You are on page 1of 1

PERCENTAGE

TOTAL
TOTAL
PAY ITEM/SUBSCRIPT CONTRACT QUANTITY UNIT OF MEASURE UNIT COST AMOUNT REPORTED RELATIVE
AMOUNT ACCOMP (%)
QUANTITY WEIGHT (%)

B.5 Project Billboard / Signboard 3.00 Each 4,600.12 13,800.36 3.00 13,800.36 100.00% 0.09%
B.7 (2) Occupational Safety and Health Program 1.00 Lump Sum 102,490.00 102,490.00 0.40 40,996.00 40.00% 0.28%
B.8 (1) Traffic Management 4.00 Month 8,024.62 32,098.48 2.00 16,049.24 50.00% 0.11%
B.9 Mobilization / Demobilization 1.00 Lump Sum 375,000.00 375,000.00 0.50 187,500.00 50.00% 1.28%
100 (1) Clearing and Grubbing 0.26 Hectare 250,520.84 65,135.42 0.23 57,619.79 88.46% 0.39%
101 (4) a1 Removal of Actual Structures/Obstruction 610 mm dia.,
32.00 Linear Meter 736.73 23,575.36 28.00 20,628.44 87.50% 0.14%
RCPC
101 (4) a3 Removal of Actual Structures/Obstruction 910 mm dia.,
5.00 Linear Meter 1,473.44 7,367.20 3.00 4,420.32 60.00% 0.03%
RCPC
102 (2) Surplus Common Excavation 5,357.07 Cubic Meter 329.58 1,765,583.13 2,740.00 903,049.20 51.15% 6.14%
103 (1) a Structure Excavation Common Soil 70.91 Cubic Meter 362.63 25,714.09 50.00 18,131.50 70.51% 0.12%
104 (1) a Embankment from roadway/structure excavation Common
409.07 Cubic Meter 397.91 162,773.04 253.47 100,858.24 61.96% 0.69%
Soil
105 (1) b Subgrade Preparation Existing Pavement 5,121.60 Square Meter 28.95 148,270.32 3,841.20 111,202.74 75.00% 0.76%
200 (1) Aggregate Subbase Course 1,594.58 Cubic Meter 1,385.41 2,209,147.08 1,036.48 1,435,949.75 65.00% 9.77%
311 (1) e1 Portland Cement Concrete Pavement (Unreinforced) 0.28 m
3,537.60 Square Meter 1,941.16 6,867,047.62 - 0.00% 0.00%
thick, 14 days
404 (1) a Reinforcing Steel Grade 40 3,586.21 Kilogram 76.60 274,703.69 - 0.00% 0.00%
405 (1) a3 Structural Concrete 28 days, 20.68MPa, A 31.94 Cubic Meter 8,952.80 285,952.43 - 0.00% 0.00%
500 (1) a1 Pipe Culverts RCPC, 610 mm dia., Class II 44.00 Linear Meter 3,642.35 160,263.40 44.00 160,263.40 100.00% 1.09%
500 (1) a3 Pipe Culverts RCPC, 910 mm dia., Class II 11.00 Linear Meter 6,332.31 69,655.41 11.00 69,655.41 100.00% 0.47%
505 (2) a Grouted Riprap A 51.17 Cubic Meter 3,745.83 191,674.12 - 0.00% 0.00%
506 (1) Stone Masonry 291.73 Cubic Meter 4,744.35 1,384,069.23 116.03 550,486.93 39.77% 3.74%
603 (3) a1 Metal Guardrail (Metal Beam) Including Post Single, W-
155.00 Linear Meter 3,263.41 505,828.55 - 0.00% 0.00%
Beam
603 (4) b Metal Beam End Piece Bull Nose 14.00 Each 2,087.50 29,225.00 - 0.00% 0.00%
TOTAL 14,699,373.92 3,690,611.32 25.11%

You might also like