Nov‐17 22‐Jul‐19 28‐Jun‐17 2‐Aug‐17 3‐Aug‐17 4‐Oct‐17 16‐Oct‐17 29‐Nov‐17 95% 95% 0% 0.026% 0.026%
1214 5 INSTRUMENTA 3963‐FAHM‐4‐31‐0001 OT INSTRUMENT MTO’S (FAHM) 3 A 0.042% 10‐Aug‐17 20‐Aug‐17 25‐Aug‐17 8‐Sep‐17 13‐Sep‐17 13‐Sep‐17 31‐Oct‐18 28‐Sep‐17 29‐Sep‐17 1‐Oct‐17 8‐Nov‐17 8‐Nov‐17 14‐Dec‐17 22‐Jul‐19 28‐Sep‐17 29‐Sep‐17 1‐Oct‐17 8‐Nov‐17 8‐Nov‐17 14‐Dec‐17 95% 95% 0% 0.040% 0.040%
1215 5 INSTRUMENTA 3963‐FAHM‐4‐55‐0001 OT INSTRUMENT CABLE BLOCK DIAGRAM (FAHM) 1 A 0.028% 6‐May‐17 16‐May‐17 21‐May‐17 21‐Jun‐17 12‐Jul‐17 22‐Jul‐17 31‐Oct‐18 25‐May‐17 5‐Jun‐17 5‐Jun‐17 26‐Jul‐17 10‐Aug‐17 19‐Oct‐17 22‐Jul‐19 25‐May‐17 5‐Jun‐17 5‐Jun‐17 26‐Jul‐17 10‐Aug‐17 19‐Oct‐17 95% 95% 0% 0.026% 0.026%
1216 5 INSTRUMENTA 3963‐FAHM‐4‐56‐0001 OT F&G CABLE BLOCK DIAGRAM (FAHM) 1 A 0.028% 13‐May‐17 23‐May‐17 28‐May‐17 28‐Jun‐17 19‐Jul‐17 29‐Jul‐17 31‐Oct‐18 25‐May‐17 5‐Jun‐17 5‐Jun‐17 26‐Jul‐17 10‐Aug‐17 19‐Oct‐17 22‐Jul‐19 25‐May‐17 5‐Jun‐17 5‐Jun‐17 26‐Jul‐17 10‐Aug‐17 19‐Oct‐17 95% 95% 0% 0.026% 0.026%
1217 5 INSTRUMENTA 3963‐FAHM‐4‐50‐0001 OT INSTRUMENT LOCATION LAYOUT (FAHM) 1 A 0.042% 29‐Apr‐17 9‐May‐17 14‐May‐17 14‐Jun‐17 5‐Jul‐17 15‐Jul‐17 31‐Oct‐18 18‐May‐17 19‐May‐17 21‐May‐17 5‐Oct‐17 12‐Oct‐17 12‐Oct‐17 22‐Jul‐19 18‐May‐17 19‐May‐17 21‐May‐17 5‐Oct‐17 12‐Oct‐17 12‐Oct‐17 95% 95% 0% 0.040% 0.040%
1218 5 INSTRUMENTA 3963‐FAHM‐4‐65‐0001 OT INSTRUMENT INTERCONNECTION DIAGRAM (FAHM) 1 A 0.042% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 11‐Jul‐17 10‐Oct‐17 12‐Oct‐17 19‐Nov‐17 7‐Dec‐17 7‐Dec‐17 22‐Jul‐19 11‐Jul‐17 10‐Oct‐17 12‐Oct‐17 19‐Nov‐17 7‐Dec‐17 7‐Dec‐17 95% 95% 0% 0.040% 0.040%
1219 5 INSTRUMENTA 3963‐FAHM‐4‐65‐0002 OT FIRE & GAS INTERCONNECTION DIAGRAM (FAHM) 1 A 0.042% 21‐Jun‐17 1‐Jul‐17 6‐Jul‐17 6‐Aug‐17 27‐Aug‐17 6‐Sep‐17 31‐Oct‐18 22‐Jun‐17 20‐Oct‐17 22‐Oct‐17 27‐Nov‐17 11‐Dec‐17 11‐Dec‐17 22‐Jul‐19 22‐Jun‐17 20‐Oct‐17 22‐Oct‐17 27‐Nov‐17 11‐Dec‐17 11‐Dec‐17 95% 95% 0% 0.040% 0.040%
1220 5 INSTRUMENTA 3963‐FAHM‐4‐66‐0001 OT INSTRUMENT LOOP DIAGRAM (FAHM) 1 A 0.056% 8‐Jul‐17 18‐Jul‐17 23‐Jul‐17 23‐Aug‐17 10‐Sep‐17 17‐Sep‐17 31‐Oct‐18 11‐Jul‐17 17‐Nov‐17 19‐Nov‐17 7‐Dec‐17 12‐Mar‐18 12‐Mar‐18 22‐Jul‐19 11‐Jul‐17 17‐Nov‐17 19‐Nov‐17 7‐Dec‐17 12‐Mar‐18 12‐Mar‐18 95% 95% 0% 0.053% 0.053%
1221 5 INSTRUMENTA 3963‐FAHM‐4‐66‐0002 OT FIRE & GAS LOOP DIAGRAM (FAHM) 1 A 0.028% 29‐Jul‐17 8‐Aug‐17 13‐Aug‐17 31‐Aug‐17 10‐Sep‐17 20‐Sep‐17 31‐Oct‐18 19‐Oct‐17 4‐Nov‐17 6‐Nov‐17 29‐Nov‐17 11‐Jan‐18 11‐Jan‐18 22‐Jul‐19 19‐Oct‐17 4‐Nov‐17 6‐Nov‐17 29‐Nov‐17 11‐Jan‐18 11‐Jan‐18 95% 95% 0% 0.026% 0.026%
1222 5 INSTRUMENTA 3963‐FAHN‐4‐45‐0001 OT SCOPE OF WORK FOR EXISTING SYSTEM MODIFICATIONS (FAHN) 1 A 0.028% 14‐Jun‐17 24‐Jun‐17 29‐Jun‐17 30‐Jul‐17 20‐Aug‐17 30‐Aug‐17 31‐Oct‐18 8‐Jul‐17 26‐Jul‐17 27‐Jul‐17 12‐Sep‐17 25‐Sep‐17 19‐Oct‐17 22‐Jul‐19 8‐Jul‐17 26‐Jul‐17 27‐Jul‐17 12‐Sep‐17 25‐Sep‐17 19‐Oct‐17 95% 95% 0% 0.026% 0.026%
1223 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0001 OT DATA SHEET FOR PRESSURE GAUGES (FAHN) 1 B 0.028% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 15‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 22‐Jul‐19 15‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 95% 95% 0% 0.026% 0.026%
1224 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0002 OT DATA SHEET FOR TEMP GAUGES (FAHN) 1 B 0.028% 24‐May‐17 3‐Jun‐17 8‐Jun‐17 9‐Jul‐17 30‐Jul‐17 9‐Aug‐17 31‐Oct‐18 15‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 4‐Oct‐17 22‐Jul‐19 15‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 4‐Oct‐17 95% 95% 0% 0.026% 0.026%
1225 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0003 OT DATA SHEET FOR PRESSURE TRANSMITTERS (FAHN) 1 B 0.028% 16‐May‐17 26‐May‐17 31‐May‐17 1‐Jul‐17 22‐Jul‐17 1‐Aug‐17 31‐Oct‐18 15‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 22‐Jul‐19 15‐May‐17 13‐Jun‐17 14‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 95% 95% 0% 0.026% 0.026%
1226 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0004 OT DATA SHEET FOR TEMP TRANSMITTERS (FAHN) 1 B 0.028% 16‐May‐17 26‐May‐17 31‐May‐17 1‐Jul‐17 22‐Jul‐17 1‐Aug‐17 31‐Oct‐18 15‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 22‐Jul‐19 15‐May‐17 10‐Jun‐17 11‐Jun‐17 15‐Jul‐17 19‐Jul‐17 24‐Sep‐17 95% 95% 0% 0.026% 0.026%
1227 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0005 OT DATA SHEET FOR FLOWMETER ‐ CORIOLIS (FAHN) 1 A 0.042% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 25‐May‐17 11‐Jul‐17 12‐Jul‐17 22‐Aug‐17 4‐Oct‐17 4‐Oct‐17 22‐Jul‐19 25‐May‐17 11‐Jul‐17 12‐Jul‐17 22‐Aug‐17 4‐Oct‐17 4‐Oct‐17 95% 95% 0% 0.040% 0.040%
1228 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0006 OT DATA SHEET FOR LEVEL TRANSMITTERS (FAHN) 1 B 0.028% 22‐May‐17 1‐Jun‐17 6‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 17‐May‐17 19‐Jul‐17 20‐Jul‐17 14‐Sep‐17 25‐Sep‐17 14‐Dec‐17 22‐Jul‐19 17‐May‐17 19‐Jul‐17 20‐Jul‐17 14‐Sep‐17 25‐Sep‐17 14‐Dec‐17 95% 95% 0% 0.026% 0.026%
1229 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0007 OT DATA SHEET FOR BS&W ANALYSERS (FAHN) 1 A 0.042% 13‐May‐17 23‐May‐17 28‐May‐17 28‐Jun‐17 19‐Jul‐17 29‐Jul‐17 31‐Oct‐18 25‐May‐17 18‐Jun‐17 19‐Jun‐17 26‐Jul‐17 24‐Sep‐17 24‐Sep‐17 22‐Jul‐19 25‐May‐17 18‐Jun‐17 19‐Jun‐17 26‐Jul‐17 24‐Sep‐17 24‐Sep‐17 95% 95% 0% 0.040% 0.040%
1230 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0008 OT DATA SHEET FOR SHUTDOWN & BLOWDOWN VALVES (FAHN) 1 A 0.042% 2‐May‐17 12‐May‐17 17‐May‐17 17‐Jun‐17 8‐Jul‐17 18‐Jul‐17 31‐Oct‐18 4‐Apr‐17 15‐Aug‐17 17‐Aug‐17 27‐Sep‐17 18‐Oct‐17 26‐Dec‐17 22‐Jul‐19 4‐Apr‐17 15‐Aug‐17 17‐Aug‐17 27‐Sep‐17 18‐Oct‐17 26‐Dec‐17 95% 95% 0% 0.040% 0.040%
1231 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0009 OT DATA SHEET FOR CONTROL VALVES (FAHN) 1 A 0.042% 2‐May‐17 12‐May‐17 17‐May‐17 17‐Jun‐17 8‐Jul‐17 18‐Jul‐17 31‐Oct‐18 3‐May‐17 1‐Aug‐17 3‐Aug‐17 30‐Aug‐17 20‐Sep‐17 19‐Oct‐17 22‐Jul‐19 3‐May‐17 1‐Aug‐17 3‐Aug‐17 30‐Aug‐17 20‐Sep‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
1232 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0010 OT DATA SHEET FOR FLOWMETER ‐ VORTEX (FAHN) 1 B 0.042% 8‐May‐17 18‐May‐17 23‐May‐17 23‐Jun‐17 14‐Jul‐17 24‐Jul‐17 31‐Oct‐18 10‐May‐17 19‐Jun‐17 20‐Jun‐17 22‐Aug‐17 18‐Oct‐17 19‐Oct‐17 22‐Jul‐19 10‐May‐17 19‐Jun‐17 20‐Jun‐17 22‐Aug‐17 18‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.040% 0.040%
1233 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0011 OT DATA SHEET FOR RESTRICTION ORIFICE (FAHN) 1 A 0.028% 13‐May‐17 23‐May‐17 28‐May‐17 28‐Jun‐17 19‐Jul‐17 29‐Jul‐17 31‐Oct‐18 25‐May‐17 19‐Sep‐17 20‐Sep‐17 18‐Oct‐17 8‐Nov‐17 8‐Nov‐17 22‐Jul‐19 25‐May‐17 19‐Sep‐17 20‐Sep‐17 18‐Oct‐17 8‐Nov‐17 8‐Nov‐17 95% 95% 0% 0.026% 0.026%
1234 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0012 OT DATA SHEET FOR FIRE & GAS DEVICES (FAHN) 1 A 0.042% 22‐May‐17 1‐Jun‐17 6‐Jun‐17 6‐Jul‐17 27‐Jul‐17 6‐Aug‐17 31‐Oct‐18 17‐May‐17 17‐Jun‐17 18‐Jun‐17 24‐Jul‐17 10‐Aug‐17 28‐Sep‐17 22‐Jul‐19 17‐May‐17 17‐Jun‐17 18‐Jun‐17 24‐Jul‐17 10‐Aug‐17 28‐Sep‐17 95% 95% 0% 0.040% 0.040%
1235 5 INSTRUMENTA 3963‐FAHN‐4‐13‐0013 OT DATA SHEET FOR LEVEL GAUGES (FAHN) 1 B 0.042% 23‐Jun‐17 28‐Jun‐17 1‐Jul‐17 1‐Aug‐17 22‐Aug‐17 6‐Aug‐17 31‐Oct‐18 15‐May‐17 19‐Jul‐17 20‐Jul‐17 20‐Jul‐17 22‐Aug‐17 23‐Aug‐17 22‐Jul‐19 15‐May‐17 19‐Jul‐17 20‐Jul‐17 20‐Jul‐17 22‐Aug‐17 23‐Aug‐17 95% 95% 0% 0.040% 0.040%
1236 5 INSTRUMENTA 3963‐FAHN‐4‐00‐0001 OT INSTRUMENT INDEX (FAHN) 1 A 0.028% 30‐May‐17 9‐Jun‐17 14‐Jun‐17 15‐Jul‐17 5‐Aug‐17 15‐Aug‐17 31‐Oct‐18 31‐May‐17 10‐Jun‐17 11‐Jun‐17 2‐Aug‐17 3‐Aug‐17 20‐Nov‐17 22‐Jul‐19 31‐May‐17 10‐Jun‐17 11‐Jun‐17 2‐Aug‐17 3‐Aug‐17 20‐Nov‐17 95% 95% 0% 0.026% 0.026%
1237 5 INSTRUMENTA 3963‐FAHN‐4‐39‐0001 OT INPUT / OUTPUT LIST ‐ DCS/ESD/F&G (FAHN) 1 A 0.028% 5‐Jun‐17 15‐Jun‐17 20‐Jun‐17 21‐Jul‐17 11‐Aug‐17 21‐Aug‐17 31‐Oct‐18 8‐Jun‐17 10‐Jul‐17 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 22‐Jul‐19 8‐Jun‐17 10‐Jul‐17 11‐Jul‐17 2‐Aug‐17 3‐Aug‐17 7‐Dec‐17 95% 95% 0% 0.026% 0.026%
1238 5 INSTRUMENTA 3963‐FAHN‐4‐67‐0001 OT ALARM & TRIP LIST (MAJOR INPUT BY PROCESS) (FAHN) 1 A 0.028% 19‐Jun‐17 29‐Jun‐17 4‐Jul‐17 4‐Aug‐17 25‐Aug‐17 4‐Sep‐17 31‐Oct‐18 22‐Jun‐17 30‐Jul‐17 31‐Jul‐17 17‐Sep‐17 25‐Sep‐17 10‐Dec‐17 22‐Jul‐19 22‐Jun‐17 30‐Jul‐17 31‐Jul‐17 17‐Sep‐17 25‐Sep‐17 10‐Dec‐17 95% 95% 0% 0.026% 0.026%
1239 5 INSTRUMENTA 3963‐FAHN‐4‐37‐0001 OT INSTRUMENT CABLE SCHEDULE ‐ DCS/ESD/F&G (FAHN) 1 A 0.028% 25‐Jun‐17 5‐Jul‐17 10‐Jul‐17 10‐Aug‐17 31‐Aug‐17 10‐Sep‐17 31‐Oct‐18 28‐Jun‐17 29‐Jul‐17 30‐Jul‐17 4‐Oct‐17 18‐Oct‐17 19‐Oct‐17 22‐Jul‐19 28‐Jun‐17 29‐Jul‐17 30‐Jul‐17 4‐Oct‐17 18‐Oct‐17 19‐Oct‐17 95% 95% 0% 0.026% 0.026%

Page 10 of 13
Page 81 of 170
PROJECT PLANNING PACKAGE

Attachment 8

PROCUREMENT REGISTER

Page 82 of 170
Procurement Control Register - Equipment
Project No. - 3963
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS"
As Of : 25-Oct-18
Materails QP inspected and All Spare parts
SL. Proc. Issue RFQ to Issue Purchase Approve Vendor Received Filled SPIR Inspection cleared & Ex-works Del. & FOB
Description Sec. Issue MR received and cleared material at received & SPIR % Weight % Progress
No. Category Vendors Order Document (QP) (Mftg.) FAT Complete
cleared at site site completed
Progress Scale 5% 10% 15% 30% 40% 60% 70% 85% 90% 100% WTGE % Phy. Comp. % Variance
1.0 LONG LEAD ITEMS P 75.800% (10.569)

F 75.80% 65.231% 0.00%

A 65.231%
1 Equipment
P 13-May-17 13-May-17 19-Jul-17 10-Sep-17 08-Dec-17 04-Jul-18 10-Jul-18 24-Jul-18 27-Jul-18 27-Jul-18 100.00% 0.00
1.1 Test Separator F 28-May-17 12-Jun-17 12-Sep-17 26-Oct-17 18-Jan-18 11-Jun-18 14-Jun-18 03-Jul-18 25-Aug-18 25-Aug-18 12.16% 100.00% 0.00
A 28-May-17 12-Jun-17 12-Sep-17 26-Oct-17 18-Jan-18 11-Jun-18 14-Jun-18 03-Jul-18 25-Aug-18 25-Aug-18 100.00%
P 01-Jun-17 01-Jun-17 09-Aug-17 12-Oct-17 09-Jan-18 12-Feb-18 18-Feb-18 03-Apr-18 06-Apr-18 06-Apr-18 100.00% (15.00)
1.2 BS&W Meter F 12-Jul-17 23-Jul-17 18-Jan-18 17-May-18 24-May-18 12-Jul-18 30-Aug-18 04-Oct-18 29-Nov-18 29-Nov-18 3.42% 85.00% 0.00
A 12-Jul-17 23-Jul-17 18-Jan-18 17-May-18 24-May-18 12-Jul-18 30-Aug-18 04-Oct-18 85.00%
P 13-May-17 13-May-17 19-Jul-17 10-Sep-17 08-Dec-17 04-Jul-18 10-Jul-18 24-Jul-18 27-Jul-18 27-Jul-18 100.00% 0.00
1.3 Sand Jetting F 28-May-17 12-Jun-17 12-Sep-17 26-Oct-17 18-Jan-18 11-Jun-18 14-Jun-18 03-Jul-18 25-Aug-18 25-Aug-18 1.47% 100.00% 0.00
A 28-May-17 12-Jun-17 12-Sep-17 26-Oct-17 18-Jan-18 11-Jun-18 14-Jun-18 03-Jul-18 25-Aug-18 25-Aug-18 100.00%
2 Piping
P 03-Apr-17 03-Apr-17 08-May-17 27-May-17 15-Jun-17 15-Aug-17 28-Aug-17 30-Sep-17 04-Oct-17 04-Oct-17 100.00% 0.00
2.1 Early Tie-in Valves F 03-Apr-17 03-Apr-17 11-May-17 04-Jul-17 03-Aug-17 24-Aug-17 21-Sep-17 31-Oct-17 27-Nov-17 27-Nov-17 1.51% 100.00% 0.00
A 03-Apr-17 03-Apr-17 11-May-17 04-Jul-17 03-Aug-17 24-Aug-17 21-Sep-17 31-Oct-17 27-Nov-17 27-Nov-17 100.00%
3 Instrumentation
P 10-Aug-17 10-Aug-17 19-Oct-17 07-Dec-17 05-Jan-18 02-Feb-18 08-Feb-18 09-Mar-18 12-Mar-18 12-Mar-18 100.00% (15.00)
ELECTRONIC
3.1 F 19-Jul-17 23-Jul-17 18-Jan-18 22-Apr-18 10-May-18 30-Aug-18 03-Sep-18 27-Sep-18 10-Dec-18 10-Dec-18 4.16% 85.00% 0.00
INSTRUMENTS (PT/TT)
A 19-Jul-17 23-Jul-17 18-Jan-18 22-Apr-18 10-May-18 30-Aug-18 03-Sep-18 27-Sep-18 85.00%
P 10-Aug-17 10-Aug-17 19-Oct-17 07-Dec-17 05-Jan-18 02-Feb-18 08-Feb-18 09-Mar-18 12-Mar-18 12-Mar-18 100.00% (15.00)
LEVEL GAUGES
3.2 F 24-Jul-17 26-Jul-17 12-Dec-17 28-Mar-18 08-Feb-18 02-Sep-18 02-Sep-18 03-Oct-18 10-Dec-18 10-Dec-18 0.46% 85.00% 0.00
(MAGNETIC)
A 24-Jul-17 26-Jul-17 12-Dec-17 28-Mar-18 08-Feb-18 02-Sep-18 02-Sep-18 03-Oct-18 85.00%
P 10-Aug-17 10-Aug-17 19-Oct-17 07-Dec-17 05-Jan-18 02-Feb-18 08-Feb-18 09-Mar-18 12-Mar-18 12-Mar-18 100.00% (15.00)
3.3 GAUGES (PG/TG) Field F 20-Jul-17 23-Jul-17 30-Jan-18 28-Mar-18 15-Feb-18 30-Aug-18 02-Sep-18 13-Sep-18 10-Dec-18 10-Dec-18 3.24% 85.00% 0.00
A 20-Jul-17 23-Jul-17 30-Jan-18 28-Mar-18 15-Feb-18 30-Aug-18 02-Sep-18 13-Sep-18 85.00%
Instrumentat
P 10-Aug-17 10-Aug-17 19-Oct-17 07-Dec-17 05-Jan-18 02-Feb-18 08-Feb-18 09-Mar-18 12-Mar-18 12-Mar-18 100.00% (40.00)
LEVEL GAUGES (GLASS ion
3.4 F 24-Jul-17 26-Jul-17 15-Feb-18 02-Sep-18 17-May-18 05-Sep-18 04-Dec-18 07-Dec-18 10-Dec-18 10-Dec-18 0.46% 60.00% 0.00
TYPE)
A 24-Jul-17 26-Jul-17 15-Feb-18 02-Sep-18 17-May-18 05-Sep-18 60.00%
P 10-Aug-17 10-Aug-17 19-Oct-17 07-Dec-17 05-Jan-18 02-Feb-18 08-Feb-18 09-Mar-18 12-Mar-18 12-Mar-18 100.00% (30.00)
LEVEL TRANSMITTERS
3.5 F 25-Jul-17 30-Jul-17 28-Dec-17 29-Apr-18 08-Feb-18 02-Sep-18 10-Sep-18 01-Nov-18 10-Dec-18 10-Dec-18 0.92% 70.00% 0.00
(DISPLACER)
A 25-Jul-17 30-Jul-17 28-Dec-17 29-Apr-18 08-Feb-18 02-Sep-18 10-Sep-18 01-Nov-18 70.00%
P 10-Aug-17 10-Aug-17 19-Oct-17 07-Dec-17 05-Jan-18 02-Feb-18 08-Feb-18 09-Mar-18 12-Mar-18 12-Mar-18 100.00% (30.00)
LEVEL TRANSMITTERS
3.6 F 25-Jul-17 30-Jul-17 30-Jan-18 12-Apr-18 15-Mar-18 02-Sep-18 10-Sep-18 29-Nov-18 10-Dec-18 10-Dec-18 1.39% 70.00% 0.00
(RADAR)
A 25-Jul-17 30-Jul-17 30-Jan-18 12-Apr-18 15-Mar-18 02-Sep-18 10-Sep-18 70.00%
P 15-Jun-17 15-Jun-17 23-Aug-17 11-Oct-17 08-Jan-18 24-Feb-18 02-Mar-18 15-Apr-18 18-Apr-18 18-Apr-18 100.00% 0.00
3.7 RESTRICTION ORIFICE F 02-Aug-17 12-Nov-17 15-Feb-18 10-May-18 15-Mar-18 04-Jul-18 12-Jul-18 02-Aug-18 03-Sep-18 03-Sep-18 2.09% 100.00% 0.00
A 02-Aug-17 12-Nov-17 15-Feb-18 10-May-18 15-Mar-18 04-Jul-18 12-Jul-18 02-Aug-18 03-Sep-18 03-Sep-18 100.00%
P 15-Jun-17 15-Jun-17 23-Aug-17 11-Oct-17 08-Jan-18 24-Feb-18 02-Mar-18 15-Apr-18 18-Apr-18 18-Apr-18 100.00% (40.00)
SHUTDOWN & BLOWDOWN
3.8 Control F 19-Jun-17 20-Aug-17 05-Apr-18 30-Aug-18 15-Sep-18 02-Oct-18 29-Nov-18 16-Dec-18 20-Dec-18 20-Dec-18 2.09% 60.00% 0.00
VALVES
Valve / SD & A 19-Jun-17 20-Aug-17 05-Apr-18 30-Aug-18 15-Sep-18 02-Oct-18 60.00%
P 15-Jun-17 15-Jun-17 23-Aug-17 11-Oct-17 08-Jan-18 24-Feb-18 02-Mar-18 15-Apr-18 18-Apr-18 18-Apr-18 100.00% (15.00)
BD Valve /
3.9 FLOW TRANSMITTERS F 13-Jul-17 23-Jul-17 18-Jan-18 06-May-18 15-Feb-18 20-Sep-18 25-Sep-18 30-Sep-18 10-Dec-18 10-Dec-18 2.09% 85.00% 0.00
PRV/ Orifice
A 13-Jul-17 23-Jul-17 18-Jan-18 06-May-18 15-Feb-18 20-Sep-18 25-Sep-18 30-Sep-18 85.00%
/ Flow P 15-Jun-17 15-Jun-17 23-Aug-17 11-Oct-17 08-Jan-18 24-Feb-18 02-Mar-18 15-Apr-18 18-Apr-18 18-Apr-18 100.00% 0.00
3.10 CONTROL VALVES Meters F 03-Aug-17 06-Aug-17 19-Nov-17 28-Dec-17 13-Dec-17 28-May-18 31-May-18 12-Jul-18 28-Aug-18 28-Aug-18 2.09% 100.00% 0.00
A 03-Aug-17 06-Aug-17 19-Nov-17 28-Dec-17 13-Dec-17 28-May-18 31-May-18 12-Jul-18 28-Aug-18 28-Aug-18 100.00%

Page 83 of 170
Procurement Control Register - Equipment
Project No. - 3963
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS"
As Of : 25-Oct-18
Materails QP inspected and All Spare parts
SL. Proc. Issue RFQ to Issue Purchase Approve Vendor Received Filled SPIR Inspection cleared & Ex-works Del. & FOB
Description Sec. Issue MR received and cleared material at received & SPIR % Weight % Progress
No. Category Vendors Order Document (QP) (Mftg.) FAT Complete
cleared at site site completed
Progress Scale 5% 10% 15% 30% 40% 60% 70% 85% 90% 100% WTGE % Phy. Comp. % Variance
P 15-Jun-17 15-Jun-17 23-Aug-17 11-Oct-17 08-Jan-18 24-Feb-18 02-Mar-18 15-Apr-18 18-Apr-18 18-Apr-18 100.00% (15.00)
3.11 PRESSURE RELIEF VALVES F 15-Aug-17 19-Aug-17 04-Jan-18 27-Mar-18 19-Mar-18 28-Jun-18 05-Jul-18 15-Sep-18 10-Dec-18 10-Dec-18 2.09% 85.00% 0.00
A 15-Aug-17 19-Aug-17 04-Jan-18 27-Mar-18 19-Mar-18 28-Jun-18 05-Jul-18 15-Sep-18 85.00%
EXISTING SYSTEM P 29-Jun-17 29-Jun-17 06-Sep-17 25-Oct-17 22-Jan-18 27-Mar-18 02-Apr-18 01-May-18 04-May-18 04-May-18 100.00% 0.00
3.12 MODIFICATIONS F 03-Aug-17 17-Oct-01 28-Dec-17 17-May-18 08-Feb-18 19-Jul-18 19-Jul-18 19-Jul-18 19-Jul-18 19-Jul-18 4.00% 100.00% 0.00
(HONEYWELL) A 03-Aug-17 17-Oct-01 28-Dec-17 17-May-18 08-Feb-18 19-Jul-18 19-Jul-18 19-Jul-18 19-Jul-18 19-Jul-18 100.00%
EXISTING SYSTEM Modification P 29-Jun-17 29-Jun-17 06-Sep-17 25-Oct-17 22-Jan-18 27-Mar-18 02-Apr-18 01-May-18 04-May-18 04-May-18 100.00% (15.00)
3.13 MODIFICATIONS of Existing F 10-Aug-17 17-Oct-17 28-Dec-17 17-May-18 10-May-18 07-Jun-18 12-Jul-18 27-Sep-18 10-Dec-18 10-Dec-18 8.00% 85.00% 0.00
(EMERSON) System, A 10-Aug-17 17-Oct-17 28-Dec-17 17-May-18 10-May-18 07-Jun-18 12-Jul-18 27-Sep-18 85.00%
EXISTING SYSTEM Yokogawa,E P 29-Jun-17 29-Jun-17 06-Sep-17 25-Oct-17 22-Jan-18 27-Mar-18 02-Apr-18 01-May-18 04-May-18 04-May-18 100.00% 0.00
3.14 MODIFICATIONS merson, F 27-Jul-17 10-Aug-17 21-Dec-17 21-Dec-17 21-Dec-17 28-Dec-17 04-Jan-18 11-Jan-18 18-Jan-18 18-Jan-18 6.00% 100.00% 0.00
(YOKOGAWA)-KHATIYAH Honey well A 27-Jul-17 10-Aug-17 21-Dec-17 21-Dec-17 21-Dec-17 28-Dec-17 04-Jan-18 11-Jan-18 18-Jan-18 18-Jan-18 100.00%
EXISTING SYSTEM P 29-Jun-17 29-Jun-17 06-Sep-17 25-Oct-17 22-Jan-18 27-Mar-18 02-Apr-18 01-May-18 04-May-18 04-May-18 100.00% (15.00)
3.15 MODIFICATIONS F 27-Jul-17 10-Aug-17 21-Dec-17 28-Jun-18 10-May-18 05-Sep-18 05-Sep-18 27-Sep-18 10-Dec-18 10-Dec-18 2.00% 85.00% 0.00
(YOKOGAWA)-JALEHA A 27-Jul-17 10-Aug-17 21-Dec-17 28-Jun-18 10-May-18 05-Sep-18 05-Sep-18 27-Sep-18 85.00%
4 Electrical
P 10-Jul-17 10-Jul-17 18-Sep-17 06-Nov-17 20-Nov-17 09-Dec-17 15-Dec-17 13-Jan-18 16-Jan-18 16-Jan-18 100.00% 0.00
4.1 Junction Box/Lighting Fixture F 30-Jul-17 14-Aug-17 06-Mar-18 07-May-18 10-May-18 31-May-18 18-Jul-18 26-Aug-18 30-Sep-18 30-Sep-18 0.68% 100.00% 0.00
A 30-Jul-17 14-Aug-17 06-Mar-18 07-May-18 10-May-18 31-May-18 18-Jul-18 26-Aug-18 30-Sep-18 30-Sep-18 100.00%
5 Loss Preventation
P 11-Jul-17 11-Jul-17 23-Sep-17 11-Nov-17 25-Dec-17 24-Feb-18 02-Mar-18 31-Mar-18 03-Apr-18 03-Apr-18 100.00% (15.00)
5.1 Fire Detection System F 23-Jul-17 03-Aug-17 25-Jan-18 30-Apr-18 10-May-18 30-Aug-18 30-Aug-18 30-Sep-18 10-Dec-18 10-Dec-18 3.22% 85.00% 0.00
A 23-Jul-17 03-Aug-17 25-Jan-18 30-Apr-18 10-May-18 30-Aug-18 30-Aug-18 30-Sep-18 85.00%
P 20-Jul-17 20-Jul-17 28-Sep-17 16-Nov-17 30-Dec-17 02-Apr-18 08-Apr-18 07-May-18 10-May-18 10-May-18 100.00% (40.00)
Deluge Skids and Fire water
5.2 F 25-Jul-17 03-Aug-17 22-Feb-18 17-May-18 24-May-18 02-Oct-18 03-Jan-19 15-Jan-19 31-Jan-19 31-Jan-19 10.86% 60.00% 0.00
Spray Nozzles
A 25-Jul-17 03-Aug-17 22-Feb-18 17-May-18 24-May-18 02-Oct-18 60.00%
P 20-Jul-17 20-Jul-17 28-Sep-17 16-Nov-17 30-Dec-17 13-Feb-18 19-Feb-18 20-Mar-18 23-Mar-18 23-Mar-18 100.00% (15.00)
Firefighting & Safety
5.3 F 25-Jul-17 03-Aug-17 01-Mar-18 28-Jun-18 17-May-18 13-Sep-18 15-Sep-18 30-Sep-18 27-Dec-18 27-Dec-18 1.40% 85.00% 0.00
Equipment
A 25-Jul-17 03-Aug-17 01-Mar-18 28-Jun-18 17-May-18 13-Sep-18 15-Sep-18 30-Sep-18 85.00%

Page 84 of 170
PROJECT PLANNING PACKAGE

Attachment 9

CONSTRUCTION CONTROL REGISTER

Page 85 of 170
Attachment-6 Construction
CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3-PHASE TEST SEPARATORSTLL DEGASSING STATIONS, DUKHAN
CONSTRUCTION PROGRESS (MONITORING WEIGHTAGE): LAST WEEK Current Week Cumulative

Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
21.00% 100.00%
FABRICATION
KAHM
Structural Steel Fabrication
FAB. OF SEPERATOR & PLATFORM STR. 
1 F0010 2.40 INCL.LADDERS/STAIRS/HR/WW/CROS   FAB KM STFB Kg 9298 9112.04 06‐Sep‐18 20‐Nov‐18 6‐Sep‐18 0.04% 0.21% 100.000% 95.00% 0.00% 3.000% 65.789% 98.000% 32.21%
TRANSFER TO SITE FOR INSTLN.
FAB. OF  METERING SKID 
2 F0040 2.40 INCL.LADDERS/STAIRS/HR/WW/CROS  FAB KM STFB Kg 4078 4078 08‐Aug‐18 15‐Oct‐18 8‐Aug‐18 15‐Oct‐18 0.04% 0.21% 100.000% 95.00% 0.00% 5.000% 100.000% 100.000% 0.00%
TRANSFER TO SITE FOR INSTALLATION
FAB. OF PSV 
INCL.LADDERS/STAIRS/HR/WW/CROS. 
3 F0030 2.40 FAB KM STFB Kg 1705 1705 09‐Aug‐18 23‐Oct‐18 15‐Jul‐18 23‐Oct‐18 0.04% 0.21% 100.000% 98.00% 0.00% 0.000% 100.000% 100.000% 0.00%
STRUCTURE  TRANSFER TO SITE FOR 
INSTALLATION
FAB. OF PIPESUPPORT  STRUCTURE  SHIFT 
4 F0020 XX 2.40 FAB KM STFB Sqm 5780 5780 07‐Jun‐18 12‐Nov‐18 4‐Feb‐18 19‐Jul‐18 0.02% 0.11% 100.000% 100.00% 0.00% 0.000% 88.679% 100.000% 11.32%
TO SITE
FAB. OF PIPESUPPORT  STRUCTURE  SHIFT 
5 F0020 XX 2.40 FAB KM STFB Sqm 1320 1280.4 07‐Jun‐18 12‐Nov‐18 7‐Jun‐18 0.04% 0.21% 100.000% 97.00% 0.00% 0.000% 88.679% 97.000% 8.32%
TO SITE
FABRICATION OF INSTRUMENT STANCHION 
6 F0020‐1 2.40 FAB KM STFB 0 13‐Aug‐18 03‐Sep‐18 20‐Jun‐18 27‐Jul‐18 0.04% 0.21% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
SUPPORTS
Piping Fabrication
FBE PIPING (AT KUWAIT)
PIPING FABRICATION  & FBE COATINGT 
9 F0080 2.10 FAB KM PPFB DIN 2677 535.4 08‐Oct‐18 10‐Dec‐18 08‐Oct‐18 0.17% 0.80% 74.074% 12.00% ‐45.95% 8.000% 28.125% 20.000% ‐8.13%
KUWAIT
10 F0110 2.10 FBE PIPING BULK DELIVERT SITE FAB KM PPFB LM 110 0 05‐Dec‐18 15‐Dec‐18 0.06% 0.27% 0.000% 0.00% 0.00% 0.000% 0.000% 0.000% 0.00%
REMANING PIPING (NON FBE)
12 ETPFKM‐1 2.10 Early Tie‐in Fabrication Works FAB KM PPFB 0 19‐Dec‐17 18‐Jan‐18 19‐Dec‐17 18‐Jan‐18 0.05% 0.23% 100.000% 100.00% 0.00% 0.0% 100.000% 100.00% 0.00%
COMPLETE PIPING FABRICATION   INCL. 
13 F0080‐1 2.10 FAB KM PPFB 0 24‐Oct‐18 08‐Dec‐18 24‐Oct‐18 0.22% 1.07% 91.892% 5.00% ‐87.54% 0.000% 4.348% 5.000% 0.65%
HYDROTEST/ PAINTING & COATING
14 F0110‐1 2.10 FABRICATION SPOOLS DELIVER TO SITE FAB KM PPFB 0 28‐Nov‐18 12‐Dec‐18 0.11% 0.53% 50.000% 0.00% ‐50.00% 0.000% 0.000% 0.000% 0.00%
KAHN
Structural Steel Fabrication
FAB. OF SEPERATOR & PLATFORM STR. 
17 F110 1.40 INCL.LADDERS/STAIRS/HR/WW/CROS  FAB KN STFB Kg 9298 8368.2 19‐Sep‐18 13‐Nov‐18 19‐Sep‐18 0.04% 0.21% 100.000% 75.00% 0.00% 15.000% 66.071% 90.000% 23.93%
TRANSFER TO SITE FOR INSTLN.
FAB. OF  METERING SKID 
18 F140 XX 1.40 INCL.LADDERS/STAIRS/HR/WW/CROS.   FAB KN STFB Kg 4909.18 4909.175 28‐May‐18 16‐Aug‐18 28‐May‐18 19‐Jul‐18 0.02% 0.08% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
TRANSFER TO SITE FOR INSTALLATION
FAB. OF  METERING SKID 
19 F140 XX 1.40 INCL.LADDERS/STAIRS/HR/WW/CROS.   FAB KN STFB Kg 866.325 866.325 28‐May‐18 16‐Aug‐18 28‐May‐18 20‐Aug‐18 0.04% 0.21% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
TRANSFER TO SITE FOR INSTALLATION
FAB. OF PSV 
20 F130 XX 1.40 INCL.LADDERS/STAIRS/HR/WW/CROS.  FAB KN STFB Kg 6570.5 6570.5 17‐May‐18 21‐Aug‐18 17‐May‐18 19‐Jul‐18 0.02% 0.08% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
STRUCTURE  TO SITE FOR INSTALLATION

FAB. OF PSV 
21 F130 XX 1.40 INCL.LADDERS/STAIRS/HR/WW/CROS.  FAB KN STFB Kg 1159.5 1159.5 17‐May‐18 21‐Aug‐18 17‐May‐18 26‐Aug‐18 0.04% 0.21% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
STRUCTURE  TO SITE FOR INSTALLATION
COMPLETE  FAB. OF PIPESUPPORT  
22 F120 XX 1.40 STRUCTURE  TRANSFER TO SITE FOR  FAB KN STFB Kg 7140 7140 9‐May‐18 13‐Nov‐18 5‐Feb‐18 19‐Jul‐18 0.02% 0.08% 100.000% 100.00% 0.00% 0.000% 89.947% 100.000% 10.05%
INSTALLATION
COMPLETE  FAB. OF PIPESUPPORT  
23 F120 XX 1.40 STRUCTURE  TRANSFER TO SITE FOR  FAB KN STFB Kg 1660 1643.4 09‐May‐18 13‐Nov‐18 9‐May‐18 0.04% 0.21% 100.000% 98.00% 0.00% 1.000% 89.947% 99.000% 9.05%
INSTALLATION
FABRICATION OF INSTRUMENT STANCHION 
24 F120‐1 1.40 FAB KN STFB 0 15‐Aug‐18 16‐Sep‐18 26‐Jun‐18 26‐Jul‐18 0.04% 0.21% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
SUPPORTS
Piping Fabrication
FBE PIPING (AT KUWAIT)
PIPING FABRICATION  & FBE COATINGT 
27 F180 1.10 FAB KN PPFB DIN 3118 623.6 08‐Oct‐18 03‐Dec‐18 08‐Oct‐18 0.21% 0.99% 74.074% 12.00% ‐42.50% 8.000% 31.579% 20.000% ‐11.58%
KUWAIT
28 F210 1.10 FBE PIPING BULK DELIVERT SITE FAB KN PPFB LM 147 0 01‐Dec‐18 15‐Dec‐18 0.07% 0.33% 0.000% 0.00% 0.000% 0.000% 0.00%
REMAINING PIPING ( NON FBE)
30 ETPFKN‐1 1.10 Early Tie‐in Fabrication Works FAB KN PPFB 0 19‐Dec‐17 19‐Jan‐18 19‐Dec‐17 19‐Jan‐18 0.06% 0.29% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
COMPLETE PIPING FABRICATION . 
31 F180‐1 1.10 FAB KN PPFB 0 27‐Oct‐18 03‐Dec‐18 27‐Oct‐18 0.28% 1.31% 91.892% 5.00% ‐91.89% 0.000% 0.000% 5.000% 5.00%
HYDROTEST/ PAINTING & COATING
32 F210‐1 1.10 FABRICATION SPOOLS DELIVER TO SITE FAB KN PPFB 0 24‐Nov‐18 08‐Dec‐18 0.14% 0.66% 50.000% ‐50.00% 0.000% 0.000% 0.00%
KAHS
Structural Steel Fabrication
FAB. OF  METERING SKID 
35 F250 XX 3.40 INCL.LADDERS/STAIRS/HR/WW/CROS.   FAB KS STFB Kg 4594.25 4594.25 19‐Jun‐18 26‐Aug‐18 19‐Jun‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
TRANSFER TO SITE FOR INSTALLATION
Page 86 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
FAB. OF  METERING SKID 
36 F250 XX 3.40 INCL.LADDERS/STAIRS/HR/WW/CROS.   FAB KS STFB Kg 810.75 810.75 19‐Jun‐18 26‐Aug‐18 20‐Jun‐18 26‐Aug‐18 0.04% 0.20% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
TRANSFER TO SITE FOR INSTALLATION
FAB. OF PIPESUPPORT  STRUCTURE  
37 F230 XX 3.40 FAB KS STFB Kg 1620 1620 06‐Feb‐18 10‐Nov‐18 6‐Feb‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 0.000% 94.245% 100.000% 5.76%
TRANSFER TO SITE FOR INSTALLATION
FAB. OF PIPESUPPORT  STRUCTURE  
38 F230 XX 3.40 FAB KS STFB Kg 850 833 6‐Feb‐18 10‐Nov‐18 7‐Apr‐18 0.04% 0.20% 100.000% 98.00% 0.00% 98.000% 94.245% 98.000% 3.76%
TRANSFER TO SITE FOR INSTALLATION
FAB. OF SEPERATOR & PLATFORM STR. 
39 F220 3.40 INCL.LADDERS/STAIRS/HR/WW/CROS.  FAB KS STFB Kg 9298 8833.1 16‐Aug‐18 05‐Nov‐18 25‐Aug‐18 0.04% 0.20% 100.000% 92.00% 0.00% 95.000% 86.585% 95.000% 8.41%
TRANSFER TO SITE FOR INSTLN.
FAB. OF PSV 
INCL.LADDERS/STAIRS/HR/WW/CROS. 
40 F240 3.40 FAB KS STFB Kg 1705 1619.75 06‐Feb‐18 05‐Nov‐18 10‐Jul‐18 0.04% 0.20% 100.000% 92.00% 0.00% 95.000% 95.971% 95.000% ‐0.97%
STRUCTURE   TRANSFER TO SITE FOR 
INSTALLATION
FABRICATION OF INSTRUMENT STANCHION 
41 F260‐1 3.40 FAB KS STFB 0 02‐Sep‐18 16‐Sep‐18 26‐Jun‐18 26‐Jul‐18 0.04% 0.20% 100.000% 100.00% 0.00% 100.000% 100.000% 100.000% 0.00%
SUPPORTS
Piping Fabrication
FBE PIPING (AT KUWAIT)
PIPING FABRICATION  & FBE COATINGT 
44 F290 3.10 FAB KS PPFB DIN 2945 589 08‐Oct‐18 03‐Dec‐18 08‐Oct‐18 0.20% 0.93% 58.621% 12.00% ‐27.04% 8.000% 31.579% 20.000% ‐11.58%
KUWAIT
45 F320‐2 3.10 FBE PIPING BULK DELIVERT SITE FAB KS PPFB 0 04‐Dec‐18 13‐Dec‐18 0.07% 0.31% 0.000% 0.00% 0.000% 0.000% 0.00%
REMAINING PIPING (NON ‐ FBE)
47 SDCN100 3.10 Early Tie‐in Fabrication Works FAB KS PPFB 0 19‐Dec‐17 18‐Jan‐18 19‐Dec‐17 18‐Jan‐18 0.06% 0.27% 100.000% 100.00% 0.00% 0.000% 100.000% 100.000% 0.00%
COMPLETE PIPING FABRICATION INCL. 
48 F290‐1 3.10 FAB KS PPFB 0 25‐Oct‐18 24‐Nov‐18 25‐Oct‐18 0.26% 1.24% 91.892% 5.00% ‐88.67% 0.000% 3.226% 5.000% 1.77%
HYDROTEST/ PAINTING & COATING
49 F320‐1 3.10 FABRICATION SPOOLS DELIVER TO SITE FAB KS PPFB 0 18‐Nov‐18 02‐Dec‐18 0.13% 0.62% 62.500% ‐62.50% 0.000% 0.000% 0.00%
JALM
Structural Steel Fabrication
FAB. OF SEPERATOR & PLATFORM STR. 
52 F330 7.40 INCL.LADDERS/STAIRS/HR/WW/CROS.   FAB JL STFB Kg 9298 5578.8 11‐Sep‐18 22‐Dec‐18 11‐Sep‐18 0.09% 0.41% 100.000% 50.00% ‐56.31% 10.000% 43.689% 60.000% 16.31%
TRANSFER TO SITE FOR INSTLN.
FAB. OF METERING SKID 
53 F340 7.40 INCL.LADDERS/STAIRS/HR/WW/CROS.  FAB JL STFB Kg 2470 2173.6 11‐Sep‐18 22‐Dec‐18 11‐Sep‐18 0.01% 0.03% 100.000% 85.00% ‐56.31% 3.000% 43.689% 88.000% 44.31%
TRANSFER TO SITE FOR INSTALLATION
FAB. OF PSV 
INCL.LADDERS/STAIRS/HR/WW/CROS. 
54 F350 7.40 FAB JL STFB Kg 1705 545.6 12‐Sep‐18 22‐Dec‐18 12‐Sep‐18 0.01% 0.06% 100.000% 25.00% ‐56.86% 7.000% 43.137% 32.000% ‐11.14%
STRUCTURE  TRANSFER TO SITE FOR 
INSTALLATION
FAB. OF PIPESUPPORT  STRUCTURE  
55 F360 7.40 FAB JL STFB Kg 4078 1835.1 20‐Sep‐18 31‐Dec‐18 12‐Sep‐18 0.01% 0.06% 79.070% 35.00% ‐44.12% 10.000% 34.951% 45.000% 10.05%
TRANSFER TO SITE FOR INSTALLATION
FABRICATION OF INSTRUMENT STANCHION 
56 F370 7.40 FAB JL STFB PCS 151 151 02‐Sep‐18 16‐Sep‐18 26‐Jun‐18 26‐Jul‐18 0.14% 0.67% 0.000% 100.00% 100.00% 0.000% 100.000% 100.000% 0.00%
SUPPORTS
Piping Fabrication
FBE PIPING (AT KUWAIT)
PIPING FABRICATION  & FBE COATINGT 
59 F400 7.10 FAB JL PPFB DIN 3564 712.8 11‐Oct‐18 22‐Dec‐18 11‐Oct‐18 0.24% 1.14% 48.780% 12.00% ‐28.23% 8.000% 20.548% 20.000% ‐0.55%
KUWAIT
60 F430 7.10 FBE PIPING BULK DELIVERT SITE FAB JL PPFB LM 170 0 23‐Dec‐18 01‐Jan‐19 0.08% 0.38% 0.000% 0.00% 0.000% 0.000% 0.00%
REMAINING PIPING (NON FBE0
COMPLETE PIPING FABRICATION 
62 F400‐1 7.10 FAB JL PPFB 0 28‐Nov‐18 05‐Jan‐19 0.32% 1.51% 65.789% ‐65.79% 5.000% 0.000% 5.000% 5.00%
HYDROTEST/ PAINTING & COATING
63 F430‐1 7.10 FABRICATION SPOOLS DELIVER TO SITE FAB JL PPFB 0 26‐Dec‐18 09‐Jan‐19 0.16% 0.76% 0.000% 0.00% 0.000% 0.000% 0.00%
FAHS
Structural Steel Fabrication
COMPLETE  FAB. OF SEPERATOR & 
PLATFORM STR. 
66 F440 6.40 INCL.LADDERS/STAIRS/HR/WW/CROS. BY  FAB FS STFB Kg 9298 6043.7 11‐Sep‐18 29‐Dec‐18 11‐Sep‐18 0.10% 0.48% 89.474% 60.00% ‐48.56% 5.000% 40.909% 65.000% 24.09%
PETROSERV & TRANSFER TO SITE FOR 
INSTLN.
COMPLETE SS FAB. OF  METERING SKID 
INCL.LADDERS/STAIRS/HR/WW/CROS. BY 
67 F450 6.40 FAB FS STFB Kg 2470 2223 09‐Sep‐18 29‐Dec‐18 9‐Sep‐18 0.01% 0.05% 89.474% 85.00% ‐47.51% 5.000% 41.964% 90.000% 48.04%
PETROSERV & TRANSFER TO SITE FOR 
INSTALLATION
COMPLETE  FAB. OF PSV 
INCL.LADDERS/STAIRS/HR/WW/CROS. 
68 F460 6.40 FAB FS STFB Kg 1705 818.4 11‐Sep‐18 10‐Dec‐18 11‐Sep‐18 0.02% 0.10% 100.000% 40.00% ‐50.55% 8.000% 49.451% 48.000% ‐1.45%
STRUCTURE  BY PETROSERV & TRANSFER TO 
SITE FOR INSTALLATION
COMPLETE  FAB. OF PIPESUPPORT  
69 F470 6.40 STRUCTURE  BY PETROSERV & TRANSFER TO  FAB FS STFB Kg 4078 2039 12‐Sep‐18 19‐Dec‐18 12‐Sep‐18 0.02% 0.10% 86.207% 45.00% ‐41.76% 5.000% 44.444% 50.000% 5.56%
SITE FOR INSTALLATION
FABRICATION OF INSTRUMENT STANCHION 
70 F480 6.40 FAB FS STFB PCS 151 151 03‐Sep‐18 16‐Sep‐18 26‐Jun‐18 27‐Jul‐18 0.12% 0.55% 45.000% 100.00% 55.00% 0.000% 100.000% 100.000% 0.00%
SUPPORTS
Piping Fabrication
FBE PIPING (AT KUWAIT)
PIPING FABRICATION  & FBE COATINGT 
73 F510 6.10 FAB FS PPFB DIN 2678 535.6 18‐Oct‐18 16‐Dec‐18 18‐Oct‐18 0.18% 0.88% 48.780% 12.00% ‐35.45% 8.000% 13.333% 20.000% 6.67%
KUWAIT
74 F540 6.10 FBE PIPING BULK DELIVERT SITE FAB FS PPFB LM 142 0 17‐Dec‐18 25‐Dec‐18 0.06% 0.29% 0.000% 0.00% 0.000% 0.000% 0.00%
REMANING PIPING (NON FBE)
Page 87 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
COMPLETE PIPING FABRICATION  INCL. 
76 F510‐1 6.10 FAB FS PPFB 0 05‐Nov‐18 12‐Dec‐18 0.25% 1.17% 65.789% ‐65.79% 5.000% 0.000% 5.000% 5.00%
HYDROTEST/ PAINTING & COATING
77 F540‐1 6.10 FABRICATION SPOOLS DELIVER TO SITE FAB FS PPFB 0 04‐Dec‐18 22‐Dec‐18 0.12% 0.59% 10.000% ‐10.00% 0.000% 0.000% 0.00%
FAHN
Structural Steel Fabrication
FAB. OF SEPERATOR & PLATFORM STR. 
80 F550 4.40 INCL.LADDERS/STAIRS/HR/WW/CROS  FAB FN STFB Kg 9298 5578.8 10‐Sep‐18 02‐Jan‐19 10‐Sep‐18 0.12% 0.58% 89.474% 50.00% ‐49.47% 10.000% 40.000% 60.000% 20.00%
TRANSFER TO SITE FOR INSTLN.
FAB OF METERING SKID 
81 F560 4.40 INCL.LADDERS/STAIRS/HR/WW/CROS.   FAB FN STFB Kg 2470 2223 12‐Sep‐18 02‐Jan‐19 12‐Sep‐18 0.01% 0.06% 89.474% 85.00% ‐50.54% 5.000% 38.938% 90.000% 51.06%
TRANSFER TO SITE FOR INSTALLATION
FAB OF PSV 
INCL.LADDERS/STAIRS/HR/WW/CROS. 
82 F570 4.40 FAB FN STFB Kg 1705 1193.5 11‐Sep‐18 19‐Dec‐18 11‐Sep‐18 0.02% 0.12% 89.474% 50.00% ‐44.47% 20.000% 45.000% 70.000% 25.00%
STRUCTURE  TRANSFER TO SITE FOR 
INSTALLATION
FAB. OF PIPESUPPORT  STRUCTURE  
83 F580 4.40 FAB FN STFB Kg 4078 2120.56 11‐Sep‐18 02‐Jan‐19 11‐Sep‐18 0.02% 0.12% 89.474% 48.00% ‐50.00% 4.000% 39.474% 52.000% 12.53%
TRANSFER TO SITE FOR INSTALLATION
FABRICATION OF INSTRUMENT STANCHION 
84 F590 4.40 FAB FN STFB PCS 151 151 03‐Sep‐18 11‐Oct‐18 26‐Jul‐18 0.11% 0.53% 45.000% 100.00% 55.00% 0.000% 100.000% 100.000% 0.00%
SUPPORTS
Piping Fabrication
FBE PIPING (AT KUWAIT)
PIPING FABRICATION  & FBE COATINGT 
87 F620 4.10 FAB FN PPFB DIN 2522 504.4 14‐Oct‐18 25‐Dec‐18 14‐Oct‐18 0.18% 0.86% 48.780% 12.00% ‐32.34% 8.00% 16.44% 20.00% 3.56%
KUWAIT
88 F650 4.10 FBE PIPING BULK DELIVERT SITE FAB FN PPFB LM 164 0 26‐Dec‐18 05‐Jan‐19 0.06% 0.29% 0.000% 0.00% 0.00% 0.00% 0.00%
REMAINING PIPING (NON FBE)
COMPLETE PIPING FABRICATION   INCL. 
90 F620‐1 4.10 FAB FN PPFB 0 19‐Nov‐18 26‐Dec‐18 0.24% 1.15% 65.789% ‐65.79% 5.00% 0.00% 5.00% 5.00%
HYDROTEST/ PAINTING & COATING
91 F650‐1 4.10 FABRICATION SPOOLS DELIVER TO SITE FAB FN PPFB 0 16‐Dec‐18 03‐Jan‐19 0.12% 0.58% 0.000% 0.00% 0.00% 0.00% 0.00%
FAHM
Structural Steel Fabrication
FAB. OF SEPERATOR & PLATFORM STR. 
94 F660 5.40 INCL.LADDERS/STAIRS/HR/WW/CROS.  FAB FM STFB Kg 9298 4370.06 13‐Sep‐18 24‐Jan‐19 13‐Sep‐18 0.08% 0.39% 71.429% 40.00% ‐39.34% 7.00% 32.09% 47.00% 14.91%
TRANSFER TO SITE FOR INSTLN.
FAB. OF  METERING SKID 
95 F670 5.40 INCL.LADDERS/STAIRS/HR/WW/CROS  FAB FM STFB Kg 2470 1778.4 13‐Sep‐18 24‐Jan‐19 13‐Sep‐18 0.01% 0.04% 71.429% 30.00% ‐39.34% 42.00% 32.09% 72.00% 39.91%
TRANSFER TO SITE FOR INSTALLATION
FAB.OF PSV 
INCL.LADDERS/STAIRS/HR/WW/CROS. 
96 F680 5.40 FAB FM STFB Kg 1705 596.75 13‐Sep‐18 09‐Jan‐19 13‐Sep‐18 0.02% 0.08% 71.429% 30.00% ‐35.29% 5.00% 36.13% 35.00% ‐1.13%
STRUCTURE  TRANSFER TO SITE FOR 
INSTALLATION
FAB. OF PIPESUPPORT  STRUCTURE  
97 F690 5.40 FAB FM STFB Kg 4078 3140.06 12‐Sep‐18 05‐Jan‐19 12‐Sep‐18 0.02% 0.08% 62.500% 75.00% ‐24.57% 2.00% 37.93% 77.00% 39.07%
TRANSFER TO SITE FOR INSTALLATION
FABRICATION OF INSTRUMENT STANCHION 
98 F700 5.40 FAB FM STFB PCS 151 151 03‐Sep‐18 16‐Sep‐18 3‐Sep‐18 16‐Sep‐18 0.11% 0.53% 0.000% 100.00% 100.00% 0.00% 100.00% 100.00% 0.00%
SUPPORTS
Piping Fabrication
FBE PIPING (AT KUWAIT)
PIPING FABRICATION  & FBE COATINGT 
101 F730 5.10 FAB FM PPFB DIN 2775 555 18‐Oct‐18 31‐Dec‐18 18‐Oct‐18 0.20% 0.93% 43.478% 12.00% ‐32.81% 8.00% 10.67% 20.00% 9.33%
KUWAIT
102 F760 5.10 FBE PIPING BULK DELIVERT SITE FAB FM PPFB LM 146 0 01‐Jan‐19 10‐Jan‐19 0.07% 0.31% 0.000% 0.00% 0.00% 0.00% 0.00%
REMAINING PIPING (NON FBE)
COMPLETE PIPING FABRICATION   INCL. 
104 F730‐1 5.10 FAB FM PPFB 0 29‐Nov‐18 14‐Jan‐19 0.26% 1.25% 50.000% ‐50.00% 5.00% 0.00% 5.00% 5.00%
HYDROTEST/ PAINTING & COATING
105 F760‐1 5.10 FABRICATION SPOOLS DELIVER TO SITE FAB FM PPFB 0 29‐Dec‐18 16‐Jan‐19 0.13% 0.62% 0.000% 0.00% 0.00% 0.00% 0.00%
INSTALLATION
KAHN
Civil Works
COMMOMN
110 A1440 1.40 GRADING INS KN CV SQM 246 246 10‐Feb‐18 31‐May‐18 09‐Feb‐18 19‐Jul‐18 0.04% 0.18% 100.000% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00%
CABLE TRENCHESND UTILITY ROAD 
111 A1510 1.40 INS KN CV LM 500 175 25‐Aug‐18 21‐Nov‐18 25‐Aug‐18 0.00% 0.01% 100.000% 25.00% ‐30.34% 10.00% 69.66% 35.00% ‐34.66%
CROSSINGS
112 A1520 1.40 DRAINAGE PIPE CULVERTS INS KN CV LM 33 33 30‐Sep‐18 16‐Oct‐18 30‐Sep‐18 16‐Oct‐18 0.01% 0.02% 0.000% 100.00% 100.00% 0.00% 100.00% 100.00% 0.00%

113 A1530 1.40 ROAD SAFETY CRASH BARRIERSND BOLLARD INS KN CV PCS 1 0 02‐Jan‐19 16‐Jan‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

ROADSND PAVING(INCLUDING 
114 A1500 1.40 INS KN CV SQM 231 0 02‐Jan‐19 16‐Jan‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MODIFICATIONS)
115 A1440‐1 1.40 PROTECTION OF UNDERGROUND CABLES INS KN CV 0 05‐Sep‐18 21‐Nov‐18 05‐Sep‐18 0.01% 0.04% 100.000% 90.00% ‐34.62% 0.00% 65.38% 90.00% 24.62%

SOAKWAY PIT EXCAVATION & INSTALLATION 
116 A1445‐6 1.40 INS KN CV 0 14‐Aug‐18 17‐Nov‐18 14‐Aug‐18 0.01% 0.04% 100.000% 90.00% ‐23.96% 0.00% 76.04% 90.00% 13.96%
INCL. DEMOLITION ‐  IFPPLICABLE
RE‐INSTATEMENT OF EXISTING PAVEMENT 
117 A1530‐1 1.40 INS KN CV 0 02‐Jan‐19 16‐Jan‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(INTERLOCK PAVING)
TEST SEPERATOR
119 A1445 1.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS KN CV CUM 40 40 09-Feb-18 29-Mar-18 09-Feb-18 29-Mar-18 0.02% 0.09% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

120 A1450 1.40 FOUNDATION WORK  (STEEL FIXING) INS KN CV ton 1534 1534 01-Apr-18 12-Apr-18 01-Apr-18 12-Apr-18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
121 A1450‐1 1.40 FOUNDATION WORK  (CONCRETE) INS KN CV CUM 15.8 15.8 01-Apr-18 26-Apr-18 01-Apr-18 26-Apr-18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
Page 88 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)

122 A1450‐2 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV CUM 45 45 24-May-18 11-Aug-18 27-May-18 19-Jul-18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

123 A1450‐2 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV CUM 45 45 24‐May‐18 11‐Aug‐18 24-May-18 11-Aug-18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

TEST SEPERATOR PLATFORM
125 A1445‐1 1.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS KN CV 0 09‐Feb‐18 29‐Mar‐18 09‐Feb‐18 29‐Mar‐18 0.02% 0.09% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

126 A1450‐3 1.40 FOUNDATION WORK  (STEEL FIXING) INS KN CV 0 01‐Apr‐18 16‐Jul‐18 01‐Apr‐18 16‐Jul‐18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
127 A1450‐4 1.40 FOUNDATION WORK  (CONCRETE) INS KN CV 0 01‐Apr‐18 26‐Jul‐18 01‐Apr‐18 26‐Jul‐18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

128 A1450‐5 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV 0 27‐May‐18 11-Aug-18 27‐May‐18 19-Jul-18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

129 A1450‐5 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV 0 27‐May‐18 11‐Aug‐18 27‐May‐18 11‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

METERING SKID
131 A1445‐2 1.40 EXCAVATION INS KN CV CUM 60 60 06‐Mar‐18 29‐Mar‐18 06‐Mar‐18 29‐Mar‐18 0.04% 0.19% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
132 A1490 1.40 FOUNDATION WORK  (STEEL FIXING) INS KN CV kg 1656 1656 01‐Apr‐18 12‐Apr‐18 01‐Apr‐18 12‐Apr‐18 0.03% 0.15% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
133 A1490‐1 1.40 FOUNDATION WORK  (CONCRETE) INS KN CV CUM 14.55 14.55 01‐Apr‐18 26‐Apr‐18 01‐Apr‐18 26‐Apr‐18 0.03% 0.15% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

134 A1490‐2 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV CUM 108 108 28‐May‐18 11‐Aug‐18 28‐May‐18 11‐Aug‐18 0.03% 0.15% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

PIPE SUPPORT
EXCAVATION FOR STRUCTURAL STEEL PIPE 
136 A1445‐3 XX 1.40 INS KN CV CUM 78.6 78.6 22‐Mar‐18 06‐Aug‐18 22‐Mar‐18 31‐May‐18 0.04% 0.19% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
SUPPORTS
EXCAVATION FOR STRUCTURAL STEEL PIPE 
137 A1445‐3 XX 1.40 INS KN CV CUM 78.6 78.6 22‐Mar‐18 06‐Aug‐18 22‐Mar‐18 06‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
SUPPORTS
138 A1470 XX 1.40 FOUNDATION WORK  (STEEL FIXING) INS KN CV kg 2880 2880 10‐Dec‐17 18‐Aug‐18 10‐Dec‐17 19‐Jul‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
139 A1470 XX 1.40 FOUNDATION WORK  (STEEL FIXING) INS KN CV kg 2880 2880 10‐Dec‐17 18‐Aug‐18 10‐Dec‐17 18‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
140 A1470‐1 XX 1.40 FOUNDATION WORK  (CONCRETE) INS KN CV CUM 24 24 10‐Dec‐17 18‐Aug‐18 10‐Dec‐17 19‐Jul‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
141 A1470‐1 XX 1.40 FOUNDATION WORK  (CONCRETE) INS KN CV CUM 24 24 10‐Dec‐17 18‐Aug‐18 10‐Dec‐17 18‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

142 A1470‐2 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV CUM 76 76 10‐Dec‐17 23‐Aug‐18 10‐Dec‐17 19‐Jul‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

143 A1470‐2 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV CUM 76 76 10‐Dec‐17 23‐Aug‐18 10‐Dec‐17 23‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

PSV
EXCAVATION (INCLUDINGREA LIGHTING 
145 A1445‐4 1.40 INS KN CV CUM 100 100 24‐Mar‐18 05‐Jul‐18 24‐Mar‐18 05‐Jul‐18 0.04% 0.19% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
POLES)
146 A1490‐3 1.40 FOUNDATION WORK  (STEEL FIXING) INS KN CV CUM 3647 3647 15‐Apr‐18 08‐Aug‐18 15‐Apr‐18 08‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
147 A1490‐5 1.40 FOUNDATION WORK  (CONCRETE) INS KN CV CUM 26 26 22‐Apr‐18 08‐Aug‐18 22‐Apr‐18 08‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

148 A1490‐6 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV CUM 206 206 04‐Jun‐18 11‐Aug‐18 04‐Jun‐18 19‐Jul‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

149 A1490‐6 XX 1.40 CURING / WATERPROOFING / BACK FILLING INS KN CV CUM 206 206 04‐Jun‐18 11‐Aug‐18 04‐Jun‐18 11‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

Structural Steel
TEST SEPERATOR
INSTALLATION OF STRUCTURAL STEELWORK 
152 A2360 1.40 OPERATINGNDCCESS PLATFORMS (TEST  INS KN STIN Kg 9298 1394.7 02‐Oct‐18 03‐Dec‐18 02‐Oct‐18 0.09% 0.44% 100.000% 10.00% ‐61.90% 5.00% 38.10% 15.00% ‐23.10%
SEPERATOR & PLATFORM)
INSTALLATION OF LADDERS, STAIRS, 
153 A2400 1.40 INS KN STIN PCS 151 0 14‐Nov‐18 03‐Dec‐18 0.01% 0.04% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
HANDRAILS
METERING SKID
INSTALLATION OF STRUCTURAL STEEL OF 
155 A2360‐1 1.40 METERING SKID INCL. WALK WAY OR CROSS  INS KN STIN 0 04‐Oct‐18 06‐Dec‐18 04‐Oct‐18 30‐Oct‐18 0.02% 0.08% 100.000% 10.00% ‐65.63% 5.00% 34.38% 15.00% ‐19.38%
OVER
PSV
INSTALLATION OF PSV VALVESCCESS 
157 A2380 1.40 INS KN STIN Kg 1705 255.75 10‐Oct‐18 06‐Dec‐18 10‐Oct‐18 0.01% 0.04% 100.000% 10.00% ‐72.41% 5.00% 27.59% 15.00% ‐12.59%
PLATFORMS
PIPE SUPPORT
INSTALLATION OF STRUCTURAL STEEL PIPE 
159 A2370 1.40 SUPPORTS & MODIFICATIONS OF  INS KN STIN Kg 2470 247 11‐Oct‐18 18‐Dec‐18 11‐Oct‐18 0.00% 0.02% 100.000% 0.00% ‐78.26% 10.00% 21.74% 10.00% ‐11.74%
EXISTINGCCESS PLATFORMS (IFPPLICABLE)
FIELD INSTRUMENT
161 A2370‐1 1.40 INSTALLATION OF INSTRUMENT STANCHION INS KN STIN 0 15‐Dec‐18 18‐Dec‐18 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

Mechanical
163 A2775 1.10 INSTALLATION OF NEW TEST SEPARATOR INS KN ME SET 137.5 137.5 05‐Sep‐18 06‐Sep‐18 04‐Sep‐18 06‐Sep‐18 0.02% 0.10% 100.000% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00%

Piping
EARLY SHUTDOWN WORKS ‐ Pre Shutdownnd Plant Shutdown Tie‐in
166 A5550 1.10 MOBILIZATION OF OF TEAMPPLY PTW INS KN PPIN 0 31‐Dec‐17 31‐Dec‐17 31‐Dec‐17 31‐Dec‐17 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
SCAFFOLDING / PLATE FORM / WORK 
167 A5560 1.10 INS KN PPIN PCS 150 150 31‐Dec‐17 05‐Jan‐18 31‐Dec‐17 05‐Jan‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
PERMIT ISSUE
168 A5570 1.10 PIPING TIE‐IN / NDT INS KN PPIN DIN 90 90 09‐Feb‐18 14‐Feb‐18 09‐Feb‐18 14‐Feb‐18 0.01% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
169 A5580 1.10 TIE‐IN COMPLETE / REMOVE SCAFFOLD INS KN PPIN PCS 15 15 06‐Feb‐18 17‐Feb‐18 06‐Feb‐18 17‐Feb‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
PIPING ‐REMAINING
PIPING INSTALLATION ON PIPE 
171 A2920 1.10 INS KN PPIN DIN 334.728 0 10‐Dec‐18 29‐Dec‐18 0.03% 0.12% 20.690% 0.00% ‐20.69% 0.00% 0.00% 0.00% 0.00%
SUPPORT,PIERACK &ROUND EQUIPMENT
Page 89 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)

172 A2920‐1 1.10 INSTALLATION OF BALL VALVE & GGC VALVE INS KN PPIN 0 19‐Dec‐18 27‐Dec‐18 0.03% 0.12% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HYDRO‐TESTING, FLUSHING, DRAININGND 
173 A2940 1.10 INS KN PPIN SET 220.8 0 26‐Dec‐18 02‐Jan‐19 0.03% 0.16% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PURGING
174 A2950 1.10 TIE‐IN INS KN PPIN PCS 2007.81 0 02‐Jan‐19 06‐Jan‐19 0.31% 1.48% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INLET PIPING  TIE‐IN TO SEPARATOR 
175 A2930 1.10 INS KN PPIN DIN 334.88 0 02‐Jan‐19 06‐Jan‐19 0.05% 0.25% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(PARTIAL SHUTDOWN TIE‐IN)
REPLACE THE SHUTVALVET POINT OF OIL‐IN 
176 A2951 1.10 INS KN PPIN PCS 32.384 0 03‐Jan‐19 06‐Jan‐19 0.01% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TIE‐IN / INSTALL SDV
Electrical
178 A5990 1.30 CABLE TRENCHES INS KN EL M 500 175 25‐Aug‐18 21‐Nov‐18 25‐Aug‐18 0.00% 0.00% 100.000% 0.00% ‐30.34% 35.00% 69.66% 35.00% ‐34.66%
A6000 1.30 EARTH PIT DRILLING  INS KN EL NO 3 0 12‐Nov‐18 17‐Nov‐18 0.01% 0.07% 0.00% 0.00% 0.00%
178 A3290 1.30 CABLE TRAY INSTALLATION INS KN EL LM 301.4 0 06‐Dec‐18 15‐Dec‐18 0.03% 0.16% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
179 A3280 1.30 U/G CABLE LAYING INS KN EL LM 170.5 0 06‐Dec‐18 20‐Dec‐18 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
180 A3310 1.30 CABLE LAYING INS KN EL LM 165 0 09‐Dec‐18 27‐Dec‐18 0.03% 0.12% 33.333% 0.00% ‐33.33% 0.00% 0.00% 0.00% 0.00%
181 A3280‐2 1.30 BACK FILLING OF CABLE TRENCH INS KN EL 0 09‐Dec‐18 23‐Dec‐18 0.01% 0.06% 40.000% 0.00% ‐40.00% 0.00% 0.00% 0.00% 0.00%
182 A3270 1.30 CABLE GLANDINGND TERMINATION INS KN EL LM 123.2 0 18‐Dec‐18 31‐Dec‐18 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

183 A3300 1.30 ELECTRICAL EQUIPMENTS INSTALLATION INS KN EL PCS 96.8 0 18‐Dec‐18 31‐Dec‐18 0.01% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

184 A3320 1.30 LIGHTING FICTUREND DB INSTALLATION INS KN EL PCS 233.2 0 25‐Dec‐18 31‐Dec‐18 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

185 A3310‐1 1.30 HOOK UP INS KN EL 0 31‐Dec‐18 05‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
186 A3330 1.30 ELECTRICAL TIE‐INS INS KN EL SET 44 0 05‐Jan‐19 09‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
187 A3340 1.30 ENERGIZATION INS KN EL SET 44 0 09‐Jan‐19 12‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Instrument & Control
189 A3950 1.20 CABLE TRAYND SUPPORT INSTALLATION INS KN IN LM 36.3 0 22‐Nov‐18 12‐Dec‐18 0.02% 0.07% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

189 A4790 1.20 JB SUPPORT INSTALLATION INS KN IN 0 09‐Dec‐18 11‐Dec‐18 0.00% 0.01% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
190 A4870 1.20 JB INSTALLATION INS KN IN 0 11‐Dec‐18 13‐Dec‐18 0.00% 0.01% 41.667% 0.00% ‐41.67% 0.00% 0.00% 0.00% 0.00%
190 A3980 1.20 INSTRUMENT CABLE LAYING INS KN IN LM 1218.8 0 11‐Dec‐18 29‐Dec‐18 0.02% 0.07% 41.667% 0.00% ‐41.67% 0.00% 0.00% 0.00% 0.00%

191 A3970 1.20 INSTRUMENT EQUIPEMNT INSTALLATION INS KN IN SET 396 0 22‐Dec‐18 29‐Dec‐18 0.04% 0.18% 5.000% 0.00% ‐5.00% 0.00% 0.00% 0.00% 0.00%

FIELD INSTRUMENT INSTALLATION (GAUGES 
192 A3970‐1 1.20 INS KN IN 0 24‐Dec‐18 30‐Dec‐18 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
& TRANSMITTERS)
191 A3970‐11 1.20 CABLE GLANDND TERMINATION (ALONG JBs) INS KN IN 0 25‐Dec‐18 29‐Dec‐18 0.00% 0.01% 5.000% 0.00% ‐5.00% 0.00% 0.00% 0.00% 0.00%

CABLE GLANDND TERMINATION (ALONG 
192 A3970‐21 1.20 INS KN IN 0 27‐Dec‐18 01‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTS)
INSTALLATION OF BS & WNALYZERS ON 
193 A3970‐2 1.20 INS KN IN 0 29‐Dec‐18 31‐Dec‐18 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
DCS MODIFICATION IN CONTROL ROOM BY 
194 A3990 1.20 INS KN IN 0 29‐Dec‐18 07‐Jan‐19 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
VENDOR
195 A3970‐3 1.20 INSTALLATION OF INSTRUMENT VALVE INS KN IN 0 26‐Dec‐18 29‐Dec‐18 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
196 A4860 1.50 INSTALLATION OF  DELUGE INS KN IN SET 671 0 01‐Jan‐19 05‐Jan‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
197 A3980‐2 1.20 SS TUBEND LEAK TEST INS KN IN 0 01‐Jan‐19 05‐Jan‐19 0.06% 0.27% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT EQUIPMENT CALIBRATION / 
198 A3960 1.20 INS KN IN SET 154 0 02‐Jan‐19 06‐Jan‐19 0.08% 0.36% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LOOP TEST
F&G System
189 A6010 1.20 F&G SUPPORTS INSTALLATION INS KN IN 0 09‐Dec‐18 12‐Dec‐18 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
189 A6030 1.20 F&G CABLE INSTALLATION INS KN IN 0 11‐Dec‐18 20‐Dec‐18 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
190 A6020 1.20 F&G DEVICES INSTALLATION INS KN IN 0 11‐Dec‐18 15‐Dec‐18 0.00% 0.02% 41.667% 0.00% ‐41.67% 0.00% 0.00% 0.00% 0.00%
190 A6040 1.20 F&G JB SUPPORT INSTALLATION INS KN IN 0 11‐Dec‐18 13‐Dec‐18 0.00% 0.02% 41.667% 0.00% ‐41.67% 0.00% 0.00% 0.00% 0.00%
191 A6050 1.20 F&G JB INSTALLATION INS KN IN 0 12‐Dec‐18 15‐Dec‐18 0.00% 0.02% 5.000% 0.00% ‐5.00% 0.00% 0.00% 0.00% 0.00%

192 A6060 1.20 F&G CABLE GLANDINGND TERMINATION INS KN IN 0 27‐Dec‐18 01‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

191 A6070 1.20 F&G LOOP PREPARATION INS KN IN 0 01‐Jan‐19 02‐Jan‐19 0.00% 0.02% 5.000% 0.00% ‐5.00% 0.00% 0.00% 0.00% 0.00%
192 A6080 1.20 F&G LOOP TESTING INS KN IN 0 03‐Jan‐19 07‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting & Fireproofing
200 A4300 1.40 STRUCTURAL STEEL PAINTINGND TOUCH‐UP INS KN FP SQM 206 0 15‐Dec‐18 23‐Dec‐18 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

201 A4310 1.10 PIPING PAINTINGND TOUCH‐UP INS KN FP SQM 178 0 29‐Dec‐18 06‐Jan‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

202 A4320 1.50 FIREPROOFING FOR STRUCTURAL STEEL INS KN FP SQM 1051.6 0 15‐Dec‐18 27‐Dec‐18 0.16% 0.77% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Demolition Works
204 D0000 1.60 WORK PERMITPPROVED FOR DEMOLITION INS KN DEM PCS 8.8 0 26‐Jan‐19 29‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

DEPRESSURIZATION / ISOLATION (PIPING & 
205 D0010 1.60 INS KN DEM PCS 34.1 0 29‐Jan‐19 30‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTATION)
206 D0030 1.60 APPLYNTI RUST TO FOUNDATION BOTLS INS KN DEM PCS 22 0 30‐Jan‐19 02‐Feb‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

207 D0020 1.60 COLD CUTTING INLETND OUTLET PIPING INS KN DEM PCS 77 0 02‐Feb‐19 25‐Feb‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

208 D0040 1.60 UNBOLD & REMOVE EXISTING SEPARATOR INS KN DEM PCS 132 0 25‐Feb‐19 27‐Feb‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

REMOVE CONCRETE FOUNDATION / GRADE 
209 D0050 1.60 INS KN DEM PCS 174 0 28‐Feb‐19 13‐Mar‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
THEREA
KAHM
Civil Works Page 90 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
COMMOMN
213 A1580 2.40 GRADING INS KM CV SQM 357.5 357.5 17‐Feb‐18 02‐Apr‐18 17‐Feb‐18 18‐Jul‐18 0.06% 0.26% 100.000% 100.00% 0.00% 0.00% 100.00% 100.00% 0.00%

SOAKWAY PIT EXCAVATION & INSTALLATION 
214 A1700 2.40 INS KM CV PCS 123.2 117.04 04‐Aug‐18 05‐Nov‐18 04‐Aug‐18 0.02% 0.09% 100.000% 95.00% 0.00% 0.00% 88.30% 95.00% 6.70%
INCL. DEMOLITION ‐  IFPPLICABLE
CABLE TRENCHESND UTILITY ROAD 
215 A1650 2.40 INS KM CV LM 700 210 25‐Sep‐18 21‐Nov‐18 25‐Sep‐18 0.01% 0.06% 100.000% 12.00% ‐46.55% 18.00% 53.45% 30.00% ‐23.45%
CROSSINGS
216 A1580‐1 2.40 PROTECTION OF UNDERGROUND CABLES INS KM CV 0 23‐Sep‐18 21‐Nov‐18 23‐Sep‐18 0.01% 0.06% 100.000% 50.00% ‐45.00% 10.00% 55.00% 60.00% 5.00%

217 A1660 2.40 DRAINAGE PIPE CULVERTS INS KM CV LM 0.187 0.1496 16‐Oct‐18 05‐Dec‐18 16‐Oct‐18 0.01% 0.03% 0.000% 70.00% 19.61% 10.00% 19.61% 80.00% 60.39%
218 A1690 2.40 PAVING&GRADING(GRAVEL FILL) INS KM CV 0 05‐Jan‐19 14‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
ROADSND PAVING(INCLUDING 
219 A1640 2.40 INS KM CV SQM 60.5 0 03‐Jan‐19 14‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MODIFICATIONS)
220 A1670 2.40 ROAD SAFETY CRASH BARRIERSND BOLLARD INS KM CV PCS 107.8 0 05‐Jan‐19 14‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TEST SEPERATOR
222 A1585 2.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS KM CV CUM 40 40 17‐Feb‐18 02‐Apr‐18 17‐Feb‐18 02‐Apr‐18 0.02% 0.09% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

223 A1590 2.40 FOUNDATION WORK  (STEEL FIXING) INS KM CV kg 1534 1534 19‐May‐18 18‐Jul‐18 19‐May‐18 18‐Jul‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
224 A1590‐1 2.40 FOUNDATION WORK  (CONCRETE) INS KM CV CUM 15.8 15.8 01‐Apr‐18 04‐Aug‐18 01‐Apr‐18 04‐Aug‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

225 A1590‐2 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 45 45 09‐Jul‐18 18‐Aug‐18 09‐Jul‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

226 A1590‐2 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 45 45 09‐Jul‐18 18‐Aug‐18 09‐Jul‐17 18‐Aug‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

TEST SEPERATOR PLATFORM
228 A1585‐1 2.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS KM CV 0 17‐Feb‐18 02‐Apr‐18 17‐Feb‐18 02‐Apr‐18 0.02% 0.09% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

229 A1590‐3 2.40 FOUNDATION WORK  (STEEL FIXING) INS KM CV 0 19‐May‐18 18‐Jul‐18 19‐May‐18 18‐Jul‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
230 A1590‐4 2.40 FOUNDATION WORK  (CONCRETE) INS KM CV 0 01‐Apr‐18 04‐Aug‐18 01‐Apr‐18 04‐Aug‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

231 A1590‐5 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV 0 09‐Jul‐18 20‐Sep‐18 09‐Jul‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

232 A1590‐5 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV 0 09‐Jul‐18 20‐Sep‐18 09‐Jul‐18 20‐Sep‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

METERING SKID
234 A1585‐2 2.40 EXCAVATION INS KM CV CUM 60 60 03‐Mar‐18 01‐Apr‐18 03‐Mar‐18 01‐Apr‐18 0.04% 0.19% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
235 A1630 2.40 FOUNDATION WORK  (STEEL FIXING) INS KM CV kg 1656 1656 19‐May‐18 18‐Jul‐18 19‐May‐18 18‐Jul‐18 0.03% 0.12% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
236 A1630‐1 2.40 FOUNDATION WORK  (CONCRETE) INS KM CV CUM 14.55 14.55 01‐Apr‐18 02‐Aug‐18 01‐Apr‐18 02‐Aug‐18 0.03% 0.12% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

237 A1630‐2 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 108 108 01‐Jul‐18 18‐Sep‐18 01‐Jul‐18 19‐Jul‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

238 A1630‐2 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 108 108 01‐Jul‐18 18‐Sep‐18 01‐Jul‐18 18‐Sep‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

PIPE SUPPORT
EXCAVATION FOR STRUCTURAL STEEL PIPE 
240 A1585‐3 2.40 INS KM CV CUM 63.87 63.87 03‐Dec‐17 18‐Jul‐18 03‐Dec‐17 18‐Jul‐18 0.04% 0.19% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
SUPPORTS
241 A1610 XX 2.40 FOUNDATION WORK  (STEEL FIXING) INS KM CV CUM 1455 1455 16‐Dec‐17 25‐Aug‐18 16‐Dec‐17 19‐Jul‐18 0.05% 0.22% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
242 A1610 XX 2.40 FOUNDATION WORK  (STEEL FIXING) INS KM CV CUM 1455 1455 16‐Dec‐17 25‐Aug‐18 16‐Dec‐17 25‐Aug‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
243 A1610‐1 XX 2.40 FOUNDATION WORK  (CONCRETE) INS KM CV CUM 30 30 16‐Dec‐17 27‐Aug‐18 16‐Dec‐17 19‐Jul‐18 0.04% 0.21% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
244 A1610‐1 XX 2.40 FOUNDATION WORK  (CONCRETE) INS KM CV CUM 30 30 16‐Dec‐17 27‐Aug‐18 16‐Dec‐17 27‐Aug‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

245 A1610‐2 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 76 76 16‐Dec‐17 29‐Aug‐18 16‐Dec‐17 19‐Jul‐18 0.04% 0.19% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

246 A1610‐2 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 76 76 16‐Dec‐17 29‐Aug‐18 16‐Dec‐17 29‐Aug‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

PSV
EXCAVATION (INCLUDINGREA LIGHTING 
248 A1585‐4 2.40 INS KM CV CUM 100 100 17‐Feb‐18 21‐Jun‐18 17‐Mar‐18 21‐Jun‐18 0.04% 0.19% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
POLES)
249 A1630‐3 XX 2.40 FOUNDATION WORK  (STEEL FIXING) INS KM CV CUM 3647 3647 20‐May‐18 25‐Aug‐18 20‐May‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
250 A1630‐3 XX 2.40 FOUNDATION WORK  (STEEL FIXING) INS KM CV CUM 3647 3647 20‐May‐18 25‐Aug‐18 20‐May‐18 25‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
251 A1630‐4 XX 2.40 FOUNDATION WORK  (CONCRETE) INS KM CV CUM 26 26 20‐May‐18 26‐Aug‐18 18‐May‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
252 A1630‐4 XX 2.40 FOUNDATION WORK  (CONCRETE) INS KM CV CUM 26 26 20‐May‐18 26‐Aug‐18 18‐May‐18 26‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

253 A1630‐5 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 206 206 02‐Jul‐18 13‐Sep‐18 02‐Jul‐18 19‐Jul‐18 0.01% 0.04% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

254 A1630‐5 XX 2.40 CURING / WATERPROOFING / BACK FILLING INS KM CV CUM 206 206 02‐Jul‐18 13‐Sep‐18 02‐Jul‐18 13‐Sep‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

Structural Steel
TEST SEPERATOR
INSTALLATION OF STRUCTURAL STEELWORK 
257 A2420 2.40 OPERATINGNDCCESS PLATFORMS (TEST  INS KM STIN Kg 9298 1394.7 14‐Oct‐18 29‐Nov‐18 14‐Oct‐18 0.10% 0.49% 100.000% 5.00% ‐74.47% 10.00% 25.53% 15.00% ‐10.53%
SEPERATOR & PLATFORM)
INSTALLATION OF LADDERS, STAIRS, 
258 A2460 2.40 INS KM STIN PCS 151 0 20‐Nov‐18 29‐Nov‐18 0.01% 0.04% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
HANDRAILS
METERING SKID
INSTALLATION OF STRUCTURAL STEEL OF 
260 A2430 2.40 METERING SKID INCL. WALK WAY OR CROSS  INS KM STIN Kg 2470 247 04‐Oct‐18 22‐Nov‐18 04‐Oct‐18 0.01% 0.03% 100.000% 10.00% ‐56.00% 0.00% 44.00% 10.00% ‐34.00%
OVER
PSV
INSTALLATION OF PSV VALVESCCESS 
262 A2440 2.40 INS KM STIN Kg 1705 0 08‐Nov‐18 17‐Nov‐18 01‐Nov‐18 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
PLATFORMS Page 91 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
PIPE SUPPORT
INSTALLATION OF STRUCTURAL STEEL PIPE 
264 A2450 2.40 SUPPORTS & MODIFICATIONS OF  INS KM STIN Kg 4078 0 13‐Nov‐18 01‐Dec‐18 0.01% 0.05% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
EXISTINGCCESS PLATFORMS (IFPPLICABLE)
FIELD INSTRUMENT
266 A2450‐1 2.40 INSTALLATION OF INSTRUMENT STANCHION INS KM STIN 0 25‐Nov‐18 01‐Dec‐18 0.01% 0.05% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

Mechanical
268 A2795 2.10 INSTALLATION OF NEW TEST SEPARATOR INS KM ME SET 137.5 137.5 16‐Oct‐18 18‐Oct‐18 16‐Oct‐18 18‐Oct‐18 0.02% 0.10% 100.000% 20.00% 0.00% 80.00% 100.00% 100.00% 0.00%

Piping
EARLY SHUTDOWN WORKS ‐ Pre Shutdownnd Plant Shutdown Tie‐in
271 A5590 2.10 MOBILIZATION OF OF TEAMPPLY PTW INS KM PPIN 0 31‐Dec‐17 31‐Dec‐17 31‐Dec‐17 31‐Dec‐17 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
SCAFFOLDING / PLATE FORM / WORK 
272 A5600 2.10 INS KM PPIN PCS 156 156 31‐Dec‐17 05‐Jan‐18 31‐Dec‐17 05‐Jan‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
PERMIT ISSUE
273 A5610 2.10 PIPING TIE‐IN / NDT INS KM PPIN DIN 93 93 09‐Feb‐18 14‐Feb‐18 09‐Feb‐18 14‐Feb‐18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
274 A5620 2.10 TIE‐IN COMPLETE / REMOVE SCAFFOLD INS KM PPIN PCS 16 16 06‐Feb‐18 17‐Feb‐18 06‐Feb‐18 17‐Feb‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
PIPING ‐REMAINING
PIPING INSTALLATION ON PIPE 
276 A2970 2.10 INS KM PPIN DIN 392.6 0 29‐Nov‐18 22‐Dec‐18 0.03% 0.14% 17.857% 0.00% ‐17.86% 0.00% 0.00% 0.00% 0.00%
SUPPORT,PIERACK &ROUND EQUIPMENT

277 A2970‐1 2.10 INSTALLATION OF BALL VALVE & GGC VALVE INS KM PPIN 0 11‐Dec‐18 20‐Dec‐18 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HYDRO‐TESTING, FLUSHING, DRAININGND 
278 A2990 2.10 INS KM PPIN SET 220 0 17‐Dec‐18 26‐Dec‐18 0.03% 0.16% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PURGING
INLET PIPING  TIE‐IN TO SEPARATOR 
279 A2980 2.10 INS KM PPIN DIN 390 0 26‐Dec‐18 30‐Dec‐18 0.06% 0.29% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(PARTIAL SHUTDOWN TIE‐IN)
280 A3000 2.10 TIE‐IN INS KM PPIN PCS 2000 0 26‐Dec‐18 30‐Dec‐18 0.31% 1.47% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REPLACE THE SHUTVALVET POINT OF OIL‐IN 
281 A3001 2.10 INS KM PPIN PCS 60 0 27‐Dec‐18 30‐Dec‐18 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TIE‐IN / INSTALL SDV
Electrical
283 A6090 2.30 CABLE TRENCHES INS KM EL LM 700 210 25‐Sep‐18 21‐Nov‐18 0.00% 0.00% 100.000% 5.00% ‐46.55% 25.00% 53.45% 30.00% ‐23.45%
284 A3440 2.30 EARTH PIT DRILLING INS KM EL NO 3 0 17‐Nov‐18 20‐Nov‐18 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
283 A3380 2.30 CABLE TRAY INSTALLATION INS KM EL LM 292.6 0 25‐Nov‐18 04‐Dec‐18 0.01% 0.05% 100.000% 5.00% ‐100.00% ‐5.00% 0.00% 0.00% 0.00%
284 A3370 2.30 U/G CABLE LAYING INS KM EL LM 154 0 28‐Nov‐18 13‐Dec‐18 0.02% 0.11% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
285 A3400 2.30 CABLE LAYING INS KM EL LM 114.4 0 10‐Dec‐18 26‐Dec‐18 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
286 A3370‐1 2.30 BACK FILLING OF CABLE TRENCH INS KM EL 0 15‐Dec‐18 27‐Dec‐18 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
287 A3360 2.30 CABLE GLANDINGND TERMINATION INS KM EL LM 116.6 0 15‐Dec‐18 27‐Dec‐18 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

288 A3390 2.30 ELECTRICAL EQUIPMENTS INSTALLATION INS KM EL PCS 92.4 0 15‐Dec‐18 27‐Dec‐18 0.01% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

289 A3410 2.30 LIGHTING FIXTUREND DB INSTALLATION INS KM EL PCS 231 0 22‐Dec‐18 27‐Dec‐18 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

290 A3400‐1 2.30 HOOK UP INS KM EL 0 29‐Dec‐18 01‐Jan‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
291 A3420 2.30 ELECTRICAL TIE‐INS INS KM EL SET 44 0 02‐Jan‐19 06‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
292 A3430 2.30 ENERGIZATION INS KM EL SET 44 0 07‐Jan‐19 09‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Instrument & Control
294 A4000 2.20 CABLE TRAY/DUCT INSTALLATION INS KM IN LM 36.3 0 26‐Nov‐18 13‐Dec‐18 0.02% 0.08% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
294 A4590 2.20 JB SUPPORT INSTLLATION INS KM IN 0 11‐Dec‐18 13‐Dec‐18 0.00% 0.01% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
295 A5350 2.20 JB INSTALLATION INS KM IN 0 15‐Dec‐18 17‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
295 A4030 2.20 INSTRUMENT CABLE LAYING INS KM IN LM 1464.1 0 05‐Dec‐18 25‐Dec‐18 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

296 A4020 2.20 INSTRUMENT EQUIPEMNT INSTALLATION INS KM IN SET 317.9 0 25‐Dec‐18 01‐Jan‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

FIELD INSTRUMENT INSTALLATION (GAUGES 
297 A4020‐1 2.20 INS KM IN 0 25‐Dec‐18 01‐Jan‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
& TRANSMITTER)
296 A4020‐11 2.20 CABLE GLANDND TERMINATION (ALONG JBs) INS KM IN 0 30‐Dec‐18 05‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

CABLE GLANDND TERMINATION (ALONG 
297 A4020‐21 2.20 INS KM IN 0 30‐Dec‐18 06‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTS)
DCS MODIFICATION IN CONTROL ROOM BY 
298 A4040 2.20 INS KM IN 0 23‐Dec‐18 01‐Jan‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
VENDOR
INSTALLATION OF BS & WNALYZERS ON 
299 A4020‐2 2.20 INS KM IN 0 30‐Dec‐18 01‐Jan‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
300 A4020‐3 2.20 INSTALLATION OF INSTRUMENT VALVE INS KM IN 0 01‐Jan‐19 05‐Jan‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
301 A4030‐1 2.20 SS TUBEND LEAK TEST INS KM IN 0 02‐Jan‐19 06‐Jan‐19 0.06% 0.29% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
302 A5280 2.50 INSTALLATION OF  DELUGE INS KM IN SET 671 0 01‐Jan‐19 07‐Jan‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT EQUIPMENT CALIBRATION / 
303 A4010 2.20 INS KM IN SET 154 0 07‐Jan‐19 10‐Jan‐19 0.08% 0.39% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LOOP TEST
F&G System
294 A6100 2.50 F&G SUPPORT INSTALLATION INS KM IN 0 10‐Dec‐18 13‐Dec‐18 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
294 A6110 2.50 F&G DEVICES INSTALLATION INS KM IN 0 12‐Dec‐18 16‐Dec‐18 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
295 A6130 2.50 F&G JB SUPPORT INSTALLATION INS KM IN 0 15‐Dec‐18 16‐Dec‐18 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
295 A6120 2.50 F&G CABLE INSTALLATION INS KM IN 0 16‐Dec‐18 25‐Dec‐18 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
296 A6140 2.50 F&G JB INSTALLATION INS KM IN 0 17‐Dec‐18 18‐Dec‐18 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

297 A6150 2.50 F&G CABLE GLANDINGND TERMINATION INS KM IN 0 31‐Dec‐18 05‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

296 A6160 2.50 F&G LOOP PREPARATION INS KM IN 0 05‐Jan‐19 06‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
297 A6170 2.50 F&G LOOP TESTING INS KM IN 0 07‐Jan‐19 10‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% Page 92 of 170
0.00% 0.00% 0.00% 0.00%
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
Painting & Fireproofing
305 A4340 2.10 PIPING PAINTINGND TOUCH‐UP INS KM FP SQM 277 0 22‐Dec‐18 29‐Dec‐18 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

306 A4350 2.50 FIREPROOFING FOR STRUCTURAL STEEL INS KM FP SQM 1180.3 0 02‐Dec‐18 20‐Dec‐18 0.18% 0.87% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

307 A4330 2.40 STRUCTURAL STEEL PAINTINGND TOUCH‐UP INS KM FP SQM 231.3 0 28‐Nov‐18 08‐Dec‐18 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Demolition Works
309 DM1000 2.60 WORK PERMITPPROVED FOR DEMOLITION INS KM DEM PCS 8.8 0 24‐Jan‐19 27‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

DEPRESSURIZATION / ISOLATION (PIPING & 
310 DM1010 2.60 INS KM DEM PCS 41.8 0 27‐Jan‐19 29‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTATION)
311 DM1030 2.60 APPLYNTI RUST TO FOUNDATION BOTLS INS KM DEM PCS 28.6 0 29‐Jan‐19 30‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

312 DM1020 2.60 COLD CUTTING INLETND OUTLET PIPING INS KM DEM PCS 66 0 30‐Jan‐19 23‐Feb‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

313 DM1040 2.60 UNBOLD & REMOVE EXISTING SEPARATOR INS KM DEM PCS 165 0 23‐Feb‐19 24‐Feb‐19 0.03% 0.12% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

REMOVE CONCRETE FOUNDATION / GRADE 
314 DM1050 2.60 INS KM DEM PCS 218 0 24‐Feb‐19 10‐Mar‐19 0.03% 0.16% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
THEREA
KAHS
Civil Works
COMMOMN
318 A1710 3.40 GRADING INS KS CV SQM 286 286 10‐Feb‐18 31‐May‐18 10‐Feb‐18 19‐Jul‐18 0.04% 0.21% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

SOAKWAY PIT EXCAVATION & INSTALLATION 
319 A1715‐6 3.40 INS KS CV 0 06‐Aug‐18 03‐Nov‐18 06‐Aug‐18 0.01% 0.05% 100.000% 95.00% 0.00% 98.00% 90.00% 98.00% 8.00%
INCL. DEMOLITION ‐  IFPPLICABLE
320 A1780‐2 3.40 CABLE TRENCHES INS KS CV 0 24‐Sep‐18 22‐Nov‐18 24‐Sep‐18 0.00% 0.00% 100.000% 20.00% 0.00% 35.00% 53.33% 35.00% ‐18.33%

321 A1710‐1 3.40 PROTECTION OF UNDERGROUND CABLES INS KS CV 0 14‐Sep‐18 22‐Nov‐18 14‐Sep‐18 0.00% 0.01% 100.000% 90.00% 0.00% 90.00% 60.00% 90.00% 30.00%

322 A1780 3.40 UTILITY ROAD CROSSINGS INS KS CV PCS 140.8 0 11‐Dec‐18 09‐Jan‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
323 A1790 3.40 DRAINAGE PIPE CULVERTS INS KS CV LM 0.187 0 08‐Dec‐18 30‐Dec‐18 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
ROADSND PAVING(INCLUDING 
324 A1770 3.40 INS KS CV SQM 35.2 0 31‐Dec‐18 14‐Jan‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MODIFICATIONS)
325 A1800 3.40 ROAD SAFETY CRASH BARRIERSND BOLLARD INS KS CV PCS 132 0 31‐Dec‐18 14‐Jan‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

RE‐INSTATEMENT OF EXISTING PAVEMENT 
326 A1800‐1 3.40 INS KS CV 0 30‐Dec‐18 13‐Jan‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(INTERLOCK PAVING)
TEST SEPERATOR
328 A1715 3.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS KS CV CUM 40 40 10‐Feb‐18 01‐Mar‐18 10‐Feb‐18 01‐Mar‐18 0.02% 0.08% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

329 A1720 3.40 FOUNDATION WORK  (STEEL FIXING) INS KS CV kg 1656 1656 07‐Apr‐18 12‐Apr‐18 07‐Apr‐18 12‐Apr‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
330 A1720‐1 3.40 FOUNDATION WORK  (CONCRETE) INS KS CV CUM 14.55 14.55 07‐Apr‐18 26‐Apr‐18 07‐Apr‐18 26‐Apr‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

331 A1720‐2 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 108 108 17‐May‐18 08‐Aug‐18 17‐May‐18 16‐Jul‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

332 A1720‐2 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 108 108 17‐May‐18 08‐Aug‐18 17‐May‐18 08‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

TEST SEPERATOR PLATFORM
334 A1715‐1 3.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS KS CV 0 10‐Feb‐18 01‐Mar‐18 10‐Feb‐18 01‐Mar‐18 0.02% 0.08% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

335 A1720‐3 3.40 FOUNDATION WORK  (STEEL FIXING) INS KS CV 0 07‐Apr‐18 12‐Apr‐18 07‐Apr‐18 12‐Apr‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
336 A1720‐4 3.40 FOUNDATION WORK  (CONCRETE) INS KS CV 0 07‐Apr‐18 26‐Apr‐18 07‐Apr‐18 26‐Apr‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

337 A1720‐5 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV 0 17‐May‐18 08‐Aug‐18 17‐May‐18 16‐Jul‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

338 A1720‐5 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV 0 17‐May‐18 08‐Aug‐18 17‐May‐18 08‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

METERING SKID
340 A1715‐2 3.40 EXCAVATION INS KS CV CUM 60 60 10‐Feb‐18 24‐Mar‐18 10‐Feb‐18 24‐Mar‐18 0.03% 0.16% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
341 A1760‐1 3.40 FOUNDATION WORK  (STEEL FIXING) INS KS CV kg 1656 1656 22‐Mar‐18 12‐Apr‐18 22‐Mar‐18 12‐Apr‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
342 A1760 3.40 FOUNDATION WORK  (CONCRETE) INS KS CV CUM 14.55 14.55 18‐Mar‐18 24‐May‐18 18‐Mar‐18 24‐May‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

343 A1760‐2 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 108 108 15‐May‐18 08‐Aug‐18 15‐May‐18 19‐Jul‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

344 A1760‐2 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 108 108 15‐May‐18 08‐Aug‐18 15‐May‐18 08‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

PIPE SUPPORT
EXCAVATION FOR STRUCTURAL STEEL PIPE 
346 A1715‐3 3.40 INS KS CV CUM 72 72 25‐Dec‐17 19‐Jul‐18 10‐Feb‐18 19‐Apr‐18 0.03% 0.16% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
SUPPORTS
347 A1740 XX 3.40 FOUNDATION WORK  (STEEL FIXING) INS KS CV CUM 4200 4200 25‐Dec‐17 08‐Aug‐18 25‐Dec‐17 19‐Jul‐18 0.03% 0.15% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
348 A1740 XX 3.40 FOUNDATION WORK  (STEEL FIXING) INS KS CV CUM 4200 4200 25‐Dec‐17 08‐Aug‐18 25‐Dec‐17 08‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
349 A1740‐1 XX 3.40 FOUNDATION WORK  (CONCRETE) INS KS CV CUM 35 35 25‐Dec‐17 14‐Aug‐18 25‐Dec‐17 19‐Jul‐18 0.03% 0.15% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
350 A1740‐1 XX 3.40 FOUNDATION WORK  (CONCRETE) INS KS CV CUM 35 35 25‐Dec‐17 14‐Aug‐18 25‐Dec‐17 14‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

351 A1740‐2 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 150 150 25‐Dec‐17 25‐Oct‐18 25‐Dec‐17 19‐Jul‐18 0.03% 0.15% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

352 A1740‐2 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 150 150 25‐Dec‐17 25‐Oct‐18 25‐Dec‐17 0.00% 0.00% 100.000% 98.00% 0.00% 100.00% 100.00% 100.00% 0.00%

PSV
EXCAVATION (INCLUDINGREA LIGHTING 
354 A1715‐4 3.40 INS KS CV CUM 100 100 05‐Mar‐18 31‐May‐18 05‐Mar‐18 31‐May‐18 0.03% 0.16% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
POLES)
355 A1760‐5 3.40 FOUNDATION WORK  (STEEL FIXING) INS KS CV CUM 3647 3647 25‐Mar‐18 17‐May‐18 25‐Mar‐18 17‐May‐18 0.01% 0.03% 100.000% 100.00% 0.00% Page 93
100.00% of 170
100.00% 100.00% 0.00%
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
356 A1760‐3 3.40 FOUNDATION WORK  (CONCRETE) INS KS CV CUM 26 26 18‐Mar‐18 21‐Jun‐18 18‐Mar‐18 21‐Jun‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

357 A1760‐4 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 206 206 18‐Mar‐18 06‐Aug‐18 18‐Mar‐18 19‐Jul‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

358 A1760‐4 XX 3.40 CURING / WATERPROOFING / BACK FILLING INS KS CV CUM 206 206 18‐Mar‐18 06‐Aug‐18 18‐Mar‐18 06‐Aug‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

Structural Steel
TEST SEPERATOR
INSTALLATION OF STRUCTURAL STEELWORK 
361 A2480 3.40 OPERATINGNDCCESS PLATFORMS (TEST  INS KS STIN Kg 9298 929.8 27‐Sep‐18 21‐Nov‐18 27‐Sep‐18 0.09% 0.45% 100.000% 10.00% ‐48.21% 10.00% 51.79% 10.00% ‐41.79%
SEPERATOR & PLATFORM)
INSTALLATION OF LADDERS, STAIRS, 
362 A2510 3.40 INS KS STIN Kg 4078 0 12‐Nov‐18 21‐Nov‐18 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
HANDRAILS
METERING SKID
INSTALLATION OF STRUCTURAL STEEL OF 
364 A2490 3.40 METERING SKID INCL. WALK WAY OR CROSS  INS KS STIN Kg 2470 2470 13‐Oct‐18 23‐Oct‐18 13‐Oct‐18 23‐Oct‐18 0.01% 0.03% 100.000% 70.00% 0.00% 100.00% 100.00% 100.00% 0.00%
OVER
PSV
INSTALLATION OF PSV VALVESCCESS 
366 A2500 3.40 INS KS STIN Kg 1705 596.75 17‐Oct‐18 15‐Nov‐18 17‐Oct‐18 01‐Nov‐18 0.01% 0.06% 100.000% 35.00% 0.00% 35.00% 30.00% 35.00% 5.00%
PLATFORMS
PIPE SUPPORT
INSTALLATION OF STRUCTURAL STEEL PIPE 
368 A2520 3.40 SUPPORTS & MODIFICATIONS OF  INS KS STIN PCS 151 30.2 10‐Oct‐18 27‐Nov‐18 10‐Oct‐18 0.00% 0.02% 100.000% 10.00% ‐67.35% 20.00% 32.65% 20.00% ‐12.65%
EXISTINGCCESS PLATFORMS (IFPPLICABLE)
FIELD INSTRUMENT
370 A2520‐1 3.40 INSTALLATION OF INSTRUMENT STANCHION INS KS STIN 0 25‐Nov‐18 29‐Nov‐18 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

Mechanical
372 A2815 3.10 INSTALLATION OF NEW TEST SEPARATOR INS KS ME SET 137.5 137.5 09‐Aug‐18 09‐Aug‐18 09‐Aug‐18 09‐Aug‐18 0.02% 0.10% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

Piping
EARLY SHUTDOWN WORKS ‐ Pre Shutdownnd Plant Shutdown Tie‐in
375 A3061 3.10 MOBILIZATION OF OF TEAMPPLY PTW INS KS PPIN 0 31‐Dec‐17 31‐Dec‐17 31‐Dec‐17 31‐Dec‐17 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
SCAFFOLDING / PLATE FORM / WORK 
376 A3071 3.10 INS KS PPIN PCS 142 142 31‐Dec‐17 05‐Jan‐18 31‐Dec‐17 05‐Jan‐17 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
PERMIT ISSUE
377 A3091 3.10 TIE‐IN COMPLETE / REMOVE SCAFFOLD INS KS PPIN PCS 14 14 06‐Feb‐18 17‐Feb‐18 06‐Feb‐18 17‐Feb‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
378 A3081 3.10 PIPING TIE‐IN / NDT INS KS PPIN DIN 85 85 09‐Feb‐18 14‐Feb‐18 09‐Feb‐18 14‐Feb‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
STATION PIPING
PIPING INSTALLATION ON PIPE 
380 A3020 3.10 INS KS PPIN DIN 368 0 16‐Dec‐18 05‐Jan‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SUPPORT,PIERACK &ROUND EQUIPMENT

381 A3020‐1 3.10 INSTALLATION OF BALL VALVE & GGC VALVE INS KS PPIN 0 24‐Dec‐18 02‐Jan‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HYDRO‐TESTING, FLUSHING, DRAININGND 
382 A3040 3.10 INS KS PPIN SET 220.8 0 24‐Dec‐18 06‐Jan‐19 0.03% 0.16% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PURGING
INLET PIPING  TIE‐IN TO SEPARATOR 
383 A3030 3.10 INS KS PPIN DIN 367.896 0 06‐Jan‐19 09‐Jan‐19 0.06% 0.27% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(PARTIAL SHUTDOWN TIE‐IN)
384 A3050 3.10 TIE‐IN INS KS PPIN PCS 1752.78 0 06‐Jan‐19 09‐Jan‐19 0.27% 1.29% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REPLACE THE SHUTVALVET POINT OF OIL‐IN 
385 A3051 3.10 INS KS PPIN PCS 60.72 0 07‐Jan‐19 09‐Jan‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TIE‐IN / INSTALL SDV
Instrument & Control
387 A4050 3.20 CABLE TRAY/DUCT INSTALLATION INS KS IN LM 36.3 0 13‐Nov‐18 02‐Dec‐18 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
387 A4640 3.20 JB SUPPORT INSTALLATION INS KS IN 0 02‐Dec‐18 05‐Dec‐18 0.00% 0.01% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
388 A4740 3.20 JB INSTALLATION INS KS IN 0 04‐Dec‐18 06‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
388 A4080‐1 3.20 INSTRUMENT CABLE LAYING INS KS IN 0 05‐Dec‐18 24‐Dec‐18 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

389 A4070 3.20 INSTRUMENT EQUIPEMNT INSTALLATION  INS KS IN SET 317.9 0 20‐Dec‐18 26‐Dec‐18 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

FIELD INSTRUMENT INSTALLATION 
390 A4080‐2 3.20 INS KS IN 0 16‐Dec‐18 23‐Dec‐18 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(GAUGESND TRANSMITTERS)
389 A4080‐11 3.20 CABLE GLANDND TERMINATION (ALONG JB) INS KS IN 0 24‐Dec‐18 03‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

CABLE GLANDND TERMINATION (ALONG 
390 A4080‐21 3.20 INS KS IN 0 20‐Dec‐18 25‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT)
DCS INSTALLATION IN CONTROL ROOM BY 
391 A4090 3.20 INS KS IN 0 25‐Dec‐18 05‐Jan‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
VENDOR
INSTALLATION OF BS & WNALYZERS ON 
392 A4090‐1 3.20 INS KS IN 0 25‐Dec‐18 26‐Dec‐18 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
393 A4090‐2 3.20 INSTALLATION OF INSTRUMENT VALVE INS KS IN 0 23‐Dec‐18 25‐Dec‐18 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
394 A5300 3.50 INSTALLATION OF  DELUGE INS KS IN SET 451 0 01‐Jan‐19 08‐Jan‐19 0.02% 0.11% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT EQUIPMENT CALIBRATION / 
395 A4060 3.20 INS KS IN SET 0 0 05‐Jan‐19 08‐Jan‐19 0.05% 0.22% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LOOP TEST
396 A4080 3.20 SS TUBEND LEAK TEST INS KS IN LM 1056 0 01‐Jan‐19 05‐Jan‐19 0.06% 0.30% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Electrical
387 A1780‐12 3.40 CABLE TRENCH INS KS IN M 500 400 24‐Sep‐18 22‐Nov‐18 0.00% 0.00% 100.000% 0.00% ‐46.67% 80.00% 53.33% 80.00% 26.67%
388 A3530 3.30 EARTH PIT DRILLING INS KS IN NO 3 0 08‐Nov‐18 12‐Nov‐18 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
398 A3460 3.30 U/G CABLE LAYING INS KS EL LM 161.7 0 29‐Nov‐18 04‐Dec‐18 0.02% 0.12% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
399 A3470 3.30 CABLE TRAY INSTALLATION INS KS EL LM 292.6 0 22‐Nov‐18 01‐Dec‐18 0.01% 0.05% 100.000% 0.00% ‐100.00% Page 94 of 170
0.00% 0.00% 0.00% 0.00%
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
400 A3490 3.30 CABLE LAYING INS KS EL LM 88 0 02‐Dec‐18 10‐Dec‐18 0.01% 0.06% 42.105% 0.00% ‐42.11% 0.00% 0.00% 0.00% 0.00%
401 A3460‐1 3.30 BACK FILLING OF CABLE TRENCH INS KS EL 0 02‐Dec‐18 11‐Dec‐18 0.02% 0.07% 53.333% 0.00% ‐53.33% 0.00% 0.00% 0.00% 0.00%
402 A3450 3.30 CABLE GLANDINGND TERMINATION INS KS EL LM 116.6 0 22‐Dec‐18 29‐Dec‐18 0.02% 0.09% 7.143% 0.00% ‐7.14% 0.00% 0.00% 0.00% 0.00%

403 A3480 3.30 ELECTRICAL EQUIPMENTS INSTALLATION INS KS EL PCS 92.4 0 09‐Dec‐18 19‐Dec‐18 0.01% 0.07% 7.143% 0.00% ‐7.14% 0.00% 0.00% 0.00% 0.00%

404 A3500 3.30 LIGHTING FIXTUREND DB INSTALLATION INS KS EL PCS 231 0 16‐Dec‐18 24‐Dec‐18 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

405 A3510‐1 3.30 HOOK UP INS KS EL 0 25‐Dec‐18 29‐Dec‐18 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
406 A3510 3.30 ELECTRICAL TIE‐INS INS KS EL SET 44 0 03‐Jan‐19 05‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
407 A3520 3.30 ENERGIZATION INS KS EL SET 44 0 05‐Jan‐19 07‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
F&G System
387 A5920 3.50 F&G SUPPORTS INSTALLATION INS KS IN LM 36.3 0 28‐Nov‐18 02‐Dec‐18 0.00% 0.01% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
387 A5930 3.50 F&G DEVICES INSTALLATION INS KS IN 0 04‐Dec‐18 09‐Dec‐18 0.00% 0.01% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
388 A5910 3.50 F&G CABLE INSTALLATION INS KS IN 0 05‐Dec‐18 15‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
388 A5940 3.50 F&G JB SUPPORT INSTALLATION INS KS IN 0 05‐Dec‐18 06‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
389 A5950 3.50 F&G JB INSTALLATION INS KS IN SET 317.9 0 06‐Dec‐18 09‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

390 A5960 3.50 F&G CABLE GLANDINGND TERMINATION INS KS IN 0 20‐Dec‐18 25‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

389 A5970 3.50 F&G LOOP PREPARATION INS KS IN 0 25‐Dec‐18 27‐Dec‐18 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
390 A5980 3.50 F&G LOOP TESTING INS KS IN 0 31‐Dec‐18 05‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting & Fireproofing
409 A4360 3.40 STRUCTURAL STEEL PAINTINGND TOUCH‐UP INS KS FP SQM 194 0 15‐Dec‐18 27‐Dec‐18 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

410 A4370 3.10 PIPING PAINTINGND TOUCH‐UP INS KS FP SQM 259 0 24‐Dec‐18 27‐Dec‐18 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

411 A4380 3.50 FIREPROOFING FOR STRUCTURAL STEEL INS KS FP SQM 995.5 0 19‐Dec‐18 06‐Jan‐19 0.15% 0.73% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Demolition Works
413 DM1070 3.60 WORK PERMITPPROVED FOR DEMOLITION INS KS DEM PCS 8.8 0 17‐Jan‐19 20‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

DEPRESSURIZATION / ISOLATION (PIPING & 
414 DM1080 3.60 INS KS DEM PCS 39.93 0 27‐Jan‐19 28‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTATION)
415 DM1100 3.60 APPLYNTI RUST TO FOUNDATION BOTLS INS KS DEM PCS 19.965 0 28‐Jan‐19 30‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

COLD CUTTING INLETND OUTLET PIPING 
416 DM1090 3.60 INS KS DEM PCS 39.93 0 28‐Jan‐19 20‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REMOVAL
417 DM1110 3.60 UNBOLD & REMOVE EXISTING SEPARATOR INS KS DEM PCS 139.755 0 20‐Feb‐19 24‐Feb‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

REMOVE CONCRETE FOUNDATION / GRADE 
418 DM1120 3.60 INS KS DEM PCS 169 0 24‐Feb‐19 10‐Mar‐19 0.03% 0.12% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
THEREA
JALM
Civil Works
COMMOMN
422 A1840 7.40 GRADING INS JL CV SQM 374 374 05‐Jun‐18 12‐Jun‐18 05‐Jun‐18 18‐Jul‐18 0.06% 0.28% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

SOAKWAY PIT EXCAVATION & INSTALLATION 
423 A1845‐6 7.40 INS JL CV 0 23‐Aug‐18 21‐Nov‐18 23‐Aug‐18 0.02% 0.09% 100.000% 70.00% ‐29.67% 77.00% 70.33% 77.00% 6.67%
INCL. DEMOLITION ‐  IFPPLICABLE
CABLE TRENCHESND UTILITY ROAD 
424 A1910 7.40 INS JL CV PCS 316.8 15.84 18‐Oct‐18 23‐Dec‐18 18‐Oct‐10 0.02% 0.09% 68.966% 0.00% ‐57.03% 5.00% 11.94% 5.00% ‐6.94%
CROSSINGS
425 A1840‐1 7.40 PROTECTION OF UNDERGROUND CABLES INS JL CV 0 04‐Dec‐18 09‐Dec‐18 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

426 A1920 7.40 DRAINAGE PIPE CULVERTS INS JL CV LM 56.1 0 09‐Dec‐18 20‐Jan‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

427 A1936 7.40 RE‐INSTATEMENT OF EXISTINGSPHALT ROAD INS JL CV SQM 14.3 0 13‐Mar‐19 28‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

428 A1930 7.40 ROAD SAFETY CRASH BARRIERSND BOLLARD INS JL CV PCS 66 0 17‐Mar‐19 31‐Mar‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

RE‐INSTATEMENT OF EXISTING PAVEMENT 
429 A1938 7.40 INS JL CV SQM 13.2 0 17‐Mar‐19 31‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(INTERLOCK PAVING)
430 A1935 7.40 NEW RETAINING WALLS INS JL CV CUM 168 0 13‐Mar‐19 28‐Mar‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
431 A1937 7.40 CONCRETE KERB INS JL CV CUM 235.4 0 13‐Mar‐19 28‐Mar‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TEST SEPERATOR
433 A1845 XX 7.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS JL CV CUM 55.33 55.33 12‐Jun‐18 09‐Aug‐18 12‐Jun‐18 18‐Jul‐18 0.03% 0.16% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

434 A1845 XX 7.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS JL CV CUM 55.33 55.33 12‐Jun‐18 09‐Aug‐18 12‐Jun‐18 09‐Aug‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

435 A1850 XX 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV CUM 1534 1534 10‐Jul‐18 19‐Aug‐18 10‐Jul‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
436 A1850 XX 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV CUM 1534 1534 10‐Jul‐18 19‐Aug‐18 10‐Jul‐18 19‐Aug‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
437 A1850‐1 7.40 FOUNDATION WORK  (CONCRETE) INS JL CV CUM 15.8 15.8 13‐Aug‐18 23‐Aug‐18 13‐Aug‐18 23‐Aug‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

438 A1850‐2 7.40 CURING / WATERPROOFING / BACK FILLING INS JL CV CUM 45 45 26‐Aug‐18 08‐Oct‐18 26‐Aug‐18 08‐Oct‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

TEST SEPERATOR PLATFORM
440 A1845‐1 7.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS JL CV 0 27‐Jul‐18 11‐Aug‐18 27‐Jul‐18 11‐Aug‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

441 A1850‐3 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV 0 12‐Aug‐18 03‐Sep‐18 12‐Aug‐18 03‐Sep‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
442 A1850‐4 7.40 FOUNDATION WORK  (CONCRETE) INS JL CV 0 03‐Sep‐18 22‐Sep‐18 03‐Sep‐18 22‐Sep‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

443 A1850‐5 7.40 CURING / WATERPROOFING / BACK FILLING INS JL CV 0 11‐Sep‐18 25‐Sep‐18 11‐Sep‐18 25‐Sep‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

METERING SKID
445 A1845‐2 7.40 EXCAVATION / Blinidng INS JL CV CUM 60 60 12‐Jun‐18 05‐Jul‐18 12‐Jun‐18 05‐Jul‐18 0.03% 0.16% 100.000% 100.00% 0.00% Page 95
100.00% of 170
100.00% 100.00% 0.00%
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
446 A1890 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV CUM 1656 1656 03‐Jul‐18 31‐Jul‐18 03‐Jul‐18 31‐Jul‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
447 A1890‐1 7.40 FOUNDATION WORK  (CONCRETE) INS JL CV CUM 14.55 14.55 09‐Jul‐18 05‐Aug‐18 09‐Jul‐18 05‐Aug‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

448 A1890‐3 7.40 CURING / WATERPROOFING / BACK FILLING INS JL CV CUM 108 108 08‐Aug‐18 27‐Sep‐18 08‐Aug‐18 27‐Sep‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

PIPE SUPPORT
EXCAVATION FOR STRUCTURAL STEEL PIPE 
450 A1845‐3 7.40 INS JL CV CUM 50 49 03‐Aug‐18 22‐Nov‐18 03‐Aug‐18 0.03% 0.16% 100.000% 98.00% ‐25.00% 98.00% 75.00% 98.00% 23.00%
SUPPORTS
451 A1870‐1 XX 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV CUM 4200 4200 09‐Jul‐18 06‐Dec‐18 09‐Jul‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% ‐27.81% 100.00% 72.19% 100.00% 27.81%
452 A1870‐1 XX 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV CUM 4200 3528 09‐Jul‐18 06‐Dec‐18 06‐Aug‐18 0.02% 0.10% 100.000% 80.00% ‐27.81% 84.00% 72.19% 84.00% 11.81%
453 A1870‐2 7.40 FOUNDATION WORK  (CONCRETE) INS JL CV CUM 35 26.25 10‐Sep‐18 16‐Dec‐18 10‐Sep‐18 0.03% 0.16% 100.000% 55.00% ‐53.06% 75.00% 46.94% 75.00% 28.06%

454 A1870‐3 7.40 CURING / WATERPROOFING / BACK FILLING INS JL CV CUM 76 45.6 20‐Sep‐18 25‐Dec‐18 20‐Sep‐18 0.03% 0.16% 100.000% 30.00% ‐62.89% 60.00% 37.11% 60.00% 22.89%

PSV
456 A1845‐4 XX 7.40 EXCAVATION INS JL CV CUM 30 30 05‐Jun‐18 06‐Sep‐18 05‐Jun‐18 19‐Jul‐18 0.01% 0.05% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
457 A1845‐4 XX 7.40 EXCAVATION INS JL CV CUM 70 70 05‐Jun‐18 06‐Sep‐18 05‐Jun‐18 06‐Sep‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
458 A1890‐4 XX 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV CUM 3647 3647 09‐Jul‐18 13‐Sep‐18 09‐Jul‐18 19‐Jul‐18 0.00% 0.01% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
459 A1890‐4 XX 7.40 FOUNDATION WORK  (STEEL FIXING) INS JL CV CUM 3647 3647 09‐Jul‐18 13‐Sep‐18 09‐Jul‐18 13‐Sep‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
460 A1890‐5 7.40 FOUNDATION WORK  (CONCRETE) INS JL CV CUM 26 26 16‐Aug‐18 16‐Sep‐18 16‐Aug‐18 16‐Sep‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

461 A1890‐6 7.40 CURING / WATERPROOFING / BACK FILLING INS JL CV CUM 206 206 03‐Sep‐18 03‐Oct‐18 03‐Sep‐18 03‐Oct‐18 0.01% 0.03% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

Structural Steel
TEST SEPERATOR
INSTALLATION OF STRUCTURAL STEELWORK 
464 A2540 7.40 OPERATINGNDCCESS PLATFORMS (TEST  INS JL STIN Kg 9298 464.9 07‐Oct‐18 09‐Jan‐19 07‐Oct‐18 0.10% 0.45% 60.000% 5.00% ‐40.00% 5.00% 20.00% 5.00% ‐15.00%
SEPERATOR & PLATFORM)
INSTALLATION OF LADDERS, STAIRS, 
465 A2580 7.40 INS JL STIN PCS 151 0 01‐Jan‐19 09‐Jan‐19 0.02% 0.11% 18.182% 0.00% ‐18.18% 0.00% 0.00% 0.00% 0.00%
HANDRAILS
METERING SKID
INSTALLATION OF STRUCTURAL STEEL OF 
467 A2550 7.40 METERING SKID INCL. WALK WAY OR CROSS  INS JL STIN Kg 2470 0 01‐Jan‐19 14‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
OVER
PSV
INSTALLATION OF PSV VALVESCCESS 
469 A2560 7.40 INS JL STIN Kg 1705 0 01‐Jan‐19 14‐Jan‐19 0.01% 0.06% 18.182% 0.00% ‐18.18% 0.00% 0.00% 0.00% 0.00%
PLATFORMS
PIPE SUPPORT
INSTALLATION OF STRUCTURAL STEEL PIPE 
471 A2570 7.40 SUPPORTS & MODIFICATIONS OF  INS JL STIN Kg 4078 0 27‐Dec‐18 14‐Jan‐19 0.01% 0.03% 15.000% 0.00% ‐15.00% 0.00% 0.00% 0.00% 0.00%
EXISTINGCCESS PLATFORMS (IFPPLICABLE)
FIELD INSTRUMENT
473 A2570‐1 7.40 INSTALLATION OF INSTRUMENT STANCHION INS JL STIN 0 10‐Jan‐19 14‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Mechanical
475 A2835 7.10 INSTALLATION OF NEW TEST SEPARATOR INS JL ME SET 137.5 137.5 10‐Sep‐18 14‐Oct‐18 10‐Sep‐18 14‐Oct‐18 0.02% 0.10% 100.000% 50.00% 0.00% 100.00% 100.00% 100.00% 0.00%

Piping
HOT TAPPING
MOBILIZATION OF HOT TAPPING SUB 
478 HT1080 7.10 INS JL HTAP 0 10‐Feb‐19 12‐Feb‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
CONTRACTOR
SCAFFOLDING / PLATE FORM / WORK 
479 HT1090 7.10 INS JL HTAP 0 12‐Feb‐19 19‐Feb‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERMIT ISSUE
480 HT1100 7.10 FLARE TAPPING / NDT INS JL HTAP 0 19‐Feb‐19 28‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FLARE TAPPING COMPLETE / REMOVE 
481 HT1110 7.10 INS JL HTAP 0 24‐Feb‐19 28‐Feb‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SCAFFOLD
Pre Shutdownnd Plant Shutdown Tie‐in
483 A3100‐2 7.10 MOBILIZATION OF OF TEAMPPLY PTW INS JL PPIN 0 04‐Mar‐19 05‐Mar‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SCAFFOLDING / PLATE FORM / WORK 
484 A3100‐3 7.10 INS JL PPIN 0 05‐Mar‐19 11‐Mar‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERMIT ISSUE
485 A3100‐4 7.10 PIPING TIE‐IN / NDT PRE SHUT DOWN INS JL PPIN 0 21‐Feb‐19 28‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
486 A3100‐5 7.10 PIPING TIE‐IN / NDT SHUT DOWN INS JL PPIN 0 05‐Mar‐19 15‐Mar‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PIPING ‐REMAINING
PIPING INSTALLATION ON PIPE 
488 A3070 7.10 INS JL PPIN DIN 446 0 01‐Jan‐19 06‐Feb‐19 0.10% 0.48% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SUPPORT,PIERACK &ROUND EQUIPMENT

489 A3070‐1 7.10 INSTALLATION OF BALL VALVE & GGC VALVE INS JL PPIN 0 27‐Jan‐19 05‐Feb‐19 0.05% 0.24% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

INLET PIPING  TIE‐IN TO SEPARATOR 
490 A3080 7.10 INS JL PPIN DIN 446 0 06‐Mar‐19 11‐Mar‐19 0.10% 0.48% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(PARTIAL SHUTDOWN TIE‐IN)
HYDRO‐TESTING, FLUSHING, DRAININGND 
491 A3090 7.10 INS JL PPIN SET 240 0 07‐Feb‐19 20‐Feb‐19 0.05% 0.24% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PURGING
492 A3100 7.10 TIE‐IN INS JL PPIN PCS 2151.6 0 05‐Mar‐19 11‐Mar‐19 0.07% 0.34% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REPLACE THE SHUTVALVET POINT OF OIL‐IN 
493 A3101 7.10 INS JL PPIN PCS 66 0 09‐Mar‐19 11‐Mar‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TIE‐IN / INSTALL SDV
Electrical
495 A6180 7.40 CABLE TRENCH INS JL EL LM 500 0 25‐Nov‐18 23‐Dec‐18 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
496 A6190 7.30 EARTH PIT DRILLING INS JL EL NO 3 0 04‐Dec‐18 10‐Dec‐18 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
495 A3560 7.30 CABLE TRAY INSTALLATION INS JL EL LM 292.6 0 10‐Jan‐19 19‐Jan‐19 0.01% 0.05% 0.000% 0.00% 0.00% Page 96 of 170
0.00% 0.00% 0.00% 0.00%
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
496 A3550 7.30 U/G CABLE LAYING INS JL EL LM 275 0 12‐Jan‐19 26‐Jan‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
497 A3580 7.30 CABLE LAYING INS JL EL LM 243.1 0 15‐Jan‐19 06‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

498 A3570 7.30 ELECTRICAL EQUIPMENTS INSTALLATION INS JL EL PCS 83.6 0 03‐Feb‐19 16‐Feb‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

499 A3550‐1 7.30 BACK FILLING OF CABLE TRENCH INS JL EL 0 26‐Jan‐19 09‐Feb‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
500 A3540 7.30 CABLE GLANDND TERMINATION INS JL EL LM 116.6 0 05‐Feb‐19 16‐Feb‐19 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

501 A3590 7.30 LIGHTING FIXTUREND DB INSTALLATION INS JL EL PCS 198 0 10‐Feb‐19 16‐Feb‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

502 A3580‐1 7.30 HOOK UP INS JL EL 0 17‐Feb‐19 20‐Feb‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
503 A3600 7.30 ELECTRICAL TIE‐INS INS JL EL SET 44 0 20‐Feb‐19 26‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
504 A3610 7.30 ENERGIZATION INS JL EL SET 44 0 26‐Feb‐19 02‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Instrument & Control
506 A4100 7.20 CABLE TRAYND SUPPORT INSTALLATION INS JL IN LM 36.3 0 29‐Dec‐18 16‐Jan‐19 0.02% 0.08% 20.000% 0.00% ‐20.00% 0.00% 0.00% 0.00% 0.00%

506 A4540 7.20 JB SUPPORT INSTALLATION INS JL IN 0 16‐Jan‐19 19‐Jan‐19 0.00% 0.01% 20.000% 0.00% ‐20.00% 0.00% 0.00% 0.00% 0.00%
507 A4880 7.20 JB INSTALLATION INS JL IN 0 20‐Jan‐19 22‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
507 A4130 7.20 INSTRUMENT CABLE LAYING INS JL IN LM 1672 0 12‐Jan‐19 31‐Jan‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

508 A4120 7.20 INSTRUMENT EQUIPEMNT INSTALLATION INS JL IN SET 317.9 0 24‐Jan‐19 16‐Feb‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

FIELD INSTRUMENT INSTALLATION 
509 A4120‐1 7.20 INS JL IN 0 30‐Jan‐19 19‐Feb‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(GAUGESND TRANSMITTER)
INSTALLATION OF BS & WNALYZERS ON 
510 A4120‐3 7.20 INS JL IN 0 14‐Feb‐19 16‐Feb‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
508 A4120‐11 7.20 CABLE GLANDND TERMINATION (ALONG JB) INS JL IN 0 31‐Jan‐19 06‐Feb‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

CABLE GLANDND TERMINATION (ALONG 
509 A4120‐21 7.20 INS JL IN 0 19‐Feb‐19 25‐Feb‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT)
DCS INSTALLATION IN CONTROL ROOM BY 
511 A4140 7.20 INS JL IN 0 20‐Feb‐19 25‐Feb‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
VENDOR
512 A5310 7.50 INSTALLATION OF  DELUGE  INS JL IN SET 605 0 12‐Feb‐19 20‐Feb‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
513 A4120‐2 7.20 INSTALLATION OF INSTRUMENT VALVE INS JL IN 0 19‐Feb‐19 24‐Feb‐19 0.06% 0.31% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
514 A4130‐1 7.20 SS TUBEND LEAK TEST INS JL IN 0 21‐Feb‐19 25‐Feb‐19 0.06% 0.31% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT EQUIPMENT CALIBRATION / 
515 A4110 7.20 INS JL IN SET 154 0 25‐Feb‐19 02‐Mar‐19 0.09% 0.41% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LOOP TEST
F&G System
506 A6230 7.50 F&G CABLE INSTALLATION INS JL IN 0 12‐Jan‐19 21‐Jan‐19 0.00% 0.01% 20.000% 0.00% ‐20.00% 0.00% 0.00% 0.00% 0.00%
506 A6200 7.50 F&G SUPPORT INSTALLATION INS JL IN 0 13‐Jan‐19 16‐Jan‐19 0.00% 0.01% 20.000% 0.00% ‐20.00% 0.00% 0.00% 0.00% 0.00%
507 A6210 7.50 F&G DEVICES INSTALLATION INS JL IN 0 15‐Jan‐19 19‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
507 A6220 7.50 F&G JB SUPPORT INSTALLATION INS JL IN 0 20‐Jan‐19 21‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
508 A6240 7.50 F&G JB INSTALLATION INS JL IN 0 22‐Jan‐19 23‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

509 A6250 7.50 F&G CABLE GLANDINGND TERMINATION INS JL IN 0 21‐Feb‐19 25‐Feb‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

510 A6260 7.50 F&G LOOP PREPARATION INS JL IN 0 26‐Feb‐19 27‐Feb‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
508 A6270 7.50 F&G LOOP TESTING INS JL IN 0 27‐Feb‐19 02‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting & Fireproofing
517 A4390 7.40 STRUCTURAL STEEL PAINTINGND TOUCH‐UP INS JL FP SQM 203 0 06‐Feb‐19 20‐Feb‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

518 A4400 7.10 PIPING PAINTINGND TOUCH‐UP INS JL FP SQM 302 0 06‐Feb‐19 20‐Feb‐19 0.05% 0.22% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

519 A4410 7.50 FIREPROOFING FOR STRUCTURAL STEEL INS JL FP SQM 1037.3 0 06‐Feb‐19 25‐Feb‐19 0.16% 0.76% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Demolition Works
521 DM1140 7.60 WORK PERMITPPROVED FOR DEMOLITION INS JL DEM PCS 8.8 0 03‐Apr‐19 06‐Apr‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

DEPRESSURIZATION / ISOLATION (PIPING & 
522 DM1150 7.60 INS JL DEM PCS 80.96 0 07‐Apr‐19 09‐Apr‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTATION)
523 DM1170 7.60 APPLYNTI RUST TO FOUNDATION BOTLS INS JL DEM PCS 40.48 0 09‐Apr‐19 10‐Apr‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

524 DM1160 7.60 COLD CUTTING INLETND OUTLET PIPING INS JL DEM PCS 80.96 0 10‐Apr‐19 06‐May‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

525 DM1180 7.60 UNBOLD & REMOVE EXISTING SEPARATOR INS JL DEM PCS 283.36 0 06‐May‐19 08‐May‐19 0.04% 0.21% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

REMOVE CONCRETE FOUNDATION / GRADE 
526 DM1190 7.60 INS JL DEM PCS 333 0 08‐May‐19 26‐May‐19 0.05% 0.25% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
THEREA
FAHS
Civil Works
COMMOMN
530 A1960 6.40 GRADING INS FS CV SQM 239.8 239.8 08‐Apr‐18 14‐Apr‐18 08‐Apr‐18 14‐Apr‐18 0.04% 0.17% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

531 A1960‐1 6.40 PROTECTION OF UNDERGROUND CABLES INS FS CV 0 10‐Sep‐18 10‐Dec‐18 10‐Sep‐18 0.00% 0.00% 100.000% 90.00% 0.00% 90.00% 50.00% 90.00% 40.00%

CABLE TRENCHESND UTILITY ROAD 
532 A2030 6.40 INS FS CV PCS 369.6 166.32 10‐Sep‐18 10‐Dec‐18 10‐Sep‐18 0.03% 0.14% 100.000% 35.00% 0.00% 45.00% 50.00% 45.00% ‐5.00%
CROSSINGS
SOAKWAY PIT EXCAVATION & INSTALLATION 
533 A1965‐5 6.40 INS FS CV 0 05‐Sep‐18 10‐Dec‐18 05‐Sep‐18 0.03% 0.14% 100.000% 55.00% 0.00% 65.00% 52.58% 65.00% 12.42%
INCL. DEMOLITION ‐  IFPPLICABLE
534 A2040 6.40 DRAINAGE PIPE CULVERTS INS FS CV LM 4.95 0 11‐Dec‐18 21‐Jan‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
ROADSND PAVING(INCLUDING 
535 A2020 6.40 INS FS CV SQM 57.75 0 04‐Apr‐19 20‐Apr‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MODIFICATIONS)
Page 97 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)

536 A2050 6.40 ROAD SAFETY CRASH BARRIERSND BOLLARD INS FS CV PCS 66 0 18‐Apr‐19 02‐May‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

RE‐INSTATEMENT OF EXISTING PAVEMENT 
537 A2080 6.40 INS FS CV SQM 25.85 0 02‐May‐19 16‐May‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(INTERLOCK PAVING)
TEST SEPERATOR
539 A1965 6.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS FS CV CUM 40 40 08‐Apr‐18 04‐May‐18 08‐Apr‐18 04‐May‐18 0.04% 0.17% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

540 A1970 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV CUM 1534 1534 02‐Jun‐18 05‐Jul‐18 02‐Jun‐18 05‐Jul‐18 0.03% 0.13% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
541 A1970‐1 XX 6.40 FOUNDATION WORK  (CONCRETE) INS FS CV CUM 15.8 15.8 02‐Jun‐18 19‐Jul‐18 02‐Jun‐18 19‐Jul‐18 0.03% 0.12% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
542 A1970‐1 XX 6.40 FOUNDATION WORK  (CONCRETE) INS FS CV CUM 15.8 15.8 02‐Jun‐18 19‐Jul‐18 02‐Jun‐18 20‐Jul‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

543 A1970‐2 XX 6.40 CURING / WATERPROOFING / BACK FILLING INS FS CV CUM 45 45 19‐Jul‐18 13‐Sep‐18 19‐Jul‐18 19‐Jul‐18 0.01% 0.04% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

544 A1970‐2 XX 6.40 CURING / WATERPROOFING / BACK FILLING INS FS CV CUM 45 45 19‐Jul‐18 13‐Sep‐18 19‐Jul‐18 13‐Sep‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

TEST SEPERATOR PLATFORM
546 A1965‐1 6.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS FS CV 0 01‐Aug‐18 09‐Oct‐18 01‐Aug‐18 09‐Oct‐18 0.00% 0.02% 100.000% 95.00% 0.00% 100.00% 100.00% 100.00% 0.00%

547 A1970‐3 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV 0 22‐Aug‐18 06‐Dec‐18 22‐Aug‐18 0.00% 0.02% 100.000% 90.00% 0.00% 97.00% 60.75% 97.00% 36.25%
548 A1970‐4 6.40 FOUNDATION WORK  (CONCRETE) INS FS CV 0 03‐Sep‐18 16‐Dec‐18 03‐Sep‐18 0.00% 0.02% 100.000% 45.00% 0.00% 75.00% 50.48% 75.00% 24.52%

549 A1970‐5 6.40 CURING / WATERPROOFING / BACK FILLING INS FS CV 0 16‐Sep‐18 25‐Dec‐18 16‐Sep‐18 0.00% 0.02% 100.000% 25.00% 0.00% 60.00% 39.60% 60.00% 20.40%

METERING SKID
551 A1965‐2 XX 6.40 EXCAVATION INS FS CV CUM 62.91 62.91 14‐Apr‐18 21‐Jul‐18 14‐Apr‐18 21‐Jun‐18 0.04% 0.17% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
552 A1965‐2 XX 6.40 EXCAVATION INS FS CV CUM 62.91 62.91 14‐Apr‐18 21‐Jul‐18 14‐Apr‐18 21‐Jul‐17 0.02% 0.09% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
553 A2010 XX 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV CUM 1656 1656 09‐Jul‐18 10‐Sep‐18 09‐Jul‐18 19‐Jul‐18 0.01% 0.04% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
554 A2010 XX 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV CUM 1656 1656 09‐Jul‐18 10‐Sep‐18 09‐Jul‐18 10‐Sep‐18 0.02% 0.08% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
555 A2010‐1 6.40 FOUNDATION WORK  (CONCRETE) INS FS CV CUM 14.55 14.55 15‐Aug‐18 24‐Sep‐18 15‐Aug‐18 24‐Sep‐18 0.02% 0.09% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

556 A2010‐2 6.40 CURING / WATERPROOFING / BACK FILLING INS FS CV CUM 108 97.2 11‐Sep‐18 01‐Dec‐18 11‐Sep‐18 0.02% 0.09% 100.000% 65.00% 0.00% 90.00% 54.88% 90.00% 35.12%

PIPE SUPPORT
EXCAVATION FOR STRUCTURAL STEEL PIPE 
558 A1965‐3 XX 6.40 INS FS CV CUM 50 50 18‐Jul‐18 24‐Nov‐18 18‐Jul‐18 19‐Jul‐18 0.00% 0.00% 100.000% 100.00% ‐23.08% 100.00% 76.92% 100.00% 23.08%
SUPPORTS
EXCAVATION FOR STRUCTURAL STEEL PIPE 
559 A1965‐3 XX 6.40 INS FS CV CUM 50 47.5 18‐Jul‐18 24‐Nov‐18 18‐Jul‐18 0.03% 0.17% 100.000% 88.00% 0.00% 95.00% 76.92% 95.00% 18.08%
SUPPORTS
560 A1990 XX 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV CUM 4200 4200 14‐Sep‐18 05‐Dec‐18 10‐Jun‐18 19‐Jul‐18 0.02% 0.12% 100.000% 100.00% ‐49.40% 100.00% 50.60% 100.00% 49.40%
561 A1990 XX 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV CUM 4200 2730 14‐Sep‐18 05‐Dec‐18 14‐Sep‐18 0.02% 0.08% 100.000% 30.00% ‐49.40% 65.00% 50.60% 65.00% 14.40%
562 A1990‐1 6.40 FOUNDATION WORK  (CONCRETE) INS FS CV CUM 35 11.55 30‐Sep‐18 10‐Dec‐18 30‐Sep‐18 0.04% 0.19% 100.000% 10.00% ‐63.89% 33.00% 36.11% 33.00% ‐3.11%

563 A1990‐2 6.40 CURING / WATERPROOFING / BACK FILLING INS FS CV CUM 76 25.08 03‐Oct‐18 10‐Dec‐18 03‐Oct‐18 0.04% 0.19% 100.000% 10.00% ‐66.67% 33.00% 33.33% 33.00% ‐0.33%

PSV
565 A1965‐4 6.40 EXCAVATION INS FS CV CUM 100 100 21‐May‐18 08‐Aug‐18 21‐May‐18 08‐Aug‐18 0.04% 0.17% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
566 A2010‐3 XX 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV CUM 3647 3647 05‐Jun‐18 15‐Nov‐18 05‐Jun‐18 19‐Jul‐18 0.01% 0.03% 100.000% 100.00% ‐12.80% 100.00% 87.20% 100.00% 12.80%
567 A2010‐3 XX 6.40 FOUNDATION WORK  (STEEL FIXING) INS FS CV CUM 3647 3464.65 05‐Jun‐18 15‐Nov‐18 05‐Jun‐18 28‐Oct‐18 0.00% 0.02% 100.000% 95.00% ‐12.80% 95.00% 87.20% 95.00% 7.80%
568 A2010‐4 XX 6.40 FOUNDATION WORK  (CONCRETE) INS FS CV CUM 26 26 08‐Jul‐18 29‐Nov‐18 08‐Jul‐18 19‐Jul‐18 0.00% 0.01% 100.000% 100.00% ‐24.14% 100.00% 75.86% 100.00% 24.14%
569 A2010‐4 XX 6.40 FOUNDATION WORK  (CONCRETE) INS FS CV CUM 26 23.4 08‐Jul‐18 29‐Nov‐18 08‐Jul‐18 31‐Oct‐18 0.01% 0.03% 100.000% 90.00% ‐24.14% 90.00% 75.86% 90.00% 14.14%

570 A2010‐5 6.40 CURING / WATERPROOFING / BACK FILLING INS FS CV CUM 206 185.4 08‐Sep‐18 13‐Dec‐18 08‐Sep‐18 0.01% 0.04% 100.000% 90.00% ‐50.52% 90.00% 49.48% 90.00% 40.52%

Structural Steel
TEST SEPERATOR
INSTALLATION OF STRUCTURAL STEELWORK 
573 A2600 6.40 OPERATINGNDCCESS PLATFORMS (TEST  INS FS STIN Kg 9298 0 30‐Dec‐18 17‐Jan‐19 0.11% 0.51% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SEPERATOR & PLATFORM)
INSTALLATION OF LADDERS, STAIRS, 
574 A2640 6.40 INS FS STIN PCS 151 0 08‐Jan‐19 17‐Jan‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HANDRAILS
METERING SKID
INSTALLATION OF STRUCTURAL STEEL OF 
576 A2610 6.40 METERING SKID INCL. WALK WAY OR CROSS  INS FS STIN Kg 2470 0 31‐Dec‐18 20‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
OVER
PSV
INSTALLATION OF PSV VALVESCCESS 
578 A2620 6.40 INS FS STIN Kg 1705 0 16‐Dec‐18 24‐Dec‐18 0.01% 0.07% 18.182% 0.00% ‐18.18% 0.00% 0.00% 0.00% 0.00%
PLATFORMS
PIPE SUPPORT
INSTALLATION OF STRUCTURAL STEEL PIPE 
580 A2630 6.40 SUPPORTS & MODIFICATIONS OF  INS FS STIN Kg 4078 0 20‐Dec‐18 21‐Jan‐19 0.01% 0.03% 10.000% 0.00% ‐10.00% 0.00% 0.00% 0.00% 0.00%
EXISTINGCCESS PLATFORMS (IFPPLICABLE)
FIELD INSTRUMENT
582 A2630‐1 6.40 INSTALLATION OF INSTRUMENT STANCHION INS FS STIN 0 28‐Jan‐19 02‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Mechanical
584 A2855 6.10 INSTALLATION OF NEW TEST SEPARATOR INS FS ME SET 137.5 137.5 06‐Oct‐18 08‐Oct‐18 06‐Oct‐18 08‐Oct‐18 0.02% 0.10% 100.000% 0.00% 0.00% 100.00% 100.00% 100.00% 0.00%

Piping
HOT TAPPING
MOBILIZATION OF HOT TAPPING SUB 
587 HT1120 6.10 INS FS HTAP 0 28‐Feb‐19 03‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
CONTRACTOR
Page 98 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
SCAFFOLDING / PLATE FORM / WORK 
588 HT1130 6.10 INS FS HTAP 0 03‐Mar‐19 12‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERMIT ISSUE
589 HT1140 6.10 FLARE TIE‐IN / NDT INS FS HTAP 0 13‐Mar‐19 27‐Mar‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

590 HT1150 6.10 HOT TIE‐IN COMPLETE / REMOVE SCAFFOLD INS FS HTAP 0 09‐Apr‐19 22‐Apr‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Pre Shutdownnd Plant Shutdown Tie‐in
592 A3150‐000 6.10 MOBILIZATION OF OF TEAMPPLY PTW INS FS PPIN 0 30‐Mar‐19 30‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
593 A3150‐1 6.10 PIPING TIE‐IN / NDT PRE SHUT DOWN INS FS PPIN 0 30‐Mar‐19 15‐Apr‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SCAFFOLDING / PLATE FORM / WORK 
594 A3150‐00 6.10 INS FS PPIN 0 31‐Mar‐19 08‐Apr‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERMIT ISSUE
595 A3150‐2 6.10 PIPING TIE‐IN / NDT SHUT DOWN INS FS PPIN 0 15‐Apr‐19 22‐Apr‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PIPING ‐REMAINING
PIPING INSTALLATION ON PIPE 
597 A3120 6.10 INS FS PPIN DIN 335 0 23‐Dec‐18 03‐Feb‐19 0.07% 0.34% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SUPPORT,PIERACK &ROUND EQUIPMENT

598 A3120‐1 6.10 INSTALLATION OF BALL VALVE & GGC VALVE INS FS PPIN 0 15‐Jan‐19 24‐Jan‐19 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HYDRO‐TESTING, FLUSHING, DRAININGND 
599 A3140 6.10 INS FS PPIN SET 240 0 29‐Jan‐19 12‐Feb‐19 0.07% 0.34% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PURGING
INLET PIPING  TIE‐IN TO SEPARATOR 
600 A3130 6.10 INS FS PPIN DIN 335 0 29‐Jan‐19 03‐Feb‐19 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(PARTIAL SHUTDOWN TIE‐IN)
601 A3150 6.10 TIE‐IN INS FS PPIN PCS 1412.4 0 29‐Jan‐19 03‐Feb‐19 0.05% 0.24% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REPLACE THE SHUTVALVET POINT OF OIL‐IN 
602 A3151 6.10 INS FS PPIN PCS 66 0 31‐Jan‐19 03‐Feb‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TIE‐IN / INSTALL SDV
Electrical
604 A6520 6.40 CABLE TRENCH INS FS EL LM 500 0 10‐Sep‐18 10‐Dec‐18 0.00% 0.00% 100.000% 0.00% ‐50.00% 0.00% 50.00% 0.00% ‐50.00%
605 A3920 6.30 EARTH PIT DRILLING INS FS EL NO 3 0 20‐Dec‐18 24‐Dec‐18 0.00% 0.02% 40.000% 0.00% ‐40.00% 0.00% 0.00% 0.00% 0.00%
604 A3650 6.30 CABLE TRAY INSTALLATION INS FS EL LM 301.4 0 20‐Dec‐18 08‐Jan‐19 0.01% 0.05% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
605 A3640 6.30 U/G CABLE LAYING INS FS EL LM 319 0 03‐Jan‐19 10‐Jan‐19 0.05% 0.23% 40.000% 0.00% ‐40.00% 0.00% 0.00% 0.00% 0.00%
606 A3640‐1 6.30 BACK FILLING OF CABLE TRENCH INS FS EL 0 10‐Jan‐19 27‐Jan‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
607 A3670 6.30 CABLE LAYING INS FS EL LM 259.6 0 23‐Dec‐18 08‐Jan‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
608 A3630 6.30 CABLE GLADND TERMINATION INS FS EL LM 123.2 0 30‐Dec‐18 12‐Jan‐19 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

609 A3660 6.30 ELECTRICAL EQUIPMENTS INSTALLATION INS FS EL PCS 110 0 30‐Dec‐18 12‐Jan‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

610 A3680 6.30 LIGHTING FIXTUREND DB INSTALLATION INS FS EL PCS 253 0 05‐Jan‐19 12‐Jan‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

611 A3670‐1 6.30 HOOK UP INS FS EL 0 12‐Jan‐19 16‐Jan‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
612 A3690 6.30 ELECTRICAL TIE‐INS INS FS EL SET 44 0 16‐Jan‐19 17‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
613 A3700 6.30 ENERGIZATION INS FS EL SET 44 0 17‐Jan‐19 21‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Instrument & Control
615 A4150 6.20 CABLE TRAY/DUCT INSTALLATION INS FS IN LM 36.3 0 05‐Jan‐19 21‐Jan‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
615 A3710 6.20 JB SUPPORT INSTALLATION INS FS IN 0 17‐Jan‐19 21‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
616 A3810 6.20 JB INSTALLATION INS FS IN 0 22‐Jan‐19 26‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
616 A4180 6.20 INSTRUMENT CABLE LAYING INS FS IN LM 1117.6 0 17‐Jan‐19 05‐Feb‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

617 A3900 6.20 CABLE GLANDND TERMINATION (ALONG JB) INS FS IN 0 27‐Jan‐19 31‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

617 A4170 6.20 INSTRUMENT EQUIPEMNT INSTALLATION INS FS IN SET 306.9 0 02‐Feb‐19 20‐Feb‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

FIELD INSTRUMENT INSTALLATION 
618 A4170‐2 6.20 INS FS IN 0 02‐Feb‐19 20‐Feb‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(GAUGESND TRANSMITTER)
INSTALLATION OF BS & WNALYZERS ON 
619 A4170‐3 6.20 INS FS IN 0 18‐Feb‐19 20‐Feb‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
CABLE GLANDND TERMINATION (ALONG 
618 A3910 6.20 INS FS IN 0 20‐Feb‐19 25‐Feb‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTS)
DCS MODIFICATIOM IN CONTROL ROOM BY 
620 A4190 6.20 INS FS IN 0 24‐Feb‐19 02‐Mar‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
VENDOR
621 A4170‐1 6.20 INSTALLATION OF INSTRUMENT VALVE INS FS IN 0 14‐Feb‐19 20‐Feb‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
622 A5320 6.50 INSTALLATION OF  DELUGE  INS FS IN SET 451 0 16‐Feb‐19 20‐Feb‐19 0.02% 0.11% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT EQUIPMENT CALIBRATION / 
623 A4160 6.20 INS FS IN SET 147.4 0 05‐Mar‐19 11‐Mar‐19 0.05% 0.23% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LOOP TEST
624 A4180‐1 6.20 SS TUBEND LEAK TEST INS FS IN 0 02‐Mar‐19 05‐Mar‐19 0.06% 0.30% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
F&G System
615 A6290 6.50 F&G SUPPORT INSTALLATION INS FS IN 0 17‐Jan‐19 21‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
615 A6280 6.50 F&G CABLE INSTALLATION INS FS IN 0 17‐Jan‐19 27‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
616 A6300 6.50 F&G DEVICES INSTALLATION INS FS IN 0 21‐Jan‐19 24‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
616 A6310 6.50 F&G JB SUPPORT INSTALLATION INS FS IN 0 22‐Jan‐19 23‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
617 A6320 6.50 F&G JB INSTALLATION INS FS IN 0 27‐Jan‐19 28‐Jan‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

617 A6330 6.50 F&G CABLE GLANDINGND TERMINATION INS FS IN 0 20‐Feb‐19 25‐Feb‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

618 A6340 6.50 F&G LOOP PREPARATION INS FS IN 0 25‐Feb‐19 27‐Feb‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
619 A6350 6.50 F&G LOOP TESTING INS FS IN 0 03‐Mar‐19 05‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting & Fireproofing
626 A4430 6.10 PIPING PAINTINGND TOUCH‐UP INS FS FP SQM 241 0 29‐Jan‐19 12‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

627 A4440 6.50 FIREPROOFING FOR STRUCTURAL STEEL INS FS FP SQM 1146.2 0 02‐Feb‐19 02‐Mar‐19 0.18% 0.84% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

628 A4420 6.40 STRUCTURAL STEEL PAINTINGND TOUCH‐UP INS FS FP SQM 237 0 27‐Jan‐19 09‐Feb‐19 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Demolition Works Page 99 of 170


Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)

630 DM1210 6.60 WORK PERMITPPROVED FOR DEMOLITION INS FS DEM PCS 8.8 0 18‐May‐19 20‐May‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

DEPRESSURIZATION / ISOLATION (PIPING & 
631 DM1220 6.60 INS FS DEM PCS 47.52 0 21‐May‐19 22‐May‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTATION)
632 DM1240 6.60 APPLYNTI RUST TO FOUNDATION BOTLS INS FS DEM PCS 23.76 0 22‐May‐19 23‐May‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

633 DM1230 6.60 COLD CUTTING INLETND OUTLET PIPING INS FS DEM PCS 47.52 0 23‐May‐19 16‐Jun‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

634 DM1250 6.60 UNBOLD & REMOVE EXISTING SEPARATOR INS FS DEM PCS 166.32 0 16‐Jun‐19 18‐Jun‐19 0.03% 0.12% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

REMOVE CONCRETE FOUNDATION / GRADE 
635 DM1260 6.60 INS FS DEM PCS 199 0 18‐Jun‐19 01‐Jul‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
THEREA
FAHN
Civil Works
COMMOMN
639 A2090 4.40 GRADING INS FN CV SQM 338.8 338.8 05‐May‐18 10‐May‐18 05‐May‐18 10‐May‐18 0.05% 0.24% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

640 A2090‐1 4.40 PROTECTION OF UNDERGROUND CABLES INS FN CV 0 13‐Aug‐18 24‐Dec‐18 13‐Aug‐18 0.00% 0.00% 0.000% 80.00% 55.22% 80.00% 55.22% 80.00% 24.78%

SOAKWAY PIT EXCAVATION & INSTALLATION 
641 A2095‐00 4.40 INS FN CV 0 18‐Sep‐18 07‐Nov‐18 12‐Sep‐18 0.01% 0.05% 100.000% 50.00% ‐25.49% 55.00% 74.51% 55.00% ‐19.51%
INCL. DEMOLITION ‐  IFPPLICABLE
642 A2160‐1 4.40 CABLE TRENCHES INS FN CV 0 08‐Nov‐18 24‐Dec‐18 0.01% 0.05% 42.857% 0.00% ‐42.86% 0.00% 0.00% 0.00% 0.00%
643 A2170 4.40 DRAINAGE PIPE CULVERTS INS FN CV LM 4.587 0 25‐Dec‐18 06‐Jan‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
RE‐INSTATEMENT OF EXISTING PAVEMENT 
644 A2200 4.40 INS FN CV SQM 178.75 0 13‐Apr‐19 28‐Apr‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(INTERLOCK PAVING)
ROADSND PAVING(INCLUDING 
645 A2150 4.40 INS FN CV SQM 0 0 13‐Apr‐19 28‐Apr‐19 0.01% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MODIFICATIONS)
646 A2160 4.40 UTILITY ROAD CROSSINGS INS FN CV PCS 211.2 0 16‐Apr‐19 05‐May‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

647 A2180 4.40 ROAD SAFETY CRASH BARRIERSND BOLLARD INS FN CV PCS 66 0 21‐Apr‐19 05‐May‐19 0.01% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

TEST SEPERATOR
649 A2095 XX 4.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS FN CV CUM 40 40 05‐May‐18 04‐Aug‐18 05‐May‐18 05‐Jul‐18 0.04% 0.18% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

650 A2095 XX 4.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS FN CV CUM 40 40 05‐May‐18 04‐Aug‐18 05‐May‐18 04‐Aug‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

651 A2100 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 1534 1534 03‐Jul‐18 16‐Aug‐18 03‐Jul‐18 19‐Jul‐18 0.02% 0.12% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
652 A2100 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 1534 1534 03‐Jul‐18 16‐Aug‐18 03‐Jul‐18 16‐Aug‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
653 A2100‐1 XX 4.40 FOUNDATION WORK  (CONCRETE) INS FN CV CUM 15.8 15.8 17‐Jul‐18 23‐Aug‐18 17‐Jul‐18 17‐Jul‐18 0.01% 0.06% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
654 A2100‐1 XX 4.40 FOUNDATION WORK  (CONCRETE) INS FN CV CUM 15.8 15.8 17‐Jul‐18 23‐Aug‐18 17‐Jul‐18 23‐Aug‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

655 A2100‐3 4.40 CURING / WATERPROOFING / BACK FILLING INS FN CV CUM 45 45 05‐Aug‐18 09‐Sep‐18 05‐Aug‐18 09‐Sep‐18 0.00% 0.02% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%

TEST SEPERATOR PLATFORM
657 A2095‐1 4.40 EXCAVATION FOR THE MAIN FOUNDATIONS INS FN CV 0 28‐Aug‐18 26‐Nov‐18 28‐Aug‐18 0.01% 0.03% 100.000% 50.00% ‐35.16% 84.00% 64.84% 84.00% 19.16%

658 A2100‐4 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV 0 10‐Oct‐18 03‐Dec‐18 10‐Oct‐18 0.01% 0.03% 100.000% 0.00% ‐70.91% 60.00% 29.09% 60.00% 30.91%
659 A2100‐5 4.40 FOUNDATION WORK  (CONCRETE) INS FN CV 0 22‐Nov‐18 12‐Dec‐18 0.01% 0.03% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

660 A2140‐125 4.40 CURING / WATERPROOFING / BACK FILLING INS FN CV 0 03‐Dec‐18 31‐Dec‐18 0.01% 0.03% 40.000% 0.00% ‐40.00% 0.00% 0.00% 0.00% 0.00%

METERING SKID
662 A2095‐2 4.40 EXCAVATION INS FN CV CUM 60 60 05‐May‐18 07‐Aug‐18 05‐May‐18 07‐Aug‐18 0.03% 0.15% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
663 A2140 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 1656 1656 04‐Jul‐18 05‐Sep‐18 04‐Jul‐18 04‐Jul‐18 0.01% 0.04% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
664 A2140 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 1656 1656 04‐Jul‐18 05‐Sep‐18 04‐Jul‐18 05‐Sep‐18 0.02% 0.11% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
665 A2140‐1 4.40 FOUNDATION WORK  (CONCRETE) INS FN CV CUM 14.55 14.55 28‐Aug‐18 28‐Oct‐18 28‐Aug‐18 20‐Oct‐18 0.02% 0.11% 100.000% 98.00% ‐4.84% 100.00% 95.16% 100.00% 4.84%

666 A2140‐2 4.40 CURING / WATERPROOFING / BACK FILLING INS FN CV CUM 108 103.68 08‐Oct‐18 26‐Nov‐18 08‐Oct‐18 0.02% 0.11% 100.000% 92.00% ‐64.00% 96.00% 36.00% 96.00% 60.00%

PIPE SUPPORT
EXCAVATION FOR STRUCTURAL STEEL PIPE 
668 A2095‐3 4.40 INS FN CV CUM 50 47.5 04‐Aug‐18 15‐Nov‐18 04‐Aug‐18 0.04% 0.19% 100.000% 92.00% ‐20.19% 95.00% 79.81% 95.00% 15.19%
SUPPORTS
669 A2120 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 4200 4200 08‐Sep‐18 29‐Nov‐18 09‐Jul‐18 09‐Jul‐18 0.02% 0.07% 100.000% 100.00% ‐42.17% 100.00% 57.83% 100.00% 42.17%
670 A2120 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 4200 3570 08‐Sep‐18 29‐Nov‐18 08‐Sep‐18 0.04% 0.19% 100.000% 85.00% ‐42.17% 85.00% 57.83% 85.00% 27.17%
671 A2120‐1 4.40 FOUNDATION WORK  (CONCRETE) INS FN CV CUM 35 29.75 11‐Sep‐18 19‐Dec‐18 11‐Sep‐18 0.04% 0.19% 85.106% 80.00% ‐40.11% 85.00% 45.00% 85.00% 40.00%

672 A2120‐2 4.40 CURING / WATERPROOFING / BACK FILLING INS FN CV CUM 76 38 16‐Sep‐18 02‐Jan‐19 16‐Sep‐18 0.04% 0.19% 60.417% 30.00% ‐23.72% 50.00% 36.70% 50.00% 13.30%

PSV
674 A2095‐4 XX 4.40 EXCAVATION INS FN CV CUM 100 100 26‐May‐18 22‐Oct‐18 26‐May‐18 26‐May‐18 0.02% 0.07% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
675 A2095‐4 XX 4.40 EXCAVATION INS FN CV CUM 100 100 26‐May‐18 22‐Oct‐18 26‐May‐18 22‐Oct‐18 0.02% 0.11% 100.000% 95.00% 0.00% 100.00% 100.00% 100.00% 0.00%
676 A2140‐3 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 3647 3647 09‐Jul‐18 15‐Nov‐18 09‐Jul‐18 09‐Jul‐18 0.00% 0.02% 100.000% 100.00% ‐16.15% 100.00% 83.85% 100.00% 16.15%
677 A2140‐3 XX 4.40 FOUNDATION WORK  (STEEL FIXING) INS FN CV CUM 3647 3099.95 09‐Jul‐18 15‐Nov‐18 09‐Jul‐18 0.01% 0.03% 100.000% 85.00% ‐16.15% 85.00% 83.85% 85.00% 1.15%
678 A2140‐4 4.40 FOUNDATION WORK  (CONCRETE) INS FN CV CUM 26 19.5 10‐Sep‐18 29‐Dec‐18 10‐Sep‐18 0.01% 0.05% 100.000% 70.00% ‐58.56% 75.00% 41.44% 75.00% 33.56%

679 A2140‐5 4.40 CURING / WATERPROOFING / BACK FILLING INS FN CV CUM 206 133.9 18‐Sep‐18 15‐Dec‐18 18‐Sep‐18 0.01% 0.05% 100.000% 50.00% ‐57.30% 65.00% 42.70% 65.00% 22.30%

Structural Steel
TEST SEPERATOR
INSTALLATION OF STRUCTURAL STEELWORK 
682 A2660 4.40 OPERATINGNDCCESS PLATFORMS (TEST  INS FN STIN Kg 9298 0 06‐Jan‐19 26‐Jan‐19 0.06% 0.30% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SEPERATOR & PLATFORM)

Page 100 of 170


Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
INSTALLATION OF LADDERS, STAIRS, 
683 A2660‐1 4.40 INS FN STIN 0 16‐Jan‐19 26‐Jan‐19 0.06% 0.30% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HANDRAILS
METERING SKID
INSTALLATION OF STRUCTURAL STEEL OF 
685 A2670 4.40 METERING SKID INCL. WALK WAY OR CROSS  INS FN STIN Kg 2470 0 09‐Jan‐19 21‐Jan‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
OVER
PSV
INSTALLATION OF PSV VALVESCCESS 
687 A2680 4.40 INS FN STIN Kg 1705 0 26‐Dec‐18 05‐Jan‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PLATFORMS
PIPE SUPPORT
INSTALLATION OF STRUCTURAL STEEL PIPE 
689 A2690 4.40 SUPPORTS & MODIFICATIONS OF  INS FN STIN Kg 4078 0 10‐Jan‐19 30‐Jan‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
EXISTINGCCESS PLATFORMS (IFPPLICABLE)
FIELD INSTRUMENT
691 A2700 4.40 INSTALLATION OF INSTRUMENT STANCHION INS FN STIN PCS 151 0 30‐Jan‐19 04‐Feb‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Mechanical
693 A2875 4.10 INSTALLATION OF NEW TEST SEPARATOR INS FN ME SET 137.5 137.5 05‐Sep‐18 12‐Sep‐18 05‐Sep‐18 12‐Sep‐18 0.02% 0.10% 0.000% 100.00% 100.00% 100.00% 100.00% 100.00% 0.00%

Piping
Pre Shutdownnd Plant Shutdown Tie‐in
696 A3200‐a 4.10 MOBILIZATION OF OF TEAMPPLY PTW INS FN PPIN 0 24‐Mar‐19 24‐Mar‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SCAFFOLDING / PLATE FORM / WORK 
697 A3200‐b 4.10 INS FN PPIN 0 24‐Mar‐19 31‐Mar‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERMIT ISSUE
698 A3200‐1 4.10 PIPING TIE‐IN / NDT PRE SHUT DOWN INS FN PPIN 0 31‐Mar‐19 15‐Apr‐19 0.06% 0.29% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
699 A3200‐2 4.10 PIPING TIE‐IN / NDT SHUT DOWN INS FN PPIN 0 15‐Apr‐19 22‐Apr‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PIPING ‐REMAINING
PIPING INSTALLATION ON PIPE 
701 A3170 4.10 INS FN PPIN DIN 316 0 21‐Jan‐19 13‐Feb‐19 0.08% 0.39% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SUPPORT,PIERACK &ROUND EQUIPMENT

702 A3170‐1 4.10 INSTALLATION OF BALL VALVE & GGC VALVE INS FN PPIN 0 29‐Jan‐19 11‐Feb‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HYDRO‐TESTING, FLUSHING, DRAININGND 
703 A3190 4.10 INS FN PPIN SET 240 0 02‐Feb‐19 16‐Feb‐19 0.08% 0.39% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PURGING
INLET PIPING  TIE‐IN TO SEPARATOR 
704 A3180 4.10 INS FN PPIN DIN 316 0 15‐Apr‐19 20‐Apr‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(PARTIAL SHUTDOWN TIE‐IN)
705 A3200 4.10 TIE‐IN INS FN PPIN PCS 1782 0 15‐Apr‐19 20‐Apr‐19 0.06% 0.27% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REPLACE THE SHUTVALVET POINT OF OIL‐IN 
706 A3201 4.10 INS FN PPIN PCS 66 0 17‐Apr‐19 20‐Apr‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TIE‐IN / INSTALL SDV
Electrical
708 A2160‐11 4.40 CABLE TRENCH INS FN EL LM 141.9 0 08‐Nov‐18 24‐Dec‐18 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
709 A3930 4.30 EARTH PIT DRILLING INS FN EL 0 31‐Dec‐18 05‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
708 A3730 4.30 U/G CABLE LAYING INS FN EL LM 141.9 0 30‐Dec‐18 07‐Jan‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
709 A3730‐1 4.30 BACK FILLING OF CABLE TRENCH INS FN EL 0 06‐Jan‐19 19‐Jan‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
710 A3760 4.30 CABLE LAYING INS FN EL LM 88 0 30‐Jan‐19 18‐Feb‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
711 A3720 4.30 CABLE GLANDND TERMINATION INS FN EL LM 116.6 0 16‐Feb‐19 28‐Feb‐19 0.02% 0.09% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

712 A3750 4.30 ELECTRICAL EQUIPMENTS INSTALLATION INS FN EL PCS 92.4 0 02‐Feb‐19 14‐Feb‐19 0.01% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

713 A3770 4.30 LIGHTING FIXTUREND DB INSTALLATION INS FN EL PCS 231 0 21‐Feb‐19 03‐Mar‐19 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

714 A3740 4.30 CABLE TRAY INSTALLATION INS FN EL LM 292.6 0 26‐Jan‐19 04‐Feb‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
715 A3760‐1 4.30 HOOK UP INS FN EL 0 03‐Mar‐19 07‐Mar‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
716 A3780 4.30 ELECTRICAL TIE‐INS INS FN EL SET 44 0 07‐Mar‐19 09‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
717 A3790 4.30 ENERGIZATION INS FN EL SET 44 0 10‐Mar‐19 13‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Instrument & Control
719 A4200 4.20 CABLE TRAY/DUCT INSTALLATION INS FN IN LM 36.3 0 16‐Jan‐19 30‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
719 A4940 4.20 JB SUPPORT INSTALLATION  INS FN IN LM 36.3 0 27‐Jan‐19 30‐Jan‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
720 A4930 4.20 JB INSTALLATION INS FN IN 0 30‐Jan‐19 02‐Feb‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FIELD INSTRUMENT INSTALLATION 
720 A4220‐2 4.20 INS FN IN 0 23‐Jan‐19 18‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(GAUGESND TRANMITTERS)
721 A4230 4.20 INSTRUMENT CABLE LAYING INS FN IN LM 1441 0 22‐Jan‐19 09‐Feb‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

722 A4220 4.20 INSTRUMENT EQUIPEMNT INSTALLATION INS FN IN SET 317.9 0 23‐Jan‐19 12‐Feb‐19 0.05% 0.23% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

721 A4980 4.20 CABLE GLANDND TERMINATION (ALONG JB) INS FN IN LM 1441 0 10‐Feb‐19 20‐Feb‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

CABLE GLANDND TERMINATION (ALONG 
722 A4990 4.20 INS FN IN SET 317.9 0 16‐Feb‐19 23‐Feb‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTS)
DCS MODIFICATION IN CONTROL ROOM BY 
723 A4240 4.20 INS FN IN 0 12‐Feb‐19 21‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
VENDOR
724 A4220‐1 4.20 INSTALLATION OF INSTRUMENT VALVE INS FN IN 0 10‐Feb‐19 12‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTALLATION OF BS & WNALYZERS ON 
725 A4220‐3 4.20 INS FN IN 0 10‐Feb‐19 12‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
726 A4230‐1 4.20 SS TUBEND LEAK TEST INS FN IN 0 23‐Feb‐19 26‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT EQUIPMENT CALIBRATION / 
727 A4210 4.20 INS FN IN SET 154 0 25‐Feb‐19 03‐Mar‐19 0.02% 0.11% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LOOP TEST
728 A5330 4.50 INSTALLATION OF  DELUGE INS FN IN SET 550 0 05‐Feb‐19 12‐Feb‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
F&G System Page 101 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)
719 A6360 4.50 F&G CABLE INSTALLATION INS FN IN LM 36.3 0 22‐Jan‐19 30‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
719 A6370 4.50 F&G SUPPORT INSTALLATION INS FN IN LM 36.3 0 27‐Jan‐19 30‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
720 A6380 4.50 F&G DEVICES INSTALLATION INS FN IN 0 29‐Jan‐19 02‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
720 A6390 4.50 F&G JB SUPPORT INSTALLATION INS FN IN 0 30‐Jan‐19 31‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
721 A6400 4.50 F&G JB INSTALLATION INS FN IN LM 1441 0 02‐Feb‐19 04‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

722 A6410 4.50 F&G CABLE GLANDINGND TERMINATION INS FN IN SET 317.9 0 18‐Feb‐19 23‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

721 A6420 4.50 F&G LOOP PREPARATION INS FN IN LM 1441 0 23‐Feb‐19 24‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
722 A6430 4.50 F&G LOOP TESTING INS FN IN SET 317.9 0 24‐Feb‐19 27‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting & Fireproofing
730 A4460 4.10 PIPING PAINTINGND TOUCH‐UP INS FN FP SQM 256 0 04‐Feb‐19 18‐Feb‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

731 A4450 4.40 STRUCTURAL STEEL PAINTINGND TOUCH‐UP INS FN FP SQM 247 0 04‐Feb‐19 18‐Feb‐19 0.04% 0.18% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

732 A4470 4.50 FIREPROOFING FOR STRUCTURAL STEEL INS FN FP SQM 1256.2 0 10‐Feb‐19 04‐Mar‐19 0.19% 0.92% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Demolition Works
734 DM1280 4.60 WORK PERMITPPROVED FOR DEMOLITION INS FN DEM PCS 8.8 0 07‐May‐19 09‐May‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

DEPRESSURIZATION / ISOLATION (PIPING & 
735 DM1290 4.60 INS FN DEM PCS 54.56 0 11‐May‐19 12‐May‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTATION)
736 DM1310 4.60 APPLYNTI RUST TO FOUNDATION BOTLS INS FN DEM PCS 27.28 0 12‐May‐19 13‐May‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

737 DM1300 4.60 COLD CUTTING INLETND OUTLET PIPING INS FN DEM PCS 54.56 0 13‐May‐19 05‐Jun‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

738 DM1320 4.60 UNBOLD & REMOVE EXISTING SEPARATOR INS FN DEM PCS 190.96 0 05‐Jun‐19 06‐Jun‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

REMOVE CONCRETE FOUNDATION / GRADE 
739 DM1330 4.60 INS FN DEM PCS 227 0 08‐Jun‐19 25‐Jun‐19 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
THEREA
FAHM
DEMOLITION WORKS
METHOD STATEMENT RE SUBMISSION  
742 FM‐DEM‐1010 5.60 INS FM DEM 0 24‐Jun‐18 19‐Sep‐18 24‐Jun‐18 19‐Sep‐18 0.00% 0.00% 100.000% 100.00% 0.00% 100.00% 100.00% 100.00% 0.00%
&PPROVED BY QP
OPERATION CLEARANCE & VESSEL 
DEPRESSURIZATION BY QP OPERATION 
743 FM‐DEM‐1020 5.60 INS FM DEM 0 01‐Nov‐18 06‐Nov‐18 01‐Nov‐18 0.000% 0.00% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
TEAM & HANDOVER TO CPECCTO START 
ISOLATION & DEMOLITION
PURGING  / SYSTEM ISOLATE  SEPERATOR 
744 FM‐DEM‐1030 5.60 INS FM DEM 0 07‐Nov‐18 14‐Nov‐18 01‐Nov‐18 0.00% 0.00% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
FROM EXISTING  SYSTEM
COMPLETE  DEMO WORK  OF SEPARATOR & 
745 FM‐DEM‐1040 5.60 METERING SKID FOUNDATION (CIVIL,PIPING,  INS FM DEM 0 15‐Nov‐18 19‐Dec‐18 0.00% 0.00% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
ELEC. & INSTR.)
ISOLATION WORKS
PIPING ISOLATION
749 A5630 5.60 ISOLATION OF EXISTING VALVES INS FM DEM 0 07‐Nov‐18 12‐Nov‐18 0.01% 0.05% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT ISOLATION
749 A5640 5.60 ISOLATION OFSSOCIATED INTRUMENTS INS FM DEM 0 11‐Nov‐18 12‐Nov‐18 0.01% 0.05% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

ELECTRICAL ISOLATION
749 A5650 5.60 ISOLATION OFSSOCIATED ELECTRICAL ITEMS INS FM DEM 0 13‐Nov‐18 14‐Nov‐18 0.01% 0.05% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

DEMOLITION WORKS
DEMOLITION OF EXISTING PIPING
REMOVAL OF EXISITNG PIPING WITH 
749 A5660 5.60 INS FM DEM 0 14‐Nov‐18 21‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
SEPARATOR
DEMOLITION OF EXISTING INSTRUMENTATION
REMOVAL OF EXISITNG INTRUMENTSND 
749 A5670 5.60 INS FM DEM 0 19‐Nov‐18 21‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
CABLES WITH SEPARATOR
REMOVAL OF SEPARTOR FROM EXISTING 
749 A5680 5.60 INS FM DEM 0 20‐Nov‐18 25‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
LOGIC
DISMANTLING OF EXISTING SEPARATOR
REMOVAL OF EXISITNG INTRUMENTSND 
749 A5690 5.60 INS FM DEM 0 25‐Nov‐18 26‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
CABLES WITH SEPARATOR
REMOVAL OF SEPARTOR FROM EXISTING 
749 A5700 5.60 INS FM DEM 0 25‐Nov‐18 26‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
LOGIC
REMOVAL OF SEPARTOR FROM EXISTING 
749 A5710 5.60 INS FM DEM 0 27‐Nov‐18 28‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
LOGIC
DISMANTLING OF EXISTING SEPARATOR PLATFORM
749 A5750 5.60 APPLICATION OFNTI‐RUST PAINT/COATING INS FM DEM 0 26‐Nov‐18 26‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

UNBOLTING OF SEPARATOR FROM 
749 A5760 5.60 INS FM DEM 0 26‐Nov‐18 27‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
FOUNDATION
749 A5770 5.60 LIFITNGND REMOVAL FROM FOUNDATION INS FM DEM 0 27‐Nov‐18 01‐Dec‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

DISMANTLING OF EXISTING METERING SKID
Page 102 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)

749 A5720 5.60 APPLICATION OFNTI‐RUST PAINT/COATING INS FM DEM 0 27‐Nov‐18 27‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

UNBOLTING OF PLATFORM FROM 
749 A5730 5.60 INS FM DEM 0 27‐Nov‐18 28‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
FOUNDATION
749 A5740 5.60 LIFTINGND REMOVAL FROM FOUNDATION INS FM DEM 0 01‐Dec‐18 02‐Dec‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

DISMANTLING OF EXISTING METERING SKID PLATFORM
749 A5780 5.60 APPLICATION OFNTI‐RUST PAINT/COATING INS FM DEM 0 27‐Nov‐18 28‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

749 A5790 5.60 UNBOLTING FROM FOUNDATION INS FM DEM 0 27‐Nov‐18 29‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

749 A5800 5.60 LIFTINGND REMOVAL FROM FOUNDATION INS FM DEM 0 02‐Dec‐18 05‐Dec‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

DISMANTLING OF EXISTING PSV PLATFORM
749 A5810 5.60 APPLICATION OFNTI‐RUST PAINT/COATING INS FM DEM 0 27‐Nov‐18 28‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

UNBOLTING OF PLATFORM FROM 
749 A5820 5.60 INS FM DEM 0 27‐Nov‐18 29‐Nov‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
FOUNDATION
749 A5830 5.60 LIFTINGND REMOVAL FROM FOUNDATION INS FM DEM 0 04‐Dec‐18 05‐Dec‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

DEMOLITION OF EXISITNG SEPARATOR FOUNDATION
EXISTING SEPARATOR FOUNDATION 
749 A5840 5.60 INS FM DEM 0 02‐Dec‐18 20‐Dec‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
DEMOLITION
DEMOLITION OF EXISTING METERING SKID FOUNDATION
749 A5850 5.60 EXISTING FOUNDATION DEMOLITION INS FM DEM 0 06‐Dec‐18 15‐Dec‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
DEMOLITION OF EXISTING PSV FOUNDATION
749 A5860 5.60 EXISTING FOUNDATION DEMOLITION INS FM DEM 0 06‐Dec‐18 13‐Dec‐18 0.00% 0.01% 100.000% 65.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
INSTALLATION
Civil Works
COMMOMN
749 A2230 5.40 GRADING INS FM CV SQM 363 272.25 14‐Sep‐18 15‐Nov‐18 14‐Sep‐18 0.06% 0.27% 100.000% 65.00% ‐33.33% 75.00% 66.67% 75.00% 8.33%
CABLE TRENCHESND UTILITY ROAD 
750 A2300 5.40 INS FM CV PCS 827.2 0 04‐Dec‐18 01‐Jan‐19 0.03% 0.15% 75.862% 0.00% ‐75.86% 0.00% 0.00% 0.00% 0.00%
CROSSINGS
SOAKWAY PIT EXCAVATION & INSTALLATION 
751 A2280‐3 5.40 INS FM CV 0 25‐Nov‐18 18‐Dec‐18 0.03% 0.15% 91.667% 0.00% ‐91.67% 0.00% 0.00% 0.00% 0.00%
INCL. DEMOLITION ‐  IFPPLICABLE

752 A2230‐1 5.40 PROTECTION OF UNDERGROUND CABLES INS FM CV 0 26‐Dec‐18 10‐Jan‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

ROADSND PAVING(INCLUDING 
753 A2290 5.40 INS FM CV SQM 0 0 18‐Apr‐19 07‐May‐19 0.03% 0.15% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MODIFICATIONS)
754 A2310 5.40 DRAINAGE PIPE CULVERTS INS FM CV LM 3.3 0 22‐Jan‐19 19‐Feb‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

755 A2320 5.40 ROAD SAFETY CRASH BARRIERSND BOLLARD INS FM CV PCS 66 0 07‐May‐19 26‐May‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

RE‐INSTATEMENT OF EXISTING PAVEMENT 
756 A2350 5.40 INS FM CV SQM 171.6 0 07‐May‐19 26‐May‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(INTERLOCK PAVING)
TEST SEPERATOR
758 A2240 5.40 EXCAVATION INS FM CV CUM 0 20‐Dec‐18 06‐Jan‐19 0.03% 0.14% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
759 A2250 5.40 BLINDING INS FM CV CUM 0 02‐Jan‐19 08‐Jan‐19 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
760 A2240‐1 5.40 FOUNDATION (STEEL FIXING) INS FM CV CUM 0 06‐Jan‐19 22‐Jan‐19 0.02% 0.08% 12.500% 0.00% ‐12.50% 0.00% 0.00% 0.00% 0.00%
761 A2270 5.40 FORMWORK FOR FOUNDATION INS FM CV CUM 0 14‐Jan‐19 22‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
758 A2240‐11 5.40 FOUNDATION (CONCRETE) INS FM CV CUM 0 19‐Jan‐19 30‐Jan‐19 0.02% 0.11% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
759 A2240‐2 5.40 CURING INS FM CV CUM 0 26‐Jan‐19 03‐Feb‐19 0.01% 0.04% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

760 A2240‐22 5.40 WATER PROOFING (BITUMEN COATING) INS FM CV CUM 0 29‐Jan‐19 07‐Feb‐19 0.01% 0.04% 12.500% 0.00% ‐12.50% 0.00% 0.00% 0.00% 0.00%

761 A2240‐32 5.40 BACKFILL INS FM CV CUM 0 03‐Feb‐19 12‐Feb‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TEST SEPERATOR PLATFORM
758 A5900 5.40 EXCAVATION INS FM CV CUM 0 01‐Jan‐19 26‐Jan‐19 0.00% 0.00% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
759 A2240‐62 5.40 BLINDING INS FM CV CUM 0 22‐Jan‐19 07‐Feb‐19 0.00% 0.00% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
760 A5880 5.40 FOUNDATION (STEEL FIXING) INS FM CV CUM 0 22‐Jan‐19 31‐Jan‐19 0.00% 0.00% 12.500% 0.00% ‐12.50% 0.00% 0.00% 0.00% 0.00%
761 A5890 5.40 FORMWORK FOR FOUNDATION INS FM CV CUM 0 31‐Jan‐19 07‐Feb‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
758 A2240‐72 5.40 FOUNDATION (CONCRETE) INS FM CV CUM 0 06‐Feb‐19 16‐Feb‐19 0.00% 0.00% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
759 A2240‐82 5.40 CURING INS FM CV CUM 0 11‐Feb‐19 18‐Feb‐19 0.00% 0.00% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

760 A2240‐42 5.40 WATER PROOFING (BITUMEN COATING) INS FM CV CUM 0 16‐Feb‐19 23‐Feb‐19 0.00% 0.00% 12.500% 0.00% ‐12.50% 0.00% 0.00% 0.00% 0.00%

761 A2240‐52 5.40 BACKFILL INS FM CV CUM 0 18‐Feb‐19 25‐Feb‐19 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
763 A2240‐12 5.40 EXCAVATION INS FM CV CUM 60 0 30‐Dec‐18 12‐Jan‐19 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
759 A2240‐92 5.40 BLINDING INS FM CV CUM 0 01‐Jan‐19 08‐Jan‐19 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
760 A2240‐102 5.40 FOUNDATION (STEEL FIXING) INS FM CV CUM 0 05‐Jan‐19 14‐Jan‐19 0.01% 0.06% 12.500% 0.00% ‐12.50% 0.00% 0.00% 0.00% 0.00%
761 A2240‐122 5.40 FORMWORK FOR FOUNDATION INS FM CV CUM 0 09‐Jan‐19 14‐Jan‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
758 A2240‐112 5.40 FOUNDATION (CONCRETE) INS FM CV CUM 0 12‐Jan‐19 21‐Jan‐19 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
759 A2240‐132 5.40 CURING INS FM CV CUM 0 21‐Jan‐19 28‐Jan‐19 0.01% 0.06% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

760 A2240‐142 5.40 WATER PROOFING (BITUMEN COATING) INS FM CV CUM 0 28‐Jan‐19 30‐Jan‐19 0.01% 0.06% 12.500% 0.00% ‐12.50% 0.00% 0.00% 0.00% 0.00%

761 A2240‐152 5.40 BACKFILL INS FM CV CUM 0 30‐Jan‐19 06‐Feb‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PIPE SUPPORT
EXCAVATION FOR STRUCTURAL STEEL PIPE 
765 A2235‐4 5.40 INS FM CV CUM 0 04‐Aug‐18 24‐Nov‐18 0.03% 0.14% 100.000% 63.00% ‐26.55% 63.00% 73.45% 63.00% ‐10.45%
SUPPORTS
Page 103 of 170
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)

766 A2260‐3 5.40 BLINDING CONCRETE FOR PS FOUNDATIONS INS FM CV CUM 0 07‐Nov‐18 05‐Dec‐18 01‐Nov‐18 0.00% 0.02% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

767 A2260 5.40 FOUNDATION WORK  (STEEL FIXING) INS FM CV CUM 0 13‐Nov‐18 12‐Dec‐18 0.02% 0.10% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
768 A2260‐4 5.40 FORMWORK FOR FOR PS FOUNDAITON INS FM CV CUM 0 20‐Nov‐18 12‐Dec‐18 0.01% 0.04% 68.966% 0.00% ‐68.97% 0.00% 0.00% 0.00% 0.00%
765 A2260‐1 5.40 FOUNDATION WORK  (CONCRETE) INS FM CV CUM 0 21‐Nov‐18 20‐Dec‐18 0.03% 0.15% 100.000% 63.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
766 A2260‐2 5.40 CURING INS FM CV CUM 0 24‐Nov‐18 23‐Dec‐18 0.01% 0.05% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

767 A2260‐5 5.40 WATER PROOFING (BITUMENT COATING) INS FM CV CUM 0 09‐Dec‐18 31‐Dec‐18 0.01% 0.05% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%

768 A2260‐6 5.40 BACKFILLING INS FM CV CUM 0 16‐Dec‐18 07‐Jan‐19 0.01% 0.05% 68.966% 0.00% ‐68.97% 0.00% 0.00% 0.00% 0.00%
PSV
EXCAVATION (INCLUDINGREA LIGHTING 
770 A2235‐5 5.40 INS FM CV CUM 100 0 20‐Dec‐18 06‐Jan‐19 0.03% 0.15% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
POLES)
771 A2280 5.40 FOUNDATION WORK  (STEEL FIXING) INS FM CV CUM 3647 0 06‐Jan‐19 22‐Jan‐19 0.01% 0.03% 100.000% 0.00% ‐100.00% 0.00% 0.00% 0.00% 0.00%
772 A2280‐1 5.40 FOUNDATION WORK  (CONCRETE) INS FM CV CUM 26 0 22‐Jan‐19 07‐Feb‐19 0.01% 0.03% 18.750% 0.00% ‐18.75% 0.00% 0.00% 0.00% 0.00%

773 A2280‐2 5.40 CURING / WATERPROOFING / BACK FILLING INS FM CV CUM 206 0 07‐Feb‐19 21‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Structural Steel
TEST SEPERATOR
INSTALLATION OF LADDERS, STAIRS, 
776 A2730‐1 5.40 INS FM STIN 0 26‐Feb‐19 21‐Mar‐19 0.05% 0.23% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HANDRAILS
INSTALLATION OF STRUCTURAL STEELWORK 
777 A2730 5.40 OPERATINGNDCCESS PLATFORMS (TEST  INS FM STIN Kg 9298 0 26‐Feb‐19 21‐Mar‐19 0.05% 0.23% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SEPERATOR & PLATFORM)
METERING SKID
INSTALLATION OF STRUCTURAL STEEL OF 
779 A2740 5.40 METERING SKID INCL. WALK WAY OR CROSS  INS FM STIN Kg 2470 0 04‐Feb‐19 17‐Feb‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
OVER
PSV
INSTALLATION OF PSV VALVESCCESS 
781 A2750 5.40 INS FM STIN Kg 1705 0 25‐Feb‐19 09‐Mar‐19 0.01% 0.06% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PLATFORMS
PIPE SUPPORT
INSTALLATION OF STRUCTURAL STEEL PIPE 
783 A2760 5.40 SUPPORTS & MODIFICATIONS OF  INS FM STIN Kg 4078 0 24‐Dec‐18 24‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
EXISTINGCCESS PLATFORMS (IFPPLICABLE)
MODIFICATIONS OF EXISTING PIPE SUPORT 
784 A2760‐1 5.40 INS FM STIN 0 24‐Dec‐18 09‐Jan‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
/CCESS PLATFORMS
FIELD INSTRUMENT
786 A2770 5.40 INSTALLATION OF INSTRUMENT STANCHION INS FM STIN PCS 151 0 26‐Jan‐19 30‐Jan‐19 0.01% 0.04% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Mechanical
788 A2900 5.10 INSTALLATION OF NEW TEST SEPARATOR INS FM ME SET 137.5 0 07‐Feb‐19 11‐Feb‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Piping
HOT TAPPING
MOBILIZATION OF HOT TAPPING SUB 
791 HT1160 5.10 INS FM HTAP 0 11‐Mar‐19 13‐Mar‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
CONTRACTOR
SCAFFOLDING / PLATE FORM / WORK 
792 HT1170 5.10 INS FM HTAP 0 14‐Mar‐19 23‐Mar‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERMIT ISSUE
793 HT1180 5.10 HOT TAPPING / NDT INS FM HTAP 0 24‐Mar‐19 30‐Mar‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
HOT TAPPING COMPLETE / REMOVE 
794 HT1190 5.10 INS FM HTAP 0 03‐Apr‐19 06‐Apr‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SCAFFOLD
PIPE INSTALATION & Pre Shutdown WORKS
796 A3260‐a 5.10 MOBILIZATION OF OF TEAMPPLY PTW INS FM PPIN 0 06‐Apr‐19 06‐Apr‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SCAFFOLDING / PLATE FORM / WORK 
797 A3260‐b 5.10 INS FM PPIN 0 06‐Apr‐19 13‐Apr‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PERMIT ISSUE
PIPING INSTALLATION ON PIPE 
798 A3230 5.10 INS FM PPIN DIN 347 0 02‐Feb‐19 24‐Feb‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SUPPORT,PIERACK &ROUND EQUIPMENT

799 A3230‐1 5.10 INSTALLATION OF BALL VALVE & GGC VALVE INS FM PPIN 0 07‐Feb‐19 17‐Feb‐19 0.03% 0.13% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

HYDRO‐TESTING, FLUSHING, DRAININGND 
800 A3250 5.10 INS FM PPIN SET 440 0 25‐Mar‐19 06‐Apr‐19 0.03% 0.16% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PURGING
INLET PIPING  TIE‐IN TO SEPARATOR 
801 A3240 5.10 INS FM PPIN DIN 347 0 06‐Apr‐19 11‐Apr‐19 0.05% 0.26% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(PARTIAL SHUTDOWN TIE‐IN)
802 A3260 5.10 PIPING TIE‐IN / NDT PRE SHUT DOWN INS FM PPIN PCS 1412.4 0 08‐Apr‐19 14‐Apr‐19 0.05% 0.26% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Plant Shutdown Tie‐in
804 A3260‐1 5.10 PIPING TIE‐IN / NDT SHUT DOWN INS FM PPIN 0 15‐Apr‐19 22‐Apr‐19 0.03% 0.16% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
REPLACE THE SHUTVALVET POINT OF OIL‐IN 
805 A3261 5.10 INS FM PPIN PCS 66 0 21‐Apr‐19 22‐Apr‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TIE‐IN / INSTALL SDV
Electrical
807 A6530 5.40 CABLE TRENCH INS FM EL LM 500 0 03‐Dec‐18 26‐Dec‐18 0.00% 0.00% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
808 A3940 5.30 EARTH PIT DRILLING INS FM EL NO 3 0 19‐Jan‐19 23‐Jan‐19 0.00% 0.02% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
807 A3840 5.30 CABLE TRAY INSTALLATION INS FM EL LM 292.6 0 17‐Feb‐19 03‐Mar‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
808 A3830 5.30 U/G CABLE LAYING INS FM EL LM 253 0 13‐Feb‐19 21‐Feb‐19 0.04% 0.19% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
809 A3860 5.30 CABLE LAYING INS FM EL LM 184.8 0 20‐Feb‐19 03‐Mar‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
810 A3820 5.30 CABLE GLANDND TERMINATION INS FM EL LM 116.6 0 21‐Feb‐19 03‐Mar‐19 0.02% 0.09% 0.000% 0.00% 0.00% Page 104 of 170
0.00% 0.00% 0.00% 0.00%
Inv  3963‐ 3963‐ 3963‐ Actual phy  Forecast Start Forecast Finish Actual  Overall  Const. Ind.  Last Week  Last Weekct  Current  Current  Plan %
Sr.no. Activity ID XX Activity Name U.M. Qty Actual Start Actual % Variance
Code PHASE AREA DISC progress (Rev : 04) (Rev : 04) Finish Project Wtg. Wtg. Plan (Cum) (Cum) Week Plan Weekctual (Rev : 04)

811 A3850 5.30 ELECTRICAL EQUIPMENTS INSTALLATION INS FM EL PCS 92.4 0 21‐Feb‐19 12‐Mar‐19 0.01% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

812 A3830‐1 5.30 BACK FILLING OF CABLE TRENCH INS FM EL 0 23‐Feb‐19 03‐Mar‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

813 A3870 5.30 LIGHTING FIXTUREND DB INSTALLATION INS FM EL PCS 231 0 05‐Mar‐19 12‐Mar‐19 0.04% 0.17% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

814 A3890‐1 5.30 HOOK UP INS FM EL 0 12‐Mar‐19 14‐Mar‐19 0.02% 0.07% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
815 A3880 5.30 ELECTRICAL TIE‐INS INS FM EL SET 44 0 14‐Mar‐19 17‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
816 A3890 5.30 ENERGIZATION INS FM EL SET 44 0 17‐Mar‐19 20‐Mar‐19 0.01% 0.03% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Instrument & Control
818 A4260 5.20 CABLE TRAYND SUPPORT INSTALLATION INS FM IN LM 36.3 0 16‐Feb‐19 05‐Mar‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

818 A5000 5.20 JB SUPPORT INSTALLATION INS FM IN LM 36.3 0 03‐Mar‐19 05‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
819 A5040 5.20 JB INSTALLATION INS FM IN LM 1563.1 0 06‐Mar‐19 09‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
819 A4290 5.20 INSTRUMENT CABLE LAYING INS FM IN LM 1563.1 0 28‐Feb‐19 19‐Mar‐19 0.02% 0.08% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

820 A5050 5.20 CABLE GLANDND TERMINATION (ALONG JB) INS FM IN SET 317.9 0 09‐Mar‐19 19‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

820 A4280 5.20 INSTRUMENT EQUIPEMNT INSTALLATION INS FM IN SET 317.9 0 11‐Mar‐19 20‐Mar‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

FIELD INSTRUMENT INSTALLATION 
821 A4280‐2 5.20 INS FM IN 0 11‐Mar‐19 18‐Mar‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(GAUGESND TRANSMITTER)
822 A5340 5.50 INSTALLATION OF  DELUGE INS FM IN SET 671 0 11‐Mar‐19 20‐Mar‐19 0.01% 0.05% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
CABLE GLANDND TERMINATION (ALONG 
821 A5060 5.20 INS FM IN 0 18‐Mar‐19 24‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENTS)
DCS MODIFICATION IN CONTROL ROOM BY 
823 A4920 5.20 INS FM IN 0 19‐Mar‐19 30‐Mar‐19 0.02% 0.10% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
VENDOR
INSTALLATION OF BS & WNALYZERS ON 
824 A4280‐3 5.20 INS FM IN 0 16‐Mar‐19 18‐Mar‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
METERING SKID
825 A4280‐1 5.20 INSTALLATION OF INSTRUMENT VALVE INS FM IN 0 16‐Mar‐19 18‐Mar‐19 0.06% 0.30% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
INSTRUMENT EQUIPMENT CALIBRATION / 
826 A4270 5.20 INS FM IN SET 154 0 30‐Mar‐19 02‐Apr‐19 0.06% 0.30% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
LOOP TEST
827 A4290‐1 5.20 SS TUBEND LEAK TEST INS FM IN 0 19‐Mar‐19 21‐Mar‐19 0.08% 0.40% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
F&G System
818 A6440 5.50 F&G CABLE INSTALLATION INS FM IN LM 36.3 0 28‐Feb‐19 10‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
818 A6450 5.50 F&G SUPPORT INSTALLATION INS FM IN LM 36.3 0 02‐Mar‐19 05‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
819 A6460 5.50 F&G DEVICES INSTALLATION INS FM IN LM 1563.1 0 05‐Mar‐19 09‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
819 A6470 5.50 F&G JB SUPPORT INSTALLATION INS FM IN LM 1563.1 0 06‐Mar‐19 07‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
820 A6480 5.50 F&G JB INSTALLATION INS FM IN SET 317.9 0 09‐Mar‐19 10‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

820 A6490 5.50 F&G CABLE GLANDINGND TERMINATION INS FM IN SET 317.9 0 19‐Mar‐19 24‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

821 A6500 5.50 F&G LOOP PREPARATION INS FM IN 0 24‐Mar‐19 25‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
822 A6510 5.50 F&G LOOP TESTING INS FM IN SET 671 0 25‐Mar‐19 28‐Mar‐19 0.00% 0.01% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Painting & Fireproofing
829 A4480 5.40 STRUCTURAL STEEL PAINTINGND TOUCH‐UP INS FM FP SQM 196 0 19‐Mar‐19 30‐Mar‐19 0.03% 0.14% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

830 A4500 5.50 FIREPROOFING FOR STRUCTURAL STEEL INS FM FP SQM 1002.1 0 25‐Mar‐19 08‐Apr‐19 0.15% 0.74% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

831 A4490 5.10 PIPING PAINTINGND TOUCH‐UP INS FM FP SQM 277 0 27‐Mar‐19 06‐Apr‐19 0.04% 0.20% 0.000% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Page 105 of 170


PROJECT PLANNING PACKAGE

Attachment 10

EQUIPMENT DEPLOYMENT

Page 106 of 170


PEAK M/C
Sr.No. DESCRIPTION Project Timeline (Monthwise)
QTY MONTHS

Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19
1 BOOM TRUCK 2 15 1 2 2 2 2 2 2 2
2 3-TON PICKUP 1 8 1 1 1 1 1 1 1 1
3 BOBCAT 2 12 1 2 2 2 2 1 1 1
4 DUMP TRUCK 2 12 2 2 2 2 2 2
5 WATER TANKER 3 21 2 2 2 3 3 3 3 3
6 VIBRATORS 2 9 2 2 2 1 1 1
7 VACCUM TRUCK 2 11 1 1 1 1 2 2 2 1
8 CONCRETE MIXER MACHINE 1 5 1 1 1 1 1
9 REBAR BENDING MACHINE 1 5 1 1 1 1 1
10 LOADER 1 5 1 1 1 1 1
11 HILTI MACHINE 1 8 1 1 1 1 1 1 1 1
12 JACK HAMMER 2 11 2 2 2 2 2 1
13 LEVELLING STAFF 3 17 3 3 3 2 2 2 2
14 CONCRETE CUTTING MACHINE 1 6 1 1 1 1 1 1
15 TOTAL STATION 3 18 3 3 3 2 2 2 2 1
16 PLATE COMPACTOR 1 6 1 1 1 1 1 1
17 JUMPING COMPACTOR 1 6 1 1 1 1 1 1
18 01 TON ROLLER 1 5 1 1 1 1 1
19 ASPHALT CUTTING MACHINE 1 7 1 1 1 1 1 1 1
20 BATTERY DRILL MACHINE 2 16 2 2 2 2 2 2 2 2
21 BATTERY HILTI MACHINE 2 16 2 2 2 2 2 2 2 2
22 JACK HYDRAULIC 07 TON 1 8 1 1 1 1 1 1 1 1
23 WELDING GENERATOR 10 63 7 8 10 10 10 10 6 2
24 CRANE 50T 3 11 1 1 1 1 2 3 1 1
25 CRANE 100T 2 10 2 2 1 1 1 2 1
26 TRAILER 20T 2 11 1 1 1 2 2 2 1 1
27 PWHT MACHINE 3 10 2 2 3 2 1
28 DIESEL GENERATOR 100KW 2 11 1 1 1 1 1 2 2 2
29 FORKLIFT 10T 5 13 2 2 3 3 3
30 SUV 3 27 3 3 3 3 3 3 3 3 3
31 PICK-UP 5 42 5 5 5 5 5 5 4 4 4
32 BUS 2 16 2 2 2 2 2 2 2 1 1
33 MINI BUS 3 17 2 2 2 2 2 2 2 2 1
-

TOTAL 66 458 56 59 62 63 66 64 47 32 9

REPLACEMENT THREE PHASE TEST SEPARATOR


00 ISSUED FOR APPROVAL 1-Nov-18 TAA
Rev. No. Detail Date BY

Page 107 of 170


PROJECT PLANNING PACKAGE

Attachment 11

WEEKLY REPORT FORMAT

Page 108 of 170


Contract No.: GC16101100

QP Project No.: 3963

Location Code(s): DGEN (FAHM, FAHN, FAHS, JALM, KAHM, KAHN, KAHS)

Tag Area(s):

Contractor: CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION

EPIC FOR REPLACEMENT OF OLD 3-PHASE TEST SEPARATORS AT


Contract Title:
ALL DEGASSING STATIONS, DUKHAN

Document Title:

WEEKLY PROGRESS REPORT


Cut-off Date: 08-Mar-2017

CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION

8th Mar 0 Issue for Information Li Xiuwang Zafar Wang Xilin

DATE REV. NO REASON FOR REVISION PREPARED CHECKED APPD. APPD.


QP

DOCUMENT NUMBER: 3963-WPR-0002 SHT. 001 OF 009 REV. 0

Page 109 of 170


Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

TABLE OF CONTENTS

1.0 MANAGEMENT / EXECUTIVE SUMMARY ............................................................................... 3

2.0 QUALITY AND SAFETY STATUS .............................................................................................. 3

3.0 PROGRESS STATISTICS .......................................................................................................... 5

4.0 DETAILED STATUS AND 2 WEEKS LOOK-AHEAD WITH NARRATIVES .............................. 5

5.0 AREAS OF CONCERNS ............................................................................................................ 7

6.0 SUMMARY STATUS FROM ENGINEERING AND PROCUREMENT REGISTERS ................. 8

7.0 CORRESPONDENCE LOG FOR THE WEEK ........................................................................... 8

8.0 PROGRESS S CURVES ............................................................................................................ 8

9.0 MANPOWER HISTOGRAM WITH SUMMARY TABLE.............................................................. 8

10.0 EQUIPMENT DEPLOYMENT DURING THE REPORTING PERIOD ........................................ 9

DOC. NO.: 3963-WPR-0002 REV.#0 Page 2 of 9


Page 110 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

1.0 MANAGEMENT / EXECUTIVE SUMMARY


China Petroleum Engineering & Construction Corporation (CPECC) has been
awarded contract for EPIC by Qatar Petroleum.
The project scope covers the replace the Old Three Phase Test Separators with
suitably sized New Three Phase Test Separators including the associated metering
skids at KAHN, KAHM, KAHS, FAHN, FAHM, FAHS and JALM Degassing Stations
at Dukhan Field. The existing old test separators and associated piping, structures,
utilities, instrumentation shall be demolished.
Effective date of the project is 19-Feb-2017 and completion 18-Feb-2019.
Major achievements:
 Submitted Performance Bond and Project Insurances
 CPECC, commercial registration is approved by Ministry of Commerce and
Economic and received approval message.
 CPECC proceeding for trade License requirements.
 Detailed engineering site survey is planned from 19th March.
 Shutdown activities related to engineering and procurement is consider to at
most critical for three degassing station.
 Draft Contract document is still with QP.
 RFQ for the camp with AMWAJ Company and ALAQARIA Company.
 Planning package is under preparation. Since engineering team is engaged to
developed shutdown package at early stage of project. Planning package will
be submitted on 12th March

2.0 QUALITY AND SAFETY STATUS

2.1 QA/QC

No. Documents Status Submit Day

1 Project QA/AC Plan Ongoing Plan-25-03-2017

2 Quality Records Forms Ongoing Plan-20-03-2017

CPECC Quality Management


3 Ongoing Plan-25-03-2017
Procedure

4 ITP plan Ongoing Plan-25-03-2017

 Visual Inspection: NIL


 RFI Issuance: NIL
 Vendor document reviewed: NIL
 Quality meeting: NIL

DOC. NO.: 3963-WPR-0002 REV.#0 Page 3 of 9


Page 111 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

2.2 HSE

 Status HSE deliverable status:

No. Documents Status Submission

1 Project HSE Plan Ongoing Plan - 30-03-2017

2 Emergency Response Plan Ongoing Plan - 30-03-2017

3 Road Safety Plan Ongoing Plan - 30-03-2017

4 HSE Training Plan Ongoing Plan - 30-03-2017

5 Environment Management Plan Ongoing Plan - 25-03-2017

HSE Audit and Inspection Ongoing


6 Plan - 20-03-2017
Procedure

Construction and Fabrication HSE Ongoing


7 Plan - 30-03-2017
Procedures

Incentive and Disciplinary Ongoing


8 Plan - 30-03-2017
Procedure

Incident investigation and reporting Ongoing


9 Plan - 30-03-2017
procedure

 HSE Statistics
This Year Project REMARKS
No. DESCRIPTION
Week Todate Todate (If any)

1 FATALITIES 0 0 0

2 MAN-POWER 19 36 36

3 MAN-HOURS WORKED 760 1440 1440


LOST TIME INCIDENT FREQUENCY
4 0 0 0
(LTIF)
TOTAL RECORDABLE INCIDENT RATE:
5 0 0 0
(TRIP = TRI 1,000,000/MAN-HOURS)*
6 VEHICLE ACCIDENT 0 0 0

7 FIRST-AID CASES 0 0 0
8 HAZARDS & NEAR MISSES 0 0 0
* TRI = Fatality + Restricted Workday Case (RWC) + Medical Treatment Case (MTC)

DOC. NO.: 3963-WPR-0002 REV.#0 Page 4 of 9


Page 112 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

3.0 PROGRESS STATISTICS


Progress Statistics (Planned Vs Actual progress)

Overall Project PREVIOUS WEEK CURRENT WEEK UP TO DATE

REL.
S.
DESCRIPTION WT. PLANNED ACTUAL DEV. PLANNED ACTUAL DEV. PLANNED ACTUAL DEV.
No.
%
ENGINEERING
1 PHASE
3.98% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PROCUREMENT
2 PHASE
65.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
CONSTRUCTION
3 PHASE
21.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
PRE-
4 COMMISSIONING & 8.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
COMMISSIONING
CLOSE-OUT
5 DOCUMENTS
2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Overall Project 100% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4.0 DETAILED STATUS AND 2 WEEKS LOOK-AHEAD WITH NARRATIVES

4.1 Engineering

Activities of This Week

Process

 Review of Feed Package is ongoing.


 Markup of P&IDs related to shutdown tie-in works is finalized.
 Early Tie-ins Philosophy is under preparation.
 Required input for Valves related to shutdown tie-ins is finalized.

Safety & Loss Prevention

 Review of Feed Package is ongoing.

Piping

 Review of Feed Package is ongoing.


 Markup of Specifications and PMS related to shutdown tie-ins works is in
progress.
 Preparing Datasheets for Valves.
 Preparing Need List for Site Survey is in progress.

Mechanical

 Review of Feed Package is ongoing.

DOC. NO.: 3963-WPR-0002 REV.#0 Page 5 of 9


Page 113 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

 Preparing Need List for Site Survey.

Electrical

 Review of Feed Package is ongoing.


 Preparing Need List for Site Survey.

Instrumentation

 Review of Feed Package is ongoing.


 Preparing Need List for Site Survey.

Civil & Structural

 Review of Feed Package is ongoing.


 Preparing Need List for Site Survey.
 Scope of work for U/G survey is under preparation.

Activities Look-Ahead for Next 2 Weeks

Process

 Prepare inputs for DBM.


 Finalize Early Tie-ins Philosophy.

Safety & Loss Prevention

 Prepare inputs for DBM.

Piping

 Prepare inputs for DBM.


 Marking of Specifications and PMS related to shutdown tie-ins works will be
finalized.
 Datasheets for Valves (related to shutdown tie-in works) will be finalized.
 Conducting site survey.

Mechanical

 Prepare inputs for DBM.

Electrical

 Prepare inputs for DBM.


 Conducting site survey.

Instrumentation

 Prepare inputs for DBM.


DOC. NO.: 3963-WPR-0002 REV.#0 Page 6 of 9
Page 114 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

 Conducting site survey.

Civil & Structural

 Prepare inputs for DBM.


 Finalize U/G survey scope of work.

4.2 Procurement

Activities of This Week


Nil

Activities Look-Ahead for Next 2 Weeks


 RFQ for Shutdown valves issuance.

4.3 Construction
Activities of This Week
 Prepare the planning package.
 Pre-RFQ for construction equpment.
Activities Look-Ahead for Next 2 Weeks
 Site survey is planned from 19 to 23th March.
 Renting Camps.
 Contact and pay a visit to local subcontractor.

4.4 HSE
 Preparing the HSE documents according to QP’s HSE procedures and
standards.

4.5 QA/QC
 QA/QC plan will be submitted by 25-03-2017

5.0 AREAS OF CONCERNS

5.1 General
Nil

5.2 Engineering
Early approval of deliverables based on preliminary markup (Only for early tie-ins
scope / activities).

5.3 Procurement
To approve the shutdown procurement package in 5 days.

DOC. NO.: 3963-WPR-0002 REV.#0 Page 7 of 9


Page 115 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

5.4 Construction
NIL

5.5 HSE
CPECC request for HSE standards and procedures, the list of requested HSE
documents has already been sent to QP through DCC of CPECC.
Request for the name list of QP approved third party, including training, equipment &
tools inspection, waste disposal, PPE brands, medical service, etc.

5.6 QA/QC
NIL

6.0 SUMMARY STATUS FROM ENGINEERING AND PROCUREMENT REGISTERS


Summary Status from Engineering and Procurement Registers (Planned Vs Actual in
numbers)

6.1 Engineering
EDR under preparing

6.2 Procurement
Nil

7.0 CORRESPONDENCE LOG FOR THE WEEK


See Attachment (format)
7.1 List of Overdue Documents
7.2 List of Documents Issued and Received
7.3 List of Correspondence from CPECC to QP
7.4 List of Correspondence from QP to CPECC

8.0 PROGRESS S CURVES (attachment format only)


See Attachment (format)
8.1 - (Overall S-Curve)
8.2 – Engineering
8.3– Procurement
8.4 - Construction

9.0 MANPOWER HISTOGRAM WITH SUMMARY TABLE

See Attachment
9.1-Home Office Manpower Histogram
9.2-Construction Manpower Deployment Schedule

DOC. NO.: 3963-WPR-0002 REV.#0 Page 8 of 9


Page 116 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Weekly Progress Report

10.0 EQUIPMENT DEPLOYMENT DURING THE REPORTING PERIOD


See Attachment
10.1-Construction Plant & Equipment Deployment Schedule

DOC. NO.: 3963-WPR-0002 REV.#0 Page 9 of 9


Page 117 of 170
PROJECT PLANNING PACKAGE

Attachment 12

MONTHLY REPORT FORMAT

Page 118 of 170


TABLE OF CONTENTS

1.0 MANAGEMENT / EXECUTIVE SUMMARY ............................................................................... 2

2.0 QA/QC STATUS ........................................................................................................................ 2

3.0 Safety Status .............................................................................................................................. 4

4.0 Project Control ........................................................................................................................... 4

5.0 DETAILED STATUS .................................................................................................................. 5

6.0 AREAS OF CONCERNS ............................................................................................................ 6

7.0 CORRESPONDENCE LOG FOR THE MONTH ........................................................................ 7

8.0 COST CONTROL REPORTS .................................................................................................... 7

9.0 Project Photographs ................................................................................................................... 8

Page 119 of 170


Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Monthly Progress Report

1.0 MANAGEMENT / EXECUTIVE SUMMARY


Management / Executive Summary (Project information along with major
achievements), including a brief summary of the project.
 Project information with Milestone Status

Milestone - Planned Date Actual Date Status


Description
1.
2.
3.
4.

 Overall progress statistics ( Planned Vs Actual)


Cutoff Date Overall Planned % Overall Progress % Variance %
Engineering
Procurement
Construction
Overall

 Write-up on Major achievements for each phase


Narrative
 Major Areas of concern affecting schedule completion
 Updated Level 1 Schedule ( attachment -1)
 Updated Overall Progress Curve ( attachment -2)
 Updated Overall Manpower Histogram ( attachment -3)

2.0 QA/QC STATUS


This Section shall include a comprehensive report on QA/QC aspects of the project.
Following shall be included in detail:
 QA/QC document Status

Rev. Planned
No. Documents Status
no Submission

DOC. NO.: 3963-MPR-0001 REV.#0 Page 2 of 8


Page 120 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Monthly Progress Report

 Quality Audit Schedule for each phase


S.no Department Audit Date Close Status Next
Reporting Audit
Date Planned
1
2
3

 Concession Request (CR) with Cost/Time Impact Status


S.no Content of CR Date Cause Impact Status
Requested
1
2
3

 Non Conformance Report (NCR) and Corrective Action Report (CAR) Status

No. Name of Nonconforming Time Unit Nonconforming Corrective Closing Current Remarks
nonconforming products No. causes and time status
product preventive
Actions

 Inspection and Clearance Status

REQUEST FOR INSPECTION (RFI) STATISTICS

No. INSPECTION
Total Total Total QP % % % QP
RFI Accepted Cancelled Closed Accepted Cancelled Closed
1 RC 0

STEEL
2
STRUCUTRE
0

3 PIPING 0

DOC. NO.: 3963-MPR-0001 REV.#0 Page 3 of 8


Page 121 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Monthly Progress Report

4 NDT 0

5 TEST 0

3.0 Safety Status


This Section shall include following in detail:
 Lost Time Accidents
 Incidents / Near Misses
 Safety meetings / Tool room workshops held during the month
 Safety man-hours status table as per approved QP format.

Sl. No. DESCRIPTION This Week Year To date Project To date

1 FATALITIES 0 0 0

2 MAN-POWER 17 17 17

3 MAN-HOURS WORKED 680 1360 1360

LOST TIME INCIDENT


4 0 0 0
FREQUENCY (LTIF)
TOTAL RECORDABLE INCIDENT
RATE:
5 0 0 0
(TRIP = TRI 1,000,000/MAN-
HOURS)*

6 VEHICLE ACCIDENT 0 0 0

7 FIRST-AID CASES 0 0 0

8 HAZARDS & NEAR MISSES 0 0 0

9 SAFETY MEETINGS 1 1 1

10 TOOL BOX TALKS 0 0 0

4.0 Project Control


This Section shall include following in detail:
 Updated Milestone Status with forecast completion dates ( from P6 file)
 Critical activity listing with total floats based on current update ( from P6 file)
 Mitigation plan for arresting delays, if any

DOC. NO.: 3963-MPR-0001 REV.#0 Page 4 of 8


Page 122 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Monthly Progress Report

5.0 DETAILED STATUS


This Section shall include following in detail:

5.1 Summary Status from Engineering and Procurement Registers (Planned Vs


Actual in numbers)

Engineering

Total Planned to Actual Issue Variance Planned for


Documents Issue next month to
issue

Procurement

Description Total Numbers Planned to Actual Issue Variance


Issue

RFQ

PO

Vendor Data

Material Delivery
to Site

5.2 Progress per discipline

Description Total Numbers Planned to Actual Issue Variance


Issue

Process

Instrumentation

Electrical

Civil

DOC. NO.: 3963-MPR-0001 REV.#0 Page 5 of 8


Page 123 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Monthly Progress Report

5.3 A narrative of the months events by discipline for each phase


XXXXXXX

5.4 Forecast for next reporting period


XXXXXXX

5.5 “Hold” Register

Document no Description Planned to Actual Issue Variance


Issue

1.

2.

3.

4.

5.6 Critical pending approval Status

Document no Description Planned to Actual Issue Variance


Issue

1.

2.

3.

4.

5.7 Productivity table during the reporting period


XXXXXXX

6.0 AREAS OF CONCERNS


This Section shall include following in detail:

6.1 Concern on critical activities, if any

Narrative

6.2 Late Finish Date and Anticipated Completion Date for these activities

Activity ID Description Late Finished Anticipated Remarks


Date Completion
Date

DOC. NO.: 3963-MPR-0001 REV.#0 Page 6 of 8


Page 124 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Monthly Progress Report

1.

2.

3.

4.

6.3 Impact on Schedule


Narrative support

7.0 CORRESPONDENCE LOG FOR THE MONTH


7.1 - List of Overdue Documents
7.2 - List of Documents Issued and Received
7.3 - List of Correspondence from CPECC to QP
7.4 - List of Correspondence from QP to CPECC

8.0 COST CONTROL REPORTS


This Section shall include following in detail:

8.1 Cost Report


Cost report indicating payable amount for the month and cumulative showing
breakdown as in Schedule of Price.

8.2 Invoice Register


 Invoice details
 Details of invoices submitted
 Amount of each invoice ( including reporting month)
 Details of invoices paid
 Date when payment was received
 Cumulative Payment as on date
 Details on Bank Guarantees
 Actual and Forecast Cash flow curve

8.3 Variation Register giving the following details


 Variation Order Number
 Brief Description
 Variation Amount
 Paid Amount

DOC. NO.: 3963-MPR-0001 REV.#0 Page 7 of 8


Page 125 of 170
Project No.: 3963
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST
SEPARATORS AT ALL DEGASSING STATIONS IN DHK
Monthly Progress Report

8.4 Change Register giving the following details


 Work Change Request / Claims submitted details.
 Brief Description
 Schedule and Cost Impact
 QP Response
 Work Change Request / Claim Status

9.0 Project Photographs


This Section shall include following in detail:
 Concern on critical activities, if any
 Late Finish Date and Anticipated Completion Date for these activities
 Impact on Schedule

10.0 LIST OF ATTACHMENTS


• Updated Level 1 Schedule ( attachment -1)
• Updated Overall Progress Curve ( attachment -2)
• Updated Overall Manpower Histogram ( attachment -3)
• List of Overdue Documents (attachment-4)
• List of Documents Issued and Received (attachment-5)
• List of Correspondence from CPECC to QP (attachment-6)
• List of Correspondence from QP to CPECC (attachment-7)

DOC. NO.: 3963-MPR-0001 REV.#0 Page 8 of 8


Page 126 of 170
PROJECT PLANNING PACKAGE

Attachment 13

PRODUCTIVITY CALCULATION

Page 127 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHM DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
E MACHINE HAND HOURS
MECHANICAL
1 SEPARATOR INSTALLATION EA 1 EA/H 0.01 125 125
PIPING
1 TOTAL LENGTH LM 501 LM/H 1.20 418 418
2 Nos. of WELDS EA 704
3 DIN (Fabrication) DIN 1224 DIN/H 3.00 408 408
4 DIN (Erection) DIN 1224 DIN/H 1.50 816 816
5 Nos. of RADIOGRAPHS PC 3207 FILM/H 4.00 802 802
6 TIE-INS SHUTDOWN EA 10 EA/H 0.01 1120 1120
7 TIE-INS NON SHUTDOWN EA 2 EA/H 0.01 224 224
8 PWHT EA 476 EA/H 0.67 710 710
ELECTRICAL
1 Low Voltage cable LM 1550 LM/H 6.00 258 258
2 cable gland PCS 14 PCS/H 0.50 28 28
3 earthing cable LM 130 LM/H 8.90 15 15
4 earth rod PCS 3 PCS/H 0.22 14 14
5 earth busbar PCS 5 PCS/H 0.25 20 20
6 exothermic weld (T-JOINT) and connector PCS 31 PCS/H 0.50 62 62
7 EARTH BOSS PCS 1 PCS/H 0.13 8 8
8 cable tray LM 140 LM/H 0.57 246 246
9 cable tray elbow PCS 5 PCS/H 0.25 20 20
10 cable tray tee PCS 0 PCS/H 0
11 welding socket PCS 1 PCS/H 0.13 8 8
12 lighting PCS 15 PCS/H 0.50 30 30
13 lighting circuits distribution junction boxes PCS 15 PCS/H 0.25 60 60
14 conduits,fittings,cable lugs,etc PCS 1 PCS/H 0.01 180 180
15 cable installation materials PCS 1 PCS/H 0.01 180 180
16 concrete duck bank(sulphate resistant) PCS 47 PCS/H 0.06 752 752
17 junction box for fed lighting PCS 1 PCS/H 0.13 8 8
18 junction box for fed AC UPS loads PCS 1 PCS/H 0.13 8 8
INSTRUMENTATION 0
1 pressure transmitter SET 6 SET/H 0.25 24 24
2 tempreture transmitter SET 4 SET/H 0.25 16 16
3 flow transmitter SET 3 SET/H 0.25 12 12
4 level transmitter SET 5 SET/H 0.25 20 20
5 pressure guage SET 5 SET/H 0.50 10 10
6 tempreture guage SET 2 SET/H 0.50 4 4
7 control valve SET 5 SET/H 0.13 40 40
8 cut off valve SET 1 SET/H 0.13 8 8
9 restriction orifice SET 3 SET/H 0.20 15 15
10 flammable gas detector SET 5 SET/H 0.20 25 25

Page 128 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHM DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
E MACHINE HAND HOURS
11 toxic gas detector SET 5 SET/H 0.20 25 25
12 infrared radiation flame detector SET 3 SET/H 0.20 15 15
13 manual call point SET 1 SET/H 0.13 8 8
14 sounder SET 1 SET/H 0.13 8 8
15 beacon SET 2 SET/H 0.13 16 16
16 relief valve SET 3 SET/H 0.13 24 24
17 analyzer transmitter SET 1 SET/H 0.13 8 8
18 level guage SET 2 SET/H 0.50 4 4
19 junction box PCS 12 PCS/H 0.13 96 96
20 cable LM 6368 LM/H 6.00 1061 1061
21 cable gland PCS 139 PCS/H 0.50 278 278
22 cable tray LM 19 LM/H 0.57 33 33
23 stainless tube LM 139 LM/H 1.00 139 139
24 pipe fittings PCS 92 PCS/H 1.00 92 92
25 bolts/nuts SET 216 SET/H 8.00 27 27
26 hot galvanizing angle steel LM 49 LM/H 0.30 163 163
27 hot galvanizing channel steel LM 22 LM/H 0.20 110 110
28 hot galvanizing pipe LM 47 LM/H 0.50 94 94
29 steel plate PCS 190 PCS/H 2.00 95 95
30 sunshade PCS 22 PCS/H 2.00 11 11
31 nameplate PCS 32 PCS/H 3.00 11 11
COATING & FIREPROOFING
1 STEEL STRUCTURE COATING SQM 445.4 SQM/H 0.50 891 445 445
2 PIPING EXTERNAL COATING SQM 301.809 SQM/H 0.40 755 453 302
3 PIPING INTERNAL COATING SQM 126.4081 SQM/H 0.25 506 303 202
4 FIREPROOF SQM 455.4 SQM/H 0.50 911 546 364
DEMOLISHING WORKS
1 STEEL STRUCTURE DEMOLISHING WORKS TON 12.02 Kg/H 48.00 250 125 125
2 CONCRETE DEMOLISHING WORKS CUM 29.39 CUM/H 1.00 29 29
3 SEPARATOR DEMONISHING WORK EA 1 EA/H 0.01 83 83
PRECOMMISSIONING
1 Systematic conformity checks SET 1 SET/H 0.00 400 400
2 Static, de-energized tests of specific equipment SET 1 SET/H 0.01 200 200
3 Pressure, vacuum and leak tests SET 1 SET/H 0.00 400 400
4 Clerance of the punch list SET 1 SET/H 0.00 400 400
COMMISSIONING
1 Functional Testing SET 1 SET/H 0.00 800 800
2 Performance Tests SET 1 SET/H 0.00 1440 640

Page 129 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHN DEGASSING STATION


SKILLED
ITEM TOTAL PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIMATE Y UNIT MACHIN HOURS HOURS
HAND HOURS
E
CIVIL WORKS
1 EXCAVATION CUM 824.27 CUM/H 120.00 0.25 171.38 171.38
2 BACKFILL CUM 721.82 CUM/H 60.00 0.12 312.19 312.19
3 STRUCTURE CONCRETE: C40 CUM 95.92 CUM/H 3.00 0.30 118.30
4 BLINDING CONCRETE CUM 15.50 CUM/H 0.30 51.68
5 CONCRETE SCREED CUM 4.82 CUM/H 0.30 16.06
6 CONCRETE PROTECTION BELOW GRADE LEVEL SQM 394.03 SQM/H 8.00 49.25
7 CONCRETE PROTECTION ABOVE GRADE LEVEL SQM 77.02 SQM/H 8.00 9.63
8 0.25mm POLYETHYLENE SHEET SQM 216.21 SQM/H 4.80 45.04
9 NON-SHRINK LEVELING GROUT CUM 0.61 CUM/H 0.26 2.34
10 REINFORCEMENT BARS TON 10.55 Kg/H 0.02 527.74
11 FORMWORKS SQM 376.29 SQM/H 0.70 537.56
12 FORMWORKS REMOVAL SQM 376.29 SQM/H 1.40 268.78
13 ANCHOR BOLTS:(GALVANISED)
14 M24 WITH 2 NUTS & PLAIN WASHERS PCS 8.00 PCS/H 3.00 2.67
15 M20 WITH 2 NUTS & PLAIN WASHERS PCS 244.00 PCS/H 3.00 81.33
16 M16 WITH 1 NUTS & PLAIN WASHERS PCS 12.00 PCS/H 3.00 4.00
17 PAVING & GRADING SQM N/A SQM/H
18 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) SQM 325.00 SQM/H 2.00 162.50
19 PVC DRAINAGE PIPE LAID UNDERGROUND, 200mm DIA LM 25.00 LM/H 6.00 4.17
STRUCTURAL STEEL WORKS
1 STRUCTURAL STEEL FABRICATION KG 22637.65 Kg/H 38 595.73
2 STRUCTURAL STEEL ERECTION KG 22637.65 Kg/H 72 314.41 125.76
3 STEELGRATING:30x5mm BEARING BAR AT 30 PITCH SQM 59.11 SQM/H 1.5 39.41
4 STEEL HANDRAIL LM 80.36 LM/H 0.8 100.45
5 STEEL CAGED LADDER(7.3M HIGH) SET 1 SET/H 0.01 108.00
6 STEEL LADDER(2.45M HIGH) SET 2 SET/H 0.01 72.00
7 STEEL LADDER(1.5M HIGH) SET 1 SET/H 0.03 36.00

Page 130 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHN DEGASSING STATION


SKILLED
ITEM TOTAL PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIMATE Y UNIT MACHIN HOURS HOURS
HAND HOURS
E
8 BOL & NUTS WITH PLAIN WASHER
9 M16 WITH 2 NUTS & PLAIN WASHERS PCS 176 PCS/H 8.00 22.00 22.00
10 M20WITH 2 NUTS & PLAIN WASHERS PCS 150 PCS/H 8.00 18.75 18.75
MECHANICAL
1 SEPARATOR INSTALLATION EA 1 EA/H 0.01 125.00
PIPING
1 TOTAL LENGTH LM 565 LM/H 1.20 470.83
2 Nos. of WELDS EA 500
3 DIN (Fabrication) DIN 1096.5 DIN/H 3.00 365.50
4 DIN (Erection) DIN 1096.5 DIN/H 1.50 731.00
5 Nos. of RADIOGRAPHS PC 2780 FILM/H 4.00 695.00
6 TIE-INS SHUTDOWN EA 11 EA/H 0.01 1,232.00
7 TIE-INS NON SHUTDOWN EA 4 EA/H 0.01 448.00
8 PWHT EA 404 EA/H 0.67 602.99
ELECTRICAL
1 Low Voltage cable LM 390 LM/H 6.00 65.00 65.00
2 cable gland PCS 14 PCS/H 0.50 28.00
3 earthing cable LM 130 LM/H 8.90 14.61 14.61
4 earth rod PCS 3 PCS/H 0.22 13.50
5 earth busbar PCS 5 PCS/H 0.25 20.00
6 exothermic weld (T-JOINT) and connector PCS 27 PCS/H 0.50 54.00
7 EARTH BOSS PCS 1 PCS/H 0.13 8.00
8 cable tray LM 140 LM/H 0.57 245.61
9 cable tray elbow PCS 8 PCS/H 0.25 32.00
10 cable tray tee PCS 3 PCS/H
11 welding socket PCS 1 PCS/H 0.13 8.00
12 lighting PCS 15 PCS/H 0.50 30.00
13 lighting circuits distribution junction boxes PCS 15 PCS/H 0.25 60.00
14 conduits,fittings,cable lugs,etc PCS 1 PCS/H 0.01 180.00
15 cable installation materials PCS 1 PCS/H 0.01 180.00
16 concrete duck bank(sulphate resistant) PCS 12 PCS/H 0.06 192.00
17 junction box for fed lighting PCS 1 PCS/H 0.13 8.00
18 junction box for fed AC UPS loads PCS 1 PCS/H 0.13 8.00
INSTRUMENTATION
1 pressure transmitter SET 6 SET/H 0.25 24.00

Page 131 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHN DEGASSING STATION


SKILLED
ITEM TOTAL PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIMATE Y UNIT MACHIN HOURS HOURS
HAND HOURS
E
2 tempreture transmitter SET 4 SET/H 0.25 16.00
3 flow transmitter SET 3 SET/H 0.25 12.00
4 level transmitter SET 5 SET/H 0.25 20.00
5 pressure guage SET 5 SET/H 0.50 10.00
6 tempreture guage SET 2 SET/H 0.50 4.00
7 control valve SET 5 SET/H 0.13 40.00
8 cut off valve SET 1 SET/H 0.13 8.00
9 restriction orifice SET 3 SET/H 0.20 15.00
10 flammable gas detector SET 5 SET/H 0.20 25.00
11 toxic gas detector SET 5 SET/H 0.20 25.00
12 infrared radiation flame detector SET 3 SET/H 0.20 15.00
13 manual call point SET 1 SET/H 0.13 8.00
14 sounder SET 1 SET/H 0.13 8.00
15 beacon SET 2 SET/H 0.13 16.00
16 relief valve SET 3 SET/H 0.13 24.00
17 analyzer transmitter SET 1 SET/H 0.13 8.00
18 level guage SET 2 SET/H 0.50 4.00
19 junction box PCS 12 PCS/H 0.13 96.00
20 cable LM 4998 LM/H 6.00 833.00 833.00
21 cable gland PCS 143 PCS/H 0.50 286.00
22 cable tray LM 19 LM/H 0.57 33.33 33.33
23 stainless tube LM 139 LM/H 1.00 139.00
24 pipe fittings PCS 92 PCS/H 1.00 92.00
25 bolts/nuts SET 216 SET/H 8.00 27.00
26 hot galvanizing angle steel LM 49 LM/H 0.30 163.33
27 hot galvanizing channel steel LM 22 LM/H 0.20 110.00
28 hot galvanizing pipe LM 47 LM/H 0.50 94.00 94.00
29 steel plate PCS 190 PCS/H 2.00 95.00
30 sunshade PCS 22 PCS/H 2.00 11.00
31 nameplate PCS 32 PCS/H 3.00 10.67
COATING & FIREPROOFING
1 STEEL STRUCTURE COATING SQM 560.74 SQM/H 0.50 1,121.48 560.74
2 PIPING EXTERNAL COATING SQM 327.883384 SQM/H 0.40 819.71 327.88
3 PIPING INTERNAL COATING SQM 85.875075 SQM/H 0.25 343.50 137.40
4 FIREPROOF SQM 570.74 SQM/H 0.50 1,141.48 456.59
DEMOLISHING WORKS

Page 132 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHN DEGASSING STATION


SKILLED
ITEM TOTAL PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIMATE Y UNIT MACHIN HOURS HOURS
HAND HOURS
E
1 STEEL STRUCTURE DEMOLISHING WORKS TON 18.38 Kg/H 48.00 382.92 191.46
2 CONCRETE DEMOLISHING WORKS CUM 29.3917 CUM/H 1.00 29.39 29.39
3 SEPARATOR DEMONISHING WORK EA 1 EA/H 0.01 83.33
PRECOMMISSIONING
1 Systematic conformity checks SET 1 SET/H 0.00 400.00
2 Static, de-energized tests of specific equipment SET 1 SET/H 0.01 200.00
3 Pressure, vacuum and leak tests SET 1 SET/H 0.00 400.00
4 Clerance of the punch list SET 1 SET/H 0.00 400.00
COMMISSIONING
1 Functional Testing SET 1 SET/H 0.00 800.00
2 Performance Tests SET 1 SET/H 0.00 640.00

Page 133 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHS DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT MACHIN HOURS HOURS
E HAND HOURS
E
CIVIL WORKS
1 EXCAVATION CUM 779.46 CUM/H 120.00 0.25 162.06 162.06
2 BACKFILL CUM 686.11 CUM/H 60.00 0.12 296.74 296.74
3 STRUCTURE CONCRETE: C40 CUM 87.87 CUM/H 3.00 0.30 108.37
4 BLINDING CONCRETE CUM 14.45 CUM/H 0.30 48.18
5 CONCRETE SCREED CUM 4.29 CUM/H 0.30 14.31
6 CONCRETE PROTECTION BELOW GRADE LEVEL SQM 377.83 SQM/H 8.00 47.23
7 CONCRETE PROTECTION ABOVE GRADE LEVEL SQM 72.37 SQM/H 8.00 9.05
8 0.25mm POLYETHYLENE SHEET SQM 201.82 SQM/H 4.80 42.05
9 NON-SHRINK LEVELING GROUT CUM 0.63 CUM/H 0.26 2.43
10 REINFORCEMENT BARS TON 9.67 Kg/H 0.02 483.27
11 FORMWORKS SQM 368.75 SQM/H 0.70 526.78
12 FORMWORKS REMOVAL SQM 368.75 SQM/H 1.40 263.39
13 ANCHOR BOLTS:(GALVANISED)
14 M24 WITH 2 NUTS & PLAIN WASHERS PCS 8.00 PCS/H 3.00 2.67
15 M20 WITH 2 NUTS & PLAIN WASHERS PCS 272.00 PCS/H 3.00 90.67
16 M16 WITH 1 NUTS & PLAIN WASHERS PCS 6.00 PCS/H 3.00 2.00
17 PAVING & GRADING SQM 105.00 SQM/H
18 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) SQM 47.00 SQM/H 2.00 23.50
19 PVC DRAINAGE PIPE LAID UNDERGROUND, 200mm DIA LM 27.00 LM/H 6.00 4.50
STRUCTURAL STEEL WORKS
1 STRUCTURAL STEEL FABRICATION KG 18757.36 Kg/H 38 493.61
2 STRUCTURAL STEEL ERECTION KG 18757.36 Kg/H 72 260.52 104.21
3 STEELGRATING:30x5mm BEARING BAR AT 30 PITCH SQM 73.49 SQM/H 1.5 48.99
4 STEEL HANDRAIL LM 93.37 LM/H 0.8 116.71
5 STEEL CAGED LADDER(5.8M HIGH) SET 1 SET/H 0.01 108.00
6 STEEL LADDER(2.45M HIGH) SET 1 SET/H 0.01 72.00
7 STEEL LADDER(1.5M HIGH) SET 1 SET/H 0.03 36.00

Page 134 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHS DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT MACHIN HOURS HOURS
E HAND HOURS
E
8 BOL & NUTS WITH PLAIN WASHER
9 M16 WITH 2 NUTS & PLAIN WASHERS PCS 169 PCS/H 8.00 21.13 21.13
10 M20WITH 2 NUTS & PLAIN WASHERS PCS 150 PCS/H 8.00 18.75 18.75
MECHANICAL
1 SEPARATOR INSTALLATION EA 1 EA/H 0.01 125.00
PIPING
1 TOTAL LENGTH LM 490 LM/H 1.20 408.33
2 Nos. of WELDS EA 318
3 DIN (Fabrication) DIN 1365 DIN/H 3.00 455.00
4 DIN (Erection) DIN 1365 DIN/H 1.50 910.00
5 Nos. of RADIOGRAPHS PC 2660 FILM/H 4.00 665.00
6 TIE-INS SHUTDOWN EA 9 EA/H 0.01 1,008.00
7 TIE-INS NON SHUTDOWN EA 3 EA/H 0.01 336.00
8 PWHT EA 406 EA/H 0.67 605.97
ELECTRICAL
1 Low Voltage cable LM 470 LM/H 6.00 78.33 78.33
2 cable gland PCS 14 PCS/H 0.50 28.00
3 earthing cable LM 130 LM/H 8.90 14.61 14.61
4 earth rod PCS 3 PCS/H 0.22 13.50
5 earth busbar PCS 5 PCS/H 0.25 20.00
6 exothermic weld (T-JOINT) and connector PCS 30 PCS/H 0.50 60.00
7 EARTH BOSS PCS 1 PCS/H 0.13 8.00
8 cable tray LM 140 LM/H 0.57 245.61
9 cable tray elbow PCS 8 PCS/H 0.25 32.00
10 cable tray tee PCS 1 PCS/H
11 welding socket PCS 1 PCS/H 0.13 8.00
12 lighting PCS 17 PCS/H 0.50 34.00
13 lighting circuits distribution junction boxes PCS 17 PCS/H 0.25 68.00
14 conduits,fittings,cable lugs,etc PCS 1 PCS/H 0.01 180.00
15 cable installation materials PCS 1 PCS/H 0.01 180.00
16 concrete duck bank(sulphate resistant) PCS 21 PCS/H 0.06 336.00
17 junction box for fed lighting PCS 1 PCS/H 0.13 8.00
18 junction box for fed AC UPS loads PCS 1 PCS/H 0.13 8.00
INSTRUMENTATION
1 pressure transmitter SET 6 SET/H 0.25 24.00

Page 135 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHS DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT MACHIN HOURS HOURS
E HAND HOURS
E
2 tempreture transmitter SET 4 SET/H 0.25 16.00
3 flow transmitter SET 3 SET/H 0.25 12.00
4 level transmitter SET 5 SET/H 0.25 20.00
5 pressure guage SET 5 SET/H 0.50 10.00
6 tempreture guage SET 2 SET/H 0.50 4.00
7 control valve SET 5 SET/H 0.13 40.00
8 cut off valve SET 1 SET/H 0.13 8.00
9 restriction orifice SET 3 SET/H 0.20 15.00
10 flammable gas detector SET 4 SET/H 0.20 20.00
11 toxic gas detector SET 4 SET/H 0.20 20.00
12 infrared radiation flame detector SET 2 SET/H 0.20 10.00
13 manual call point SET 1 SET/H 0.13 8.00
14 sounder SET 1 SET/H 0.13 8.00
15 beacon SET 2 SET/H 0.13 16.00
16 relief valve SET 3 SET/H 0.13 24.00
17 analyzer transmitter SET 1 SET/H 0.13 8.00
18 level guage SET 2 SET/H 0.50 4.00
19 junction box PCS 12 PCS/H 0.13 96.00
20 cable LM 2742 LM/H 6.00 457.00 457.00
21 cable gland PCS 139 PCS/H 0.50 278.00
22 cable tray LM 19 LM/H 0.57 33.33 33.33
23 stainless tube LM 139 LM/H 1.00 139.00
24 pipe fittings PCS 92 PCS/H 1.00 92.00
25 bolts/nuts SET 216 SET/H 8.00 27.00
26 hot galvanizing angle steel LM 49 LM/H 0.30 163.33
27 hot galvanizing channel steel LM 22 LM/H 0.20 110.00
28 hot galvanizing pipe LM 46 LM/H 0.50 92.00 92.00
29 steel plate PCS 189 PCS/H 2.00 94.50
30 sunshade PCS 22 PCS/H 2.00 11.00
31 nameplate PCS 37 PCS/H 3.00 12.33
COATING & FIREPROOFING
1 STEEL STRUCTURE COATING SQM 537.6 SQM/H 0.50 1,075.20 537.60
2 PIPING EXTERNAL COATING SQM 295.794 SQM/H 0.40 739.48 295.79
3 PIPING INTERNAL COATING SQM 75.57007 SQM/H 0.25 302.28 120.91
4 FIREPROOF SQM 547.6 SQM/H 0.50 1,095.20 438.08
DEMOLISHING WORKS

Page 136 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR FAHS DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT MACHIN HOURS HOURS
E HAND HOURS
E
1 STEEL STRUCTURE DEMOLISHING WORKS TON 15.23 Kg/H 48.00 317.29 158.65
2 CONCRETE DEMOLISHING WORKS CUM 31.18001 CUM/H 1.00 31.18 31.18
3 SEPARATOR DEMONISHING WORK EA 1 EA/H 0.01 83.33
PRECOMMISSIONING
1 Systematic conformity checks SET 1 SET/H 0.00 400.00
2 Static, de-energized tests of specific equipment SET 1 SET/H 0.01 200.00
3 Pressure, vacuum and leak tests SET 1 SET/H 0.00 400.00
4 Clerance of the punch list SET 1 SET/H 0.00 400.00
COMMISSIONING
1 Functional Testing SET 1 SET/H 0.00 800.00
2 Performance Tests SET 1 SET/H 0.00 640.00

Page 137 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHM DEGASSING STATION


TOTAL PRODUCTIVITY SKILLED
ITEM PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
E MACHINE HAND HOURS

CIVIL WORKS
1 EXCAVATION CUM 803 CUM/H 120.00 0.25 167 167
2 BACKFILL CUM 699 CUM/H 60.00 0.12 302 302
3 STRUCTURE CONCRETE: C40 CUM 98 CUM/H 3.00 0.30 121 121
4 BLINDING CONCRETE CUM 17 CUM/H 0.30 58 58
5 CONCRETE SCREED CUM 4 CUM/H 0.30 15 15
6 CONCRETE PROTECTION BELOW GRADE LEVEL SQM 380 SQM/H 8.00 47 47
7 CONCRETE PROTECTION ABOVE GRADE LEVEL SQM 84 SQM/H 8.00 10 10
8 0.25mm POLYETHYLENE SHEET SQM 264 SQM/H 4.80 55 55
9 NON-SHRINK LEVELING GROUT CUM 1 CUM/H 0.26 2 2
10 REINFORCEMENT BARS TON 11 Kg/H 0.02 539 539
11 FORMWORKS SQM 377 SQM/H 0.70 538 538
12 FORMWORKS REMOVAL SQM SQM/H 1.40 0 0
13 ANCHOR BOLTS:(GALVANISED)
14 M24 WITH 2 NUTS & PLAIN WASHERS PCS 8 PCS/H 3.00 3 3
15 M20 WITH 2 NUTS & PLAIN WASHERS PCS 236 PCS/H 3.00 79 79
16 M16 WITH 1 NUTS & PLAIN WASHERS PCS 12 PCS/H 3.00 4 4
17 PAVING & GRADING SQM N/A SQM/H
18 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) SQM 210 SQM/H 2.00 105 105
19 PVC DRAINAGE PIPE LAID UNDERGROUND, 200mm DIA LM 30 LM/H 6.00 5 5
20 NEW SOAKAWAY PIT (STANDARD SIZE) SET 1 SET/H 0.00 224 224
STRUCTURAL STEEL WORKS
1 STRUCTURAL STEEL FABRICATION KG 16126.03 Kg/H 38 424 424
2 STRUCTURAL STEEL ERECTION KG 16126.03 Kg/H 72 224 134 90
3 STEELGRATING:30x5mm BEARING BAR AT 30 PITCH SQM 59.11 SQM/H 1.5 39 39
4 STEEL HANDRAIL LM 80.36 LM/H 0.8 100 100
5 STEEL CAGED LADDER(7.3M HIGH) SET 1 SET/H 0.01 108 108

Page 138 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHM DEGASSING STATION


TOTAL PRODUCTIVITY SKILLED
ITEM PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
E MACHINE HAND HOURS

6 STEEL LADDER(2.45M HIGH) SET 2 SET/H 0.01 72 72


7 STEEL LADDER(1.5M HIGH) SET 1 SET/H 0.03 36 36
8 BOLT & NUTS WITH PLAIN WASHER
9 M16 WITH 2 NUTS & PLAIN WASHERS PCS 144 PCS/H 8.00 18 18
10 M20WITH 2 NUTS & PLAIN WASHERS PCS 150 PCS/H 8.00 19 19
MECHANICAL
1 SEPARATOR INSTALLATION EA 1 EA/H 0.01 125 125
PIPING
1 TOTAL LENGTH LM 402 LM/H 1.20 335 335
2 Nos. of WELDS EA 606
3 DIN (Fabrication) DIN 1624 DIN/H 3.00 541 541
4 DIN (Erection) DIN 1624 DIN/H 1.50 1083 1083
5 Nos. of RADIOGRAPHS PC 2881 FILM/H 4.00 720 720
6 TIE-INS SHUTDOWN EA 9 EA/H 0.01 1008 1008
7 TIE-INS NON SHUTDOWN EA 9 EA/H 0.01 1008 1008
8 PWHT EA 420 EA/H 0.67 627 627
ELECTRICAL
1 Low Voltage cable LM 1060 LM/H 6.00 177 177
2 cable gland PCS 14 PCS/H 0.50 28 28
3 earthing cable LM 130 LM/H 8.90 15 15
4 earth rod PCS 3 PCS/H 0.22 14 14
5 earth busbar PCS 5 PCS/H 0.25 20 20
6 exothermic weld (T-JOINT) and connector PCS 28 PCS/H 0.50 56 56
7 EARTH BOSS PCS 1 PCS/H 0.13 8 8
8 cable tray LM 140 LM/H 0.57 246 246
9 cable tray elbow PCS 7 PCS/H 0.25 28 28
10 cable tray tee PCS 0 PCS/H 0
11 welding socket PCS 1 PCS/H 0.13 8 8

Page 139 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHM DEGASSING STATION


TOTAL PRODUCTIVITY SKILLED
ITEM PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
E MACHINE HAND HOURS

12 lighting PCS 16 PCS/H 0.50 32 32


13 lighting circuits distribution junction boxes PCS 16 PCS/H 0.25 64 64
14 conduits,fittings,cable lugs,etc PCS 1 PCS/H 0.01 180 180
15 cable installation materials PCS 1 PCS/H 0.01 180 180
16 concrete duck bank(sulphate resistant) PCS 14 PCS/H 0.06 224 224
17 junction box for fed lighting PCS 1 PCS/H 0.13 8 8
18 junction box for fed AC UPS loads PCS 1 PCS/H 0.13 8 8
INSTRUMENTATION 0
1 pressure transmitter SET 6 SET/H 0.25 24 24
2 tempreture transmitter SET 4 SET/H 0.25 16 16
3 flow transmitter SET 3 SET/H 0.25 12 12
4 level transmitter SET 5 SET/H 0.25 20 20
5 pressure guage SET 5 SET/H 0.50 10 10
6 tempreture guage SET 2 SET/H 0.50 4 4
7 control valve SET 5 SET/H 0.13 40 40
8 cut off valve SET 1 SET/H 0.13 8 8
9 restriction orifice SET 3 SET/H 0.20 15 15
10 flammable gas detector SET 5 SET/H 0.20 25 25
11 toxic gas detector SET 5 SET/H 0.20 25 25
12 infrared radiation flame detector SET 3 SET/H 0.20 15 15
13 manual call point SET 1 SET/H 0.13 8 8
14 relief valve SET 3 SET/H 0.13 24 24
15 analyzer transmitter SET 1 SET/H 0.13 8 8
16 level guage SET 2 SET/H 0.50 4 4
17 junction box PCS 12 PCS/H 0.13 96 96
18 cable LM 5016 LM/H 6.00 836 836
19 cable gland PCS 143 PCS/H 0.50 286 286
20 cable tray LM 19 LM/H 0.57 33 33
21 stainless tube LM 139 LM/H 1.00 139 139
22 pipe fittings PCS 92 PCS/H 1.00 92 92
23 bolts/nuts SET 237 SET/H 8.00 30 30
24 hot galvanizing angle steel LM 49 LM/H 0.30 163 163
25 hot galvanizing channel steel LM 22 LM/H 0.20 110 110
26 hot galvanizing pipe LM 46 LM/H 0.50 92 92
27 steel plate PCS 189 PCS/H 2.00 95 95

Page 140 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHM DEGASSING STATION


TOTAL PRODUCTIVITY SKILLED
ITEM PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
E MACHINE HAND HOURS

28 sunshade PCS 22 PCS/H 2.00 11 11


29 nameplate PCS 32 PCS/H 3.00 11 11
COATING & FIREPROOFING
1 STEEL STRUCTURE COATING SQM 467.78 SQM/H 0.50 936 468 468
2 PIPING EXTERNAL COATING SQM 259.2209 SQM/H 0.40 648 389 259
3 PIPING INTERNAL COATING SQM 39.84603 SQM/H 0.25 159 96 64
4 FIREPROOF SQM 477.78 SQM/H 0.50 956 573 382
DEMOLISHING WORKS
1 STEEL STRUCTURE DEMOLISHING WORKS TON 13.08 Kg/H 48.00 273 136 136
2 CONCRETE DEMOLISHING WORKS CUM 35.32539 CUM/H 1.00 35 35
3 SEPARATOR DEMONISHING WORK EA 1 EA/H 0.01 83 83
PRECOMMISSIONING
1 Systematic conformity checks SET 1 SET/H 0.00 400 400
2 Static, de-energized tests of specific equipment SET 1 SET/H 0.01 200 200
3 Pressure, vacuum and leak tests SET 1 SET/H 0.00 400 400
4 Clerance of the punch list SET 1 SET/H 0.00 400 400
COMMISSIONING
1 Functional Testing SET 1 SET/H 0.00 800 800
2 Performance Tests SET 1 SET/H 0.00 640 640

Page 141 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHN DEGASSING STATION


PRODUCTIVITY SKILLED
ITEM TOTAL PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIAMTED Y UNIT HOURS HOURS
MACHINE HAND HOURS
CIVIL WORKS
1 EXCAVATION CUM 835.979324 CUM/H 120.00 0.25 173.81 173.81
2 BACKFILL CUM 1180.95126 CUM/H 60.00 0.12 510.76 510.76
3 STRUCTURE CONCRETE: C40 CUM 98.263 CUM/H 3.00 0.30 121.19
4 BLINDING CONCRETE CUM 15.783 CUM/H 0.30 52.61
5 CONCRETE SCREED CUM 4.936 CUM/H 0.30 16.45
6 CONCRETE PROTECTION BELOW GRADE LEVEL SQM 396.35 SQM/H 8.00 49.54
7 CONCRETE PROTECTION ABOVE GRADE LEVEL SQM 77.033 SQM/H 8.00 9.63
8 0.25mm POLYETHYLENE SHEET SQM 218.179 SQM/H 4.80 45.45
9 NON-SHRINK LEVELING GROUT CUM 0.62025 CUM/H 0.26 2.39
10 REINFORCEMENT BARS TON 10.81 Kg/H 0.02 540.50
11 FORMWORKS SQM 376.223 SQM/H 0.70 537.46
12 FORMWORKS REMOVAL SQM 376.223 SQM/H 1.40 268.73
13 ANCHOR BOLTS:(GALVANISED)
14 M24 WITH 2 NUTS & PLAIN WASHERS PCS 8 PCS/H 3.00 2.67
15 M20 WITH 2 NUTS & PLAIN WASHERS PCS 220 PCS/H 3.00 73.33
16 M16 WITH 1 NUTS & PLAIN WASHERS PCS 12 PCS/H 3.00 4.00
17 PAVING & GRADING SQM 198 SQM/H
18 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) SQM 12 SQM/H 2.00 6.00
19 PVC DRAINAGE PIPE LAID UNDERGROUND, 200mm DIA LM 1 LM/H 6.00 0.17
STRUCTURAL STEEL WORKS
1 STRUCTURAL STEEL FABRICATION KG 20727.07 Kg/H 38 545.45
2 STRUCTURAL STEEL ERECTION KG 20727.07 Kg/H 72 287.88 115.15
3 STEELGRATING:30x5mm BEARING BAR AT 30 PITCH SQM 59.11 SQM/H 1.5 39.41
4 STEEL HANDRAIL LM 80.36 LM/H 0.8 100.45
5 STEEL CAGED LADDER(7.3M HIGH) SET 1 SET/H 0.01 108.00
6 STEEL LADDER(2.45M HIGH) SET 2 SET/H 0.01 72.00

Page 142 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHN DEGASSING STATION


PRODUCTIVITY SKILLED
ITEM TOTAL PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIAMTED Y UNIT HOURS HOURS
MACHINE HAND HOURS
7 STEEL LADDER(1.5M HIGH) SET 1 SET/H 0.03 36.00
8 BOL & NUTS WITH PLAIN WASHER
9 M16 WITH 2 NUTS & PLAIN WASHERS PCS 168 PCS/H 8.00 21.00 21.00
10 M20WITH 2 NUTS & PLAIN WASHERS PCS 150 PCS/H 8.00 18.75 18.75
MECHANICAL
1 SEPARATOR INSTALLATION EA 1 EA/H 0.01 125.00
PIPING
1 TOTAL LENGTH LM 599 LM/H 1.20 499.17
2 Nos. of WELDS EA 730
3 DIN (Fabrication) DIN 1857 DIN/H 3.00 619.00
4 DIN (Erection) DIN 1857 DIN/H 1.50 1,238.00
5 Nos. of RADIOGRAPHS PC 3254 FILM/H 4.00 813.50
6 TIE-INS SHUTDOWN EA 15 EA/H 0.01 1,680.00
7 TIE-INS NON SHUTDOWN EA 3 EA/H 0.01 336.00
8 PWHT EA 457 EA/H 0.67 682.09
ELECTRICAL
1 Low Voltage cable LM 700 LM/H 6.00 116.67 116.67
2 cable gland PCS 14 PCS/H 0.50 28.00
3 earthing cable LM 130 LM/H 8.90 14.61 14.61
4 earth rod PCS 3 PCS/H 0.22 13.50
5 earth busbar PCS 3 PCS/H 0.25 12.00
6 exothermic weld (T-JOINT) and connector PCS 29 PCS/H 0.50 58.00
7 EARTH BOSS PCS 1 PCS/H 0.13 8.00
8 cable tray LM 140 LM/H 0.57 245.61
9 cable tray elbow PCS 5 PCS/H 0.25 20.00
10 cable tray tee PCS 0 PCS/H
11 welding socket PCS 1 PCS/H 0.13 8.00
12 lighting PCS 15 PCS/H 0.50 30.00
13 lighting circuits distribution junction boxes PCS 15 PCS/H 0.25 60.00

Page 143 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHN DEGASSING STATION


PRODUCTIVITY SKILLED
ITEM TOTAL PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIAMTED Y UNIT HOURS HOURS
MACHINE HAND HOURS
14 conduits,fittings,cable lugs,etc PCS 1 PCS/H 0.01 180.00
15 cable installation materials PCS 1 PCS/H 0.01 180.00
16 concrete duck bank(sulphate resistant) PCS 10 PCS/H 0.06 160.00
17 junction box for fed lighting PCS 1 PCS/H 0.13 8.00
18 junction box for fed AC UPS loads PCS 1 PCS/H 0.13 8.00
INSTRUMENTATION
1 pressure transmitter SET 6 SET/H 0.25 24.00
2 tempreture transmitter SET 4 SET/H 0.25 16.00
3 flow transmitter SET 3 SET/H 0.25 12.00
4 level transmitter SET 5 SET/H 0.25 20.00
5 pressure guage SET 5 SET/H 0.50 10.00
6 tempreture guage SET 2 SET/H 0.50 4.00
7 control valve SET 5 SET/H 0.13 40.00
8 cut off valve SET 1 SET/H 0.13 8.00
9 restriction orifice SET 3 SET/H 0.20 15.00
10 flammable gas detector SET 5 SET/H 0.20 25.00
11 toxic gas detector SET 5 SET/H 0.20 25.00
12 infrared radiation flame detector SET 3 SET/H 0.20 15.00
13 manual call point SET 1 SET/H 0.13 8.00
14 sounder SET 1 SET/H 0.13 8.00
15 beacon SET 2 SET/H 0.13 16.00
16 relief valve SET 3 SET/H 0.13 24.00
17 analyzer transmitter SET 1 SET/H 0.13 8.00
18 level guage SET 2 SET/H 0.50 4.00
19 junction box PCS 12 PCS/H 0.13 96.00
20 cable LM 6192 LM/H 6.00 1,032.00 1,032.00
21 cable gland PCS 139 PCS/H 0.50 278.00
22 cable tray LM 19 LM/H 0.57 33.33 33.33
23 stainless tube LM 143 LM/H 1.00 143.00
24 pipe fittings PCS 92 PCS/H 1.00 92.00
25 bolts/nuts SET 237 SET/H 8.00 29.63
26 hot galvanizing angle steel LM 49 LM/H 0.30 163.33
27 hot galvanizing channel steel LM 22 LM/H 0.20 110.00
28 hot galvanizing pipe LM 14 LM/H 0.50 28.00 28.00
29 steel plate PCS 189 PCS/H 2.00 94.50

Page 144 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHN DEGASSING STATION


PRODUCTIVITY SKILLED
ITEM TOTAL PRODUCTIVIT TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT WORKER MARK
NUMBER ESTIAMTED Y UNIT HOURS HOURS
MACHINE HAND HOURS
30 sunshade PCS 22 PCS/H 2.00 11.00
31 nameplate PCS 32 PCS/H 3.00 10.67
COATING & FIREPROOFING
1 STEEL STRUCTURE COATING SQM 526.65 SQM/H 0.50 1,053.30 526.65
2 PIPING EXTERNAL COATING SQM 410.817787 SQM/H 0.40 1,027.04 410.82
3 PIPING INTERNAL COATING SQM 57.7080504 SQM/H 0.25 230.83 92.33
4 FIREPROOF SQM 536.65 SQM/H 0.50 1,073.30 429.32
DEMOLISHING WORKS
1 STEEL STRUCTURE DEMOLISHING WORKS TON 16.82 Kg/H 48.00 350.42 175.21
2 CONCRETE DEMOLISHING WORKS CUM 29.3943 CUM/H 1.00 29.39 29.39
3 SEPARATOR DEMONISHING WORK EA 1 EA/H 0.01 83.33
PRECOMMISSIONING
1 Systematic conformity checks SET 1 SET/H 0.00 400.00
2 Static, de-energized tests of specific equipment SET 1 SET/H 0.01 200.00
3 Pressure, vacuum and leak tests SET 1 SET/H 0.00 400.00
4 Clerance of the punch list SET 1 SET/H 0.00 400.00
COMMISSIONING
1 Functional Testing SET 1 SET/H 0.00 800.00
2 Performance Tests SET 1 SET/H 0.00 640.00

Page 145 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHS DEGASSING STATION


ITEM TOTAL SKILLED
PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
NUMBE ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
Y UNIT MACHINE HAND HOURS HOURS
R ED HOURS
CIVIL WORKS
1 EXCAVATION CUM 684.62 CUM/H 120.00 0.25 142 142
2 BACKFILL CUM 598.57 CUM/H 60.00 0.12 259 259
3 STRUCTURE CONCRETE: C40 CUM 82.19 CUM/H 3.00 0.30 101 101
4 BLINDING CONCRETE CUM 13.25 CUM/H 0.30 44 44
5 CONCRETE SCREED CUM 3.90 CUM/H 0.30 13 13
6 CONCRETE PROTECTION BELOW GRADE LEVEL SQM 330.90 SQM/H 8.00 41 41
7 CONCRETE PROTECTION ABOVE GRADE LEVEL SQM 72.48 SQM/H 8.00 9 9
8 0.25mm POLYETHYLENE SHEET SQM 187.87 SQM/H 4.80 39 39
9 NON-SHRINK LEVELING GROUT CUM 0.54 CUM/H 0.26 2 2
10 REINFORCEMENT BARS TON 9.04 Kg/H 0.02 452 452
11 FORMWORKS SQM 328.77 SQM/H 0.70 470 470
12 FORMWORKS REMOVAL SQM 328.77 SQM/H 1.40 235 235
13 ANCHOR BOLTS:(GALVANISED)
14 M24 WITH 2 NUTS & PLAIN WASHERS PCS 8.00 PCS/H 3.00 3 3
15 M20 WITH 2 NUTS & PLAIN WASHERS PCS 204.00 PCS/H 3.00 68 68
16 M16 WITH 1 NUTS & PLAIN WASHERS PCS 12.00 PCS/H 3.00 4 4
17 PAVING & GRADING SQM 52.00 SQM/H
18 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) SQM 12.00 SQM/H 2.00 6 6
19 PVC DRAINAGE PIPE LAID UNDERGROUND, 200mm DIA LM 1.00 LM/H 6.00 0 0
STRUCTURAL STEEL WORKS
1 STRUCTURAL STEEL FABRICATION KG 16301.85 Kg/H 38 429 429
2 STRUCTURAL STEEL ERECTION KG 16301.85 Kg/H 72 226 136 91
3 STEELGRATING:30x5mm BEARING BAR AT 30 PITCH SQM 59.11 SQM/H 1.5 39 39
4 STEEL HANDRAIL LM 80.36 LM/H 0.8 100 100
5 STEEL CAGED LADDER(7.3M HIGH) SET 1 SET/H 0.01 108 108
6 STEEL LADDER(2.45M HIGH) SET 2 SET/H 0.01 72 72
7 STEEL LADDER(1.5M HIGH) SET 1 SET/H 0.03 36 36

Page 146 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHS DEGASSING STATION


ITEM TOTAL SKILLED
PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
NUMBE ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
Y UNIT MACHINE HAND HOURS HOURS
R ED HOURS
8 BOLT & NUTS WITH PLAIN WASHER
9 M16 WITH 2 NUTS & PLAIN WASHERS PCS 168 PCS/H 8.00 21 21
10 M20WITH 2 NUTS & PLAIN WASHERS PCS 150 PCS/H 8.00 19 19
MECHANICAL
1 SEPARATOR INSTALLATION EA 1 EA/H 0.01 125 125
PIPING
1 TOTAL LENGTH LM 553 LM/H 1.20 461 461
2 Nos. of WELDS EA 815
3 DIN (Fabrication) DIN 1742 DIN/H 3.00 581 581
4 DIN (Erection) DIN 1742 DIN/H 1.50 1161 1161
5 Nos. of RADIOGRAPHS PC 3129 FILM/H 4.00 782 782
6 TIE-INS SHUTDOWN EA 12 EA/H 0.01 1344 1344
7 TIE-INS NON SHUTDOWN EA 4 EA/H 0.01 448 448
8 PWHT EA 436 EA/H 0.67 651 651
ELECTRICAL
1 Low Voltage cable LM 500 LM/H 6.00 83 83
2 cable gland PCS 14 PCS/H 0.50 28 28
3 earthing cable LM 130 LM/H 8.90 15 15
4 earth rod PCS 3 PCS/H 0.22 14 14
5 earth busbar PCS 3 PCS/H 0.25 12 12
6 exothermic weld (T-JOINT) and connector PCS 29 PCS/H 0.50 58 58
7 EARTH BOSS PCS 1 PCS/H 0.13 8 8
8 cable tray LM 140 LM/H 0.57 246 246
9 cable tray elbow PCS 9 PCS/H 0.25 36 36
10 cable tray tee PCS 3 PCS/H 0
11 welding socket PCS 1 PCS/H 0.13 8 8
12 lighting PCS 15 PCS/H 0.50 30 30
13 lighting circuits distribution junction boxes PCS 15 PCS/H 0.25 60 60
14 conduits,fittings,cable lugs,etc PCS 1 PCS/H 0.01 180 180
15 cable installation materials PCS 1 PCS/H 0.01 180 180

Page 147 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHS DEGASSING STATION


ITEM TOTAL SKILLED
PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
NUMBE ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
Y UNIT MACHINE HAND HOURS HOURS
R ED HOURS
16 concrete duck bank(sulphate resistant) PCS 8 PCS/H 0.06 128 128
17 junction box for fed lighting PCS 1 PCS/H 0.13 8 8
18 junction box for fed AC UPS loads PCS 1 PCS/H 0.13 8 8
INSTRUMENTATION 0
1 pressure transmitter SET 6 SET/H 0.25 24 24
2 tempreture transmitter SET 4 SET/H 0.25 16 16
3 flow transmitter SET 3 SET/H 0.25 12 12
4 level transmitter SET 5 SET/H 0.25 20 20
5 pressure guage SET 5 SET/H 0.50 10 10
6 tempreture guage SET 2 SET/H 0.50 4 4
7 control valve SET 5 SET/H 0.13 40 40
8 cut off valve SET 1 SET/H 0.13 8 8
9 restriction orifice SET 3 SET/H 0.20 15 15
10 flammable gas detector SET 5 SET/H 0.20 25 25
11 toxic gas detector SET 5 SET/H 0.20 25 25
12 infrared radiation flame detector SET 3 SET/H 0.20 15 15
13 manual call point SET 1 SET/H 0.13 8 8
14 sounder SET 1 SET/H 0.13 8 8
15 beacon SET 2 SET/H 0.13 16 16
16 relief valve SET 3 SET/H 0.13 24 24
17 analyzer transmitter SET 1 SET/H 0.13 8 8
18 level guage SET 2 SET/H 0.50 4 4
19 junction box PCS 12 PCS/H 0.13 96 96
20 cable LM 2790 LM/H 6.00 465 465
21 cable gland PCS 139 PCS/H 0.50 278 278
22 cable tray LM 19 LM/H 0.57 33 33
23 stainless tube LM 139 LM/H 1.00 139 139
24 pipe fittings PCS 92 PCS/H 1.00 92 92
25 bolts/nuts SET 237 SET/H 8.00 30 30
26 hot galvanizing angle steel LM 49 LM/H 0.30 163 163
27 hot galvanizing channel steel LM 22 LM/H 0.20 110 110
28 hot galvanizing pipe LM 14 LM/H 0.50 28 28
29 steel plate PCS 189 PCS/H 2.00 95 95
30 sunshade PCS 22 PCS/H 2.00 11 11
31 nameplate PCS 32 PCS/H 3.00 11 11
COATING & FIREPROOFING

Page 148 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR KAHS DEGASSING STATION


ITEM TOTAL SKILLED
PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
NUMBE ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
Y UNIT MACHINE HAND HOURS HOURS
R ED HOURS
1 STEEL STRUCTURE COATING SQM 442.5 SQM/H 0.50 885 443 443
2 PIPING EXTERNAL COATING SQM 337.0503 SQM/H 0.40 843 506 337
3 PIPING INTERNAL COATING SQM 83.81407 SQM/H 0.25 335 201 134
4 FIREPROOF SQM 452.5 SQM/H 0.50 905 543 362
DEMOLISHING WORKS
1 STEEL STRUCTURE DEMOLISHING WORKS TON 12 Kg/H 48.00 250 125 125
2 CONCRETE DEMOLISHING WORKS CUM 29.3943 CUM/H 1.00 29 29
3 SEPARATOR DEMONISHING WORK EA 1 EA/H 0.01 83 83
PRECOMMISSIONING
1 Systematic conformity checks SET 1 SET/H 0.00 400 400
2 Static, de-energized tests of specific equipment SET 1 SET/H 0.01 200 200
3 Pressure, vacuum and leak tests SET 1 SET/H 0.00 400 400
4 Clerance of the punch list SET 1 SET/H 0.00 400 400
COMMISSIONING
1 Functional Testing SET 1 SET/H 0.00 800 800
2 Performance Tests SET 1 SET/H 0.00 640 640

Page 149 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR JALM DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
ED MACHINE HAND HOURS
CIVIL WORKS
1 EXCAVATION CUM 758.57 CUM/H 120.00 0.25 158 158
2 BACKFILL CUM 662.96 CUM/H 60.00 0.12 287 287
3 STRUCTURE CONCRETE: C40 CUM 91.17 CUM/H 3.00 0.30 112 112
4 BLINDING CONCRETE CUM 14.33 CUM/H 0.30 48 48
5 CONCRETE SCREED CUM 4.36 CUM/H 0.30 15 15
6 CONCRETE PROTECTION BELOW GRADE LEVEL SQM 370.43 SQM/H 8.00 46 46
7 CONCRETE PROTECTION ABOVE GRADE LEVEL SQM 76.28 SQM/H 8.00 10 10
8 0.25mm POLYETHYLENE SHEET SQM 204.36 SQM/H 4.80 43 43
9 NON-SHRINK LEVELING GROUT CUM 0.64 CUM/H 0.26 2 2
10 REINFORCEMENT BARS TON 10.03 Kg/H 0.02 501 501
11 FORMWORKS SQM 364.75 SQM/H 0.70 521 521
12 FORMWORKS REMOVAL SQM 364.75 SQM/H 1.40 261 261
13 ANCHOR BOLTS:(GALVANISED)
14 M24 WITH 2 NUTS & PLAIN WASHERS PCS 8.00 PCS/H 3.00 3 3
15 M20 WITH 2 NUTS & PLAIN WASHERS PCS 220.00 PCS/H 3.00 73 73
16 M16 WITH 1 NUTS & PLAIN WASHERS PCS 4.00 PCS/H 3.00 1 1
17 PAVING & GRADING SQM 185.00 SQM/H
18 RE-INSTATEMENT OF EXISTING PAVEMENT (INTERLOCK PAVING) SQM 24.00 SQM/H 2.00 12 12
19 PVC DRAINAGE PIPE LAID UNDERGROUND, 200mm DIA LM 305.00 LM/H 6.00 51 51
20 CONCRETE KERB (RETAINING WALL & CULVERT) CUM 90.00 CUM/H 0.42 214 214
STRUCTURAL STEEL WORKS
1 STRUCTURAL STEEL FABRICATION KG 16529.77 Kg/H 38 435 435
2 STRUCTURAL STEEL ERECTION KG 16529.77 Kg/H 72 230 138 92
3 STEELGRATING:30x5mm BEARING BAR AT 30 PITCH SQM 64.24 SQM/H 1.5 43 43
4 STEEL HANDRAIL LM 72.84 LM/H 0.8 91 91
5 STEEL CAGED LADDER(7.3M HIGH) SET 0 SET/H 0.01 108 108

Page 150 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR JALM DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
ED MACHINE HAND HOURS
6 STEEL LADDER(2.45M HIGH) SET 0 SET/H 0.01 72 72
7 STEEL LADDER(1.5M HIGH) SET 0 SET/H 0.03 36 36
8 CRASH BARRIER LM 51.6 LM/H 0.25 206 206
9 BOLT & NUTS WITH PLAIN WASHER
10 M16 WITH 2 NUTS & PLAIN WASHERS PCS 169 PCS/H 8.00 21 21
11 M20WITH 2 NUTS & PLAIN WASHERS PCS 150 PCS/H 8.00 19 19
MECHANICAL
1 SEPARATOR INSTALLATION EA 1 EA/H 0.01 125 125
PIPING
1 TOTAL LENGTH LM 710 LM/H 1.20 592 592
2 Nos. of WELDS EA 1640
3 DIN (Fabrication) DIN 1673 DIN/H 3.00 558 558
4 DIN (Erection) DIN 1673 DIN/H 1.50 1115 1115
5 Nos. of RADIOGRAPHS PC 3772 FILM/H 4.00 943 943
6 TIE-INS SHUTDOWN EA 16 EA/H 0.01 1792 1792
7 TIE-INS NON SHUTDOWN EA 2 EA/H 0.01 224 224
8 PWHT EA 564 EA/H 0.67 842 842
ELECTRICAL
1 Low Voltage cable LM 1550 LM/H 6.00 258 258
2 cable gland PCS 14 PCS/H 0.50 28 28
3 earthing cable LM 130 LM/H 8.90 15 15
4 earth rod PCS 4 PCS/H 0.22 18 18
5 earth busbar PCS 23 PCS/H 0.25 92 92
6 exothermic weld (T-JOINT) and connector PCS 1 PCS/H 0.50 2 2
7 EARTH BOSS PCS 1 PCS/H 0.13 8 8
8 cable tray LM 140 LM/H 0.57 246 246
9 cable tray elbow PCS 6 PCS/H 0.25 24 24
10 cable tray tee PCS 1 PCS/H 0

Page 151 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR JALM DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
ED MACHINE HAND HOURS
11 welding socket PCS 1 PCS/H 0.13 8 8
12 lighting PCS 14 PCS/H 0.50 28 28
13 lighting circuits distribution junction boxes PCS 14 PCS/H 0.25 56 56
14 conduits,fittings,cable lugs,etc PCS 1 PCS/H 0.01 180 180
15 cable installation materials PCS 1 PCS/H 0.01 180 180
16 concrete duck bank(sulphate resistant) PCS 18 PCS/H 0.06 288 288
17 junction box for fed lighting PCS 1 PCS/H 0.13 8 8
18 junction box for fed AC UPS loads PCS 1 PCS/H 0.13 8 8
INSTRUMENTATION 0
1 pressure transmitter SET 6 SET/H 0.25 24 24
2 tempreture transmitter SET 4 SET/H 0.25 16 16
3 flow transmitter SET 3 SET/H 0.25 12 12
4 level transmitter SET 5 SET/H 0.25 20 20
5 pressure guage SET 5 SET/H 0.50 10 10
6 tempreture guage SET 2 SET/H 0.50 4 4
7 control valve SET 5 SET/H 0.13 40 40
8 cut off valve SET 1 SET/H 0.13 8 8
9 restriction orifice SET 3 SET/H 0.20 15 15
10 flammable gas detector SET 5 SET/H 0.20 25 25
11 toxic gas detector SET 5 SET/H 0.20 25 25
12 infrared radiation flame detector SET 3 SET/H 0.20 15 15
13 manual call point SET 1 SET/H 0.13 8 8
14 sounder SET 1 SET/H 0.13 8 8
15 beacon SET 2 SET/H 0.13 16 16
16 relief valve SET 3 SET/H 0.13 24 24
17 analyzer transmitter SET 1 SET/H 0.13 8 8
18 level guage SET 2 SET/H 0.50 4 4
19 junction box PCS 12 PCS/H 0.13 96 96
20 cable LM 6516 LM/H 6.00 1086 1086
21 cable gland PCS 143 PCS/H 0.50 286 286
22 cable tray LM 19 LM/H 0.57 33 33
23 stainless tube LM 139 LM/H 1.00 139 139
24 pipe fittings PCS 92 PCS/H 1.00 92 92
25 bolts/nuts SET 216 SET/H 8.00 27 27
26 hot galvanizing angle steel LM 49 LM/H 0.30 163 163
27 hot galvanizing channel steel LM 22 LM/H 0.20 110 110

Page 152 of 170


CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

CONSTRUCTION PRODUCTIVITY AND REQUIRED MANHOURS FOR JALM DEGASSING STATION


TOTAL SKILLED
ITEM PRODUCTIVIT PRODUCTIVITY TOTAL LABOUR
ACTIVITY DESCRIPTION UNIT ESTIMAT WORKER MARK
NUMBER Y UNIT HOURS HOURS
ED MACHINE HAND HOURS
28 hot galvanizing pipe LM 46 LM/H 0.50 92 92
29 steel plate PCS 208 PCS/H 2.00 104 104
30 sunshade PCS 22 PCS/H 2.00 11 11
31 nameplate PCS 32 PCS/H 3.00 11 11
COATING & FIREPROOFING
1 STEEL STRUCTURE COATING SQM 461.37 SQM/H 0.50 923 461 461
2 PIPING EXTERNAL COATING SQM 441.4491 SQM/H 0.40 1104 662 441
3 PIPING INTERNAL COATING SQM 67.68895 SQM/H 0.25 271 162 108
4 FIREPROOF SQM 471.37 SQM/H 0.50 943 566 377
DEMOLISHING WORKS
1 STEEL STRUCTURE DEMOLISHING WORKS TON 13.42 Kg/H 48.00 280 140 140
2 CONCRETE DEMOLISHING WORKS CUM 28.46599 CUM/H 1.00 28 28
3 EXCAVATION FOR CONCRETE KERB (RETAINING WALL & CULVERT) CUM 345 CUM/H 1.00 345 345
4 SEPARATOR DEMONISHING WORK EA 1 EA/H 0.01 83 83
PRECOMMISSIONING
1 Systematic conformity checks SET 1 SET/H 0.00 400 400
2 Static, de-energized tests of specific equipment SET 1 SET/H 0.01 200 200
3 Pressure, vacuum and leak tests SET 1 SET/H 0.00 400 400
4 Clerance of the punch list SET 1 SET/H 0.00 400 400
COMMISSIONING
1 Functional Testing SET 1 SET/H 0.00 800 800
2 Performance Tests SET 1 SET/H 0.00 640 640

Page 153 of 170


PROJECT PLANNING PACKAGE

Attachment 14

INVOICE FORMAT

Page 154 of 170


EPIC FOR  REPLACEMENT OF OLD 3‐PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DUKHAN
 (PROJECT NO. 3963)

INVOICE

Part 1
1.1 Invoice No. XXXXX 1.2  Date 29‐Jun‐17
1.3 Vendor Number XXXXX
1.4 Period of work done/ invoiced : From :  1‐May‐17 End : 28‐Jun‐17
1.5 Contract No. GC16101100 01

1.6 Contract Title EPIC FOR REPLACING OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DUKHAN

1.7 Release Order No XXXXX

1.8 Service Entry Sheet No:  XXXXX

Part 2

2.1 Original Contract Value                                                                                                  43,453,804.00 QR

2.2 Variations if Any (+/‐)                                                                                                                   ‐ QR

2.3 Current Contract Value                                                                                                  43,453,804.00 QR

Part 3
3.1 Total Advance Paid:                                                                                                                   ‐ QR
3.2 Advance recovered till last Invoice                                                                                                                   ‐ QR
3.3 Balance advance to be recovered as of date                                                                                                                   ‐ QR

Part 4
4.1 Cummulative Value of work done/ Invoiced as of date                                                                                                                   ‐ QR
4.2 Less : Value of work done upto last invoice                                                                                                                   ‐ QR
4.3 Gross value of work done as per this invoice                                                                                                                   ‐ QR

Part 5
5.1 Gross Value of work done as per this invoice                                                                                                                   ‐ QR
5.2 Less : Advance                                                                                                                   ‐ QR
5.3 Less : Retention as per this Invoice                                                                                                                   ‐ QR
5.4 Less : Liquidated Damages as per this Invoice                                                                                                                   ‐ QR
5.5 Net amount claimed as per this Invoice                                                                                                                   ‐ QR
5.6 Amount in Words :
QATAR RIYALS FOUR HUNDRED TWO THOUSAND THREE HUNDRED SIXTY EIGHT AND TWENTY TWO DHIRAMS ONLY

Part 6
6.1 Authorized Signature
6.2 Name of Authorized Signatory
6.3 Designation

Company seal

Page 155 of 170


GC16101100
EPIC FOR REPLACING OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DUKHAN

SUMMARY
Date:
METHODOLOGY OF PAYMENT  Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM
Item ITEM DESCRIPTION FOR THE LUMP SUM AMOUNT 
 AMOUNT (QAR) % progress Amount QR. % progress Amount QR. % progress Amount QR.
(QAR)
2.2.1.1 App B Part 1 clause 2.2.1.1  Ninety five percent 95% of the LUMP PRICE portion is based on physical progress for the month
1 Preliminaries & General Matters         6,039,699.00                                5,737,714.05
2 Detailed Engineering         1,602,400.00                                1,522,280.00
3 Procurement       26,216,175.00                              20,972,940.00
4 Construction         8,446,830.00                                8,024,488.50
5  Pre‐Commissioning, Commissioning & Operational Testing         1,148,700.00                                1,091,265.00
2.2.1.4.2.d Full value of Procurement
Full value of Procurement
Completion of the commissioning and
6                                5,243,235.00
testing for the WORK excluding project
dossier and As‐built drawings
2.2.2 Completion of following activities / deliverables:
 Completion of SPIR, SAP,CMMS and Handing over of Spare parts,
 As‐Built drawings,
7                                    861,881.45
 Project Dossiers,
 Close out report, Asset Capitalization Schedule
TOTAL (DETAILED ENGINEERING DESIGN)       43,453,804.00                              43,453,804.00 0.00%                           ‐ 0.00%                           ‐ 0.00%                           ‐

2 of 16
Page 156 of 170
CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING
(PROJECT NO. 3963)
OVERALL Cost (QR) Cummulative till last Invoice This Invoice Cummulative upto this invoice
Level‐2 Level‐3 % progress Amount QR. % progress Amount QR. % progress Amount QR.
Preliminaries            457,603.00
Article 11.7 : Performance Bond           157,248.00
Appendix ‐ C : Insurance Specific to the Contract           300,355.00
GENERAL MATTERS         5,582,096.00
Mobilisation of all supervision, labour, plant, 
materials and equipment necessary for the proper            391,323.00
execution of the WORK.
De‐mobilisation of all supervision, labour, plant, 
materials and equipment necessary for the proper            201,013.00
execution of the WORK.
WORKSITE Facilities and Utilities
Provision, maintenance and subsequently removal 
of all temporary office, site facilities and utilities at 
WORKSITE for CONTRACTOR and SUBCONTRACTOR        1,958,130.00
personnel as required for the COMPLETION of the 
WORK.
Provision of project planning/management, QA/QC 
activities, proprietary design softwares, liasion and 
      1,870,087.00
all office overhead necessary for the proper 
execution of the WORK.
Provision of all temporary works as required for the 
          651,626.00
COMPLETION of the WORK.
Provision of compliance with CONTRACT terms and 
conditions regarding obtaining QP permit to WORK,            286,317.00
entry permit, ID cards, Inductions, Safetywear etc.

Provision of progress and safety meeting with QP.             44,790.00
Provision of Asset Capitalization Schedule             30,457.00
Compilation and entry of required data for all 
supplied items in QP's computerised Maintenance              64,641.00
Management System (CMMS)
Provision for Digital Data for GIS as described in the 
            20,069.00
CONTRACT. 
Provision of Project Dossiers includung As‐Built 
Drawings, Construction Data Books,  and start ‐up,  
            63,643.00
Operation and Maintenance Manuals as described 
in the CONTRACT. 
Total         6,039,699.00
Progress Percentage Calculation for
Progress as on
Preliminaries and General Matters as per Schedule Price
date
Appendix B Clause 2.0
DESIGN & DETAILED ENGINEERING         1,602,400.00                         ‐ Refer to App B Part I, 2.2.1.2
PROCUREMENT       26,216,175.00                         ‐ Refer to App B Part I, 2.2.1.2
CONSTRUCTION         8,446,830.00                         ‐ Refer to App B Part I, 2.2.1.2
PRE-COMMISSIONING & COMMISSIONING         1,148,700.00                         ‐ Refer to App B Part I, 2.2.1.2
Total       37,414,105.00                         ‐
% Progress of Preliminaries 0.00% Refer to App B Part I, 2.2.1.2

1 of 14 
Page 157 of 170
CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION
EPIC FOR REPLACEMENT OF OLD 3 PHASE TEST SEPARATORS AT ALL DEGASSING STATIONS IN DHK
(PROJECT NO. 3963)

Detailed Engineering
Date:
ITEM DESCRIPTION Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM 95%
 AMOUNT (QAR) OF LUMP SUM 
AMOUNT (QAR) % progress Amount QR. % progress Amount QR. % progress Amount QR.
2.2.1.1 App B Part 1 clause 2.2.1.1  Ninety five percent 95% of the LUMP PRICE portion is based on physical progress for the month

Schedule 02: Detailed Engineering

A Site Survey and Document Retrieval, as required in Scope of


Work Clause 4.2, Appendix A and reference drawings. 56,530.00 53,703.50

B Prepare and submit for QP review and approval the Design


Basis Memorandum including relevant detail design drawings 123,061.00 116,907.95
as required in Scope of Work Clause 4.3, Appendix A.
C Prepare and submit Process engineering deliverables as
required in Scope of Work Clause 4.4.2, Appendix A and 189,591.00 180,111.45
reference drawings.
D Prepare and submit Mechanical/Piping engineering
deliverables as required in Scope of Work Clause 4.4.3, 246,121.00 233,814.95
Appendix A and reference drawings.
E Prepare and submit Instrumentation and Control System
engineering deliverables as required in Scope of Work Clause 246,121.00 233,814.95
4.4.5, Appendix A and reference drawings.
F Prepare and submit Electrical engineering deliverables as
required in Scope of Work Clause 4.4.6, Appendix A and 133,061.00 126,407.95
reference drawings.
G Prepare and submit Civil/Structural engineering deliverables
as required in Scope of Work Clause 4.4.7, Appendix A and 133,061.00 126,407.95
reference drawings.
H Prepare and submit Loss Prevention engineering deliverables
as required in Scope of Work Clause 4.4.9 Appendix A and
reference drawings. 169,591.00 161,111.45

I Prepare and submit Environmental engineering deliverables


as required in Scope of Work Clause 4.4.10, Appendix A and 113,061.00 107,407.95
reference drawings.
J Prepare and submit Demolition engineering deliverables as
required in Scope of Work Clause 4.4.14, Appendix A and 56,530.00 53,703.50
reference drawings.
K Prepare and submit Tie-in Engineering Package & Tie-in
Schedule as required in Scope of Work Clause 4.4.15, 67,836.00 64,444.20
Appendix A and reference drawings.
L Carry out and implement HAZID and HAZOP Studies as
required in Scope of Work Clause 4.4.9, Appendix A and 56,530.00 53,703.50
reference drawings.
M Prepare and submit list for Spare Parts requirements for
Second and Third Year of Operation, all as required in Scope 11,306.00 10,740.70
of Work Clause 4.5.6, Appendix A.

Total Detailed Engineering 1,602,400.00 1,522,280.00

Page 158 of 170


1 of 14
CONTRACT NO: GC16110300
EPIC FOR EXTENSION OF MANIFOLDS TO CREATE ADDITIONAL SLOTS AT KN AND KS IN DUKHAN 

Procurement

Item DESCRIPTION Cummulative till last Invoice This Invoice Cummulative upto this invoice


 LUMP SUM 80%
 AMOUNT (QAR)   OF LUMP SUM 
AMOUNT  % progress Amount QR. % progress Amount QR. % progress Amount QR.
(QAR) 

Schedule 03: Procurement -

1 KHATIYAH NORTH    
1.1 Mechanical and Piping (10)
1.1.1 Three Phase Test Separator                       438,760.00                 351,008.00 
1.1.2 BS&W Meter                       118,181.00                    94,544.80 
1.1.3 Sand Jetting                          50,530.00                    40,424.00 
1.1.4 Pipes                          79,981.00                    63,984.80 
1.1.5 Flanges                          23,283.00                    18,626.40 
1.1.6 Gasket                            2,959.00                      2,367.20 
1.1.7 Valves                       255,715.00                 204,572.00 
1.1.8 Fittings                          19,691.00                    15,752.80 
1.1.9 Stud Bolt & Nuts                          13,224.00                    10,579.20 
1.1.10 Any Other Item/Material                          22,407.00                    17,925.60 
1.2 Instrumentation & Control (6)                                 ‐   
1.2.1 All Instrument Equipment, Field Instruments and accessories                       367,549.00                 294,039.20 
1.2.2 All Control System Equipment and accessories                       429,319.00                 343,455.20 
1.2.3 Softwares for I & C Integration with existing systems                        276,926.00                 221,540.80 
1.2.4 Cables, cable trays and accessories                       145,930.00                 116,744.00 
1.2.5 Hardwares (Input cards, termination units, terminals, additional wiring 
                      415,389.00                 332,311.20 
etc.)
1.2.6 Any Other Item/Material                                        ‐                                    ‐   
1.3 Electrical   (8)                                 ‐   
1.3.1 Cables                          22,475.00                    17,980.00 
1.3.2 Cable Glands                            1,684.00                      1,347.20 
1.3.3 Earthing System                            8,056.00                      6,444.80 
1.3.4 Cable Tray                            6,162.00                      4,929.60 
1.3.5 Welding Sockets                                        ‐                                    ‐   
1.3.6 UPS Power Systems                                        ‐                                    ‐   
1.3.7 Lighting Fixtures and Socket Outlets                          15,631.00                    12,504.80 
1.3.8 Any Other Item/Material                                        ‐                                    ‐   
1.4 Loss Prevention  (3)                                 ‐   
1.4.1 Fire & Gas Detection Systems                       111,245.00                    88,996.00 
1.4.2 Fire Extinguishers                       417,462.00                 333,969.60 
1.4.3 Any Other Item/Material                                        ‐                                    ‐   
1.5 Civil/Structural  (1)                                 ‐   
1.5.1 Materials for Civil/Structural Scope of Work                       250,769.00                 200,615.20 
1.6 Other                                 ‐   
1.6.1 Any other Mmaterials and consumables  (1)                                        ‐                                    ‐   
2 KHATIYAH MAIN                                    ‐   
2.1 Mechanical and Piping                                  ‐   
2.1.1 Three Phase Test Separator                       430,705.00                 344,564.00 
2.1.2 BS&W Meter                       118,181.00                    94,544.80 
2.1.3 Sand Jetting                          50,530.00                    40,424.00 
2.1.4 Pipes                          86,355.00                    69,084.00 
2.1.5 Flanges                          19,334.00                    15,467.20 
2.1.6 Gasket                            2,223.00                      1,778.40 
2.1.7 Valves                       280,423.00                 224,338.40 
2.1.8 Fittings                          20,474.00                    16,379.20 
2.1.9 Stud Bolt & Nuts                          10,981.00                      8,784.80 
2.1.10 Any Other Item/Material                          11,851.00                      9,480.80  Page 159 of 170
2.2 Instrumentation & Control                                 ‐   
2.2.1 All Instrument Equipment, Field Instruments and accessories                       367,549.00                 294,039.20 
14 of 14
Item DESCRIPTION Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM 80%
2.2.2 All Control System Equipment and accessories                       350,797.00                 280,637.60 
2.2.3 Softwares for I & C Integration with existing systems                        276,926.00                 221,540.80 
2.2.4 Cables, cable trays and accessories                       145,930.00                 116,744.00 
2.2.5 Hardwares (Input cards, termination units, terminals, additional wiring 
                      415,389.00                 332,311.20 
etc.)
2.2.6 Any Other Item/Material                                        ‐                                    ‐   
2.3 Electrical                                  ‐   
2.3.1 Cables                          22,475.00                    17,980.00 
2.3.2 Cable Glands                            1,684.00                      1,347.20 
2.3.3 Earthing System                            8,056.00                      6,444.80 
2.3.4 Cable Tray                            6,162.00                      4,929.60 
2.3.5 Welding Sockets                                        ‐                                    ‐   
2.3.6 UPS Power Systems                                        ‐                                    ‐   
2.3.7 Lighting Fixtures and Socket Outlets                          15,631.00                    12,504.80 
2.3.8 Any Other Item/Material                                        ‐                                    ‐   
2.4 Loss Prevention                                  ‐   
2.4.1 Fire & Gas Detection Systems                       111,245.00                    88,996.00 
2.4.2 Fire Extinguishers                       417,462.00                 333,969.60 
2.4.3 Any Other Item/Material                                        ‐                                    ‐   
2.5 Civil/Structural                                 ‐   
2.5.1 Materials for Civil/Structural Scope of Work                       291,169.00                 232,935.20 
2.6 Other                                 ‐   
2.6.1 Any other Mmaterials and consumables                                        ‐                                    ‐   
3 KHATIYAH SOUTH                                    ‐   
3.1 Mechanical and Piping                                  ‐   
3.1.1 Three Phase Test Separator                       430,705.00                 344,564.00 
3.1.2 BS&W Meter                       118,181.00                    94,544.80 
3.1.3 Sand Jetting                          50,530.00                    40,424.00 
3.1.4 Pipes                          80,053.00                    64,042.40 
3.1.5 Flanges                         15,971.00                   12,776.80 
3.1.6 Gasket                           1,938.00                     1,550.40 
3.1.7 Valves                       273,887.00                219,109.60 
3.1.8 Fittings                         19,358.00                   15,486.40 
3.1.9 Stud Bolt & Nuts                           9,071.00                     7,256.80 
3.1.10 Any Other Item/Material                         11,851.00                     9,480.80 
3.2 Instrumentation & Control                                 ‐   
3.2.1 All Instrument Equipment, Field Instruments and accessories                       367,549.00                294,039.20 
3.2.2 All Control System Equipment and accessories                       350,797.00                280,637.60 
3.2.3 Softwares for I & C Integration with existing systems                        276,926.00                221,540.80 
3.2.4 Cables, cable trays and accessories                       145,930.00                116,744.00 
3.2.5 Hardwares (Input cards, termination units, terminals, additional wiring 
                      415,389.00                332,311.20 
etc.)
3.2.6 Any Other Item/Material                                     ‐                                 ‐   
3.3 Electrical                                  ‐   
3.3.1 Cables                         22,475.00                   17,980.00 
3.3.2 Cable Glands                           1,684.00                     1,347.20 
3.3.3 Earthing System                           8,056.00                     6,444.80 
3.3.4 Cable Tray                           6,162.00                     4,929.60 
3.3.5 Welding Sockets                                     ‐                                 ‐   
3.3.6 UPS Power Systems                                     ‐                                 ‐   
3.3.7 Lighting Fixtures and Socket Outlets                         15,631.00                   12,504.80 
3.3.8 Any Other Item/Material                                     ‐                                 ‐   
3.4 Loss Prevention                                  ‐   
3.4.1 Fire & Gas Detection Systems                       111,245.00                   88,996.00 
3.4.2 Fire Extinguishers                       417,462.00                333,969.60 
3.4.3 Any Other Item/Material                                     ‐                                 ‐   
3.5 Civil/Structural                                 ‐   
3.5.1 Materials for Civil/Structural Scope of Work                       279,357.00                223,485.60 
3.6 Other                                 ‐   
3.6.1 Any other Mmaterials and consumables                                     ‐                                 ‐   
4 FAHAHIL NORTH                                    ‐   
4.1 Mechanical and Piping                                  ‐   
4.1.1 Three Phase Test Separator                       430,705.00                344,564.00 
4.1.2 BS&W Meter                       118,181.00                   94,544.80 
4.1.3 Sand Jetting                         50,530.00                   40,424.00  Page 160 of 170
4.1.4 Pipes                       130,535.00                104,428.00 
4.1.5 Flanges                         27,875.00                   22,300.00  14 of 14
Item DESCRIPTION Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM 80%
4.1.6 Gasket                           3,824.00                     3,059.20 
4.1.7 Valves                       272,482.00                217,985.60 
4.1.8 Fittings                         29,956.00                   23,964.80 
4.1.9 Stud Bolt & Nuts                         15,831.00                   12,664.80 
4.1.10 Any Other Item/Material                         11,851.00                     9,480.80 
4.2 Instrumentation & Control                                 ‐   
4.2.1 All Instrument Equipment, Field Instruments and accessories                       367,549.00                 294,039.20 
4.2.2 All Control System Equipment and accessories                       350,797.00                 280,637.60 
4.2.3 Softwares for I & C Integration with existing systems                        276,926.00                 221,540.80 
4.2.4 Cables, cable trays and accessories                       145,930.00                 116,744.00 
4.2.5 Hardwares (Input cards, termination units, terminals, additional wiring 
                      415,389.00                 332,311.20 
etc.)
4.2.6 Any Other Item/Material                                        ‐                                    ‐   
4.3 Electrical                                  ‐   
4.3.1 Cables                          22,475.00                    17,980.00 
4.3.2 Cable Glands                            1,684.00                      1,347.20 
4.3.3 Earthing System                            8,056.00                      6,444.80 
4.3.4 Cable Tray                            6,162.00                      4,929.60 
4.3.5 Welding Sockets                                        ‐                                    ‐   
4.3.6 UPS Power Systems                                        ‐                                    ‐   
4.3.7 Lighting Fixtures and Socket Outlets                          15,631.00                    12,504.80 
4.3.8 Any Other Item/Material                                        ‐                                    ‐   
4.4 Loss Prevention                                  ‐   
4.4.1 Fire & Gas Detection Systems                       111,245.00                    88,996.00 
4.4.2 Fire Extinguishers                       417,462.00                 333,969.60 
4.4.3 Any Other Item/Material                                        ‐                                    ‐   
4.5 Civil/Structural                                 ‐   
4.5.1 Materials for Civil/Structural Scope of Work                       400,929.00                 320,743.20 
4.6 Other                                 ‐   
4.6.1 Any other Mmaterials and consumables                                        ‐                                    ‐   
5 FAHAHIL MAIN                                    ‐   
5.1 Mechanical and Piping                                  ‐   
5.1.1 Three Phase Test Separator                       430,705.00                 344,564.00 
5.1.2 BS&W Meter                       118,181.00                    94,544.80 
5.1.3 Sand Jetting                          50,530.00                    40,424.00 
5.1.4 Pipes                          73,841.00                    59,072.80 
5.1.5 Flanges                          16,321.00                    13,056.80 
5.1.6 Gasket                            2,588.00                      2,070.40 
5.1.7 Valves                       223,361.00                 178,688.80 
5.1.8 Fittings                          24,227.00                    19,381.60 
5.1.9 Stud Bolt & Nuts                            9,270.00                      7,416.00 
5.1.10 Any Other Item/Material                          17,776.00                    14,220.80 
5.2 Instrumentation & Control                                 ‐   
5.2.1 All Instrument Equipment, Field Instruments and accessories                       367,549.00                 294,039.20 
5.2.2 All Control System Equipment and accessories                       350,797.00                 280,637.60 
5.2.3 Softwares for I & C Integration with existing systems                        276,926.00                 221,540.80 
5.2.4 Cables, cable trays and accessories                       145,930.00                 116,744.00 
5.2.5 Hardwares (Input cards, termination units, terminals, additional wiring 
                      415,389.00                 332,311.20 
etc.)
5.2.6 Any Other Item/Material                                        ‐                                    ‐   
5.3 Electrical                                  ‐   
5.3.1 Cables                          22,475.00                    17,980.00 
5.3.2 Cable Glands                            1,684.00                      1,347.20 
5.3.3 Earthing System                            8,056.00                      6,444.80 
5.3.4 Cable Tray                            6,162.00                      4,929.60 
5.3.5 Welding Sockets                                        ‐                                    ‐   
5.3.6 UPS Power Systems                                        ‐                                    ‐   
5.3.7 Lighting Fixtures and Socket Outlets                          15,631.00                    12,504.80 
5.3.8 Any Other Item/Material                                        ‐                                    ‐   
5.4 Loss Prevention                                  ‐   
5.4.1 Fire & Gas Detection Systems                       111,245.00                    88,996.00 
5.4.2 Fire Extinguishers                       417,462.00                 333,969.60 
5.4.3 Any Other Item/Material                                        ‐                                    ‐   
5.5 Civil/Structural                                 ‐   
5.5.1 Materials for Civil/Structural Scope of Work                       286,776.00                 229,420.80  Page 161 of 170
5.6 Other                                 ‐   
5.6.1 Any other Mmaterials and consumables                                        ‐                                    ‐    14 of 14
Item DESCRIPTION Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM 80%
6 FAHAHIL SOUTH                                 ‐   
6.1 Mechanical and Piping                                  ‐   
6.1.1 Three Phase Test Separator                       439,982.00                 351,985.60 
6.1.2 BS&W Meter                       147,727.00                 118,181.60 
6.1.3 Sand Jetting                          63,162.00                    50,529.60 
6.1.4 Pipes                       146,232.00                 116,985.60 
6.1.5 Flanges                          22,548.00                    18,038.40 
6.1.6 Gasket                            3,051.00                      2,440.80 
6.1.7 Valves                       355,151.00                 284,120.80 
6.1.8 Fittings                          32,831.00                    26,264.80 
6.1.9 Stud Bolt & Nuts                          12,806.00                    10,244.80 
6.1.10 Any Other Item/Material                          14,813.00                    11,850.40 
6.2 Instrumentation & Control                                 ‐   
6.2.1 All Instrument Equipment, Field Instruments and accessories                       459,436.00                 367,548.80 
6.2.2 All Control System Equipment and accessories                       438,496.00                 350,796.80 
6.2.3 Softwares for I & C Integration with existing systems                        346,157.00                 276,925.60 
6.2.4 Cables, cable trays and accessories                       182,412.00                 145,929.60 
6.2.5 Hardwares (Input cards, termination units, terminals, additional wiring 
                      519,236.00                 415,388.80 
etc.)
6.2.6 Any Other Item/Material                                        ‐                                    ‐   
6.3 Electrical                                  ‐   
6.3.1 Cables                          28,094.00                    22,475.20 
6.3.2 Cable Glands                            2,105.00                      1,684.00 
6.3.3 Earthing System                          10,070.00                      8,056.00 
6.3.4 Cable Tray                            7,702.00                      6,161.60 
6.3.5 Welding Sockets                                        ‐                                    ‐   
6.3.6 UPS Power Systems                                        ‐                                    ‐   
6.3.7 Lighting Fixtures and Socket Outlets                          19,539.00                    15,631.20 
6.3.8 Any Other Item/Material                                        ‐                                    ‐   
6.4 Loss Prevention                                  ‐   
6.4.1 Fire & Gas Detection Systems                       139,056.00                 111,244.80 
6.4.2 Fire Extinguishers                       521,827.00                 417,461.60 
6.4.3 Any Other Item/Material                                        ‐                                    ‐   
6.5 Civil/Structural                                 ‐   
6.5.1 Materials for Civil/Structural Scope of Work                       415,228.00                 332,182.40 
6.6 Other                                 ‐   
6.6.1 Any other Mmaterials and consumables                                        ‐                                    ‐   
7 JALEHA                                     ‐   
7.1 Mechanical and Piping                                  ‐   
7.1.1 Three Phase Test Separator                       538,382.00                 430,705.60 
7.1.2 BS&W Meter                       147,727.00                 118,181.60 
7.1.3 Sand Jetting                          63,162.00                    50,529.60 
7.1.4 Pipes                       123,869.00                    99,095.20 
7.1.5 Flanges                          25,494.00                    20,395.20 
7.1.6 Gasket                            3,337.00                      2,669.60 
7.1.7 Valves                       286,808.00                 229,446.40 
7.1.8 Fittings                          34,974.00                    27,979.20 
7.1.9 Stud Bolt & Nuts                          14,479.00                    11,583.20 
7.1.10 Any Other Item/Material                          14,813.00                    11,850.40 
7.2 Instrumentation & Control                                 ‐   
7.2.1 All Instrument Equipment, Field Instruments and accessories                       459,436.00                 367,548.80 
7.2.2 All Control System Equipment and accessories                       438,496.00                 350,796.80 
7.2.3 Softwares for I & C Integration with existing systems                        346,157.00                 276,925.60 
7.2.4 Cables, cable trays and accessories                       182,412.00                 145,929.60 
7.2.5 Hardwares (Input cards, termination units, terminals, additional wiring 
                      519,236.00                 415,388.80 
etc.)
7.2.6 Any Other Item/Material                                        ‐                                    ‐   
7.3 Electrical                                   ‐   
7.3.1 Cables                          28,094.00                    22,475.20 
7.3.2 Cable Glands                            2,105.00                      1,684.00 
7.3.3 Earthing System                          10,070.00                      8,056.00 
7.3.4 Cable Tray                            7,702.00                      6,161.60 
7.3.5 Welding Sockets                                        ‐                                    ‐   
7.3.6 UPS Power Systems                                        ‐                                    ‐   
7.3.7 Lighting Fixtures and Socket Outlets                          19,539.00                    15,631.20  Page 162 of 170
7.3.8 Any Other Item/Material                                        ‐                                    ‐   
7.4 Loss Prevention                                  ‐    14 of 14
Item DESCRIPTION Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM 80%
7.4.1 Fire & Gas Detection Systems                       139,056.00                 111,244.80 
7.4.2 Fire Extinguishers                       521,827.00                 417,461.60 
7.4.3 Any Other Item/Material                                        ‐                                    ‐   
7.5 Civil/Structural                                 ‐   
7.5.1 Materials for Civil/Structural Scope of Work                       325,999.00                 260,799.20 
7.6 Other                                 ‐   
7.6.1 Any other Mmaterials and consumables                                        ‐                                    ‐   
8 SPARES                                 ‐   
8.1 Spares for Commissioning and start‐up, as required in Scope of Work
                      127,690.00                 102,152.00 
Clause 4.5.6,  Appendix A. 
8.2 Spares for Guarantee Period, as required in Scope of Work Clause 4.5.6,
                         97,695.00                    78,156.00 
Appendix A. 

Total Procurement                  26,216,175.00            20,972,940.00  0.00%                                       ‐

CONTRACTOR to split the aboave table into Bulk & Long lead items in terms of value for payment purposes.

Page 163 of 170

14 of 14
Equipment - Procurement Control Register for Invoice
Project No. - 3963
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS"
As Of : 06-Jul-17
QP inspected Successful
Issue
SL. Plan/ Actual Inspection and cleared commissioning
Description Purchase % Weight % Progress
No. Date cleared & FAT material at and handover
Order
site of spares
Progress Scale 10% 55% 80% 100% WTGE % Phy. Comp.
0.15%
1.0 LONG LEAD ITEMS 75.80%
0.15%
1 Equipment
Plan Date 19-Jul-17 4-Jul-18 27-Jul-18 27-Jul-18 0.00%
1.1 Test Separator 12.16%
Actual Date 0.00%
Plan Date 9-Aug-17 12-Feb-18 6-Apr-18 6-Apr-18 0.00%
1.2 BS&W Meter 3.42%
Actual Date 0.00%
Plan Date 19-Jul-17 4-Jul-18 27-Jul-18 27-Jul-18 0.00%
1.3 Sand Jetting 1.47%
Actual Date 0.00%
2 Piping
Plan Date 8-May-17 15-Aug-17 4-Oct-17 4-Oct-17 10.00%
2.1 Early Tie-in Valves 1.51%
Actual Date 11-May-17 10.00%
3 Instrumentation
Plan Date 19-Oct-17 2-Feb-18 12-Mar-18 12-Mar-18 0.00%
3.1 Field Instrumentation 10.63%
Actual Date 0.00%
Control Valve / SD & BD Valve / PRV/ Orifice / Plan Date 23-Aug-17 24-Feb-18 18-Apr-18 18-Apr-18 0.00%
3.2 10.44%
Flow Meters
Actual Date 0.00%
Modification of Existing System, Plan Date 6-Sep-17 27-Mar-18 4-May-18 4-May-18 0.00%
3.3 20.01%
Yokogawa,Emerson, Honey well
Actual Date 0.00%
4 Electrical
Plan Date 18-Sep-17 9-Dec-18 16-Jan-18 16-Jan-18 0.00%
4.1 Junction Box/Lighting Fixture 0.68%
Actual Date 0.00%
5 Loss Preventation
Plan Date 23-Sep-17 24-Feb-18 3-Apr-18 3-Apr-18 0.00%
5.1 Fire Detection System 3.22%
Actual Date 0.00%
Plan Date 28-Sep-17 2-Apr-18 10-May-18 10-May-18 0.00%
5.2 Deluge Skids and Fire water Spray Nozzles 10.86%
Actual Date 0.00%
Plan Date 28-Sep-17 13-Feb-18 23-Mar-18 23-Mar-18 0.00%
5.3 Firefighting & Safety Equipment 1.40%
Actual Date 0.00%

Page 164 of 170


Bulk Material - Procurement Control Register for Invoice
Project No. - 3963
"EPIC OF REPLACMENT OF THREE PHASE TEST SEPARATORS IN ALL DEGASSING STATIONS"
As Of : 06-Jul-17
Successful
Issue QP inspected and
SL. Plan/ Actual Inspection commissioning
Description Purchase cleared material at % Weight % Progress
No. Date cleared & FAT and handover of
Order site
spares
Progress Scale 10% 55% 80% 100% WTGE % Phy. Comp.
0.919%
2.0 BULK MATERIAL 24.20%
0.000%
1 Piping
Plan Date 28-Aug-17 9-Nov-17 28-Nov-17 26-Dec-17 0.00%
1.1 Bolts&Nuts/Gaskets 0.40%
Actual Date 0.00%
2 Intrumentation
Plan Date 7-Nov-17 25-Dec-17 8-Jan-18 28-Jan-18 0.00%
2.1 Cable tray/cable/tubes & fittings 4.18%
Actual Date 0.00%
3 Electrical
Plan Date 18-Sep-17 5-Nov-17 24-Nov-17 23-Dec-17 0.00%
3.1 Cable Trays/cable 0.87%
Actual Date 0.00%
4 Civil/Strctural Steel
Plan Date 5-Oct-17 12-Nov-17 26-Nov-17 16-Dec-17 0.00%
4.1 Civle/Strctural Steel 8.54%
Actual Date 0.00%
Successful
Issue QP inspected and
Inspection commissioning
2 Early Tie-in Piping Purchase cleared material at
cleared & FAT and handover of
Order site
spares
Plan Date 28-May-17 25-Jun-17 30-Jul-17 14-Aug-17 55.00%
2.1 Pipes Early Tie-ins 1.11%
Actual Date 0.00%
Plan Date 28-May-17 25-Jun-17 31-Aug-17 13-Sep-17 55.00%
2.2 Early Tie-in Flanges 0.23%
Actual Date 0.00%
Plan Date 28-May-17 25-Jun-17 31-Aug-17 13-Sep-17 55.00%
2.3 Early Tie-in Fittings 0.33%
Actual Date 0.00%
Plan Date 10-Aug-17 18-Feb-18 4-Apr-18 16-Apr-18 0.00%
2.4 Ball Valve / GGC Valve 6.00%
Actual Date 0.00%
Plan Date 28-Aug-17 21-Nov-17 23-Dec-17 4-Jan-18 0.00%
2.5 Pipes Remaining 1.69%
Actual Date 0.00%
Plan Date 28-Aug-17 21-Nov-17 23-Dec-17 4-Jan-18 0.00%
2.6 Flanges 0.35%
Actual Date 0.00%
Plan Date 28-Aug-17 21-Nov-17 23-Dec-17 4-Jan-18 0.00%
0.49%
2.7 Remiaining Project Fittings Actual Date 0.00%

Page 165 of 170


CONTRACT NO: GC16110300
EPIC FOR EXTENSION OF MANIFOLDS TO CREATE ADDITIONAL SLOTS AT KN AND KS IN DUKHAN 

Construction

Item DESCRIPTION 95% Cummulative till last Invoice This Invoice Cummulative upto this invoice


LUMP SUM
 AMOUNT  OF LUMP SUM 
(QAR) AMOUNT  % progress Amount QR. % progress Amount QR. % progress Amount QR.
(QAR)
2.2.1.1 App B Part 1 clause 2.2.1.1  Ninety five percent 95% of the LUMP PRICE portion is based on physical progress for the month

Schedule 04: Construction

1 KHATIYAH NORTH

1.1
All “Mechanical/ Piping/ Machinery” construction works 210,537.00 200,010.15

1.2
All “Instrumentation & Controls” construction works 293,393.00 278,723.35

1.3
All “Electrical” construction works 177,334.00 168,467.30

1.4
All “Civil/Structural/Architectural” construction works 490,498.00 465,973.10

1.5
All “Loss Prevention” construction works 73,348.00 69,680.60

1.6 Demolition Work 147,149.00 139,791.55

1.7 Any Other Item -

2 KHATIYAH MAIN

2.1
All “Mechanical/ Piping/ Machinery” construction works 172,493.00 163,868.35

2.2
All “Instrumentation & Controls” construction works 249,258.00 236,795.10

2.3
All “Electrical” construction works 145,290.00 138,025.50

2.4
All “Civil/Structural/Architectural” construction works 401,865.00 381,771.75

2.5
All “Loss Prevention” construction works 60,094.00 57,089.30

2.6 Demolition Work 120,560.00 114,532.00

2.7 Any Other Item -

3 KHATIYAH SOUTH

Page 166 of 170

1 of 14
Item DESCRIPTION 95% Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM
3.1
All “Mechanical/ Piping/ Machinery” construction works 169,288.00 160,823.60

3.2
All “Instrumentation & Controls” construction works 235,911.00 224,115.45

3.3
All “Electrical” construction works 142,591.00 135,461.45

3.4
All “Civil/Structural/Architectural” construction works 394,399.00 374,679.05

3.5
All “Loss Prevention” construction works 58,978.00 56,029.10

3.6 Demolition Work 118,320.00 112,404.00

3.7 Any Other Item - -

4 FAHAHIL NORTH
-

4.1
All “Mechanical/ Piping/ Machinery” construction works 156,146.00 148,338.70

4.2
All “Instrumentation & Controls” construction works 217,596.00 206,716.20

4.3
All “Electrical” construction works 131,520.00 124,944.00

4.4
All “Civil/Structural/Architectural” construction works 363,780.00 345,591.00

4.5
All “Loss Prevention” construction works 54,399.00 51,679.05

4.6 Demolition Work 109,135.00 103,678.25

4.7 Any Other Item - -

5 FAHAHIL MAIN
-

5.1
All “Mechanical/ Piping/ Machinery” construction works 197,910.00 188,014.50

5.2
All “Instrumentation & Controls” construction works 275,797.00 262,007.15

5.3
All “Electrical” construction works 166,698.00 158,363.10

5.4
All “Civil/Structural/Architectural” construction works 461,081.00 438,026.95

5.5
All “Loss Prevention” construction works 68,949.00 65,501.55

5.6 Demolition Work 138,324.00 131,407.80

5.7 Any Other Item - - Page 167 of 170

2 of 14
Item DESCRIPTION 95% Cummulative till last Invoice This Invoice Cummulative upto this invoice
LUMP SUM
6 FAHAHIL SOUTH
-

6.1
All “Mechanical/ Piping/ Machinery” construction works 161,392.00 153,322.40

6.2
All “Instrumentation & Controls” construction works 224,908.00 213,662.60

6.3
All “Electrical” construction works 135,940.00 129,143.00

6.4
All “Civil/Structural/Architectural” construction works 376,004.00 357,203.80

6.5
All “Loss Prevention” construction works 56,227.00 53,415.65

6.6 Demolition Work 112,801.00 107,160.95

6.7 Any Other Item - -

7 JALEHA
-

7.1
All “Mechanical/ Piping/ Machinery” construction works 208,217.00 197,806.15

7.2
All “Instrumentation & Controls” construction works 290,160.00 275,652.00

7.3
All “Electrical” construction works 175,380.00 166,611.00

7.4
All “Civil/Structural/Architectural” construction works 485,092.00 460,837.40

7.5
All “Loss Prevention” construction works 72,540.00 68,913.00

7.6 Demolition Work 145,528.00 138,251.60

7.7 Any Other Item - -

Total Construction 8,446,830.00 8,024,488.50

Page 168 of 170

3 of 14
CONTRACT NO: GC16110300
EPIC FOR EXTENSION OF MANIFOLDS TO CREATE ADDITIONAL SLOTS AT KN AND KS IN DUKHAN 
Pre-Commissioning, Commissioning & Operational Testing

Item DESCRIPTION 95% Cummulative till last Invoice This Invoice Cummulative upto this invoice


LUMP SUM OF LUMP SUM 
 AMOUNT  AMOUNT (QAR)
% progress Amount QR. % progress Amount QR. % progress Amount QR.
(QAR)

2.2.1.1 App B Part 1 clause 2.2.1.1  Ninety five percent 95% of the LUMP PRICE portion is based on physical progress for the month
Schedule 05: Pre‐Commissioning, Commissioning & Operational 
Testing
1 KHATIYAH NORTH
1.1 All pre-commissioning activities of the FACILITY, including 15,682.00
preparation of check lists, test sheets, status index, punch list,                     14,897.90 
pre-commissioning dossier and spare parts
1.2 All commissioning activities of the FACILITY including 25,354.00
preliminary checks, functional checks, and compilation of a                     24,086.30 
“Ready For Startup” dossier and spare parts.
1.3 All Operations and performance tests including Site 89,537.00                     85,060.15 
Acceptance Tests (SAT) requirements.
1.4 Project Dossier: compilation by sub-system as required in 15,139.00                     14,382.05 
Scope of Work Clause 4.10, Appendix A
1.5 Any Other Item 18,388.00                     17,468.60 
2 KHATIYAH MAIN                                    ‐   
2.1 All pre-commissioning activities of the FACILITY, including 15,682.00
preparation of check lists, test sheets, status index, punch list,                     14,897.90 
pre-commissioning dossier and spare parts
2.2 All commissioning activities of the FACILITY including 25,354.00
preliminary checks, functional checks, and compilation of a                     24,086.30 
“Ready For Startup” dossier and spare parts.
2.3 All Operations and performance tests including Site 89,537.00                     85,060.15 
Acceptance Tests (SAT) requirements.
2.4 Project Dossier: compilation by sub-system as required in 15,139.00                     14,382.05 
Scope of Work Clause 4.10, Appendix A
2.5 Any Other Item 18,388.00                     17,468.60 
3 KHATIYAH SOUTH                                    ‐   
3.1 All pre-commissioning activities of the FACILITY, including 15,682.00
preparation of check lists, test sheets, status index, punch list,                     14,897.90 
pre-commissioning dossier and spare parts
3.2 All commissioning activities of the FACILITY including 25,354.00
preliminary checks, functional checks, and compilation of a                     24,086.30 
“Ready For Startup” dossier and spare parts.
3.3 All Operations and performance tests including Site 89,537.00                     85,060.15 
Acceptance Tests (SAT) requirements.
3.4 Project Dossier: compilation by sub-system as required in 15,139.00                     14,382.05 
Scope of Work Clause 4.10, Appendix A
1.5 Any Other Item 18,388.00                     17,468.60 
4 FAHAHIL NORTH                                    ‐   
4.1 All pre-commissioning activities of the FACILITY, including 15,682.00
preparation of check lists, test sheets, status index, punch list,                     14,897.90 
pre-commissioning dossier and spare parts
4.2 All commissioning activities of the FACILITY including 25,354.00
preliminary checks, functional checks, and compilation of a                     24,086.30 
“Ready For Startup” dossier and spare parts.
4.3 All Operations and performance tests including Site 89,537.00                     85,060.15 
Acceptance Tests (SAT) requirements.
4.4 Project Dossier: compilation by sub-system as required in 15,139.00                     14,382.05 
Scope of Work Clause 4.10, Appendix A
4.5 Any Other Item 18,388.00                     17,468.60 
5 FAHAHIL MAIN                                    ‐   
                                   ‐   
5.1 All pre-commissioning activities of the FACILITY, including 15,682.00 Page 169 of 170
preparation of check lists, test sheets, status index, punch list,                     14,897.90 
pre-commissioning dossier and spare parts 1 of 14
Item DESCRIPTION 95% Cummulative till last Invoice This Invoice Cummulative upto this invoice
5.2 All commissioning activities of the FACILITY including 25,354.00
preliminary checks, functional checks, and compilation of a                     24,086.30 
“Ready For Startup” dossier and spare parts.
5.3 All Operations and performance tests including Site 89,537.00                     85,060.15 
Acceptance Tests (SAT) requirements.
5.4 Project Dossier: compilation by sub-system as required in 15,139.00                     14,382.05 
Scope of Work Clause 4.10, Appendix A
5.5 Any Other Item 18,388.00                     17,468.60 
6 FAHAHIL SOUTH                                    ‐   
6.1 All pre-commissioning activities of the FACILITY, including 15,682.00
preparation of check lists, test sheets, status index, punch list,                     14,897.90 
pre-commissioning dossier and spare parts
6.2 All commissioning activities of the FACILITY including 25,354.00
preliminary checks, functional checks, and compilation of a                     24,086.30 
“Ready For Startup” dossier and spare parts.
6.3 All Operations and performance tests including Site 89,537.00                     85,060.15 
Acceptance Tests (SAT) requirements.
6.4 Project Dossier: compilation by sub-system as required in 15,139.00                     14,382.05 
Scope of Work Clause 4.10, Appendix A
6.5 Any Other Item 18,388.00                     17,468.60 
7 JALEHA                                    ‐   
7.1 All pre-commissioning activities of the FACILITY, including 15,682.00
preparation of check lists, test sheets, status index, punch list,                     14,897.90 
pre-commissioning dossier and spare parts
7.2 All commissioning activities of the FACILITY including 25,354.00
preliminary checks, functional checks, and compilation of a                     24,086.30 
“Ready For Startup” dossier and spare parts.
7.3 All Operations and performance tests including Site 89,537.00                     85,060.15 
Acceptance Tests (SAT) requirements.
7.4 Project Dossier: compilation by sub-system as required in 15,139.00                     14,382.05 
Scope of Work Clause 4.10, Appendix A
7.5 Any Other Item 18,388.00                     17,468.60 
Total  Pre‐Commissioning, Commissioning & Operational Testing              1,148,700.00              1,091,265.00

Page 170 of 170