You are on page 1of 2

Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


Zamboanga del Sur 1st Engineering District
Pagadian City

Accomplishment no._________
Contrat ID :14JO0046
Name of Project :Concrete Reconstruction including drainage along Pagadian City-Zamboanga City Road, Zamboanga del Sur
Station :K1649+000.00-K650+000.00, K1661+847.80-K1662+514.56, K1663+564.00-K1665+250.95
Location :Tiguma, Pagadian City, Zamboanga del Sur
Contractor: :ESR Construction and Development Corporation
Contract amount: : 51,083,167.64
Status:
STATEMENT OF WORK ACCOMPLISHMENT (SWA)
AS OF :

%
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL RELATIVE QUANTITY ACCOMPLISHMENT
Wt. PREV. THIS PERIOD TO DATE
101(2) Removal of Existing RCPC Headwalls(stone Masonry) 8.00 each 1,221.82 9,774.56 0.019%
101(3) Removal of Structures & Obstruction(Removal of Existing ACP) 21,469.50 sq. m. 96.02 2,061,567.30 4.036%
101(4a) Removal of Existing RCPC, 910 mm dia. 11.00 ln.m. 1,110.74 12,218.14 0.024%
101(4b) Removal of Existing RCPC, 610 mm dia. 45.00 ln.m. 814.55 36,654.75 0.072%
102(2) Surplus Common Excavation 6,860.00 cu.m. 141.22 968,769.20 1.896%
103(3) Foundation Fill 9.00 cu. m. 685.52 6,169.68 0.012%
103(6) Pipe Culvert and Drain Excavation 141.00 cu. m. 194.90 27,480.90 0.054%
104(1a) Embankment from Excavation 677.00 cu. m. 271.22 183,615.94 0.359%
105 Subgrade Preparation 31,611.50 sq. m. 22.40 708,097.60 1.386%
200 Aggregate Subbase Course 9,831.50 cu. m. 781.00 7,678,401.50 15.031%
300 Aggregate Surface Course 791.50 cu. m. 757.54 599,592.91 1.174%
311a PCCP-using Conventional Method, 0.15 Thick 23,196.50 sq. m. 1,493.49 34,643,815.00 67.818%
311b PCCP, 0.15 Thick 222.00 sq. m. 966 214,454.22 0.420%
500(1a) RC Culvert Pipe, 910 mm (36''dia.) 72.00 ln.m. 5,459.51 393,084.72 0.769%
505(5) Grouted Riprap, Class A 18.00 cu.m. 3,246.46 58,436.28 0.114%
506 Stone Masonry 39.50 cu.m. 3,550.46 140,243.17 0.275%
612(1) Reflectorized Thermoplastic Pavement markings (white) 838.00 sq. m. 1,298.74 1,088,344.12 2.131%
612(2) Reflectorized Thermoplastic Pavement markings (yellow) 49.50 sq. m. 1,528.52 75,661.74 0.148%
FEA 1.1a Bunkhouse, (7.00 x 9.00) 1.00 LS 347,553.28 347,553.28 0.680%
FEA 1.1b Facilities for the Engineers 1.00 LS 174,090.00 174,090.00 0.341%
FEA 1.2 Project Billboard 2.00 Unit 3,713.92 7,427.84 0.015%
FEA 1.3 Construction Safety and Health Program 1.00 LS 166,430.04 166,430.04 0.326%
FEA 1.4 Provision of a service vehicle for engineers 1.00 LS 469,694.82 469,694.82 0.919%
SPL-1 Mobilization and Demobilization 1.00 LS 496,504.68 496,504.68 0.972%
SPL-2 Construction Survey and Staking 3.35 Km. 33,274.58 111,469.83 0.218%
500 RC Culvert Pipe, 610 mm 18.00 ln.m. 2,299.54 41,391.72 0.081%
502(1) Manhole 6.00 each 2,379.23 14,275.38 0.028%
502(4) Concrete Cover 6.00 each 1,005.85 6,035.10 0.012%
503 Metal Frame & Grating 6.00 set 1,296.00 7,776.00 0.015%
600(3) Concrete Curb and Gutter 122.00 ln.m. 808.61 98,651.02 0.193%
601 Sidewalk 244.00 sq. m. 904.22 220,630.52 0.432%
605(3) Informatory Signs 2.00 units 7,427.84 14,855.68 0.029%
TOTAL 51,083,167.64 100.00%

Prepared by: Checked & Verified by:


ENGR. JESUS A. MANIAGO JR.
Project Engineer Authorized Managing Officer
Date Started:
Target Completion Date:
% Proj. Accomp. To Date:
Slippage;

WA)

ACCOMPLISHMENT
% WEIGHTED REMARKS
SHMENT % ACCOMPLISHMENT VALUE OF ACCOMPLISHMENT ACCOMP.
TO DATE PREV. THIS PERIOD TO DATE PREV. THIS PERIOD TO DATE

Approved by:
TESSIE J. YU
Proprietor