Professional Documents
Culture Documents
000 TO KM 208.000
(Package-4) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM WITH JICA LOAN ASSISTANCE
Authority : National Highways & Infrastructure Development Corporation Limited (NHIDCL)
Authority's Engineer : TPF GETINSA EUROESTUDIOS S.L. in Joint venture with RODIC Consultants Pvt. Ltd. in association with Anandjiwala Infra Advisory.
Contractor : ABCI Infrastructures Pvt. Ltd.
Percentage Value as per Contract Total Target Qty (01-12-2020 to 31- Target Amount (01-12-2020 to
Item Item Descriptions Unit Payment Terms
Weightage (Rs) Length/nos. 12-2020) 31-12-2020))
1 2 3 4 5 6 7
A- Road works including culverts, widening of repair of
bridges
A-1-Widening and Strengthing of Existing Road 62.60% 275,75,30,043 88,737,058
(i) Hill cutiing upto top of existing road 14.58% Km 40,20,47,880 11,545,800.94 34.822 1.370 15,817,747.288
(ii) Earth work in filling in valley side upto top of existing road 2.64% Km 7,27,98,793 2,090,597.70 34.822 0.685 1,432,059.425
(iii) Earth work upto Sub-grade from top of existing road 0.63% Km 1,73,72,439 498,892.63 34.822 1.180 588,693.303
Road works including (2) Spoil Bank Construction by cutting of surplus soil 12.11% Nos 33,39,36,888 13,914,037.01 24.000 1.750 24,349,564.768
culverts, widening of
repair of bridges (3) Sub-base Course (GSB) 14.71% Km 40,56,32,669 9,657,920.70 42.000 1.180 11,396,346.426
(4) Non Bituminous Base Course (WMM) 12.14% Km 33,47,64,147 7,970,574.93 42.000 1.500 11,955,862.395
(5) Bituminous base course (DBM) 21.52% Km 59,34,20,465 14,129,058.70 42.000 3.990 56,374,944.213
Percentage Value as per Contract Total Target Qty (01-12-2020 to 31- Target Amount (01-12-2020 to
Item Item Descriptions Unit Payment Terms
Weightage (Rs) Length/nos. 12-2020) 31-12-2020))
1 2 3 4 5 6 7
(vi) Construction/ Repair of protection works other than
approaches to the bridges, elevated sections/ flyovers/ grade
separators and ROBs/RUBs.
a) Wet Masonry Retaining Wall (H=3m) 16.330% Km 266,298,376.47 15,096,279.85 17.64 0.060 905,776.791
Other Works b) Wet Masonry Retaining Wall (H=7m) 9.700% Km 158,180,909.48 54,545,141.20 2.90 0.130 7,090,868.356
c) Gravity Wall (H=1.5m) 1.460% Km 23,808,672.97 17,767,666.40 1.34 -
d) Gravity Wall (H=2m) 4.100% Km 66,859,972.05 23,709,209.95 2.82 -
e) Gravity Wall (H=3m) 7.310% Km 119,206,437.97 35,584,011.33 3.35 -
f) Gravity Wall (H=4m) 10.040% Km 163,725,394.96 47,456,636.22 3.45 -
g) Gravity Wall (H=5m) 8.070% Km 131,599,993.76 59,279,276.47 2.22 -
h) Gravity Wall (H=6m) 11.170% Km 182,152,655.55 71,153,381.07 2.56 -
i) Reinforced Earth (H-7m) 6.420% Km 104,692,931.84 174,488,219.73 0.60 -
j) Reinforced Earth Retaining Wall (H=8m) 3.420% Km 55,771,001.07 199,182,146.68 0.28 -
k) Reinforced Earth Retaining Wall (H=9m) 2.200% Km 35,876,082.56 224,225,516.00 0.16 -
l) Reinforced Earth Retaining Wall (H=10m) 2.440% Km 39,789,837.02 248,686,481.38 0.16 -
m) Gabion Wall (1:0.3) 0.200% Km 3,261,462.05 3,166,468.01 1.03 -
n) Rock fall Preventon wall (H=3m) 0.000% Km - - - -
o) Rock fall Prevention Fence (H=2m) 0.000% Km - - - -
p) Hydroseeding (t=5cm) 0.000% Km - - - -
q) Seeding and Mulching (Soil Cut Slope) 3.050% Sqm 49,737,296.28 227.05 219,058.00 -
r) Turfing (Embankment) 0.340% Sqm 5,544,485.49 79.57 69,682.00 -
100.00% 4,405,000,069.00 156,691,212
HIGHWAY WORK PROGRAM 01-12-2020 TO 31-12-2020
Chainage
S.No. Side Unit Length Hill Cutting Subgrade GSB WMM DBM BC Remarks
From To
1 202+400 203+000 LHS Km 0.600 05-12-2020 TO 31-12-2020 - - - - -
2 204+500 205+200 LHS Km 0.700 05-12-2020 TO 31-12-2020 - - - - -
3 175+670 175+740 LHS Km 0.070 01-12-2020 TO 07-12-2020 - - - - -
4 166+000 167+500 RHS Km 1.500 - - - 01-12-2020 TO 10-12-2020 - - -
5 167+820 169+000 RHS Km 1.180 - 01-12-2020 TO 12-12-2020 02-12-2020 TO 13-12-2020 - - -
6 168+010 172+000 BHS Km 3.990 - - - - 15-12-2020 TO 31-12-2020 - -
Total Quatities of Spoil Bank as per NHIDCL (24 No's) 930052 Cum Note: Weightage fixed by NHIDCL
Qty Planned 67,798 Cum For Toe wall construction 50%
For dumping of Earth 10%
% Planned in Numbers 1.75 Nos. For Compaction 25%
For Drainage works 8%
For finishing works including turfing 7%