ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL Wt. QUANTITY ACCO
PREV.
PART A- FACILITIES FOR THE ENGINEERS
FE A.1.3 Construction Safety and Health Program 1.00 L.S. 129,080.00 129,080.00 0.679%
PART B- OTHER GENERAL REQUIREMENTS
1 Maintain and Protect of Traffic 158.00 Days 613.16 96,879.28 0.509%
PART C- EARTHWORK
101(2) Removal of Concrete Bridge Structure (Sidewalk & Railings) 20.46 Cu.m. 5,647.62 115,550.31 0.608%
103(2)A Bridge Excavation (Common Soil) 563.86 Cu.m. 150.32 84,759.44 0.446%
103(5)B Shoring and other related works (assumed footing arean= 15 sq.m.) 15.00 Sq.m. 16,047.73 240,715.95 1.266%
104(2) Embankment (from selected Borrow) 194.28 Cu.m. 568.70 110,487.04 0.581%
PART F- BRIDGE CONSTRUCTION
400(4)a Precast Concrete piles, Furnished (400mm x 400mm-type B) 1,248.00 Mtr. 4,449.21 5,552,614.08 29.199%
400(14)b Precast Concrete piles, driven 1,150.00 Mtr. 2,201.18 2,531,357.00 13.312%
400(16)a Test Piles, Furnished and driven (400mm x 400mm) 52.00 Mtr. 3,900.21 202,810.92 1.067%
401a Reinforced Concrete Railing (Double) 20.00 m. 4,753.18 95,063.60 0.500%
403(1) Structural Steel (Furnished, Fabricated and Erected) 1,262.00 Kg. 101.45 128,029.90 0.673%
404a Reinforcing steel Bar, Grade 40 (Bridge Structures and other Major Structures 3,536.96 Kg. 66.95 236,799.47 1.245%
404b Reinforcing steel Bar, Grade 60 (Bridge Structures and other Major Structures 33,618.18 Kg. 78.75 2,647,431.68 13.922%
405(1) Structural Concrete Class A (Major Structure)-Bridge Substructure, 27 Mpa 207.06 Cu.m. 7,321.70 1,516,031.20 7.972%
405(2) Structural Concrete Class A (Major Structure)-Bridge Substructure, 20.70 Mpa 80.94 Cu.m. 7,777.87 629,540.80 3.311%
405(3) Structural Concrete Class A (Lean Concrete-minor structure) 8.80 Cu.m. 6,669.00 58,687.20 0.309%
406(1) Pre-Stressed Concrete Girder, Type III (20 meters) 4.00 Each 736,452.50 2,945,810.00 15.491%
412 Elastomeric Bearing Pad 8.00 Each 21,190.50 169,524.00 0.891%
PART G-DRAINAGE AND SLOPE PROTECTION
507 Rubble Concrete 156.68 Cu.m. 3,438.13 538,686.21 2.833%
OTHER ITEMS
SPL I Installation of expansion joint 40.00 Ln.m. 21,781.90 871,276.00 4.582%
SPL II Mobilization & Demobilization 1.00 L.S. 115,080.00 115,080.00 0.605%
TOTAL 19,016,230.08 100.00%
Prepared by:
Checked & Verified by:
ACCOMPLISHMENT %
QUANTITY ACCOMPLISHMENT % ACCOMPLISHMENT VALUE OF ACCOMPLISHMENT WEIGHTED REMARKS
ACCOMP.
THIS PERIOD TO DATE PREV. THIS PERIOD TO DATE PREV. THIS PERIOD TO DATE
Approved by:
TESSIE J. YU
fficer Proprietor