Professional Documents
Culture Documents
Page 1 of 8
2. BASIC CONTRACT DATA OF THE WORKS CONTRACT
Page 2 of 8
3. EXTENSION OF TIME AND TIME RELATED COST ASSESSMENT
3.1 THE PROPOSED VARIATION ORDERS
We have summarized the cost estimate of the above mentioned works as shown in the table
below.
Amount (Birr)
I/No Description
Contract Final Difference
A Adigoshu – Lugdi Project
Page 3 of 8
Humera town additional 1 km.
a) Earth Works
0 2,201,600.05 2,201,600.05
b) Pavement 0 1,687,972.53 1,687,972.53
4 c) Asphalt Work
0 1,752,500.35 1,752,500.35
d) Minor Drainage Structures
0 2,152,246.95 2,152,246.95
e) Major Drainage Structures
0 8,620,042.00 8,620,042.00
Group Total 0 16,414,361.88 16,414,361.88
Adigoshu - Humera section.
a) Earth Works 56,200,538.73 93,552,873.67 37,352,334.94
b) Pavement 81,192,032.53 81,281,737.81 89,705.28
c) Asphalt Work 70,295,129.65 69,694,580.35 -600,549.30
5
d) Minor Drainage Structures
43,138,909.03 42,024,888.74 -1,114,020.29
e) Major Drainage Structures
13,834,290.61 18,686,184.27 4,851,893.66
Page 4 of 8
We have further summarized the outcome of the above analysis to indicate the revised contract
amount along with the different variations and increase in quantities due to under estimation of
quantities in the original contract.
The bases for the Extension of Time determination are GCC Sub-Clause 6.4 and Sub - Clause
44.1 “Extension of time for Completion”
(a) The amount or nature of extra or additional work,,… or being such as fairly to entitle the
Contractor to an extension of the Time for Completion of the Works, or any Section or part
thereof, the Engineer shall, after due consultation with the Employer and the Contractor,
determine the amount of such extension and shall notify the Contractor accordingly, with a copy
to the Employer.
We have calculated the time required to complete the work for each pay item based on
production rates from the original cost breakdown, revised work programme on October 2009
and revised work programme on September 2010. Even though the time required for some
activities seems very large due to various reasons, we have considered construction of earth
works as critical activity. The other activities like construction of the 10 Bridge Structures and
minor drainage structures can be performed by increasing the number of crews. Accordingly, the
time required to complete the earth works is 595 working days. We have used a factor of 1.18 to
change working days to calendar days. Thus, the total calendar days required for the work with is
700 starting from the issuance date of the variation orders. Since the contract completion date of
the project is January 09, 2011, the effective entitlement of the EOT to the Contractor will be
700 calendar days. For detail assessment of EOT for each activity with the options, please refer
to the attached sheets.
From the above assessment, it is clearly seen that the Contractor may deserve minimum of 700
calendar days of extension of time based on the above basic assumptions.
Page 5 of 8
3.3 TIME RELATED COST ASSESSMENT
We have identified the possible major financial head of claims and analyzed each of them in
detail as indicated hereunder. We have analyzed the financial claims based on the minimum 700
calendar days EOT identified in the above section.
a) Prolongation Cost
We have calculated the recoverable overhead using the well known Corrected Hudson formula.
The prolongation cost is taken as a percentage of the recoverable overheads and as per our
experience in other contracts and standard texts available; this value ranges from 25% to 40% for
a standard 3- years Contract. We have adopted the maximum amount of prolongation cost that
can be incurred by the Contractor as follows:
The Contractor has already mobilized and installed Asphalt Plant and asphalt work has been
commenced in the project. Thus, unless all the earth work and structure works are fully
completed, he may not complete the asphalt work and demobilize the equipments from the
project. This shows that the asphalt crew will be idle for some additional periods of time.
Besides, he may also claim the mobilization and demobilization costs within the project and idle
equipment costs for the other activities. Since these costs may not be major, we have considered
only the idle equipment and labour costs of the asphalt team as shown hereunder. The rates to be
used for valuation should be either rental rates or flat depreciation cost for the owned equipments
after analyzing site records with respect to working, down and idle equipment. For the time
being, we have used the day work rates of equipments for our analysis. We have assumed that 26
Page 6 of 8
days per month and 8 hours per day as working hours for calculation. Thus, the total hours is
(595) (8) = 4,760 hours. Due to the Contractor’s poor efficiency, these hours may be reduced by
70%. Thus, we used 30% of the time that is 1400 hours for determination of idle machinery cost.
The Employer may request rate revision based on Sub-Clause 52.3 (a) of the GCC. Sub-Clause
52.3 ‘Variations Exceeding 15 percent’ (a) of the GCC states that;
“If … it is found that as a result of all varied work valued under sub-clause 52.1 and 52.2 …
there have been additions to or deductions from the Contract Price which taken together are in
excess of 15 percent of the Effective Contract Price, … then there shall be added to or deducted
from the Contract Price such further sum as may be agreed between the Contractor and the
Engineer,.. having regard to the Contractor’s site and general overhead costs of the
Contract…”
From the above clause it is clearly seen that the rate revision request by the Employer can be
based on the fixed component of the Contractor’s overhead cost. We have estimated in the above
section that the fixed element of the Contractor’s overhead would be a maximum of 60% of his
overhead cost. Thus;
Page 7 of 8
As this fixed overhead had been planned to be used for the Original Contract Period, 1280 days,
the over-recovered amount of the fixed component of the Contractor’s overhead with the revised
Contract Period, 1280 + 700 = 1980 days, shall be as shown hereunder, on a pro-rota basis:
1980 - 1
Over Recovered OH = 1280 (38,618,824.40) = ETB 21,119,669.59
From this amount only certain items will qualify for 15% quantity increment and 2% effect in the
contract amount for rate revision request by the Employer. Hence, the total amount of
recoverable OH by the Employer should reduce from this amount. However, we have used this
amount for our assessment.
From the above assessment it is clearly seen that the Contractor may deserve minimum 700
calendar days. Regarding the financial claim, based on our assessment with the minimum 700
calendar days EOT as indicated in the above table, the amount recoverable by the Contractor is
ETB 32,858,022.93 and by the Employer is ETB 21,119,669.59.
Based on the above facts, we have the opinion that the Contractor may deserve EOT of 700
calendar days and net cost of ETB 11,738,353.34.
Page 8 of 8