You are on page 1of 102

Stage Strengthening of the existing pavement from 0.00 Kmp to 49.

00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II


during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

EPC Schedules

EPC Schedules 1 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

SCHEDULE - A

(See Clauses 2.1 and 8.1)

SITE OF THE PROJECT


1. The Site

(i) Site of the Project shall include the land, buildings, structures and road works as
described in Annex-I of this Schedule-A.
(ii) The dates of handing over Right of Way to the Contractor are specified in the Annex-II of this
Schedule A.

(iii) An inventory of the Site including the land, buildings, structures, road works, trees and any
other immovable property on, or attached to, the Site shall be prepared jointly by the
Authority Representative and the Contractor, and such inventory shall form part of the
memorandum referred to in Clause 8.2.(i) of this Agreement.

(iv) The alignment plans of the Project Highway and its approaches are specified in Annex-III. In
the case of sections where no modification in the existing alignment of the Project Highway is
contemplated, the alignment plan has not been provided. Alignment plans have only been
given for sections where the existing alignment is proposed to be upgraded. The proposed
profile of the Project Highways shall be followed by the contractor with minimum FRL as
indicated in the alignment plan. The contractor, however, improve/upgrade the Road Profile
as indicated in Annexure-III based on site/design requirement.

(v) The status of the environment clearances obtained or awaited is given in Annex - IV.

EPC Schedules 2 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex - I
(Schedule-A)

Site

[Note: Through suitable drawings and description in words, the land, buildings,
structures and road works comprising the Site shall be specified briefly but
precisely in this Annex-I. All the chainages /location referred to in Annex-I to
Schedule-A shall be existing chainages.]

1. Site

The Site of the Two-Lane Project Highway comprises the section of National
Highway NH-2B commencing from km Ch. 0.00 km to 49.00 km in the district
of Purba Bardhaman & Birbhum in the State of West Bengal. The land,
carriageway and structures comprising the Site are described below.

2. Land

The Site of the Project Highway comprises the existing Two lane carriageway
with earthen shoulders of width varies from 1.00 m to 2.00 m on either side
along with the side slopes along the existing alignment.
3. Carriageway

The project corridor has an average carriageway width of 9.00 m with earthen
shoulder varies from 1.00 m to 2.00 m on either side from Km 0.000 to Km
27.000 and average carriageway 7.0 m with earthen shoulder varies from 1.00 m
to 2.00 m on either side from Km 27.00 to Km 49.00. Formation width of
corridor varies from 9.00 m to 13.0 m for most of the length. The embankment
height along the project corridor is ranging between 0.20 m to 3.50 m. The type
of the existing pavement is flexible.

4. Major Bridges
The Site includes the following Major Bridges:

Length
Existing Carriageway
Sl. Type of of
Chainage No. of Span with Span Length Width
No. Structures Bridge
(Km) (m)
(m)
9+900 RCC Box 1 x 9.10m + 1 x 21.50m + 1 x
1 91.60 6.70
(Haldi Bridge) Girder 24.40m + 1 x 21.40m + 1 x 9.10m
28+312 RCC Solid 1 x 8.0m + 6 x 7.20m + 3 x 7.10m +
2 133.00 5.50
(Kunur Bridge) Slab Bridge 7 x 7.20m + 1 x 8.0m
44+400 RCC Box 622.360 m (Main Bridge)
3 785.00 7.50
(Aban Setu) Girder 77.520 m (Viaduct - Both Side)

EPC Schedules 3 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

5. Road over-bridges (ROB)/ Road under-bridges (RUB)

The Site includes the following ROB (road over railway line) / RUB (road under
railway line):

S. Chainage Type of Structure No. of Spans with Width ROB/


No. (km) span length (m) (m) RUB
Foundation Superstructure

Nil Nil Nil Nil Nil Nil Nil

6. Grade separators

The Site includes the following grade separators:

S. No. Chainage Type of Structure No. of Spans with Width


(km) span length (m) (m)
Foundation Superstructure
Nil Nil Nil Nil Nil Nil

7. Minor bridges

The Site includes the following minor bridges:

Existing Nos. of Span Carriageway


Type of Length
Sl. No. Chainage with Span Width
Structures (m)
(Km) Length (m)

RCC Solid 2 x 11.00


1 0+914 23.30 10.50
Slab m
RCC Solid
2 3+640 4 x 5.00 m 21.80 7.50
Slab
RCC Solid
3 7+538 1 x 8.50 m 17.00 10.50
Slab
1 x 11.50
4 18+920 RCC Girder 19.20 10.50
m
RCC Solid
5 19+000 3 x 9.40 m 35.95 10.50
Slab
6 25+808 Arch 2 x 5.00 m 12.30 6.00
7 36+776 Arch 2 x 3.00 m 10.75 4.60
8 42+985 RCC Box 6 x 4.00 m 26.00 7.60
9 43+543 RCC Box 6 x 4.00 m 26.00 7.60
10 44+810 RCC Box 3 x 3.00 m 25.50 7.50

EPC Schedules 4 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

8. Culverts
The Site includes the following culverts
Sl. Existing Ch. Nos. of Span with Span Carriageway
Type of Culverts
No. (Km) Length Width (m)
1 0+053 Slab 1 x 1.80 m 8.80
2 0+111 Slab 1 x 1.80 m 8.80
3 0+519 Slab 1 x 1.75 m 8.80
4 1+180 Slab 1 x 1.80 m 8.80
5 1+341 Slab 1 x 1.80 m 8.85
6 1+542 Slab 1 x 1.80 m 8.80
7 1+794 Slab 1 x 1.80 m 8.80
8 2+040 Slab 1 x 1.80 m 8.80
9 2+524 Slab 1 x 1.80 m 8.80
10 2+600 Slab 1 x 1.75 m 8.80
11 2+915 Slab 1 x 1.80 m 8.80
12 4+034 Slab 1 x 1.80 m 8.80
13 5+436 Slab 1 x 1.80 m 8.80
14 5+622 Slab 1 x 1.80 m 8.80
15 5+978 Slab 1 x 1.80 m 8.80
16 6+140 Slab 1 x 1.80 m 8.80
17 6+507 Slab 1 x 1.75 m 8.80
18 7+190 Slab 1 x 1.80 m 8.80
19 7+362 Slab 1 x 1.80 m 8.80
20 8+825 Slab 1x 1.25 m (LHS) & 1 x 8.80
21 10+403 Slab 1 x 1.80 m 8.80
22 10+665 Slab 1 x 1.80 m 8.80
23 11+016 Slab 1 x 2.00 m 8.80
24 11+321 Slab 1 x 1.80 m 8.80
25 11+649 Slab 1 x 1.80 m 8.90
26 11+710 Slab 1 x 1.80 m 9.00
27 11+812 Slab 1 x 1.80 m 8.80
28 12+349 Slab 1 x 1.80 m 8.70
29 12+695 Slab 1 x 1.80 m 8.90
30 12+879 Slab 1 x 2.80 m 8.80
31 13+377 Slab 1 x 1.70 m 8.80
32 13+460 Slab 1 x 1.80 m 9.00
33 13+663 Pipe 1 x 600 mm Dia. 8.80
34 14+076 Slab 1 x 2.00 m 9.00
35 14+316 Slab 1 x 1.80 m 9.00
36 14+663 Slab 1 x 1.80 m 8.90
37 14+960 Slab 1 x 1.80 m 9.00
38 15+400 Slab 1 x 1.80 m 9.10
39 16+005 Slab 1 x 2.00 m 8.90
40 16+113 Slab 1 x 2.10 m 8.30
41 16+443 Slab 1 x 1.00 m 8.90
42 16+720 Slab 1 x 1.80 m 8.90
43 17+178 Slab 1 x 1.80 m 9.00
44 17+935 Slab 1 x 1.80 m 8.80

EPC Schedules 5 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Sl. Existing Ch. Nos. of Span with Span Carriageway


Type of Culverts
No. (Km) Length Width (m)
45 19+042 Pipe 2 x 900 mm Dia. 9.30
46 19+922 Slab 1 x 1.80 m 9.00
47 20+109 Slab 1 x 1.80 m 9.10
48 20+365 Slab 1 x 1.80 m 8.90
49 20+734 Slab 1 x 1.70 m 8.80
50 20+829 Slab 1 x 1.70 m 9.30
51 20+609 Slab 1 x 1.80 m 8.90
52 21+782 Pipe 1 x 900 mm Dia. 9.00
53 21+970 Slab 1 x 1.80 m 8.90
54 22+061 Slab 1 x 1.80 m 8.90
55 22+578 Slab 1 x 1.80 m 8.90
56 23+146 Slab 1 x 2.60 m 8.90
57 23+455 Slab 1 x 2.80 m 6.60
58 23+897 Slab 1 x 1.80 m 9.20
59 24+044 Slab 1 x 1.80 m 8.90
60 24+478 Slab 1 x 1.80 m 9.00
61 24+674 Slab 1 x 1.80 m 8.60
62 25+494 Slab 1 x 1.80 m 0.30
63 25+726 Slab 1 x 1.80 m 0.30
64 25+900 Pipe 4 x 600 mm + 1 x 1000 -
65 26+602 Slab 1 x 2.60 m 0.30
66 28+636 Slab 1 x 0.60 m 0.25
67 28+861 Slab 1 x 2.80 m 0.35
68 28+933 Slab 1 x 4.00 m 0.35
69 29+094 Slab 1 x 4.50 m 0.35
70 29+250 Slab 1 x 4.60 m 0.35
71 29+656 Slab 1 x 3.20 m 0.35
72 31+295 Slab 1 x 1.50 m 10.90
73 31+662 Slab 1 x 1.70 m 10.90
74 31+737 Slab 1 x 3.00 m 9.40
75 32+317 Slab 1 x 1.60 m 11.00
76 32+989 Slab 1 x 3.20 m 9.10
77 33+095 Slab 1 x 1.50 m 10.90
78 33+155 Slab 1 x 5.00 m 11.00
79 33+254 Slab 1 x 3.10 m 9.50
80 33+909 Slab 1 x 3.20 m 9.50
81 34+250 Slab 1 x 3.10 m 9.40
82 34+694 Slab 1 x 3.00 m 9.30
83 34+798 Slab 1 x 1.60 m 10.90
84 34+885 Slab 1 x 3.20 m 9.40
85 35+239 Slab 1 x 1.50 m 11.00
86 35+623 Slab 1 x 1.50 m 11.10
87 36+148 Slab 1 x 3.00 m 9.30
88 36+171 Slab 1 x 3.20 m 10.60
89 36+300 Slab 1 x 0.95 m 10.00
90 36+858 Slab 1 x 3.90 m 9.40

EPC Schedules 6 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Sl. Existing Ch. Nos. of Span with Span Carriageway


Type of Culverts
No. (Km) Length Width (m)
91 36+962 Slab 1 x 1.60 m 10.20
92 37+281 Slab 1 x 2.90 m 11.10
93 37+431 Slab 1 x 2.40 m 10.90
94 37+569 Slab 1 x 3.20 m 9.20
95 37+702 Slab 1 x 1.30 m 10.90
96 37+979 Pipe 1 x 600 mm Dia. 10.10
97 38+142 Slab 1 x 0.55 m 9.10
98 38+259 Slab 1 x 1.00 m 11.00
99 38+629 Slab 1 x 0.90 m 10.90
100 39+045 Slab 1 x 1.50 m 10.90
101 39+312 Slab 1 x 3.00 m 11.00
102 40+396 Slab 1 x 1.50 m 10.90
103 40+906 Slab 1.30 m 10.90
104 41+049 Slab 1 x 1.50 m 10.90
105 41+551 Slab 1.60 m 10.90
106 41+614 Slab 4.00 m 10.90
107 42+022 Slab 1 x 1.50 m 11.40
108 42+153 Slab 1 x 1.50 m 10.90
109 42+225 Slab 1 x 3.00 m 9.50
110 42+261 Slab 4.00 m 11.00
111 42+425 Slab 2.00 m 11.20
112 42+597 Slab 1 x 3.00 m 10.90
113 42+822 Slab 1 x 3.00 m 10.90
114 44+831 Pipe 2 x 1000 mm Dia. 7.00
115 45+144 Pipe 2 x 1000 mm Dia. 7.00
116 45+448 Slab 1 x 2.50 m 7.00
117 45+536 Pipe 1 x 1000 mm Dia. 10.00
118 45+973 Slab 1 x 1.50 m 10.90
119 46+020 Pipe 2 x 900 mm Dia. 20.10
120 46+206 Slab 1 x 1.50 m 7.50
121 46+617 Pipe 1 x 600 mm Dia. 9.10
122 47+404 Slab 1 x 1.50 m 10.80
123 47+662 Slab 1 x 1.50 m 9.90
124 47+826 Slab 1 x 4.80 m 10.90
125 47+885 Slab 1 x 1.50 m 10.90
126 48+178 Slab 1 x 1.50 m 10.90
127 48+580 Pipe 1 x 600 m 11.00

9. Railway level crossings


The Site includes the following railway level crossings:

S. No. Location (km) Remarks


1 3+920 Talit Level Crossion

EPC Schedules 7 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

10. Underpasses (vehicular, non-vehicular)

The Site includes the following underpasses:

S. No. Chainage Type of Structure No. of Spans with Width


(km) span length (m) (m)
1 41+735 RCC Slab Girder 1 x 3.50 m 3.50
11. Bus bays

The details of bus bays on the Site are as follows:

S. No. Chainage(km) Length (m) Left Hand Right Hand Side


Side

Nil Nil Nil Nil Nil

12. Truck Lay byes

The details of truck lay byes are as follows:

S. No. Chainage Length (m) Left Hand Right Hand


(km) Side Side
Nil Nil Nil Nil Nil

13. Junctions

(a) The details of major junctions are as follows:


Sl. Exisitng Chainage Category of Cross Road
At Grade Separated
No. (Km) NH SH MDR Others
0+000 G.T.
1 At Grade - NH-2 - -
(Nababhat More) Road
2 9+675 At Grade - - - - BT Road
3 10+700 At Grade - - - - BT Road
4 16+100 At Grade - - - - BT Road
25+775
5 At Grade - - SH-14 - -
(Balgona More)
Gushkara
27+225
6 At Grade - - - - Station
(Guskara More)
Road
48.300 km
7 At Grade
(Shib Tola)

(NH: National Highway, SH: State Highway, MDR: Major District Road)

EPC Schedules 8 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(b) The details of minor junctions are as follows:

Sl.
Chainage Side Type of Junction Category of Road
No. (Km)
1 0+332 Left Side 3 Leged Bitumen Road
2 5.441 Right Side 3 Leged Bitumen Road

3 9.117 Left Side 3 Leged Bitumen Road


4 10.50 Right Side 3 Leged Bitumen Road
5 24.247 Left Side 3 Leged Bitumen Road
6 32.364 Both Side 4 Leged Bitumen Road
7 39.700 Left Side 3 Leged Bitumen Road
8 46.075 Right Side 3 Leged Bitumen Road

14. Bypasses
The details of the existing road sections proposed to be bypassed are as follows:

S. Name of bypass Chainage (km) Length


No. (town) From km to km (in Km)

Nil

15. Built-up Areas


The site includes the following built up areas

Sl. Built-up Stretches (Km)


Name of the Township
No. From To

1 0+150 0+575 Nababhat


2 0+575 0+750 Nababhat
3 5+125 5+475 Talit
4 9+025 9+400 Dey Para
5 13+300 13+975 Kairapur
6 15+800 15+900 Kairapur
7 20+400 20+950 Orgram
8 25+320 25+625 Shibda
9 25+625 28+570 Gushkara
10 30+375 30+750 Gushkara
11 32+275 32+690 Gobindapur
12 35+100 35+650 Gangarampur
13 36+100 37+100 Batagram
14 37+100 38+125 Kalyanpur
15 39+000 39+900 Bhedia
16 45+600 46+100 Gheropara
17 46+100 46+700 Nurpur

EPC Schedules 9 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex - II
(Schedule-A)

Dates for providing Right of Way

The dates on which the Authority shall provide Right of Way to the Contractor on different
stretches of the Site are stated below:

Sl. No. From km to Length Width Date of providing


km (km) (m) ROW*

1 2 3 4 5
(i) Full Right of 0.00 km to 49.00 Total - 9.80 to 36.00 m
Way (full 49.00 km of 49.00 km On Appointed Date
width) NH-2B

* The dates specified herein shall in no case be beyond 150 (one hundred and fifty)
days after the Appointed Date.

EPC Schedules 10 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex - III
(Schedule-A)

Alignment Plans

The existing alignment of the Project Highway shall be modified in the following sections
as per the alignment plan indicated below:

Not required. Existing alignment shall be followed.

EPC Schedules 11 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex - IV
(Schedule-A)

Environment Clearances

The following environment clearances have been obtained: Not Required


The following environment clearances are awaited:

Not Required
_

EPC Schedules 12 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

SCHEDULE - B
(See Clause 2.1)

Development of the Project Highway

1 Development of the Project Highway

Development of the Project Highway shall include design and construction of the
Project Highway as described in this Schedule-B and in Schedule-C.

2 [Rehabilitation and augmentation]

Rehabilitation and augmentation shall include Stage Strengthening of the existing


pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway
Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba
Bardhaman & Birbhum ,West Bengal as described in annex-I of this Schedule-B and
in Schedule-C.

3 Specifications and Standards

The Project Highway shall be designed and constructed in conformity with the
Specifications and Standards specified in Annex-I of Schedule-D.

EPC Schedules 13 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex - I
(Schedule-B)

Description of Periodical Renewal Works

1 WIDENING OF THE EXISTING HIGHWAY

(i) The Project Highway shall follow the existing alignment unless otherwise
specified by the Authority and shown in the alignment plans specified in Annex III
of Schedule-A. No widening of existing carriageway is required.

(ii) WIDTH OF CARRIAGEWAY

The project corridor has an average carriageway width of 9.00 m with earthen
shoulder varies from 1.50 m to 2.00 m on either side from Km 0.000 to Km 27.000
and average 7.0 m with earthen shoulder varies from 1.50 m to 2.00 m on either side
from Km 27.000 to Km 49.00. Formation width of corridor varies from 9.00 m to 13.0
m for most of the length. The embankment height along the project corridor is ranging
between 0.20 m to 3.50 m. Width of carriage way is more in Junction areas.

2 GEOMETRIC DESIGN AND GENERAL FEATURES

(i) General
Geometric design and general features of the Project Highway shall be in
accordance with Section 2 of the Manual.

(ii) Design speed

The design speed shall be the minimum design speed of 80 km per hr for plain/
rolling terrain.

(iii) Improvement of the existing road geometrics


[Refer to paragraph 2.1 (vi) of the Manual and provide details]
The existing road geometrics shall be followed along the project stretch. There is
no need of any further improvement of road geometrics.

(iv) Right of Way

[Refer to paragraph 2.3 of the Manual]. Details of the Right of Way are given in
Annex II of Schedule-A.

EPC Schedules 14 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(v) Type of shoulders

[Refer to table 2.5.2 of the Manual and specify]

Earthen soft shoulders are to be mended as per the proposed finished level of
bituminous layer. Side slope of the embankment should be 1:2. In addition to this as
minimum provision 200 mm compacted thick hard shoulder need to be laid for a
minimum width of 1.50 m on both side with minimum length of 47.40 km X 2 side
within the project zone except bridge and culvert portion.

(vi) Lateral and vertical clearances at underpasses

(a) Lateral and vertical clearances at underpasses and provision of guardrails/crash


barriers shall be as per paragraph 2.11 of the Manual.

(b) Lateral clearance: The width of the opening at the underpasses shall be as
follows:

Sl. No. Location Span/opening (m) Remarks


(chainage)
(from km to km)
Not Not Applicable Not Applicable Not Applicable
Applicable

(vii) Lateral and vertical clearances at overpasses

(a) Lateral and vertical clearances at overpasses shall be as per paragraph 2.12 of
the Manual.
(b) Lateral clearance: The width of the opening at the overpasses shall be as
follows:

Sl. No. Location Span / opening Remarks


(chainage) (m)
(from km to km)
Not Applicable Not Applicable Not Applicable Not Applicable

(viii) Service roads


Service roads shall be constructed at the locations and for the lengths indicated below:
[Refer to paragraph 2.13 of the Manual and provide details]

Sl. No. Location of Right hand side (RHS)/Left Length (km) of


service road (from km hand side (LHS)/ or Both sides service road
to km)
Not Applicable Not Applicable Not Applicable Not Applicable

EPC Schedules 15 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(ix) Grade separated structures

(a) Grade separated structures shall be provided as per paragraph 2.14 of the Manual.
The requisite particulars are given below:

[Refer to paragraphs 2.13.1 of the Manual and provide details]

Sl. No. Location of Length (m) Number Approach Remarks,


structure and length gradient if any
of spans (m)
Not Not Applicable Not Not Not Not
Applicable Applicable Applicable Applicable Applicable

(b) In the case of grade separated structures, the type of structure and the level of the
Project Highway and the cross roads shall be as follows: [Refer to paragraphs 2.14.2
of the Manual and specify the type of vehicular under pass/ overpass structure and
whether the cross road is to be carried at the existing level, raised or lowered]

Sl. Location Type of Cross road at Remarks, if


No. structure any
Existing Raised Lowered
(m)
Level Level Level
Not Applicable

(x) Cattle and pedestrian underpass /overpass

Cattle and pedestrian underpass/ overpass shall be constructed as follows: [Refer to


paragraphs 2.14.3 of the Manual and specify the requirements of cattle and
pedestrian underpass/ overpass]

Sl. No. Location Type of crossing


Not Applicable Not Applicable Not Applicable

(xi) Typical cross-sections of the Project Highway

[Give typical cross-sections of the Project Highway by reference to the Manual].


As per existing cross section of 2-lane configuration. Cross section attached as per
schedule I
3 INTERSECTIONS AND GRADE SEPARATORS

All intersections and grade separators shall be as per Section 3 of the Manual.
Existing intersections which are deficient shall be improved to the prescribed standards.
[Refer to paragraphs 3.1.1, 3.1.2 and 3.3 of the Manual and specify the requirements.
Explain where necessary with drawings/sketches/general arrangement]
The important intersection to be treated with 40 mm bituminous concrete over 50 mm
thick DBM as minimum provision up to the limit of the ROW.

EPC Schedules 16 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Major Intersections

Sl. No. Location(Km) Place Type of Junction


1 0.000 Km Nababhat More 3Leged
2 9.675 Km --- 3Leged
3 10.700 Km --- 3Leged
4 16.100 Km --- 4Leged
5 25.775 Km Balgona More 3Leged
6 27.225 Km GuskaraMore 3Leged
7 48.300 km Shib Tola 4 Leged

Minor Intersections

Sl. No. Side Type of Junction


Location(Km)
1 0.332 Km Right Side 3 Leged
2 5.441 Km Right Side 3 Leged
3 9.117 Km Left Side 3 Leged
4 10.500 Km Right Side 3 Leged
5 24.247 Km Left Side 3 Leged
6 32.364 Km Both Side 4 Leged
7 39.700 Km Left Side 3 Leged
8 46.075 Km Right Side 3 Leged

4 Stage Strengthening Work

(i) The existing bituminous wearing course by BC should be removed before over laying.
Over the levelling course by DBM, the pavement is to be overlaid with 50 mm thick
DBM and 40 mm thick BC as wearing course in the overall project stretch except in the
portion of Aban Setu (44.40 km), Haldi Bridge (9.90 km), Kunur Bridge (28.312 km)
and Eight other minor bridges at (0.914 km,3.64 km, 7.538 km, 18.92 km, 19.00
km,25.808 km, 42.985 km, 43.543 km) where the bridge portions including suitable
length of bridge approaches for a total minimum area of 9100 sqm has to be treated with
25 mm thick mastic over 40 mm thick BC as minimum provision, removing the existing
wearing course of suitable thickness to make the carriage way true to the profile. In case
of Aban setu the entire existing disintegrated concrete wearing course to be removed
before laying wearing course i.e 40 BC & 25 mastic to make the carriage way true to the
profile. The Built-up Areas in different locations are to be treated with 40 mm thick
mastic over DBM for a total area of 24000 sqm as minimum provision following the IRC
specification. Over laying on the Project Length to be with proper camber and
longitudinal profile replacing the existing damaged and cracked surface with fresh
leveling course. In addition to this, rehabilitation of the existing depressed carriage way
zones where necessary need to be done for Base course/Sub base/ Subgrade as per
specification and standards.
A minimum provision of 250 mm thick WMM as non-bituminous base and (75+50) mm
thick DBM as bituminous base followed by 40mm Bituminous Concrete has to be carried
out. Total minimum length of rehabilitation zone is 5190 m

EPC Schedules 17 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Details of the Rehabilitation Stretches

Sl. No. From To Total Length


1. 1.500 km. 1.700 km. 200.00 m.
2. 2.500 km. 2.700 km. 200.00 m.
3. 2.800 km. 3.100 km. 300.00 m.
4. 3.650 km. 3.850 km. 200.00 m.
5. 4.500 km. 4.700 km. 200.00 m
6 5.500 km. 5.600 km. 100.00 m
7. 8.400 km. 8.600 km. 200.00 m.
8. 9. 600km. 9.850 km. 250.00 m.
9. 10.750 km. 11.000 km. 250.00 m.
10. 11.350 km. 11.550 km. 200.00 m
11. 15.800 km. 15.950 km. 150.00 m
12. 16.180 km. 16.400 km. 220.00 m
13. 17.275 km. 17.550 km. 275.00 m.
14. 17.650 km. 17.850 km. 200.00 m.
15. 18.800 km. 18.900 km. 100.00 m.
16. 20.100 km. 20.300 km. 200.00 m.
17. 28.900 km. 29.000 km. 100.00 m.
18. 29.050 km. 29.300 km. 250.00 m.
19. 29.800 km. 30.000 km. 200.00 m.
20. 30.180 km. 30.450 km. 270.00 m.
21. 30.800 km. 31.000 km. 200.00 m.
22. 31.550 km. 31.750 km. 200.00 m.
23. 31.900 km. 32.000 km. 100.00 m.
24. 32.300 km. 32.500 km. 200.00 m.
25. 32.800 km. 32.950 km. 150.00 m.
26. 33.500 km. 33.700 km. 200.00 m.
27. 37.100 km. 37.175 km. 75.00 m.
Total= 5190 M

(Note:- The above locations are tentative subject to change as per site requirement)

A stretch of 5 km in suitable locations within the project stretch to be constructed


using plastic waste with bitumen in case of bituminous layers i.e DBM & BC. The
technical assistance regarding re-use of plastic in bituminous layers to be taken
either from IIT’s or NIT’s. Methodology in this regard to be adopted is as per
IRC:SP:98- 2013 and as per direction of the concerned IIT or NIT. Arrangement to
be made in such a way that overall guidance/directions would be available from the
selected IIT or NIT regarding technology, method of application, construction and
performance study during maintenance period.
No additional payment will be admissible for the whole process of reuse of plastic
as stated above. The defect liability period as well as maintenance period for the
above mentioned stretch of 5 km is to be considered same as the DLP applicable for
the rest project stretch.
Requisite display board giving details of the project shall be provided as per MORT&
H guidelines.

(ii) Type of pavement


[Refer to paragraph 5.1 of the Manual and state specific requirement, if any, of
providing cement concrete pavement.] Flexible.
The work of road items should not be continued over the bridges. The longitudinal
profile of the immediate approaches should be suitably adjusted to merge with the
road level of the bridges.
5. Hazard Locations

The safety barriers shall be provided at the following hazardous locations:

W : Metal Beam Crash Barrirer – 5090 RM(As minimum requirement)


EPC Schedules 18 CE NH, P.W.(Roads) Dte
Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Metal Beam Crash Barrier At High Embankment :-


Sl. No. From To Total Metal Crash Barrier

1. 4.700 km. 4.800 km. 100.00 m. Left side (pond)

2. 13.600 km. 13.800 km. 200.00 m. Right side (pond)

3. 14.150 km. 14.350 km. 200.00 m.x2= Both side (pond)


400.00 m

4. 21.050 km. 21.250 km. 200.00 m. Right side (pond)

5 26.780 km 26.900 km 120.00 m Left side (pond)

6 28.450 km. 28.525 km. 75.00 m Left side (pond)

7 34.550 km. 34.750 km. 200.00 m x 2 = Both side(Curve)


400.00 m
8 36.100 km. 36.300 km. 200.00 m. Right side

9 36.500 km. 36.625 km. 125.00 m. Left side

10 36.800 km. 36.900 km. 100.00 m. Left side

11 37.050 km. 37.350 km. 300.00 m x 2= Both side(Curve)


600.00 m

12 37.700 km. 37.800 km. 100.00 m x 2 Both side


=200.00 m
13 39.050 km. 39.250 km. 200.00 m Left side (pond)

14 42.300 km. 42.400 km. 100.00 m. x 2= Both side(Curve)


200.00 m
15 47.550 km. 47.775 km. 225.00 m. x2 = Both side(Curve)
450.00 m

Metal beam crush barrier For Major Bridges :-


Sl. Existing Chainage Locations
Length of crush barrier
No. (Km)
10+000
1 100 m. x 4 =400 m. 4 side of approach of bridge
(Haldi Bridge)
44+400 .
2 150 m. x 4 =600 m
(AbanSetu) 4 side of approach of bridge
Metal beam crush barrier For Minor bridges :
Sl. Existing Chainage Locations
Length of crush barrier
No. (Km)
1 0+914 20 m. x 4= 80 m. 4 side of approach of bridge
2 3+640 20 m. x 4= 80 m. 4 side of approach of bridge
3 7+538 20 m. x 4= 80 m. 4 side of approach of bridge

EPC Schedules 19 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Metal beam crush barrier For Culvert :


Sl. Existing Ch. Locations
Length of crush barrier
No. (Km)
1 12+695 20 m. x 4 = 80m. 4 side of approach of bridge
2 23+146 15 m. x 4 = 60 m. 4 side of approach of bridge
3 23+455 20 m. x 4 = 80 m. 4 side of approach of bridge
4 24+044 15 m. x 4 = 60 m. 4 side of approach of bridge
Total minimum Length of Crush barrier 5090.00 M

(Note :- The above locations are tentative subject to change as per site requirement)
6. Curves Location
The curved locations are to make safe for traffic by providing Cats eye (10000 nos), and
Chevron board (210 nos) as minimum provisions.
7. Painting of Bridges and Culverts
All Bridges and culverts within the project stretch are to be painted applying 2 coats of water
based cement paint/ synthetic enamel paint.

8. TRAFFIC CONTROL DEVICES AND ROAD SAFETY WORKS


8.1 Traffic control devices and road safety works shall be provided in accordance with
Section 9 of the Manual.

8.2 Specifications of the reflective sheeting. [Refer to paragraph 9.3 of the Manual and
specify]
9. ROADSIDE FURNITURE

(i) Roadside furniture shall be provided in accordance with the provisions of Section
11of the Manual. ( As per relevant IRC code)
Minimum provisions shall be as under: -
a. Retro-reflectorised cautionary, mandatory and informatory sign
I. Rectangular Sign Board area up to 0.9 sqm – 90 Nos
II. Rectangular Sign Board area more than 0.9sqm- 60 Nos.
III. 90 cm equilateral traingle. – 90 Nos
IV. 60 cm circular – 30 Nos.
V. Chevron (60 X 45) -210 nos
VI. Over Head Gantry- 3 nos
VII. Rumble strips – 40 locations.
b. Pavement Marker (CATS EYE) - 10000 Nos.
c. Supplying & fixing of Hazard Markers.- 100 Nos
d. W : Metal Beam Crash Barrirer – 5090 RM
e. Road Distance Indicator (5th KM post) – 10 Nos.
f. Road Distance Indicator (Ordinary KM post) – 38 Nos.
g. Road Distance Indicator (Hectometer Post) – Throughout the length.
h. Road Marking with Hot Applied Thermoplastic Compound- 17750 Sqm.

EPC Schedules 20 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(ii) Overhead traffic signs: location and size


[Refer to paragraph 11.5 of the Manual and provide details]
3 (Three) Nos over head gantry at 0.50 km, 28.00 km and 48.30 km.The locations are
tentative subject to change as per site suitability.

10. CHANGE OF SCOPE


The length of Structures and bridges specified hereinabove shall be treated as an
approximate assessment. The actual lengths as required on the basis of detailed
investigations shall be determined by the Contractor in accordance with the Specifications
and Standards. Any variations in the lengths specified in this Schedule-B shall not
constitute a Change of Scope, save and except any variations in the length arising out of a
Change of Scope expressly undertaken in accordance with the provisions of Article 13.

EPC Schedules 21 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(Schedule B-1)

1. The shifting of utilities and felling of trees shall be carried out by the
Contractor. The cost of the same shall be borne by the Authority. The details of
utilities are as follows:

Sr. Type of Utility Unit Quantity Location/stretch

No (LHS/RHS)

A Electrical Utilities NA

A1 Electrical Poles Nos. NA

A2 Electrical cables meters NA

A3 Transformers Nos. NA

- ------ -- NA

- ------- -- NA

B Water/Sewage NA

pipeline NA

B1 Sewage meters NA

B2 Water supply meters NA

- ------- -- NA

- ------- -- NA

C Felling of Tress Nos. NA

EPC Schedules 22 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

SCHEDULE – C
(See Clause 2.1)

PROJECT FACILITIES

1 Project Facilities

The Contractor shall construct the Project Facilities in accordance with the provisions of this Agreement. Such Project Facilities shall
include:

(a) roadside furniture;

(b) pedestrian facilities;

(c) tree plantation;

(d) Other to be specified

2 Description of Project Facilities

Each of the Project Facilities is described below:

S. No. Project Facility Location Design Other essential


Requirements details

As furnished below

EPC Schedules 23 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Road side Furniture-


1. Traffic Signs and Pavement Markings:
Traffic signs and pavement markings shall include roadside signs, Rectangular
Sign Board, Rectangular Sign Board area more than 0.9sqm, equilateral
triangle, 60 cm circular, overhead signs; Chevron, curve mounted signs and
road marking along the project highway. The locations for these provisions
shall be finalized in consultation with Authority Engineer.

2. Kilometer Stones/Hectometer Stones /5th Kilometer Stone


3. W metal beam Crash barrier
4. Raised Pavement Marker
5. Rumble strips
Pedestrian Facility-
Pedestrian facilities in the form of footpath shall be provided wherever required

Note: Provide adequate details of each Project Facility to ensure their design and completion in accordance with the project-specific
requirements and the provisions of the Manual.

EPC Schedules 24 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

SCHEDULE - D

(See Clause 2.1)

SPECIFICATIONS AND STANDARDS

1 Construction

The Contractor shall comply with the Specifications and Standards set forth in Annex-I of this Schedule-D for construction of the
Project Highway.

2 Design Standards

The Project Highway including Project Facilities shall conform to design requirements set out in the following documents:

a) Manual of Specifications and Standards for Two Laning of Highways (IRC: SP: 73-2015), referred to herein as the Manual, MoRTH
Specifications for Road and Bridge Works – 5th Revision and IRC: 120-2015. I.R.C.: 37 (2012), I.R.C. : 81 (1997), I.R.C. : SP : 13
(2004), I.R.C. : 35 (LATEST),I.R.C. : SP :19, I.R.C : 67 (LATEST), I.R.C :S.P : 73 (2015), STANDARD DATA BOOK (ROAD &
BRIDGE), S.O.R.(N.H.) WEST BENGAL (w.e.f 1st JUNE 2019), IRC:112-2017,IRC:SP:98-2013 and any other Specifications and
Standards as relevant with the project.

[Note: Specify the relevant Manual, Specifications and Standards]

EPC Schedules 25 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex - I
(Schedule-D)
Specifications and Standards for Construction
1. Specification and Standards

All Materials, works and construction operations shall conform to the Manual of Specifications and Standards for Two-Laning of
Highways (IRC: SP 73-2015), referred to as the Manual, MoRTH Specifications for Road and Bridge Works and IRC: 120-2015.
Where the specification for a work is not given, Good Industry Practice shall be adopted to the satisfaction of the Authority’s
Engineer.

2. Deviations from the Specifications and Standards

(i) The terms “Concessionaire”, “Independent Engineer” and “Concession Agreement” used in the Manual shall be deemed to be
substituted by the terms “Contractor”, “Authority’s Engineer” and “Agreement” respectively.
(ii) [Notwithstanding anything to the contrary contained in Paragraph 1 above, the following Specifications and Standards shall apply to
the Project Highway, and for purposes of this Agreement, the aforesaid Specifications and Standards shall be deemed to be amended
to the extent set forth below.]

[Note 1: Deviations from the aforesaid Specifications and Standards shall be listed out here. Such deviations shall be specified only
if they are considered essential in view of project-specific requirements.]

EPC Schedules 26 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule – E
(See Clause 2.1 and 14.2)

MAINTENANCE REQUIREMENTS

1. Maintenance Requirements
(i) The Contractor shall, at all time maintain the Project Highway in accordance with the provisions of this Agreement, Applicable Laws and
Applicable Permits.
(ii) The Contractor shall repair or rectify any Defect or deficiency set forth in Paragraph 2 of this Schedule-E within the time limit specified
therein and any failure in this behalf shall constitute non-fulfillment of the Maintenance obligations by the Contractor. Upon occurrence
of any breach hereunder, the Authority shall be entitled to effect reduction in monthly lump sum payment as set forth in Clause 14.6 of
this Agreement, without prejudice to the rights of the Authority under this Agreement, including Termination thereof.
(iii) All Materials, works and construction operations shall conform to the "SPECIFICATIONS FOR ROAD AND BRIDGE WORKS
(FIFTH REVISION, April 2013)”, including latest corrections slips, issued by the Ministry of Surface Transport & Highways,
Government of India and the relevant IRC publications. Where the specifications for a work are not given, Good Industry Practice shall
be adopted.

2. Repair/rectification of Defects and deficiencies


The obligations of the Contractor in respect of Maintenance Requirements shall include repair and rectification of the Defects and
deficiencies specified in Annex-I of this Schedule-E within the time limit set forth therein.

3. Other Defects and deficiencies


In respect of any Defect or deficiency not specified in Annex-I of this Schedule-E, the Authority’s Engineer may, in conformity with
Good Industry Practice, specify the permissible limit of deviation or deterioration with reference to the Specifications and Standards, and

EPC Schedules 27 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

any deviation or deterioration beyond the permissible limit shall be repaired or rectified by the Contractor within the time limit specified
by the Authority’s Engineer.

4. Extension of time limit


Notwithstanding anything to the contrary specified in this Schedule-E, if the nature and extent of any Defect or deficiency justifies more
time for its repair or rectification than the time specified herein, the Contractor shall be entitled to additional time in conformity with
Good Industry Practice. Such additional time shall be determined by the Authority’s Engineer and conveyed to the Contractor and the
Authority with reasons thereof;

5. Emergency repairs/restoration
Notwithstanding anything to the contrary contained in this Schedule-E, if any Defect, deficiency or deterioration in the Project Highway
poses a hazard to safety or risk of damage to property, the Contractor shall promptly take all reasonable measures for eliminating or
minimizing such danger.

6. Daily inspection by the Contractor


The Contractor shall, through its engineer, undertake a daily visual inspection of the Project Highway and maintain a record thereof in a
register to be kept in such form and manner as the Authority’s Engineer may specify. Such record shall be kept in safe custody of the
Contractor and shall be open to inspection by the Authority and the Authority’s Engineer at any time during office hours.

7. Pre-monsoon inspection / Post-monsoon inspection


The Contractor shall carry out a detailed pre-monsoon inspection of all bridges, culverts and drainage system before [1st June] every year
in accordance with the guidelines contained in IRC: SP:35. Report of this inspection together with details of proposed maintenance
works as required on the basis of this inspection shall be sent to the Authority’s Engineer before the [10th June] every year. The
Contractor shall complete the required repairs before the onset of the monsoon and send to the Authority’s Engineer a compliance report.
Post monsoon inspection shall be done by the [30th September] and the inspection report together with details of any damages observed
and proposed action to remedy the same shall be sent to the Authority’s Engineer.

EPC Schedules 28 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

8. Repairs on account of natural calamities


All damages occurring to the Project Highway on account of a Force Majeure Event or default or neglect of the Authority shall be
undertaken by the Authority at its own cost. The Authority may instruct the Contractor to undertake the repairs at the rates agreed
between the Parties.

EPC Schedules 29 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex – I
(Schedule-E)

Repair/rectification of Defects and deficiencies


The Contractor shall repair and rectify the Defects and deficiencies specified in this Annex-I of Schedule-E within the time limit set forth in the table below.

Table -1: Maintenance Criteria for Pavements:

Frequen Maintenanc
Time limit for
cy of Tools/Equipm Standards and References for Inspection and e
Level of Service (LOS) Rectification/Re
Inspecti ent Data Analysis Specificatio
Performa pair
on ns
nce
Paramete Acceptabl
Desirable
Asset Type r e

Flexible < 0.1 % of


Pavement area and
MORT&H
subject to
(Pavement Length IRC 82: 2015 and Distress Identification 24-48 hours Specification
limit of 10
of MCW, Measurement Manual for Long Term Pavement 3004.2
mm in
Service Potholes Unit like Scale, Performance Program, FHWA 2003
Nil depth Daily
Road, Tape, (http://www.tfhrc.com/pavement/lttp/report
approaches <5% odometer etc. s/03031/) MORT&H
of Grade subject to 7-15 days Specification
structure, limit of 3004.3
Cracking Nil Daily
approaches 0.5 sqm

EPC Schedules 30 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Frequen Maintenanc
Time limit for
cy of Tools/Equipm Standards and References for Inspection and e
Level of Service (LOS) Rectification/Re
Inspecti ent Data Analysis Specificatio
Performa pair
on ns
nce
Paramete Acceptabl
Desirable
Asset Type r e

of for any 50
connecting m length
roads, slip
roads, lay MORT&H
byes etc. as < 5 mm 15 -30 days Specification
applicable) Rutting Nil Daily Straight Edge 3004.2

Corrugation
< 0.1 % of
s and 2-7 days IRC:82-2015
area
Shoving Nil Daily
Length
MORT&H
< 1 % of Measurement
3-7 days Specification
area Unit like Scale,
Bleeding Nil Daily 3004.4
Tape,
odometer etc.
IRC:82-2015
< 1 % of
7-15 days read with IRC
Ravelling/ area
SP 81
Stripping Nil Daily

EPC Schedules 31 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Frequen Maintenanc
Time limit for
cy of Tools/Equipm Standards and References for Inspection and e
Level of Service (LOS) Rectification/Re
Inspecti ent Data Analysis Specificatio
Performa pair
on ns
nce
Paramete Acceptabl
Desirable
Asset Type r e

< 1 m for
any 100 m
section
and width
< 0.1 m at
any 7- 15 days IRC:82-2015
location,
restricted
Edge to 30 cm
Deformatio from the
n/ Breaking Nil edge Daily

Roughness 2000 2400 Bi- Class I Class I Profilometer : ASTM E950 (98) :2004 –
180 days IRC:82-2015
BI mm/km mm/km Annually Profilometer Standard Test Method for measuring
Longitudinal Profile of Travelled Surfaces with
SCRIM Accelerometer Established Inertial Profiling
Skid Bi- (Sideway- Reference BS: 7941-1:
50SN 180 days
Number 60SN Annually force ASTM E1656 -94: 2000- Standard Guide for 2006

EPC Schedules 32 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Frequen Maintenanc
Time limit for
cy of Tools/Equipm Standards and References for Inspection and e
Level of Service (LOS) Rectification/Re
Inspecti ent Data Analysis Specificatio
Performa pair
on ns
nce
Paramete Acceptabl
Desirable
Asset Type r e

Pavement Coefficient Classification of Automatic Pavement


Condition 3 2.1 Routine Condition Survey Equipment 180 days IRC:82-2015
Bi-
Index Investigation
Annually
Machine or
Other equivalent)
Pavement Bi- 2-7 days IRC:82-2015
Distresses Annually

Deflection/
Remaining Annuall Falling Weight IRC 115: 2014 180 days IRC:115-2014
Life y Deflectometer

Rigid
Bi- ASTM E950 (98) :2004 and ASTM E1656 -94: IRC:SP:83-
Pavement Roughness 2200mm/k 2400mm/ Class I 180 days
Annually 2000 2008
BI m km Profilometer
(Pavement
of MCW, Skid Resistance no. at SCRIM
Service different speed of Bi- (Sideway- IRC:SP:83-
Road, Skid vehicles force IRC:SP:83-2008 180 days
Annually 2008
Grade Coefficient
structure, Minimum Traffic Routine

EPC Schedules 33 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Frequen Maintenanc
Time limit for
cy of Tools/Equipm Standards and References for Inspection and e
Level of Service (LOS) Rectification/Re
Inspecti ent Data Analysis Specificatio
Performa pair
on ns
nce
Paramete Acceptabl
Desirable
Asset Type r e

approaches SN Speed Investigation


of (Km/h) Machine or
connecting equivalent)
roads, slip 36 50
roads, lay
33 65
byes etc. as
applicable) 32 80

31 95

31 110

MORT&H
Edge drop
Nil 40mm Daily 7-15 days Specification
at shoulders
408.4
Embankme Length
<2% IRC
nt/ Slope Slope of Measurement MORT&H
variation Unit like Scale,
camber/cr Nil in Daily 7-15 days Specification
oss fall Tape, 408.4
prescribe odometer etc.
d slope of

EPC Schedules 34 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Frequen Maintenanc
Time limit for
cy of Tools/Equipm Standards and References for Inspection and e
Level of Service (LOS) Rectification/Re
Inspecti ent Data Analysis Specificatio
Performa pair
on ns
nce
Paramete Acceptabl
Desirable
Asset Type r e

camber
/cross fall

<15 %
variation MORT&H
Embankmen
Nil in Daily 7-15 days Specification
t Slopes
prescribe 408.4
side slope

Embankmen MORT&H
Nil Nil Daily 7-15 days
t Protection NA Specification

Daily
Rain Cuts/ Specially
MORT&H
Gullies in Nil Nil During 7-15 days
Specification
slope Rainy
Season NA

EPC Schedules 35 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

In addition to the above performance criterion, the contractor shall strictly maintain the rigid pavements as per requirements in the following table

Table -2: Maintenance Criteria for Rigid Pavements:

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity For the case d < D/2 For the case d > D/2

CRACKING

0 Nil, not discernible


No Action Not applicable
1 w < 0.2 mm. hair cracks

w = 0.2 - 0.5 mm, discernible from


2 Seal, and stitch if L >
w = width of crack slow-moving car
Single Discrete Cracks Seal without delay lm.
L = length of crack
1 Not intersecting with w = 0.5 - 1.5 mm, discernible from
d = depth of crack 3 Within 7days
any joint fast-moving car
D = depth of slab
4 w = 1.5 - 3.0 mm Staple or Dowel Bar
Seal, and stitch if L > l m. Retrofit, FDR for
affected portion.
5 w > 3 mm. Within 7 days
Within 15days

2 Single Transverse (or w = width of crack 0 Nil, not discernible No Action

EPC Schedules 36 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

Diagonal) Crack L = length of crack 1 w < 0.2 mm, hair cracks Route and seal with Staple or Dowel Bar
intersecting with one d = depth of crack epoxy. Retrofit.
or more joints D = depth of slab w = 0.2 - 0.5 mm, discernible from
2
slow vehicle Within 7 days Within 15days

Route, seal and stitch, if L


w = 0.5 - 3.0 mm, discernible from > 1 m.
3
fast vehicle
Within 7 days

Dowel Bar Retrofit. Full Depth Repair


Dismantle and
4 w = 3.0 - 6.0 mm Within 15 days reconstruct affected.

Portion with norms


and specifications -
w > 6 mm, usually associated with Not Applicable, as it may See Para 5.5 & 9.2
5 spalling, and/or slab rocking under be full
Within 15days
traffic depth

w = width of crack 0 Nil, not discernible No Action


3 Single Longitudinal
L = length of crack
Crack intersecting with 1
d = depth of crack w < 0.5 mm, discernable from slow Seal with epoxy, if L > 1 Staple or dowel bar

EPC Schedules 37 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

one or more joints D = depth of slab moving vehicle m. retrofit.

Within 7 days Within 15days

Route seal and stitch, if L


w = 0.5 - 3.0 mm, discernible from > l m.
2 -
fast vehicle
Within 15 days

Staple, if L > 1 m.
3 w = 3.0 - 6.0 mm Partial Depth Repair
Within 15 days with stapling.

w = 6.0 - 12.0 mm, usually associated Within 15 days


4
with spalling
Not Applicable, as it may
be full Full Depth Repair
w > 12 mm, usually associated with Dismantle and
5 spalling, and/or slab rocking under depth reconstruct affected
traffic portion as per norms
and specifications -

EPC Schedules 38 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

See Para 5.6.4

Within 15 days

0 Nil, not discernible No Action

1 w < 0.2 mm, hair cracks


Seal, and stitch if L > l m. -
w = 0.2 - 0.5 mm. discernible from
2 Within 15 days
slow vehicle
Multiple Cracks
4 intersecting with one w = width of crack w = 0.5 - 3.0 mm, discernible from
3
or more joints fast vehicle Dismantle, Reinstate
subbase, Reconstruct
w = 3.0 - 6.0 mm panel broken into 2 Full depth repair within
4 whole slab as per
or 3 pieces 15 days
specifications within
w > 6 mm and/or panel broken into 30 days
5
more than 4 pieces

0 Nil, not discernible No Action -


w = width of crack
5 Corner Break 1 w < 0.5 mm; only 1 corner broken Seal with low viscosity Seal with epoxy seal
L = length of crack
epoxy to with epoxy
2 w < 1.5 mm; L < 0.6 m, only one

EPC Schedules 39 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

corner broken secure broken parts Within 7days

Within 7 days

w < 1.5 mm; L < 0.6 m, two corners


3
broken
Full depth repair
w > 1.5 mm; L > 0.6 m or three Partial Depth (Refer
4 Figure 8.3 of
corners broken

IRC:SP: 83-2008) Reinstate sub-base,


and reconstruct the
Within 15 days
5 three or four corners broken slab as per norms and
specifications within
30days

0 Nil, not discernible No Action

Punchout (Applicable 1 w < 0.5 mm; L < 3 m/m2 Seal with low
to Continuous w = width of crack viscosity epoxy to
6 2 either w > 0.5 mm or L < 3 m/m2
Reinforced Concrete L = length (m/m2) Not Applicable, as it may secure broken parts.
Pavement (CRCP) only) 3 w > 1.5 mm and L < 3 m/m2 be full depth
Within 15days

4 w > 3 mm, L < 3 m/m2 and Full depth repair - Cut

EPC Schedules 40 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

deformation out and replace


damaged area taking
care not to damage
w > 3 mm, L > 3 m/m2 and reinforcement.
5
deformation
Within 30days

Surface Defects

Short Term Long Term


0 Nil, not discernible
No action.

1 r<2% Local repair of areas


damaged
r = area damaged
Ravelling or surface/total surface and liable to be damaged.
2 r = 2 - 10 %
7 Honeycomb type of slab (%) h =
surface maximum depth of Within 15 days Not Applicable
damage
3 r = 10-25% Bonded Inlay, 2 or 3 slabs
if

4 r = 25 - 50 % affecting.

Within 30 days

EPC Schedules 41 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

Reconstruct slabs, 4 or
5 r > 50% and h > 25 mm more slabs if affecting.

Within 30 days

Short Term Long Term


0 Nil, not discernible
No action.

1 r<2% Local repair of areas


damaged
r = damaged
surface/total surface and liable to be damaged.
2 r = 2 - 10 %
8 Scaling of slab (%)
h = maximum depth Within 7days Not Applicable
of damage
3 r = 10 - 20% Bonded Inlay within 15
days
4 r = 20 - 30 %

Reconstruct slab within 30


5 r > 30 % and h > 25 mm
days

Polished t = texture depth, 0


9 No action. Not Applicable
Surface/Glazing sand patch test 1 t > 1 mm

EPC Schedules 42 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

2' t = 1 - 0.6 mm
Monitor rate of
3 t = 0.6 - 0.3 mm
deterioration
4 t = 0.3 - 0.1 mm

Diamond Grinding if
affecting

50% or more slabs in a

5 t < 0.1 mm continuous stretch of


minimum

5 km.

Within 30 days

d < 50 mm; h < 25 mm; n < 1 per 5


0 No action.
m2
2
n = number/m
Popout (Small Hole),
10 d = diameter d = 50 - 100 mm; h < 50 mm; n < 1 Partial depth repair 65 mm Not Applicable
Pothole Refer Para 8.4 1
h = maximum depth per 5 m2 deep.

2 d = 50 - 100 mm; h > 50 mm; n < 1 Within 15 days

EPC Schedules 43 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Repair Action
Measured Degree of
S.No. Type of Distress Assessment Rating
Parameter Severity
For the case d < D/2 For the case d > D/2

per 5 m2

d = 100 - 300 mm; h < 100 mm n < 1 Partial depth repair


3
per 5 m2 110mm

i.e.10 mm more than the


depth
d = 100 - 300 mm; h > 100 mm; n < 1
4
per 5 m2 of the hole.

Within 30 days

d > 300 mm; h > 100 mm: n > 1 per 5 Full depth repair.
5
m2 Within 30 days

EPC Schedules 44 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Joint Defects

Short Term Long Term


0 Difficult to discern.
No action.

Discernible, L< 25% but of


little immediate
consequence with regard
1 Clean joint, inspect later.
to ingress of water or
trapping incompressible
material.
loss or damage
11 Joint Seal Defects L = Length as % total Notable. L > 25% Clean and reapply sealant in Not Applicable
joint length insufficient protection
3 against ingress of water selected locations.
and trapping
incompressible material. Within 7 days

Severe; w > 3 mm
negligible protection Clean, widen and reseal the joint.
5 against ingress of water
and trapping Within 7 days
incompressible material.

12 Spalling of Joints w = width on either 0 Nil, not discernible No action. Not Applicable

EPC Schedules 45 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

side of the joint L = 1 w < 10 mm Apply low viscosity epoxy resin/


length of spalled mortar in cracked portion.
portion (as % joint 2 w = 10 - 20 mm, L < 25%
length) Within 7 days

Partial Depth Repair.


3 w = 20 - 40 mm, L > 25%
Within 15 days

30 - 50 mm deep, h = w + 20% of
4 w = 40 - 80 mm, L > 25%
w, within 30 days

50 - 100 mm deep repair.

5 w > 80 mm, and L > 25% H = w + 20% of w.

Within 30 days

0 not discernible, < 1 mm No action.


No action.
1 f < 3 mm

Faulting (or Stepping) in Determine cause and observe, take Replace the slab as
13 f = difference of level 2 f = 3 - 6 mm
Cracks or Joints action for diamond grinding appropriate.

3 f = 6 - 12 mm Diamond Grinding Within 30days

4 f= 12 - 18 mm Raise sunken slab. Replace the slab as

EPC Schedules 46 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Strengthen subgrade and sub-base appropriate.


5 f> 18 mm by grouting and
Within 30days
raising sunken slab

Short Term Long Term


0 Nil, not discernible

No Action
1 h < 6 mm

h = vertical 2 h = 6 - 12 mm Install Signs to Warn Traffic


14 Blowup or Buckling displacement from
3 h = 12 - 25 mm within 7 days
normal profile
Full Depth Repair.
4 h > 25 mm
Within 30 days

shattered slabs, ie 4 or Replace broken slabs.


5
more pieces Within 30 days

0 Not discernible, h < 5 mm


h = negative vertical No action.
displacement from 1 h = 5 - 15 mm
15 Depression Not Applicable
normal profile L
=length h = 15-30 mm, Nos <20%
2 Install Signs to Warn Traffic
joints

EPC Schedules 47 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

3 h = 30 - 50 mm within 7 days

4 h > 50 mm or > 20% joints Strengthen subgrade.

Reinstate pavement at normal level


if L < 20 m.
5 h > 100 mm
Within 30 days

Not discernible. h < 5 Short Term Long Term


0
mm No action.

1 h = 5 - 15 mm Follow up.
h = positive vertical
displacement from h = 15 - 30 mm, Nos
2 Install Signs to Warn Traffic
16 Heave normal profile. <20% joints
within 7 days scrabble
L = length 3 h = 30 - 50 mm

h > 50 mm or > 20% Stabilise subgrade. Reinstate


4
joints pavement at normal level if length <
5 h > 100 mm 20 m. Within 30 days

0 h < 4 mm No action
h = vertical
17 Bump displacement from Grind, in case of new construction Construction Limit
normal profile 1 h = 4 - 7 mm for New
within 7 days Construction.

EPC Schedules 48 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Grind, in case of ongoing Replace in case of


3 h = 7 - 15 mm Maintenance new construction.

within 15 days Within 30days

Full Depth Repair. Full Depth Repair.


5 h > 15 mm
Within 30 days Within 30days

Nil, not discernible Short Term Long Term


0
< 3mm No action.

1 f = 3 - 10 mm Spot repair of shoulder

2 f = 10 - 25 mm within 7 days

f = difference of 3 f = 25 - 50 mm
18 Lane to Shoulder Dropoff
level
4 f = 50 - 75 mm For any 100 m
Fill up shoulder stretch Reconstruct
shoulder, if
within 7 dayss affecting 25% or
5 f > 75 mm more of stretch.

Within 30days

Drainage

19 Pumping quantity of fines 0 not discernible No Action

EPC Schedules 49 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

and water expelled slight/ occasional Nos < Repair cracks and joints Without Inspect and repair
1 to 2
through open joints 10% delay. sub-drainage at
and cracks Nos distressed sections
appreciable/ Frequent 10
3 to 4 Lift or jack slab within 30 days. and upstream.
- 25%

Repair distressed pavement


abundant, crack sections. Strengthen subgrade and
Nos/100 m stretch 5 subbase. Replace slab.
development > 25%
Within 30 days

0-2 No discernible problem No action.

Blockages observed in
Ponding on slabs Clean drains etc within 7 days, Action required to
3 to 4 drains, but water
20 Ponding due to blockage of Follow up
flowing stop water damaging
drains foundation within 30
Ponding, accumulation days.
5 -do-
of water observed

EPC Schedules 50 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Table -3: Maintenance Criteria for Safety Related Items and Other Furniture Items:

Asset Performance Level of Service (LOS) Frequency Testing Recommended Time limit for Specificatio
Type Parameter of Method Remedial Rectification ns and
Measureme measures Standards
nt
Highwa Availability As per IRC SP :84-2014, a minimum Monthly Manual Removal of obstruction within 24 IRC:SP
y of Safe of safe stopping sight distance shall Measureme hours, in case of sight line affected 84-2014
Sight be available throughout. nts with by temporary objects such as trees,
Distance Odometer
temporary encroachments.
Safe along with
Desirable
Design Stoppin video/ In case of permanent structure or
Minimum
Speed, g Sight image
Sight Distance design deficiency:
kmph Distanc backup
(m) Removal of
e (m)
obstruction/improvement of
100 360 180 deficiency at the earliest
Speed Restriction boards
80 260 130 and suitable traffic calming
measures such as transverse bar
marking, blinkers, etc. shall be
applied during the period of
rectification.

Paveme Wear <70% of marking remaining Bi- Visual Re - painting Cat-1 Defect – IRC:35-
nt Annually Assessment within 24 hours 2015
Marking as per Cat-2 Defect -
Annexure-F of within 2 months
IRC:35-2015

EPC Schedules 51 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Day time During expected life Service Time Monthly As per Re - painting Cat-1 Defect – IRC:35-
Visibility Cement Road - Annexure-D within 24 hours 2015
130mcd/m2/lux of IRC:35- Cat-2 Defect –
Bituminous Road - 2015 within 2
100mcd/m2/lux months
Night Time Initial and Minimum Performance Bi-Annually As per Re - painting Cat-1 Defect – IRC:35-2015
Visibility for Dry Retro reflectivity during Annexure-E of within 24 hours
night time: IRC:35-2015 Cat-2 Defect –
Design (RL) Retro within 2
Speed Reflectivity months
(mcd/m2/lux)

Initial (7 Minimum
days) Threshold level
(TL) & warranty
period required
up to 2 years

Up to 65 200 80

65 - 100 250 120

Above 350 150


100
Initial and Minimum Performance for
Night Visibility under wet condition
(Retro reflectivity):
Initial 7 days Retro reflectivity: 100
mcd/m2/lux
Minimum Threshold Level: 50
mcd/m2/lux

EPC Schedules 52 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Skid Initial and Minimum performance Bi-Annually As per Within 24 hours IRC:35-2015
Resistance for Skid Resistance: Annexure-G
Initial (7days): 55BPN of IRC:35-
Min. Threshold: 44BPN 2015
*Note: shall be considered under
urban/city traffic condition
encompassing the locations like
pedestrian crossings, bus bay, bus
stop, cycle track intersection
delineation, transverse bar markings
etc
Road Shape and Shape and Position as per IRC:67- Daily Visual with Improvement IRC:67-2012
Signs Position 2012. video/image of shape, in 48 hours in case
Signboard should be clearly visible for backup case if shape is of Mandatory
the design speed of the section. damaged. Signs,
Cautionary and
Relocation as Informatory
per Signs (Single
requirement and Dual post
signs)

15 Days in case
of
Gantry/Cantilev
er Sign boards
Retro As per specifications in IRC:67-2012 Bi-Annually Testing of Change of 48 hours in case IRC:67-2012
reflectivity each signboard of Mandatory
signboard Signs,
using Retro Cautionary and
Reflectivity Informatory
Measuring Signs (Single
Device. In and Dual post

EPC Schedules 53 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

accordance signs)
with ASTM D
4956-09. 1 Month in case
of
Gantry/Cantilev
er Sign boards
Kerb Kerb Height As per IRC 86:1983 depending upon Bi- Use of distance Raising Kerb Within 1 Month IRC 86:1983
type of Kerb Annually measuring Height
tape
Kerb Painting Functionality: Functioning of Kerb Daily Visual with Kerb Repainting Within 7-days IRC 35:2015
painting as intended video/image
backup
Other Reflective Numbers and Functionality as per Daily Counting New Installation Within 2 months IRC:SP:84-
Road Pavement specifications in IRC:SP:84-2014 and 2014,
Furnitur Markers IRC:35-2015, unless specified in IRC:35-2015
e (Road Studs) Schedule-B.
Pedestrian Functionality: Functioning of guardrail Daily Visual with Rectification Within 15 days IRC:SP:84-
Guardrail as intended video/image 2014
backup
Traffic Safety Functionality: Functioning of Safety Daily Visual with Rectification Within 7 days IRC:SP:84-
Barriers Barriers as intended video/image 2014,
backup IRC:119-
2015
End Functionality: Functioning of End Daily Visual with Rectification Within 7 days IRC:SP:84-
Treatment of Treatment as intended video/image 2014,
Traffic Safety backup IRC:119-
Barriers 2015
Attenuators Functionality: Functioning of Daily Visual with Rectification Within 7 days IRC:SP-
Attenuators as intended video/image 2014,
backup IRC:119-
2015

EPC Schedules 54 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Guard Posts Functionality: Functioning of Guard Daily Visual with Rectification Within 15 days IRC: 79 -
and Posts and Delineators as intended video/image 1981
Delineators backup
Overhead Overhead sign structure shall be Daily Visual with Rectification Within 15 days IRC:67-2012
Sign structurally adequate video/image
Structure backup
Traffic Functionality: Functioning of Traffic Daily Visual with Rectification Within 7 days IRC:SP:84-
Blinkers Blinkers as intended video/image 2014
backup
Highwa Highway Illumination: Daily The Improvement 24 hours IRC:SP:84-
y Lights Minimum 40 Lux illumination on the illumination in Lighting 2014
Lighting road surface level shall be System
System measured with
luxmeter
No major failure in the lighting system Daily - Rectification of 24 hours IRC:SP:84-
failure 2014
No minor failure in the lighting system Monthly - Rectification of 8 hours IRC:SP:84-
failure 2014
Toll Plaza Minimum 40 Lux illumination on the Daily The Improvement 24 hours IRC:SP:84-
Canopy road surface illumination in Lighting 2014
Lights level shall be System
measured
with luxmeter
No major/minor failure in the lighting Daily - Rectification of 8 hours IRC:SP:84-
system failure 2014

EPC Schedules 55 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Trees Obstruction No obstruction due to trees Monthly Visual with Removal of trees Immediate IRC:SP:84-
and in a video/image 2014
Plantati minimum backup
on head-room
includin of 5.5 m
g above
median carriageway
plantati or
on obstruction
in visibility
of road signs
Deterioratio Health of plantation shall be as per Daily Visual with Timely Within 90 days IRC:SP:84-
n in health requirement of specifications & video/image watering and 2014
of trees and instructions issued by Authority from backup treatment. Or
time to time Replacement of
bushes
Trees and
Bushes.
Vegetation Sight line shall be free from Daily Visual with Removal of Trees Immediate IRC:SP 84-
affecting obstruction by vegetation video/image 2014
sight line backup
and road
structures
Rest Cleaning of - Daily - - Every 4 hours
Areas toilets
Defects in - Daily - Rectification 24 hours
electrical,
water and
sanitary

EPC Schedules 56 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

installations

Other Damage or deterioration in Approach Roads, Daily - Rectification 15 days IRC:SP 84-
Project pedestrian facilities, truck lay-bys, bus-bays, bus- 2014
Facilitie shelters, cattle crossings, Traffic Aid Posts, Medical
s and Aid Posts and other works
Approa
ch
roads

EPC Schedules 57 CE NH, P.W.(Roads) Dte


Asset Type Performanc Level of Service Frequency of Testing Method Recommended Remedial Time limit Specifications
e (LOS) Measuremen measures for and
Stage Strengtheningof theParameter
existing pavement from 0.00 Kmp to 49.00 kmp of NH-t 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in theRectification Standards
district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441
Pipe/box/slab Free 85% of culvert 2 times in a Inspection by Bridge Cleaning silt up soils and 15 days IRC 5-2015,
culverts waterway/ normal flow area year (before Engineer as per IRC debris in culvert barrel before IRC SP:40-
unobstruct to available. and after SP: 35-1990 and after rainy season, removal onset of 1993 and
ed flow rainy recording of depth of bushes and vegetation, monsoon IRC SP:13-
section season) of silting and area of U/s of barrel, under barrel and within 2004
vegetation. and D/s of barrel before 30 days
rainy season. after end of
rainy
season.
Leak- No leakage Bi-Annually Physical inspection Fixing with sealant 30 days or IRC SP:40-
proof through of expansion joints suitably before 1993 and
expansio expansion joints as per IRC SP: 35- onset of IRC SP:69-
n joints if 1990 if any, for rains 2011
any leakage strains on whichever
walls at joints. comes
earlier
Structural Spalling of Bi-Annually Detailed inspection Repairs to spalling, 15 days IRC SP 40-
ly sound concrete not of all components cracking, delamination, 1993 and
more than 0.25 of culvert as per rusting shall be followed MORTH
sqm IRC SP:35-1990 and as per IRC:SP:40-1993. Specificatio
recording the ns clause
Delamination of defects 2800
concrete not
more than 0.25
sq.m.

EPC Schedules 58 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Cracks wider
than 0.3 mm
not more than
1m aggregate
length

Protection Damaged of 2 times in Condition survey as Repairs to damaged 30 days IRC: SP 40-
works in rough stone a year per IRC SP:35-1990 aprons and pitching after 1993 and
good apron or bank (before and defect IRC:SP:13-
condition revetment not after rainy observatio 2004.
more than 3 season) n or 2
sqm, damage to weeks
solid apron before
(concrete apron) onset of
not more than 1 rainy
sqm season
whichever
is earlier.
Bridges Riding No pothole in Daily Visual inspection as Repairs to BC or wearing 15 days MORT&H
including ROBs quality or wearing coat on per IRC SP:35-1990 coat Specificatio
Flyover etc. as user bridge deck n 2811
applicable comfort

EPC Schedules 59 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Bridge -Super Bumps No bump at Daily Visual inspection Repairs to BC on either 15 days MORT&H
Structure expansion joint as per IRC SP:35- side of expansion joints, Specificatio
1990 profile correction course n 3004.2 &
on approach slab in case 2811.
of settlement to
approach embankment
User No damaged or Daily Visual inspection Repairs and replacement 3days IRC: 5-
safety missing stretch and detailed of safety barriers as the 1998, IRC
(conditio of crash barrier condition survey as case may be SP: 84-
n of or pedestrian per IRC SP: 35- 2014 and
crash hand railing 1990. IRC SP: 40-
barrier 1993.
and
guard
rail)
Rusted Not more than Bi- Detailed condition All the corroded 15 days IRC SP:
reinforce 0.25 sq.m Annually survey as per IRC reinforcement shall need 40-1993
ment SP: 35-1990 using to be thoroughly cleaned and
Spalling Not more than Mobile Bridge from rusting and applied MORTH
of 0.50 sq.m Inspection Unit with anti-corrosive Specificati
concrete coating before carrying on 1600.
Delaminati Not more than out the repairs to affected
on 0.50 sq.m concrete portion with
epoxy mortar / concrete.

EPC Schedules 60 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Cracks Not more than Bi-Annually Detailed condition Grouting with epoxy 48 Hours IRC SP: 40-
wider 1m total length survey as per IRC mortar, investigating 1993 and
than 0.30 SP: 35-1990 using causes for cracks MORTH
mm Mobile Bridge development and carry Specificatio
Inspection Unit out necessary n 2800.
rehabilitation.
Rainwate Leakage - nil Quarterly Detailed condition Grouting of deck slab at 1 months MORTH
r seepage survey as per IRC leakage areas, specification
through SP: 35-1990 using waterproofing, repairs to s 2600 &
deck slab Mobile Bridge drainage spouts 2700.
Inspection Unit

Deflectio Within design Once in Load test method Carry out major 6 months IRC SP: 51-
n due to limits. every 10 rehabilitation works on 1999.
permane years for bridge to retain original
nt loads spans more design loads capacity
and live than 40 m
loads

Vibrations Frequency of Once in Laser displacement Strengthening of super 4 months AASHTO


in bridge vibrations shall every 5 sensors or laser structure LRFD
deck due not be more years for vibro-meters specification
to moving than 5 Hz spans more s
trucks than 30m
and every
10 years for

EPC Schedules 61 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

spans
between 15
to 30 m

Leakage in No damage to Bi-Annually Detailed condition Replace of seal in 15 days MORTH


Expansion elastomeric survey as per IRC expansion joint specification
joints sealant SP:35-1990 using s 2600 and
compound in Mobile Bridge IRC SP: 40-
strip seal Inspection Unit 1993.
expansion joint,
no leakage of
rain water
through
expansion joint
in case of buried
and asphalt plug
and copper strip
joint.
Debris No dust or Monthly Detailed condition Cleaning of expansion 3 days MORTH
and dust debris in survey as per IRC joint gaps thoroughly specificatio
in strip expansion joint SP:35-1990 using ns 2600 and
seal gap. Mobile Bridge IRC SP: 40-
expansio Inspection Unit 1993.
n joint
Drainage No down take Monthly Detailed condition Cleaning of drainage 3 days MORTH
spouts pipe survey as per IRC spouts thoroughly. specificatio
missing/broken SP: 35-1990 using Replacement of n 2700.

EPC Schedules 62 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

below soffit of Mobile Bridge missing/broken down


the deck slab. Inspection Unit take pipes with a
No silt, debris, minimum pipe extension
clogging of of 500mm below soffit of
drainage spout slab. Providing sealant
collection around the drainage
chamber. spout if any leakages
observed.
Bridge- Cracks/s No cracks, Bi- Detailed condition All the corroded 30 days IRC SP: 40-
substructure palling spalling of Annually survey as per IRC reinforcement shall need 1993 and
of concrete and SP: 35-1990 using to be thoroughly cleaned MORTH
concrete rusted steel Mobile Bridge from rusting and applied specificatio
/rusted Inspection Unit with anti-corrosive n 2800.
steel coating before carrying
out repairs to
substructure by
grouting/guniting and
micro concreting
depending on type of
defect noticed

EPC Schedules 63 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Bearings Delamination of Bi- Detailed condition In case of failure of even 3 months MORTH
bearing Annually survey as per IRC one bearing on any specificatio
reinforcement SP: 35-1990 using pier/abutment, all the n 2810 and
not more than Mobile Bridge bearings on that IRC SP: 40-
5%, cracking or Inspection Unit pier/abutment shall be 199.
tearing of replaced, in order to get
rubber not uniform load transfer on
more than 2 to bearings.
locations per
side, no rupture
of
reinforcement
or rubber
Bridge Scouring Scouring shall Bi- Condition survey Suitable protection 1 month IRC SP: 40-
Foundations around not be lower Annually and visual works around 1993, IRC
foundati than maximum inspection as per pier/abutment 83-2014,
ons scour level for IRC SP:35-1990 MORTH
the bridge using Mobile specificatio
Bridge Inspection n 2500
Unit.
In case of doubt,
use Underwater
camera for
inspection of
deep wells in
major Rivers.

EPC Schedules 64 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum
,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Protecti Damaged of 2 times Condition survey Repairs to damaged


30 days IRC: SP 40-
on rough stone in a year as per IRC SP:35- aprons and pitching.
after 1993 and
works in apron or bank (before 1990 defect IRC:SP:13-
good revetment not and after observati 2004.
conditio more than 3 rainy on or 2
n sq.m, damage season) weeks
to solid apron before
(concrete onset of
apron) not rainy
more than 1 season
sq.m whicheve
r is
earlier.
Note: Any Structure during the entire contract period which is found that does not complies with all requirements of this Table will be prepared,
rehabilitated or even reconstructed under the scope of the contractor.

Table 4: Maintenance Criteria for Structures and Culverts:

EPC Schedules 65 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Table 5: Maintenance Criteria for Hill Roads

In addition to above, for hill roads the following provisions for maintenance is also to done.

Hill Roads

(i) Damage to Retaining wall/ Breast wall 7 (Seven) days

(ii) Landslides requiring clearance 12 (Twelve) hours

(iii) Snow requiring clearance 24 (Twenty Four) hours

Note: For all tables 1 to 5 above, latest BIS & IRC standards (even those not indicated herewith)
along with MoRTH specifications shall be binding for all maintenance activities.

EPC Schedules 66 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

A. Flexible Pavement

Nature of Defect or deficiency Time limit for repair/


rectification

(b) Granular earth shoulders, side slopes, drains and culverts

(i) Variation by more than 1 % in the prescribed slope 7 (seven) days


of camber/cross fall (shall not be less than the
camber on the main carriageway)

(ii) Edge drop at shoulders exceeding 40 mm 7 (seven) days

(iii) Variation by more than 15% in the prescribed side 30 (thirty) days
(embankment) slopes

(iv) Rain cuts/gullies in slope 7 (seven) days

(v) Damage to or silting of culverts and side drains 7 (seven) days

(vi) Desilting of drains in urban/semi- urban areas 24 (twenty four) hours

(vii) Railing, parapets, crash barriers 7 (seven) days (Restore


immediately if causing safety
hazard)

(c) Road side furniture including road sign and pavement marking

(i) Damage to shape or position, poor visibility or loss 48 (forty eight) hours
of retro- reflectivity

(ii) Painting of km stone, railing, parapets, crash As and when required/ Once
barriers every year

(iii) Damaged/missing signs road requiring 7 (seven) days


replacement

(iv) Damage to road mark ups 7 (seven) days

(d) Road lighting

(i) Any major failure of the system 24 (twenty four) hours

(ii) Faults and minor failures 8 (eight) hours

(e) Trees and plantation

EPC Schedules 67 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Nature of Defect or deficiency Time limit for repair/


rectification

(i) Obstruction in a minimum head- room of 5 m 24 (twenty four)hours


above carriageway or obstruction in visibility of
road signs

(ii) Removal of fallen trees from carriageway 4 (four) hours

(iii) Deterioration in health of trees and bushes Timely watering and treatment

(iv) Trees and bushes requiring replacement 30 (thirty) days

(v) Removal of vegetation affecting sight line and road 15 (fifteen) days
structures

(f) Rest area

(i) Cleaning of toilets Every 4 (four) hours

(ii) Defects in electrical, water and sanitary 24 (twenty four) hours


installations

(g) [Toll Plaza]

(h) Other Project Facilities and Approach


roads

(i) Damage in approach roads, pedestrian facilities, 15 (fifteen) days


truck lay- byes, bus-bays, bus-shelters, cattle
crossings, [Traffic Aid Posts, Medical Aid Posts] and
service roads

(ii) Damaged vehicles or debris on the road 4 (four) hours

(iii) Malfunctioning of the mobile crane 4 (four) hours

Bridges

(a) Superstructure

(i) Any damage, cracks, spalling/ scaling within 48 (forty eight) hours
Temporary measures within 15 (fifteen) days or as
specified by the Authority’s
Permanent measures
Engineer

(b) Foundations

EPC Schedules 68 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Nature of Defect or deficiency Time limit for repair/


rectification

(i) Scouring and/or cavitation 15 (fifteen) days

(c) Piers, abutments, return walls and wing walls

(i) Cracks and damages including settlement and 30 (thirty) days


tilting, spalling, scaling

(d) Bearings (metallic) of bridges

(i) Deformation, damages, tilting or shifting of 15 (fifteen) days Greasing


bearings of metallic bearings once in
a year

(e) Joints

(i) Malfunctioning of joints 15 (fifteen) days

(f) Other items

(i) Deforming of pads in elastomeric bearings 7 (seven) days

(ii) Gathering of dirt in bearings and joints; or clogging 3 (three) days


of spouts, weep holes and vent-holes

(iii) Damage or deterioration in kerbs, parapets, 3 (three) days (immediately


handrails and crash barriers within 24 hours if posing
danger to safety)

(iv) Rain-cuts or erosion of banks of the side slopes of 7 (seven) days


approaches

(v) Damage to wearing coat 15 (fifteen) days

(vi) Damage or deterioration in approach slabs, 30 (thirty) days


pitching, apron, toes, floor or guide bunds

(vii) Growth of vegetation affecting the structure or 15 (fifteen) days


obstructing the waterway

(g) Hill Roads

(i) Damage to retaining wall/breast wall 7 (seven) days

(ii) Landslides requiring clearance 12 (twelve) hours

(iii) Snow requiring clearance 24 (twenty four) hours

EPC Schedules 69 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

[Note: Where necessary, the Authority may modify the time limit for repair/rectification, or add to
the nature of Defect or deficiency before issuing the bidding document, with the approval of
the competent authority.]

EPC Schedules 70 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-F
(See Clause 3.1.5(a))

APPLICABLE PERMITS

1. Applicable Permits
(i) The Contractor shall obtain, as required under the Applicable Laws, the following
Applicable Permits:

(a) Permission of the State Government for extraction of boulders from quarry;

(b) Permission of Village Panchayat and Pollution Control Board for installation of
crushers;

(c) License for use of explosives;

(d) Permission of the State Government for drawing water from river/reservoir;

(e) License from inspector of factories or other competent Authority for setting up
batching plant;

(f) Clearance of Pollution Control Board for setting up batching plant;

(g) Clearance of Village Panchayats and Pollution Control Board for setting up
asphalt plant;

(h) Permission of Village Panchayats and State Government for borrow earth;

(i) Applicable clearances from RTO, PESO ( Petroleum Explosive Safety


Organization) and PCB (Pollution Control Board) for movement and operation of
HIPR train and

(j) Any other permits, clearances or approvals required under Applicable Laws.

(ii) Applicable permits, as required, relating to environmental protection and conservation


shall have been produced by the Authority in accordance with the provisions of this
Agreement.

EPC Schedules 71 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-G

(See Clause 7.1 and 19.2)


Annex-I
(See Clause 7.1)

FORM OF BANK GUARANTEE


[Performance Security / Additional Performance Security]
Chief Engineer
National Highway
P.W.(Roads) Directorate,
West Bengal

WHEREAS:

___________________ [name and address of contractor] (hereinafter called the


“Contractor”) and the Chief Engineer, National Highway, P.W.(Roads) Directorate,
Government of West Bengal represented through the Superintending Engineer, N. H.
Circle No. II, P. W. (Roads) Directorate, Sadak Bhawan, Lambodarpur, Suri,
Birbhum,, (hereinafter called the “Authority”) have entered into an agreement (hereinafter
called the “Agreement”) for “Stage Strengthening of the existing pavement from 0.00 Kmp
to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the
year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal, in EPC mode Job
No. 2B-WB-2019-20/441 “ subject to and in accordance with the provisions of the
Agreement.

(A) The Agreement requires the Contractor to furnish a Performance Security for
due and faithful performance of its obligations, under and in accordance with
the Agreement, during the {Construction Period / Defects Liability Period and
Maintenance Period} (as defined in the Agreement) in a sum of Rs. …. Crore
(Rupees …. Crore) (the “Guarantee Amount”).

(B) We, ……………..through our branch at …………………………. (the


“Bank”) have agreed to furnish this bank guarantee (hereinafter called the
“Guarantee”) by way of Performance Security.

NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and
affirms as follows:

1. The Bank hereby unconditionally and irrevocably guarantees the due and
faithful performance of the Contractor’s obligations during the {Construction
Period / Defects Liability Period and Maintenance Period} under and in
accordance with the Agreement, and agrees and undertakes to pay to the
Authority, upon its mere first written demand, and without any demur,
reservation, recourse, contest or protest, and without any reference to the
Contractor, such sum or sums up to an aggregate sum of the guarantee amount
as the Authority shall claim, without the Authority being required to prove or

EPC Schedules 72 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

to show grounds or reasons for its demand and/or for the sum specified
therein.

2. A letter from the Authority, under the hand of an officer not below the rank of
[Executive Engineer, PWD], that the Contractor has committed default in the due
and faithful performance of all or any of its obligations under and in accordance
with the Agreement shall be conclusive, final and binding on the Bank. The Bank
further agrees that the Authority shall be the sole judge as to whether the Contractor
is in default in due and faithful performance of its obligations during and under the
Agreement and its decision that the Contractor is in default shall be final, and
binding on the Bank, notwithstanding any differences between the Authority and the
Contractor, or any dispute between them pending before any court, tribunal,
arbitrators or any other Authority or body, or by the discharge of the Contractor for
any reason whatsoever.

3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if
the Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.

4. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.

5. The Authority shall have the liberty, without affecting in any manner the liability of
the Bank under this Guarantee, to vary at any time, the terms and conditions of the
Agreement or to extend the time or period for the compliance with, fulfillment
and/or performance of all or any of the obligations of the Contractor contained in
the Agreement or to postpone for any time, and from time to time, any of the rights
and powers exercisable by the Authority against the Contractor, and either to
enforce or forbear from enforcing any of the terms and conditions contained in the
Agreement and/or the securities available to the Authority, and the Bank shall not
be released from its liability and obligation under these presents by any exercise by
the Authority of the liberty with reference to the matters aforesaid or by reason of
time being given to the Contractor or any other forbearance, indulgence, act or
omission on the part of the Authority or of any other matter or thing whatsoever
which under any law relating to sureties and guarantors would but for this provision
have the effect of releasing the Bank from its liability and obligation under this
Guarantee and the Bank hereby waives all of its rights under any such law.

6. This Guarantee is in addition to and not in substitution of any other guarantee or


security now or which may hereafter be held by the Authority in respect of or
relating to the Agreement or for the fulfillment, compliance and/or performance of
all or any of the obligations of the Contractor under the Agreement.

7. Notwithstanding anything contained hereinbefore, the liability of the Bank under


this Guarantee is restricted to the Guarantee amount and this Guarantee will remain
in force for the period specified in paragraph 8 below and unless a demand or claim
in writing is made by the Authority on the Bank under this Guarantee all rights of

EPC Schedules 73 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

the Authority under this Guarantee shall be forfeited and the Bank shall be relieved
from its liabilities hereunder.

8. The Guarantee shall cease to be in force and effect on ****1. Unless a demand or
claim under this Guarantee is made in writing before the expiry of the Guarantee,
the Bank shall be discharged from its liabilities hereunder.

9. The Bank undertakes not to revoke this Guarantee during its currency, except with
the previous express consent of the Authority in writing, and declares and warrants
that it has the power to issue this Guarantee and the undersigned has full powers to
do so on behalf of the Bank.

10. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have
been duly authorized to receive such notice and to effect payment thereof forthwith,
and if sent by post it shall be deemed to have been given at the time when it ought to
have been delivered in due course of post and in proving such notice, when given by
post, it shall be sufficient to prove that the envelope containing the notice was
posted and a certificate signed by an officer of the Authority that the envelope was
so posted shall be conclusive.

11. This Guarantee shall come into force with immediate effect and shall remain in
force and effect for up to the date specified in para 8 above or until it is released
earlier by the Authority pursuant to the provisions of the Agreement.

Signed and sealed this ……….. day of ………. 20…….. at ………

SIGNED, SEALED AND DELIVERED

For and on behalf of the Bank by:

(Signature)

(Name)

(Designation)

(Code Number)

(Address)

NOTES:

(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.

1
Insert a date being 2 (two) years from the date of issuance of this Guarantee (in accordance with Clause 7.2
of the agreement)

EPC Schedules 74 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(ii) The address, telephone number and other details of the head office of the Bank as well
as of issuing branch should be mentioned on the covering letter of issuing branch.

EPC Schedules 75 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex-II

(Schedule-G)

(See Clause 19.2)

Form for Guarantee for Advance Payment

Chief Engineer
National Highway
P.W.(Roads) Directorate,
West Bengal

WHEREAS:

[name and address of contractor] (hereinafter called “the Contractor”) has executed an
agreement (hereinafter called the “Agreement”) with the Chief Engineer, National
Highway, P.W.(Roads) Directorate, Government of West Bengal represented through
the Superintending Engineer, N. H. Circle No. II, P. W. (Roads) Directorate, Sadak
Bhawan, Lambodarpur, Suri, Birbhum, (“the Authority”) for “Stage Strengthening of
the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway
Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman &
Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441“. basis, subject to and in
accordance with the provisions of the agreement.

(A) in accordance with the Clause 19.2 of the Agreement the Authority shall make
to the Contractor an interest bearing @ Bank Rate + 3% advance payment
(hereinafter called “Advance Payment”) equal to 10% (ten per cent) of the
contract price and that the Advance Payment shall be made in two installments
subject to the Contractor furnishing an irrevocable and unconditional
guarantee by a scheduled bank for an amount equivalent to 110% (one
hundred and ten percent) of such installment to remain effective till the
complete and full repayment of the installment of the Advance Payment as
security for compliance with its obligations in accordance with the Agreement.
The amount of {first/second} installment of the Advance Payment is Rs. ****
cr. (Rupees ***** crore) (the “Guarantee Amount”)2.

(B) We, ……………..through our branch at …………………………. (the


“Bank”) have agreed to furnish this bank guarantee (hereinafter called the
“Guarantee”) for the Guarantee Amount.

NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and
affirms as follows:

2
Te Guarantee Amount should be equivalent to 110% of the value of the applicable instalment.

EPC Schedules 76 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful repayment
on time of the aforesaid installment of the Advance Payment under and in accordance with
the Agreement, and agrees and undertakes to pay to the Authority, upon its mere first written
demand, and without any demur, reservation, recourse, contest or protest, and without any
reference to the Contractor, such sum or sums up to an aggregate sum of the Guarantee
Amount as the Authority shall claim, without the Authority being required to prove or to
show grounds or reasons for its demand and/or for the sum specified therein.

A letter from the Authority, under the hand of an officer not below the rank of [Executive
Engineer, PWD], that the Contractor has committed default in the due and faithful
performance of all or any of its obligations for the repayment of the installment of the
Advance Payment under and in accordance with the Agreement shall be conclusive, final and
binding on the Bank. The Bank further agrees that the Authority shall be the sole judge as to
whether the Contractor is in default in due and faithful performance of its obligations during
and under the Agreement and its decision that the Contractor is in default shall be final, and
binding on the Bank, notwithstanding any differences between the Authority and the
Contractor, or any dispute between them pending before any court, tribunal, arbitrators or any
other Authority or body, or by the discharge of the Contractor for any reason whatsoever.

2. In order to give effect to this Guarantee, the Authority shall be entitled to act as if the Bank
were the principal debtor and any change in the constitution of the Contractor and/or the
Bank, whether by their absorption with any other body or corporation or otherwise, shall not
in any way or manner affect the liability or obligation of the Bank under this Guarantee.

3. It shall not be necessary, and the Bank hereby waives any necessity, for the Authority to
proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.

4. The Authority shall have the liberty, without affecting in any manner the liability of the Bank
under this Guarantee, to vary at any time, the terms and conditions of the Advance Payment
or to extend the time or period of its repayment or to postpone for any time, and from time to
time, any of the rights and powers exercisable by the Authority against the Contractor, and
either to enforce or forbear from enforcing any of the terms and conditions contained in the
Agreement and/or the securities available to the Authority, and the Bank shall not be released
from its liability and obligation under these presents by any exercise by the Authority of the
liberty with reference to the matters aforesaid or by reason of time being given to the
Contractor or any other forbearance, indulgence, act or omission on the part of the Authority
or of any other matter or thing whatsoever which under any law relating to sureties and
guarantors would but for this provision have the effect of releasing the Bank from its liability
and obligation under this Guarantee and the Bank hereby waives all of its rights under any
such law.

5. This Guarantee is in addition to and not in substitution of any other guarantee or security now
or which may hereafter be held by the Authority in respect of or relating to the Advance
Payment.

6. Notwithstanding anything contained hereinbefore, the liability of the Bank under this
Guarantee is restricted to the Guarantee amount and this Guarantee will remain in force for
the period specified in paragraph 8 below and unless a demand or claim in writing is made by
the Authority on the Bank under this Guarantee all rights of the Authority under this
Guarantee shall be forfeited and the Bank shall be relieved from its liabilities hereunder.

EPC Schedules 77 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

7. The guarantee shall cease to be in force and effect on ****3. Unless a demand or claim under
this Guarantee is made in writing on or before the afore-said date, the Bank shall be
discharged from its liabilities hereunder.

8. The Bank undertakes not to revoke this Guarantee during its currency, except with the
previous express consent of the Authority in writing, and declares and warrants that it has the
power to issue this Guarantee and the undersigned has full powers to do so on behalf of the
Bank.

9. Any notice by way of request, demand or otherwise hereunder may be sent by post addressed
to the Bank at its above referred branch, which shall be deemed to have been duly authorized
to receive such notice and to effect payment thereof forthwith, and if sent by post it shall be
deemed to have been given at the time when it ought to have been delivered in due course of
post and in proving such notice, when given by post, it shall be sufficient to prove that the
envelope containing the notice was posted and a certificate signed by an officer of the
Authority that the envelope was so posted shall be conclusive.

10. This Guarantee shall come into force with immediate effect and shall remain in force and
effect for up to the date specified in para 8 above or until it is released earlier by the
Authority pursuant to the provisions of the Agreement.

Signed and sealed this ……….. day of ………. 20…….. at ………

SIGNED, SEALED AND DELIVERED

For and on behalf of the Bank by:

(Signature)

(Name)

(Designation)

(Code Number)

(Address)

NOTES:

(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.

(ii) The address, telephone number and other details of the head office of the Bank as well
as of issuing branch should be mentioned on the covering letter of issuing branch.

3
Insert a date being 90 (ninety) days after the end of one year from the date of payment of the Advance
Payment to the Contractor (in accordance with Clause 19.2 of the Agreement)

EPC Schedules 78 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

SCHEDULE –H

(See clauses 10.1.(iv) and 19.3)


Contract Price Weightages
1.1 The Contract Price for this Agreement is Rs.
1.2 Proportions of the Contract Price for different stages of Construction of the Project
Highway shall be as specified below:

Weightage in
percentage to Percentage
Item Stage for Payment
the Contract weightage
Price
1 2 3 4
Road works 92.84 (1) Rehabilitation including dismantling 12.94
including culverts, of pavement, non-bituminous &
widening and bituminous base course, primer coat and
repair of culverts. tack coat
(2) Levelling course including tack coat 3.30
(3) Dense Bituminous Macadam including 37.35
Scarifying the existing bituminous road
surface
(4) Bituminous Concrete. 28.48
(5) Hard Shoulder including Clearing and 11.33
Grubbing Road Land
(6) Mastic including dismantling of 6.60
concrete wearing course of Ajay Bridge

(1) Road marking


31.29
(2) W Metal beam crush barrier
44.57
(3) Over head Gantry
4.37
Other works 7.16
(4) Cats eye, 90 cm equilateral traingle,60
cm circular, Chevron, Direction and
Place Identification Sign Board, Hazard
19.77
Markers,5th KM post, Ordinary KM
post, Hectometer Post, Rumble strips,
Painting of Bridges and culverts etc.

1.3 Procedure of estimating the value of work done


1.3.1 Road works.
Procedure for estimating the value of road work done shall be as follows:

EPC Schedules 79 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Table 1.3.1
Percentage Payment procedure
Stage for Payment
weightage
Rehabilitation including dismantling 12.94 Unit of measurement is linear length.
of pavement, non-bituminous & Payment of each stage shall be made on
bituminous base course, primer coat pro rata basis on completion of a stage in
and tack coat
a length of not less than 20 (Twenty)
percent of the project length.

Levelling course including tack coat 3.30


Unit of measurement is linear length.
Dense Bituminous Macadam 37.35 Payment of each stage shall be made on
including Scarifying the existing
bituminous road surface pro rata basis on completion of a stage in
Bituminous Concrete. 28.48 a length of not less than 10 (Ten) percent
of the project length.
Hard Shoulder including Clearing and 11.33
Grubbing Road Land

Mastic including dismantling of 6.60 Unit of measurement is linear length.


concrete wearing course of Ajay Payment of each stage shall be made on
Bridge pro rata basis on completion of a stage in
a length of not less than 20 (Twenty)
percent of the scope length.

For example, if the total length of bituminous work to be done is 100 km. The cost per km. of
bituminous work shall be determined as follows:
Cost per km = p X weightage for road work X weightage for bituminous work X (1/L)
Where P= Contract price
L= Total length in Km
Similarly, the rates per Km for other stages shall be worked out accordingly.
Note: The length affected due to law and order problems or litigation during execution due to
which the contractor is unable to execute the work, may be deducted from the total project
length for payment purpose. The total length calculated here is only for payment purposes
and will not affect and referred in other clauses of the Contract Agreement.

1.3.2 Other works.


Procedure for estimating the value of Other Works shall be as state in table 1.3.2.

EPC Schedules 80 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Table-1.3.2
Percentage Payment procedure
Stage for Payment
weightage
Road marking 31.29 Unit of measurement is linear length.
Payment of each stage shall be made on
pro rata basis on completion of a stage
in a length of not less than 20 (Twenty)
percent of the total length.
W Metal beam crush barrier 44.57 Unit of measurement is linear length.
Payment of each stage shall be made on
pro rata basis on completion of a stage
in a length of not less than 10 (Ten)
percent of the scope length.
Gantry 4.37
Cats eye, 90 cm equilateral traingle,60 cm circular, 19.77
Chevron, Direction and Place Identification Sign Board,
Hazard Markers,5th KM post, Ordinary KM post, On completion
Hectometer Post, Rumble strips, Painting of Bridges and
culverts.

2. Procedure for payment for Maintenance.


a) The cost for maintenance shall be as stated in Clause 14.1.(v).
(b) Payment for Maintenance shall be made in accordance with the provisions of
Article 14 and Article 19

EPC Schedules 81 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-I
(See Clause 10.2.4)

DRAWINGS

1. Drawings

In compliance of the obligations set forth in Clause 10.2 of this Agreement, the
Contractor shall furnish to the Authority’s Engineer, free of cost, all Drawings
listed in Annex-I of this Schedule-I.

2. Additional Drawings

If the Authority’s Engineer determines that for discharging its duties and functions
under this Agreement, it requires any drawings other than those listed in Annex-I,
it may by notice require the Contractor to prepare and furnish such drawings
forthwith. Upon receiving a requisition to this effect, the Contractor shall
promptly prepare and furnish such drawings to the Authority’s Engineer, as if
such drawings formed part of Annex-I of this Schedule-I.

EPC Schedules 82 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex-I

(Schedule-I)

List of Drawings
[Note: The Authority shall describe in this Annex-I, all the Drawings that the Contractor is
required to furnish under Clause 10.2.]

● Horizontal and Vertical Alignment (with plan & profile) with details of reference
pillars. Horizontal Intersection Point, Vertical Intersection Points, elements of curves,
and sight distances.
● Cross-section at 50m interval along the alignment within ROW.
● Typical Cross-section with details of pavement structures.
● Detailed drawings of individual Bridges/Structures/ROB.
● Detailed drawing for individual culverts.
● Detailed layout drawings for intersections and interchanges.
● Drawings for Road sign, Markings.
● Traffic Management drawings for safety in construction zones.
● Detailed drawings of guide bunds and protection works and retaining structures.
● Detailed drawings of Drainage including Masonry drains and other drains.

EPC Schedules 83 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-J
(See Clause 10.3.2)

PROJECT COMPLETION SCHEDULE

1. Project Completion Schedule


During Construction period, the Contractor shall comply with the requirements set
forth in this Schedule J for each of the Project Milestones and the Scheduled
Completion Date. Within 15 (fifteen) days of the date of each Project Milestone, the
Contractor shall notify the Authority of such compliance along with necessary
particulars thereof.
2. Project Milestone-I

(i) Project Milestone-I shall occur on the date falling on the 120 th (one hundred and
twentieth) day from the Appointed Date (the “Project Milestone-I”).
(ii) Prior to the occurrence of Project Milestone-I, the Contractor shall have commenced
construction of the Project Highway and submitted to the Authority duly and validly
prepared Stage Payment Statements for an amount not less than 20% (twenty per
cent) of the Contract Price.
3. Project Milestone-II

(i) Project Milestone-II shall occur on the date falling on the 240th (two hundred and
fortieth) day from the Appointment Date (the “Project Milestone-II”).
Prior to the occurrence of Project Milestone-II, the Contractor shall have continued
with the construction of the Project Highway and submitted to the Authority duly and
validly prepared Stage Payment Statements for an amount not less than 70% (seventy
per cent) of the Contract Price.
4 Deleted

5 Schedule Completion Date


(i) The Schedule Completion Date shall occur on the 330 th (three hundred and
thirtieth)] day from the Appointed Date.
(ii) On or before the Scheduled Completion Date, the Contractor shall have completed
construction in accordance with this Agreement.
6 Extension of time
Upon extension of any or all of the aforesaid Project Milestones or the Scheduled
Completion Date, as the case may be, under and in accordance with the provisions of
this Agreement, the Project Completion Schedule shall be deemed to have been
amended.accordingly.

EPC Schedules 84 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-K
(See Clause 12.1.2)

Tests on Completion

1. Schedule for Tests


(i) The Contractor shall, no later than 30 (thirty) days prior to the likely completion of
construction, notify the Authority’s Engineer and the Authority of its intent to subject
the Project Highway to Tests, and no later than 10 (ten) days prior to the actual date of
Tests, furnish to the Authority’s Engineer and the Authority detailed inventory and
particulars of all works and equipment forming part of Works.

(ii) The Contractor shall notify the Authority’s Engineer of its readiness to subject the
Project Highway to Tests at any time after 10 (ten) days from the date of such notice,
and upon receipt of such notice, the Authority’s Engineer shall, in consultation with
the Contractor, determine the date and time for each Test and notify the same to the
Authority who may designate its representative to witness the Tests. The Authority’s
Engineer shall thereupon conduct the Tests itself or cause any of the Tests to be
conducted in accordance with Article 12 and this Schedule K.

2. Tests
(i) Visual and physical test: The Authority’s Engineer shall conduct a visual and physical
check of construction to determine that all works and equipment forming part thereof
conform to the provisions of this Agreement. The physical tests shall include: all the
tests specified in IRC code, manual and MORTH Specifications for the Road and
Bridge Works, 5th Revision, 2013.

(ii) Riding quality test: Riding quality of each lane of the carriageway shall be checked
with the help of a Network Survey Vehicle (NSV) fitted with latest equipments and
the maximum permissible roughness for purposes of this Test shall be [2,000 (two
thousand)] mm for each kilometer.

(iii) Tests for bridges: All major and minor bridges shall be subjected to the rebound
hammer and ultrasonic pulse velocity tests, to be conducted in accordance with the
procedure described in Special Report No. 17: 1996 of the IRC Highway Research
Board on Nondestructive Testing Techniques, at two spots in every span, to be chosen
at random by the Authority’s Engineer. Bridges with a span of 15 (fifteen) meters or
more shall also be subjected to load testing.

(iv) Other tests: The Authority’s Engineer may require the Contractor to carry out or cause
to be carried additional tests, in accordance with Good Industry Practice, for
determining the compliance of the Project Highway with Specifications and Standards
except tests as specified in clause 5,but shall include measuring the reflectivity of road
markings and road signs; and measuring the illumination level (lux) of lighting using
requisite testing equipment.

EPC Schedules 85 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(v) Environmental audit: The Authority’s Engineer shall carry out a check to determine
conformity of the Project Highway with the environmental requirements set forth in
Applicable Laws and Applicable Permits.
(vi) Safety Audit: The Authority’s Engineer shall carry out or cause to be carried out, a
safety audit to determine conformity of the Project Highway with the safety
requirements and Good Industry Practice.

3. Agency for conducting Tests


All Tests set forth in this Schedule-K shall be conducted by the Authority’s Engineer
or such other agency or person as it may specify in consultation with the Authority.

4. Completion Certificate
Upon successful completion of Tests, the Authority’s Engineer shall issue the
Completion Certificate in accordance with the provisions of Article 12.

5. The Authority Engineer will carry out tests with following equipment at his own cost
in the presence of contractor’s representative.

Sr. Key metrics of Equipment to be used Frequency of condition survey


No. Asset

1 Surface defects Network Survey At least twice a year (As per survey
of pavement Vehicle (NSV) months defined for the state basis
rainy season)

2 Roughness of Network Survey At least twice a year (As per survey


pavement Vehicle (NSV) months defined for the state basis
rainy season)

3 Strength of Falling Weight At least once a year


pavement Deflectometer (FWD)

4 Bridges Mobile Bridge At least twice a year (As per survey


Inspection Unit (MBU months defined for the state basis
rainy season

5 Road signs Retro-reflectometer At least twice a year (As per survey


months defined for the state basis
rainy season)

The first testing with the help of NSV shall be conducted at the time of issue of
Completion Certificate.

EPC Schedules 86 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-L
(See Clause 12.2)

COMPLETION CERTIFICATE
I, …………….. (Name of the Authority’s Engineer), acting as Authority’s Engineer, under
and in accordance with the Agreement dated ………….. (the “Agreement”), for construction
of the “Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH-
2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the
district of Purba Bardhaman & Birbhum ,West Bengal (EPC Mode)
"through…………………. (Name of Contractor), hereby certify that the Tests in accordance
with Article 12 of the Agreement have been successfully undertaken to determine compliance
of the Project Highway with the provisions of the Agreement, and I am satisfied that the
Project Highway can be safety and reliably placed in service of the Users thereof.

1. It is certified that, in terms of the aforesaid Agreement, all works forming part of
Project Highway have been completed, and the Project Highway is hereby declared fit
for entry into operation on this the ………..day of ……..20 ….. Scheduled
Completion Date for which was the ………..day of …..20….

SIGNED, SEALED AND DELIVERED

For and on behalf of Authority’s Engineer by:

(Signature)

(Name)

(Designation)

(Address)

EPC Schedules 87 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-M
(See Clauses 14.6., 15.2 and 19.7)

PAYMENT REDUCTION FOR NON-COMPLIANCE

1. Payment reduction for non-compliance with the Maintenance Requirements

(i) Monthly lump sum payments for maintenance shall be reduced in the case of non-
compliance with the Maintenance Requirements set forth in Schedule-E.

(ii) Any deduction made on account of non-compliance with the maintenance


Requirements shall not be paid even after compliance subsequently. The
deduction shall continue to be made every month until compliance is done.

(iii) The Authority’s Engineer shall calculate the amount of payment reduction on the
basis of weightage in percentage assigned to non-conforming items as given in
Paragraph 2.

2. Percentage reductions in lump sum payments

(i) The following percentages shall govern the payment reduction:

S. No. Item/Defect/Deficiency Percentage

(a) Carriageway/Pavement

(i) Potholes, cracks, other surface defects 45%

(ii) Repairs of Edges, Rutting 15%

(b) Road, Embankment, Cuttings, Shoulders

(i) Edge drop, inadequate crossfall, undulations, 10%


settlement, potholes, ponding, obstructions
(ii) Deficient slopes, raincuts, disturbed pitching, 5%
vegetation growth, pruning of trees
(c) Bridges and Culverts

(i) Desilting, cleaning. vegetation growth, damaged 20%


pitching, flooring, parapets, wearing course,
footpaths, any damage to foundations

EPC Schedules 88 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(ii) Any Defects in superstructures, bearings and sub- 10%


structures
(iii) Painting, repairs/replacement kerbs, railings, 5%
parapets, guideposts/crash barriers
(d) Roadside Drains

(i) Cleaning and repair of drains 5%

(e) Road Furniture

(i) Cleaning, painting, replacement of road signs, 5%


delineators, road markings, 200 m/km/5th km stones,
W metal beam, road marking, over head gantry
(f) Miscellaneous Items

(i) Removal of dead animals, broken down/accidented 10%


vehicles, fallen trees, road blockades or
malfunctioning of mobile crane
(ii) Any other Defects in accordance with paragraph 1. 5%

(g) Defects in Other Project Facilities 5%

(ii) The amount to be deducted from monthly lump-sum payment for non-compliance of
particular item shall be calculated as under:
R=P/100 * M * L1/L
Where. P= Percentage of particular item//Defect/deficiency for deduction
M = Monthly lump-sum payment in accordance with the Bid
L1 = Non-complying length
L = Total length of the road,
R = Reduction (the amount to be deducted for noncompliance for a particular
item/Defect/deficiency
The total amount of reduction shall be arrived at by summation of reductions for such
items/Defects/deficiency or noncompliance.
For any Defect in a part of one kilometer, the non-conforming length shall be taken as
one kilometer.

EPC Schedules 89 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-N
(See Clause 18.1.1)

SELECTION OF AUTHORITY’S ENGINEER

1 Selection of Authority’s Engineer

(i) The provisions of the Model Request for Proposal for Selection of Technical
Consultants, issued by the Ministry of Finance in May 2009, or any substitute thereof
shall apply for selection of an experienced firm to discharge the functions and duties
of an Authority’s Engineer.

(ii) In the event of termination of the Technical Consultants appointed in accordance with
the provisions of Paragraph 1.(i), the Authority shall appoint another firm of
Technical Consultants forthwith and may engage a government-owned entity in
accordance with the provisions of Paragraph 3 of this Schedule-N.

2 Terms of Reference

The Terms of Reference for the Authority’s Engineer (the “TOR”) shall substantially
conform with Annex 1 to this Schedule N.

3 Appointment of Government entity as Authority’s Engineer

Notwithstanding anything to the contrary contained in this Schedule, the Authority


may in its discretion appoint a government-owned entity as the Authority’s Engineer;
provided that such entity shall be a body corporate having as one of its primary
functions the provision of consulting, advisory and supervisory services for
engineering projects; provided further that a government-owned entity which is
owned or controlled by the Authority shall not be eligible for appointment as
Authority’s Engineer.

EPC Schedules 90 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Annex – I

(Schedule - N)

TERMS OF REFERENCE FOR AUTHORITY’S ENGINEER

1. Scope

(i)These Terms of Reference (the “TOR”) for the Authority’s Engineer are being specified
pursuant to the EPC Agreement dated ........... (the “Agreement), which has been entered into
between the […………………………….] (the “Authority”) and .......... (the “Contractor”)#
for “Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B
under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the
district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-
20/441 and a copy of which is annexed hereto and marked as Annex-A to form part of this
TOR.

# - In case the bid of Authority’s Engineer is invited simultaneously with the bid of
EPC project, then the status of bidding of EPC project only to be indicated.

(ii) The TOR shall apply to construction and maintenance of the Project Highway.

2. Definitions and interpretation

(i) The words and expressions beginning with or in capital letters and not defined herein
but defined in the Agreement shall have, unless repugnant to the context, the meaning
respectively assigned to them in the Agreement.

(ii) References to Articles, Clauses and Schedules in this TOR shall, except where the
context otherwise requires, be deemed to be references to the Articles, Clauses and
Schedules of the Agreement, and references to Paragraphs shall be deemed to be
references to Paragraphs of this TOR.

(iii) The rules of interpretation stated in Article 1 of the Agreement shall apply, mutatis
mutandis, to this TOR.
3. General

(i) The Authority’s Engineer shall discharge its duties in a fair, impartial and efficient
manner, consistent with the highest standards of professional integrity and Good
Industry Practice.
(ii) The Authority’s Engineer shall perform the duties and exercise the authority in
accordance with the provisions of this Agreement, but subject to obtaining prior
written approval of the Authority before determining:

(a) any Time extension;


(b) any additional cost to be paid by the Authority to the Contractor;
(c) the Termination Payment; or

EPC Schedules 91 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(d) any other matter which is not specified in (a), (b) or (c) above and which
creates a financial liability on either party.
(iii) The Authority’s Engineer shall submit regular periodic reports, at least once every
month, to the Authority in respect of its duties and functions under this Agreement.
Such reports shall be submitted by the Authority’s Engineer within 10 (ten) days of
the beginning of every month.
(iv) The Authority’s Engineer shall inform the Contractor of any delegation of its duties
and responsibilities to its suitably qualified and experienced personnel; provided,
however, that it shall not delegate the authority to refer any matter for the Authority’s
prior approval in accordance with the provisions of Clause 18.2.

(v) The Authority’s Engineer shall aid and advise the Authority on any proposal for
Change of Scope under Article 13.

(vi) In the event of any disagreement between the Parties regarding the meaning, scope
and nature of Good Industry Practice, as set forth in any provision of the Agreement,
the authority’s Engineer shall specify such meaning, scope and nature by issuing a
reasoned written statement relying on good industry practice and authentic literature.

4 Construction Period

(i) During the Construction Period, the Authority’s Engineer shall review and approve
the Drawings furnished by the Contractor along with supporting data, including the
geo-technical and hydrological investigations, characteristics of materials from
borrow areas and quarry sites, topographical surveys, and the recommendations of the
Safety Consultant in accordance with the provisions of Clause 10.1.(vi). The
Authority’s Engineer shall complete such review and approval and send its
observations to the Authority and the Contractor within 15 (fifteen) days of receipt of
such Drawings; provided, however that in case of a Major Bridge or Structure, the
aforesaid period of 15 (fifteen) days may be extended upto 30 (thirty) days. In
particular, such comments shall specify the conformity or otherwise of such Drawings
with the Scope of the Project and Specifications and Standards.

(ii) The Authority’s Engineer shall review and approve any revised Drawings sent to it by
the Contractor and furnish its comments within 10 (ten) days of receiving such
Drawings.

(iii) The Authority’s Engineer shall review and approve the Quality Assurance Plan
submitted by the Contractor and shall convey its comments to the Contractor within a
period of 21 (twenty-one) days stating the modifications, if any, required thereto.

(iv) The Authority’s Engineer shall complete the review and approve of the methodology
proposed to be adopted by the Contractor for executing the Works, and convey its
comments to the Contractor within a period of 10 (ten) days from the date of receipt
of the proposed methodology from the Contractor.

EPC Schedules 92 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(v) The Authority’s Engineer shall grant written approval to the Contractor, where
necessary, for interruption and diversion of the flow of traffic in the existing lane(s) of
the Project Highway for purposes of maintenance during the Construction Period in
accordance with the provisions of Clause 10.4.

(vi) The Authority’s Engineer shall review the monthly progress report furnished by the
Contractor and send its comments thereon to the Authority and the Contractor within
7 (seven) days of receipt of such report.

(vii) The Authority’s Engineer shall inspect the Construction Works and the Project
Highway and shall submit a monthly Inspection Report bringing out the results of
inspections and the remedial action taken by the Contractor in respect of Defects or
deficiencies. In particular, the Authority’s Engineer shall include in its Inspection
Report, the compliance of the recommendations made by the Safety Consultant.

(viii) The Authority’s Engineer shall conduct the pre-construction review of manufacturer's
test reports and standard samples of manufactured Materials, and such other Materials
as the Authority’s Engineer may require.

(ix) For determining that the Works conform to Specifications and Standards, the
Authority’s Engineer shall require the Contractor to carry out, or cause to be carried
out, tests at such time and frequency and in such manner as specified in the
Agreement and in accordance with Good Industry Practice for quality assurance. For
purposes of this Paragraph 4.(ix), the tests specified in the IRC Special Publication-11
(Handbook of Quality Control for Construction of Roads and Runways) and the
Specifications for Road and Bridge Works issued by MORTH (the “Quality Control
Manuals”) or any modification/substitution thereof shall be deemed to be tests
conforming to Good Industry Practice for quality assurance.

(x) The Authority’s Engineer shall test check at least 50 (fifty) percent of the quantity or
number of tests prescribed for each category or type of test for quality control by the
Contractor.

(xi) The timing of tests referred to in Paragraph 4.(ix), and the criteria for acceptance/
rejection of their results shall be determined by the Authority’s Engineer in
accordance with the Quality Control Manuals. The tests shall be undertaken on a
random sample basis and shall be in addition to, and independent of, the tests that
may be carried out by the Contractor for its own quality assurance in accordance with
Good Industry Practice.

(xii) In the event that results of any tests conducted under Clause 11.10 establish any
Defects or deficiencies in the Works, the Authority’s Engineer shall require the
Contractor to carry out remedial measures.

EPC Schedules 93 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(xiii) The Authority’s Engineer may instruct the Contractor to execute any work which is
urgently required for the safety of the Project Highway, whether because of an
accident, unforeseeable event or otherwise; provided that in case of any work required
on account of a Force Majeure Event, the provisions of Clause 21.6 shall apply.

(xiv) In the event that the Contractor fails to achieve any of the Project Milestones, the
Authority’s Engineer shall undertake a review of the progress of construction and
identify potential delays, if any. If the Authority’s Engineer shall determine that
completion of the Project Highway is not feasible within the time specified in the
Agreement, it shall require the Contractor to indicate within 15 (fifteen) days the steps
proposed to be taken to expedite progress, and the period within which the Project
Completion Date shall be achieved. Upon receipt of a report from the Contractor, the
Authority’s Engineer shall review the same and send its comments to the Authority
and the Contractor forthwith.

(xv) The Authority’s Engineer shall obtain from the Contractor a copy of all the
Contractor’s quality control records and documents before the Completion Certificate
is issued pursuant to Clause 12.2.

(xvi) Authority’s Engineer may recommend to the Authority suspension of the whole or
part of the Works if the work threatens the safety of the Users and pedestrians. After
the Contractor has carried out remedial measure, the Authority’s Engineer shall
inspect such remedial measures forthwith and make a report to the Authority
recommending whether or not the suspension hereunder may be revoked.

(xvii) In the event that the Contractor carries out any remedial measures to secure the safety
of suspended works and Users, and requires the Authority’s Engineer to inspect such
works, the Authority’s Engineer shall inspect the suspended works within 3 (three)
days of receiving such notice, and make a report to the Authority forthwith,
recommending whether or not such suspension may be revoked by the Authority.

(xviii) The Authority’s Engineer shall carry out, or cause to be carried out, all the Tests
specified in Schedule-K and issue a Completion Certificate, as the case may be. For
carrying out its functions under this Paragraph 4.(xviii) and all matters incidental
thereto, the Authority’s Engineer shall act under and in accordance with the
provisions of Article 12 and Schedule-K.

5. Maintenance Period
(i) The Authority’s Engineer shall aid and advise the Contractor in the preparation of its
monthly Maintenance Programme and for this purpose carry out a joint monthly
inspection with the Contractor.

(ii) The Authority’s Engineer shall undertake regular inspections, at least once every
month, to evaluate compliance with the Maintenance Requirements and submit a
Maintenance Inspection Report to the Authority and the Contractor.

(iii) The Authority’s Engineer shall specify the tests, if any, that the Contractor shall carry
out, or cause to be carried out, for the purpose of determining that the Project
Highway is in conformity with the Maintenance Requirements. It shall monitor and

EPC Schedules 94 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

review the results of such tests and the remedial measures, if any, taken by the
Contractor in this behalf.

(iv) In respect of any defect or deficiency referred to in Paragraph 3 of Schedule- E, the


Authority’s Engineer shall, in conformity with Good Industry Practice, specify the
permissible limit of deviation or deterioration with reference to the Specifications and
Standards and shall also specify the time limit for repair or rectification of any
deviation or deterioration beyond the permissible limit.

(v) The Authority’s Engineer shall examine the request of the Contractor for closure of
any lane(s) of the Project Highway for undertaking maintenance/repair thereof, and
shall grant permission with such modifications, as it may deem necessary, within 5
(five) days of receiving a request from the Contractor. Upon expiry of the permitted
period of closure, the Authority’s Engineer shall monitor the reopening of such
lane(s), and in case of delay, determine the Damages payable by the Contractor to the
Authority under Clause 14.5.

6 Determination of costs and time

(i) The Authority’s Engineer shall determine the costs, and/or their reasonableness, that
are required to be determined by it under the Agreement.

(ii) The Authority’s Engineer shall determine the period of Time Extension that is
required to be determined by it under the Agreement.

(iii) The Authority’s Engineer shall consult each Party in every case of determination in
accordance with the provisions of Clause 18.5.

7. Payments

(i) The Authority’s Engineer shall withhold payments for the affected works for which
the Contractor fails to revise and resubmit the Drawings to the Authority’s Engineer
in accordance with the provisions of Clause 10.2.(iv) (d).

(ii) Authority’s Engineer shall -

(a) within 10 (ten) days of receipt of the Stage Payment Statement from the
Contractor pursuant to Clause 19.4, determine the amount due to the
Contractor and recommend the release of 90 (ninety) percent of the amount so
determined as part payment, pending issue of the Interim Payment Certificate;
and

(b) within 15 (fifteen) days of the receipt of the Stage Payment Statement referred
to in Clause 19.4, deliver to the Authority and the Contractor an Interim
Payment Certificate certifying the amount due and payable to the Contractor,
after adjustments in accordance with the provisions of Clause 19.10.

EPC Schedules 95 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(iii) The Authority’s Engineer shall, within 15 (fifteen) days of receipt of the Monthly
Maintenance Statement from the Contractor pursuant to Clause 19.6, verify the
Contractor’s monthly statement and certify the amount to be paid to the Contractor in
accordance with the provisions of the Agreement.

(iv) The Authority’s Engineer shall certify final payment within 30 (thirty) days of the
receipt of the final payment statement of Maintenance in accordance with the
provisions of Clause 19.16.

8. Other duties and functions

The Authority’s Engineer shall perform all other duties and functions as specified in
the Agreement.

9 Miscellaneous

(i) A copy of all communications, comments, instructions, Drawings or Documents sent


by the Authority's Engineer to the Contractor pursuant to this TOR, and a copy of all
the test results with comments of the Authority's Engineer thereon, shall be furnished
by the Authority's Engineer to the Authority forthwith.

(ii) The Authority's Engineer shall retain at least one copy each of all Drawings and
Documents received by it, including 'as-built' Drawings, and keep them in its safe
custody.

(iii) Within 90 (ninety) days of the Project Completion Date, the Authority's Engineer
shall obtain a complete set of as-built Drawings, in 2 (two) hard copies and in micro
film form or in such other medium as may be acceptable to the Authority, reflecting
the Project Highway as actually designed, engineered and constructed, including an
as-built survey illustrating the layout of the Project Highway and setback lines, if any,
of the buildings and structures forming part of Project Facilities; and shall hand them
over to the Authority against receipt thereof.

(iv) The Authority's Engineer, if called upon by the Authority or the Contractor or both,
shall mediate and assist the Parties in arriving at an amicable settlement of any
Dispute between the Parties.

(v) The Authority's Engineer shall inform the Authority and the Contractor of any event
of Contractor's Default within one week of its occurrence.

EPC Schedules 96 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

SCHEDULE - O

(See Clauses 19.4.1, 19.6.1, and 19.8.1)

Forms of Payment Statements

1. Stage Payment Statement for Works


The Stage Payment Statement for Works shall state:

(a) The estimated amount for the Works executed in accordance with
Clause 19.3.(i) subsequent to the last claim;
(b) Amounts reflecting adjustments in price for the aforesaid claim;
(c) The estimated amount of each Change of Scope Order executed
subsequent to the last claim;
(d) Amounts reflecting adjustment in price, if any, for (c) above in
accordance with the provisions of Clause 13.2.(iii) (a);
(e) Total of (a), (b), (c) and (d) above;
(f) Deductions:
(i) Any amount to be deducted in accordance with the provisions
of the Agreement except taxes;
(ii) Any amount towards deduction of taxes; and
(iii) Total of (i) and (ii) above.
(g) Net claim: (e) – (f) (iii);
(h) The amounts received by the Contractor upto the last claim:
(i) For the Works executed (excluding Change of Scope orders);
(ii) For Change of Scope Orders, and
(iii) Taxes deducted

2. Monthly Maintenance Payment Statement


The monthly Statement for Maintenance Payment shall state:
(a) the monthly payment admissible in accordance with the provisions of the
agreement;
(b) the deductions for maintenance work not done;
(c) net payment for maintenance due, (a) minus (b);
(d) amounts reflecting adjustments in price under Clause 19.12; and
(e) amount towards deduction of taxes

3. Contractor’s claim for Damages


Note: The Contractor shall submit its claims in a form acceptable to the Authority.

EPC Schedules 97 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-P

(See Clause 20.1)

INSURANCE

1. Insurance during Construction Period


(i) The Contractor shall effect and maintain at its own cost, from the Appointed Date till the
date of issue of the last Completion Certificate, the following insurances for any loss or
damage occurring on account of Non Political Event of Force Majeure, malicious act,
accidental damage, explosion, fire and terrorism:

(a) insurance of Works, Plant and Materials and an additional sum of [15 (fifteen)] per cent
of such replacement cost to cover any additional costs of and incidental to the
rectification of loss or damage including professional fees and the cost of demolishing
and removing any part of the Works and of removing debris of whatsoever nature; and

(b) insurance for the Contractor’s equipment and Documents brought onto the Site by the
Contractor, for a sum sufficient to provide for their replacement at the Site.

(ii) The insurance under paragraph (a) and (b) above shall cover the authority and the
Contractor against all loss or damage from whatsoever cause arising under paragraph 1.(i)
other than risks which are not insurable at commercial terms.

2. Insurance for Contractor’s Defects Liability


The Contractor shall effect and maintain insurance cover for the works from the date of
issue of the Completion Certificate until the end of the Defects Liability Period for any
loss or damage for which the Contractor is liable and arises from a cause occurring prior
to the issue of Completion Certificate. The Contractor shall also maintain other
insurances for maximum sums as may be required under the Applicable Laws and in
accordance with Good Industry Practice.

3. Insurance against injury to persons and damage to property


(i) The Contractor shall insure against each Party’s liability for any loss, damage, death or
bodily injury or damage to any property (except things insured under Paragraph l and 2
of this Schedule) or to any person (except persons insured under Clause 20.9), which
may arise out of the Contractor’s performance of this This insurance shall be for a limit
per occurrence of not less than the amount stated below with no limit on the number of
occurrences.

The insurance cover shall not be less than Rs. 3.00 lac (three lac) only.

EPC Schedules 98 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

(ii) The insurance shall be extended to cover liability for all loss and damage to the
Authority’s property arising out of the Contractor’s performance of this Agreement
excluding:

(a) the Authority’s right to have the construction works executed on, over, under, in or
through any land, and to occupy this land for the Works; and

(b) Damage which is and unavoidable result of the Contractor’s obligations to


execute the Works.

4. Insurance to be in joint names


The insurance under paragraphs 1 to 3 above shall be in the joint names of the Contract.

EPC Schedules 99 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-Q

(See Clause 14.10)

Tests on Completion of Maintenance Period

1. Riding Quality test:

Riding quality test: Riding quality of each lane of the carriageway shall be checked
with the help of a calibrated bump integrator and the maximum permissible
roughness for purposes of this Test shall be [2,200 (two thousand and two hundred
only)] mm for each kilometre.
2. Visual and physical test:
The Authority’s Engineer shall conduct a visual and physical check of construction
to determine that all works and equipment forming part thereof conform to the
provisions of this Agreement. The physical tests shall include measurement of
cracking, rutting, stripping and potholes and shall be as per the requirement of
maintenance mentioned in Schedule-E.

EPC Schedules 100 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

Schedule-R
(See Clause 14.10)
Taking Over Certificate
I, ……………………. (Name and designation of the Authority’s Representative)
under and in accordance with the Agreement dated ………… (the “Agreement”), for
[construction of the ****section (km ** to km **) of

****] (the “Project Highway”) on Engineering, Procurement and Construction


(EPC) basis through …………………. (Name of Contractor), hereby certify that the
Tests on completion of Maintenance Period in accordance with Article 14 of the
Agreement have been successfully undertaken to determine compliance of the
Project Highway with the provisions of the Agreement and I hereby certify that the
Authority has taken over the Project highway from the Contractor on this day.........

SIGNED, SEALED AND DELIVERED

(Signature)

(Name and designation of Authority’s Representative)

(Address)

EPC Schedules 101 CE NH, P.W.(Roads) Dte


Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II
during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC mode Job No. 2B-WB-2019-20/441

End of the Document

EPC Schedules 102 CE NH, P.W.(Roads) Dte

You might also like