0% found this document useful (0 votes)
335 views1 page

Accomplishment Report

This document appears to be a payment summary for various project items showing quantities, unit costs, amounts, percentages reported and completed, and relative weights. It includes line items for signage, safety programs, traffic management, mobilization, excavation works, subbase works, drainage works like culverts, concrete works, guardrails and more. The total contract value was over 14.6 million but only around 3.7 million or 25.11% of the works had been reported as completed so far.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
335 views1 page

Accomplishment Report

This document appears to be a payment summary for various project items showing quantities, unit costs, amounts, percentages reported and completed, and relative weights. It includes line items for signage, safety programs, traffic management, mobilization, excavation works, subbase works, drainage works like culverts, concrete works, guardrails and more. The total contract value was over 14.6 million but only around 3.7 million or 25.11% of the works had been reported as completed so far.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

PERCENTAGE

TOTAL
TOTAL
PAY ITEM/SUBSCRIPT CONTRACT QUANTITY UNIT OF MEASURE UNIT COST AMOUNT REPORTED RELATIVE
AMOUNT ACCOMP (%)
QUANTITY WEIGHT (%)

B.5 Project Billboard / Signboard 3.00 Each 4,600.12 13,800.36 3.00 13,800.36 100.00% 0.09%
B.7 (2) Occupational Safety and Health Program 1.00 Lump Sum 102,490.00 102,490.00 0.40 40,996.00 40.00% 0.28%
B.8 (1) Traffic Management 4.00 Month 8,024.62 32,098.48 2.00 16,049.24 50.00% 0.11%
B.9 Mobilization / Demobilization 1.00 Lump Sum 375,000.00 375,000.00 0.50 187,500.00 50.00% 1.28%
100 (1) Clearing and Grubbing 0.26 Hectare 250,520.84 65,135.42 0.23 57,619.79 88.46% 0.39%
101 (4) a1 Removal of Actual Structures/Obstruction 610 mm dia.,
32.00 Linear Meter 736.73 23,575.36 28.00 20,628.44 87.50% 0.14%
RCPC
101 (4) a3 Removal of Actual Structures/Obstruction 910 mm dia.,
5.00 Linear Meter 1,473.44 7,367.20 3.00 4,420.32 60.00% 0.03%
RCPC
102 (2) Surplus Common Excavation 5,357.07 Cubic Meter 329.58 1,765,583.13 2,740.00 903,049.20 51.15% 6.14%
103 (1) a Structure Excavation Common Soil 70.91 Cubic Meter 362.63 25,714.09 50.00 18,131.50 70.51% 0.12%
104 (1) a Embankment from roadway/structure excavation Common
409.07 Cubic Meter 397.91 162,773.04 253.47 100,858.24 61.96% 0.69%
Soil
105 (1) b Subgrade Preparation Existing Pavement 5,121.60 Square Meter 28.95 148,270.32 3,841.20 111,202.74 75.00% 0.76%
200 (1) Aggregate Subbase Course 1,594.58 Cubic Meter 1,385.41 2,209,147.08 1,036.48 1,435,949.75 65.00% 9.77%
311 (1) e1 Portland Cement Concrete Pavement (Unreinforced) 0.28 m
3,537.60 Square Meter 1,941.16 6,867,047.62 - 0.00% 0.00%
thick, 14 days
404 (1) a Reinforcing Steel Grade 40 3,586.21 Kilogram 76.60 274,703.69 - 0.00% 0.00%
405 (1) a3 Structural Concrete 28 days, 20.68MPa, A 31.94 Cubic Meter 8,952.80 285,952.43 - 0.00% 0.00%
500 (1) a1 Pipe Culverts RCPC, 610 mm dia., Class II 44.00 Linear Meter 3,642.35 160,263.40 44.00 160,263.40 100.00% 1.09%
500 (1) a3 Pipe Culverts RCPC, 910 mm dia., Class II 11.00 Linear Meter 6,332.31 69,655.41 11.00 69,655.41 100.00% 0.47%
505 (2) a Grouted Riprap A 51.17 Cubic Meter 3,745.83 191,674.12 - 0.00% 0.00%
506 (1) Stone Masonry 291.73 Cubic Meter 4,744.35 1,384,069.23 116.03 550,486.93 39.77% 3.74%
603 (3) a1 Metal Guardrail (Metal Beam) Including Post Single, W-
155.00 Linear Meter 3,263.41 505,828.55 - 0.00% 0.00%
Beam
603 (4) b Metal Beam End Piece Bull Nose 14.00 Each 2,087.50 29,225.00 - 0.00% 0.00%
TOTAL 14,699,373.92 3,690,611.32 25.11%

You might also like