You are on page 1of 6

Name of Work - WIDENING AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 166.

000 TO KM 208.000
(Package-4) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM WITH JICA LOAN ASSISTANCE
Authority : National Highways & Infrastructure Development Corporation Limited (NHIDCL)
Authority's Engineer : TPF GETINSA EUROESTUDIOS S.L. in Joint venture with RODIC Consultants Pvt. Ltd. in association with Anandjiwala Infra Advisory.
Contractor : ABCI Infrastructures Pvt. Ltd.

Contract Price 440,50,00,069

Percentage Value as per Contract Total Target Qty (01-12-2020 to 31- Target Amount (01-12-2020 to
Item Item Descriptions Unit Payment Terms
Weightage (Rs) Length/nos. 12-2020) 31-12-2020))

1 2 3 4 5 6 7
A- Road works including culverts, widening of repair of
bridges
A-1-Widening and Strengthing of Existing Road 62.60% 275,75,30,043 88,737,058

(i) Hill cutiing upto top of existing road 14.58% Km 40,20,47,880 11,545,800.94 34.822 1.370 15,817,747.288

(ii) Earth work in filling in valley side upto top of existing road 2.64% Km 7,27,98,793 2,090,597.70 34.822 0.685 1,432,059.425

(iii) Earth work upto Sub-grade from top of existing road 0.63% Km 1,73,72,439 498,892.63 34.822 1.180 588,693.303

Road works including (2) Spoil Bank Construction by cutting of surplus soil 12.11% Nos 33,39,36,888 13,914,037.01 24.000 1.750 24,349,564.768
culverts, widening of
repair of bridges (3) Sub-base Course (GSB) 14.71% Km 40,56,32,669 9,657,920.70 42.000 1.180 11,396,346.426

(4) Non Bituminous Base Course (WMM) 12.14% Km 33,47,64,147 7,970,574.93 42.000 1.500 11,955,862.395

(5) Bituminous base course (DBM) 21.52% Km 59,34,20,465 14,129,058.70 42.000 3.990 56,374,944.213

(6) Wearing Coat (BC) 11.08% Km 30,55,34,329 7,274,626.88 42.000 -


(7) Widening and repair of culverts/ Re-Construction and New
10.59% Km 29,20,22,432 1,275,207.12 229.000 21.000 26,779,349.520
culverts on existing road, realignments
A-1 Widening and Repair of Minor bridges (length >6m and
Minor <60m)
Bridges/Underpasses/Ov Minor Bridges
erpasses
A-2 New Minor Bridges (length >6 and <60 m.) 0.38% 1,67,39,000

Major Bridges (length


A.1- Widening and repairs of Major Bridges 0.380% Rmt 1,67,39,000 16,739,000.26 1.000 -
>60 m.) works and
ROB/RUB/Elevated
Secctions/Flyovers
A.2- New Major Bridges - -
including Viaducts, if any

Other Works 37.02% 163,07,31,026

(i) Toll Plaza 0.000% Nos - - -


(ii) Drainage/Road Side Drain 5.260% Km 85,776,451.94 2,042,296.47 42.000 -
(iii) Road Signs, markings Km. Stones, safety devices, and other
appurtenances, safety and traffic management during Construction, 2.550% Km 41,583,641.15 990,086.69 42.000 -
etc...
(iv) Project Facilities -
(a) Bus Bays 1.440% Km 23,482,526.77 7,827,508.92 3 -
(b) Truck lay-bys - Nos - - - -
(c ) View points 0.070% Nos 1,141,511.72 1,141,511.72 1 -
(d) Devolopments of Junctions 3.320% Nos 54,140,270.05 27,070,135.03 2 -
(e ) Office & Vehicle for Authority and office for Authority 's Engineers 1.110% Nos 18,101,114.38 18,101,114.38 1 -
(v) Road side plantation 0.000% Km - - - -
Name of Work - WIDENING AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 166.000 TO KM 208.000
(Package-4) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM WITH JICA LOAN ASSISTANCE
Authority : National Highways & Infrastructure Development Corporation Limited (NHIDCL)
Authority's Engineer : TPF GETINSA EUROESTUDIOS S.L. in Joint venture with RODIC Consultants Pvt. Ltd. in association with Anandjiwala Infra Advisory.
Contractor : ABCI Infrastructures Pvt. Ltd.

Contract Price 440,50,00,069

Percentage Value as per Contract Total Target Qty (01-12-2020 to 31- Target Amount (01-12-2020 to
Item Item Descriptions Unit Payment Terms
Weightage (Rs) Length/nos. 12-2020) 31-12-2020))

1 2 3 4 5 6 7
(vi) Construction/ Repair of protection works other than
approaches to the bridges, elevated sections/ flyovers/ grade
separators and ROBs/RUBs.
a) Wet Masonry Retaining Wall (H=3m) 16.330% Km 266,298,376.47 15,096,279.85 17.64 0.060 905,776.791
Other Works b) Wet Masonry Retaining Wall (H=7m) 9.700% Km 158,180,909.48 54,545,141.20 2.90 0.130 7,090,868.356
c) Gravity Wall (H=1.5m) 1.460% Km 23,808,672.97 17,767,666.40 1.34 -
d) Gravity Wall (H=2m) 4.100% Km 66,859,972.05 23,709,209.95 2.82 -
e) Gravity Wall (H=3m) 7.310% Km 119,206,437.97 35,584,011.33 3.35 -
f) Gravity Wall (H=4m) 10.040% Km 163,725,394.96 47,456,636.22 3.45 -
g) Gravity Wall (H=5m) 8.070% Km 131,599,993.76 59,279,276.47 2.22 -
h) Gravity Wall (H=6m) 11.170% Km 182,152,655.55 71,153,381.07 2.56 -
i) Reinforced Earth (H-7m) 6.420% Km 104,692,931.84 174,488,219.73 0.60 -
j) Reinforced Earth Retaining Wall (H=8m) 3.420% Km 55,771,001.07 199,182,146.68 0.28 -
k) Reinforced Earth Retaining Wall (H=9m) 2.200% Km 35,876,082.56 224,225,516.00 0.16 -
l) Reinforced Earth Retaining Wall (H=10m) 2.440% Km 39,789,837.02 248,686,481.38 0.16 -
m) Gabion Wall (1:0.3) 0.200% Km 3,261,462.05 3,166,468.01 1.03 -
n) Rock fall Preventon wall (H=3m) 0.000% Km - - - -
o) Rock fall Prevention Fence (H=2m) 0.000% Km - - - -
p) Hydroseeding (t=5cm) 0.000% Km - - - -
q) Seeding and Mulching (Soil Cut Slope) 3.050% Sqm 49,737,296.28 227.05 219,058.00 -
r) Turfing (Embankment) 0.340% Sqm 5,544,485.49 79.57 69,682.00 -
100.00% 4,405,000,069.00 156,691,212
HIGHWAY WORK PROGRAM 01-12-2020 TO 31-12-2020
Chainage
S.No. Side Unit Length Hill Cutting Subgrade GSB WMM DBM BC Remarks
From To
1 202+400 203+000 LHS Km 0.600 05-12-2020 TO 31-12-2020 - - - - -
2 204+500 205+200 LHS Km 0.700 05-12-2020 TO 31-12-2020 - - - - -
3 175+670 175+740 LHS Km 0.070 01-12-2020 TO 07-12-2020 - - - - -
4 166+000 167+500 RHS Km 1.500 - - - 01-12-2020 TO 10-12-2020 - - -
5 167+820 169+000 RHS Km 1.180 - 01-12-2020 TO 12-12-2020 02-12-2020 TO 13-12-2020 - - -
6 168+010 172+000 BHS Km 3.990 - - - - 15-12-2020 TO 31-12-2020 - -

Total Planned Qty


Item Qty
Hill Cutting 1.370
Subgrade 1.180
GSB 1.180
WMM 1.500
DBM 3.990
BC -
Valley side filling 0.685
PIPE CULVERT WORK PROGRAM 01-12-2020 TO 31-12-2020
LHS HEAD WALL LHS Main Carriage Way RHS Main Carriage Way RHS HEAD WALL
SL. NO. CHAINAGE SIDE LENGTH (Mtr) REMARKS
CRADLE CRADLE
Excavation PCC 1ST LIFT 2ND LIFT 3RD LIFT 4TH LIFT FINAL LIFT EXCAVATION PCC PIPE LAYING EXCAVATION PCC PIPE LAYING Excavation PCC 1ST LIFT 2ND LIFT 3RD LIFT 4TH LIFT FINAL LIFT
CONCRETE CONCRETE
1 167+920 BHS 11.90 01-12-20 01-12-20 02-12-20 03-12-20 04-12-20 05-12-20 06-12-20 01-12-20 01-12-20 02-12-20 03-12-20 03-12-20 03-12-20 04-12-20 05-12-20 02-12-20 02-12-20 03-12-20 04-12-20 05-12-20 06-12-20 07-12-20
2 175+106 BHS 14.45 01-12-20 01-12-20 02-12-20 03-12-20 04-12-20 05-12-20 06-12-20 01-12-20 01-12-20 02-12-20 03-12-20 03-12-20 03-12-20 04-12-20 05-12-20 02-12-20 02-12-20 03-12-20 04-12-20 05-12-20 06-12-20 07-12-20
3 175+185 BHS 15.37 01-12-20 01-12-20 02-12-20 03-12-20 04-12-20 05-12-20 06-12-20 01-12-20 01-12-20 02-12-20 03-12-20 03-12-20 03-12-20 04-12-20 05-12-20 02-12-20 02-12-20 03-12-20 04-12-20 05-12-20 06-12-20 07-12-20
4 175+320 BHS 12.01 05-12-20 05-12-20 06-12-20 07-12-20 08-12-20 09-12-20 10-12-20 05-12-20 05-12-20 06-12-20 07-12-20 07-12-20 07-12-20 08-12-20 09-12-20 06-12-20 06-12-20 07-12-20 08-12-20 09-12-20 10-12-20 11-12-20
5 175+402 BHS 15.64 05-12-20 05-12-20 06-12-20 07-12-20 08-12-20 09-12-20 10-12-20 05-12-20 05-12-20 06-12-20 07-12-20 07-12-20 07-12-20 08-12-20 09-12-20 06-12-20 06-12-20 07-12-20 08-12-20 09-12-20 10-12-20 11-12-20
6 175+556 BHS 19.03 05-12-20 05-12-20 06-12-20 07-12-20 08-12-20 09-12-20 10-12-20 05-12-20 05-12-20 06-12-20 07-12-20 07-12-20 07-12-20 08-12-20 09-12-20 06-12-20 06-12-20 07-12-20 08-12-20 09-12-20 10-12-20 11-12-20
7 175+711 BHS 13.34 08-12-20 08-12-20 09-12-20 10-12-20 11-12-20 12-12-20 13-12-20 09-12-20 09-12-20 10-12-20 11-12-20 11-12-20 11-12-20 12-12-20 13-12-20 12-12-20 12-12-20 13-12-20 14-12-20 15-12-202 16-12-20 17-12-20
8 175+825 BHS 16.44 12-12-20 12-12-20 13-12-20 14-12-20 15-12-20 16-12-20 17-12-20 12-12-20 12-12-20 13-12-20 14-12-20 14-12-20 14-12-20 15-12-20 16-12-20 15-12-20 15-12-20 16-12-20 17-12-20 18-12-20 19-12-20 20-12-20
9 175+865 BHS 13.37 12-12-20 12-12-20 13-12-20 14-12-20 15-12-20 16-12-20 17-12-20 12-12-20 12-12-20 13-12-20 14-12-20 14-12-20 14-12-20 15-12-20 16-12-20 15-12-20 15-12-20 16-12-20 17-12-20 18-12-20 19-12-20 20-12-20
10 175+920 BHS 11.87 15-12-20 15-12-20 16-12-20 17-12-20 18-12-20 19-12-20 20-12-20 16-12-20 16-12-20 17-12-20 18-12-20 19-12-20 19-12-20 20-12-20 21-12-20 18-12-20 18-12-20 19-12-20 20-12-20 21-12-20 22-12-20 23-12-20
11 176+090 BHS 14.17 15-12-20 15-12-20 16-12-20 17-12-20 18-12-20 19-12-20 20-12-20 16-12-20 16-12-20 17-12-20 18-12-20 19-12-20 19-12-20 20-12-20 21-12-20 18-12-20 18-12-20 19-12-20 20-12-20 21-12-20 22-12-20 23-12-20
12 176+379 BHS 18.73 15-12-20 15-12-20 16-12-20 17-12-20 18-12-20 19-12-20 20-12-20 16-12-20 16-12-20 17-12-20 18-12-20 19-12-20 19-12-20 20-12-20 21-12-20 18-12-20 18-12-20 19-12-20 20-12-20 21-12-20 22-12-20 23-12-20
13 176+572 BHS 19.58 18-12-20 18-12-20 19-12-20 20-12-20 21-12-20 22-12-20 23-12-20 22-12-20 22-12-20 23-12-20 24-12-20 25-12-20 25-12-20 26-12-20 27-12-20 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20
14 176+780 BHS 13.81 18-12-20 18-12-20 19-12-20 20-12-20 21-12-20 22-12-20 23-12-20 22-12-20 22-12-20 23-12-20 24-12-20 25-12-20 25-12-20 26-12-20 27-12-20 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20
15 176+900 BHS 12.42 18-12-20 18-12-20 19-12-20 20-12-20 21-12-20 22-12-20 23-12-20 22-12-20 22-12-20 23-12-20 24-12-20 25-12-20 25-12-20 26-12-20 27-12-20 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20
16 177+015 BHS 12.77 21-12-20 21-12-20 22-12-20 23-12-20 24-12-20 25-12-20 26-12-20 25-12-20 25-12-20 26-12-20 27-12-20 28-12-20 28-12-20 29-12-20 30-12-20 27-12-20 27-12-20 28-12-20 29-12-20 30-12-20 31-12-20 01-01-21
17 177+238 BHS 12.26 21-12-20 21-12-20 22-12-20 23-12-20 24-12-20 25-12-20 26-12-20 25-12-20 25-12-20 26-12-20 27-12-20 28-12-20 28-12-20 29-12-20 30-12-20 27-12-20 27-12-20 28-12-20 29-12-20 30-12-20 31-12-20 01-01-21
18 184+070 BHS 12.77 21-12-20 21-12-20 22-12-20 23-12-20 24-12-20 25-12-20 26-12-20 25-12-20 25-12-20 26-12-20 27-12-20 28-12-20 28-12-20 29-12-20 30-12-20 27-12-20 27-12-20 28-12-20 29-12-20 30-12-20 31-12-20 01-01-21
19 184+335 BHS 12.70 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 27-12-20 28-12-20 29-12-20 25-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20 30-12-20
20 184+710 BHS 13.37 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 27-12-20 28-12-20 29-12-20 25-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20 30-12-20
21 184+888 BHS 11.87 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20 24-12-20 24-12-20 25-12-20 26-12-20 27-12-20 27-12-20 28-12-20 29-12-20 25-12-20 25-12-20 26-12-20 27-12-20 28-12-20 29-12-20 30-12-20
RETAINING WALL WORK PROGRAM 01-12-2020 TO 31-12-2020
SL. CHAINAGE Height LENGTH
SIDE EXCAVATION PCC 1ST LIFT 2ND LIFT 3RD LIFT 4TH LIFT FINAL LIFT REMARKS
NO. FROM TO (m) MTR
1 175+000 175+010 7.0 10 RHS
2 175+010 175+020 7.0 10 RHS
3 175+020 175+030 6.0 10 RHS
4 175+030 175+040 5.5 10 RHS
5 175+040 175+050 2.5 10 RHS
6 175+080 175+090 4.0 10 RHS
7 175+120 175+130 4.0 10 RHS
8 175+180 175+190 6.5 10 RHS
9 175+190 175+200 4.5 10 RHS
10 175+260 175+270 2.0 10 RHS
11 175+270 175+280 4.5 10 RHS
12 175+280 175+290 4.0 10 RHS
13 175+290 175+300 1.5 10 RHS
14 189+000 189+010 2.0 10 LHS
15 189+020 189+035 4.5 15 LHS
16 189+035 189+040 3.5 5 LHS
17 189+070 189+080 4.0 10 LHS
18 189+080 189+090 3.5 10 LHS
19 189+090 189+100 3.0 10 LHS
20 189+110 189+120 3.0 10 LHS
21 189+120 189+130 4.0 10 LHS
22 189+130 189+140 4.5 10 LHS
23 189+140 189+150 4.0 10 LHS
24 189+160 189+170 2.5 10 LHS
25 189+170 189+180 2.0 10 LHS
26 189+190 189+200 5.5 10 LHS

Completed Progress Total


Length Less than 3m 60 0 60 0.06 Km
Length more than 3m 130 0 130 0.13 Km
GABION WALL WORK PROGRAM 01-12-2020 TO 31-12-2020
CHAINAGE Qty as per Wall Executed Planned
Planned
S. No. SIDE design Length Wall Wall C&G EXCAVATION PCC 1ST LIFT 2ND LIFT 3RD LIFT 4TH LIFT FINAL LIFT REMARKS
FROM TO Qty
(Cum) (Mtr) Length Length

1 175+610 175+686 RHS 20500 190 60 130 2337.72 06-12-2020 TO 14-12-2020


2 186+085 186+247 LHS 256100 220 100 220 34922.73 03-12-2020 TO 15-12-2020 16-12-2020 TO 30-12-2020
3 184+847 185+020 LHS 174500 150 140 140 30537.5 05-12-2020 TO 13-12-2020 14-12-2020 TO 30-12-2020

Total Quatities of Spoil Bank as per NHIDCL (24 No's) 930052 Cum Note: Weightage fixed by NHIDCL
Qty Planned 67,798 Cum For Toe wall construction 50%
For dumping of Earth 10%
% Planned in Numbers 1.75 Nos. For Compaction 25%
For Drainage works 8%
For finishing works including turfing 7%