You are on page 1of 105

FY 2020 CONTRACTS WITH NEGATIVE SLIPPAGE

REGULAR INFRA - Region-Implemented


As of 31 August 2021

Region XI - Regional Office


A. ORIGINAL A. CONTRACT % PHYSICAL
CONTRACT EFFECTIVITY ACCOMPLISHMENT CAUSE/S OF DELAY
COST
CONTRACT B. CONTRACT B. ORIGINAL A. TARGET REMARKS
COST CONTRACT B. ACTUAL
EXPIRY DATE
C. SLIPPAGE DETAIL ACTION TAKEN
C. CONTRACT RESOLVED
EXPIRY
1 20L00002 A. 64,182,072.05 A. 12/29/2020 A. 100.00 The project was completed as of 27
CONSTRUCTION OF ROAD B. 64,182,072.05 B. 7/27/2021 B. 95.99 July 2021 with minor corrections.
SLOPE PROTECTION C. 7/27/2021 C. -4.01
STRUCTURE ON SPECIFIC
LOCATIONS ALONG DAANG
MAHARLIKA (MN) (S00126MN),
K1399+500 - K1400+225,
COMPOSTELA VALLEY
WEE ENG CONSTRUCTION, INC.
(16380)

PCMA 8/31/2021 5:01:21 PM Page 1 Of 105


2 20L00003 A. 191,543,242.73 A. 6/9/2020 A. 100.00 P00401102MN- Tagging, inventory, and 1.The project was suspended
CONSTRUCTION OF CONCRETE B. 191,543,242.73 B. 4/4/2021 B. 73.97 CW1 (Permit to identification of affected persons effective May 16,2021 due to road-
ROAD - MONKAYO BOSTON C. 7/5/2021 C. -26.03 enter issues) were done to come up with a right-of-way problems encountered at
ROAD (MONKAYO SECTION) detailed estimates that were used the project site. Once project is
PACKAGE E, COMPOSTELA to be the basis of giving cash resumed and equivalent Time
VALLEY assistance to the affected Extension is approved, the revised
METRO GEAR CONSTRUCTION residents.Project was suspended planned schedule will be 76.64% and
CORP. (43024) / RELY as of 16 November 2020 due to incurred negative slippage of -
CONSTRUCTION & SUPPLY Road Right-of-Way encountered at 2.672%. Request for revision on
(10433) the project site. process.
1.The project was suspended
effective May 16,2021 due to road-
right-of-way problems encountered
at the project site. Once project is
resumed and equivalent Time
Extension is approved, the revised
planned schedule will be 76.64%
and incurred negative slippage of
-9.328%. Request for revision on
process.
3 20L00004 A. 178,954,616.42 A. 4/13/2020 A. 100.00 P00401132MN- on-going negotiation between the -Project suspended effective 18
CONSTRUCTION OF CONCRETE B. 178,954,616.42 B. 3/3/2021 B. 0.17 CW1 (Awaiting contractors of the projects involved August 2020 due to Inaccessibility
BRIDGE-MONKAYO- C. 7/6/2021 C. -99.83 for completion of and the implementing offfice going to the project site and pending
COMPOSTELA ROAD, PACKAGE construction of completion of Construction of
F, COMPOSTELA VALLEY other Phases) Concrete Bridge - Monkayo-
MAC BUILDERS (7249) Compostela Road, Package D
(under separate contract - CY 2019
Infrastructure Program), which
greatly affects the implementation of
the Project, Once project is resumed
and equivalent Time Extension is
approved, revised planned schedule
will be 0.27% and incurred negative
slippage -0.27%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 2 Of 105


3 20L00004 A. 178,954,616.42 A. 4/13/2020 A. 100.00 P00401132MN- on-going negotiation between the -Project suspended effective 18
CONSTRUCTION OF CONCRETE B. 178,954,616.42 B. 3/3/2021 B. 0.17 CW2 (Awaiting contractors of the projects involved August 2020 due to Inaccessibility
BRIDGE-MONKAYO- C. 7/6/2021 C. -99.83 for completion of and the implementing offfice going to the project site and pending
COMPOSTELA ROAD, PACKAGE construction of completion of Construction of
F, COMPOSTELA VALLEY other Phases) Concrete Bridge - Monkayo-
MAC BUILDERS (7249) Compostela Road, Package D
(under separate contract - CY 2019
Infrastructure Program), which
greatly affects the implementation of
the Project, Once project is resumed
and equivalent Time Extension is
approved, revised planned schedule
will be 0.27% and incurred negative
slippage -0.27%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
P00401132MN- The project is suspended due to 8/16/2020 -Project suspended effective 18
CW1 (Epidemic strict implementation of community August 2020 due to Inaccessibility
(s)) quarantine due to pandemic going to the project site and pending
caused by the spread of COVID-19 completion of Construction of
virus infection within Region XI. Concrete Bridge - Monkayo-
The contractor has sent a letter Compostela Road, Package D
regarding the situation on the (under separate contract - CY 2019
project site and a situational report Infrastructure Program), which
has been made by the greatly affects the implementation of
Implementing Office. the Project, Once project is resumed
and equivalent Time Extension is
approved, revised planned schedule
will be 0.27% and incurred negative
slippage -0.27%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
4 20L00005 A. 139,007,958.70 A. 4/13/2020 A. 100.00 P00401136MN- Corresponding documents of project suspended as of june
CONSTRUCTION OF CONCRETE B. 139,007,958.70 B. 2/6/2021 B. 76.71 CW1 (Changes in Variation Order No. 1 was 01,2021 due to Revision of plan,
ROAD-MAWAB-MARAGUSAN- C. 3/26/2021 C. -23.29 approved complied to suit actual site revision for pcma is on process once
CARAGA ROAD, SECTION 1, plans/designs) condition. Once approved, Request aprroved will be forwarded to BOC-
PACKAGE G, COMPOSTELA for Revision in the PCMA will then PMD for approval the revised sched
VALLEY be sent to the BOC-PMD for accomp. is 81.640% and the actual is
MAC BUILDERS (7249) approval. 76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.

PCMA 8/31/2021 5:01:21 PM Page 3 Of 105


4 20L00005 A. 139,007,958.70 A. 4/13/2020 A. 100.00 P00401136MN- Corresponding documents of project suspended as of june
CONSTRUCTION OF CONCRETE B. 139,007,958.70 B. 2/6/2021 B. 76.71 CW2 (Changes in Variation Order No. 1 was 01,2021 due to Revision of plan,
ROAD-MAWAB-MARAGUSAN- C. 3/26/2021 C. -23.29 approved complied to suit actual site revision for pcma is on process once
CARAGA ROAD, SECTION 1, plans/designs) condition. Once approved, Request aprroved will be forwarded to BOC-
PACKAGE G, COMPOSTELA for Revision in the PCMA will then PMD for approval the revised sched
VALLEY be sent to the BOC-PMD for accomp. is 81.640% and the actual is
MAC BUILDERS (7249) approval. 76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- Suspension of project effective 5/30/2020 project suspended as of june
CW1 (Epidemic April 01, 2020 was administered 01,2021 due to Revision of plan,
(s)) due to implementation of revision for pcma is on process once
community quarantine caused by aprroved will be forwarded to BOC-
COVID-19 Pandemic. PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june
CW1 (Epidemic Guidelines and due to the 01,2021 due to Revision of plan,
(s)) declaration of General Community revision for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june
CW2 (Epidemic Guidelines and due to the 01,2021 due to Revision of plan,
(s)) declaration of General Community revision for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- the respective Local Government 5/31/2020 project suspended as of june
CW1 (Epidemic Unit issued Executive Order No. 20 01,2021 due to Revision of plan,
(s)) and strictly implemented revision for pcma is on process once
community quarantine to prevent aprroved will be forwarded to BOC-
the spread of COVID-19 virus PMD for approval the revised sched
inspection accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
PCMA 8/31/2021 5:01:21 PM Page 4 Of 105
4 20L00005 A. 139,007,958.70 A. 4/13/2020 A. 100.00 P00401136MN- the respective Local Government 5/31/2020 project suspended as of june
CONSTRUCTION OF CONCRETE B. 139,007,958.70 B. 2/6/2021 B. 76.71 CW2 (Epidemic Unit issued Executive Order No. 20 01,2021 due to Revision of plan,
ROAD-MAWAB-MARAGUSAN- C. 3/26/2021 C. -23.29 (s)) and strictly implemented revision for pcma is on process once
CARAGA ROAD, SECTION 1, community quarantine to prevent aprroved will be forwarded to BOC-
PACKAGE G, COMPOSTELA the spread of COVID-19 virus PMD for approval the revised sched
VALLEY inspection accomp. is 81.640% and the actual is
MAC BUILDERS (7249) 76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- the respective Local Government 5/31/2020 project suspended as of june
CW1 (Epidemic Unit issued Executive Order No. 20 01,2021 due to Revision of plan,
(s)) and strictly implemented revision for pcma is on process once
community quarantine to prevent aprroved will be forwarded to BOC-
the spread of COVID-19 virus PMD for approval the revised sched
inspection accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- the respective Local Government 5/31/2020 project suspended as of june
CW2 (Epidemic Unit issued Executive Order No. 20 01,2021 due to Revision of plan,
(s)) and strictly implemented revision for pcma is on process once
community quarantine to prevent aprroved will be forwarded to BOC-
the spread of COVID-19 virus PMD for approval the revised sched
inspection accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june
CW1 (Epidemic Guidelines and due to the 01,2021 due to Revision of plan,
(s)) declaration of General Community revision for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june
CW2 (Epidemic Guidelines and due to the 01,2021 due to Revision of plan,
(s)) declaration of General Community revision for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
PCMA 8/31/2021 5:01:21 PM Page 5 Of 105
4 20L00005 A. 139,007,958.70 A. 4/13/2020 A. 100.00 P00401136MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june
CONSTRUCTION OF CONCRETE B. 139,007,958.70 B. 2/6/2021 B. 76.71 CW1 (Epidemic Guidelines and due to the 01,2021 due to Revision of plan,
ROAD-MAWAB-MARAGUSAN- C. 3/26/2021 C. -23.29 (s)) declaration of General Community revision for pcma is on process once
CARAGA ROAD, SECTION 1, Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
PACKAGE G, COMPOSTELA Region. PMD for approval the revised sched
VALLEY accomp. is 81.640% and the actual is
MAC BUILDERS (7249) 76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june
CW2 (Epidemic Guidelines and due to the 01,2021 due to Revision of plan,
(s)) declaration of General Community revision for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- on process negotiation 11/16/2020 project suspended as of june
CW1 (Permit to 01,2021 due to Revision of plan,
enter issues) revision for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- on process negotiation 11/16/2020 project suspended as of june
CW2 (Permit to 01,2021 due to Revision of plan,
enter issues) revision for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.

PCMA 8/31/2021 5:01:21 PM Page 6 Of 105


4 20L00005 A. 139,007,958.70 A. 4/13/2020 A. 100.00 P00401136MN- Negotiation with the project 11/16/2020 project suspended as of june
CONSTRUCTION OF CONCRETE B. 139,007,958.70 B. 2/6/2021 B. 76.71 CW1 (Permit to affected persons and processing of 01,2021 due to Revision of plan,
ROAD-MAWAB-MARAGUSAN- C. 3/26/2021 C. -23.29 enter issues) documents related to RROW revision for pcma is on process once
CARAGA ROAD, SECTION 1, problem were done. aprroved will be forwarded to BOC-
PACKAGE G, COMPOSTELA Tagging/inventory/identification of PMD for approval the revised sched
VALLEY affected persons were done to accomp. is 81.640% and the actual is
MAC BUILDERS (7249) come up with a detailed estimates 76.709% and the negative slippage
that were used to be the basis of is -4.931% the revised expiry is
giving cash assistance to the november 09, 2021.
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
09, 2020 due to RROW
P00401136MN- Negotiation with the project 11/16/2020 project suspended as of june
CW2 (Permit to affected persons and processing of 01,2021 due to Revision of plan,
enter issues) documents related to RROW revision for pcma is on process once
problem were done. aprroved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval the revised sched
affected persons were done to accomp. is 81.640% and the actual is
come up with a detailed estimates 76.709% and the negative slippage
that were used to be the basis of is -4.931% the revised expiry is
giving cash assistance to the november 09, 2021.
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
09, 2020 due to RROW
P00401136MN- signed permit to enter 11/16/2020 project suspended as of june
CW1 (Permit to 01,2021 due to Revision of plan,
enter issues) revision for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.

PCMA 8/31/2021 5:01:21 PM Page 7 Of 105


4 20L00005 A. 139,007,958.70 A. 4/13/2020 A. 100.00 P00401136MN- signed permit to enter 11/16/2020 project suspended as of june
CONSTRUCTION OF CONCRETE B. 139,007,958.70 B. 2/6/2021 B. 76.71 CW2 (Permit to 01,2021 due to Revision of plan,
ROAD-MAWAB-MARAGUSAN- C. 3/26/2021 C. -23.29 enter issues) revision for pcma is on process once
CARAGA ROAD, SECTION 1, aprroved will be forwarded to BOC-
PACKAGE G, COMPOSTELA PMD for approval the revised sched
VALLEY accomp. is 81.640% and the actual is
MAC BUILDERS (7249) 76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- negotiated 11/16/2020 project suspended as of june
CW1 (Permit to 01,2021 due to Revision of plan,
enter issues) revision for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- negotiated 11/16/2020 project suspended as of june
CW2 (Permit to 01,2021 due to Revision of plan,
enter issues) revision for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 81.640% and the actual is
76.709% and the negative slippage
is -4.931% the revised expiry is
november 09, 2021.
P00401136MN- Negotiation with the project 11/16/2020 project suspended as of june
CW1 (Permit to affected persons and processing of 01,2021 due to Revision of plan,
enter issues) documents related to RROW revision for pcma is on process once
problem were done. aprroved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval the revised sched
affected persons were done to accomp. is 81.640% and the actual is
come up with a detailed estimates 76.709% and the negative slippage
that were used to be the basis of is -4.931% the revised expiry is
giving cash assistance to the november 09, 2021.
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
01, 2020 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 8 Of 105


4 20L00005 A. 139,007,958.70 A. 4/13/2020 A. 100.00 P00401136MN- Negotiation with the project 11/16/2020 project suspended as of june
CONSTRUCTION OF CONCRETE B. 139,007,958.70 B. 2/6/2021 B. 76.71 CW2 (Permit to affected persons and processing of 01,2021 due to Revision of plan,
ROAD-MAWAB-MARAGUSAN- C. 3/26/2021 C. -23.29 enter issues) documents related to RROW revision for pcma is on process once
CARAGA ROAD, SECTION 1, problem were done. aprroved will be forwarded to BOC-
PACKAGE G, COMPOSTELA Tagging/inventory/identification of PMD for approval the revised sched
VALLEY affected persons were done to accomp. is 81.640% and the actual is
MAC BUILDERS (7249) come up with a detailed estimates 76.709% and the negative slippage
that were used to be the basis of is -4.931% the revised expiry is
giving cash assistance to the november 09, 2021.
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
01, 2020 due to RROW
5 20L00006 A. 141,457,460.65 A. 4/13/2020 A. 100.00 P00401137MN- Corresponding documents of project suspended as of june 01,
CONSTRUCTION OF CONCRETE B. 141,457,460.65 B. 2/6/2021 B. 83.91 CW1 (Changes in Variation Order No. 1 was 2021 due to revision of plan , revision
ROAD-MAWAB-MARAGUSAN- C. 6/10/2021 C. -16.09 approved complied to suit actual site for pcma is on process once
CARAGA ROAD, SECTION 1, plans/designs) condition. Once approved, Request aprroved will be forwarded to BOC-
PACKAGE H, COMPOSTELA for Revision in the PCMA will then PMD for approval the revised sched
VALLEY be sent to the BOC-PMD for accomp. is 86.00% and the actual is
MAC BUILDERS (7249) approval. 83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- Suspension of project effective 5/30/2020 project suspended as of june 01,
CW1 (Epidemic April 01, 2020 was administered 2021 due to revision of plan , revision
(s)) due to implementation of for pcma is on process once
community quarantine caused by aprroved will be forwarded to BOC-
COVID-19 Pandemic. PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june 01,
CW1 (Epidemic Guidelines and due to the 2021 due to revision of plan , revision
(s)) declaration of General Community for pcma is on process once
Quarantine aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021

PCMA 8/31/2021 5:01:21 PM Page 9 Of 105


5 20L00006 A. 141,457,460.65 A. 4/13/2020 A. 100.00 P00401137MN- the respective Local Government 5/31/2020 project suspended as of june 01,
CONSTRUCTION OF CONCRETE B. 141,457,460.65 B. 2/6/2021 B. 83.91 CW1 (Epidemic Unit issued Executive Order No. 20 2021 due to revision of plan , revision
ROAD-MAWAB-MARAGUSAN- C. 6/10/2021 C. -16.09 (s)) and strictly implemented for pcma is on process once
CARAGA ROAD, SECTION 1, community quarantine to prevent aprroved will be forwarded to BOC-
PACKAGE H, COMPOSTELA the spread of COVID-19 virus PMD for approval the revised sched
VALLEY inspection accomp. is 86.00% and the actual is
MAC BUILDERS (7249) 83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- the respective Local Government 5/31/2020 project suspended as of june 01,
CW1 (Epidemic Unit issued Executive Order No. 20 2021 due to revision of plan , revision
(s)) and strictly implemented for pcma is on process once
community quarantine to prevent aprroved will be forwarded to BOC-
the spread of COVID-19 virus PMD for approval the revised sched
inspection accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june 01,
CW1 (Epidemic Guidelines and due to the 2021 due to revision of plan , revision
(s)) declaration of General Community for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june 01,
CW1 (Epidemic Guidelines and due to the 2021 due to revision of plan , revision
(s)) declaration of General Community for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of june 01,
CW1 (Epidemic Guidelines and due to the 2021 due to revision of plan , revision
(s)) declaration of General Community for pcma is on process once
Quarantine (GCQ) in Davao aprroved will be forwarded to BOC-
Region. PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
PCMA 8/31/2021 5:01:21 PM Page 10 Of 105
5 20L00006 A. 141,457,460.65 A. 4/13/2020 A. 100.00 P00401137MN- Ongoing negotiation between 11/16/2020 project suspended as of june 01,
CONSTRUCTION OF CONCRETE B. 141,457,460.65 B. 2/6/2021 B. 83.91 CW1 (Permit to DPWH and LGUs with tribal 2021 due to revision of plan , revision
ROAD-MAWAB-MARAGUSAN- C. 6/10/2021 C. -16.09 enter issues) leaders within the project limit. for pcma is on process once
CARAGA ROAD, SECTION 1, aprroved will be forwarded to BOC-
PACKAGE H, COMPOSTELA PMD for approval the revised sched
VALLEY accomp. is 86.00% and the actual is
MAC BUILDERS (7249) 83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- Negotiation with the project 11/16/2020 project suspended as of june 01,
CW1 (Permit to affected persons and processing of 2021 due to revision of plan , revision
enter issues) documents related to RROW for pcma is on process once
problem were done. aprroved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval the revised sched
affected persons were done to accomp. is 86.00% and the actual is
come up with a detailed estimates 83.9030% and the negative slippage
that were used to be the basis of is -2.10% the revised expiry is
giving cash assistance to the november 09, 2021
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
09, 2020 due to RROW
P00401137MN- signed permit to enter 11/16/2020 project suspended as of june 01,
CW1 (Permit to 2021 due to revision of plan , revision
enter issues) for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- signed permit to enter 11/16/2020 project suspended as of june 01,
CW1 (Permit to 2021 due to revision of plan , revision
enter issues) for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021

PCMA 8/31/2021 5:01:21 PM Page 11 Of 105


5 20L00006 A. 141,457,460.65 A. 4/13/2020 A. 100.00 P00401137MN- negotiated with the affected land 11/16/2020 project suspended as of june 01,
CONSTRUCTION OF CONCRETE B. 141,457,460.65 B. 2/6/2021 B. 83.91 CW1 (Permit to owners 2021 due to revision of plan , revision
ROAD-MAWAB-MARAGUSAN- C. 6/10/2021 C. -16.09 enter issues) for pcma is on process once
CARAGA ROAD, SECTION 1, aprroved will be forwarded to BOC-
PACKAGE H, COMPOSTELA PMD for approval the revised sched
VALLEY accomp. is 86.00% and the actual is
MAC BUILDERS (7249) 83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- negotiated with affected owners 11/16/2020 project suspended as of june 01,
CW1 (Permit to 2021 due to revision of plan , revision
enter issues) for pcma is on process once
aprroved will be forwarded to BOC-
PMD for approval the revised sched
accomp. is 86.00% and the actual is
83.9030% and the negative slippage
is -2.10% the revised expiry is
november 09, 2021
P00401137MN- Negotiation with the project 11/16/2020 project suspended as of june 01,
CW1 (Permit to affected persons and processing of 2021 due to revision of plan , revision
enter issues) documents related to RROW for pcma is on process once
problem were done. aprroved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval the revised sched
affected persons were done to accomp. is 86.00% and the actual is
come up with a detailed estimates 83.9030% and the negative slippage
that were used to be the basis of is -2.10% the revised expiry is
giving cash assistance to the november 09, 2021
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
01, 2020 due to RROW
6 20L00007 A. 238,767,777.88 A. 12/28/2020 A. 76.40 P00401138MN- Corresponding documents of project suspended as of july 16,2021
CONSTRUCTION OF CONCRETE B. 238,767,777.88 B. 11/17/2021 B. 62.23 CW1 (Changes in Variation Order No. 1 was due to RROw, revision for pcma is
ROAD-MAWAB-MARAGUSAN- C. 11/17/2021 C. -14.17 approved complied to suit actual site on process once aprroved will be
CARAGA ROAD, SECTION 1, plans/designs) condition. Once approved, Request forwarded to BOC-PMD for approval
PACKAGE I, COMPOSTELA for Revision in the PCMA will then the revised sched accomp. is 61.30%
VALLEY be sent to the BOC-PMD for and the actual is 62.230% and the
ULTICON BUILDERS, INC. approval. negative slippage is 1.00% the
(17267) revised expiry is January 03, 2022.

PCMA 8/31/2021 5:01:21 PM Page 12 Of 105


7 20L00008 A. 120,069,040.22 A. 3/9/2020 A. 100.00 P00400782MN- Negotiation with the project project suspended as of may 1 ,
WIDENING OF BRIDGE-OSMEÑA B. 120,069,040.22 B. 1/2/2021 B. 97.54 CW1 (Permit to affected persons and processing of 2021 due to road roght of way
BRIDGE (B00082MN) ALONG C. 3/3/2021 C. -2.46 enter issues) documents related to RROW problem . revision for pcma is on
MONTEVISTA-COMPOSTELA- problem were done. process once approved will be
MATI BDRY. ROAD, Tagging/inventory/identification of forwarded to BOC_PMD for
COMPOSTELA VALLEY affected persons were done to approval.
LICSAL CONSTRUCTION come up with a detailed estimates
SERVICES (41652) / RELY that were used to be the basis of
CONSTRUCTION & SUPPLY giving cash assistance to the
(10433) affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended May 01,
2021 due to RROW
P00400782MN- Suspension of project effective 5/30/2020 project suspended as of may 1 ,
CW1 (Epidemic April 01, 2020 was administered 2021 due to road roght of way
(s)) due to implementation of problem . revision for pcma is on
community quarantine caused by process once approved will be
COVID-19 Pandemic. forwarded to BOC_PMD for
approval.
P00400782MN- declaration of General Community 5/31/2020 project suspended as of may 1 ,
CW1 (Epidemic Quarantine (GCQ) and pursuant to 2021 due to road roght of way
(s)) the Revised Omnibus Guidelines in problem . revision for pcma is on
Davao Region process once approved will be
forwarded to BOC_PMD for
approval.
P00400782MN- the respective Local Government 5/31/2020 project suspended as of may 1 ,
CW1 (Epidemic Unit issued Executive Order No. 20 2021 due to road roght of way
(s)) and strictly implemented problem . revision for pcma is on
community quarantine to prevent process once approved will be
the spread of COVID-19 virus forwarded to BOC_PMD for
inspection approval.
P00400782MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of may 1 ,
CW1 (Epidemic Guidelines and due to the 2021 due to road roght of way
(s)) declaration of General Community problem . revision for pcma is on
Quarantine (GCQ) in Davao process once approved will be
Region. forwarded to BOC_PMD for
approval.

PCMA 8/31/2021 5:01:21 PM Page 13 Of 105


7 20L00008 A. 120,069,040.22 A. 3/9/2020 A. 100.00 P00400782MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of may 1 ,
WIDENING OF BRIDGE-OSMEÑA B. 120,069,040.22 B. 1/2/2021 B. 97.54 CW1 (Epidemic Guidelines and due to the 2021 due to road roght of way
BRIDGE (B00082MN) ALONG C. 3/3/2021 C. -2.46 (s)) declaration of General Community problem . revision for pcma is on
MONTEVISTA-COMPOSTELA- Quarantine (GCQ) in Davao process once approved will be
MATI BDRY. ROAD, Region. forwarded to BOC_PMD for
COMPOSTELA VALLEY approval.
8 20L00009 A. 8,726,801.55 A. 3/23/2020 A. 100.00 P00431729MN- Suspension of project effective 5/30/2020 project completed as of July 31,
CONSTRUCTION OF B. 8,726,801.55 B. 9/18/2020 B. 99.65 CW1 (Epidemic April 01, 2020 was administered 2021, revision for time extension is
MARAGUSAN MUNICIPAL C. 11/17/2020 C. -0.35 (s)) due to implementation of on propcess once approved will be
POLICE STATION, MARAGUSAN, community quarantine caused by forwarded to BOC-PMD for approval.
COMPOSTELA VALLEY COVID-19 Pandemic. the revised expiry date is on January
PROVINCE 16, 2021.
AB APONESTO P00431729MN- declaration of General Community 5/31/2020 project completed as of July 31,
CONSTRUCTION, PARTS & CW1 (Epidemic Quarantine (GCQ) and pursuant to 2021, revision for time extension is
SUPPLIES, INC. (FORMERLY:AB (s)) the Revised Omnibus Guidelines in on propcess once approved will be
APONESTO CONSTRUCTION Davao Region forwarded to BOC-PMD for approval.
PARTS & SUPPLY) (22998) the revised expiry date is on January
16, 2021.
P00431729MN- the respective Local Government 5/31/2020 project completed as of July 31,
CW1 (Epidemic Unit issued Executive Order No. 20 2021, revision for time extension is
(s)) and strictly implemented on propcess once approved will be
community quarantine to prevent forwarded to BOC-PMD for approval.
the spread of COVID-19 virus the revised expiry date is on January
inspection 16, 2021.
P00431729MN- the respective Local Government 5/31/2020 project completed as of July 31,
CW1 (Epidemic Unit issued Executive Order No. 20 2021, revision for time extension is
(s)) and strictly implemented on propcess once approved will be
community quarantine to prevent forwarded to BOC-PMD for approval.
the spread of COVID-19 virus the revised expiry date is on January
inspection 16, 2021.
P00431729MN- pursuant to the Revised Omnibus 5/31/2020 project completed as of July 31,
CW1 (Epidemic Guidelines and due to the 2021, revision for time extension is
(s)) declaration of General Community on propcess once approved will be
Quarantine (GCQ) in Davao forwarded to BOC-PMD for approval.
Region. the revised expiry date is on January
16, 2021.
P00431729MN- pursuant to the Revised Omnibus 5/31/2020 project completed as of July 31,
CW1 (Epidemic Guidelines and due to the 2021, revision for time extension is
(s)) declaration of General Community on propcess once approved will be
Quarantine (GCQ) in Davao forwarded to BOC-PMD for approval.
Region. the revised expiry date is on January
16, 2021.

PCMA 8/31/2021 5:01:21 PM Page 14 Of 105


9 20L00010 A. 8,702,426.55 A. 3/12/2020 A. 100.00 P00431730MN- Advised the contractor to provide 4/1/2020 Project Completed as of December
CONSTRUCTION OF NEW B. 8,702,426.55 B. 9/7/2020 B. 99.73 CW1 (Insufficient additional manpower and fast track 06, 2020 with minor corrections.
BATAAN MUNICIPAL POLICE C. 11/6/2020 C. -0.27 manpower) construction activities to cope up Project Implementation Schedule in
STATION, NEW BATAAN, with delayed activities. the PCMA will be revised once the
COMPOSTELA VALLEY corresponding time extension due to
AB APONESTO work suspension is approved.
CONSTRUCTION, PARTS & P00431730MN- Situational report was rendered by 5/30/2020 Project Completed as of December
SUPPLIES, INC. (FORMERLY:AB CW1 (Epidemic the Project Engineer concerning 06, 2020 with minor corrections.
APONESTO CONSTRUCTION (s)) some issues raised by the Project Implementation Schedule in
PARTS & SUPPLY) (22998) Contractor in relation to the the PCMA will be revised once the
implementation of project. corresponding time extension due to
work suspension is approved.
P00431730MN- pursuant to the Revised Omnibus 5/31/2020 Project Completed as of December
CW1 (Epidemic Guidelines and due to the 06, 2020 with minor corrections.
(s)) declaration of General Community Project Implementation Schedule in
Quarantine (GCQ) in Davao the PCMA will be revised once the
Region. corresponding time extension due to
work suspension is approved.
10 20L00011 A. 132,219,357.91 A. 3/25/2020 A. 100.00 P00401133MN- Negotiation with the project project is suspended as of May 10,
CONSTRUCTION OF CONCRETE B. 132,219,357.91 B. 1/8/2021 B. 82.62 CW1 (Permit to affected persons and processing of 2021 due to RROW problem
ROAD-MARAGUSAN-PANTUKAN C. 3/9/2021 C. -17.38 enter issues) documents related to RROW (difficulty of land acquisition/ revision
ROAD (PANTUKAN problem were done. for time extension on process once
SECTION),PACKAGE Tagging/inventory/identification of approved will be forwarded to BOC-
F,COMPOSTELA VALLEY affected persons were done to PMD for approval. The Revised
MAC BUILDERS (7249) come up with a detailed estimates accomplishment is 94.724% actual is
that were used to be the basis of 85.607% the slippage to date is -
giving cash assistance to the 9.117% the revised expiry date is
affected residents. Once approved, october 28, 2021.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended May 10,
2021 due to RROW
P00401133MN- Suspension of project effective 5/30/2020 project is suspended as of May 10,
CW1 (Epidemic April 01, 2020 was administered 2021 due to RROW problem
(s)) due to implementation of (difficulty of land acquisition/ revision
community quarantine caused by for time extension on process once
COVID-19 Pandemic. approved will be forwarded to BOC-
PMD for approval. The Revised
accomplishment is 94.724% actual is
85.607% the slippage to date is -
9.117% the revised expiry date is
october 28, 2021.

PCMA 8/31/2021 5:01:21 PM Page 15 Of 105


10 20L00011 A. 132,219,357.91 A. 3/25/2020 A. 100.00 P00401133MN- pursuant to the Revised Omnibus 5/31/2020 project is suspended as of May 10,
CONSTRUCTION OF CONCRETE B. 132,219,357.91 B. 1/8/2021 B. 82.62 CW1 (Epidemic Guidelines in Davao Region 2021 due to RROW problem
ROAD-MARAGUSAN-PANTUKAN C. 3/9/2021 C. -17.38 (s)) (difficulty of land acquisition/ revision
ROAD (PANTUKAN for time extension on process once
SECTION),PACKAGE approved will be forwarded to BOC-
F,COMPOSTELA VALLEY PMD for approval. The Revised
MAC BUILDERS (7249) accomplishment is 94.724% actual is
85.607% the slippage to date is -
9.117% the revised expiry date is
october 28, 2021.
P00401133MN- the respective Local Government 5/31/2020 project is suspended as of May 10,
CW1 (Epidemic Unit issued Executive Order No. 20 2021 due to RROW problem
(s)) and strictly implemented (difficulty of land acquisition/ revision
community quarantine to prevent for time extension on process once
the spread of COVID-19 virus approved will be forwarded to BOC-
inspection PMD for approval. The Revised
accomplishment is 94.724% actual is
85.607% the slippage to date is -
9.117% the revised expiry date is
october 28, 2021.
P00401133MN- pursuant to the Revised Omnibus 5/31/2020 project is suspended as of May 10,
CW1 (Epidemic Guidelines and due to the 2021 due to RROW problem
(s)) declaration of General Community (difficulty of land acquisition/ revision
Quarantine (GCQ) in Davao for time extension on process once
Region. approved will be forwarded to BOC-
PMD for approval. The Revised
accomplishment is 94.724% actual is
85.607% the slippage to date is -
9.117% the revised expiry date is
october 28, 2021.
P00401133MN- pursuant to the Revised Omnibus 5/31/2020 project is suspended as of May 10,
CW1 (Epidemic Guidelines and due to the 2021 due to RROW problem
(s)) declaration of General Community (difficulty of land acquisition/ revision
Quarantine (GCQ) in Davao for time extension on process once
Region. approved will be forwarded to BOC-
PMD for approval. The Revised
accomplishment is 94.724% actual is
85.607% the slippage to date is -
9.117% the revised expiry date is
october 28, 2021.

PCMA 8/31/2021 5:01:21 PM Page 16 Of 105


10 20L00011 A. 132,219,357.91 A. 3/25/2020 A. 100.00 P00401133MN- pursuant to the Revised Omnibus 5/31/2020 project is suspended as of May 10,
CONSTRUCTION OF CONCRETE B. 132,219,357.91 B. 1/8/2021 B. 82.62 CW1 (Epidemic Guidelines and due to the 2021 due to RROW problem
ROAD-MARAGUSAN-PANTUKAN C. 3/9/2021 C. -17.38 (s)) declaration of General Community (difficulty of land acquisition/ revision
ROAD (PANTUKAN Quarantine (GCQ) in Davao for time extension on process once
SECTION),PACKAGE Region. approved will be forwarded to BOC-
F,COMPOSTELA VALLEY PMD for approval. The Revised
MAC BUILDERS (7249) accomplishment is 94.724% actual is
85.607% the slippage to date is -
9.117% the revised expiry date is
october 28, 2021.
11 20L00014 A. 79,971,655.39 A. 7/29/2020 A. 100.00 P00401134MN- Ongoing negotiation with the Project resumed dated 09 August
CONSTRUCTION OF CONCRETE B. 79,971,655.39 B. 4/14/2021 B. 79.82 CW1 (Permit to affected land owner 2021.
ROAD -MAWAB-MACO BYPASS C. 4/14/2021 C. -20.18 enter issues) Project On-going.
ROAD, PACKAGE A,
COMPOSTELA VALLEY P00401134MN- Ongoing negotiation with the Project resumed dated 09 August
PREMIUM MEGASTRUCTURES CW2 (Permit to affected land owner 2021.
INC. (36079) enter issues) Project On-going.

P00401134MN- issued Calibrated Action to the 3/1/2021 Project resumed dated 09 August
CW1 (Slow Contractor due to the incurred 2021.
Performance) negative slippage of 4.837% Project On-going.

P00401134MN- issued Calibrated Action to the 3/1/2021 Project resumed dated 09 August
CW2 (Slow Contractor due to the incurred 2021.
Performance) negative slippage of 4.837% Project On-going.

12 20L00015 A. 72,588,494.36 A. 3/18/2020 A. 100.00 P00401135MN- Issued work suspension order due Project suspended dated 02 August
CONSTRUCTION OF CONCRETE B. 72,588,494.36 B. 12/7/2020 B. 66.19 CW1 (Permit to to unsettled Road Right-of-Way at 2021 due to unsettled Road Right-of-
ROAD-MAWAB-MACO BYPASS C. 2/5/2021 C. -33.81 enter issues) Sta. 1816+354.226 to Sta. Way at Sta. 1816+354.226 to Sta.
ROAD, PACKAGE B, 1817+154.26 (B/S) 1817+154.26 (B/S).
COMPOSTELA VALLEY Once the project is resumed and
PREMIUM MEGASTRUCTURES equivalent Time Extension is
INC. (36079) approved, revised planned schedule
will be 65.28% and incurred a
negative of 0.91%.
P00401135MN- Issued work suspension order due Project suspended dated 02 August
CW2 (Permit to to unsettled Road Right-of-Way at 2021 due to unsettled Road Right-of-
enter issues) Sta. 1816+354.226 to Sta. Way at Sta. 1816+354.226 to Sta.
1817+154.26 (B/S) 1817+154.26 (B/S).
Once the project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 65.28% and incurred a
negative of 0.91%.

PCMA 8/31/2021 5:01:21 PM Page 17 Of 105


12 20L00015 A. 72,588,494.36 A. 3/18/2020 A. 100.00 P00401135MN- Issued work suspension order to 5/31/2020 Project suspended dated 02 August
CONSTRUCTION OF CONCRETE B. 72,588,494.36 B. 12/7/2020 B. 66.19 CW1 (Epidemic the contractor dated 01 April 2020 2021 due to unsettled Road Right-of-
ROAD-MAWAB-MACO BYPASS C. 2/5/2021 C. -33.81 (s)) due to implementation of Way at Sta. 1816+354.226 to Sta.
ROAD, PACKAGE B, community quarantine caused by 1817+154.26 (B/S).
COMPOSTELA VALLEY COVID-19. Once the project is resumed and
PREMIUM MEGASTRUCTURES equivalent Time Extension is
INC. (36079) approved, revised planned schedule
will be 65.28% and incurred a
negative of 0.91%.
P00401135MN- Issued work suspension order to 5/31/2020 Project suspended dated 02 August
CW2 (Epidemic the contractor dated 01 April 2020 2021 due to unsettled Road Right-of-
(s)) due to implementation of Way at Sta. 1816+354.226 to Sta.
community quarantine caused by 1817+154.26 (B/S).
COVID-19. Once the project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 65.28% and incurred a
negative of 0.91%.
P00401135MN- Negotiation with the Project 5/3/2021 Project suspended dated 02 August
CW1 (Permit to Affected Persons (PAPs) and 2021 due to unsettled Road Right-of-
enter issues) processing of RROW documents Way at Sta. 1816+354.226 to Sta.
are still on going. Tagging, 1817+154.26 (B/S).
inventory, and identification of Once the project is resumed and
affected persons were done to equivalent Time Extension is
come up with detailed estimates approved, revised planned schedule
that were used as basis for just will be 65.28% and incurred a
compensation of the PAPs negative of 0.91%.
P00401135MN- Negotiation with the Project 5/3/2021 Project suspended dated 02 August
CW2 (Permit to Affected Persons (PAPs) and 2021 due to unsettled Road Right-of-
enter issues) processing of RROW documents Way at Sta. 1816+354.226 to Sta.
are still on going. Tagging, 1817+154.26 (B/S).
inventory, and identification of Once the project is resumed and
affected persons were done to equivalent Time Extension is
come up with detailed estimates approved, revised planned schedule
that were used as basis for just will be 65.28% and incurred a
compensation of the PAPs negative of 0.91%.
P00401135MN- Ongoing negotiation with the 5/3/2021 Project suspended dated 02 August
CW1 (Permit to affected owners. 2021 due to unsettled Road Right-of-
enter issues) Issued Work Suspension Order Way at Sta. 1816+354.226 to Sta.
No. 2 due to unsettled road right of 1817+154.26 (B/S).
way problems (structures and Once the project is resumed and
improvements) equivalent Time Extension is
approved, revised planned schedule
will be 65.28% and incurred a
negative of 0.91%.
PCMA 8/31/2021 5:01:21 PM Page 18 Of 105
13 20L00024 A. 114,827,218.71 A. 12/22/2020 A. 95.87 Project was declared completed as
CONSTRUCTION OF ROAD B. 114,827,218.71 B. 9/21/2021 B. 81.06 of 31 March 2021. Documents are
SLOPE PROTECTION C. 9/21/2021 C. -14.81 processed for approval. Once
STRUCTURE ALONG DAVAO approved, request for revision will be
CITY DIV. RD. (S00013MN) K1510 submitted to PMD-BOC for approval.
+ 230-K1510 + 324, DAVAO CITY
MONOLITHIC CONSTRUCTION &
CONCRETE PRODUCTS, INC.
(5733)
14 20L00028 A. 51,759,665.71 A. 8/11/2020 A. 100.00 P00401548MN- On-going negotiation of the -Project suspended effective 20
RECONSTRUCTION OF B. 51,759,665.71 B. 4/20/2021 B. 29.99 CW1 (Permit to affected structures, improvements November 2020 due to Road Right of
CONCRETE PAVEMENT - C. 4/20/2021 C. -70.01 enter issues) and land c/o Legal Way problem (structures and land)
MATINA CROSSING ROAD (JCT. Division. within the project limit. Once project
DAVAO - COTABATO ROAD - is resumed and equivalent Time
JCT. DAVAO CITY DIVERSION Extension is approved revised
ROAD), DAVAO CITY planned schedule will be 38.481%
ABU CONSTRUCTION (22313) and incurred negative slippage -
8.481%. Revision in the PCMA on
process, waiting for approved time
extension in view of approved
suspension and resumption order.
P00401548MN- On-going negotiation of the -Project suspended effective 20
CW2 (Permit to affected structures, improvements November 2020 due to Road Right of
enter issues) and land c/o Legal Way problem (structures and land)
Division. within the project limit. Once project
is resumed and equivalent Time
Extension is approved revised
planned schedule will be 38.481%
and incurred negative slippage -
8.481%. Revision in the PCMA on
process, waiting for approved time
extension in view of approved
suspension and resumption order.
P00401548MN- On-going negotiation of the -Project suspended effective 20
CW3 (Permit to affected structures, improvements November 2020 due to Road Right of
enter issues) and land c/o Legal Way problem (structures and land)
Division. within the project limit. Once project
is resumed and equivalent Time
Extension is approved revised
planned schedule will be 38.481%
and incurred negative slippage -
8.481%. Revision in the PCMA on
process, waiting for approved time
extension in view of approved
suspension and resumption order.
PCMA 8/31/2021 5:01:21 PM Page 19 Of 105
15 20L00029 A. 52,132,089.85 A. 12/29/2020 A. 99.42 P00401549MN- On going negotiation with the -Project suspended effective 16
CONSTRUCTION OF CONCRETE B. 52,132,089.85 B. 9/4/2021 B. 58.00 CW1 (Permit to affected land owners c/o with the August 2021 due to Road Right of
ROAD - BYPASS ROAD AT MAA C. 9/4/2021 C. -41.42 enter issues) legal division. Way problem (structures,
RADIO STATION - DATU LOHO improvements and land) within the
ST. - RIVERSIDE - JCT. BACACA project limit. Once project is resumed
ROAD, DAVAO CITY and equivalent Time Extension is
GEMMA CONSTRUCTION approved revised planned schedule
SUPPLY, INC. will be 63.004% and incurred
(FORMERLY:GEMMA CON (5044) negative slippage -4.999%. Revision
in the PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
P00401549MN- On going negotiation with the -Project suspended effective 16
CW2 (Permit to affected land owners c/o with the August 2021 due to Road Right of
enter issues) legal division. Way problem (structures,
improvements and land) within the
project limit. Once project is resumed
and equivalent Time Extension is
approved revised planned schedule
will be 63.004% and incurred
negative slippage -4.999%. Revision
in the PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
P00401549MN- On going negotiation with the -Project suspended effective 16
CW3 (Permit to affected land owners c/o with the August 2021 due to Road Right of
enter issues) legal division. Way problem (structures,
improvements and land) within the
project limit. Once project is resumed
and equivalent Time Extension is
approved revised planned schedule
will be 63.004% and incurred
negative slippage -4.999%. Revision
in the PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 20 Of 105


16 20L00030 A. 186,863,777.88 A. 12/28/2020 A. 91.98 P00401383MN- Project mutually terminated due to -Project mutually terminated due to
CONSTRUCTION OF FLYOVER B. 186,863,777.88 B. 10/18/2021 B. 0.00 CW2 (Permit to difficulty in acquiring Road Right of difficulty in acquiring Road Right of
ALONG DAVAO - COTABATO C. 10/18/2021 C. -91.98 enter issues) Way Way
ROAD - JUNCTION MAA ROAD,
PACKAGE 1, DAVAO CITY
ULTICON BUILDERS, INC.
(17267)
17 20L00032 A. 208,472,610.44 A. 8/12/2020 A. 100.00 P00442813MN- Tagging of affected Persons and -Project suspended as of 16 July
RECONSTRUCTION TO B. 208,472,610.44 B. 6/17/2021 B. 87.22 CW1 (Permit to Structures has been completed. 2021 due to Road Right-of-Way
CONCRETE PAVEMENT - JCT. R C. 6/17/2021 C. -12.78 enter issues) problem, Once project is resumed
MAGSAYSAY AVE. - L. MA. On going of submission of and equivalent times extension is
GUERRERO ST. - GUZMAN ST. - requirements and processing of approved, revised planned schedule
VINZON ST. - T. PALMA GIL ST. - documents needed for the request will be 92.40% and incurred negative
JCT. DACUDAO - JCT. J.P. of funding for RROW since the slippage of -4.85%. Revision in the
CABAGUIO AVE., DAVAO CITY project has no RROW budget PCMA on process, waiting for
DREIRICH BUILDERS (39521) / approved time extension in view of
THREE W BUILDERS, INC. approved suspension and
(10722) resumption order.
-Revision in the PCMA documents
due to Variation Order No. 1 on
process, once approved
corresponding request for revision in
the PCMA will be forwarded to PMD-
BOC for approval.
18 20L00033 A. 98,285,255.05 A. 12/28/2020 A. 100.00 P00400494MN- Corresponding documents of Project Completed as of July 26,
PREVENTIVE MAINTENANCE OF B. 98,285,255.05 B. 6/26/2021 B. 99.77 CW1 (Changes in Variation order was complied to 2021 with minor corrections on-
ROAD: ASPHALT OVERLAY ON C. 6/26/2021 C. -0.23 approved suit the actual site condition. Once going. Variation order No. 1 on
SPECIFIC LOCATIONS ALONG plans/designs) approved, request for revision in process. Once approved, request for
DAANG MAHARLIKA (MN) the PCMA will then be sent to the revision in the PCMA will then be
(S00001MN) K1499+1002- BOC-PMD for approval. sent to the BOC-PMD for approval.
K1502+150 & (S01460MN)
CHAINAGE 1201- CHAINAGE
1684, DAVAO CITY
EDCL CONSTRUCTION AND
SUPPLY (39587) / RELY
CONSTRUCTION & SUPPLY
(10433)

PCMA 8/31/2021 5:01:21 PM Page 21 Of 105


19 20L00034 A. 102,644,079.19 A. 12/28/2020 A. 100.00 P00400491MN- Project suspended effective 17 Project resume on July 21, 2021.
PREVENTIVE MAINTENANCE OF B. 102,644,079.19 B. 6/30/2021 B. 78.90 CW1 May 2021, due to obstruction of
ROAD: ASPHALT OVERLAY ON C. 6/30/2021 C. -21.10 (Unworkable site DCWD pipe on the provision of
SPECIFIC LOCATIONS ALONG condition (i.e. drainage inlets along the
J.P. CABAGUIO AVENUE unfavorable carriageway at left side. Once
(S00025MN), K1507+(-876) - weather condition Contract Time Extension is
K1507+549, DAVAO CITY at the project site, approved, corresponding Request
VICENTE T. LAO access to project for Revision will be submitted to
CONSTRUCTION (7040) site not BOC-PMD for approval.
passable))
20 20L00035 A. 87,622,677.42 A. 12/28/2020 A. 100.00 P00400279MN- Negotiation with the project project suspended as of july 1,2021
ROAD WIDENING ON SPECIFIC B. 87,622,677.42 B. 8/28/2021 B. 62.67 CW1 (Permit to affected persons and processing of due to RROw, revision for pcma is
LOCATIONS-ALONG MABUHAY- C. 8/28/2021 C. -37.33 enter issues) documents related to RROW on process once aprroved will be
PAÑALUM-PAQUIBATO ROAD problem were done. forwarded to BOC-PMD for approval
(S01339MN), K1525+470- Tagging/inventory/identification of the revised sched accomp. is 62.42%
K1527+750, DAVAO CITY affected persons were done to and the actual is 62.69% and the
RELY CONSTRUCTION & come up with a detailed estimates negative slippage is 0.27% the
SUPPLY (10433) that were used to be the basis of revised expiry is october 29, 2021.
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended July 01,
2021 due to RROW
21 20L00036 A. 158,139,777.88 A. 3/23/2020 A. 100.00 P00401117MN- Corresponding documents of project suspended as of july 10, 2020
CONSTRUCTION OF CONCRETE B. 158,139,777.88 B. 1/21/2021 B. 6.20 CW1 (Changes in Variation Order No. 1 was due to realignment / revision for
BRIDGE-ALTERNATE ROAD C. 3/22/2021 C. -93.80 approved complied to suit actual site pcma is on process once aprroved
FROM REGION XI TO REGION X, plans/designs) condition. Once approved, Request will be forwarded to BOC-PMD
PACKAGE 2E, DAVAO CITY for Revision in the PCMA will then
ULTICON BUILDERS, INC. be sent to the BOC-PMD for
(17267) approval.
P00401117MN- Corresponding documents of project suspended as of july 10, 2020
CW2 (Changes in Variation Order No. 1 was due to realignment / revision for
approved complied to suit actual site pcma is on process once aprroved
plans/designs) condition. Once approved, Request will be forwarded to BOC-PMD
for Revision in the PCMA will then
be sent to the BOC-PMD for
approval.
P00401117MN- Suspension of project effective 5/30/2020 project suspended as of july 10, 2020
CW1 (Epidemic April 01, 2020 was administered due to realignment / revision for
(s)) due to implementation of pcma is on process once aprroved
community quarantine caused by will be forwarded to BOC-PMD
COVID-19 Pandemic.

PCMA 8/31/2021 5:01:21 PM Page 22 Of 105


21 20L00036 A. 158,139,777.88 A. 3/23/2020 A. 100.00 P00401117MN- the respective Local Government 5/31/2020 project suspended as of july 10, 2020
CONSTRUCTION OF CONCRETE B. 158,139,777.88 B. 1/21/2021 B. 6.20 CW1 (Epidemic Unit issued Executive Order No. 20 due to realignment / revision for
BRIDGE-ALTERNATE ROAD C. 3/22/2021 C. -93.80 (s)) and strictly implemented pcma is on process once aprroved
FROM REGION XI TO REGION X, community quarantine to prevent will be forwarded to BOC-PMD
PACKAGE 2E, DAVAO CITY the spread of COVID-19 virus
ULTICON BUILDERS, INC. inspection
(17267) P00401117MN- the respective Local Government 5/31/2020 project suspended as of july 10, 2020
CW2 (Epidemic Unit issued Executive Order No. 20 due to realignment / revision for
(s)) and strictly implemented pcma is on process once aprroved
community quarantine to prevent will be forwarded to BOC-PMD
the spread of COVID-19 virus
inspection
P00401117MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of july 10, 2020
CW1 (Epidemic Guidelines and due to the due to realignment / revision for
(s)) declaration of General Community pcma is on process once aprroved
Quarantine (GCQ) in Davao will be forwarded to BOC-PMD
Region.
P00401117MN- pursuant to the Revised Omnibus 5/31/2020 project suspended as of july 10, 2020
CW2 (Epidemic Guidelines and due to the due to realignment / revision for
(s)) declaration of General Community pcma is on process once aprroved
Quarantine (GCQ) in Davao will be forwarded to BOC-PMD
Region.
22 20L00037 A. 107,498,962.52 A. 12/28/2020 A. 88.11 project suspended as of july 1 , 2021
CONSTRUCTION OF CONCRETE B. 107,498,962.52 B. 10/13/2021 B. 49.80 due to Road right of way revision for
ROAD-BUHANGIN-TIGATTO- C. 10/13/2021 C. -38.31 pcma is on process once approved
MANDUG-CALLAWA-FATIMA will be forwarded to BOC_PMD for
ROAD, PACKAGE 10, DAVAO approval.
CITY
COASTLAND CONSTRUCTION &
DEVELOPMENT CORP. (11487)
23 20L00038 A. 130,110,326.88 A. 12/22/2020 A. 73.53 P00401114MN- On-going negotiation with the Project suspended effective 16 May
CONSTRUCTION OF CONCRETE B. 130,110,326.88 B. 11/6/2021 B. 31.04 CW1 (Permit to Owner regarding the acquisition of 2021 due to Road Right-of-Way
BRIDGE - BYPASS ROAD AT JCT. C. 11/6/2021 C. -42.49 enter issues) the area. problem, Once project is resumed
MAMAY ROAD - LA VERNA - and equivalent times extension is
DAVAO CITY DIVERSION (JCT. approved, revised planned schedule
AIRPORT SECTION), DAVAO will be 21.82% and incurred negative
CITY slippage of 0.55%. Revision in the
R.A. PAHATI CONST. & SUPPLY, PCMA on process, waiting for
INC. (35843) approved time extension in view of
approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 23 Of 105


23 20L00038 A. 130,110,326.88 A. 12/22/2020 A. 73.53 P00401114MN- On-going negotiation with the Project suspended effective 16 May
CONSTRUCTION OF CONCRETE B. 130,110,326.88 B. 11/6/2021 B. 31.04 CW2 (Permit to Owner regarding the acquisition of 2021 due to Road Right-of-Way
BRIDGE - BYPASS ROAD AT JCT. C. 11/6/2021 C. -42.49 enter issues) the area. problem, Once project is resumed
MAMAY ROAD - LA VERNA - and equivalent times extension is
DAVAO CITY DIVERSION (JCT. approved, revised planned schedule
AIRPORT SECTION), DAVAO will be 21.82% and incurred negative
CITY slippage of 0.55%. Revision in the
R.A. PAHATI CONST. & SUPPLY, PCMA on process, waiting for
INC. (35843) approved time extension in view of
approved suspension and
resumption order.
24 20L00039 A. 97,199,959.42 A. 12/22/2020 A. 99.33 P00401115MN- Negotiation with the project Project suspended effective June 11,
CONSTRUCTION OF BYPASS B. 97,199,959.42 B. 9/21/2021 B. 38.20 CW1 (Permit to affected persons and processing of 2021 due to unsettled Road right of
ROAD AT MALAGAMOT ROAD- C. 9/21/2021 C. -61.13 enter issues) documents related to RROW way problem encountered during
JCT. MUDIANG ROAD, DAVAO problems were done. The construction activities. Once project
CITY contractor requested for Work is resumed and equivalent Time
MONOLITHIC CONSTRUCTION & Suspension Order No. 1 due to Extension is approved, the revised
CONCRETE PRODUCTS, INC. encountered RROW issues. Once planned schedule will be 36.735%
(5733) Contract Time Extension due to and the incurred slippage 0.242%.
WSO is approved, corresponding Revision in the PCMA on process,
Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.
25 20L00040 A. 190,152,663.19 A. 6/3/2020 A. 99.88 P00401126MN- The Contractor requested for Work Project is suspended
CONSTRUCTION OF CONCRETE B. 190,152,663.19 B. 4/18/2021 B. 40.31 CW1 (Permit to Suspension Order No. 2 due to March 16, 2021 due
BRIDGE-JCT. CABANTIAN ROAD C. 9/17/2021 C. -59.57 enter issues) Road Right-of-Way problem. to Road Right-of-Way
(ACACIA SECTION)-JCT. problem.
MANDUG-CALLAWA ROAD (In connection to
(MANDUG SECTION), DAVAO WSO, WRO
CITY and CTE, revised
P.L. SEBASTIAN construction
CONSTRUCTION, INC. schedule is
(FORMERLY: P.L. SEBASTIAN 47.64% and incurred
CONSTRUCTION) (35840) / WEE slippage of -4.96%)
ENG CONSTRUCTION, INC. Time
(16380) Extension Order is on
process. once
approved,
revisions in the
PCMA will
be forwarded.
Revised
Contract Expiry Date
is
February 02, 2022.

PCMA 8/31/2021 5:01:21 PM Page 24 Of 105


25 20L00040 A. 190,152,663.19 A. 6/3/2020 A. 99.88 P00401126MN- The Contractor requested for Work Project is suspended
CONSTRUCTION OF CONCRETE B. 190,152,663.19 B. 4/18/2021 B. 40.31 CW2 (Permit to Suspension Order no. 2 due to March 16, 2021 due
BRIDGE-JCT. CABANTIAN ROAD C. 9/17/2021 C. -59.57 enter issues) Road Right-of-Way Problem. to Road Right-of-Way
(ACACIA SECTION)-JCT. problem.
MANDUG-CALLAWA ROAD (In connection to
(MANDUG SECTION), DAVAO WSO, WRO
CITY and CTE, revised
P.L. SEBASTIAN construction
CONSTRUCTION, INC. schedule is
(FORMERLY: P.L. SEBASTIAN 47.64% and incurred
CONSTRUCTION) (35840) / WEE slippage of -4.96%)
ENG CONSTRUCTION, INC. Time
(16380) Extension Order is on
process. once
approved,
revisions in the
PCMA will
be forwarded.
Revised
Contract Expiry Date
is
February 02, 2022.
P00401126MN- The Contractor requested for Work Project is suspended
CW3 (Permit to Suspension Order no. 2 due to March 16, 2021 due
enter issues) Road Right-of-Way Problem. to Road Right-of-Way
problem.
(In connection to
WSO, WRO
and CTE, revised
construction
schedule is
47.64% and incurred
slippage of -4.96%)
Time
Extension Order is on
process. once
approved,
revisions in the
PCMA will
be forwarded.
Revised
Contract Expiry Date
is
February 02, 2022.

PCMA 8/31/2021 5:01:21 PM Page 25 Of 105


25 20L00040 A. 190,152,663.19 A. 6/3/2020 A. 99.88 P00401126MN- The contractor requested for Work 12/1/2020 Project is suspended
CONSTRUCTION OF CONCRETE B. 190,152,663.19 B. 4/18/2021 B. 40.31 CW1 (Changes in Suspension Order No.1 due to March 16, 2021 due
BRIDGE-JCT. CABANTIAN ROAD C. 9/17/2021 C. -59.57 approved Revision of Plans. to Road Right-of-Way
(ACACIA SECTION)-JCT. plans/designs) problem.
MANDUG-CALLAWA ROAD (In connection to
(MANDUG SECTION), DAVAO WSO, WRO
CITY and CTE, revised
P.L. SEBASTIAN construction
CONSTRUCTION, INC. schedule is
(FORMERLY: P.L. SEBASTIAN 47.64% and incurred
CONSTRUCTION) (35840) / WEE slippage of -4.96%)
ENG CONSTRUCTION, INC. Time
(16380) Extension Order is on
process. once
approved,
revisions in the
PCMA will
be forwarded.
Revised
Contract Expiry Date
is
February 02, 2022.
P00401126MN- The Contractor requested for Work 12/1/2020 Project is suspended
CW2 (Changes in Suspension Order No. 1 due to March 16, 2021 due
approved Revision of plans. to Road Right-of-Way
plans/designs) problem.
(In connection to
WSO, WRO
and CTE, revised
construction
schedule is
47.64% and incurred
slippage of -4.96%)
Time
Extension Order is on
process. once
approved,
revisions in the
PCMA will
be forwarded.
Revised
Contract Expiry Date
is
February 02, 2022.

PCMA 8/31/2021 5:01:21 PM Page 26 Of 105


25 20L00040 A. 190,152,663.19 A. 6/3/2020 A. 99.88 P00401126MN- The Contractor requested for Work 12/1/2020 Project is suspended
CONSTRUCTION OF CONCRETE B. 190,152,663.19 B. 4/18/2021 B. 40.31 CW3 (Changes in Suspension Order No. 1 due to March 16, 2021 due
BRIDGE-JCT. CABANTIAN ROAD C. 9/17/2021 C. -59.57 approved Revision of plans. to Road Right-of-Way
(ACACIA SECTION)-JCT. plans/designs) problem.
MANDUG-CALLAWA ROAD (In connection to
(MANDUG SECTION), DAVAO WSO, WRO
CITY and CTE, revised
P.L. SEBASTIAN construction
CONSTRUCTION, INC. schedule is
(FORMERLY: P.L. SEBASTIAN 47.64% and incurred
CONSTRUCTION) (35840) / WEE slippage of -4.96%)
ENG CONSTRUCTION, INC. Time
(16380) Extension Order is on
process. once
approved,
revisions in the
PCMA will
be forwarded.
Revised
Contract Expiry Date
is
February 02, 2022.
26 20L00041 A. 28,389,401.04 A. 1/3/2021 A. 96.96 P00401116MN- Project suspended effective 01
CONSTRUCTION OF CONCRETE B. 28,389,401.04 B. 7/11/2021 B. 11.77 CW1 (Permit to February 2021 due to pending
ROAD-JCT. DAVAO CITY C. 10/24/2021 C. -85.19 enter issues) completion of CY 2018 and 2019
DIVERSION ROAD-BUHANGIN- regular infra projects (both under
TIGATTO ROAD (BUHANGIN separate contract) on the same road
GALLERA SECTION), DAVAO stretch, due ton RROW problem
CITY within the project limit
ALZAM ENTERPRISES P00401116MN- Project suspended effective 01
INCORPORATED (FORMERLY: CW2 (Permit to February 2021 due to pending
ALZAM ENTERPRISES) (19113) enter issues) completion of CY 2018 and 2019
regular infra projects (both under
separate contract) on the same road
stretch, due ton RROW problem
within the project limit
27 20L00042 A. 51,855,670.47 A. 3/18/2020 A. 100.00 P00401106MN- Suspension of project effective 5/30/2020 project completed as of April 15,
CONSTRUCTION OF CONCRETE B. 51,855,670.47 B. 11/16/2020 B. 98.93 CW1 (Epidemic April 01, 2020 was administered 2021. time extension on process
ROAD-MAHAYAG-GATUNGAN- C. 1/15/2021 C. -1.07 (s)) due to implementation of once approved will be forwarded to
CALLAWA DIVERSION ROAD, community quarantine caused by BOC-PMD for approval.
DAVAO CITY COVID-19 Pandemic.
ABU CONSTRUCTION (22313)

PCMA 8/31/2021 5:01:21 PM Page 27 Of 105


27 20L00042 A. 51,855,670.47 A. 3/18/2020 A. 100.00 P00401106MN- pursuant to the Revised Omnibus 5/31/2020 project completed as of April 15,
CONSTRUCTION OF CONCRETE B. 51,855,670.47 B. 11/16/2020 B. 98.93 CW1 (Epidemic Guidelines and due to the 2021. time extension on process
ROAD-MAHAYAG-GATUNGAN- C. 1/15/2021 C. -1.07 (s)) declaration of General Community once approved will be forwarded to
CALLAWA DIVERSION ROAD, Quarantine (GCQ) in Davao BOC-PMD for approval.
DAVAO CITY Region.
ABU CONSTRUCTION (22313) P00401106MN- pursuant to the Revised Omnibus 5/31/2020 project completed as of April 15,
CW1 (Epidemic Guidelines and due to the 2021. time extension on process
(s)) declaration of General Community once approved will be forwarded to
Quarantine (GCQ) in Davao BOC-PMD for approval.
Region.
28 20L00043 A. 151,791,887.16 A. 12/28/2020 A. 99.86 Project is suspended
CONSTRUCTION OF CONCRETE B. 151,791,887.16 B. 9/23/2021 B. 85.70 as of August 10,
ROAD - BYPASS ROAD AT JCT. C. 9/23/2021 C. -14.16 2021.(In
DAANG MAHARLIKA ROAD - connection to WSO,
CARMELITE ROAD - MAHAYAG WRO
ST. - JCT. DAVAO CITY and CTE, revised
DIVERSION ROAD, DAVAO CITY construction
ER SALAC BUILDERS schedule is
CORPORATION (37948) / FFJJ 87.223% and incurred
CONSTRUCTION (16712) slippage of 0.189%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is September 09,
2021

PCMA 8/31/2021 5:01:21 PM Page 28 Of 105


29 20L00044 A. 144,339,891.99 A. 1/3/2021 A. 73.33 P00401121MN- Instructed the Contractor to Project is suspended
CONSTRUCTION OF CONCRETE B. 144,339,891.99 B. 10/29/2021 B. 53.64 CW1 conduct overtime works in order to as of August 16,
ROAD-FATIMA-MALABOG ROAD C. 10/29/2021 C. -19.69 (Unworkable site cover-up wasted time/days due to 2021.(In
(MALABOG-GUMITAN), PACKAGE condition (i.e. unworkable ground caused by bad connection to WSO,
D, DAVAO CITY unfavorable weather condition. WRO
DREIRICH BUILDERS (39521) / weather condition and CTE, revised
RELY CONSTRUCTION & at the project site, construction
SUPPLY (10433) access to project schedule is
site not 96.17% and incurred
passable)) slippage of -4.20%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is October 29,
2021
30 20L00045 A. 141,131,414.13 A. 5/18/2020 A. 100.00 P00401122MN- Ongoing negotiation with the Project is on going.
CONSTRUCTION OF CONCRETE B. 141,131,414.13 B. 3/13/2021 B. 63.28 CW1 (Permit to affected PAPs. (In
ROAD-FATIMA-MALABOG ROAD C. 3/13/2021 C. -36.72 enter issues) connection to WSO,
(MALABOG-GUMITAN), PACKAGE WRO
E, DAVAO CITY and CTE, revised
RELY CONSTRUCTION & construction
SUPPLY (10433) schedule is
63.15% and incurred
slippage of 0.08%)
Time
Extension Order is on
process. once
approved,
revisions in the pcma
will
be forwarded.
31 20L00046 A. 7,948,587.52 A. 4/13/2020 A. 100.00 P00431732MN- Suspension of project effective 5/30/2020 project on going/ revision for pcma is
CONSTRUCTION OF POLICE B. 7,948,587.52 B. 11/8/2020 B. 62.49 CW1 (Epidemic April 01, 2020 was administered on process once approved will be
STATION 7 BUILDING, C. 12/26/2020 C. -37.51 (s)) due to implementation of forwarded to BOC-PMD for approval
MALABOG, DAVAO CITY community quarantine caused by the negative slippage is 0.19% and
ROSBILL CONSTRUCTION AND COVID-19 Pandemic. the revised sched. accomplishment
SUPPLY (45622) 62.30 %.

PCMA 8/31/2021 5:01:21 PM Page 29 Of 105


31 20L00046 A. 7,948,587.52 A. 4/13/2020 A. 100.00 P00431732MN- pursuant to the Revised Omnibus 5/31/2020 project on going/ revision for pcma is
CONSTRUCTION OF POLICE B. 7,948,587.52 B. 11/8/2020 B. 62.49 CW1 (Epidemic Guidelines and due to the on process once approved will be
STATION 7 BUILDING, C. 12/26/2020 C. -37.51 (s)) declaration of General Community forwarded to BOC-PMD for approval
MALABOG, DAVAO CITY Quarantine (GCQ) in Davao the negative slippage is 0.19% and
ROSBILL CONSTRUCTION AND Region. the revised sched. accomplishment
SUPPLY (45622) 62.30 %.
P00431732MN- the respective Local Government 5/31/2020 project on going/ revision for pcma is
CW1 (Epidemic Unit issued Executive Order No. 20 on process once approved will be
(s)) and strictly implemented forwarded to BOC-PMD for approval
community quarantine to prevent the negative slippage is 0.19% and
the spread of COVID-19 virus the revised sched. accomplishment
inspection 62.30 %.
P00431732MN- pursuant to the Revised Omnibus 5/31/2020 project on going/ revision for pcma is
CW1 (Epidemic Guidelines and due to the on process once approved will be
(s)) declaration of General Community forwarded to BOC-PMD for approval
Quarantine (GCQ) in Davao the negative slippage is 0.19% and
Region. the revised sched. accomplishment
62.30 %.
P00431732MN- pursuant to the Revised Omnibus 5/31/2020 project on going/ revision for pcma is
CW1 (Epidemic Guidelines and due to the on process once approved will be
(s)) declaration of General Community forwarded to BOC-PMD for approval
Quarantine (GCQ) in Davao the negative slippage is 0.19% and
Region. the revised sched. accomplishment
62.30 %.
P00431732MN- Waiting for the result of requested 3/6/2021 project on going/ revision for pcma is
CW1 (Issuance of letter from PNP Director to City on process once approved will be
necessary Council that the building must be forwarded to BOC-PMD for approval
permits by LGU constructed to original location at the negative slippage is 0.19% and
(except MMDA)) PNP site. the revised sched. accomplishment
62.30 %.
P00431732MN- signed permit to enter 4/6/2021 project on going/ revision for pcma is
CW1 (Permit to on process once approved will be
enter issues) forwarded to BOC-PMD for approval
the negative slippage is 0.19% and
the revised sched. accomplishment
62.30 %.
P00431732MN- the final location of the PNP Police 4/6/2021 project on going/ revision for pcma is
CW1 (Issuance of Station building has been resolved on process once approved will be
necessary and will be constructed in its forwarded to BOC-PMD for approval
permits by LGU original location at PNP lot. the negative slippage is 0.19% and
(except MMDA)) the revised sched. accomplishment
62.30 %.

PCMA 8/31/2021 5:01:21 PM Page 30 Of 105


32 20L00047 A. 15,070,572.87 A. 3/11/2020 A. 100.00 P00431733MN- suspended effective April 01, 2020 5/31/2020 Project completed on 05 December
CONST. OF REGIONAL POLICE B. 15,070,572.87 B. 10/6/2020 B. 92.60 CW1 (Epidemic due to implementation of 2020 with corrections on some items
SECURITY AND PROTECTION C. 12/5/2020 C. -7.40 (s)) community quarantine caused by of works.
UNITS (RPSPUS) & COVID-19 Pandemic.
PRESIDENTIAL PROTECTION P00431733MN- Due to strict guidelines imposed by 9/15/2020 Project completed on 05 December
DIVISION (PPD) BUILDING CW1 (Epidemic LGU the contractor is having a 2020 with corrections on some items
UNDER THE POLICE SECURITY (s)) difficulties in construction activities of works.
AND PROTECTION GROUP due to limited resources. Once the
(PSPG)-PNP-RPSPU, DAVAO situation is normalize, they will be
CITY advise to provide additional inputs
JLACE BUILDERS to eliminate the negative slippage.
CORPORATION (FOR. JLA
CONSTRUCTION & SUPPLIES)
(24503)
33 20L00048 A. 93,589,892.52 A. 5/18/2020 A. 100.00 P00443088MN- The contractor was advised to "- Project completed 10 July 2021
CONSTRUCTION OF CONCRETE B. 93,589,892.52 B. 2/11/2021 B. 97.83 CW1 (Permit to work on section without road right- with minor defects.
ROAD AT SITIO BANBAN TO C. 2/24/2021 C. -2.17 enter issues) of-way problem. - Once equivalent Time Extension is
SITIO AYAGON, BRGY. LUMIAD, approved, the revised planned
PAQUIBATO DISTRICT, DAVAO schedule will be 100% and the
CITY incurred slippage 0.000%.
O. G. SANTOS CONSTRUCTION - Final Variation Order: As-Built Plan
(2050) Still on Process "
P00443088MN- Project suspended due to issuance 5/31/2020 "- Project completed 10 July 2021
CW1 (Epidemic of Davao Region Task Force with minor defects.
(s)) (RTF11-COVID 19) Order No. - Once equivalent Time Extension is
2020-001-B and strict approved, the revised planned
implementation of community schedule will be 100% and the
quarantine caused by COVID-19 incurred slippage 0.000%.
Pandemic, which greatly affects - Final Variation Order: As-Built Plan
the implementation of the project. Still on Process "
P00443088MN- Project resumed pursuant to the 5/31/2020 "- Project completed 10 July 2021
CW1 (Epidemic Revised Omnibus Guidelines and with minor defects.
(s)) due to the declaration of General - Once equivalent Time Extension is
Community Quarantine (GCQ) in approved, the revised planned
Davao Region. schedule will be 100% and the
incurred slippage 0.000%.
- Final Variation Order: As-Built Plan
Still on Process "

PCMA 8/31/2021 5:01:21 PM Page 31 Of 105


33 20L00048 A. 93,589,892.52 A. 5/18/2020 A. 100.00 P00443088MN- Project resumed effective May 31, 5/31/2020 "- Project completed 10 July 2021
CONSTRUCTION OF CONCRETE B. 93,589,892.52 B. 2/11/2021 B. 97.83 CW1 (Epidemic 2020 pursuant to the Revised with minor defects.
ROAD AT SITIO BANBAN TO C. 2/24/2021 C. -2.17 (s)) Omnibus Guidelines and due to the - Once equivalent Time Extension is
SITIO AYAGON, BRGY. LUMIAD, declaration of General Community approved, the revised planned
PAQUIBATO DISTRICT, DAVAO Quarantine (GCQ) in Davao schedule will be 100% and the
CITY Region. incurred slippage 0.000%.
O. G. SANTOS CONSTRUCTION - Final Variation Order: As-Built Plan
(2050) Still on Process "
34 20L00049 A. 93,799,805.99 A. 12/29/2020 A. 96.54 P00443090MN- Negotiation with the project project is suspended as of july 21,
CONSTRUCTION OF CONCRETE B. 93,799,805.99 B. 9/14/2021 B. 60.18 CW1 (Permit to affected persons and processing of 2021 due to Road right ofd way
ROAD-SITIO TULALIAN, SITIO C. 9/14/2021 C. -36.36 enter issues) documents related to RROW revision for time extension on
APALILI TO SITIO KINSE-KINSE, problem were done. process once approved will be
BRGY. COLOSAS, PAQUIBATO Tagging/inventory/identification of forwarded to BOC-PMD for approval.
DISTRICT, DAVAO CITY affected persons were done to The Revised accomplishment is
GEMMA CONSTRUCTION come up with a detailed estimates 65.463% actual is 65.541% the
SUPPLY, INC. that were used to be the basis of slippage to date is 0.078% the
(FORMERLY:GEMMA CON (5044) giving cash assistance to the revised expiry date is October 26,
affected residents. Once approved, 2021.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended July 21,
2021 due to RROW
P00443090MN- Negotiation with the project project is suspended as of july 21,
CW2 (Permit to affected persons and processing of 2021 due to Road right ofd way
enter issues) documents related to RROW revision for time extension on
problem were done. process once approved will be
Tagging/inventory/identification of forwarded to BOC-PMD for approval.
affected persons were done to The Revised accomplishment is
come up with a detailed estimates 65.463% actual is 65.541% the
that were used to be the basis of slippage to date is 0.078% the
giving cash assistance to the revised expiry date is October 26,
affected residents. Once approved, 2021.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended July 21,
2021 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 32 Of 105


35 20L00050 A. 93,581,936.48 A. 5/26/2020 A. 100.00 P00443091MN- The contractor was advised to "- Project Suspended effective 01
CONSTRUCTION OF CONCRETE B. 93,581,936.48 B. 2/19/2021 B. 90.59 CW1 (Permit to work on section without road right- July 2021 in view of unsigned Permit
ROAD FROM SITIO MELUYA, C. 2/19/2021 C. -9.41 enter issues) of-way problem. to Enter.
BRGY. MALABOG, PAQUIBATO - Once equivalent Time Extension is
DISTRICT TO SITIO POLOCON, approved, the revised planned
BRGY. LAMANAN, DAVAO CITY schedule will be 90.596% and the
ROSBILL CONSTRUCTION AND incurred slippage 4.200%."
SUPPLY (45622) / O. G. SANTOS P00443091MN- The contractor was advised to "- Project Suspended effective 01
CONSTRUCTION (2050) CW2 (Permit to work on section without road right- July 2021 in view of unsigned Permit
enter issues) of-way problem. to Enter.
- Once equivalent Time Extension is
approved, the revised planned
schedule will be 90.596% and the
incurred slippage 4.200%."
36 20L00051 A. 62,659,199.81 A. 1/3/2021 A. 49.16 P00400141MN- Negotiation with the Project 1. The project is suspended effective
ROAD WIDENING ALONG B. 62,659,199.81 B. 8/10/2021 B. 0.49 CW1 (Permit to Affected Persons (PAPs) and 18 February 2021 due to Road-
DAVAO-BUKIDNON ROAD C. 11/8/2021 C. -48.67 enter issues) processing of documents related to Right-of-Way problems (structures)
(S01406MN), K1691+113- RROW problem were done. within project limit.
K1692+117, DAVAO CITY Tagging/ inventory/ identification of 2. If Time Extension 1 due to WSO1
DREIRICH BUILDERS (39521) / Project Affected Persons (PAPs) (Road-Right-of-Way problem) will be
THREE W BUILDERS, INC. were done to come up with a approved, the reported slippage to
(10722) detailed estimate that were used to date is -2.177% where the planned
be the basis of just compensation accomplishment is 2.670%. Once
of the PAPs. approved, corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.
37 20L00052 A. 22,434,974.43 A. 12/28/2020 A. 100.00 P00401098MN- The contractor was advised to "- Project Suspended effective 01
CONSTRUCTION OF CONCRETE B. 22,434,974.43 B. 5/4/2021 B. 96.07 CW1 (Permit to work on section without road right- July 2021 in view of unsigned Permit
ROAD-ALTERNATE ROAD FROM C. 5/4/2021 C. -3.93 enter issues) of-way problem. to Enter.
REGION XI TO REGION X, - Once equivalent Time Extension is
PACKAGE 3C, DAVAO CITY approved, the revised planned
ROSBILL CONSTRUCTION AND schedule will be 96.065% and the
SUPPLY (45622) incurred slippage 0.153%."

PCMA 8/31/2021 5:01:21 PM Page 33 Of 105


38 20L00053 A. 52,830,363.55 A. 12/29/2020 A. 99.19 P00401462MN- Negotiation with the Project 1. The project was partially
REPLACEMENT OF BRIDGE (2 B. 52,830,363.55 B. 9/18/2021 B. 37.06 CW1 (Permit to Affected Persons (PAPs) and suspended due last 18 March 2021
INTO 4 LANES) - ANGALAN C. 9/18/2021 C. -62.13 enter issues) processing of documents related to due to Road-Right-of-Way problems
BRIDGE 1 (B00218MN) ALONG RROW problem were done. (structures) within Sta. 1690+748.50
DAVAO - BUKIDNON ROAD, Tagging/ inventory/ identification of to Sta. 1691+113.00 (R/S).
DAVAO CITY Project Affected Persons (PAPs) 2. If Time Extension 1 due to WSO1
P.L. SEBASTIAN were done to come up with a will be approved, the reported
CONSTRUCTION, INC. detailed estimate that were used to slippage to date is -0.448% where
(FORMERLY: P.L. SEBASTIAN be the basis of just compensation the planned accomplishment is
CONSTRUCTION) (35840) of the PAPs. 37.513%. Once approved,
corresponding request for revision in
the PCMA will be forwarded to PMD-
BOC for approval.
39 20L00054 A. 56,435,968.03 A. 12/22/2020 A. 96.31 P00401463MN- Negotiation with the Project 1. The project was suspended
REPLACEMENT OF BRIDGE (2 B. 56,435,968.03 B. 9/17/2021 B. 42.26 CW1 (Permit to Affected Persons (PAPs) and effective March 22, 2021 due to
INTO 4 LANES) - ANGALAN C. 9/17/2021 C. -54.05 enter issues) processing of documents related to Road right-of-way problem
BRIDGE 2 (B00217MN) ALONG RROW problem were done. (structures) since there are no more
DAVAO - BUKIDNON ROAD, Tagging/ inventory/ identification of workable areas on site.
DAVAO CITY Project Affected Persons (PAPs) 2. If Time Extension 1 due to WSO1
RAKKI CORPORATION (43053) / were done to come up with a (Road-Right-of-Way problem) will be
RELY CONSTRUCTION & detailed estimate that were used to approved, the reported slippage to
SUPPLY (10433) be the basis of just compensation date is -3.658% where the planned
of the PAPs. accomplishment is 45.922%. Once
approved, corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.
40 20L00055 A. 141,489,998.69 A. 12/29/2020 A. 46.92 P00401464MN- Negotiation with the Project 1. The project was partially
REPLACEMENT OF BRIDGE (2 B. 141,489,998.69 B. 10/29/2021 B. 35.21 CW1 (Permit to Affected Persons (PAPs) and suspended dated 08 March 2021
INTO 4 LANES) - ANGALAN C. 10/29/2021 C. -11.71 enter issues) processing of documents related to due to Road-Right-of-Way problem
BRIDGE 3 (B00216MN) ALONG RROW problem were done. (structures only) within Sta.
DAVAO - BUKIDNON ROAD, Tagging/ inventory/ identification of 1689+500.00 to Sta. 1690+365.50
DAVAO CITY Project Affected Persons (PAPs) (R/S).
ALGON ENGINEERING were done to come up with a 2. If Time Extension 1 due to WSO1
CONSTRUCTION CORPORATION detailed estimate that were used to will be approved, the reported
(00270) be the basis of just compensation slippage to date is -2.313% where
of the PAPs. the planned accomplishment is
37.530%. Once approved,
corresponding request for revision in
the PCMA will be forwarded to PMD-
BOC for approval.

PCMA 8/31/2021 5:01:21 PM Page 34 Of 105


41 20L00056 A. 98,541,236.68 A. 4/13/2020 A. 100.00 P00431330MN- Requested the contractor to -Project suspended effective 05 July
CONSTRUCTION OF CONCRETE B. 98,541,236.68 B. 1/3/2021 B. 68.91 CW1 (Delays in comply lacking attachments for the 2021 due to Road Right of Way
ROAD-SITIO BARACAYO-SITIO C. 3/4/2021 C. -31.09 approval of Time approval of Contract Time problem (structures and land) within
SAN AGUSTIN ROAD Suspension/Exte Extension. the project limit. Once project is
CONNECTING TO BANANA nsion) resumed and equivalent Time
PROCESSING AREA AND VEGIE Extension is approved revised
NOODLE PROCESSING FACILITY planned schedule will be 73.456%
IN SUPPORT TO BANANA AND and incurred negative slippage -
VEGETABLE INDUSTRIES, TORIL 4.478%. Revision in the PCMA on
DISTRICT, DAVAO CITY process, waiting for approved time
DREIRICH BUILDERS (39521) / extension in view of approved
RELY CONSTRUCTION & suspension and resumption order.
SUPPLY (10433) P00431330MN- The respective Local Government 7/1/2020 -Project suspended effective 05 July
CW1 (Epidemic Unit issued Executive Order No.20 2021 due to Road Right of Way
(s)) and strictly implemented problem (structures and land) within
community quarantine to prevent the project limit. Once project is
the spread of COVID-19 virus resumed and equivalent Time
inspection. Extension is approved revised
planned schedule will be 73.456%
and incurred negative slippage -
4.478%. Revision in the PCMA on
process, waiting for approved time
extension in view of approved
suspension and resumption order.
P00431330MN- On-going negotiation of the 4/15/2021 -Project suspended effective 05 July
CW1 (Permit to affected structures and land c/o 2021 due to Road Right of Way
enter issues) Legal Division. problem (structures and land) within
the project limit. Once project is
resumed and equivalent Time
Extension is approved revised
planned schedule will be 73.456%
and incurred negative slippage -
4.478%. Revision in the PCMA on
process, waiting for approved time
extension in view of approved
suspension and resumption order.

PCMA 8/31/2021 5:01:21 PM Page 35 Of 105


41 20L00056 A. 98,541,236.68 A. 4/13/2020 A. 100.00 P00431330MN- On going negotiation with the 4/16/2021 -Project suspended effective 05 July
CONSTRUCTION OF CONCRETE B. 98,541,236.68 B. 1/3/2021 B. 68.91 CW1 (Permit to affected land owners. 2021 due to Road Right of Way
ROAD-SITIO BARACAYO-SITIO C. 3/4/2021 C. -31.09 enter issues) problem (structures and land) within
SAN AGUSTIN ROAD the project limit. Once project is
CONNECTING TO BANANA resumed and equivalent Time
PROCESSING AREA AND VEGIE Extension is approved revised
NOODLE PROCESSING FACILITY planned schedule will be 73.456%
IN SUPPORT TO BANANA AND and incurred negative slippage -
VEGETABLE INDUSTRIES, TORIL 4.478%. Revision in the PCMA on
DISTRICT, DAVAO CITY process, waiting for approved time
DREIRICH BUILDERS (39521) / extension in view of approved
RELY CONSTRUCTION & SUPPL suspension and resumption order.
42 20L00057 A. 8,759,083.44 A. 9/7/2020 A. 100.00 project completed as of 18 June
CONSTRUCTION OF POLICE B. 8,759,083.44 B. 4/4/2021 B. 98.98 2021 with some correction of item of
STATION 12 BUILDING, C. 4/4/2021 C. -1.02 works.
MARILOG, DAVAO CITY
ROSBILL CONSTRUCTION AND
SUPPLY (45622)
43 20L00058 A. 100,213,678.90 A. 1/3/2021 A. 91.57 P00400295MN- The contractor requested for Work 5/1/2021 Project is on-going.
ROAD WIDENING ON SPECIFIC B. 100,213,678.90 B. 10/3/2021 B. 83.23 CW1 (Permit to Suspension Order. Negotiation with (Resumed as
LOCATIONS ALONG ASUNCION- C. 10/3/2021 C. -8.34 enter issues) the project affected persons and of May 01,2021)
SAN ISIDRO-LAAK-VERUELA processing of documents related to (In
ROAD(S00097MN), K1479+981 RROW problem were done. connection to WSO, WRO
MAER SUMMIT KONSTRUKT CO. and CTE, revised
(25262) construction schedule is
32.78% and incurred
slippage of 50.45%) Time
Extension Order is on
process. once approved,
revisions in the PCMA will
be forwarded. Revised
Contract Expiry Date is
December 31, 2021.
44 20L00059 A. 87,424,815.56 A. 3/23/2020 A. 99.99 P00400296MN- Negotiation with the project Project suspended effective June 24,
ROAD WIDENING ON SPECIFIC B. 87,424,815.56 B. 12/1/2020 B. 82.11 CW1 (Permit to affected persons and processing of 2021 due to unsettled Road right of
LOCATIONS ALONG TAGUM- C. 1/30/2021 C. -17.88 enter issues) documents related to RROW way problem encountered during
PANABO CIRCUMFERENTIAL problems were done. The construction activities. Once project
ROAD (S01359MN), DAVAO DEL contractor requested for Work is resumed and equivalent Time
NO Suspension Order No. 1 due to Extension is approved, the revised
P.L. SEBASTIAN encountered RROW issues. Once planned schedule will be 81.070%
CONSTRUCTION, INC. Contract Time Extension due to and the incurred slippage 1.073%.
(FORMERLY: P.L. SEBASTIAN WSO is approved, corresponding Revision in the PCMA on process,
CONSTRUCTION) (35840) Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.
PCMA 8/31/2021 5:01:21 PM Page 36 Of 105
44 20L00059 A. 87,424,815.56 A. 3/23/2020 A. 99.99 P00400296MN- The Contractor requested for Work 5/31/2020 Project suspended effective June 24,
ROAD WIDENING ON SPECIFIC B. 87,424,815.56 B. 12/1/2020 B. 82.11 CW1 (Epidemic Suspension Order No.1 due to 2021 due to unsettled Road right of
LOCATIONS ALONG TAGUM- C. 1/30/2021 C. -17.88 (s)) implementation of community way problem encountered during
PANABO CIRCUMFERENTIAL quarantine caused by COVID-19. construction activities. Once project
ROAD (S01359MN), DAVAO DEL is resumed and equivalent Time
NO Extension is approved, the revised
P.L. SEBASTIAN planned schedule will be 81.070%
CONSTRUCTION, INC. and the incurred slippage 1.073%.
(FORMERLY: P.L. SEBASTIAN Revision in the PCMA on process,
CONSTRUCTION) (35840) waiting for approved time extension
in view of the approved suspension
and resumption order.
P00400296MN- The contractor requested for Work 4/13/2021 Project suspended effective June 24,
CW1 (Permit to Suspension Order No. 2 due to 2021 due to unsettled Road right of
enter issues) encountered RROW problems. way problem encountered during
construction activities. Once project
is resumed and equivalent Time
Extension is approved, the revised
planned schedule will be 81.070%
and the incurred slippage 1.073%.
Revision in the PCMA on process,
waiting for approved time extension
in view of the approved suspension
and resumption order.
45 20L00060 A. 98,756,770.22 A. 3/23/2020 A. 100.00 P00401153MN- Suspension of project effective 5/30/2020 ject completed as of July 31, 2021
CONSTRUCTION OF GRAVEL B. 98,756,770.22 B. 12/13/2020 B. 99.85 CW1 (Epidemic April 01, 2020 was administered with minor correction of items of
ROAD-ALTERNATE ROAD FROM C. 2/11/2021 C. -0.15 (s)) due to implementation of work/ Revision for PCMA is on
REGION XI TO REGION X, community quarantine caused by process once aprroved will be
PACKAGE A, DAVAO DEL NORTE COVID-19 Pandemic. forwarded to BOC-PMD for approval.
COASTLAND CONSTRUCTION & P00401153MN- pursuant to the Revised Omnibus 5/31/2020 ject completed as of July 31, 2021
DEVELOPMENT CORP. (11487) CW1 (Epidemic Guidelines and due to the with minor correction of items of
(s)) declaration of General Community work/ Revision for PCMA is on
Quarantine (GCQ) in Davao process once aprroved will be
Region. forwarded to BOC-PMD for approval.
P00401153MN- the respective Local Government 5/31/2020 ject completed as of July 31, 2021
CW1 (Epidemic Unit issued Executive Order No. 20 with minor correction of items of
(s)) and strictly implemented work/ Revision for PCMA is on
community quarantine to prevent process once aprroved will be
the spread of COVID-19 virus forwarded to BOC-PMD for approval.
inspection

PCMA 8/31/2021 5:01:21 PM Page 37 Of 105


45 20L00060 A. 98,756,770.22 A. 3/23/2020 A. 100.00 P00401153MN- the respective Local Government 5/31/2020 ject completed as of July 31, 2021
CONSTRUCTION OF GRAVEL B. 98,756,770.22 B. 12/13/2020 B. 99.85 CW1 (Epidemic Unit issued Executive Order No. 20 with minor correction of items of
ROAD-ALTERNATE ROAD FROM C. 2/11/2021 C. -0.15 (s)) and strictly implemented work/ Revision for PCMA is on
REGION XI TO REGION X, community quarantine to prevent process once aprroved will be
PACKAGE A, DAVAO DEL NORTE the spread of COVID-19 virus forwarded to BOC-PMD for approval.
COASTLAND CONSTRUCTION & inspection
DEVELOPMENT CORP. (11487) P00401153MN- pursuant to the Revised Omnibus 5/31/2020 ject completed as of July 31, 2021
CW1 (Epidemic Guidelines and due to the with minor correction of items of
(s)) declaration of General Community work/ Revision for PCMA is on
Quarantine (GCQ) in Davao process once aprroved will be
Region. forwarded to BOC-PMD for approval.
P00401153MN- pursuant to the Revised Omnibus 5/31/2020 ject completed as of July 31, 2021
CW1 (Epidemic Guidelines and due to the with minor correction of items of
(s)) declaration of General Community work/ Revision for PCMA is on
Quarantine (GCQ) in Davao process once aprroved will be
Region. forwarded to BOC-PMD for approval.
P00401153MN- pursuant to the Revised Omnibus 5/31/2020 ject completed as of July 31, 2021
CW1 (Epidemic Guidelines and due to the with minor correction of items of
(s)) declaration of General Community work/ Revision for PCMA is on
Quarantine (GCQ) in Davao process once aprroved will be
Region. forwarded to BOC-PMD for approval.
46 20L00061 A. 178,463,777.88 A. 4/13/2020 A. 100.00 P00401144MN- Negotiation with the Project Project was suspended dated 25
CONSTRUCTION OF CONCRETE B. 178,463,777.88 B. 2/26/2021 B. 1.13 CW1 (Permit to Affected Persons (PAPs) and June 2020 due to road right-of-way
BRIDGE-CARMEN-TAGUM CITY C. 7/22/2021 C. -98.87 enter issues) processing of RROW documents problems.
COASTAL ROAD, PACKAGE A, are still on going. Tagging, Once the project is resumed and
DAVAO DEL NORTE inventory, and identification of equivalent Time Extension is
ULTICON BUILDERS, INC. affected persons were done to approved, revised planned schedule
(17267) come up with detailed estimates will be 1.07% and incurred slippage
that were used as basis for just of 0.062%.
compensation of the PAPs
P00401144MN- Negotiation with the Project Project was suspended dated 25
CW2 (Permit to Affected Persons (PAPs) and June 2020 due to road right-of-way
enter issues) processing of RROW documents problems.
are still on going. Tagging, Once the project is resumed and
inventory, and identification of equivalent Time Extension is
affected persons were done to approved, revised planned schedule
come up with detailed estimates will be 1.07% and incurred slippage
that were used as basis for just of 0.062%.
compensation of the PAPs

PCMA 8/31/2021 5:01:21 PM Page 38 Of 105


46 20L00061 A. 178,463,777.88 A. 4/13/2020 A. 100.00 P00401144MN- Issued work suspension order to 5/31/2020 Project was suspended dated 25
CONSTRUCTION OF CONCRETE B. 178,463,777.88 B. 2/26/2021 B. 1.13 CW1 (Epidemic the contractor dated 01 April 2020 June 2020 due to road right-of-way
BRIDGE-CARMEN-TAGUM CITY C. 7/22/2021 C. -98.87 (s)) due to implementation of problems.
COASTAL ROAD, PACKAGE A, community quarantine caused by Once the project is resumed and
DAVAO DEL NORTE COVID-19. equivalent Time Extension is
ULTICON BUILDERS, INC. approved, revised planned schedule
(17267) will be 1.07% and incurred slippage
of 0.062%.
P00401144MN- Issued work suspension order to 5/31/2020 Project was suspended dated 25
CW2 (Epidemic the contractor dated 01 April 2020 June 2020 due to road right-of-way
(s)) due to implementation of problems.
community quarantine caused by Once the project is resumed and
COVID-19. equivalent Time Extension is
approved, revised planned schedule
will be 1.07% and incurred slippage
of 0.062%.
47 20L00062 A. 118,574,864.88 A. 3/23/2020 A. 100.00 P00401112MN- The contractor requested for Work Project is on-going.
ROAD WIDENING-NABUNTURAN- B. 118,574,864.88 B. 12/13/2020 B. 78.72 CW1 (Permit to Suspension Order (In
NEW CORELLA-TAGUM ROAD C. 2/11/2021 C. -21.28 enter issues) connection to WSO, WRO
(TAGUM-NEW CORELLA and CTE, revised
SECTION), DAVAO DEL NORTE construction schedule is
GP & H CONSTRUCTION 78.401% and incurred
INCORPORATED (FORMERLY: slippage of 0.152%) Time
GP & H CONSTRUCTION & Extension Order is on
SUPPLY) (36141) process. once approved,
revisions in the PCMA will
be forwarded. Revised
Contract Expiry Date is
October 04, 2021.
P00401112MN- The contractor requested for Work 5/31/2020 Project is on-going.
CW1 (Epidemic Suspension Order No.1 due to the (In
(s)) implementation of Enhanced connection to WSO, WRO
Community Quarantine caused by and CTE, revised
Covid-19 pandemic. construction schedule is
78.401% and incurred
slippage of 0.152%) Time
Extension Order is on
process. once approved,
revisions in the PCMA will
be forwarded. Revised
Contract Expiry Date is
October 04, 2021.

PCMA 8/31/2021 5:01:21 PM Page 39 Of 105


48 20L00063 A. 115,715,777.88 A. 3/25/2020 A. 100.00 P00401111MN- The contractor requested for Work 5/31/2020 Project completed with minor
ROAD WIDENING-TAGUM CITY B. 115,715,777.88 B. 1/2/2021 B. 99.83 CW1 (Epidemic Suspension Order No.1 due to the defects.
BYPASS ROAD (CANOCOTAN- C. 3/3/2021 C. -0.17 (s)) implementation of Enhanced
SAN MIGUEL-PAGSABANGAN), Community Quarantine caused by
PACKAGE C, DAVAO DEL NORTE Covid-19 pandemic
ULTICON BUILDERS, INC. P00401111MN- Ongoing negotiations with the 4/16/2021 Project completed with minor
(17267) CW1 (Permit to affected Project Affected Persons. defects.
enter issues)

P00401111MN- Instructed the Contractor to 8/14/2021 Project completed with minor


CW1 conduct overtime works in order to defects.
(Unworkable site cover-up wasted time/days due to
condition (i.e. unworkable ground caused by bad
unfavorable weather condition.
weather condition
at the project site,
access to project
site not
passable))
49 20L00064 A. 135,355,777.88 A. 10/28/2020 A. 100.00 Project is completed
CONSTRUCTION OF GRAVEL B. 135,355,777.88 B. 8/23/2021 B. 91.50 as of
ROAD-BUKIDNON- C. 8/23/2021 C. -8.50 February 28, 2021.
COMPOSTELA VALLEY ROAD, As-built for approval
BRGY. NAMNAM, SAN and
FERNANDO, BUKIDNON-LAAK Final Variation will be
COMPOSTELA VALLEY, prepare, once
PACKAGE 6, DAVAO DEL NORTE approved
ULTICON BUILDERS, INC. corresponding
(17267) request for
revision of in the
PCMA
will be forwarded to
PMDBOC
for approval.

PCMA 8/31/2021 5:01:21 PM Page 40 Of 105


50 20L00066 A. 56,163,486.86 A. 3/23/2020 A. 100.00 P00420620MN- June 16, 2020: The contractor Project is suspended
CONSTRUCTION OF DIKE B. 56,163,486.86 B. 12/21/2020 B. 1.63 CW1 (Permit to requested for Work Suspension as of June 26,
ALONG TAGUM LIBUGANON C. 2/19/2021 C. -98.37 enter issues) Order due to RROW Problem 2020.(In
RIVER, BRGY. BINCUNGAN- connection to WSO,
BRGY. BUSAON, TAGUM CITY, WRO
DAVAO DEL NORTE and CTE, revised
D.L CERVANTES construction
CONSTRUCTION CORPORATION schedule is
(FORMERLY: (13799) / GP & H 0.587% and incurred
CONSTRUCTION slippage of -1.044%)
INCORPORATED (FORMERLY: Time Extension
GP & H CONSTRUCTION & Order is
SUPPLY) (36141) on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is April 27,
2022
P00420620MN- The contractor requested for Work 5/31/2020 Project is suspended
CW1 (Epidemic Suspension Order No.1 due to the as of June 26,
(s)) implementation of Enhanced 2020.(In
Community Quarantine caused by connection to WSO,
Covid-19 pandemic. WRO
and CTE, revised
construction
schedule is
0.587% and incurred
slippage of -1.044%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is April 27,
2022

PCMA 8/31/2021 5:01:21 PM Page 41 Of 105


51 20L00067 A. 55,925,609.22 A. 6/16/2020 A. 100.00 Project Completed dated May 15,
CONSTRUCTION OF HIJO RIVER B. 54,742,967.85 B. 3/16/2021 B. 56.00 2021 with minor corrections on-
FLOOD CONTROL FROM BRGY. C. 5/15/2021 C. -44.00 going.
MAGDUM-BRGY. EST-
BRGY.APOKON, TAGUM CITY,
DAVAO DEL NORTE
MAC BUILDERS (7249)
52 20L00069 A. 186,354,777.88 A. 10/28/2020 A. 100.00 P00442865MN- On going negotiation with the Proeject suspended dated 16
CONSTRUCTION OF GRAVEL B. 186,354,777.88 B. 8/23/2021 B. 0.75 CW1 (Permit to affected lot owner December 2020 due to RROW
ROAD-CARMEN-TAGUM CITY C. 8/23/2021 C. -99.25 enter issues) Problems.
COASTAL ROAD, PACKAGE B, Once the project is resumed and
DAVAO DEL NORTE equivalent Time Extension is
ULTICON BUILDERS, INC. approved, revised planned schedule
(17267) will be 1.07% and incurred slippage
of 0.062%.
53 20L00070 A. 187,847,777.88 A. 10/28/2020 A. 100.00 P00442866MN- Ongoing negotiation with the Project suspended dated 16
CONSTRUCTION OF GRAVEL B. 187,847,777.88 B. 8/23/2021 B. 0.39 CW1 (Permit to affected lot owner December 2020 due to RROW
ROAD-CARMEN-TAGUM CITY C. 8/23/2021 C. -99.61 enter issues) Problems
COASTAL ROAD, PACKAGE C, Once the project is resumed and
DAVAO DEL NORTE equivalent Time Extension is
ULTICON BUILDERS, INC. approved, revised planned schedule
(17267) will be 0.30% and incurred slippage
of 0.08%.
54 20L00071 A. 60,961,611.60 A. 12/15/2020 A. 100.00 P00401395MN- On-going negotiations with the Project suspended effective March
ROAD WIDENING ALONG B. 60,961,611.60 B. 7/15/2021 B. 20.97 CW1 (Permit to affected owners in coordination 16, 2021 due to encountered road
BABAK-SAMAL-KAPUTIAN ROAD C. 7/15/2021 C. -79.03 enter issues) with the LGU Officials. right-of-way (improvements) within
(S00095MN), DAVAO DEL project limits. Once project is
NORTE, K1502+249-K1503+750 resumed and equivalent Time
MAC BUILDERS (7249) Extension is approved, revised
planned schedule will be 20.705%
and incurred slippage 0.267%.
Revision in the PCMA is on process.
55 20L00073 A. 150,279,038.86 A. 6/16/2020 A. 100.00 P00401113MN- Corresponding documents of project is suspended as of June
CONSTRUCTION OF CONCRETE B. 150,279,038.86 B. 4/11/2021 B. 94.00 CW1 (Changes in Variation Order No. 1 was 1,2021 revision for time extension
ROAD-JCT. TAGUM-PANABO C. 4/11/2021 C. -6.00 approved complied to suit actual site on process once approved will be
CIRCUMFERENTIAL ROAD- plans/designs) condition. Once approved, Request forwarded to BOC-PMD for approval.
MALITBOG-KASILAK TO JCT. for Revision in the PCMA will then The Revised accomplishment is
CONSOLACION, DAVAO DEL be sent to the BOC-PMD for 93.798% actual is 94.00% the
NORTE approval. slippage to date is 0.206% the
MAC BUILDERS (7249) revised expiry date is September 10,
2021.

PCMA 8/31/2021 5:01:21 PM Page 42 Of 105


55 20L00073 A. 150,279,038.86 A. 6/16/2020 A. 100.00 P00401113MN- pursuant to the Revised Omnibus 5/31/2020 project is suspended as of June
CONSTRUCTION OF CONCRETE B. 150,279,038.86 B. 4/11/2021 B. 94.00 CW1 (Epidemic Guidelines and due to the 1,2021 revision for time extension
ROAD-JCT. TAGUM-PANABO C. 4/11/2021 C. -6.00 (s)) declaration of General Community on process once approved will be
CIRCUMFERENTIAL ROAD- Quarantine (GCQ) in Davao forwarded to BOC-PMD for approval.
MALITBOG-KASILAK TO JCT. Region. The Revised accomplishment is
CONSOLACION, DAVAO DEL 93.798% actual is 94.00% the
NORTE slippage to date is 0.206% the
MAC BUILDERS (7249) revised expiry date is September 10,
2021.
56 20L00075 A. 46,802,500.00 A. 1/3/2021 A. 100.00 P00401466MN- On-going negotiations with the Project suspended effective February
CONSTRUCTION OF BINOLING B. 46,802,500.00 B. 7/31/2021 B. 22.05 CW1 (Permit to affected owners in coordination 01, 2021 due to encountered road
PARALLEL BRIDGE ALONG C. 7/31/2021 C. -77.95 enter issues) with the LGU Officials. right-of-way (improvements) within
BABAK - SAMAL - KAPUTIAN RD., project limits. Once project is
DAVAO DEL NORTE resumed and equivalent Time
HI-VIEW RESOURCES & Extension is approved, revised
DEVELOPMENT CORPORATION planned schedule will be 13.903%
(28505) / RELY CONSTRUCTION and incurred slippage 8.121%.
& SUPPLY (10433) Revision in the PCMA is on process.
57 20L00076 A. 140,018,140.09 A. 3/24/2020 A. 100.00 P00431444MN- Construction activities will be 7/13/2020 Project completed effective August
CONST. OF CONCRETE ROAD- B. 140,018,140.09 B. 1/7/2021 B. 87.28 CW1 (Epidemic suspended until further notice or 05, 2021. Revision in the PCMA is
ISLAND GARDEN CITY OF C. 6/19/2021 C. -12.72 (s)) when the situation normalizes on process.
SAMAL (IGACOS) again.
CIRCUMFERENTIAL ROAD, HISTORY:
DAVAO DEL NORTE 1. Project resumed effective July 01,
ULTICON BUILDERS, INC. 2021. Revision in the PCMA is on
(17267) process.
2.Project suspended effective March
16, 2021 due to encountered road
right-of-way (improvements) within
project limits. Once project is
resumed and equivalent Time
Extension is approved, revised
planned schedule will be 87.248%
and incurred slippage 0.030%.
3.) Project resumed effective July 13,
2020
4.) Project suspended due to
issuance of Executive Order No. 20
and strict implementation of
community quarantine caused by
COVID-19 pandemic.

PCMA 8/31/2021 5:01:21 PM Page 43 Of 105


57 20L00076 A. 140,018,140.09 A. 3/24/2020 A. 100.00 P00431444MN- On-going negotiations with the 7/1/2021 Project completed effective August
CONST. OF CONCRETE ROAD- B. 140,018,140.09 B. 1/7/2021 B. 87.28 CW1 (Permit to affected owners in coordination 05, 2021. Revision in the PCMA is
ISLAND GARDEN CITY OF C. 6/19/2021 C. -12.72 enter issues) with the LGU Officials. on process.
SAMAL (IGACOS)
CIRCUMFERENTIAL ROAD, HISTORY:
DAVAO DEL NORTE 1. Project resumed effective July 01,
ULTICON BUILDERS, INC. 2021. Revision in the PCMA is on
(17267) process.
2.Project suspended effective March
16, 2021 due to encountered road
right-of-way (improvements) within
project limits. Once project is
resumed and equivalent Time
Extension is approved, revised
planned schedule will be 87.248%
and incurred slippage 0.030%.
3.) Project resumed effective July 13,
2020
4.) Project suspended due to
issuance of Executive Order No. 20
and strict implementation of
community quarantine caused by
COVID-19 pandemic.
58 20L00077 A. 56,002,576.78 A. 4/13/2020 A. 100.00 P00431445MN- On-going negotiations with the Project resumed effective July 01,
CONSTRUCTION OF CONCRETE B. 56,002,576.78 B. 11/3/2020 B. 40.52 CW1 (Permit to affected owners in coordination 2021. Revision in the PCMA is on
ROAD-TALIKUD C. 7/11/2021 C. -59.48 enter issues) with the LGU Officials. process.
CIRCUMFERENTIAL ROAD,
IGACOS, DAVAO DEL NORTE HISTORY:
MAC BUILDERS (7249) 1.)Project suspended effective
February 01, 2021 due to
encountered road right-of-way
problem (improvements) within Sta.
3+620.000 to Sta. 4+274.109. Once
project is resumed and equivalent
Time Extension is approved, revised
planned schedule will be 37.523%
and incurred slippage 2.999%.
Revision in the PCMA is on process.
2.)Project resumed effective
September 01,2020. Revision on the
PCMA is on process and Contract
Time Extension is on process.

PCMA 8/31/2021 5:01:21 PM Page 44 Of 105


58 20L00077 A. 56,002,576.78 A. 4/13/2020 A. 100.00 P00431445MN- Construction activities will be 9/1/2020 Project resumed effective July 01,
CONSTRUCTION OF CONCRETE B. 56,002,576.78 B. 11/3/2020 B. 40.52 CW1 (Epidemic suspended until further notice or 2021. Revision in the PCMA is on
ROAD-TALIKUD C. 7/11/2021 C. -59.48 (s)) when the situation normalizes process.
CIRCUMFERENTIAL ROAD, again.
IGACOS, DAVAO DEL NORTE HISTORY:
MAC BUILDERS (7249) 1.)Project suspended effective
February 01, 2021 due to
encountered road right-of-way
problem (improvements) within Sta.
3+620.000 to Sta. 4+274.109. Once
project is resumed and equivalent
Time Extension is approved, revised
planned schedule will be 37.523%
and incurred slippage 2.999%.
Revision in the PCMA is on process.
2.)Project resumed effective
September 01,2020. Revision on the
PCMA is on process and Contract
Time Extension is on process.
P00431445MN- On-going negotiations with the 12/4/2020 Project resumed effective July 01,
CW1 (Permit to affected owners in coordination 2021. Revision in the PCMA is on
enter issues) with the LGU Officials. process.

HISTORY:
1.)Project suspended effective
February 01, 2021 due to
encountered road right-of-way
problem (improvements) within Sta.
3+620.000 to Sta. 4+274.109. Once
project is resumed and equivalent
Time Extension is approved, revised
planned schedule will be 37.523%
and incurred slippage 2.999%.
Revision in the PCMA is on process.
2.)Project resumed effective
September 01,2020. Revision on the
PCMA is on process and Contract
Time Extension is on process.

PCMA 8/31/2021 5:01:21 PM Page 45 Of 105


58 20L00077 A. 56,002,576.78 A. 4/13/2020 A. 100.00 P00431445MN- On-going negotiations with the 7/1/2021 Project resumed effective July 01,
CONSTRUCTION OF CONCRETE B. 56,002,576.78 B. 11/3/2020 B. 40.52 CW1 (Demolition affected owners in coordination 2021. Revision in the PCMA is on
ROAD-TALIKUD C. 7/11/2021 C. -59.48 or other clearing with the LGU Officials. process.
CIRCUMFERENTIAL ROAD, related issues
IGACOS, DAVAO DEL NORTE (except utilities)) HISTORY:
MAC BUILDERS (7249) 1.)Project suspended effective
February 01, 2021 due to
encountered road right-of-way
problem (improvements) within Sta.
3+620.000 to Sta. 4+274.109. Once
project is resumed and equivalent
Time Extension is approved, revised
planned schedule will be 37.523%
and incurred slippage 2.999%.
Revision in the PCMA is on process.
2.)Project resumed effective
September 01,2020. Revision on the
PCMA is on process and Contract
Time Extension is on process.
59 20L00079 A. 26,256,313.09 A. 3/23/2020 A. 100.00 P00431728MN- Construction activities will be 7/13/2020 Project completed effective August
CONSTRUCTION OF IGACOS- B. 26,256,313.09 B. 1/16/2021 B. 94.15 CW1 (Epidemic suspended until further notice or 31, 2021. Revision in the PCMA is
CPO BUILDING, IGACOS, DAVAO C. 4/29/2021 C. -5.85 (s)) when the situation normalizes on process.
DEL NORTE again.
TWO DEGREES HISTORY:
CONSTRUCTION AND SUPPLY 1. Project resumed effective July 01,
(36734) 2021. Revision in the PCM is on
process.
2. Project suspended effective
February 01, 2021 due to non-
availability of materials in the locale.
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 75.344% and incurred
slippage 15.200%.
Revision in the PCMA is on process.
3. Project resumed effective July 13,
2020. Revision on the PCMA is on
process and Contract Time
Extension is on process.

PCMA 8/31/2021 5:01:21 PM Page 46 Of 105


59 20L00079 A. 26,256,313.09 A. 3/23/2020 A. 100.00 P00431728MN- Construction activities will be 7/1/2021 Project completed effective August
CONSTRUCTION OF IGACOS- B. 26,256,313.09 B. 1/16/2021 B. 94.15 CW1 (Shortage / suspended until programmed 31, 2021. Revision in the PCMA is
CPO BUILDING, IGACOS, DAVAO C. 4/29/2021 C. -5.85 Non-availability of materials were already purchased on process.
DEL NORTE construction and transported in the area.
TWO DEGREES materials in the HISTORY:
CONSTRUCTION AND SUPPLY market/locality) 1. Project resumed effective July 01,
(36734) 2021. Revision in the PCM is on
process.
2. Project suspended effective
February 01, 2021 due to non-
availability of materials in the locale.
Once project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 75.344% and incurred
slippage 15.200%.
Revision in the PCMA is on process.
3. Project resumed effective July 13,
2020. Revision on the PCMA is on
process and Contract Time
Extension is on process.
60 20L00081 A. 81,763,967.34 A. 4/13/2020 A. 100.00 P00401108MN- on-going negotiation with the -Project suspended effective 16
ROAD WIDENING - BYPASS B. 81,763,967.34 B. 1/5/2021 B. 67.06 CW1 (Permit to affected structures November 2020 due to Road Right-
ROAD, JCT. MATANAO (ALONG C. 2/19/2021 C. -32.94 enter issues) of-Way problem, Once project is
DAVAO - COTABATO ROAD) - resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 62.21% and
PACKAGE A, DAVAO DEL SUR incurred negative slippage of -1.55%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- on-going negotiation with the -Project suspended effective 16
CW2 (Permit to affected structures November 2020 due to Road Right-
enter issues) of-Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 47 Of 105


60 20L00081 A. 81,763,967.34 A. 4/13/2020 A. 100.00 P00401108MN- on-going negotiation with the -Project suspended effective 16
ROAD WIDENING - BYPASS B. 81,763,967.34 B. 1/5/2021 B. 67.06 CW3 (Permit to affected structures November 2020 due to Road Right-
ROAD, JCT. MATANAO (ALONG C. 2/19/2021 C. -32.94 enter issues) of-Way problem, Once project is
DAVAO - COTABATO ROAD) - resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 62.21% and
PACKAGE A, DAVAO DEL SUR incurred negative slippage of -1.55%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- on-going negotiation with the -Project suspended effective 16
CW4 (Permit to affected structures November 2020 due to Road Right-
enter issues) of-Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- on-going negotiation with the -Project suspended effective 16
CW5 (Permit to affected structures November 2020 due to Road Right-
enter issues) of-Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- Situational report was rendered by 5/31/2020 -Project suspended effective 16
CW2 (Epidemic the Project Engineer concerning November 2020 due to Road Right-
(s)) some issues raised by the of-Way problem, Once project is
Contractor in relation to the resumed and equivalent times
implementation of project. extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 48 Of 105


60 20L00081 A. 81,763,967.34 A. 4/13/2020 A. 100.00 P00401108MN- Situational report was rendered by 5/31/2020 -Project suspended effective 16
ROAD WIDENING - BYPASS B. 81,763,967.34 B. 1/5/2021 B. 67.06 CW3 (Epidemic the Project Engineer concerning November 2020 due to Road Right-
ROAD, JCT. MATANAO (ALONG C. 2/19/2021 C. -32.94 (s)) some issues raised by the of-Way problem, Once project is
DAVAO - COTABATO ROAD) - Contractor in relation to the resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY implementation of project. extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 62.21% and
PACKAGE A, DAVAO DEL SUR incurred negative slippage of -1.55%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- Situational report was rendered by 5/31/2020 -Project suspended effective 16
CW1 (Epidemic the Project Engineer concerning November 2020 due to Road Right-
(s)) some issues raised by the of-Way problem, Once project is
Contractor in relation to the resumed and equivalent times
implementation of project extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- Situational report was rendered by 5/31/2020 -Project suspended effective 16
CW4 (Epidemic the Project Engineer concerning November 2020 due to Road Right-
(s)) some issues raised by the of-Way problem, Once project is
Contractor in relation to the resumed and equivalent times
implementation of project. extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- Situational report was rendered by 5/31/2020 -Project suspended effective 16
CW5 (Epidemic the Project Engineer concerning November 2020 due to Road Right-
(s)) some issues raised by the of-Way problem, Once project is
Contractor in relation to the resumed and equivalent times
implementation of project. extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 49 Of 105


60 20L00081 A. 81,763,967.34 A. 4/13/2020 A. 100.00 P00401108MN- Reminder/ Warning letters were 11/16/2020 -Project suspended effective 16
ROAD WIDENING - BYPASS B. 81,763,967.34 B. 1/5/2021 B. 67.06 CW1 (Slow given to the contractor to eliminate November 2020 due to Road Right-
ROAD, JCT. MATANAO (ALONG C. 2/19/2021 C. -32.94 Performance) the incurred negative slippage. of-Way problem, Once project is
DAVAO - COTABATO ROAD) - resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 62.21% and
PACKAGE A, DAVAO DEL SUR incurred negative slippage of -1.55%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- Reminder/ Warning letters were 11/16/2020 -Project suspended effective 16
CW2 (Slow given to the contractor to eliminate November 2020 due to Road Right-
Performance) the incurred negative slippage. of-Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- Reminder/ Warning letters were 11/16/2020 -Project suspended effective 16
CW3 (Slow given to the contractor to eliminate November 2020 due to Road Right-
Performance) the incurred negative slippage. of-Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401108MN- Reminder/ Warning letters were 11/16/2020 -Project suspended effective 16
CW4 (Slow given to the contractor to eliminate November 2020 due to Road Right-
Performance) the incurred negative slippage. of-Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 62.21% and
incurred negative slippage of -1.55%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 50 Of 105


60 20L00081 A. 81,763,967.34 A. 4/13/2020 A. 100.00 P00401108MN- Reminder/ Warning letters were 11/16/2020 -Project suspended effective 16
ROAD WIDENING - BYPASS B. 81,763,967.34 B. 1/5/2021 B. 67.06 CW5 (Slow given to the contractor to eliminate November 2020 due to Road Right-
ROAD, JCT. MATANAO (ALONG C. 2/19/2021 C. -32.94 Performance) the incurred negative slippage. of-Way problem, Once project is
DAVAO - COTABATO ROAD) - resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 62.21% and
PACKAGE A, DAVAO DEL SUR incurred negative slippage of -1.55%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order.
61 20L00082 A. 76,475,284.97 A. 4/13/2020 A. 100.00 P00401109MN- on-going negotiation with the Project suspended effective 16
ROAD WIDENING - BYPASS B. 76,965,181.77 B. 12/18/2020 B. 84.39 CW1 (Permit to affected structures January 2021 due to Road Right-of-
ROAD, JCT. MATANAO (ALONG C. 4/2/2021 C. -15.61 enter issues) Way problem, Once project is
DAVAO - COTABATO ROAD) - resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 87.55% and
PACKAGE B, DAVAO DEL SUR incurred negative slippage of -2.62%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order
P00401109MN- on-going negotiation with the Project suspended effective 16
CW2 (Permit to affected structures January 2021 due to Road Right-of-
enter issues) Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 87.55% and
incurred negative slippage of -2.62%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order
P00401109MN- on-going negotiation with the Project suspended effective 16
CW3 (Permit to affected structures January 2021 due to Road Right-of-
enter issues) Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 87.55% and
incurred negative slippage of -2.62%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order

PCMA 8/31/2021 5:01:21 PM Page 51 Of 105


61 20L00082 A. 76,475,284.97 A. 4/13/2020 A. 100.00 P00401109MN- Situational report was rendered by 5/31/2020 Project suspended effective 16
ROAD WIDENING - BYPASS B. 76,965,181.77 B. 12/18/2020 B. 84.39 CW1 (Epidemic the Project Engineer concerning January 2021 due to Road Right-of-
ROAD, JCT. MATANAO (ALONG C. 4/2/2021 C. -15.61 (s)) some issues raised by the Way problem, Once project is
DAVAO - COTABATO ROAD) - Contractor in relation to the resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY implementation of project. extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 87.55% and
PACKAGE B, DAVAO DEL SUR incurred negative slippage of -2.62%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order
P00401109MN- Situational report was rendered by 5/31/2020 Project suspended effective 16
CW2 (Epidemic the Project Engineer concerning January 2021 due to Road Right-of-
(s)) some issues raised by the Way problem, Once project is
Contractor in relation to the resumed and equivalent times
implementation of project. extension is approved, revised
planned schedule will be 87.55% and
incurred negative slippage of -2.62%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order
P00401109MN- Situational report was rendered by 5/31/2020 Project suspended effective 16
CW3 (Epidemic the Project Engineer concerning January 2021 due to Road Right-of-
(s)) some issues raised by the Way problem, Once project is
Contractor in relation to the resumed and equivalent times
implementation of project. extension is approved, revised
planned schedule will be 87.55% and
incurred negative slippage of -2.62%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order
P00401109MN- Reminder/ Warning letters were 1/16/2021 Project suspended effective 16
CW1 (Slow given to the contractor to eliminate January 2021 due to Road Right-of-
Performance) the incurred negative slippage. Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 87.55% and
incurred negative slippage of -2.62%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order

PCMA 8/31/2021 5:01:21 PM Page 52 Of 105


61 20L00082 A. 76,475,284.97 A. 4/13/2020 A. 100.00 P00401109MN- Reminder/ Warning letters were 1/16/2021 Project suspended effective 16
ROAD WIDENING - BYPASS B. 76,965,181.77 B. 12/18/2020 B. 84.39 CW2 (Slow given to the contractor to eliminate January 2021 due to Road Right-of-
ROAD, JCT. MATANAO (ALONG C. 4/2/2021 C. -15.61 Performance) the incurred negative slippage. Way problem, Once project is
DAVAO - COTABATO ROAD) - resumed and equivalent times
NEW VISAYAS - JCT. HAGONOY extension is approved, revised
(ALONG DIGOS - MAKAR ROAD), planned schedule will be 87.55% and
PACKAGE B, DAVAO DEL SUR incurred negative slippage of -2.62%.
TKS BUILDERS & SUPPLIES Revision in the PCMA on process,
(23415) waiting for approved time extension
in view of approved suspension and
resumption order
P00401109MN- Reminder/ Warning letters were 1/16/2021 Project suspended effective 16
CW3 (Slow given to the contractor to eliminate January 2021 due to Road Right-of-
Performance) the incurred negative slippage. Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 87.55% and
incurred negative slippage of -2.62%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order
62 20L00083 A. 132,504,134.97 A. 3/23/2020 A. 100.00 P00401145MN- The contractor requested for Work Project was suspended effective on
REPLACEMENT OF BRIDGE- B. 132,504,134.97 B. 1/16/2021 B. 69.82 CW2 Suspension Order due to March29,2021 (Work Suspension
BYPASS ROAD, JCT. PADADA C. 3/17/2021 C. -30.18 (Removal/Relocat obstruction of electric post Order No. 2) due to the acquisition of
(ALONG DIGOS-MAKAR ROAD)- ion of utilities) (DASURECO) on the project site. Road Right of Way problem (Permit
KIBLAWAN-JCT. MALUNGON to enter issues). Once project is
(ALONG DIGOS-MAKAR ROAD), resumed and equivalent Time
PACKAGE C, DAVAO DEL SUR Extension is approved the revised
ALGON ENGINEERING planned schedule will be 26.37% and
CONSTRUCTION CORPORATION the incurred positive slippage -2.29.
(00270) Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 53 Of 105


62 20L00083 A. 132,504,134.97 A. 3/23/2020 A. 100.00 P00401145MN- The contractor requested for Work Project was suspended effective on
REPLACEMENT OF BRIDGE- B. 132,504,134.97 B. 1/16/2021 B. 69.82 CW3 Suspension Order due to March29,2021 (Work Suspension
BYPASS ROAD, JCT. PADADA C. 3/17/2021 C. -30.18 (Removal/Relocat obstruction of electric post Order No. 2) due to the acquisition of
(ALONG DIGOS-MAKAR ROAD)- ion of utilities) (DASURECO) on the project site. Road Right of Way problem (Permit
KIBLAWAN-JCT. MALUNGON to enter issues). Once project is
(ALONG DIGOS-MAKAR ROAD), resumed and equivalent Time
PACKAGE C, DAVAO DEL SUR Extension is approved the revised
ALGON ENGINEERING planned schedule will be 26.37% and
CONSTRUCTION CORPORATION the incurred positive slippage -2.29.
(00270) Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401145MN- The contractor requested for Work Project was suspended effective on
CW1 Suspension Order due to March29,2021 (Work Suspension
(Removal/Relocat obstruction of electric post Order No. 2) due to the acquisition of
ion of utilities) (DASURECO) on the project site. Road Right of Way problem (Permit
to enter issues). Once project is
resumed and equivalent Time
Extension is approved the revised
planned schedule will be 26.37% and
the incurred positive slippage -2.29.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401145MN- Issuance of Executive Order No.20 5/31/2020 Project was suspended effective on
CW1 (Epidemic and the strict implementation of March29,2021 (Work Suspension
(s)) community quarantine caused by Order No. 2) due to the acquisition of
COVID-19 pandemic, which greatly Road Right of Way problem (Permit
affects the implementation of the to enter issues). Once project is
project. resumed and equivalent Time
Extension is approved the revised
planned schedule will be 26.37% and
the incurred positive slippage -2.29.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 54 Of 105


62 20L00083 A. 132,504,134.97 A. 3/23/2020 A. 100.00 P00401145MN- Issuance of Executive Order No.20 5/31/2020 Project was suspended effective on
REPLACEMENT OF BRIDGE- B. 132,504,134.97 B. 1/16/2021 B. 69.82 CW2 (Epidemic and the strict implementation of March29,2021 (Work Suspension
BYPASS ROAD, JCT. PADADA C. 3/17/2021 C. -30.18 (s)) community quarantine caused by Order No. 2) due to the acquisition of
(ALONG DIGOS-MAKAR ROAD)- COVID-19 pandemic, which greatly Road Right of Way problem (Permit
KIBLAWAN-JCT. MALUNGON affects the implementation of the to enter issues). Once project is
(ALONG DIGOS-MAKAR ROAD), project. resumed and equivalent Time
PACKAGE C, DAVAO DEL SUR Extension is approved the revised
ALGON ENGINEERING planned schedule will be 26.37% and
CONSTRUCTION CORPORATION the incurred positive slippage -2.29.
(00270) Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401145MN- Issuance of Executive Order No.20 5/31/2020 Project was suspended effective on
CW3 (Epidemic and the strict implementation of March29,2021 (Work Suspension
(s)) community quarantine caused by Order No. 2) due to the acquisition of
COVID-19 pandemic, which greatly Road Right of Way problem (Permit
affects the implementation of the to enter issues). Once project is
project. resumed and equivalent Time
Extension is approved the revised
planned schedule will be 26.37% and
the incurred positive slippage -2.29.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
63 20L00084 A. 130,894,546.51 A. 3/23/2020 A. 100.00 P00401146MN- The contractor requested for Work -Project was suspended effective on
REPLACEMENT OF BRIDGE- B. 130,894,546.51 B. 1/16/2021 B. 77.77 CW3 Suspension Order due to March29,2021 (Work Suspension
BYPASS ROAD, JCT. PADADA C. 3/17/2021 C. -22.23 (Removal/Relocat obstruction of electric post Order No. 2) due to the acquisition of
(ALONG DIGOS-MAKAR ROAD)- ion of utilities) (DASURECO) on the project site. Road Right of Way problem (Permit
KIBLAWAN-JCT. MALUNGON to enter issues). Once project is
(ALONG DIGOS-MAKAR ROAD), resumed and equivalent Time
PACKAGE D, DAVAO DEL SUR Extension is approved the revised
ALGON ENGINEERING planned schedule will be 26.37% and
CONSTRUCTION CORPORATION the incurred positive slippage -2.29.
(00270) Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 55 Of 105


63 20L00084 A. 130,894,546.51 A. 3/23/2020 A. 100.00 P00401146MN- The contractor requested for Work -Project was suspended effective on
REPLACEMENT OF BRIDGE- B. 130,894,546.51 B. 1/16/2021 B. 77.77 CW1 Suspension Order due to March29,2021 (Work Suspension
BYPASS ROAD, JCT. PADADA C. 3/17/2021 C. -22.23 (Removal/Relocat obstruction of electric post Order No. 2) due to the acquisition of
(ALONG DIGOS-MAKAR ROAD)- ion of utilities) (DASURECO) on the project site. Road Right of Way problem (Permit
KIBLAWAN-JCT. MALUNGON to enter issues). Once project is
(ALONG DIGOS-MAKAR ROAD), resumed and equivalent Time
PACKAGE D, DAVAO DEL SUR Extension is approved the revised
ALGON ENGINEERING planned schedule will be 26.37% and
CONSTRUCTION CORPORATION the incurred positive slippage -2.29.
(00270) Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401146MN- The contractor requested for Work -Project was suspended effective on
CW2 Suspension Order due to March29,2021 (Work Suspension
(Removal/Relocat obstruction of electric post Order No. 2) due to the acquisition of
ion of utilities) (DASURECO) on the project site. Road Right of Way problem (Permit
to enter issues). Once project is
resumed and equivalent Time
Extension is approved the revised
planned schedule will be 26.37% and
the incurred positive slippage -2.29.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401146MN- Issuance of Executive Order No.20 5/31/2020 -Project was suspended effective on
CW1 (Epidemic and the strict implementation of March29,2021 (Work Suspension
(s)) community quarantine caused by Order No. 2) due to the acquisition of
COVID-19 pandemic, which greatly Road Right of Way problem (Permit
affects the implementation of the to enter issues). Once project is
project. resumed and equivalent Time
Extension is approved the revised
planned schedule will be 26.37% and
the incurred positive slippage -2.29.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 56 Of 105


63 20L00084 A. 130,894,546.51 A. 3/23/2020 A. 100.00 P00401146MN- Issuance of Executive Order No.20 5/31/2020 -Project was suspended effective on
REPLACEMENT OF BRIDGE- B. 130,894,546.51 B. 1/16/2021 B. 77.77 CW2 (Epidemic and the strict implementation of March29,2021 (Work Suspension
BYPASS ROAD, JCT. PADADA C. 3/17/2021 C. -22.23 (s)) community quarantine caused by Order No. 2) due to the acquisition of
(ALONG DIGOS-MAKAR ROAD)- COVID-19 pandemic, which greatly Road Right of Way problem (Permit
KIBLAWAN-JCT. MALUNGON affects the implementation of the to enter issues). Once project is
(ALONG DIGOS-MAKAR ROAD), project. resumed and equivalent Time
PACKAGE D, DAVAO DEL SUR Extension is approved the revised
ALGON ENGINEERING planned schedule will be 26.37% and
CONSTRUCTION CORPORATION the incurred positive slippage -2.29.
(00270) Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
P00401146MN- Issuance of Executive Order No.20 5/31/2020 -Project was suspended effective on
CW3 (Epidemic and the strict implementation of March29,2021 (Work Suspension
(s)) community quarantine caused by Order No. 2) due to the acquisition of
COVID-19 pandemic, which greatly Road Right of Way problem (Permit
affects the implementation of the to enter issues). Once project is
project. resumed and equivalent Time
Extension is approved the revised
planned schedule will be 26.37% and
the incurred positive slippage -2.29.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
64 20L00086 A. 173,085,567.78 A. 3/25/2020 A. 100.00 P00401368MN- Revision in the PCMA documents -Project completed as of 29 April
CONSTRUCTION OF CONCRETE B. 178,331,634.03 B. 1/18/2021 B. 96.90 CW1 (Changes in due to Variation Order No. 1 on 2021 with minor defects
ROAD-MATANAO-KIBLAWAN- C. 4/29/2021 C. -3.10 approved process, once approved -Variation Order No. 1 without
PADADA ROAD, PACKAGE D, plans/designs) corresponding request for revision Extension on process, once
DAVAO DEL SUR in the PCMA will be forwarded to approved corresponding request for
JEJOR'S CONSTRUCTION PMD-BOC for approval. revision in the PCMA will be
CORPORATION (5143) forwarded to PMD-BOC for approval.
P00401368MN- Situational report was rendered by 5/31/2020 -Project completed as of 29 April
CW1 (Epidemic the Project Engineer concerning 2021 with minor defects
(s)) some issues raised by the -Variation Order No. 1 without
Contractor in relation to the Extension on process, once
implementation of project. approved corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.

PCMA 8/31/2021 5:01:21 PM Page 57 Of 105


64 20L00086 A. 173,085,567.78 A. 3/25/2020 A. 100.00 P00401368MN- Reminder/ Warning letters were 4/26/2021 -Project completed as of 29 April
CONSTRUCTION OF CONCRETE B. 178,331,634.03 B. 1/18/2021 B. 96.90 CW1 (Insufficient given to the contractor to eliminate 2021 with minor defects
ROAD-MATANAO-KIBLAWAN- C. 4/29/2021 C. -3.10 manpower) the incurred negative slippage. -Variation Order No. 1 without
PADADA ROAD, PACKAGE D, Extension on process, once
DAVAO DEL SUR approved corresponding request for
JEJOR'S CONSTRUCTION revision in the PCMA will be
CORPORATION (5143) forwarded to PMD-BOC for approval.
65 20L00087 A. 109,144,212.16 A. 12/29/2020 A. 94.15 P00401509MN- Reminder/ Warning letters were -Project on going
CONSTRUCTION OF CONCRETE B. 109,144,212.16 B. 10/4/2021 B. 89.32 CW1 (Insufficient given to the contractor to eliminate
ROAD-MATANAO-KIBLAWAN- C. 10/4/2021 C. -4.83 equipment) the incurred negative slippage.
PADADA ROAD, PACKAGE E,
DAVAO DEL SUR P00401509MN- Reminder/ Warning letters were 6/16/2021 -Project on going
P.L. SEBASTIAN CW1 (Slow given to the contractor to eliminate
CONSTRUCTION, INC. Performance) the incurred negative slippage.
(FORMERLY: P.L. SEBASTIAN
CONSTRUCTION) (35840)
66 20L00089 A. 22,505,457.44 A. 12/22/2020 A. 72.29 P00431727MN- Revision in the PCMA documents -Project on going
CONSTRUCTION OF DIGOS CPO B. 22,505,457.44 B. 10/17/2021 B. 52.15 CW1 (Changes in due to Variation Order No. 1 with -Revision in the PCMA documents
BUILDING, DIGOS CITY, DAVAO C. 10/17/2021 C. -20.14 approved Extension submitted for approval due to Variation Order No. 1 with
DEL SUR plans/designs) Extension submitted for approval
MICAH CONSTRUCTION &
SUPPLY (26625)
67 20L00090 A. 134,233,979.26 A. 5/17/2020 A. 100.00 P00401101MN- Issuance of Executive Order No.20 '-Project was suspended effective on
CONSTRUCTION OF CONCRETE B. 134,233,979.26 B. 3/12/2021 B. 81.41 CW1 (Epidemic and the strict implementation of August 16,2021(Work Suspension
ROAD -MALITA DIVERSION C. 3/12/2021 C. -18.59 (s)) community quarantine caused by Order No. 2) due to the acquisition of
ROAD, DAVAO OCCIDENTAL COVID-19 pandemic, which greatly Road Right of Way problem (Permit
FFJJ CONSTRUCTION (16712) affects the implementation of the to enter issues). Revision in the
project. PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
68 20L00091 A. 143,655,911.05 A. 12/28/2020 A. 92.65 P00401127MN- The contractor was advised to '-Project was suspended effective on
CONSTRUCTION OF CONCRETE B. 143,655,911.05 B. 10/27/2021 B. 28.83 CW1 (Permit to work on section without road right May 01 ,2021 (Work Suspension
BRIDGE - TALAGUTONG - C. 10/27/2021 C. -63.82 enter issues) of way Order No. 1) due to the acquisition of
BALUNTAYA - TICULON - LITTLE Road Right of Way problem (Permit
BAGUIO DIVERSION ROAD, to enter issues). Once project is
PACKAGE C, DAVAO resumed and equivalent Time
OCCIDENTAL Extension is approved the revised
THREE W BUILDERS, INC. planned schedule will be 28.81% and
(10722) the incurred positive slippage 0.02.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 58 Of 105


68 20L00091 A. 143,655,911.05 A. 12/28/2020 A. 92.65 P00401127MN- The contractor was advsised to '-Project was suspended effective on
CONSTRUCTION OF CONCRETE B. 143,655,911.05 B. 10/27/2021 B. 28.83 CW2 (Permit to work on section without road right May 01 ,2021 (Work Suspension
BRIDGE - TALAGUTONG - C. 10/27/2021 C. -63.82 enter issues) of way Order No. 1) due to the acquisition of
BALUNTAYA - TICULON - LITTLE Road Right of Way problem (Permit
BAGUIO DIVERSION ROAD, to enter issues). Once project is
PACKAGE C, DAVAO resumed and equivalent Time
OCCIDENTAL Extension is approved the revised
THREE W BUILDERS, INC. planned schedule will be 28.81% and
(10722) the incurred positive slippage 0.02.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
69 20L00092 A. 133,237,701.15 A. 12/28/2020 A. 88.41 P00401128MN- -The contractor was advsised to '-Project was suspended effective on
CONSTRUCTION OF CONCRETE B. 133,237,701.15 B. 10/28/2021 B. 50.25 CW1 (Permit to work on section without road right July 06 ,2021 (Work Suspension
ROAD-TALAGUTONG- C. 10/28/2021 C. -38.16 enter issues) of way Order No. 1) due to the acquisition of
BALUNTAYA-TICULON-LITTLE Road Right of Way problem (Permit
BAGUIO DIVERSION ROAD, to enter issues). Once project is
PACKAGE D, DAVAO resumed and equivalent Time
OCCIDENTAL Extension is approved the revised
FFJJ CONSTRUCTION (16712) planned schedule will be 50.23% and
the incurred positive slippage 0.02.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
70 20L00093 A. 180,662,347.00 A. 12/28/2020 A. 86.14 P00401099MN- The contractor was advised to '-Project was suspended effective on
CONSTRUCTION OF CONCRETE B. 180,662,347.00 B. 11/7/2021 B. 27.37 CW1 (Permit to work on section without road right May 24 ,2021 (Work Suspension
ROAD-DEMOLOC-LITTLE C. 11/7/2021 C. -58.77 enter issues) of way Order No. 1) due to the acquisition of
BAGUIO-ALABEL ROAD, Road Right of Way problem (Permit
PACKAGE 3, to enter issues). Once project is
DAVAO OCCIDENTAL resumed and equivalent Time
FFJJ CONSTRUCTION (16712) Extension is approved the revised
planned schedule will be 27.23% and
the incurred positive slippage 0.16.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 59 Of 105


71 20L00094 A. 8,849,631.79 A. 7/28/2020 A. 100.00 P00431734MN- Negotiation with the RROW Project on going; planned schedule
CONSTRUCTION OF SARANGANI B. 8,849,631.79 B. 2/22/2021 B. 55.02 CW1 (Permit to affected persons was conducted to is 12.47% and the incurred positive
MUNICIPAL POLICE STATION, C. 2/22/2021 C. -44.98 enter issues) be able to conduct construction slippage 00.10%.
SARANGANI, DAVAO activities within the project limit.
OCCIDENTAL
RELY CONSTRUCTION &
SUPPLY (10433)
72 20L00095 A. 110,728,427.18 A. 1/3/2021 A. 94.55 "- Project Suspended effective 02
ROAD WIDENING ON SPECIFIC B. 110,728,427.18 B. 10/9/2021 B. 82.36 August 2021 in view of unsigned
LOCATIONS ALONG SURIGAO C. 10/9/2021 C. -12.19 Permit to Enter.
DEL SUR BDRY. DAVAO OR. - Once equivalent Time Extension is
COASTAL ROAD (S00140MN), D approved, the revised planned
MAVERICK BUILDERS schedule will be 82.313% and the
INCORPORATED (FORMERLY incurred slippage 0.034%."
MAVERICK (14466)
73 20L00096 A. 177,075,691.27 A. 3/25/2020 A. 100.00 "Project completed on 18 January
CONSTRUCTION OF CONCRETE B. 177,075,691.27 B. 1/18/2021 B. 94.08 2021 with minor defects
ROAD-BAGANGA DIVERSION C. 1/18/2021 C. -5.92 Variation Order No. 1 still on-
ROAD, DAVAO ORIENTAL process."
MAVERICK BUILDERS
INCORPORATED (FORMERLY
MAVERICK (14466)
74 20L00098 A. 111,775,906.76 A. 10/28/2020 A. 100.00 P00401148MN- signed permit to enter 4/16/2021 PROJECT on going/ revision for
CONSTRUCTION OF GRAVEL B. 111,775,906.76 B. 7/18/2021 B. 90.07 CW1 (Permit to pcma is on process once approved
ROAD - MAWAB-MARAGUSAN- C. 7/18/2021 C. -9.93 enter issues) will be forwarded to BOC-PMd for
CARAGA ROAD, PACKAGE F, approval.
DAVAO ORIENTAL P00401148MN- Negotiation with the project 4/16/2021 PROJECT on going/ revision for
MAC BUILDERS (7249) CW1 (Permit to affected persons and processing of pcma is on process once approved
enter issues) documents related to RROW will be forwarded to BOC-PMd for
problem were done. approval.
Tagging/inventory/identification of
affected persons were done to
come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 07,
2021 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 60 Of 105


74 20L00098 A. 111,775,906.76 A. 10/28/2020 A. 100.00 P00401148MN- Negotiation with the project 4/16/2021 PROJECT on going/ revision for
CONSTRUCTION OF GRAVEL B. 111,775,906.76 B. 7/18/2021 B. 90.07 CW1 (Permit to affected persons and processing of pcma is on process once approved
ROAD - MAWAB-MARAGUSAN- C. 7/18/2021 C. -9.93 enter issues) documents related to RROW will be forwarded to BOC-PMd for
CARAGA ROAD, PACKAGE F, problem were done. approval.
DAVAO ORIENTAL Tagging/inventory/identification of
MAC BUILDERS (7249) affected persons were done to
come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 07,
2021 due to RROW
75 20L00099 A. 84,204,923.59 A. 8/3/2020 A. 100.00 P00401149MN- Negotiation with the project project is suspended as of
CONSTRUCTION OF GRAVEL B. 84,204,923.59 B. 5/3/2021 B. 5.55 CW1 (Permit to affected persons and processing of September 15, 2020 revision for time
ROAD - MAWAB - MARAGUSAN- C. 5/3/2021 C. -94.45 enter issues) documents related to RROW extension on process once approved
CARAGA ROAD, PACKAGE G, problem were done. will be forwarded to BOC-PMD for
DAVAO ORIENTAL Tagging/inventory/identification of approval. The Revised
MAC BUILDERS (7249) affected persons were done to accomplishment is 3.17% actual is
come up with a detailed estimates 5.50% the slippage to date is 2.33%
that were used to be the basis of the revised expiry date is april 19,
giving cash assistance to the 2022.
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
15, 2020 due to RROW
P00401149MN- Negotiation with the project project is suspended as of
CW2 (Permit to affected persons and processing of September 15, 2020 revision for time
enter issues) documents related to RROW extension on process once approved
problem were done. will be forwarded to BOC-PMD for
Tagging/inventory/identification of approval. The Revised
affected persons were done to accomplishment is 3.17% actual is
come up with a detailed estimates 5.50% the slippage to date is 2.33%
that were used to be the basis of the revised expiry date is april 19,
giving cash assistance to the 2022.
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended September
15, 2020 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 61 Of 105


76 20L00100 A. 8,849,583.88 A. 7/20/2020 A. 100.00 "Project completed on 15 January
CONSTRUCTION OF BAGANGA B. 8,849,583.88 B. 1/15/2021 B. 88.55 2021 with minor defects
MUNICIPAL POLICE STATION, C. 1/15/2021 C. -11.45 Variation Order No. 1 still on-
BAGANGA, DAVAO ORIENTAL process."
RELY CONSTRUCTION &
SUPPLY (10433)
77 20L00101 A. 89,102,141.00 A. 3/23/2020 A. 100.00 P00401130MN- Issued work suspension order to 5/31/2020 Once the final variation order is
CONST. OF CONCRETE ROAD- B. 87,818,057.87 B. 12/2/2020 B. 85.81 CW1 (Epidemic the contractor dated 01 April 2020 approved, final quantities will be
DON MARIANO MARCOS-MALIG- C. 5/3/2021 C. -14.19 (s)) due to implementation of reflected in the PCMA.
SABAT-CALAGASAN-SAN community quarantine caused by
ISIDRO-TAGBOA-NEW VISAYAS- COVID-19.
MACAN P00401130MN- Negotiation with the Project 9/16/2020 Once the final variation order is
H2 LANDMARK BUILDERS, INC. CW1 (Permit to Affected Persons (PAPs) and approved, final quantities will be
(7400) enter issues) processing of RROW documents reflected in the PCMA.
are still on going. Tagging,
inventory, and identification of
affected persons were done to
come up with detailed estimates
that were used as basis for just
compensation of the PAPs
78 20L00102 A. 131,262,598.24 A. 11/17/2020 A. 99.31 P00401150MN- Issued Work Suspension Order Project suspended dated 01 July
CONSTRUCTION OF BYPASS B. 131,262,598.24 B. 9/9/2021 B. 69.27 CW1 (Permit to No. 1 due to RROW problem (ease 2021 due to RROW Problems.
ROAD-MATIAO-MAGSAYSAY C. 9/9/2021 C. -30.04 enter issues) of access for fisherfolks), Once the project is resumed and
COASTAL ROAD PACKAGE 1, negotations are on-going to equivalent Time Extension is
DAVAO ORIENTAL address the matter. approved, revised planned schedule
MAER SUMMIT KONSTRUKT CO. will be 66.74% and incurred slippage
(25262) of 2.53%.
79 20L00103 A. 108,393,556.50 A. 11/17/2020 A. 100.00 Project completed dated 27 August
CONSTRUCTION OF BYPASS B. 108,393,556.50 B. 8/27/2021 B. 97.01 2021.
ROAD-MATIAO-MAGSAYSAY C. 8/27/2021 C. -2.99 Once the final variation order is
COASTAL ROAD PACKAGE 2, approved, final quantities will be
DAVAO ORIENTAL reflected in the PCMA.
MAER SUMMIT KONSTRUKT CO.
(25262)

80 20L00104 A. 90,204,948.63 A. 6/15/2020 A. 100.00 Project completed dated 24 February


CONSTRUCTION OF CONCRETE B. 90,204,948.63 B. 2/24/2021 B. 98.80 2021.
ROAD-UPPER TIBANBAN- C. 2/24/2021 C. -1.20 Once the final variation order is
OREGON-MAGDUG ROAD, approved, final quantities will be
DAVAO ORIENTAL reflected in the PCMA.
MAER SUMMIT KONSTRUKT CO.
(25262)

PCMA 8/31/2021 5:01:21 PM Page 62 Of 105


81 20L00106 A. 221,186,912.19 A. 7/13/2020 A. 100.00 P00442878MN- Ongoing negotiation with the 4/19/2021 Project On-going.
CONSTRUCTION OF DAVAO B. 221,186,912.19 B. 5/18/2021 B. 94.80 CW1 (Permit to affected land owner.
ORIENTAL SPORTS COMPLEX, C. 9/19/2021 C. -5.20 enter issues)
MATI, DAVAO ORIENTAL
THREE W BUILDERS, INC.
(10722)
82 20L00107 A. 254,555,208.10 A. 9/23/2020 A. 100.00 P00442877MN- The contractor was advised to "- Project Suspended effective 01
CONSTRUCTION OF CONCRETE B. 254,555,208.10 B. 7/29/2021 B. 66.73 CW1 (Permit to work on section without road right- April 2021 in view of unsigned Permit
ROAD - NHJ DAWAN - MAMALI - C. 7/29/2021 C. -33.27 enter issues) of-way problem. to Enter.
MACAMBOL - MAGUM - - Once equivalent Time Extension is
CABUAYA ROAD, MATI CITY, approved, the revised planned
PACKAGE 2, DAVAO ORIENTAL schedule will be 66.307% and the
MAVERICK BUILDERS incurred slippage 0.556%."
INCORPORATED (FORMERLY P00442877MN- The contractor was advised to "- Project Suspended effective 01
MAVERICK (14466) CW2 (Permit to work on section without road right- April 2021 in view of unsigned Permit
enter issues) of-way problem. to Enter.
- Once equivalent Time Extension is
approved, the revised planned
schedule will be 66.307% and the
incurred slippage 0.556%."
83 20L00108 A. 223,728,860.89 A. 1/3/2021 A. 92.93 Project on-going.
CONSTRUCTION OF CONCRETE B. 223,728,860.89 B. 11/8/2021 B. 84.45
ROAD - NHJ DAWAN - MAMALI - C. 11/8/2021 C. -8.48
MACAMBOL - MAGUM -
CABUAYA ROAD, MATI CITY,
PACKAGE 2, DAVAO ORIENTAL
MAVERICK BUILDERS
INCORPORATED (FORMERLY
MAVERICK (14466)
84 20L00109 A. 140,691,269.39 A. 10/20/2020 A. 100.00 P00442874MN- Ongoing negotiation with the Project Suspended as of May 25,
ROAD UPGRADING OF NHJ B. 140,691,269.39 B. 8/15/2021 B. 41.91 CW1 (Permit to affected owners. 2021 rrow problems.
BUSO - SO. PAYPAY - C. 8/15/2021 C. -58.09 enter issues) Issued Work Suspension Order Once the project is resumed and
TAGBINONGA - SO. CALATAGAN, No. 2 due to road right of way equivalent Time Extension is
CALAPAGAN - SO. MATIGDAO, problem. approved, revised planned schedule
MARAYAG - SO. CALINAWAN, will be 46.12% and incurred negative
TAOCANGA ROAD, PACKAGE 1, slippage of 4.21%.
DAVAO ORIENTAL P00442874MN- Issued Work Suspension No. 1 4/21/2021 Project Suspended as of May 25,
THREE W BUILDERS, INC. CW1 (Permit to dated 22 December 2020. Ongoing 2021 rrow problems.
(10722) enter issues) negotiation with the affected lot Once the project is resumed and
owner. equivalent Time Extension is
approved, revised planned schedule
will be 46.12% and incurred negative
slippage of 4.21%.

PCMA 8/31/2021 5:01:21 PM Page 63 Of 105


85 20L00110 A. 172,703,783.56 A. 10/20/2020 A. 100.00 P00443096MN- Negotiation with the project Project Resumed as of July 02,
ROAD UPGRADING OF NHJ B. 172,703,783.56 B. 8/15/2021 B. 50.12 CW2 (Permit to affected persons and processing of 2021.
BUSO - SO. PAYPAY - C. 8/15/2021 C. -49.88 enter issues) documents related to RROW Project On-going.
TAGBINONGA - SO. CALATAGAN, problems were done. Project was
CALAPAGAN - SO. MATIGDAO, suspended due to RROW Problem.
MARAYAG - SO. CALINAWAN, Once approved, corresponding
TAOCANGA ROAD, PACKAGE 2, Revision in the PCMA will be sent
DAVAO ORIENTAL to BOC-PMD for approval.
THREE W BUILDERS, INC. P00443096MN- Negotiation with the project Project Resumed as of July 02,
(10722) CW1 (Permit to affected persons and processing of 2021.
enter issues) documents related to RROW Project On-going.
problems were done. Project was
suspended due to RROW Problem.
Once approved, corresponding
Revision in the PCMA will be sent
to BOC-PMD for approval.
86 20L00111 A. 156,375,962.98 A. 3/23/2020 A. 100.00 P00442875MN- Issued reminder letter due to Project suspended dated 01 June
ROAD UPGRADING OF SO. B. 156,375,962.98 B. 1/16/2021 B. 95.67 CW1 (Permit to incurred negative slippage of 2021 due to RROW Problems.
TAGOBOBOLO, BRGY. SAINZ, C. 3/17/2021 C. -4.33 enter issues) 4.166%. Once the project equivalent Time
MATI - SO. KALASAGAN, BRGY. Extension is approved, revised
SAN ISIDRO, LUPON, DAVAO planned schedule will be 99.84% and
ORIENTAL incurred negative slippage of 4.17%.
RAKKI CORPORATION (43053) / P00442875MN- Issued work suspension order to 5/31/2020 Project suspended dated 01 June
RELY CONSTRUCTION & CW1 (Epidemic the contractor dated 01 April 2020 2021 due to RROW Problems.
SUPPLY (10433) (s)) due to implementation of Once the project equivalent Time
community quarantine caused by Extension is approved, revised
COVID-19. planned schedule will be 99.84% and
incurred negative slippage of 4.17%.
P00442875MN- The contractor submitted letter 4/19/2021 Project suspended dated 01 June
CW1 (Permit to request for Work Suspension 2021 due to RROW Problems.
enter issues) Order dated Once the project equivalent Time
27 January 2021. Extension is approved, revised
Ongoing negotiation with the planned schedule will be 99.84% and
affected land owner incurred negative slippage of 4.17%.
87 20L00112 A. 13,742,139.04 A. 1/3/2021 A. 100.00 P00442839MN- Letters were sent to the utility and Project resume May 25, 2021.
CONSTRUCTION OF LATERAL B. 13,742,139.04 B. 5/7/2021 B. 49.62 CW1 communication companies for the
DRAINAGE ALONG TERMINAL C. 5/7/2021 C. -50.38 (Removal/Relocat removal/transfer of their posts and
DRIVE, ECOLAND, DAVAO CITY ion of utilities) cables present at the project site.
AGONG BUILDERS AND
CONSTRUCTION SUPPLY, INC.
(40494)

PCMA 8/31/2021 5:01:21 PM Page 64 Of 105


88 20L00113 A. 560,583,777.88 A. 12/28/2020 A. 80.11 P00442842MN- -Project mutually terminated due to -Project mutually terminated due to
CONSTRUCTION OF FLYOVER B. 560,583,777.88 B. 11/27/2021 B. 0.00 CW1 (Permit to difficulty in acquiring Road Right of difficulty in acquiring Road Right of
ALONG DAVAO - COTABATO C. 11/27/2021 C. -80.11 enter issues) Way Way
ROAD - JUNCTION MAA ROAD,
PACKAGE 2, DAVAO CITY
ULTICON BUILDERS, INC.
(17267)
89 20L00115 A. 93,693,924.93 A. 10/28/2020 A. 100.00 P00443712MN- on going negotiation with the Project suspended as of 01 August
CONSTRUCTION OF CONCRETE B. 93,693,924.93 B. 8/3/2021 B. 47.82 CW2 (Permit to affected land owners. 2021 due to road right of way,
ROAD AT PAG-ASA, BRGY. C. 8/3/2021 C. -52.18 enter issues) revision for pcma is on process once
SALOY TO SITIO KANACAN, approved will be forwarded to BOC-
BRGY. TAMUGAN GOING TO PMD for approval.
BRGY. LAMANAN, DAVAO CITY P00443712MN- Negotiation with the project 6/16/2021 Project suspended as of 01 August
ABU CONSTRUCTION (22313) CW2 (Permit to affected persons and processing of 2021 due to road right of way,
enter issues) documents related to RROW revision for pcma is on process once
problem were done. approved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval.
affected persons were done to
come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 16,
2021 due to RROW
P00443712MN- Negotiation with the project 6/16/2021 Project suspended as of 01 August
CW3 (Permit to affected persons and processing of 2021 due to road right of way,
enter issues) documents related to RROW revision for pcma is on process once
problem were done. approved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval.
affected persons were done to
come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 16,
2021 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 65 Of 105


89 20L00115 A. 93,693,924.93 A. 10/28/2020 A. 100.00 P00443712MN- on going negotiation with the 6/16/2021 Project suspended as of 01 August
CONSTRUCTION OF CONCRETE B. 93,693,924.93 B. 8/3/2021 B. 47.82 CW1 (Permit to affected land owners. 2021 due to road right of way,
ROAD AT PAG-ASA, BRGY. C. 8/3/2021 C. -52.18 enter issues) revision for pcma is on process once
SALOY TO SITIO KANACAN, approved will be forwarded to BOC-
BRGY. TAMUGAN GOING TO PMD for approval.
BRGY. LAMANAN, DAVAO CITY P00443712MN- Negotiation with the project 6/16/2021 Project suspended as of 01 August
ABU CONSTRUCTION (22313) CW1 (Permit to affected persons and processing of 2021 due to road right of way,
enter issues) documents related to RROW revision for pcma is on process once
problem were done. approved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval.
affected persons were done to
come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 16,
2021 due to RROW
P00443712MN- Negotiation with the project 6/16/2021 Project suspended as of 01 August
CW1 (Permit to affected persons and processing of 2021 due to road right of way,
enter issues) documents related to RROW revision for pcma is on process once
problem were done. approved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval.
affected persons were done to
come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 16,
2021 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 66 Of 105


89 20L00115 A. 93,693,924.93 A. 10/28/2020 A. 100.00 P00443712MN- Negotiation with the project 6/16/2021 Project suspended as of 01 August
CONSTRUCTION OF CONCRETE B. 93,693,924.93 B. 8/3/2021 B. 47.82 CW2 (Permit to affected persons and processing of 2021 due to road right of way,
ROAD AT PAG-ASA, BRGY. C. 8/3/2021 C. -52.18 enter issues) documents related to RROW revision for pcma is on process once
SALOY TO SITIO KANACAN, problem were done. approved will be forwarded to BOC-
BRGY. TAMUGAN GOING TO Tagging/inventory/identification of PMD for approval.
BRGY. LAMANAN, DAVAO CITY affected persons were done to
ABU CONSTRUCTION (22313) come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 16,
2021 due to RROW
P00443712MN- Negotiation with the project 6/16/2021 Project suspended as of 01 August
CW3 (Permit to affected persons and processing of 2021 due to road right of way,
enter issues) documents related to RROW revision for pcma is on process once
problem were done. approved will be forwarded to BOC-
Tagging/inventory/identification of PMD for approval.
affected persons were done to
come up with a detailed estimates
that were used to be the basis of
giving cash assistance to the
affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 16,
2021 due to RROW
90 20L00116 A. 75,030,845.36 A. 10/28/2020 A. 100.00 P00443713MN- Negotiation with the project 6/16/2021 project is suspended as of august 16,
CONSTRUCTION OF CONCRETE B. 75,030,845.36 B. 7/24/2021 B. 56.33 CW2 (Permit to affected persons and processing of 2021 due to Road right of way
ROAD AT SALOY ROAD, PAG- C. 7/24/2021 C. -43.67 enter issues) documents related to RROW revision for time extension on
IBIG, NEW LETY, BRGY. SALOY, problem were done. process once approved will be
CALINAN DISTRICT TO SITIO Tagging/inventory/identification of forwarded to BOC-PMD for approval.
CABONBON, BRGY. MALABOG, affected persons were done to The Revised accomplishment is
PAQUIBATO DISTRICT, DAVAO come up with a detailed estimates 55.986% actual is 58.363% the
CITY that were used to be the basis of slippage to date is 2.377% the
ABU CONSTRUCTION (22313) giving cash assistance to the revised expiry date is January 08,
affected residents. Once approved, 2022.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 1,
2021 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 67 Of 105


90 20L00116 A. 75,030,845.36 A. 10/28/2020 A. 100.00 P00443713MN- Negotiation with the project 6/16/2021 project is suspended as of august 16,
CONSTRUCTION OF CONCRETE B. 75,030,845.36 B. 7/24/2021 B. 56.33 CW1 (Permit to affected persons and processing of 2021 due to Road right of way
ROAD AT SALOY ROAD, PAG- C. 7/24/2021 C. -43.67 enter issues) documents related to RROW revision for time extension on
IBIG, NEW LETY, BRGY. SALOY, problem were done. process once approved will be
CALINAN DISTRICT TO SITIO Tagging/inventory/identification of forwarded to BOC-PMD for approval.
CABONBON, BRGY. MALABOG, affected persons were done to The Revised accomplishment is
PAQUIBATO DISTRICT, DAVAO come up with a detailed estimates 55.986% actual is 58.363% the
CITY that were used to be the basis of slippage to date is 2.377% the
ABU CONSTRUCTION (22313) giving cash assistance to the revised expiry date is January 08,
affected residents. Once approved, 2022.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 1,
2021 due to RROW
P00443713MN- Negotiation with the project 7/16/2021 project is suspended as of august 16,
CW1 (Permit to affected persons and processing of 2021 due to Road right of way
enter issues) documents related to RROW revision for time extension on
problem were done. process once approved will be
Tagging/inventory/identification of forwarded to BOC-PMD for approval.
affected persons were done to The Revised accomplishment is
come up with a detailed estimates 55.986% actual is 58.363% the
that were used to be the basis of slippage to date is 2.377% the
giving cash assistance to the revised expiry date is January 08,
affected residents. Once approved, 2022.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended January 16,
2021 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 68 Of 105


91 20L00117 A. 93,442,308.36 A. 10/28/2020 A. 100.00 P00443714MN- Instructed the Contractor to Project is suspended
CONSTRUCTION OF CONCRETE B. 93,442,308.36 B. 7/24/2021 B. 56.16 CW1 conduct overtime works in order to as of August 16,
ROAD AT SITIO DARILA, C. 7/24/2021 C. -43.84 (Unworkable site cover-up wasted time/days due to 2021.(In
COLABOL AND MASUPIT, BRGY. condition (i.e. unworkable ground caused by bad connection to WSO,
LAMANAN GOING CABAGTUKAN unfavorable weather condition. WRO
ELEMENTARY SCHOOL, BRGY. weather condition and CTE, revised
DOMINGA, CALINAN DISTRICT, at the project site, construction
DAVAO CITY access to project schedule is
WEE ENG CONSTRUCTION, INC. site not 92.08% and incurred
(16380) passable)) slippage of -8.96%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is November
06, 2021
P00443714MN- Instructed the Contractor to Project is suspended
CW2 conduct overtime works in order to as of August 16,
(Unworkable site cover-up wasted time/days due to 2021.(In
condition (i.e. unworkable ground caused by bad connection to WSO,
unfavorable weather condition. WRO
weather condition and CTE, revised
at the project site, construction
access to project schedule is
site not 92.08% and incurred
passable)) slippage of -8.96%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is November
06, 2021

PCMA 8/31/2021 5:01:21 PM Page 69 Of 105


91 20L00117 A. 93,442,308.36 A. 10/28/2020 A. 100.00 P00443714MN- The contractor requested for Work 5/16/2021 Project is suspended
CONSTRUCTION OF CONCRETE B. 93,442,308.36 B. 7/24/2021 B. 56.16 CW1 (Permit to Suspension order No. 1 as of August 16,
ROAD AT SITIO DARILA, C. 7/24/2021 C. -43.84 enter issues) 2021.(In
COLABOL AND MASUPIT, BRGY. connection to WSO,
LAMANAN GOING CABAGTUKAN WRO
ELEMENTARY SCHOOL, BRGY. and CTE, revised
DOMINGA, CALINAN DISTRICT, construction
DAVAO CITY schedule is
WEE ENG CONSTRUCTION, INC. 92.08% and incurred
(16380) slippage of -8.96%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is November
06, 2021
P00443714MN- The contractor requested for Work 5/16/2021 Project is suspended
CW2 (Permit to Suspension order No. 1 as of August 16,
enter issues) 2021.(In
connection to WSO,
WRO
and CTE, revised
construction
schedule is
92.08% and incurred
slippage of -8.96%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is November
06, 2021

PCMA 8/31/2021 5:01:21 PM Page 70 Of 105


92 20L00118 A. 93,605,000.00 A. 10/28/2020 A. 100.00 P00443715MN- The contractor requested for Work Project is suspended as of August
IMPROVEMENT/CONCRETING B. 93,605,000.00 B. 8/3/2021 B. 67.28 CW1 (Permit to Suspension Order No. 1 due to 16, 2021..(In
OF ACCESS ROAD AT JCT. C. 8/3/2021 C. -32.72 enter issues) RROW connection to WSO,
DAVAO - BUKIDNON ROAD WRO
(MARILOG) TO BRGY. GUMITAN, and CTE, revised
MARILOG DISTRICT, DAVAO construction
CITY schedule is
DOMERALD CONSTRUCTION 75.98% and incurred
AND SUPPLY (43664) / RELY slippage of -8.73%)
CONSTRUCTION & SUPPLY Time Extension
(10433) Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is October 18,
2021
93 20L00119 A. 82,320,773.97 A. 8/11/2020 A. 100.00 P00442841MN- On-going negotiations with the Project suspended effective February
CONSTRUCTION OF CONCRETE B. 82,320,773.97 B. 4/22/2021 B. 76.06 CW1 (Permit to affected owners in coordination 01, 2021 due to road right-of-way
ROAD - BYPASS ROAD, JCT. C. 4/22/2021 C. -23.94 enter issues) with the LGU Officials. problem (improvements). Once
BABAK - SAMAL - KAPUTIAN project is resumed and equivalent
ROAD - BRGY. SAN ANTONIO - Time Extension is approved, revised
TAGPOPONGAN, IGACOS planned schedule will be 61.405%
CIRCUMFERENTIAL ROAD, and incurred slippage 14.658%.
ISLAND GARDEN CITY OF Revision in the PCMA is on process.
SAMAL, DAVAO DEL NORTE
ALGON ENGINEERING HISTORY:
CONSTRUCTION CORPORATION -Project resumed effective
(00270) September 16, 2020. Revision on the
PCMA is on process and Contract
Time Extension is on process.

PCMA 8/31/2021 5:01:21 PM Page 71 Of 105


93 20L00119 A. 82,320,773.97 A. 8/11/2020 A. 100.00 P00442841MN- On-going negotiations with the Project suspended effective February
CONSTRUCTION OF CONCRETE B. 82,320,773.97 B. 4/22/2021 B. 76.06 CW2 (Permit to affected owners in coordination 01, 2021 due to road right-of-way
ROAD - BYPASS ROAD, JCT. C. 4/22/2021 C. -23.94 enter issues) with the LGU Officials. problem (improvements). Once
BABAK - SAMAL - KAPUTIAN project is resumed and equivalent
ROAD - BRGY. SAN ANTONIO - Time Extension is approved, revised
TAGPOPONGAN, IGACOS planned schedule will be 61.405%
CIRCUMFERENTIAL ROAD, and incurred slippage 14.658%.
ISLAND GARDEN CITY OF Revision in the PCMA is on process.
SAMAL, DAVAO DEL NORTE
ALGON ENGINEERING HISTORY:
CONSTRUCTION CORPORATION -Project resumed effective
(00270) September 16, 2020. Revision on the
PCMA is on process and Contract
Time Extension is on process.
P00442841MN- Construction activities will be 9/16/2020 Project suspended effective February
CW1 (Epidemic suspended until further notice 01, 2021 due to road right-of-way
(s)) problem (improvements). Once
project is resumed and equivalent
Time Extension is approved, revised
planned schedule will be 61.405%
and incurred slippage 14.658%.
Revision in the PCMA is on process.

HISTORY:
-Project resumed effective
September 16, 2020. Revision on the
PCMA is on process and Contract
Time Extension is on process.
94 20L00121 A. 49,367,705.98 A. 6/9/2020 A. 100.00 P00401359MN- The contractor has requested a Project was completed as scheduled.
CONSTRUCTION OF CONCRETE B. 49,367,705.98 B. 12/25/2020 B. 93.25 CW1 Contract Time Extension due to Documents are processed for
ROAD - MONTEVISTA - DNAS C. 3/5/2021 C. -6.75 (Unworkable site unfavorable weather condition approval. Once approved, request for
ROAD (DNAS- LAAK), SECTION 2, condition (i.e. encountered at the project site. revision will be submitted to PMD-
PACKAGE A, COMPOSTELA unfavorable BOC for approval.
VALLEY weather condition
MAC BUILDERS (7249) at the project site,
access to project
site not
passable))

PCMA 8/31/2021 5:01:21 PM Page 72 Of 105


95 20L00122 A. 72,491,434.33 A. 6/15/2020 A. 100.00 P00401110MN- The contractor requested for a time Project was declared completed as
CONSTRUCTION OF CONCRETE B. 72,491,434.33 B. 2/9/2021 B. 93.14 CW1 extension of 31 March 2021. Documents are
ROAD - MONTEVISTA (JCT. C. 2/9/2021 C. -6.86 (Unworkable site processed for approval. Once
MAYAON) - LAAK DIVERSION condition (i.e. approved, request for revision will be
RD., unfavorable submitted to PMD-BOC for approval.
PACKAGE A, COMPOSTELA weather condition
VALLEY at the project site,
O. G. SANTOS CONSTRUCTION access to project
(2050) site not
passable))
96 20L00124 A. 77,231,777.88 A. 6/16/2020 A. 100.00 P00401361MN- Instructed the contractor to conduct Project is completed with minor
CONSTRUCTION OF CONCRETE B. 77,231,777.88 B. 3/2/2021 B. 99.75 CW1 overtime works in order to cover-up deffects. (In
ROAD - BUKIDNON - C. 5/1/2021 C. -0.25 (Unworkable site wasted time/days due to connection to WSO,
COMPOSTELA VALLEY ROAD, condition (i.e. unworkable ground caused by bad WRO
BRGY. NAMNAM, SAN unfavorable weather condition and CTE.
FERNANDO, BUKIDNON - LAAK, weather condition Time Extension
COMPOSTELA VALLEY, at the project site, Order is
PACKAGE 3, COMPOSTELA access to project on process. Once
VALLEY site not approved, revisions
ULTICON BUILDERS, INC. passable)) in the
(17267) pcma will be
forwarded.
Revised Contract
Expiry
Date is June 30, 2021
97 20L00125 A. 23,390,016.88 A. 10/28/2020 A. 100.00 P00401364MN- Corresponding documents of Final Project completed with
CONSTRUCTION OF CONCRETE B. 23,390,016.88 B. 5/15/2021 B. 99.52 CW1 (Changes in Variation Order was complied to minor corrections as of
ROAD - NABUNTURAN - NEW C. 5/15/2021 C. -0.48 approved suit actual site condition. Once May 15, 2021. As-built
CORELLA - TAGUM ROAD plans/designs) approved, request for Revision in and Final Variation Order
(NABUNTURAN SECTION), the PCMA will be sent to the BOC- is on process, once
COMPOSTELA VALLEY PMD for approval. approved, corresponding
TAGUM BUILDERS request for revision in the
CONTRACTORS CORP. PCMA will be forwarded
(FORMERLY: TAGUM (34019) to PMD-BOC for approval

PCMA 8/31/2021 5:01:21 PM Page 73 Of 105


98 20L00126 A. 80,571,804.27 A. 1/3/2021 A. 99.36 P00401542MN- Negotiation with the project project is suspended as of April 22,
CONSTRUCTION OF CONCRETE B. 80,571,804.27 B. 9/4/2021 B. 23.83 CW1 (Permit to affected persons and processing of 2021 due to Road right of way .
ROAD - MARAGUSAN - C. 9/4/2021 C. -75.53 enter issues) documents related to RROW Revision for time extension on
PANTUKAN ROAD (PANTUKAN problem were done. process once approved will be
SECTION), Tagging/inventory/identification of forwarded to BOC-PMD for approval.
PACKAGE G, COMPOSTELA affected persons were done to The Revised accomplishment is
VALLEY come up with a detailed estimates 23.151% actual is 24.160% the
MAC BUILDERS (7249) that were used to be the basis of slippage to date is 1.009% the
giving cash assistance to the revised expiry date is january 22,
affected residents. Once approved, 2022
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended April 22,
2021 due to RROW
99 20L00127 A. 95,046,800.43 A. 1/3/2021 A. 99.69 P00401528MN- Negotiation with the project project is suspended as of april 22,
CONSTRUCTION OF CONCRETE B. 95,046,800.43 B. 9/9/2021 B. 45.23 CW1 (Permit to affected persons and processing of 2021 due to road right of way
ROAD - MARAGUSAN - C. 9/9/2021 C. -54.46 enter issues) documents related to RROW revision for . time extension on
PANTUKAN ROAD (PANTUKAN problem were done. process once approved will be
SECTION), PACKAGE H, Tagging/inventory/identification of forwarded to BOC-PMD for approval.
COMPOSTELA VALLEY affected persons were done to The Revised accomplishment is
MAC BUILDERS (7249) come up with a detailed estimates 60.23% actual is 50.442% the
that were used to be the basis of slippage to date is -9.788% the
giving cash assistance to the revised expiry date is January 18,
affected residents. Once approved, 2022.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended April 22,
2021 due to RROW
P00401528MN- Negotiation with the project project is suspended as of april 22,
CW2 (Permit to affected persons and processing of 2021 due to road right of way
enter issues) documents related to RROW revision for . time extension on
problem were done. process once approved will be
Tagging/inventory/identification of forwarded to BOC-PMD for approval.
affected persons were done to The Revised accomplishment is
come up with a detailed estimates 60.23% actual is 50.442% the
that were used to be the basis of slippage to date is -9.788% the
giving cash assistance to the revised expiry date is January 18,
affected residents. Once approved, 2022.
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended April 22,
2021 due to RROW

PCMA 8/31/2021 5:01:21 PM Page 74 Of 105


100 20L00128 A. 80,908,138.71 A. 5/27/2020 A. 100.00 P00400764MN- on-going negotiation with the -Project suspended effective 01
REPLACEMENT OF BRIDGE (2 B. 83,412,654.67 B. 2/13/2021 B. 89.80 CW1 (Permit to affected structures February 2021 due to Road Right-
INTO 4 LANES) - DIGOS BRIDGE C. 3/15/2021 C. -10.20 enter issues) of-Way problem, Once project is
1 (B00164MN) ALONG DIGOS- resumed and equivalent times
MAKAR ROAD, DAVAO DEL SUR extension is approved, revised
P.L. SEBASTIAN planned schedule will be 98.81% and
CONSTRUCTION, INC. incurred negative slippage of -5.9%.
(FORMERLY: P.L. SEBASTIAN Revision in the PCMA on process,
CONSTRUCTION) (35840) waiting for approved time extension
in view of approved suspension and
resumption order.
P00400764MN- Reminder/ Warning letters were 1/31/2021 -Project suspended effective 01
CW1 (Slow given to the contractor to eliminate February 2021 due to Road Right-
Performance) the incurred negative slippage. of-Way problem, Once project is
resumed and equivalent times
extension is approved, revised
planned schedule will be 98.81% and
incurred negative slippage of -5.9%.
Revision in the PCMA on process,
waiting for approved time extension
in view of approved suspension and
resumption order.
101 20L00134 A. 131,081,182.06 A. 12/28/2020 A. 100.00 P00444706MN- Documents submitted to planning -Project completed 05 July 2021.
PREVENTIVE MAINTENANCE - B. 131,081,182.06 B. 7/5/2021 B. 95.43 CW1 (Changes in division for checking Revision of plans on process, once
ASPHALT OVERLAY ON C. 7/5/2021 C. -4.57 approved approved corresponding request for
SPECIFIC LOCATIONS ALONG plans/designs) revision in the PCMA will be
DAVAO - COTABATO ROAD forwarded to PMD-BOC for approval.
(DAVAO CITY - JCT. DIGOS P00444706MN- Advice the contractor to provide 4/16/2021 -Project completed 05 July 2021.
SECTION) (S00039MN) CW1 (Insufficient additional manpower and fast track Revision of plans on process, once
K1513+643 - K1520+151, DAVAO manpower) construction activities to cope up approved corresponding request for
CITY with delayed activities. revision in the PCMA will be
C.T. LEONCIO CONSTRUCTION forwarded to PMD-BOC for approval.
& TRADING (17371) / RELY
CONSTRUCTION & SUPPLY P00444706MN- Advice the contractor to provide 6/16/2021 -Project completed 05 July 2021.
(10433) CW1 (Insufficient additional equipment and fast track Revision of plans on process, once
equipment) construction activities to cope up approved corresponding request for
with delayed activities. revision in the PCMA will be
forwarded to PMD-BOC for approval.

PCMA 8/31/2021 5:01:21 PM Page 75 Of 105


102 20L00135 A. 129,722,499.95 A. 1/3/2021 A. 100.00 P00444707MN- Variation Order documents -Project completed 11 July 2021.
PREVENTIVE MAINTENANCE - B. 129,722,499.95 B. 7/11/2021 B. 97.68 CW1 (Delays in submitted to planning division for Variation Order on process, once
ASPHALT OVERLAY ON C. 7/11/2021 C. -2.32 approval of checking. approved corresponding request for
SPECIFIC LOCATIONS ALONG Variation Orders) revision in the PCMA will be
DAVAO CITY DIVERSION ROAD forwarded to PMD-BOC for approval.
(S00013MN), K1514+103 -
K1515+832, DAVAO CITY
GEMMA CONSTRUCTION
SUPPLY, INC.
(FORMERLY:GEMMA CON (5044)
103 20L00137 A. 122,060,915.39 A. 1/3/2021 A. 96.38 P00444350MN- Negotiation with the Project 1. The project was suspended due
CONSTRUCTION OF CONCRETE B. 122,060,915.39 B. 10/29/2021 B. 6.19 CW1 (Permit to Affected Persons (PAPs) and last 02 March 2021 due to Road-
BRIDGE - MATINA APLAYA C. 10/29/2021 C. -90.19 enter issues) processing of documents related to Right-of-Way problems (structures
BRIDGE, DAVAO CITY RROW problem were done. and land).
ABU CONSTRUCTION (22313) Tagging/ inventory/ identification of
Project Affected Persons (PAPs)
were done to come up with a
detailed estimate that were used to
be the basis of just compensation
of the PAPs.
104 20L00138 A. 187,788,988.70 A. 1/26/2021 A. 78.13 P00443375MN- On-going negotiation of the -Project on going.
RECONSTRUCTION TO B. 187,788,988.70 B. 11/11/2021 B. 41.63 CW1 (Permit to affected structures, improvements
CONCRETE PAVEMENT ALONG C. 11/11/2021 C. -36.50 enter issues) and land c/o Legal Division.
JCT. DAVAO-COTABATO RD.
(MATINA CROSSING SECTION)- P00443375MN- On-going negotiation of the -Project on going.
MATINA APLAYA RD.-JCT. TULIP CW2 (Permit to affected structures, improvements
DRIVE (DAVAO-COTABATO RD.)- enter issues) and land c/o Legal Division.
ECOLAND DRIVE-JCT. ABC-CBN
QUIMPO BLVD. DIVERSION P00443375MN- Advice the contractor to provide 4/15/2021 -Project on going.
ROAD (JOHN PAUL SECTION), CW1 (Insufficient additional manpower and fast track
(PHASE 1) DAVAO CITY manpower) construction activities to cope up
ABU CONSTRUCTION (22313) with delayed activities.
P00443375MN- Advice the contractor to provide 4/15/2021 -Project on going.
CW2 (Insufficient additional manpower and fast track
manpower) construction activities to cope up
with delayed activities.

PCMA 8/31/2021 5:01:21 PM Page 76 Of 105


105 20L00140 A. 168,494,451.56 A. 12/22/2020 A. 79.33 P00444348MN- Negotiation with the project Request for Revision will then be
CONSTRUCTION OF CONCRETE B. 168,494,451.56 B. 10/17/2021 B. 31.50 CW1 (Permit to affected persons and processing of submitted to BOC-PMD for approval.
BRIDGE (SUBSTRUCTURE C. 10/17/2021 C. -47.83 enter issues) documents related to RROW The project was suspended March
ONLY) - MA-A BRIDGE II, DAVAO problem were done. 01, 2021 due to RROW
CITY Tagging/inventory/identification of
RAKKI CORPORATION (43053) / affected persons were done to
GEMMA CONSTRUCTION come up with a detailed estimates
SUPPLY, INC. that were used to be the basis of
(FORMERLY:GEMMA CON (5044) giving cash assistance to the
affected residents.
106 20L00141 A. 112,673,334.22 A. 12/29/2020 A. 84.31 P00444349MN- Negotiation with the Project 1. The project suspended as of 02
CONSTRUCTION OF CONCRETE B. 112,673,334.22 B. 10/18/2021 B. 5.17 CW1 (Permit to Affected Persons (PAPs) and March 2021 due to Road Right-of-
BRIDGE - MATINA APLAYA C. 10/18/2021 C. -79.14 enter issues) processing of documents related to Way problem within the project limit.
BRIDGE 2, DAVAO CITY RROW problem were done. 2. If Time Extension 1 due to WSO1
ABU CONSTRUCTION (22313) Tagging/ inventory/ identification of will be approved, the reported
Project Affected Persons (PAPs) slippage to date is -4.449% where
were also done to come up with a the planned accomplishment is
detailed estimate that were used to 9.624%. Once approved,
be the basis of just compensation corresponding request for revision in
of the PAPs. the PCMA will be forwarded to PMD-
BOC for approval.
107 20L00142 A. 121,680,376.85 A. 1/3/2021 A. 90.83 P00444352MN- Negotiation with the Project 1. Project is suspended due to Road
CONSTRUCTION OF CONCRETE B. 121,680,376.85 B. 10/29/2021 B. 10.47 CW1 (Permit to Affected Persons (PAPs) and Right-of-Way problem effective
BRIDGE - TALOMO BRIDGE 4, C. 10/29/2021 C. -80.36 enter issues) processing of documents related to March 01, 2021
DAVAO CITY RROW problem were done. 2. If Time Extension 1 due to WSO1
RAKKI CORPORATION (43053) / Tagging/ inventory/ identification of (Road-Right-of-Way problem) will be
RELY CONSTRUCTION & Project Affected Persons (PAPs) approved, the reported slippage to
SUPPLY (10433) were done to come up with a date is -80.37 %% where the
detailed estimate that were used to planned accomplishment is 10.47 %.
be the basis of just compensation Once approved, corresponding
of the PAPs. request for revision in the PCMA will
be forwarded to PMD-BOC for
approval.
108 20L00144 A. 93,797,189.67 A. 9/29/2020 A. 100.00 P00443288MN- Negotiation with the project Project resumed effective July 07,
CONSTRUCTION OF NRJ TAGUM B. 93,797,189.67 B. 6/30/2021 B. 56.43 CW2 (Permit to affected persons and processing of 2021. Contract Time Extension for
- PANABO CIRCUMFERENTIAL C. 6/30/2021 C. -43.57 enter issues) documents related to RROW approval. Once approved, request
ROAD TO BRGY. LIBERTAD TO problems were done. The for revision in the PCMA will then be
BRGY. SAN MIGUEL, STO. contractor requested for Work sent to the BOC-PMD for approval.
TOMAS INCLUDING BRIDGE Suspension Order No. 1 due to
RECONSTRUCTION (PACKAGE encountered RROW issues. Once
A), DAVAO DEL NORTE Contract Time Extension due to
MONOLITHIC CONSTRUCTION & WSO is approved, corresponding
CONCRETE PRODUCTS, INC. Request for Revision in the PCMA
(5733) will then be submitted to the BOC-
PMD for approval.
PCMA 8/31/2021 5:01:21 PM Page 77 Of 105
108 20L00144 A. 93,797,189.67 A. 9/29/2020 A. 100.00 P00443288MN- Negotiation with the project Project resumed effective July 07,
CONSTRUCTION OF NRJ TAGUM B. 93,797,189.67 B. 6/30/2021 B. 56.43 CW1 (Permit to affected persons and processing of 2021. Contract Time Extension for
- PANABO CIRCUMFERENTIAL C. 6/30/2021 C. -43.57 enter issues) documents related to RROW approval. Once approved, request
ROAD TO BRGY. LIBERTAD TO problems were done. The for revision in the PCMA will then be
BRGY. SAN MIGUEL, STO. contractor requested for Work sent to the BOC-PMD for approval.
TOMAS INCLUDING BRIDGE Suspension Order No. 1 due to
RECONSTRUCTION (PACKAGE encountered RROW issues. Once
A), DAVAO DEL NORTE Contract Time Extension due to
MONOLITHIC CONSTRUCTION & WSO is approved, corresponding
CONCRETE PRODUCTS, INC. Request for Revision in the PCMA
(5733) will then be submitted to the BOC-
PMD for approval.
109 20L00145 A. 46,804,325.49 A. 12/23/2020 A. 100.00 P00443246MN- Negotiation with the project project suspended as of march 1,
CONSTRUCTION OF CONCRETE B. 46,804,325.49 B. 8/19/2021 B. 13.17 CW1 (Permit to affected persons and processing of 2021 due to road right of way.
ROAD ALONG BYPASS ROAD AT C. 8/19/2021 C. -86.83 enter issues) documents related to RROW revision for pcma is on process once
JCT. ELPIDIO QUIRINO AVE. problem were done. approved will be forwarded to BOC-
(TIONKO AVE. SECTION) - JCT. Tagging/inventory/identification of PMD for approval.
PONCIANO ST. (DAVAO CITY affected persons were done to
POST OFFICE), DAVAO CITY come up with a detailed estimates
RAKKI CORPORATION (43053) / that were used to be the basis of
RELY CONSTRUCTION & giving cash assistance to the
SUPPLY (10433) affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended March 01,
2021 due to RROW
110 20L00146 A. 140,841,744.76 A. 1/3/2021 A. 92.22 P00443249MN- Requested the contractor to -Project on going. Revision in the
CONSTRUCTION OF CONCRETE B. 140,841,744.76 B. 10/29/2021 B. 22.78 CW1 (Delays in comply lacking attachments for the PCMA on process, waiting for
ROAD - BYPASS ROAD AT MA-A C. 10/29/2021 C. -69.44 approval of Time approval of Contract Time approved time extension in view of
RADIO STATION - DATU LOHO Suspension/Exte Extension. approved suspension and
ST. - RIVERSIDE - JCT. BACACA nsion) resumption order.
ROAD, DAVAO CITY P00443249MN- Requested the contractor to -Project on going. Revision in the
GEMMA CONSTRUCTION CW2 (Delays in comply lacking attachments for the PCMA on process, waiting for
SUPPLY, INC. approval of Time approval of Contract Time approved time extension in view of
(FORMERLY:GEMMA CON (5044) Suspension/Exte Extension. approved suspension and
nsion) resumption order.
P00443249MN- Requested the contractor to -Project on going. Revision in the
CW3 (Delays in comply lacking attachments for the PCMA on process, waiting for
approval of Time approval of Contract Time approved time extension in view of
Suspension/Exte Extension. approved suspension and
nsion) resumption order.

PCMA 8/31/2021 5:01:21 PM Page 78 Of 105


110 20L00146 A. 140,841,744.76 A. 1/3/2021 A. 92.22 P00443249MN- On-going negotiation of the 7/5/2021 -Project on going. Revision in the
CONSTRUCTION OF CONCRETE B. 140,841,744.76 B. 10/29/2021 B. 22.78 CW1 (Permit to affected structures and land c/o PCMA on process, waiting for
ROAD - BYPASS ROAD AT MA-A C. 10/29/2021 C. -69.44 enter issues) Legal Division. approved time extension in view of
RADIO STATION - DATU LOHO approved suspension and
ST. - RIVERSIDE - JCT. BACACA resumption order.
ROAD, DAVAO CITY P00443249MN- On-going negotiation of the 7/5/2021 -Project on going. Revision in the
GEMMA CONSTRUCTION CW2 (Permit to affected structures and land c/o PCMA on process, waiting for
SUPPLY, INC. enter issues) Legal Division. approved time extension in view of
(FORMERLY:GEMMA CON (5044) approved suspension and
resumption order.
P00443249MN- On-going negotiation of the 7/5/2021 -Project on going. Revision in the
CW3 (Permit to affected structures and land c/o PCMA on process, waiting for
enter issues) Legal Division. approved time extension in view of
approved suspension and
resumption order.
111 20L00148 A. 140,841,723.53 A. 1/3/2021 A. 94.35 P00443358MN- Variation Order No. 1 documents -Project on going
CONSTRUCTION OF CONCRETE B. 140,841,723.53 B. 10/19/2021 B. 75.82 CW1 (Changes in on process, once approved -Variation Order No. 1 documents on
ROAD - JCT. R MAGSAYSAY C. 10/19/2021 C. -18.53 approved corresponding request for revision process, once approved
AVE. - L.MA. GUERRERO ST. - plans/designs) in the PCMA will be forwarded to corresponding request for revision in
GUZMAN ST. - VINZON ST. - T. PMD-BOC for approval. the PCMA will be forwarded to PMD-
PALMA GIL ST. - JCT. DACUDAO BOC for approval.
- JCT. J.P. CABAGUIO AVE., P00443358MN- Variation Order No. 1 documents -Project on going
DAVAO CITY CW2 (Changes in on process, once approved -Variation Order No. 1 documents on
ABU CONSTRUCTION (22313) approved corresponding request for revision process, once approved
plans/designs) in the PCMA will be forwarded to corresponding request for revision in
PMD-BOC for approval. the PCMA will be forwarded to PMD-
BOC for approval.
112 20L00150 A. 93,602,070.22 A. 12/22/2020 A. 100.00 P00443392MN- Letters were sent to the 1. The project suspended as of 21
REHABILITATION OF PAVED B. 93,602,070.22 B. 7/9/2021 B. 56.07 CW1 corresponding utility and April 2021 due to obstruction of
ROAD ALONG BYPASS RD. AT C. 7/9/2021 C. -43.93 (Removal/Relocat telecommunications companies for public utilities/posts.
JCT. DAVAO - COTABATO RD. - ion of utilities) the removal/transfer of their 2. If Time Extension 1 due to WSO1
CENTRAL PARK (CORDILLERA electrical posts and cables present will be approved, the reported
RD.) - JCT. MATINA APLAYA RD., at the project the site. slippage to date is -43.93 % where
DAVAO CITY the planned accomplishment is 56.07
RAKKI CORPORATION (43053) / %. Once approved, corresponding
RELY CONSTRUCTION & request for revision in the PCMA will
SUPPLY (10433) be forwarded to PMD-BOC for
approval.

PCMA 8/31/2021 5:01:21 PM Page 79 Of 105


112 20L00150 A. 93,602,070.22 A. 12/22/2020 A. 100.00 P00443392MN- Letters were sent to the 1. The project suspended as of 21
REHABILITATION OF PAVED B. 93,602,070.22 B. 7/9/2021 B. 56.07 CW2 corresponding utility and April 2021 due to obstruction of
ROAD ALONG BYPASS RD. AT C. 7/9/2021 C. -43.93 (Removal/Relocat telecommunications companies for public utilities/posts.
JCT. DAVAO - COTABATO RD. - ion of utilities) the removal/transfer of their 2. If Time Extension 1 due to WSO1
CENTRAL PARK (CORDILLERA electrical posts and cables present will be approved, the reported
RD.) - JCT. MATINA APLAYA RD., at the project the site. slippage to date is -43.93 % where
DAVAO CITY the planned accomplishment is 56.07
RAKKI CORPORATION (43053) / %. Once approved, corresponding
RELY CONSTRUCTION & request for revision in the PCMA will
SUPPLY (10433) be forwarded to PMD-BOC for
approval.
113 20L00151 A. 93,894,466.20 A. 1/19/2021 A. 100.00 P00443395MN- On-going negotiation of the -Project suspended effective March
REHABILITATION OF PAVED B. 93,894,466.20 B. 8/16/2021 B. 10.00 CW1 (Permit to affected structures and land c/o 10, 2021 due to Road Right of Way
ROAD ALONG MATINA C. 8/16/2021 C. -90.00 enter issues) Legal Division. problem (difficulty in land acquisition
CROSSING ROAD (JCT. DAVAO - and obstruction of
COTABATO ROAD - JCT. DAVAO structures/improvements) within the
CITY DIVERSION ROAD), DAVAO construction limit. Once project is
CITY resumed and equivalent Time
ABU CONSTRUCTION (22313) Extension is approved revised
planned schedule will be 12.00%
and incurred negative slippage -
2.00%. Revision in the PCMA on
process, waiting for approved time
extension in view of approved
suspension and resumption order.
P00443395MN- On-going negotiation of the -Project suspended effective March
CW2 (Permit to affected structures and land c/o 10, 2021 due to Road Right of Way
enter issues) Legal Division. problem (difficulty in land acquisition
and obstruction of
structures/improvements) within the
construction limit. Once project is
resumed and equivalent Time
Extension is approved revised
planned schedule will be 12.00%
and incurred negative slippage -
2.00%. Revision in the PCMA on
process, waiting for approved time
extension in view of approved
suspension and resumption order.

PCMA 8/31/2021 5:01:21 PM Page 80 Of 105


114 20L00152 A. 281,104,489.31 A. 1/3/2021 A. 89.90 P00443425MN- Tagging, inventory, and The project was suspended effective
ROAD WIDENING & B. 281,104,489.31 B. 10/29/2021 B. 22.02 CW1 (Permit to identification of affected persons April 16, 2021 due to road-right-of-
REPLACEMENT OF BRIDGE C. 10/29/2021 C. -67.88 enter issues) were done to come up with a way problems encountered at the
ALONG JCT. DAVAO CITY detailed estimates that were used project site. Once project is resumed
DIVERSION RD. - MAGTUOD RD. to be the basis of giving cash and equivalent Time Extension is
- NEW CARMEN - BIAO ESCUELA assistance to the affected approved, the revised planned
- BIAO JOAQUIN - JCT. DAVAO - residents. Project was suspended schedule will be 15.300% and
BUKIDNON RD., DAVAO CITY effective 16 April 2021 due to Road incurred a positive slippage of
GEMMA CONSTRUCTION Right-of-Way at the project site. 6.717%. Request for revision on
SUPPLY, INC. process.
(FORMERLY:GEMMA CON (5044) P00443425MN- Tagging, inventory, and The project was suspended effective
CW2 (Permit to identification of affected persons April 16, 2021 due to road-right-of-
enter issues) were done to come up with a way problems encountered at the
detailed estimates that were used project site. Once project is resumed
to be the basis of giving cash and equivalent Time Extension is
assistance to the affected approved, the revised planned
residents. Project was suspended schedule will be 15.300% and
effective 16 April 2021 due to Road incurred a positive slippage of
Right-of-Way at the project site. 6.717%. Request for revision on
process.
115 20L00153 A. 261,026,662.28 A. 12/29/2020 A. 85.47 P00443428MN- Tagging, inventory, and The project was suspended effective
ROAD WIDENING AND B. 261,026,662.28 B. 10/24/2021 B. 3.12 CW1 (Permit to identification of affected persons April 16, 2021 due to road-right-of-
REPLACEMENT OF BRIDGE C. 10/24/2021 C. -82.35 enter issues) were done to come up with a way problems encountered at the
ALONG JCT. DAVAO CITY detailed estimates that were used project site. Once project is resumed
DIVERSION RD. (MATINA PANGI to be the basis of giving cash and equivalent Time Extension is
SECTION) - MATINA PANGI RD. - assistance to the affected approved, the revised planned
SITIO TORIL - JCT. CATALUNAN residents. Project was suspended schedule will be 12.68% and incurred
GRANDE RD., DAVAO CITY effective 16 April 2021 due to Road negative slippage of -9.56%.
GEMMA CONSTRUCTION Right-of-Way at the project site. Request for revision on process.
SUPPLY, INC. P00443428MN- Tagging, inventory, and The project was suspended effective
(FORMERLY:GEMMA CON (5044) CW2 (Permit to identification of affected persons April 16, 2021 due to road-right-of-
enter issues) were done to come up with a way problems encountered at the
detailed estimates that were used project site. Once project is resumed
to be the basis of giving cash and equivalent Time Extension is
assistance to the affected approved, the revised planned
residents. Project was suspended schedule will be 12.68% and incurred
effective 16 April 2021 due to Road negative slippage of -9.56%.
Right-of-Way at the project site. Request for revision on process.

PCMA 8/31/2021 5:01:21 PM Page 81 Of 105


116 20L00154 A. 131,452,273.37 A. 1/21/2021 A. 93.66 P00443435MN- Tagging, inventory, and The project was suspended effective
ROAD WIDENING ALONG JCT. B. 131,452,273.37 B. 11/6/2021 B. 16.83 CW1 (Permit to identification of affected persons April 16, 2021 due to road-right-of-
DAVAO CITY DIVERSION ROAD - C. 11/6/2021 C. -76.83 enter issues) were done to come up with a way problems encountered at the
LANGUB ROAD - MAGTUOD detailed estimates that were used project site. Once project is resumed
ROAD, DAVAO CITY to be the basis of giving cash and equivalent Time Extension is
GEMMA CONSTRUCTION assistance to the affected approved, the revised planned
SUPPLY, INC. residents. Project was suspended schedule will be 11.174% and
(FORMERLY:GEMMA CON (5044) effective 16 April 2021 due to Road incurred a positive slippage of
Right-of-Way at the project site. 5.657%. Request for revision on
process.
P00443435MN- Tagging, inventory, and The project was suspended effective
CW2 (Permit to identification of affected persons April 16, 2021 due to road-right-of-
enter issues) were done to come up with a way problems encountered at the
detailed estimates that were used project site. Once project is resumed
to be the basis of giving cash and equivalent Time Extension is
assistance to the affected approved, the revised planned
residents. Project was suspended schedule will be 11.174% and
effective 16 April 2021 due to Road incurred a positive slippage of
Right-of-Way at the project site. 5.657%. Request for revision on
process.
117 20L00159 A. 417,886,638.01 A. 1/19/2021 A. 63.86 1. The project is On-going.
CONSTRUCTION OF ASPHALT B. 417,886,638.01 B. 12/4/2021 B. 59.18
ROAD - DAVAO CITY COASTAL C. 12/4/2021 C. -4.68
BYPASS ROAD (BAGO APLAYA -
TIMES BEACH - ROXAS
AVENUE), PACKAGE 22, DAVAO
CITY
WEE ENG CONSTRUCTION, INC.
(16380)
118 20L00160 A. 400,425,270.70 A. 1/3/2021 A. 71.44 1. The project is On-going.
CONSTRUCTION OF ASPHALT B. 400,425,270.70 B. 11/18/2021 B. 66.56
ROAD - DAVAO CITY COASTAL C. 11/18/2021 C. -4.88
BYPASS ROAD (BAGO APLAYA-
TIMES BEACH-ROXAS AVENUE),
PACKAGE 23, DAVAO CITY
WEE ENG CONSTRUCTION, INC.
(16380)

PCMA 8/31/2021 5:01:21 PM Page 82 Of 105


119 20L00162 A. 371,022,777.88 A. 1/26/2021 A. 41.81 P00444758MN- Negotiation with the Project 1. Project suspended due to Road
CONSTRUCTION OF ASPHALT B. 371,022,777.88 B. 12/11/2021 B. 5.62 CW16 (Permit to Affected Persons (PAPs) and Right-of-Way problem encountered
ROAD - DAVAO CITY COASTAL C. 12/11/2021 C. -36.19 enter issues) processing of documents related to at the project site (May 07, 2021)
BYPASS ROAD (BAGO APLAYA - RROW problem were done. 2. If Time Extension 1 due to WSO1
TIMES BEACH - ROXAS Tagging, inventory, and (Road-Right-of-Way problem) will be
AVENUE), PACKAGE 25, DAVAO identification of Project Affected approved, the reported slippage to
CITY Persons (PAPs) were done to date is -12.843% where the planned
ULTICON BUILDERS, INC. come up with a detailed estimates accomplishment is 18.460%. Once
(17267) / MAC BUILDERS (7249) that were used to be the basis of approved, corresponding request for
just compensation of the PAPs. revision in the PCMA will be
forwarded to PMD-BOC for approval.
P00444758MN- Negotiation with the Project 1. Project suspended due to Road
CW17 (Permit to Affected Persons (PAPs) and Right-of-Way problem encountered
enter issues) processing of documents related to at the project site (May 07, 2021)
RROW problem were done. 2. If Time Extension 1 due to WSO1
Tagging, inventory, and (Road-Right-of-Way problem) will be
identification of Project Affected approved, the reported slippage to
Persons (PAPs) were done to date is -12.843% where the planned
come up with a detailed estimates accomplishment is 18.460%. Once
that were used to be the basis of approved, corresponding request for
just compensation of the PAPs. revision in the PCMA will be
forwarded to PMD-BOC for approval.
P00444758MN- Negotiation with the Project 1. Project suspended due to Road
CW18 (Permit to Affected Persons (PAPs) and Right-of-Way problem encountered
enter issues) processing of documents related to at the project site (May 07, 2021)
RROW problem were done. 2. If Time Extension 1 due to WSO1
Tagging, inventory, and (Road-Right-of-Way problem) will be
identification of Project Affected approved, the reported slippage to
Persons (PAPs) were done to date is -12.843% where the planned
come up with a detailed estimates accomplishment is 18.460%. Once
that were used to be the basis of approved, corresponding request for
just compensation of the PAPs. revision in the PCMA will be
forwarded to PMD-BOC for approval.
120 20L00163 A. 271,860,777.88 A. 1/27/2021 A. 43.48 P00444758MN- The project was suspended due to 1. The project suspended due to
CONSTRUCTION OF ASPHALT B. 271,860,777.88 B. 12/12/2021 B. 0.13 CW19 inaccessibility to the project site. inaccessibility of project site (March
ROAD - DAVAO CITY COASTAL C. 12/12/2021 C. -43.35 (Unworkable site Compliance of the necessary 19, 2021)
BYPASS ROAD (BAGO APLAYA- condition (i.e. documents were provided for the 2. If Time Extension 1 due to WSO1
TIMES BEACH - ROXAS unfavorable corresponding time extension in (Road-Right-of-Way problem) will be
AVENUE), PACKAGE 26, DAVAO weather condition lieu of the suspension. approved, the reported slippage to
CITY at the project site, date is -1.822% where the planned
ULTICON BUILDERS, INC. access to project accomplishment is 1.950%. Once
(17267) / MAC BUILDERS (7249) site not approved, corresponding request for
passable)) revision in the PCMA will be
forwarded to PMD-BOC for approval.

PCMA 8/31/2021 5:01:21 PM Page 83 Of 105


120 20L00163 A. 271,860,777.88 A. 1/27/2021 A. 43.48 P00444758MN- The project was suspended due to 1. The project suspended due to
CONSTRUCTION OF ASPHALT B. 271,860,777.88 B. 12/12/2021 B. 0.13 CW20 inaccessibility to the project site. inaccessibility of project site (March
ROAD - DAVAO CITY COASTAL C. 12/12/2021 C. -43.35 (Unworkable site Compliance of the necessary 19, 2021)
BYPASS ROAD (BAGO APLAYA- condition (i.e. documents were provided for the 2. If Time Extension 1 due to WSO1
TIMES BEACH - ROXAS unfavorable corresponding time extension in (Road-Right-of-Way problem) will be
AVENUE), PACKAGE 26, DAVAO weather condition lieu of the suspension. approved, the reported slippage to
CITY at the project site, date is -1.822% where the planned
ULTICON BUILDERS, INC. access to project accomplishment is 1.950%. Once
(17267) / MAC BUILDERS (7249) site not approved, corresponding request for
passable)) revision in the PCMA will be
forwarded to PMD-BOC for approval.
121 20L00164 A. 381,054,027.98 A. 1/3/2021 A. 59.18 P00444758MN- Negotiation with the Project 1. The project is suspended effective
CONSTRUCTION OF ASPHALT B. 381,054,027.98 B. 11/18/2021 B. 25.29 CW21 (Permit to Affected Persons (PAPs) and 16 February 2021 due to Road-
ROAD - DAVAO CITY COASTAL C. 11/18/2021 C. -33.89 enter issues) processing of documents related to Right-of-Way problems (structures
BYPASS ROAD (BAGO APLAYA - RROW problem were done. and land).
TIMES BEACH - ROXAS Tagging/ inventory/ identification of 2. If Time Extension 1 due to WSO1
AVENUE), PACKAGE 27, DAVAO Project Affected Persons (PAPs) (Road-Right-of-Way problem) will be
CITY were done to come up with a approved, the reported slippage to
R.D. INTERIOR JUNIOR detailed estimate that were used to date is 19.660% where the planned
CONSTRUCTION (6483) / RELY be the basis of just compensation accomplishment is 5.630%. Once
CONSTRUCTION & SUPPLY of the PAPs. approved, corresponding request for
(10433) revision in the PCMA will be
forwarded to PMD-BOC for approval.
P00444758MN- Negotiation with the Project 1. The project is suspended effective
CW22 (Permit to Affected Persons (PAPs) and 16 February 2021 due to Road-
enter issues) processing of documents related to Right-of-Way problems (structures
RROW problem were done. and land).
Tagging/ inventory/ identification of 2. If Time Extension 1 due to WSO1
Project Affected Persons (PAPs) (Road-Right-of-Way problem) will be
were done to come up with a approved, the reported slippage to
detailed estimate that were used to date is 19.660% where the planned
be the basis of just compensation accomplishment is 5.630%. Once
of the PAPs. approved, corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.

PCMA 8/31/2021 5:01:21 PM Page 84 Of 105


122 20L00165 A. 290,023,859.90 A. 1/3/2021 A. 61.56 P00444758MN- Negotiation with the Project 1. The project is suspended effective
CONSTRUCTION OF ASPHALT B. 290,023,859.90 B. 11/18/2021 B. 25.06 CW23 (Permit to Affected Persons (PAPs) and 16 February 2021 due to Road-
ROAD - DAVAO CITY COASTAL C. 11/18/2021 C. -36.50 enter issues) processing of documents related to Right-of-Way problems (structures
BYPASS ROAD (BAGO APLAYA- RROW problem were done. and land).
TIMES BEACH-ROXAS AVENUE), Tagging/ inventory/ identification of 2. If Time Extension 1 due to WSO1
PACKAGE 28, DAVAO CITY Project Affected Persons (PAPs) (Road-Right-of-Way problem) will be
WEE ENG CONSTRUCTION, INC. were done to come up with a approved, the reported slippage to
(16380) / HI-VIEW RESOURCES & detailed estimate that were used to date is 12.495% where the planned
DEVELOPMENT CORPORATION be the basis of just compensation accomplishment is 12.570%. Once
(28505) of the PAPs. approved, corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.
P00444758MN- Negotiation with the Project 1. The project is suspended effective
CW24 (Permit to Affected Persons (PAPs) and 16 February 2021 due to Road-
enter issues) processing of documents related to Right-of-Way problems (structures
RROW problem were done. and land).
Tagging/ inventory/ identification of 2. If Time Extension 1 due to WSO1
Project Affected Persons (PAPs) (Road-Right-of-Way problem) will be
were done to come up with a approved, the reported slippage to
detailed estimate that were used to date is 12.495% where the planned
be the basis of just compensation accomplishment is 12.570%. Once
of the PAPs. approved, corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.
P00444758MN- Negotiation with the Project 1. The project is suspended effective
CW25 (Permit to Affected Persons (PAPs) and 16 February 2021 due to Road-
enter issues) processing of documents related to Right-of-Way problems (structures
RROW problem were done. and land).
Tagging/ inventory/ identification of 2. If Time Extension 1 due to WSO1
Project Affected Persons (PAPs) (Road-Right-of-Way problem) will be
were done to come up with a approved, the reported slippage to
detailed estimate that were used to date is 12.495% where the planned
be the basis of just compensation accomplishment is 12.570%. Once
of the PAPs. approved, corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.

PCMA 8/31/2021 5:01:21 PM Page 85 Of 105


123 20L00167 A. 91,617,809.84 A. 10/28/2020 A. 100.00 P00443274MN- Negotiation with the project Project resumed effective August 23,
CONSTRUCTION OF B. 91,617,809.84 B. 6/24/2021 B. 90.37 CW1 (Permit to affected persons and processing of 2021. Once equivalent Time
KAPATAGAN - DAMPING - C. 8/4/2021 C. -9.63 enter issues) documents related to RROW Extension is approved, request for
NAMIHAN - TAPAYANON, problems were done. The revision in the PCMA will then be
KAPALONG, DAVAO DEL NORTE contractor requested for Work sent to the BOC-PMD for approval.
- TAWINIAN, LORETO, AGUSAN Suspension Order No. 1 due to
DEL SUR (PACKAGE A) encountered RROW issues. Once
MAC BUILDERS (7249) Contract Time Extension due to
WSO is approved, corresponding
Request for Revision in the PCMA
will then be submitted to the BOC-
PMD for approval.
P00443274MN- The contractor requested for 5/26/2021 Project resumed effective August 23,
CW1 contract time extension due to bad 2021. Once equivalent Time
(Unworkable site weather Extension is approved, request for
condition (i.e. revision in the PCMA will then be
unfavorable sent to the BOC-PMD for approval.
weather condition
at the project site,
access to project
site not
passable))
124 20L00168 A. 96,524,988.55 A. 12/28/2020 A. 100.00 project completed as of June 15,
REPAIR/REHABILITATION/IMPRO B. 96,524,988.55 B. 6/26/2021 B. 98.87 2021. time extension on process
VEMENT OF ROAD (ASPHALT C. 6/26/2021 C. -1.13 once approved will be forwarded to
OVERLAY) ALONG MONTEVISTA BOC-PMD for approval.
- COMPOSTELA - NEW BATAAN -
MARAGUSAN - MATI BDRY.
ROAD, COMPOSTELA VALLEY
RELY CONSTRUCTION &
SUPPLY (10433)
125 20L00169 A. 96,524,977.82 A. 12/28/2020 A. 100.00 P00444752MN- Request for Time Extension of 25 -Project completed as of 05 August
PREVENTIVE MAINTENANCE OF B. 96,524,977.82 B. 6/26/2021 B. 98.77 CW1 Calendar days due to bad weather 2021 with minor defects
ROAD: ASPHALT OVERLAY - C. 7/21/2021 C. -1.23 (Unworkable site condition -Variation Order No. 1 with Time
SPECIFIC LOCATIONS ALONG condition (i.e. Extension on process, once
DIGOS - MAKAR ROAD unfavorable approved corresponding request for
(S00202MN) K1580 + 897 - K1584 weather condition revision in the PCMA will be
+ 066 DAVAO DEL SUR at the project site, forwarded to PMD-BOC for approval.
RELY CONSTRUCTION & access to project
SUPPLY (10433) site not
passable))

PCMA 8/31/2021 5:01:21 PM Page 86 Of 105


126 20L00170 A. 77,690,052.86 A. 12/22/2020 A. 96.12 P00443372MN- Negotiation with the project project suspended as of March
RECONSTRUCTION TO B. 77,690,052.86 B. 9/27/2021 B. 33.24 CW1 (Permit to affected persons and processing of 01,2021due to Road Right of Way/
CONCRETE PAVEMENT ALONG C. 9/27/2021 C. -62.88 enter issues) documents related to RROW revision for Pcma is on process once
JCT. DAANG MAHARLIKA ROAD - problem were done. approved will be forwarded to BOC-
GOV. GREGORIO V. CAÑEDA Tagging/inventory/identification of PMD for approval.
ROAD - JCT. FS DIZON ROAD, affected persons were done to
DAVAO CITY come up with a detailed estimates
RAKKI CORPORATION (43053) / that were used to be the basis of
RELY CONSTRUCTION & giving cash assistance to the
SUPPLY (10433) affected residents. Once approved,
the corresponding Request for
Revision will then be submitted to
BOC-PMD for approval. The
project was suspended March 01,
2021 due to RROW
127 20L00174 A. 70,546,815.06 A. 11/16/2020 A. 100.00 P00401501MN- The contractor was advised to "- Project completed on 24 August
CONSTRUCTION OF SUMLOG B. 70,546,815.06 B. 7/25/2021 B. 94.95 CW1 (Permit to work on section without road right- 2021, .
PARALLEL BRIDGE C. 7/25/2021 C. -5.05 enter issues) of-way problem. -As-built and COC on process."
(SUBSTRUCTURE ONLY) ALONG
PRES. DIOSDADO P.
MACAPAGAL NATL HI-WAY,
DAVAO ORIENTAL
MAVERICK BUILDERS
INCORPORATED (FORMERLY
MAVERICK (14466)
128 20L00180 A. 28,080,664.89 A. 2/8/2021 A. 100.00 P00436506MN- Work Suspension Order no. 1 was Project resumed effective 07 June
CONSTRUCTION/REHABILITATIO B. 28,080,664.89 B. 7/7/2021 B. 84.25 CW1 issued to the contractor effective 2021. Revision in the PCMA on
N/IMPROVEMENT OF FACILITIES C. 7/7/2021 C. -15.75 (Unworkable site 01 April 2021 due to inaccessibility process, Variation order No. 1 on
FOR PERSONS WITH condition (i.e. of the project area. process. Once approved, request for
DISABILITIES (PWD) AND unfavorable revision in the PCMA will then be
ELDERLIES/SENIOR CITIZENS weather condition sent to the BOC-PMD for approval.
INCLUDING GENDER at the project site,
RESPONSIVE FACILITIES, DPWH access to project
COMPOUND REGIONAL OFFICE site not
XI, DAVAO CITY passable))
MFDB CONSTRUCTION SUPPLY
AND SERVICES (FORMERLY:
MFDB GENERAL MERCHANDISE)
(47258)

PCMA 8/31/2021 5:01:21 PM Page 87 Of 105


129 21L00003 A. 121,583,777.88 A. 4/26/2021 A. 35.04 P00550726MN- on-going negotiation with the Project suspended effective 10 June
CONSTRUCTION OF ROAD - B. 121,583,777.88 B. 2/19/2022 B. 6.35 CW1 (Permit to affected structures 2021 due to road right of way
COMPOSTELA VALLEY - C. 2/19/2022 C. -28.69 enter issues) problem (difficulty in land
VERUELA ROAD, AGUSAN DEL acquisition). Once project is resumed
SUR ROAD, (PACKAGE 1), and equivalent times extension is
MONKAYO, DAVAO DE ORO approved, revised planned schedule
ULTICON BUILDERS, INC. will be 08.30% and incurred negative
(17267) slippage of -1.95%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
P00550726MN- on-going negotiation with the Project suspended effective 10 June
CW2 (Permit to affected structures 2021 due to road right of way
enter issues) problem (difficulty in land
acquisition). Once project is resumed
and equivalent times extension is
approved, revised planned schedule
will be 08.30% and incurred negative
slippage of -1.95%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
P00550726MN- on-going negotiation with the Project suspended effective 10 June
CW3 (Permit to affected structures 2021 due to road right of way
enter issues) problem (difficulty in land
acquisition). Once project is resumed
and equivalent times extension is
approved, revised planned schedule
will be 08.30% and incurred negative
slippage of -1.95%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 88 Of 105


129 21L00003 A. 121,583,777.88 A. 4/26/2021 A. 35.04 P00550726MN- on-going negotiation with the Project suspended effective 10 June
CONSTRUCTION OF ROAD - B. 121,583,777.88 B. 2/19/2022 B. 6.35 CW4 (Permit to affected structures 2021 due to road right of way
COMPOSTELA VALLEY - C. 2/19/2022 C. -28.69 enter issues) problem (difficulty in land
VERUELA ROAD, AGUSAN DEL acquisition). Once project is resumed
SUR ROAD, (PACKAGE 1), and equivalent times extension is
MONKAYO, DAVAO DE ORO approved, revised planned schedule
ULTICON BUILDERS, INC. will be 08.30% and incurred negative
(17267) slippage of -1.95%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
130 21L00004 A. 121,585,777.88 A. 4/26/2021 A. 43.71 P00550727MN- on-going negotiation with the Project suspended effective 10 June
CONSTRUCTION OF ROAD - B. 121,585,777.88 B. 2/19/2022 B. 21.25 CW1 (Permit to affected structures 2021 due to road right of way
COMPOSTELA VALLEY - C. 2/19/2022 C. -22.46 enter issues) problem (difficulty in land
VERUELA ROAD, AGUSAN DEL acquisition). Once project is resumed
SUR ROAD (PACKAGE 2), and equivalent times extension is
MONKAYO, DAVAO DE ORO approved, revised planned schedule
ULTICON BUILDERS, INC. will be 14.12% and incurred negative
(17267) slippage of -1.66%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
P00550727MN- on-going negotiation with the Project suspended effective 10 June
CW2 (Permit to affected structures 2021 due to road right of way
enter issues) problem (difficulty in land
acquisition). Once project is resumed
and equivalent times extension is
approved, revised planned schedule
will be 14.12% and incurred negative
slippage of -1.66%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 89 Of 105


131 21L00005 A. 121,582,777.88 A. 4/26/2021 A. 49.57 P00550728MN- on-going negotiation with the Project suspended effective 10 June
CONSTRUCTION OF ROAD - B. 121,582,777.88 B. 2/19/2022 B. 23.35 CW1 (Permit to affected structures 2021 due to road right of way
COMPOSTELA VALLEY - C. 2/19/2022 C. -26.22 enter issues) problem (difficulty in land
VERUELA ROAD, AGUSAN DEL acquisition). Once project is resumed
SUR ROAD (PACKAGE 3), and equivalent times extension is
MONKAYO, DAVAO DE ORO approved, revised planned schedule
ULTICON BUILDERS, INC. will be 12.30% and incurred negative
(17267) slippage of -1.80%. Revision in the
PCMA on process, waiting for
approved time extension in view of
approved suspension and
resumption order.
132 21L00006 A. 121,585,777.88 A. 4/26/2021 A. 56.07 project is on going
CONSTRUCTION OF ROAD - B. 121,585,777.88 B. 2/2/2022 B. 55.06
NEW BATAAN - BAGANGA ROAD C. 2/2/2022 C. -1.01
(TAYTAYAN - MANURIGAO, NEW
BATAAN), PACKAGE 1, DAVAO
DE ORO
ULTICON BUILDERS, INC.
(17267)
133 21L00010 A. 122,278,407.41 A. 4/26/2021 A. 64.00 P00550757MN- on-going negotiation with the -Project resumed as of 01 August
CONSTRUCTION OF ROAD, B. 122,278,407.41 B. 2/2/2022 B. 35.77 CW1 (Permit to affected structures 2021
POBLACION, MARAGUSAN - C. 2/2/2022 C. -28.23 enter issues) -Contract Time Extension due to
PALOC ROAD, (PACKAGE 1), Work Suspension on process, once
DAVAO DE ORO approved corresponding request for
ULTICON BUILDERS, INC. revision in the PCMA will be
(17267) forwarded to PMD-BOC for approval.
P00550757MN- on-going negotiation with the -Project resumed as of 01 August
CW2 (Permit to affected structures 2021
enter issues) -Contract Time Extension due to
Work Suspension on process, once
approved corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.
P00550757MN- Reminder/ Warning letters were 6/10/2021 -Project resumed as of 01 August
CW1 (Slow given to the contractor to eliminate 2021
Performance) the incurred negative slippage. -Contract Time Extension due to
Work Suspension on process, once
approved corresponding request for
revision in the PCMA will be
forwarded to PMD-BOC for approval.

PCMA 8/31/2021 5:01:21 PM Page 90 Of 105


133 21L00010 A. 122,278,407.41 A. 4/26/2021 A. 64.00 P00550757MN- Reminder/ Warning letters were 6/10/2021 -Project resumed as of 01 August
CONSTRUCTION OF ROAD, B. 122,278,407.41 B. 2/2/2022 B. 35.77 CW2 (Slow given to the contractor to eliminate 2021
POBLACION, MARAGUSAN - C. 2/2/2022 C. -28.23 Performance) the incurred negative slippage. -Contract Time Extension due to
PALOC ROAD, (PACKAGE 1), Work Suspension on process, once
DAVAO DE ORO approved corresponding request for
ULTICON BUILDERS, INC. revision in the PCMA will be
(17267) forwarded to PMD-BOC for approval.
P00550757MN- Contract Time Extension due to 8/1/2021 -Project resumed as of 01 August
CW1 (Delays in Work Suspension on process, 2021
approval of Time once approved corresponding -Contract Time Extension due to
Suspension/Exte request for revision in the PCMA Work Suspension on process, once
nsion) will be forwarded to PMD-BOC for approved corresponding request for
approval. revision in the PCMA will be
forwarded to PMD-BOC for approval.
134 21L00011 A. 121,932,414.94 A. 4/16/2021 A. 59.79 P00550758MN- on-going negotiation with the '-Project resumed as of 01 August
CONSTRUCTION OF ROAD, B. 121,932,414.94 B. 1/20/2022 B. 44.83 CW1 (Permit to affected structures 2021
POBLACION, MARAGUSAN - C. 1/20/2022 C. -14.96 enter issues) -Contract Time Extension due to
PALOC ROAD, PACKAGE 2, Work Suspension on process, once
DAVAO DE ORO approved corresponding request for
O. G. SANTOS CONSTRUCTION revision in the PCMA will be
(2050) forwarded to PMD-BOC for approval.
135 21L00012 A. 121,938,448.64 A. 4/26/2021 A. 43.53 P00550759MN- On-going negotiation with the '-Project resumed as of 01 August
CONSTRUCTION OF ROAD, B. 121,938,448.64 B. 1/30/2022 B. 22.18 CW1 (Permit to affected individuals 2021
POBLACION, MARAGUSAN - C. 1/30/2022 C. -21.35 enter issues) -Contract Time Extension due to
PALOC ROAD, PACKAGE 3, Work Suspension on process, once
DAVAO DE ORO approved corresponding request for
ALPHA & OMEGA GEN. revision in the PCMA will be
CONTRACTOR & DEVELOPMENT forwarded to PMD-BOC for approval.
CORP. (38958)
136 21L00013 A. 65,510,461.65 A. 4/26/2021 A. 36.15 P00502192MN- Issued Work Suspension Order Project suspended dated 16 July
ROAD WIDENING - MAWAB - B. 65,510,461.65 B. 1/7/2022 B. 28.93 CW1 (Permit to No. 1 due to RROW (structures 2021 due to RROW Problem
MACO BYPASS ROAD, PACKAGE C. 1/7/2022 C. -7.22 enter issues) and improvements). (Structures and Improvements).
C, DAVAO DE ORO Once the project is resumed and
ULTICON BUILDERS, INC. equivalent Time Extension is
(17267) approved, revised planned schedule
will be 19.26% and incurred slippage
of 9.67%.

PCMA 8/31/2021 5:01:21 PM Page 91 Of 105


136 21L00013 A. 65,510,461.65 A. 4/26/2021 A. 36.15 P00502192MN- Issued Work Suspension Order Project suspended dated 16 July
ROAD WIDENING - MAWAB - B. 65,510,461.65 B. 1/7/2022 B. 28.93 CW2 (Permit to No. 1 due to RROW (structures 2021 due to RROW Problem
MACO BYPASS ROAD, PACKAGE C. 1/7/2022 C. -7.22 enter issues) and improvements). (Structures and Improvements).
C, DAVAO DE ORO Once the project is resumed and
ULTICON BUILDERS, INC. equivalent Time Extension is
(17267) approved, revised planned schedule
will be 19.26% and incurred slippage
of 9.67%.
137 21L00014 A. 77,252,777.88 A. 5/5/2021 A. 57.11 P00502193MN- issued Work Suspension Order No. Project suspended dated 01 June
CONSTRUCTION OF CONCRETE B. 77,252,777.88 B. 1/28/2022 B. 0.18 CW1 (Permit to 1 dated 01 June 2021 due to 2021 due to RROW Problem
BRIDGE - MAWAB - MACO C. 1/28/2022 C. -56.93 enter issues) RROW Problem (Structures and (Structures and Improvements).
BYPASS ROAD (PACKAGE D), Improvements) Once the project is resumed and
DAVAO DE ORO equivalent Time Extension is
ULTICON BUILDERS, INC. approved, revised planned schedule
(17267) will be 4.77% and incurred negative
slippage of 4.59%.
138 21L00016 A. 84,678,579.65 A. 4/16/2021 A. 84.34 P00502204MN- Conctractor Requested for Project is suspended
CONSTRUCTION OF CONCRETE B. 84,678,579.65 B. 12/5/2021 B. 53.06 CW1 (Permit to Contract Time Suspension / Work as of July 16,
ROAD - NABUNTURAN - NEW C. 12/5/2021 C. -31.28 enter issues) Suspension Due to Road Right of 2021.(In
CORELLA - TAGUM ROAD Way Problem. On going connection to WSO,
(NABUNTURAN SECTION), negotiation with PAPs. WRO
DAVAO DE ORO and CTE, revised
NEN BUILDERS AND construction
DEVELOPMENT SERVICES schedule is
CORPORATION (42265) 56.96% and incurred
slippage of 0.01%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is January 21,
2022

PCMA 8/31/2021 5:01:21 PM Page 92 Of 105


138 21L00016 A. 84,678,579.65 A. 4/16/2021 A. 84.34 P00502204MN- Conctractor Requested for Project is suspended
CONSTRUCTION OF CONCRETE B. 84,678,579.65 B. 12/5/2021 B. 53.06 CW2 (Permit to Contract Time Suspension / Work as of July 16,
ROAD - NABUNTURAN - NEW C. 12/5/2021 C. -31.28 enter issues) Suspension Due to Road Right of 2021.(In
CORELLA - TAGUM ROAD Way Problem. On going connection to WSO,
(NABUNTURAN SECTION), negotiation with PAPs. WRO
DAVAO DE ORO and CTE, revised
NEN BUILDERS AND construction
DEVELOPMENT SERVICES schedule is
CORPORATION (42265) 56.96% and incurred
slippage of 0.01%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is January 21,
2022
139 21L00017 A. 45,471,777.88 A. 4/21/2021 A. 40.86 P00502199MN- Negotiation with the project Project suspended effective August
CONSTRUCTION OF CONCRETE B. 45,471,777.88 B. 12/16/2021 B. 38.61 CW1 (Permit to affected persons and processing of 25, 2021 due to unsettled Road right
ROAD - BUKIDNON - C. 12/16/2021 C. -2.25 enter issues) documents related to RROW of way problem encountered during
COMPOSTELA VALLEY ROAD problems were done. The construction activities. Once project
(BRGY. NAMNAM, SAN contractor requested for Work is resumed and equivalent Time
FERNANDO, BUKIDNON - LAAK, Suspension Order No. 1 due to Extension is approved, the revised
COMPOSTELA VALLEY) encountered RROW issues. Once planned schedule will be 38.42% and
PACKAGE 4, DAVAO DE ORO Contract Time Extension due to the incurred slippage 0.19%.
ULTICON BUILDERS, INC. WSO is approved, corresponding Revision in the PCMA on process,
(17267) Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.
140 21L00018 A. 49,513,777.88 A. 4/26/2021 A. 57.40 P00502074MN- Negotiation with the project Project suspended effective July 01,
CONSTRUCTION OF CONCRETE B. 49,513,777.88 B. 12/15/2021 B. 21.90 CW1 (Permit to affected persons and processing of 2021 due to unsettled Road right of
BRIDGE - BUKIDNON - C. 12/15/2021 C. -35.50 enter issues) documents related to RROW way problem encountered during
COMPOSTELA VALLEY ROAD problems were done. The construction activities. Once project
(BRGY. NAMNAM, SAN contractor requested for Work is resumed and equivalent Time
FERNANDO, BUKIDNON - LAAK, Suspension Order No. 1 due to Extension is approved, the revised
COMPOSTELA VALLEY) encountered RROW issues. Once planned schedule will be 22.16% and
PACKAGE 5, DAVAO DE ORO Contract Time Extension due to the incurred slippage 0.01%.
ULTICON BUILDERS, INC. WSO is approved, corresponding Revision in the PCMA on process,
(17267) Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.

PCMA 8/31/2021 5:01:21 PM Page 93 Of 105


140 21L00018 A. 49,513,777.88 A. 4/26/2021 A. 57.40 P00502074MN- Negotiation with the project Project suspended effective July 01,
CONSTRUCTION OF CONCRETE B. 49,513,777.88 B. 12/15/2021 B. 21.90 CW2 (Permit to affected persons and processing of 2021 due to unsettled Road right of
BRIDGE - BUKIDNON - C. 12/15/2021 C. -35.50 enter issues) documents related to RROW way problem encountered during
COMPOSTELA VALLEY ROAD problems were done. The construction activities. Once project
(BRGY. NAMNAM, SAN contractor requested for Work is resumed and equivalent Time
FERNANDO, BUKIDNON - LAAK, Suspension Order No. 1 due to Extension is approved, the revised
COMPOSTELA VALLEY) encountered RROW issues. Once planned schedule will be 22.16% and
PACKAGE 5, DAVAO DE ORO Contract Time Extension due to the incurred slippage 0.01%.
ULTICON BUILDERS, INC. WSO is approved, corresponding Revision in the PCMA on process,
(17267) Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.
141 21L00019 A. 45,177,777.88 A. 4/21/2021 A. 36.42 P00502075MN- Negotiation with the project Project suspended effective August
CONSTRUCTION OF CONCRETE B. 45,177,777.88 B. 12/16/2021 B. 34.43 CW1 (Permit to affected persons and processing of 25, 2021 due to unsettled Road right
ROAD - BUKIDNON - C. 12/16/2021 C. -1.99 enter issues) documents related to RROW of way problem encountered during
COMPOSTELA VALLEY ROAD problems were done. The construction activities. Once project
(BRGY. NAMNAM, SAN contractor requested for Work is resumed and equivalent Time
FERNANDO, BUKIDNON - LAAK, Suspension Order No. 1 due to Extension is approved, the revised
COMPOSTELA VALLEY) encountered RROW issues. Once planned schedule will be 34.27% and
PACKAGE 6, DAVAO DE ORO Contract Time Extension due to the incurred slippage 0.16%.
ULTICON BUILDERS, INC. WSO is approved, corresponding Revision in the PCMA on process,
(17267) Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.
142 21L00020 A. 31,157,394.91 A. 3/28/2021 A. 97.02 P00502194MN- Instructed the Project is on going.
CONSTRUCTION OF CONCRETE B. 31,157,394.91 B. 9/14/2021 B. 92.45 CW1 contractor to
ROAD - MONTEVISTA - DNAS C. 9/14/2021 C. -4.57 (Unworkable site conduct overtime
(DNAS-LAAK), PACKAGE E, condition (i.e. works in order to
DAVAO DE ORO unfavorable cover-up wasted
O. G. SANTOS CONSTRUCTION weather condition time/days due to
(2050) at the project site, unworkable ground
access to project caused by bad
site not weather condition.
passable))
143 21L00025 A. 10,140,165.07 A. 3/28/2021 A. 100.00 The project was completed as of 05
CONSTRUCTION OF CONCRETE B. 10,140,165.07 B. 7/5/2021 B. 93.97 July 2021 with minor corrections.
ROAD - MAWAB - MARAGUSAN - C. 7/5/2021 C. -6.03
CARAGA ROAD, SECTION 2,
PACKAGE F, DAVAO DE ORO
ROSBILL CONSTRUCTION AND
SUPPLY (45622)

PCMA 8/31/2021 5:01:21 PM Page 94 Of 105


144 21L00026 A. 47,600,777.88 A. 4/20/2021 A. 42.39 P00502076MN- Negotiation with the project "
CONSTRUCTION OF CONCRETE B. 47,600,777.88 B. 12/15/2021 B. 40.74 CW1 (Permit to affected persons and processing of Project suspended effective August
ROAD - BUKIDNON - C. 12/15/2021 C. -1.65 enter issues) documents related to RROW 25, 2021 due to unsettled Road right
COMPOSTELA VALLEY ROAD problems were done. The of way problem encountered during
(BRGY. NAMNAM, SAN contractor requested for Work construction activities. Once project
FERNANDO, BUKIDNON - LAAK, Suspension Order No. 1 due to is resumed and equivalent Time
COMPOSTELA VALLEY) encountered RROW issues. Once Extension is approved, the revised
PACKAGE 7, DAVAO DE ORO Contract Time Extension due to planned schedule will be 40.61% and
ULTICON BUILDERS, INC. WSO is approved, corresponding the incurred slippage 0.13%.
(17267) Request for Revision in the PCMA Revision in the PCMA on process,
will then be submitted to the BOC- waiting for approved time extension
PMD for approval. in view of the approved suspension
and resumption order."
145 21L00027 A. 76,271,886.64 A. 4/26/2021 A. 47.20 P00502230MN- Conctractor Requested for Project is suspended
CONSTRUCTION OF CONCRETE B. 76,271,886.64 B. 2/5/2022 B. 32.41 CW1 (Permit to Contract Time Suspension / Work as of July 01,
ROAD - NABUNTURAN - LAAK C. 2/5/2022 C. -14.79 enter issues) Suspension Due to Road Right of 2021 due to RROW
ROAD, (PACKAGE 1), DAVAO DE Way Problem. On going problem.
ORO negotiation with PAPs. (In
TAGUM BUILDERS connection to WSO,
CONTRACTORS CORP. WRO
(FORMERLY: TAGUM (34019) and CTE, revised
construction
schedule is
7.11% and incurred
slippage of 25.31%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is May 14,
2022.

PCMA 8/31/2021 5:01:21 PM Page 95 Of 105


145 21L00027 A. 76,271,886.64 A. 4/26/2021 A. 47.20 P00502230MN- Conctractor Requested for Project is suspended
CONSTRUCTION OF CONCRETE B. 76,271,886.64 B. 2/5/2022 B. 32.41 CW2 (Permit to Contract Time Suspension / Work as of July 01,
ROAD - NABUNTURAN - LAAK C. 2/5/2022 C. -14.79 enter issues) Suspension Due to Road Right of 2021 due to RROW
ROAD, (PACKAGE 1), DAVAO DE Way Problem. On going problem.
ORO negotiation with PAPs. (In
TAGUM BUILDERS connection to WSO,
CONTRACTORS CORP. WRO
(FORMERLY: TAGUM (34019) and CTE, revised
construction
schedule is
7.11% and incurred
slippage of 25.31%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is May 14,
2022.
146 21L00028 A. 77,196,936.93 A. 4/19/2021 A. 76.82 P00502200MN- The contractor requested for Work Project is ongoing.
CONSTRUCTION OF CONCRETE B. 77,196,936.93 B. 11/11/2021 B. 69.26 CW1 (Permit to Suspension Order No. 1. .(In
ROAD - NABUNTURAN - LAAK C. 11/11/2021 C. -7.56 enter issues) connection to WSO,
ROAD, (PACKAGE 2), DAVAO DE WRO
ORO and CTE, revised
TAGUM BUILDERS construction
CONTRACTORS CORP. schedule is
(FORMERLY: TAGUM (34019) 54.74% and incurred
slippage of 14.52%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is December 24,
2021

PCMA 8/31/2021 5:01:21 PM Page 96 Of 105


147 21L00031 A. 60,847,950.69 A. 4/26/2021 A. 39.78 P00550745MN- on-going negotiation with the '-Project resumed as of 01 August
CONSTRUCTION OF ROAD - B. 60,847,950.69 B. 12/31/2021 B. 33.49 CW1 (Permit to affected structures 2021
NABUNTURAN - MACO ROAD C. 12/31/2021 C. -6.29 enter issues) -Contract Time Extension due to
(MAINIT, NABUNTURAN - Work Suspension on process, once
MASARA, MACO), (PACKAGE 1), approved corresponding request for
DAVAO DE ORO revision in the PCMA will be
COASTLAND CONSTRUCTION & forwarded to PMD-BOC for approval.
DEVELOPMENT CORP. (11487)
148 21L00032 A. 60,847,159.03 A. 4/26/2021 A. 48.44 P00550746MN- on-going negotiation with the '-Project resumed as of 01 August
CONSTRUCTION OF ROAD - B. 60,847,159.03 B. 12/31/2021 B. 40.65 CW1 (Permit to affected structures 2021
NABUNTURAN - MACO ROAD C. 12/31/2021 C. -7.79 enter issues) -Contract Time Extension due to
(MAINIT, NABUNTURAN - Work Suspension on process, once
MASARA, MACO), (PACKAGE 2), approved corresponding request for
DAVAO DE ORO revision in the PCMA will be
COASTLAND CONSTRUCTION & forwarded to PMD-BOC for approval.
DEVELOPMENT CORP. (11487)
149 21L00033 A. 60,851,976.39 A. 4/22/2021 A. 60.47 P00550747MN- on-going negotiation with the '-Project resumed as of 01 August
CONSTRUCTION OF ROAD - B. 60,851,976.39 B. 12/27/2021 B. 48.25 CW1 (Permit to affected structures 2021
NABUNTURAN - MACO ROAD C. 12/27/2021 C. -12.22 enter issues) -Contract Time Extension due to
(MAINIT, NABUNTURAN - Work Suspension on process, once
MASARA, MACO), (PACKAGE 3), approved corresponding request for
DAVAO DE ORO revision in the PCMA will be
COASTLAND CONSTRUCTION & forwarded to PMD-BOC for approval.
DEVELOPMENT CORP. (11487)
150 21L00049 A. 55,884,361.80 A. 4/26/2021 A. 28.10 P00502215MN- On-going negotiation with the Project suspended effective 16 May
CONSTRUCTION OF ROAD B. 55,884,361.80 B. 1/5/2022 B. 0.45 CW1 (Permit to residents with the help of Legal 2021 due to road right of way
SLOPE PROTECTION C. 1/5/2022 C. -27.65 enter issues) Team problem. Once project is resumed
STRUCTURE - BYPASS ROAD AT and equivalent times extension is
JCT. MAMAY ROAD - LA VERNA - approved, revised planned schedule
DAVAO CITY DIVERSION ROAD will be 0.82% and incurred negative
(JCT. AIRPORT SECTION), slippage of -0.37%. Revision in the
DAVAO CITY PCMA on process, waiting for
R.A. PAHATI CONST. & SUPPLY, approved time extension in view of
INC. (35843) approved suspension and
resumption order.

PCMA 8/31/2021 5:01:21 PM Page 97 Of 105


150 21L00049 A. 55,884,361.80 A. 4/26/2021 A. 28.10 P00502215MN- On-going negotiation with the Project suspended effective 16 May
CONSTRUCTION OF ROAD B. 55,884,361.80 B. 1/5/2022 B. 0.45 CW2 (Permit to residents with the help of Legal 2021 due to road right of way
SLOPE PROTECTION C. 1/5/2022 C. -27.65 enter issues) Team problem. Once project is resumed
STRUCTURE - BYPASS ROAD AT and equivalent times extension is
JCT. MAMAY ROAD - LA VERNA - approved, revised planned schedule
DAVAO CITY DIVERSION ROAD will be 0.82% and incurred negative
(JCT. AIRPORT SECTION), slippage of -0.37%. Revision in the
DAVAO CITY PCMA on process, waiting for
R.A. PAHATI CONST. & SUPPLY, approved time extension in view of
INC. (35843) approved suspension and
resumption order.
151 21L00050 A. 77,859,946.99 A. 3/28/2021 A. 64.06 P00502216MN- Negotiation with the project Project suspended effective June 11,
CONSTRUCTION OF DRAINAGE B. 77,859,946.99 B. 11/26/2021 B. 40.80 CW1 (Permit to affected persons and processing of 2021 due to unsettled Road right of
STRUCTURE - BYPASS ROAD AT C. 11/26/2021 C. -23.26 enter issues) documents related to RROW way problem encountered during
MALAGAMOT ROAD - JCT. problems were done. The construction activities. Once project
MUDIANG ROAD, PHASE II, contractor requested for Work is resumed and equivalent Time
DAVAO CITY Suspension Order No. 1 due to Extension is approved, the revised
MONOLITHIC CONSTRUCTION & encountered RROW issues. Once planned schedule will be 14.856%
CONCRETE PRODUCTS, INC. Contract Time Extension due to and the incurred slippage 26.043%.
(5733) WSO is approved, corresponding Revision in the PCMA on process,
Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.
P00502216MN- Negotiation with the project Project suspended effective June 11,
CW2 (Permit to affected persons and processing of 2021 due to unsettled Road right of
enter issues) documents related to RROW way problem encountered during
problems were done. The construction activities. Once project
contractor requested for Work is resumed and equivalent Time
Suspension Order No. 1 due to Extension is approved, the revised
encountered RROW issues. Once planned schedule will be 14.856%
Contract Time Extension due to and the incurred slippage 26.043%.
WSO is approved, corresponding Revision in the PCMA on process,
Request for Revision in the PCMA waiting for approved time extension
will then be submitted to the BOC- in view of the approved suspension
PMD for approval. and resumption order.

PCMA 8/31/2021 5:01:21 PM Page 98 Of 105


152 21L00051 A. 119,179,625.01 A. 4/26/2021 A. 62.26 P00502217MN- The contractor requested for Work Project is suspended as of May 17,
WIDENING OF BRIDGE - JCT. B. 119,179,625.01 B. 2/24/2022 B. 1.15 CW1 (Permit to Suspension Order No. 1 due to 2021 due to RROW problem.
CABANTIAN ROAD (ACACIA C. 2/24/2022 C. -61.11 enter issues) Road Right-of-Way. Negotiation .(In
SECTION) - JCT. MANDUG - with the affected persons and connection to WSO,
CALLAWA ROAD (MANDUG processing of documents related to WRO
SECTION), DAVAO CITY RROW problem is on process and CTE, revised
WEE ENG CONSTRUCTION, INC. construction
(16380) schedule is
1.198% and incurred
slippage of -0.05%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is June 11,
2022
P00502217MN- The contractor requested for Work Project is suspended as of May 17,
CW2 (Permit to Suspension Order No. 1 due to 2021 due to RROW problem.
enter issues) Road Right-of-Way. Negotiation .(In
with the affected persons and connection to WSO,
processing of documents related to WRO
RROW problem is on process and CTE, revised
construction
schedule is
1.198% and incurred
slippage of -0.05%)
Time Extension
Order is
on process. Once
approved, revisions
in the
pcma will be
forwarded.
Revised Contract
Expiry
Date is June 11,
2022

PCMA 8/31/2021 5:01:21 PM Page 99 Of 105


153 21L00066 A. 46,898,578.87 A. 7/20/2021 A. 7.18 Project on-going.
RECONSTRUCTION TO B. 46,898,578.87 B. 3/11/2022 B. 4.04
CONCRETE PAVEMENT ALONG C. 3/11/2022 C. -3.14
DAANG MAHARLIKA (MN)
(S00060MN), K1455 + 346 - K1456
+ 010, DAVAO DEL NORTE
LICSAL CONSTRUCTION
SERVICES (41652) / ARCINUE
COMM'L CORPORATION (6746)
154 21L00071 A. 168,718,441.90 A. 5/26/2021 A. 45.40 P00502223MN- Issued Work Suspension Order Project suspended dated 01 July
CONSTRUCTION OF CONCRETE B. 168,718,441.90 B. 3/31/2022 B. 7.49 CW1 (Permit to No. 1 due to Road Right of Way 2021 due to RROW Problems.
BRIDGE - CARMEN - TAGUM C. 3/31/2022 C. -37.91 enter issues) problems. Once the project is resumed and
CITY COASTAL ROAD (PACKAGE equivalent Time Extension is
D), DAVAO DEL NORTE approved, revised planned schedule
HEXAMINDZ CORPORATION will be 6.97% and incurred slippage
(FORMERLY:KILUSANG of 0.52%.
MAGKAIBIG (31666) / AKN P00502223MN- Issued Work Suspension Order Project suspended dated 01 July
CONSTRUCTION CORPORATION CW2 (Permit to No.1 due to Rod Right of Way 2021 due to RROW Problems.
(11845) enter issues) problems. Once the project is resumed and
equivalent Time Extension is
approved, revised planned schedule
will be 6.97% and incurred slippage
of 0.52%.
155 21L00072 A. 136,483,520.36 A. 5/26/2021 A. 32.86 P00502224MN- Issued work suspension order due Project suspended dated 16 July
CONSTRUCTION OF CONCRETE B. 136,483,520.36 B. 3/26/2022 B. 4.64 CW1 (Permit to to rrow problems. 2021 due to Road Right of Way
BRIDGE - CARMEN - TAGUM C. 3/26/2022 C. -28.22 enter issues) problems.
CITY COASTAL ROAD (PACKAGE Once the project is resumed and
E), DAVAO DEL NORTE equivalent Time Extension is
HEXAMINDZ CORPORATION approved, revised planned schedule
(FORMERLY:KILUSANG will be 4.64% and incurred negative
MAGKAIBIG (31666) / AKN slippage of 4.89%.
CONSTRUCTION CORPORATION
(11845)
156 21L00073 A. 133,048,914.04 A. 5/11/2021 A. 17.57 P00502225MN- Issued Work Suspension Order Project suspended dated 01 July
CONSTRUCTION OF GRAVEL B. 133,048,914.04 B. 1/10/2022 B. 2.45 CW1 (Permit to No. 1 due to road right-of-way 2021 due to RROW Problems.
ROAD - CARMEN - TAGUM CITY C. 1/10/2022 C. -15.12 enter issues) problems. Once the project is resumed and
COASTAL ROAD (PACKAGE F), equivalent Time Extension is
DAVAO DEL NORTE approved, revised planned schedule
HEXAMINDZ CORPORATION will be 2.08% and incurred slippage
(FORMERLY:KILUSANG of 0.37%.
MAGKAIBIG (31666)

PCMA 8/31/2021 5:01:21 PM Page 100 Of 105


157 21L00074 A. 57,712,477.55 A. 3/24/2021 A. 72.73 P00502226MN- Instructed the contractor to conduct Project is on going.
ROAD WIDENING - B. 57,712,477.55 B. 11/8/2021 B. 60.14 CW1 overtime works in order to cover-up
NABUNTURAN - NEW CORELLA - C. 11/8/2021 C. -12.59 (Unworkable site wasted time/days due to
TAGUM ROAD (NEW CORELLA - condition (i.e. unworkable ground caused by bad
TAGUM SECTION), DAVAO DEL unfavorable weather condition.
NORTE weather condition
MONOLITHIC CONSTRUCTION & at the project site,
CONCRETE PRODUCTS, INC. access to project
(5733) site not
passable))
158 21L00076 A. 131,737,777.88 A. 3/23/2021 A. 56.90 P00502228MN- Negotiation with the project "
ROAD WIDENING - TAGUM CITY B. 131,737,777.88 B. 1/16/2022 B. 56.42 CW1 (Permit to affected persons and processing of Project suspended effective August
BYPASS ROAD (CANOCOTAN - C. 1/16/2022 C. -0.48 enter issues) documents related to RROW 10, 2021 due to unsettled Road right
SAN MIGUEL - PAGSABANGAN), problems were done. The of way problem encountered during
PACKAGE D, DAVAO DEL NORTE contractor requested for Work construction activities. Once project
ULTICON BUILDERS, INC. Suspension Order No. 1 due to is resumed and equivalent Time
(17267) encountered RROW issues. Once Extension is approved, the revised
Contract Time Extension due to planned schedule will be 55.28% and
WSO is approved, corresponding the incurred slippage 1.12%.
Request for Revision in the PCMA Revision in the PCMA on process,
will then be submitted to the BOC- waiting for approved time extension
PMD for approval. in view of the approved suspension
and resumption order."
159 21L00077 A. 154,838,777.88 A. 4/26/2021 A. 76.77 P00502073MN- Instructed the Contractor to Project is on going.
CONSTRUCTION OF GRAVEL B. 154,838,777.88 B. 3/1/2022 B. 69.34 CW1 conduct overtime works in order to
ROAD-BUKIDNON-COMPOSTELA C. 3/1/2022 C. -7.43 (Unworkable site cover-up wasted time/days due to
VALLEY ROAD, BRGY. NAMNAM, condition (i.e. unworkable ground caused by bad
SAN FERNANDO, BUKIDNON- unfavorable weather condition.
LAAK-COMPOSTELA VALLEY, weather condition
(PACKAGE 10), DAVAO DEL at the project site,
NORTE access to project
ULTICON BUILDERS, INC. site not
(17267) passable))
P00502073MN- Instructed the Contractor to Project is on going.
CW2 conduct overtime works in order to
(Unworkable site cover-up wasted time/days due to
condition (i.e. unworkable ground caused by bad
unfavorable weather condition.
weather condition
at the project site,
access to project
site not
passable))

PCMA 8/31/2021 5:01:21 PM Page 101 Of 105


159 21L00077 A. 154,838,777.88 A. 4/26/2021 A. 76.77 P00502073MN- Instructed the Contractor to Project is on going.
CONSTRUCTION OF GRAVEL B. 154,838,777.88 B. 3/1/2022 B. 69.34 CW3 conduct overtime works in order to
ROAD-BUKIDNON-COMPOSTELA C. 3/1/2022 C. -7.43 (Unworkable site cover-up wasted time/days due to
VALLEY ROAD, BRGY. NAMNAM, condition (i.e. unworkable ground caused by bad
SAN FERNANDO, BUKIDNON- unfavorable weather condition.
LAAK-COMPOSTELA VALLEY, weather condition
(PACKAGE 10), DAVAO DEL at the project site,
NORTE access to project
ULTICON BUILDERS, INC. site not
(17267) passable))
160 21L00087 A. 95,476,960.04 A. 4/22/2021 A. 32.90 P00537732MN- On-going negotiations with the Project suspended effective July 01,
CONSTRUCTION OF CONCRETE B. 95,476,960.04 B. 12/22/2021 B. 25.06 CW1 (Permit to affected owners. 2021 due to encountered road right-
ROAD - ISLAND GARDEN CITY C. 12/22/2021 C. -7.84 enter issues) of-way problem (improvements).
OF SAMAL (IGACOS) Once project is resumed and
CIRCUMFERENTIAL ROAD, equivalent Time Extension is
DAVAO DEL NORTE approved, revised planned schedule
DREIRICH BUILDERS (39521) / will be 3.829% and incurred slippage
RELY CONSTRUCTION & 21.229%.
SUPPLY (10433) Revision in the PCMA is on process.
161 21L00089 A. 2,034,034.16 A. 3/24/2021 A. 100.00 Project completed dated 21 June
CONSTRUCTION (COMPLETION) B. 2,034,034.16 B. 6/21/2021 B. 53.13 2021.
OF B.E. DUJALI MUNICIPAL C. 6/21/2021 C. -46.87 Once the final variation order is
POLICE STATION BUILDING, B.E. approved, final quantities will be
DUJALI, DAVAO DEL NORTE reflected in the PCMA.
MICAH CONSTRUCTION &
SUPPLY (26625)
162 21L00101 A. 2,808,952.72 A. 5/13/2021 A. 100.00 P00537735MN- -the contractor was advised to fast 'Project suspended effective June
CONSTRUCTION (COMPLETION) B. 2,808,952.72 B. 8/10/2021 B. 47.10 CW1 (Awaiting track the execution of Phase I of 16,2021 due to pending completion
OF SARANGGANI MUNICIPAL C. 8/10/2021 C. -52.90 for completion of the project to meet the target of phase I (difficulty of transfer of
POLICE STATION, SARANGGANI, construction of scheduled accomplishment. construction materials to the project
DAVAO OCCIDENTAL other Phases) site)
RELY CONSTRUCTION &
SUPPLY (10433)
163 21L00102 A. 40,532,913.87 A. 7/29/2021 A. 4.74 "- Project suspended effective 16
ROAD WIDENING ALONG B. 40,532,913.87 B. 2/28/2022 B. 2.40 August 2021 due to road right-of-way
SURIGAO DEL SUR BDRY. - C. 2/28/2022 C. -2.34 problem..
DAVAO ORIENTAL COASTAL RD. - Once equivalent Time Extension is
(S00140MN), K1564 + 533 - K1566 approved, the revised planned
+ 033, DAVAO ORIENTAL schedule will be 2.389% and the
O. G. SANTOS CONSTRUCTION incurred slippage 0.014%."
(2050)

PCMA 8/31/2021 5:01:21 PM Page 102 Of 105


164 21L00105 A. 96,293,144.96 A. 5/4/2021 A. 38.65 "- Project suspended effective 02
CONSTRUCTION OF CONCRETE B. 96,293,144.96 B. B. 24.84 August 2021 due to road right-of-way
BRIDGE - BAGANGA DIVERSION C. 1/23/2022 C. -13.81 problem..
ROAD, DAVAO ORIENTAL - Once equivalent Time Extension is
MAVERICK BUILDERS approved, the revised planned
INCORPORATED (FORMERLY schedule will be 24.384% and the
MAVERICK (14466) incurred slippage 0.457%."

165 21L00107 A. 98,795,577.99 A. 8/16/2021 A. 0.31 P00502037MN- Ongoing negotiation with the Project suspended effective 23
CONSTRUCTION OF ROAD B. 98,795,577.99 B. 5/5/2022 B. 0.14 CW1 (Permit to affected individuals August 2021 due to road right of way
SLOPE PROTECTION C. 5/5/2022 C. -0.17 enter issues) problem. Once project is resumed
STRUCTURE ALONG DIGOS - and equivalent times extension is
MAKAR ROAD (S00202MN), approved, revised planned schedule
K1591+260 - K1591+360, DAVAO will be 00.31% and incurred negative
DEL SUR slippage of 00.00%. Revision in the
THREE W BUILDERS, INC. PCMA on process, waiting for
(10722) approved time extension in view of
approved suspension and
resumption order.
166 21L00108 A. 99,171,061.95 A. 3/18/2021 A. 57.48 "- Project suspended effective 16
CONSTRUCTION OF CONCRETE B. 99,171,061.95 B. 12/6/2021 B. 45.85 July 2021 due to road right-of-way
ROAD -JCT. ROSARIO HILLS TO C. 12/6/2021 C. -11.63 problem..
SITIO ENRIQUEZ, BRGY. SAN - Once equivalent Time Extension is
IGNACIO CONNECTING MANAY approved, the revised planned
PUBLIC TERMINAL TO schedule will be 45.712% and the
COCONUT, CACAO AND BANANA incurred slippage 0.132%."
CHIPS PROCESSING SITE,
MANAY, DAVAO ORIENTAL
RHODWILL PARTS &
HARDWARE AND
CONSTRUCTION SERVICE
(18871)
167 21L00109 A. 103,180,240.83 A. 5/13/2021 A. 23.47 "- Project suspended effective 02
CONSTRUCTION OF CONCRETE B. 103,180,240.83 B. 1/31/2022 B. 13.12 August 2021 due to road right-of-way
ROAD - NHJ SAKUAN TO BRGY. C. 1/31/2022 C. -10.35 problem..
ALVAR TO SITIO BANTOLINAO, - Once equivalent Time Extension is
BRGY. PALMA GIL TO SITIO approved, the revised planned
TUBILAN, BRGY. PICHON ROAD schedule will be 13.106% and the
CONNECTING CARAGA PUBLIC incurred slippage 0.053%."
TERMINAL TO ABACA
PROCESSING AND HAND LOOM
(DAGMAY) WEAVING IN
SUPPORT TO AGRI BUSINESS:
ABACA, COR
RAKKI CORPORATION (43053)
PCMA 8/31/2021 5:01:21 PM Page 103 Of 105
168 21L00116 A. 120,345,100.69 A. 4/26/2021 A. 26.18 P00502243MN- Issued Work Suspension Order Project Suspended Due to RROW
CONSTRUCTION OF BYPASS B. 120,345,100.69 B. 2/9/2022 B. 1.21 CW1 (Permit to No. 1 due to RROW Problems. Problems (Structures) dated 17 May
ROAD - MATIAO - MAGSAYSAY C. 2/9/2022 C. -24.97 enter issues) Negotiations with Project Affected 2021.
COASTAL ROAD PACKAGE 3, Persons is on-going. Once the project is resumed and
DAVAO ORIENTAL equivalent Time Extension is
MAER SUMMIT KONSTRUKT CO. approved, revised planned schedule
(25262) will be 0.86% and incurred positive
slippage of 0.35%.
169 21L00125 A. 103,499,235.94 A. 4/26/2021 A. 65.86 P00533110MN- Corresponding documents of Project on-going. Variation order No.
PREVENTIVE MAINTENANCE B. 103,499,235.94 B. 11/15/2021 B. 58.50 CW1 (Delays in Variation order was complied to 1 on process. Once approved,
(ASPHALT OVERLAY) ALONG C. 11/15/2021 C. -7.36 approval of suit the actual site condition. Once request for revision in the PCMA will
BAYABAS - EDEN ROAD, DAVAO Variation Orders) approved, request for revision in then be sent to the BOC-PMD for
CITY the PCMA will then be sent to the approval.
VICENTE T. LAO BOC-PMD for approval.
CONSTRUCTION (7040)
170 21L00128 A. 197,881,127.98 A. 7/27/2021 A. 13.29 P00533112MN- Issued reminder letter to the -Project on going
PREVENTIVE MAINTENANCE B. 197,881,127.98 B. 2/4/2022 B. 9.00 CW1 (Insufficient contractor
(ASPHALT OVERLAY) ON C. 2/4/2022 C. -4.29 equipment)
SPECIFIC LOCATIONS ALONG
DAVAO - COTABATO OLD ROAD P00533112MN- Issued reminder letter to the -Project on going
(S01335MN), K1520 + 389 - K1526 CW1 (Insufficient contractor
+ 398, DAVAO CITY manpower)
VICENTE T. LAO
CONSTRUCTION (7040)
171 21L00129 A. 152,951,989.19 A. 8/4/2021 A. 9.13 P00533113MN- Issued reminder letter to the Project on going
PREVENTIVE MAINTENANCE B. 152,951,989.19 B. 1/22/2022 B. 5.00 CW1 (Insufficient contractor
(ASPHALT OVERLAY) ON C. 1/22/2022 C. -4.13 equipment)
SPECIFIC LOCATIONS ALONG
DAVAO - COTABATO OLD ROAD P00533113MN- Issued Reminder letter to the Project on going
(S01335MN), K1522+680 - CW1 (Insufficient contractor
K1525+570, DAVAO CITY manpower)
VICENTE T. LAO
CONSTRUCTION (7040)

172 21L00154 A. 198,970,926.01 A. 5/4/2021 A. 28.66 P00502234MN- Reminder/ Warning letters were -Project on going
CONSTRUCTION OF CONCRETE B. 198,970,926.01 B. 2/27/2022 B. 23.86 CW1 (Slow given to the contractor to eliminate
ROAD - MATANAO - KIBLAWAN - C. 2/27/2022 C. -4.80 Performance) the incurred negative slippage.
PADADA ROAD, DAVAO DEL SUR
P.L. SEBASTIAN P00502234MN- Reminder/ Warning letters were -Project on going
CONSTRUCTION, INC. CW2 (Slow given to the contractor to eliminate
(FORMERLY: P.L. SEBASTIAN Performance) the incurred negative slippage.
CONSTRUCTION) (35840)

PCMA 8/31/2021 5:01:21 PM Page 104 Of 105


172 21L00154 A. 198,970,926.01 A. 5/4/2021 A. 28.66 P00502234MN- Reminder/ Warning letters were 7/16/2021 -Project on going
CONSTRUCTION OF CONCRETE B. 198,970,926.01 B. 2/27/2022 B. 23.86 CW1 (Slow given to the contractor to eliminate
ROAD - MATANAO - KIBLAWAN - C. 2/27/2022 C. -4.80 Performance) the incurred negative slippage.
PADADA ROAD, DAVAO DEL SUR
173 21L00158 A. 152,900,777.88 A. 4/26/2021 A. 65.87 P00502229MN- Instructed the Contractor to Project is on going.
CONSTRUCTION OF GRAVEL B. 152,900,777.88 B. 2/21/2022 B. 51.30 CW1 conduct overtime works in order to
ROAD - BUKIDNON - C. 2/21/2022 C. -14.57 (Unworkable site cover-up wasted time/days due to
COMPOSTELA VALLEY ROAD, condition (i.e. unworkable ground caused by bad
BRGY. NAMNAM, SAN unfavorable weather condition.
FERNANDO, BUKIDNON - LAAK, weather condition
COMPOSTELA VALLEY, at the project site,
PACKAGE 8, DAVAO DEL NORTE access to project
ULTICON BUILDERS, INC. site not
(17267) passable))

PCMA 8/31/2021 5:01:21 PM Page 105 Of 105

You might also like