You are on page 1of 5

A B C D E F G H I J K L

1 KANHAR NAHAR PARIYOJANA KHAND-6 MIRZAPUR


2 ESTIMATE FOR CONSTRUCTION OF V.R.B. AT KM. 1.600 OF K.K.C.

3 BILL OF QUANTITY
S.N
4
o
Items No.s Length Width Height Quantity Unit
Site Clearence for construction stream including all leads
and lifts ,labour charge , T & P etc.required for proper
5 1 completion of work and its disposal as per direction of
Engineer-in-charge.

6 L.S 2 X 1 30.000 8.500 510.000 sqm


7
Earth work in excavation of foundation in all types of soil
including all leads and lifts, labour charge , T & P
8 2 etc.required for proper completion of work and its disposal
as per direction of Engineer-in-charge.

9 2 X 1 8.500 7.172 8.700 1060.739


10 Grand Total 1060.739
11 Net Total 1060.739 cum
12
Laying C.C. 1:2:4 (M-15) in raft with cement,coarse sand of
F.M. not less than 2.00 and hard stone ballast as obtained
from the excavation of foundation including coast of all
13 3 material,labour,T & P etc. required for proper completion
of work.

14 Foundation 2 X 1 8.500 7.192 0.300 36.679


15 Total 36.679 cum
Laying R.C.C. 1:1:2(M-25) with cement,coarse sand of F.M.
not less than 2.00 and crushed hard stone grit including
cost of all material,labour,T & P etc.required for proper
completion of work but excluding cost of
16 4 reinforcement,centering and shuttering in construction of
different parts of structure.

17 Raft 2 X 1 7.900 6.592 0.900 93.738


18 Pier (Above raft) 2 X 1 6.700 (4.392+2.592)/20.900 42.114
19 2 X 1 6.700 (0+1.692)/2 5.455 30.920
20 2 X 1 6.700 0.900 5.455 65.787
21 2 X 1 6.700 0.440 1.145 6.751
22 2 X 1 6.700 0.535 0.250 1.792
23 241.102
24 Total 241.102 cum
Centering & shuttering for C.C./R.C.C. work in different
parts of structure as below including cost of all material,
25 5 labour,T & P etc. required for proper completion of work.

26 M-15 P.C.C. In foundation 2 X 2 7.192 0.300 8.630


27 2 X 2 8.500 0.300 10.200
28 M-20 R.C.C.
29 Raft 2 X 2 6.592 0.900 23.731
30 2 X 2 7.900 0.900 28.440
31 Inclind face 2 X 2 6.700 1.272 34.090
32 Inner vertical face 2 X 1 6.700 5.455 73.097
33 Outer Inclind face 2 X 1 6.700 5.711 76.527
34 2 X 2 6.700 1.145 30.686
35 2 X 1 6.700 0.106 1.420
36 2 X 1 6.700 0.175 2.345
37 Stoper side face 2 X 2 (0.900*0.900)/2 1.620
38 2 X 2 (0.900*0.900)/2 1.620
39 2 X 2 2.592 0.900 9.331
40 2 X 2 0.900 5.455 19.638
41 2 X 2 (1.692*5.455)/2 18.460
42 2 X 2 (0.075*0.075)/2 0.011
43 2 X 2 0.460 0.075 0.138
44 2 X 2 0.535 0.175 0.375
45 2 X 2 0.440 1.145 2.015
46 2 X 2 6.700 1.350 36.180
47
48 Parapet outter face 2 X 1 19.784 1.000 39.568
49 parapet stoper plate 2 X 2 Area= 0.3548 m2 1.419
50 curve side face 2 X 1 19.784 0.210 8.309
51 parapet inclined face 2 X 1 19.784 0.670 26.511
A B C D E F G H I J K L
52 curve face 2 X 1 19.784 0.295 11.673
53 Slab 2 X 1 6.700 0.820 10.988
54 2 X 1 9.450 0.820 15.498
55 492.520
56 Total 492.520 sqm
Laying R.C.C. (M-25) with cement,coarse sand of F.M. not
less than 2.00 and crushed hard stone grit including cost of
all material,labour T&P etc. required for proper completion
of work but excluding cost of reinforcement ,centering and
57 6 shuttering in construction of different parts of structure.

58 Slab 1 X 1 10.480 6.70 0.820 57.577


59 Return wall 4 X 1 4.192 (0.9+0.3)/2 8.700 87.529
60 Parapet wall 2 X 1 19.784 Area= 0.3548 m2 14.039
61 159.145
62 Total 159.145 cum
Carriage , Cutting , Bending and placing steel for
reinforcement with cost of binding wire including cost of all
63 7 materials, labour,T&P etc. required for proper completion
of work.

64 reinforcement in raft
65 Bottom main bar 20 mm dia 110 mm C/C 1 X 59 5.92 349.280
66 Bottom distribution bar16 mm dia 150 mm C/C 1 X 32 7.67 245.440
67 Top distribution bar16 mm dia 110 mm C/C 1 X 43 7.67 329.810
68 Top main bar16 mm dia 110 mm C/C 1 X 59 5.92 349.280
69
70 abutment reinforcement
71 abutment main vertical bar 20mm dia 150mm C/C 1 X 43 4.76 204.680
72 abutment main vertical bar 20mm dia 150mm C/C 1 X 43 4.76 204.680

73 abutment main vertical distribution bar 16mm dia 150mm


C/C 1 X 28 6.37 178.360
74 abutment slant main vertical bar 20mm dia 150mm C/C 1 X 45 7.23 325.350
75 abutment slant main vertical bar 20mm dia 150mm C/C 1 X 45 7.23 325.350

76
abutment slant main distribution bar 20mm dia 150mm C/C 1 X 36 6.37 229.320
77 abutment chair bar 16mm dia 150mm C/C 1 X 15 3.30 49.500
78 abutment skin bar 16mm dia 300mm C/C 1 X 2 X 3 7.37 44.220
79 abutment skin bar 16mm dia 300mm C/C 1 X 2 X 3 5.65 33.900
80 Return wall reinforcment
81 Haunch bar 16mm dia 150mm C/C 1 X 43 1.95 83.850
82 Vertical bar earth face 20mm dia 150mm C/C 1 X 2 X 23 4.56 209.760
83 Vertical bar earth face 20mm dia 150mm C/C 1 X 2 X 23 4.56 209.760
84 Vertical bar sand face 12mm dia 150mm C/C 1 X 2 X 23 4.56 209.760
85 Vertical bar sand face 12mm dia 150mm C/C 1.00 X 2.00 X 23.00 4.56 209.760
86 bender bar earth face 10mm dia 150mm C/C 1.00 X 2.00 X 28.00 3.30 184.800
87 bender bar sand face 10mm dia 150mm C/C 1.00 X 2.00 X 28.00 3.30 184.800
88 bed block steel 12mm dia 200mm C/C 1.00 X 33.00 1.08 35.475
89 bed block steel 16mm dia 200mm C/C 1.00 X 6.00 6.37 38.220
90 Slab reinforcement
91 bottom bar 20mm dia 150mm C/C 1.00 X 37.00 4.95 183.150
92 bottom distribution bar 12 mm dia 70mm C/C 1.00 X 68.00 6.75 459.000
93 top distribution bar 10mm dia 300mm C/C 1.00 X 16.00 6.00 96.000
94 top main bar 10 mm dia 300mm C/C 1.00 X 19.00 5.31 100.890
95 chair bar 20 mm dia 300mm C/C 1.00 X 20.00 3.20 63.920

96 Parapet wall Slab & return wall portion


reinforcement
97 main bar 10mm dia 300mm C/C 1.00 X 2.00 X 50.00 2.76 276.000
98 distribution bar 10mm dia 100mm C/C 1.00 X 20.00 19.12 382.400
99 Lap bar 10mm dia 100mm C/C 1.00 X 20.00 0.50 10.000
100 Total length of bar
101 20mm dai bar 2305.250
102 16mm dia bar 1352.580
103 12mm dia bar 913.995
104 10mm dia bar 1234.890
105 Weight of 20mm dia bar 2305.250 X 2.470 5693.968
106 Weight of 16mm dia bar 1352.580 X 1.580 2137.076
107 Weight of 12mm dia bar 913.995 X 0.888 811.628
108 Weight of 10mm dia bar 1234.890 X 0.617 761.927
109 9404.599 kg
110 9.404599 Mt
111 Add 2% Westage 0.188092
112 Total 9.59269 Mt
113
A B C D E F G H I J K L
Laying & Fixing joint filler board (18 mm thick ) including
114
cost of all materials,T&P etc.required for proper
completion of work.

115 Behind bed block 2.00 X 1.00 1.35 6.70 18.090


116 Total 18.090
117
Providing and fixing PVC Pipe in drainage spout & weep
hole including cost of all materials,labours,T&P etc.required
118 for proper completion of work.

119 For Weep hole 2.00 X 2.00 1.00 3.00 4.00 48.000
120 48 x 1 x 0.75 36.000
121 Total 36.000 RM
122
Laying 3mm thickPolyplus Multyplast tar paper over bed
123
block including cost of all materials,labours, T&P
etc.required for proper completion of work.
2.00 X 1.00 6.70 0.45 6.03
124 Total 6.030 sqm
125
Providing expansion joint in concrete including placing and
fixing of angle iron & M.S. plate and filling with bitumen
including cost of all materials,labours,T&P etc.required for
126 proper completion of work.

127 2.00 X 1.00 6.70 13.4


128 Total 13.400 Rm
Earth work in filling in embankment including all leads and
lift,cost of soil,labours charges,manual compaction and T&P
129 etc.withincluding proper dressing.

130 2.00 X 1.00 3.67 4.80 6.70 236.0544


131 Total 236.054 cum
Supplyng and laying coarse sand in ramp including cost of
132
all materials,labours,T&P etc.required for proper
completion of work.

133 2.00 X 1.00 6.70 2.40 0.90 28.944


134 Total 28.944 cum
Laying dry stone boulder pitching including cost of all
135
materials, labours,T&P etc. required for proper completion
of work.

136 4.00 X 1.00 4.80 4.47 0.34 29.18016


137 Total 29.180 cum
Dewatering by 5 H.P. Diesel pump of foundation including
138
cost of dewatering equipment and its accessories,required
material,labour etc.

139 60 days X 8 hour's = 480 60.00 day's X 8.00 hour's 480


140 Total 480.000 Hours
Providing / Arrangement of Beldar / chaukidar and
141
Supervisor for and watching Government Materials etc.
required for proper completion of work.

142 Beldar 2.00 X 60.00 120


143 Chaukidar 3.00 X 60.00 180
144 Total 300.000 Mday
Providing / Arrangment of Supervisor for and watching
145
Government Materials etc. required for proper completion
of work.

146 Supervisor 1.00 X 60.00 60


147 Total 60.000 Mday
148
KANHAR NAHAR PARIYOJANA KHAND-6 MIRZAPUR
ESTIMATE FOR CONSTRUCTION OF V.R.B. AT KM. 1.600 OF K.K.C.
BILL OF QUANTITY
S.No. NAME OF ITEMS UNIT QUANTITY RATE AMOUNT
1 2 3 4 5 6
Site Clearence for construction VRB including all leads and
lifts,labours charges, T&P etc. required for proper
completion of work and its disposal as per direction of sqm 510.000 3.350 1708.500
Engineer-in-charge.

Earth work in excavation of foundation in all types of soil


including all leads and lifts, labour charge, T&P etc.required
2 for proper completion of work and its disposal as per cum 1060.739 169.500 179795.227
direction of Engineer-in-charge.

Laying C.C 1:2:4(M15) in foundation with cement,coarse


sand of F.M. not less than 2.00 and hard stone ballast as
obtained from the excavation of foundation including cost
of all material,labour,T&P etc. required for proper
3 completion of works as per direction of Engineer-in-charge. cum 36.679 5726.400 210039.771

Laying C.C 1:1.5:3(M-20) in foundation with cement,coarse


sand of F.M. not less than 2.00 and hard stone ballast as
obtained from the excavation of foundation including cost
4 of all material,labour,T&P etc. required for proper cum 241.102 7211.100 1738612.514
completion of works as per direction of Engineer-in-charge.

Centering & Shuttring for P.C.C./R.C.C. work in different


parts of structure as below including cost of all
materials,labours,T&P etc.required for proper completion
5 of work as per direction of Engineer-in-charge. sqm 492.520 845.000 416179.797

Laying R.C.C.(M-25) with cement , coarde sand of F.M. not


less than 2.00 and crushed hard stone grit including cost of
all materials,labours,T&P etc. required for proper
completion of work but excluding cost of
6 reinforcement,centering and shuttering.in construction of cum 159.145 8438.600 1342959.363
different parts of structure as per direction of Engineer-in-
charge.

Carriage,Cutting,Bending and placing steel for


reinforcement with cost of binding wire including cost of all
materials,labours,T&P etc. required for proper completion
7 of work as per direction of Engineer-in-charge. Mt 9.593 68933.300 661255.816

Laying & Fixing joint filler board (18 mm thick) including


cost of all materials,labours,T&P etc.required for proper
8 completion of work as per direction of Engineer-in-charge. cum 18.090 1100.000 19899.000

Providing and fixing PVC Pipe in drainage spout & weep


hole including cost of all materials,labours,T&P etc.
9 required for proper completon of work as per direction of RM 36.000 410.000 14760.000
Engineer-in-charge.
Laying 3mm thick Polyplus Multyplast tar paper over bed
block including cost of all materials, labours,T&P
10 etc.required for proper completion of work as per direction sqm 6.030 607.000 3660.210
of Engineer-in-charge.

Providing expansion joint in concrete including placing and


fixing of angle iron & M.S. plate and filling with bitumen
including cost of all materials,laboures,T&P etc.required for
11 proper completion of work as per direction of Engineer-in- RM 13.400 5093.170 68248.478
charge.

Earth work in filling in embankment including all leads and


lift,cost of soil,labour charges,manual compaction and T&P
12 etc. with including proper dressing as per direction of cum 236.054 267.000 63026.525
Engineer-in-charge.

Supplying and laying coarse sand in ramp including cost of


all materials,labours,T&P etc. required for proper
13 completion of work as per direction of Engineer-in-charge. cum 28.944 1747.11 50568.35184

Laying dry stone boulder pitching including cost of all


materials,labours,T&P,etc.required for proper completion
14 of work as per direction of Engineer-in-charge. cum 29.18016 740.69 21613.4527104

Dewatering by 5 H.P. Diesel pump of foundation including


cost of dewatering equipment and its accessories,required
15 material,labour etc. as per direction of Engineer-in-charge. Hours 480 170 81600

Providing / Arrangement of Beldar /chaukidar and


Supervisor for and watching Government Materials etc.
16 required for proper completion of work as per direction of Mday 300 315 94500
Engineer-in-charge.

Providing / Arrangment of Supervisor for and watching


Government Materials etc. required for prper completion
17 of work as per direction of Engineer-in charge. Mday 60 367.5 22050

TOTAL AMOUNT Rs 4990477.006


Add 6.875% Centage Charge 343095.294153444
Add 12% G.S.T. 598857.240704192
Add 2% Contingency 99809.5401173654
GRAND TOTAL 6032239.081
SAY Lacs 60.3223908084327

You might also like