COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE STRUCTURE
Bill No.-10
NO. OF
S.No. Description Amount (Rs.) Amount (Lacs.)
Structure
(I) RECONSTRUCTION OF HUME PIPE CULVERT
i 1 ROW 1200 38 13,461,777.34 134.62
ii 2 ROW 1200 5 2,393,665.56 23.94

(II) WIDENING OF HUME PIPE CULVERT


i 1 ROW 1200 1 192,460.74 1.92
i 3 ROW 1200 1 498,255.85 4.98
ii 4 ROW 1000 1 397,112.42 3.97

(III) NEW- CONSTRUCTION OF HPC ON PROJECT ROAD


i 1 ROW 1200 1 322,863.58 3.23

(IV) NEW- CONSTRUCTION OF HPC ON JUNCTIONS


i 1 ROW 1200 16 7,493,110.20 74.93

(V) RECONSTRUCTION OF SLAB CULVERT


i 1X2.00 M 3 5,642,269.79 56.42
ii 1X 5.00 1 3,478,560.99 34.79

(VI) WIDENING OF HUME SLAB CULVERT


i 1X 6.00 1 2,209,411.34 22.09

(VII) REHABILITATION OF SLAB CULVERT


1X1.20 M 1 4,828.80 0.05

(VIII) RECONSTRUCTION OF MINOR BRIDGE


i 2X10.0 M 4 51,687,333.84 516.87

TOTAL 73 87,781,650 877.82


CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR RE- CONSTRUCTION OF HPC ON PROJECT ROAD
AT Ch-1+080, Ch-2+087, Ch-2+800, Ch-5+130, Ch-5+870, Ch-6+170, Ch-6+450, Ch-7+400, Ch-9+329, Ch-9+681, Ch-10+503, Ch-11+072, Ch-
11+272, Ch-11+664, Ch-13+061, Ch-18+510, Ch-22+519, Ch-22+669, Ch-23+543, Ch-23+749, Ch-23+919, Ch-24+552 , Ch-24+990, Ch-26+580,
Ch-26+970, Ch-27+220, Ch-27+940, Ch-27+820
Formation Width = 12.0 m Size = 1 x 1200

Sr. Item Length Width Thickness No. Of


ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Excavation for Structures (Earth work in excavation
of foundation of structures as per drawing and
CH- 9- 9.1

technical specification, including setting


1 out,construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved
material.)
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 2 6.400 1.400 0.920 Cum 16.486
Under pipe 1 12.200 2.040 0.550 Cum 13.688
Apron U/S 1 6.400 1.500 0.300 Cum 2.880
Apron D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 38.815 28 146.00 158674.90

Plain cement concrete complete as per drawing


CH- 9-

and Technical Specifications


9.9

PCC Grade M 15
a)

Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688 28 3768.00 283594.75

Plain cement concrete complete as per drawing


CH- 9-

and Technical Specifications


9.9

PCC M20
a)

For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 Area = 1.629 Cum -2.687
Sub Total 25.719 28 4174.00 3005855.20

Providing and fixing guard stones 200 x 200 x 900


CH- 4- 4.17

mm made of precast RCC M-20 grade fixed at 300 mm


4 into the ground in P.C.C.1:3:6 blocks of size 400 x 400
x 400 mm and given two coats of paint with white and
black bands including excavation.
2 No.. 2 28 431.00 24136.00

Providing and laying boulders apron on river bed for


protection against scour with stone boulders
CH- 9- 9.1

5 weighing not less than 40 kg each complete as per


drawing and Technical specification as per clause
2503..

A Boulder laid dry without wire crates.


U/S 1 6.400 1.500 0.300 Cum 2.880
D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 8.640 28 2413.00 583752.96
Providing and laying Pitching Stone/Boulder on
slopes laid over prepared filter media including
CH- 9- 9.11

boulder apron laid dry in front of toe of embankment


6
complete as per drawing and Technical
specifications as per clause 2504.

U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 28 2413.00 713475.84
Sr. Item Length Width Thickness No. Of
ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
CH- 9- 9.12
Technical specification including trimming of slopes
7
to proper profile and preparation of bed and as per
clause 2504.

U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 28 2079.00 307359.36

Providing and laying Reinforced Cement Concrete


pipe NP 4 /prestrssed concrete pipe on first class
bedding (Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first
CH- 9- 9.2

class bedding of granular material including fixing


8
colla r with cement mortar 1:2 and bedding aas per
clause 2904but excluding excavation, protection
works, backfilling, concrete and masonry works in
head walls and parapets . )

1200 mm dia 1 15.000 RM 15.00 28 9015.00 3786300.00

Removing all type of hume pipes and stacking within


CH- 2- 2.4

a lead up to 1000 meters including earthwork and


(ix)

9
dismantling of masonry works around pipes.

Up to 1000 mm Dia 1 10.000 RM 10.00 28 400.00 112000.00

TOTAL 8975149.01
Say ` 89.75 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR RE-CONSTRUCTION OF HPC ON PROJECT ROAD
AT Ch-0+935, Ch-7+731, Ch-10+653, Ch-11+991, Ch-16+920, Ch-21+729, Ch-22+948, Ch-24+660, Ch-24+830, Ch-26+260
Formation Width = 12.0 m Size = 1 x 1200

SOR
Sr. Length Width Thickness No. Of
Item ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. (M) (M) (M) Structure
No.
1 Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
CH- 9- 9.1

setting out,construction of shoring and bracing,


removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.)
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 2 6.400 1.400 0.920 Cum 16.486
Under pipe 1 9.200 2.040 0.550 Cum 10.322
Apron U/S 1 6.400 1.500 0.300 Cum 2.880
Apron D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 35.449 10 146.00 51755.25

2 Plain cement concrete complete as per drawing


a) CH- 9- 9.9

and Technical Specifications

PCC Grade M 15
Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688
Under Pipe (Base Concrete) 1 12.000 2.040 0.100 Cum 2.448

Qty. of Encased of Pipe 1 10.35 1.740 1.840 Cum 33.137


Deduction of pipes 1 Area= 1.629 10.350 Cum -16.856
Sub Total 21.417 10 3768.00 806974.97

3 Plain cement concrete complete as per drawing


CH- 9-

and Technical Specifications


9.9

PCC M20
a)

For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 1.629 Cum -2.687

Provide P.C.C. Slab On Pipe 1 12.000 1.740 0.300 Cum 20.880

Sub Total 46.599 10 4174.00 1945050.91

Providing and fixing guard stones 200 x 200 x 900


mm made of precast RCC M-20 grade fixed at 300
CH- 4- 4.17

mm into the ground in P.C.C.1:3:6 blocks of size 400


4
x 400 x 400 mm and given two coats of paint with
white and black bands including excavation.

2 No. 2 10 431.00 8620.00

5 Providing and laying boulders apron on river bed


for protection against scour with stone boulders
CH- 9- 9.1

weighing not less than 40 kg each complete as per


drawing and Technical specification as per
clause 2503..
A Boulder laid dry without wire crates.
U/S 1 6.400 1.500 0.300 Cum 2.880
D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 8.640 10 2413.00 208483.20
6 Providing and laying Pitching Stone/Boulder on
slopes laid over prepared filter media including
CH- 9- 9.11

boulder apron laid dry in front of toe of


embankment complete as per drawing and
Technical specifications as per clause 2504.

U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 10 2413.00 254812.80
Formation Width = 12.0 m Size = 1 x 1200

SOR
Sr. Length Width Thickness No. Of
Item ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. (M) (M) (M) Structure
No.
7 Providing and laying Filter material underneath
pitching in slopes complete as per drawing and

CH- 9- 9.12
Technical specification including trimming of
slopes to proper profile and preparation of bed
and as per clause 2504.

U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 10 2079.00 109771.20

8 Providing and laying Reinforced Cement Concrete


pipe NP 4 /prestressed concrete pipe (Laying
Reinforced cement concrete pipeNP4 /prestressed
CH- 9- 9.2

concrete pipe for culverts including fixing collar


with cement mortar 1:2 but excluding bedding
below pipe ,excavation, protection works,
backfilling, concrete and masonryworks in head
walls and parapets . )

1200 mm dia 1 12.000 RM 12.00 10 8843.00 1061160.00

9 Removing all type of hume pipes and stacking


CH- 9- 2.4

within a lead up to 1000 meters including


(ix)

earthwork and dismantling of masonry works


around pipes.

Up to 1000 mm Dia 1 10.000 RM 10.00 10 400.00 40000.00

TOTAL 4486628.33
Say ` 44.87 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR RE-CONSTRUCTION OF HPC ON PROJECT ROAD
AT Ch-6+360, Ch-19+460, Ch-20+922, Ch-21+322, Ch-22+135
Formation Width = 12.0 m Size = 2 x 1200

Sr. Item Length Width Thickness No. Of


ITEM No Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Excavation for Structures (Earth work in excavation
of foundation of structures as per drawing and
CH- 9 - 9.1

technical specification, including setting


1 out,construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved
material.)
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 2 8.100 1.400 0.920 Cum 20.866
Under pipe 1 12.200 3.980 0.550 Cum 26.706
Apron U/S 1 8.100 1.500 0.300 Cum 3.645
Apron D/S 1 8.100 3.000 0.300 Cum 7.290
Sub Total 58.506 5 146.00 42709.67

Plain cement concrete complete as per drawing


CH- 9 -9.9

2 and Technical Specifications

a) PCC Grade M 15
Under head wall (Base Concrete) 2 8.100 1.400 0.150 Cum 3.402 5 3768.00 64093.68

Plain cement concrete complete as per drawing


CH- 9 -

and Technical Specifications


9.9

a) PCC M15
For Headwall
Average breath
(0.4+1.25)/2=0.825 2 8.100 0.825 2.690 Cum 35.952
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 4 -0.825 1.629 Cum -5.374
Sub Total 30.577 5 3768.00 576079.43
Providing and fixing guard stones 200 x 200 x 900
mm made of precast RCC M-20 grade fixed at 300 mm
CH- 4 -4.17

4 into the ground in P.C.C.1:3:6 blocks of size 400 x 400


x 400 mm and given two coats of paint with white and
black bands including excavation.
2 NO. 2 5 431.00 4310.00

Providing and laying boulders apron on river bed for


protection against scour with stone boulders
CH- 9 -9.1

5 weighing not less than 40 kg each complete as per


drawing and Technical specification as per clause
2503..
A Boulder laid dry without wire crates.
U/S 1 8.100 1.500 0.300 Cum 3.645
D/S 1 8.100 3.000 0.300 Cum 7.290
Sub Total 10.935 5 2413.00 131930.78
Providing and laying Pitching Stone/Boulder on
slopes laid over prepared filter media including
CH- 9 -9.11

6 boulder apron laid dry in front of toe of embankment


complete as per drawing and Technical
specifications as per clause 2504.
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 5 2413.00 127406.40
Sr. Item Length Width Thickness No. Of
ITEM No Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Providing and laying Filter material underneath
pitching in slopes complete as per drawing and

CH- 9 -9.12
Technical specification including trimming of slopes
7
to proper profile and preparation of bed and as per
clause 2504.

U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 5 2079.00 54885.60

Providing and laying Reinforced Cement Concrete


pipe NP 4 /prestrssed concrete pipe on first class
bedding (Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first
CH- 9 -9.2

class bedding of granular material including fixing


8
colla r with cement mortar 1:2 and bedding aas per
clause 2904but excluding excavation, protection
works, backfilling, concrete and masonry works in
head walls and parapets . )

1200 mm dia 2 15.000 RM 30.00 5 9015.00 1352250.00

Removing all type of hume pipes and stacking within a


CH- 2-2.4 (ix)

lead up to 1000 meters including earthwork and


9 dismantling of masonry works around pipes.

Up to 1000 mm Dia 2 10.000 RM 20.000 5 400.000 40000.000

TOTAL 2393665.560
Say ` 23.94 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR LHS WIDENING OF HPC ON PROJECT ROAD
AT Ch-19+180
Formation Width = 12.0 m Size = 1 x 1200

Sr. Item Length Width Thickness No. Of


ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Excavation for Structures (Earth work in excavation
of foundation of structures as per drawing and
CH- 9- 9.1

technical specification, including setting


1 out,construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved
material.)
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 1 6.400 1.400 0.920 Cum 8.243
Under pipe 1 6.100 2.040 0.550 Cum 6.844
Apron U/S 1 6.400 1.500 0.300 Cum 2.880
Apron D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 23.727 1 146.00 3464.20

Plain cement concrete complete as per drawing


CH- 9-

and Technical Specifications


9.9

PCC Grade M 15
a)

Under head wall (Base Concrete) 1 6.400 1.400 0.150 Cum 1.344 1 3768.00 5064.19

Plain cement concrete complete as per drawing


CH- 9-

and Technical Specifications


9.9

PCC M20
a)

For Headwall
Average breath
(0.40+1.25)/2=0.825 1 6.400 0.825 2.690 Cum 14.203
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 1 -0.825 Area = 1.629 Cum -1.344
Sub Total 12.860 1 4174.00 53675.99

Providing and fixing guard stones 200 x 200 x 900


CH- 4- 4.17

mm made of precast RCC M-20 grade fixed at 300 mm


4 into the ground in P.C.C.1:3:6 blocks of size 400 x 400
x 400 mm and given two coats of paint with white and
black bands including excavation.
2 No.. 2 1 431.00 862.00

Providing and laying boulders apron on river bed for


protection against scour with stone boulders
CH- 9- 9.1

5 weighing not less than 40 kg each complete as per


drawing and Technical specification as per clause
2503..

A Boulder laid dry without wire crates.


U/S 1 6.400 1.500 0.300 Cum 2.880
D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 8.640 1 2413.00 20848.32
Providing and laying Pitching Stone/Boulder on
slopes laid over prepared filter media including
CH- 9- 9.11

boulder apron laid dry in front of toe of embankment


6
complete as per drawing and Technical
specifications as per clause 2504.

U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 1 2413.00 25481.28
Sr. Item Length Width Thickness No. Of
ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Providing and laying Filter material underneath
pitching in slopes complete as per drawing and

CH- 9- 9.12
Technical specification including trimming of slopes
7
to proper profile and preparation of bed and as per
clause 2504.

U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 1 2079.00 10977.12

Providing and laying Reinforced Cement Concrete


pipe NP 4 /prestrssed concrete pipe on first class
bedding (Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first
CH- 9- 9.2

class bedding of granular material including fixing


8
colla r with cement mortar 1:2 and bedding aas per
clause 2904but excluding excavation, protection
works, backfilling, concrete and masonry works in
head walls and parapets . )

1200 mm dia 1 7.500 RM 7.50 1 9015.00 67612.50

9 Dismantling of existing structures like culverts,


bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
2.4 (i)

wherever necessary, sorting the dismantled material,


disposal of unserviceable material and stacking the
serviceable material with all lifts and lead up to
1000 meters and as per relevant clauses of section-
200 in 1 12.86 CUM 12.86 1 348.00 4475.14
TOTAL 192460.74
Say ` 1.92 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR BHS WIDENING OF HPC ON PROJECT ROAD
AT Ch--13+690
Formation Width = 12.0 m Size = 3 x 1200

Sr. Item Length Width Thickness No. Of


ITEM No Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Excavation for Structures (Earth work in excavation
of foundation of structures as per drawing and
CH- 9 - 9.1

technical specification, including setting


1 out,construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved
material.)
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 2 9.300 1.400 0.920 Cum 23.957
Under pipe 1 7.200 5.920 0.550 Cum 23.443
Apron U/S 1 9.300 1.500 0.300 Cum 4.185
Apron D/S 1 9.300 3.000 0.300 Cum 8.370
Sub Total 59.955 1 146.00 8753.43

Plain cement concrete complete as per drawing


CH- 9 -9.9

2 and Technical Specifications

a) PCC Grade M 15
Under head wall (Base Concrete) 2 9.300 1.400 0.150 Cum 3.906 1 3768.00 14717.81

Plain cement concrete complete as per drawing


CH- 9 -

and Technical Specifications


9.9

a) PCC M15
For Headwall
Average breath
(0.4+1.25)/2=0.825 2 9.300 0.825 2.690 Cum 41.278
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 6 -0.825 1.629 Cum -8.062
Sub Total 33.216 1 3768.00 125159.67

Providing and fixing guard stones 200 x 200 x 900


mm made of precast RCC M-20 grade fixed at 300 mm
CH- 4 -4.17

4 into the ground in P.C.C.1:3:6 blocks of size 400 x 400


x 400 mm and given two coats of paint with white and
black bands including excavation.
2 NO. 2 1 431.00 862.00

Providing and laying boulders apron on river bed for


CH- 9 -9.1

protection against scour with stone boulders


5 weighing not less than 40 kg each complete as per
drawing and Technical specification as per clause
2503..
A Boulder laid dry without wire crates.
U/S 1 9.300 1.500 0.300 Cum 4.185
D/S 1 9.300 3.000 0.300 Cum 8.370
Sub Total 12.555 1 2413.00 30295.22
Providing and laying Pitching Stone/Boulder on
CH- 9 -9.11

slopes laid over prepared filter media including


6 boulder apron laid dry in front of toe of embankment
complete as per drawing and Technical
specifications as per clause 2504.
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 1 2413.00 25481.28
Sr. Item Length Width Thickness No. Of
ITEM No Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Providing and laying Filter material underneath

CH- 9 -9.12
pitching in slopes complete as per drawing and
7 Technical specification including trimming of slopes
to proper profile and preparation of bed and as per
clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 1 2079.00 10977.12

Providing and laying Reinforced Cement Concrete


pipe NP 4 /prestrssed concrete pipe on first class
bedding (Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first
CH- 9 -9.2

class bedding of granular material including fixing


8
colla r with cement mortar 1:2 and bedding aas per
clause 2904but excluding excavation, protection
works, backfilling, concrete and masonry works in
head walls and parapets . )

1200 mm dia 3 10.000 RM 30.00 1 9015.00 270450.00

9 Dismantling of existing structures like culverts,


bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
2.4 (i)

wherever necessary, sorting the dismantled material,


disposal of unserviceable material and stacking the
serviceable material with all lifts and lead up to
1000 meters and as per relevant clauses of section-
200 in 1 33.22 CUM 33.22 1 348.00 11559.33

TOTAL 498255.851
Say ` 4.98 Lacs
CHHATTISGARH ROAD DEVLELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR LHS WIDEINING OF CROSS DRAINAGE STRUCTURES
Formation Width = 12.0 m Size = 4 x 1000

AT CH- 2+482
SOR
Sr. Length Width Thickness No. Of
ITEM ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. (M) (M) (M) Structure
NO.
1 Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out,construction of shoring and bracing,
9.1

removal of stumps and other deleterious matter,


dressing of sides and bottom and backfilling with
approved material.)
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 1 12.500 1.400 0.920 Cum 16.100
Under pipe 1 6.100 7.020 0.550 Cum 23.552
Apron U/S 1 12.500 1.500 0.300 Cum 5.625
Apron D/S 1 12.500 3.000 0.300 Cum 11.250
Sub Total 56.527 1 146.00 8252.96

2 Plain cement concrete complete as per drawing


9.9

and Technical Specifications

PCC Grade M 15
a)

Under head wall (Base Concrete) 1 12.500 1.400 0.150 Cum 2.625 1 3768.00 9891.00

3 Plain cement concrete complete as per drawing


a) 9.9

and Technical Specifications


PCC M20
For Headwall
Average breath
(0.40+1.25)/2=0.825 1 12.500 0.825 2.480 Cum 25.575
Deduction of pipes
Area of pipe
3.14/4X(1.23)2=1.188 4 -0.825 1.188 Cum -3.921
Sub Total 21.654 1 4174.00 90383.15

Providing and fixing guard stones 200 x 200 x 900


mm made of precast RCC M-20 grade fixed at 300
mm into the ground in P.C.C.1:3:6 blocks of size 400
4.17

4
x 400 x 400 mm and given two coats of paint with
white and black bands including excavation.

2 No.. 2.000 1 431.00 862.00

5 Providing and laying boulders apron on river bed


for protection against scour with stone boulders
9.10

weighing not less than 40 kg each complete as per


drawing and Technical specification as per
clause 2503..
A Boulder laid dry without wire crates.
U/S 1 12.500 1.500 0.300 Cum 5.625
D/S 1 12.500 3.000 0.300 Cum 11.250
Sub Total 16.875 1 2413.00 40719.38
6 Providing and laying Pitching Stone/Boulder on
slopes laid over prepared filter media including
9.11

boulder apron laid dry in front of toe of


embankment complete as per drawing and
Technical specifications as per clause 2504.
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 1 2413.00 25481.28
SOR
Sr. Length Width Thickness No. Of
ITEM ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. (M) (M) (M) Structure
NO.
7 Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
9.12
Technical specification including trimming of
slopes to proper profile and preparation of bed
and as per clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 1 2079.00 10977.12

8 Providing and laying Reinforced Cement


Concrete pipe NP 4 /prestrssed concrete pipe on
first class bedding (Laying Reinforced cement
concrete pipe NP4/prestressed concrete pipe for
culverts on first class bedding of granular material
9.2

including fixing colla r with cement mortar 1:2 and


bedding aas per clause 2904but excluding
excavation, protection works, backfilling,
concrete and masonry works in head walls and
parapets . )
1000 mm dia 4 7.500 RM 30.00 1 6767.00 203010.00

9 Dismantling of existing structures like culverts,


bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled
2.4 (i)

material, disposal of unserviceable material and


stacking the serviceable material with all lifts and
lead up to 1000 meters and as per relevant
clauses of section-200 in
1 21.65 CUM 21.65 1 348.00 7535.54

TOTAL 397112.42
Say ` 3.97 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR NEW- CONSTRUCTION OF HPC ON PROJECT ROAD
AT CH-6+200
Formation Width = 12.0 m Size = 1 x 1200

Sr. Item Length Width No. Of


ITEM No 3.000 Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) Structure
Excavation for Structures (Earth work in excavation
of foundation of structures as per drawing and
CH- 9- 9.1

technical specification, including setting


1 out,construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved
material.)
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 2 6.400 1.400 0.920 Cum 16.486
Under pipe 1 12.200 2.040 2.290 Cum 56.994
Apron U/S 1 6.400 1.500 0.300 Cum 2.880
Apron D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 82.120 1 146.00 11989.51

Plain cement concrete complete as per drawing


CH- 9-

and Technical Specifications


9.9

PCC Grade M 15
a)

Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688 1 3768.00 10128.38

Plain cement concrete complete as per drawing


CH- 9-

and Technical Specifications


9.9

PCC M20
a)

For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 Area = 1.629 Cum -2.687
Sub Total 25.719 1 4174.00 107351.97

Providing and fixing guard stones 200 x 200 x 900


CH- 4- 4.17

mm made of precast RCC M-20 grade fixed at 300 mm


4 into the ground in P.C.C.1:3:6 blocks of size 400 x 400
x 400 mm and given two coats of paint with white and
black bands including excavation.
2 No.. 2 1 431.00 862.00

Providing and laying boulders apron on river bed for


CH- 9- 9.1

protection against scour with stone boulders


5 weighing not less than 40 kg each complete as per
drawing and Technical specification as per clause
2503..
A Boulder laid dry without wire crates.
U/S 1 6.400 1.500 0.300 Cum 2.880
D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 8.640 1 2413.00 20848.32
Providing and laying Pitching Stone/Boulder on
slopes laid over prepared filter media including
CH- 9- 9.11

boulder apron laid dry in front of toe of embankment


6
complete as per drawing and Technical
specifications as per clause 2504.

U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 1 2413.00 25481.28
Sr. Item Length Width No. Of
ITEM No 3.000 Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) Structure
Providing and laying Filter material underneath

CH- 9- 9.12
pitching in slopes complete as per drawing and
7 Technical specification including trimming of slopes
to proper profile and preparation of bed and as per
clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 1 2079.00 10977.12

Providing and laying Reinforced Cement Concrete


pipe NP 4 /prestrssed concrete pipe on first class
bedding (Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first
CH- 9- 9.2

class bedding of granular material including fixing


8
colla r with cement mortar 1:2 and bedding aas per
clause 2904but excluding excavation, protection
works, backfilling, concrete and masonry works in
head walls and parapets . )

1200 mm dia 1 15.000 RM 15.00 1 9015.00 135225.00

TOTAL 322863.58
Say ` 3.23 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR NEW- CONSTRUCTION OF HPC ON JUNCTIONS
Provide New 16 No. HPC at Junctions
Size = 1 x 1200

Sr. Item Length Width Thickness No. Of


ITEM No Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure

Excavation for Structures (Earth work in excavation


of foundation of structures as per drawing and
technical specification, including setting
CH- 9 -9.1

1 out,construction of shoring and bracing, removal of


stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved
material.)

Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 2 6.400 1.400 0.920 Cum 16.486
Under pipe 1 27.200 2.040 2.290 Cum 127.068
Apron U/S 1 6.400 1.500 0.300 Cum 2.880
Apron D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 152.194 16 146.00 355525.00

Plain cement concrete complete as per drawing


a) CH- 9 -9.9

2 and Technical Specifications

PCC Grade M 15
Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688 16 3768.00 162054.14

Plain cement concrete complete as per drawing


a) CH- 9 -9.9

3
and Technical Specifications

PCC M20
For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 1.629 Cum -2.687
Sub Total 25.719 16 4174.00 1717631.54

Providing and fixing guard stones 200 x 200 x 900


mm made of precast RCC M-20 grade fixed at 300
CH- 4 -4.17

mm into the ground in P.C.C.1:3:6 blocks of size 400


4
x 400 x 400 mm and given two coats of paint with
white and black bands including excavation.

2 NO. 2 16 431.00 13792.00

Providing and laying boulders apron on river bed


for protection against scour with stone boulders
CH- 9 -9.10

weighing not less than 40 kg each complete as per


5
drawing and Technical specification as per clause
2503..

A Boulder laid dry without wire crates.


U/S 1 6.400 1.500 0.300 Cum 2.880
D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 8.640 16 2413.00 333573.12
Providing and laying Pitching Stone/Boulder on
CH- 9-9.11

slopes laid over prepared filter media including


6 boulder apron laid dry in front of toe of
embankment complete as per drawing and
Technical specifications as per clause 2504.
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 16 2413.00 407700.48
Sr. Item Length Width Thickness No. Of
ITEM No Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure

Providing and laying Filter material underneath


pitching in slopes complete as per drawing and

CH- 9-9.12
Technical specification including trimming of
7
slopes to proper profile and preparation of bed
and as per clause 2504.

U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 16 2079.00 175633.92

Providing and laying Reinforced Cement Concrete


pipe NP 4 /prestrssed concrete pipe on first class
bedding (Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first
CH- 9- 9.2

class bedding of granular material including fixing


8
colla r with cement mortar 1:2 and bedding aas per
clause 2904but excluding excavation, protection
works, backfilling, concrete and masonry works
in head walls and parapets . )

1200 mm dia 1 30.000 RM 30.00 16 9015.00 4327200.00

TOTAL 7493110.20
Say ` 74.93 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF SLAB CULVERT
AT CH- 3+180 SPAN = 1 X 2.00 M
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

1 1.4 1.4 Dismantling of existing structures like


culverts, bridges, retaining walls and other
structure comprising of masonry,
cement concrete, wood work, steel work,
including T&P and scaffolding wherever
necessary, sorting the dismantled material,
disposal of unserviceable material and
stacking the serviceable material with all
lifts and lead upto 1000 meters and as per
relevant clauses of section-200 in

(B ) Cement Concrete Grade M-15 & M-20 RM 1 1.5 7.5 1.5 16.88 1 16.88 348.00 5,872.50

2 2.1 Excavation for Structures Earth work in


excavation of foundation of structures as
per drawing and technical specification,
including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides
and bottom and backfilling with approved
material including dewatering etc.
complete.
I Ordinary Soil

(i) Depth upto 3 m


For Abutment Cum 2 12.15 2.88 1.72 120.02
For Return Cum 4 3.65 2.355 1.72 58.97
Sub Total 178.99 1 178.99 146.00 26,132.45

3 2.6 Plain/Reinforced cement concrete in open


foundation complete as per drawing and
technical specifications.
A Using concrete mixer
(i) PCC Grade M15
Below foundation
For Abutment Cum 2 12.15 2.880 0.15 10.50
For Return Cum 4 3.65 2.355 0.15 5.16
Sub Total 15.66 1 15.66 4,613.00 72,216.75

4 2.6 Plain/Reinforced cement concrete in open


foundationcomplete as per drawing and
technical specifications.
A Using concrete mixer
(ii) PCC Grade M25
For Abutment Foundation Cum 2 12.00 2.730 0.200 13.10
Cum 2 12.00 2.330 0.200 11.18
Cum 2 12.00 2.030 0.400 19.49
Cum 2 12.00 1.830 0.400 17.57
Cum 2 12.00 0.200 0.400 0.96
Return wall Foundation Cum 4 3.50 2.205 0.400 12.35
Cum 4 3.50 2.005 0.400 11.23
Cum 4 3.50 1.705 0.400 9.55
Cum 4 3.50 0.300 0.400 0.84
Total 96.27 1 96.27 5,921.00 570,002.83

5 2.24 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in foundation complete as
per drawing and technical specifications as
per section 1600
Reinforcement @ 5kg/Cum MT 96.27 0.005 0.48 1 0.48 68,693.00 33,064.7

6 3.6 Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
as per drawing and technical
specifications section 1500, 1700 and
2200 (Newly laid concrete shall be covered
by gunny bags)
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

A Height upto 5m
(a) Using concrete Mixer
(iii) P.C.C. Grade M-25
A Height upto 5m
For abutment Substructure Cum 2 12.0 1.165 0.96 26.90
For Return Wall Substructure Cum 4 3.5 1.10 1.46 22.57
Total 49.46 1 49.46 6,278.00 310,531.79
(ii) R.C.C. Grade M-25
Durt wall Cum 2 12.0 0.3 0.250 1.80
abutment Cap Cum 2 12.0 0.7 0.500 8.40
Bracket 2 12.0 Area= 0.032 0.78
Total 10.98 1 10.98 6,339.00 69,587.01

7 3.7 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bars
reinforcement in sub-structure complete as
per drawing and technical specifications
section 1600 and 2200.
Substructure Reinforcement @ 5kg/sqm MT 49.46 0.005 0.25
Abt cap, Dirt wall (70kg/cum) MT 10.98 0.07 0.77
Sub Total 1.02 1 1.0 69,002.0 70,088.74

8 4.1 Furnishing and Placing


Reinforced/Prestressed cement concrete in
super-structure as per drawing and
Technical Specification sections 1500, 1600
and 1700 (Newly laid concrete shall be
covered by gunny bags).
C RCC Grade M 30
(ii) Height UPTO 5m
I. Solid slab Super structure Cum 1.0 2.40 12.00 0.25 7.20 1 7.2 6,973.0 50,205.60

9 4.2 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in super-structurecomplete
as per drawing and technical specifications

Super structure@ 100kg/Cum MT 1 7.20 0.1 0.720


Total 0.720 1 0.72 70,101.00 50,472.72

10 3.8 Providing weep holes in Brick masonry/


Plain/ Reinforced concrete abutment, wing
wall/return wall with 100 mm dia. AC
pipe, extending through the full width of the
structure with slope of 1 V: 20 H towards
drawing face. Complete as per drawing and
Technical specifications section 2706 and
2200.
For abutment meter 2 11.00 1.17 25.63
For Return meter 4 3.00 1.10 13.00
Total Qty. 38.63 1 38.63 321.00 12,400.23

11 3.9 Back filling behind abutment, wing wall


and return wall complete as per drawing
and Technical specification 710.1.4 of I.R.C.
78 and 2200.
(i.) Granular Material Cum 2 8.59 0.96 0.56 4.61
Total Qty. 4.61 1 4.61 905.00 4,172.73

12 3.10 Providing and laying of Filter media with


granular materials/stone crushed
aggregates satisfying the requirements
laid down in clause 2504.2.2. of
MORT&H specifications to a thickness of
not less than 600 mm with smaller size
towards the soil and bigger size towards
the wa ll and provided over the entire
surface behind abutment, wing wall and
return wall to the full height compacted
to a firm condition complete as per
drawing and technical Specifications
710.1.4 of I.R.C. 78 and 2200
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

Cum 2 8.59 0.96 0.60 9.92


Cum 4 2.90 0.96 0.60 6.70
Total Qty. 16.61 1 16.61 1,926.00 31,994.36
13 3.17 Providing and fixing in position tar paper
bearing for slab as per approved drawings
and specification.

Sqm 2.00 12 0.40 9.60 1 9.60 66.00 633.60

Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 12.00 0.25 6.00 1 6.00 1,204.00 7,224.00

15 4.10 PCC M15 Grade leveling course below


approach slab complete as per drawing and
Technical specification and as
per relevant section 2700 Cum 1.00 12.00 3.50 0.10 42.00 1 42.00 4,437.00 186,354.00

16 4.11 Providing and laying M-30 grade


Reinforced cement concrete approach slab
including reinforcement and formwork
complete as per drawing and Technical
specification and as per relevant sections
1500, 1600, 1700 and 2704
Cum 1.00 12.0 3.500 0.200 8.40 1 8.40 9,467.00 79,522.80

17 4.4 Providing and laying Cement concrete


wearing coat M-30 grade including
reinforcement complete as per drawing and
Technical Specifications as per relevant
clause of section 2700 Cum 1.00 12.00 9.40 0.075 8.46 1 8.46 11,847.00 100,225.62

18 4.9 Drainage Spouts complete as per


drawing and Technical specifications of Each 2.00 2.00 1 2.00 2,007.00 4,014.00
section 2705
19 5.4 Providing and laying Pitching on slopes laid
over prepared filter media including
boulder apron laid dry in front of toe of
embankment complete as per drawing
and Technical specifications as per section
2504
a) Stone/Boulder (All four side slopes ) Cum 1.00 Area= 24.63 0.30 7.39 1 7.39 2,413.00 17,830.83

20 5.5 Providing and laying Filter material


underneath pitching in slopes complete as
per drawing and Technical specification
including trimming of slopes to proper
profile and preparation of bed as per
section 2504. Cum 1.00 Area= 24.63 0.15 3.69 1 3.69 2,079.00 7,681.37

21 4.27 Providing and fixing for hand railing top of


crash barrier in cluding cost of material
complete as per approved drawing Rmt 2 9.40 18.80 1 18.80 600.00 11,280.00

TOTAL COST (Rs.) 1,721,508.61


TOTAL COST (Cr.) 0.17
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF SLAB CULVERT
AT CH- 3+600 SPAN = 1 X 2.00 M
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

1 1.4 1.4 Dismantling of existing structures like


culverts, bridges, retaining walls and other
structure comprising of masonry,
cement concrete, wood work, steel work,
including T&P and scaffolding wherever
necessary, sorting the dismantled material,
disposal of unserviceable material and
stacking the serviceable material with all
lifts and lead upto 1000 meters and as per
relevant clauses of section-200 in

(B ) Cement Concrete Grade M-15 & M-20 RM 1 1.5 7.5 1.5 16.88 1 16.88 348.00 5,872.50

2 2.1 Excavation for Structures Earth work in


excavation of foundation of structures as
per drawing and technical specification,
including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides
and bottom and backfilling with approved
material including dewatering etc. complete.

I Ordinary Soil

(i) Depth upto 3 m


For Abutment Cum 2 12.15 2.945 1.66 118.80
For Return Cum 4 3.65 2.355 1.66 57.08
Sub Total 175.87 1 175.87 146.00 25,677.19

3 2.6 Plain/Reinforced cement concrete in open


foundation complete as per drawing and
technical specifications.
A Using concrete mixer
(i) PCC Grade M15
Below foundation
For Abutment Cum 2 12.15 2.945 0.15 10.73
For Return Cum 4 3.65 2.355 0.15 5.16
Sub Total 15.89 1 15.89 4,613.00 73,309.68

4 2.6 Plain/Reinforced cement concrete in open


foundationcomplete as per drawing and
technical specifications.
A Using concrete mixer
(ii) PCC Grade M25
For Abutment Foundation Cum 2 12.00 2.795 0.200 13.42
Cum 2 12.00 2.395 0.200 11.50
Cum 2 12.00 1.995 0.400 19.15
Cum 2 12.00 1.795 0.400 17.23
Cum 2 12.00 0.200 0.400 0.96
Return wall Foundation Cum 4 3.50 2.205 0.400 12.35
Cum 4 3.50 2.005 0.400 11.23
Cum 4 3.50 1.705 0.400 9.55
Cum 4 3.50 0.300 0.400 0.84
Total 96.22 1 96.22 5,921.00 569,718.62

5 2.24 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in foundation complete as
per drawing and technical specifications as
per section 1600
Reinforcement @ 5kg/Cum MT 96.22 0.005 0.48 1 0.48 68,693.00 33,048.2

6 3.6 Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
as per drawing and technical
specifications section 1500, 1700 and
2200 (Newly laid concrete shall be covered
by gunny bags)
A Height upto 5m
(a) Using concrete Mixer
(iii) P.C.C. Grade M-25
A Height upto 5m
For abutment Substructure Cum 2 12.0 1.148 0.86 23.57
For Return Wall Substructure Cum 4 3.5 1.10 1.36 20.93
Total 44.50 1 44.50 6,278.00 279,396.74
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

(ii) R.C.C. Grade M-25


Durt wall Cum 2 12.0 0.3 0.250 1.80
abutment Cap Cum 2 12.0 0.7 0.500 8.40
Bracket 2 12.0 Area= 0.032 0.78
Total 10.98 1 10.98 6,339.00 69,587.01

7 3.7 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bars
reinforcement in sub-structure complete as
per drawing and technical specifications
section 1600 and 2200.
MT
Substructure Reinforcement @ 5kg/sqm 44.50 0.005 0.22
Abt cap, Dirt wall (70kg/cum) MT 10.98 0.07 0.77
Sub Total 0.99 1 1.0 69,002.0 68,377.70

8 4.1 Furnishing and Placing


Reinforced/Prestressed cement concrete in
super-structure as per drawing and
Technical Specification sections 1500, 1600
and 1700 (Newly laid concrete shall be
covered by gunny bags).
C RCC Grade M 30
(ii) Height UPTO 5m
I. Solid slab Super structure Cum 1.0 2.40 12.00 0.25 7.20 1 7.2 6,973.0 50,205.60

9 4.2 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in super-structurecomplete
as per drawing and technical specifications

Super structure@ 100kg/Cum MT 1 7.20 0.1 0.720


Total 0.720 1 0.72 70,101.00 50,472.72

10 3.8 Providing weep holes in Brick masonry/


Plain/ Reinforced concrete abutment, wing
wall/return wall with 100 mm dia. AC
pipe, extending through the full width of the
structure with slope of 1 V: 20 H towards
drawing face. Complete as per drawing and
Technical specifications section 2706 and
2200.
For abutment meter 2 11.00 1.15 25.25
For Return meter 4 3.00 1.10 13.00
Total Qty. 38.25 1 38.25 321.00 12,276.65

11 3.9 Back filling behind abutment, wing wall


and return wall complete as per drawing
and Technical specification 710.1.4 of I.R.C.
78 and 2200.
(i.) Granular Material Cum 2 8.59 0.86 0.50 3.65
Total Qty. 3.65 1 3.65 905.00 3,303.83

12 3.10 Providing and laying of Filter media with


granular materials/stone crushed
aggregates satisfying the requirements laid
down in clause 2504.2.2. of MORT&H
specifications to a thickness of not less
than 600 mm with smaller size towards
the soil and bigger size towards the wa ll
and provided over the entire surface behind
abutment, wing wall and return wall to
the full height compacted to a firm
condition complete as per drawing and
technical Specifications 710.1.4 of I.R.C. 78
and 2200

Cum 2 8.59 0.86 0.60 8.82


Cum 4 2.90 0.86 0.60 5.96
Total Qty. 14.78 1 14.78 1,926.00 28,468.99
13 3.17 Providing and fixing in position tar paper
bearing for slab as per approved drawings
and specification.

Sqm 2.00 12 0.40 9.60 1 9.60 66.00 633.60

Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 12.00 0.25 6.00 1 6.00 1,204.00 7,224.00
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

15 4.10 PCC M15 Grade leveling course below


approach slab complete as per drawing and
Technical specification and as
per relevant section 2700 Cum 1.00 12.00 3.50 0.10 42.00 1 42.00 4,437.00 186,354.00

16 4.11 Providing and laying M-30 grade


Reinforced cement concrete approach slab
including reinforcement and formwork
complete as per drawing and Technical
specification and as per relevant sections
1500, 1600, 1700 and 2704
Cum 1.00 12.0 3.500 0.200 8.40 1 8.40 9,467.00 79,522.80

17 4.4 Providing and laying Cement concrete


wearing coat M-30 grade including
reinforcement complete as per drawing and
Technical Specifications as per relevant
clause of section 2700 Cum 1.00 12.00 9.40 0.075 8.46 1 8.46 11,847.00 100,225.62

18 4.9 Drainage Spouts complete as per drawing


and Technical specifications of section 2705 Each 2.00 2.00 1 2.00 2,007.00 4,014.00

19 5.4 Providing and laying Pitching on slopes laid


over prepared filter media including
boulder apron laid dry in front of toe of
embankment complete as per drawing
and Technical specifications as per section
2504
a) Stone/Boulder (All four side slopes ) Cum 1.00 Area= 19.50 0.30 5.85 1 5.85 2,413.00 14,117.86

20 5.5 Providing and laying Filter material


underneath pitching in slopes complete as
per drawing and Technical specification
including trimming of slopes to proper
profile and preparation of bed as per
section 2504. Cum 1.00 Area= 19.50 0.15 2.93 1 2.93 2,079.00 6,081.86

21 4.27 Providing and fixing for hand railing top of


crash barrier in cluding cost of material
complete as per approved drawing Rmt 2 9.40 18.80 1 18.80 600.00 11,280.00

TOTAL COST (Rs.) 1,679,169.17


TOTAL COST (Cr.) 0.17
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF SLAB CULVERT
AT CH- 16+470 SPAN = 1 X 2.00 M
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

1 1.4 1.4 Dismantling of existing structures like


culverts, bridges, retaining walls and other
structure comprising of masonry,
cement concrete, wood work, steel work,
including T&P and scaffolding wherever
necessary, sorting the dismantled material,
disposal of unserviceable material and
stacking the serviceable material with all
lifts and lead upto 1000 meters and as per
relevant clauses of section-200 in

(B ) Cement Concrete Grade M-15 & M-20 RM 1 1.5 7.5 1.5 16.88 1 16.88 348.00 5,872.50

2 2.1 Excavation for Structures Earth work in


excavation of foundation of structures as
per drawing and technical specification,
including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides
and bottom and backfilling with approved
material including dewatering etc.
complete.
I Ordinary Soil

(i) Depth upto 3 m


For Abutment Cum 2 12.15 3.025 2.14 157.01
For Return Cum 4 3.65 2.62 2.14 81.71
Sub Total 238.72 1 238.72 146.00 34,852.87

3 2.6 Plain/Reinforced cement concrete in open


foundation complete as per drawing and
technical specifications.
A Using concrete mixer
(i) PCC Grade M15
Below foundation
For Abutment Cum 2 12.15 3.025 0.15 11.03
For Return Cum 4 3.65 2.620 0.15 5.74
Sub Total 16.76 1 16.76 4,613.00 77,331.99

4 2.6 Plain/Reinforced cement concrete in open


foundationcomplete as per drawing and
technical specifications.
A Using concrete mixer
(ii) PCC Grade M25
For Abutment Foundation Cum 2 12.00 2.875 0.200 13.80
Cum 2 12.00 2.475 0.200 11.88
Cum 2 12.00 2.175 0.400 20.88
Cum 2 12.00 1.975 0.400 18.96
Cum 2 12.00 0.200 0.400 0.96
Return wall Foundation Cum 4 3.50 2.470 0.400 13.83
Cum 4 3.50 2.170 0.400 12.15
Cum 4 3.50 1.870 0.400 10.47
Cum 4 3.50 0.300 0.400 0.84
Total 103.78 1 103.78 5,921.00 614,457.70

5 2.24 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in foundation complete as
per drawing and technical specifications as
per section 1600
Reinforcement @ 5kg/Cum MT 103.78 0.005 0.52 1 0.52 68,693.00 35,643.4

6 3.6 Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
as per drawing and technical
specifications section 1500, 1700 and
2200 (Newly laid concrete shall be
covered by gunny bags)
A Height upto 5m
(a) Using concrete Mixer
(iii) P.C.C. Grade M-25
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

A Height upto 5m
For abutment Substructure Cum 2 12.0 1.238 1.97 58.57
For Return Wall Substructure Cum 4 3.5 1.19 2.47 41.01
Total 99.58 1 99.58 6,278.00 625,156.21
(ii) R.C.C. Grade M-25
Durt wall Cum 2 12.0 0.3 0.250 1.80
abutment Cap Cum 2 12.0 0.7 0.500 8.40
Bracket 2 12.0 Area= 0.032 0.78
Total 10.98 1 10.98 6,339.00 69,587.01

7 3.7 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bars
reinforcement in sub-structure complete as
per drawing and technical specifications
section 1600 and 2200.
MT
Substructure Reinforcement @ 5kg/sqm 99.58 0.005 0.50
Abt cap, Dirt wall (70kg/cum) MT 10.98 0.07 0.77
Sub Total 1.27 1 1.3 69,002.0 87,379.05

8 4.1 Furnishing and Placing


Reinforced/Prestressed cement concrete in
super-structure as per drawing and
Technical Specification sections 1500, 1600
and 1700 (Newly laid concrete shall be
covered by gunny bags).
C RCC Grade M 30
(ii) Height UPTO 5m
I. Solid slab Super structure Cum 1.0 2.40 12.00 0.25 7.20 1 7.2 6,973.0 50,205.60

9 4.2 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in super-structurecomplete
as per drawing and technical specifications

Super structure@ 100kg/Cum MT 1 7.20 0.1 0.720


Total 0.720 1 0.72 70,101.00 50,472.72

10 3.8 Providing weep holes in Brick masonry/


Plain/ Reinforced concrete abutment, wing
wall/return wall with 100 mm dia. AC
pipe, extending through the full width of
the structure with slope of 1 V: 20 H
towards drawing face. Complete as per
drawing and Technical specifications
section 2706 and 2200.
For abutment meter 2 11.00 1.24 27.23
For Return meter 4 3.00 1.19 14.00
Total Qty. 41.23 1 41.23 321.00 13,233.23

11 3.9 Back filling behind abutment, wing wall


and return wall complete as per drawing
and Technical specification 710.1.4 of I.R.C.
78 and 2200.
(i.) Granular Material Cum 2 8.26 1.97 1.14 18.63
Total Qty. 18.63 1 18.63 905.00 16,860.50

12 3.10 Providing and laying of Filter media with


granular materials/stone crushed
aggregates satisfying the requirements
laid down in clause 2504.2.2. of
MORT&H specifications to a thickness of
not less than 600 mm with smaller size
towards the soil and bigger size towards
the wa ll and provided over the entire
surface behind abutment, wing wall and
return wall to the full height compacted
to a firm condition complete as per
drawing and technical Specifications
710.1.4 of I.R.C. 78 and 2200

Cum 2 8.26 1.97 0.60 19.55


Cum 4 2.90 1.97 0.60 13.73
Total Qty. 33.27 1 33.27 1,926.00 64,081.07
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

13 3.17 Providing and fixing in position tar paper


bearing for slab as per approved drawings
and specification.

Sqm 2.00 12 0.40 9.60 1 9.60 66.00 633.60

Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete
as per drawing & Technical Specification
Sqm 2 12.00 0.25 6.00 1 6.00 1,204.00 7,224.00

15 4.10 PCC M15 Grade leveling course below


approach slab complete as per drawing and
Technical specification and as
per relevant section 2700 Cum 1.00 12.00 3.50 0.10 42.00 1 42.00 4,437.00 186,354.00

16 4.11 Providing and laying M-30 grade


Reinforced cement concrete approach
slab including reinforcement and
formwork complete as per drawing and
Technical specification and as per
relevant sections 1500, 1600, 1700 and
2704 Cum 1.00 12.0 3.500 0.200 8.40 1 8.40 9,467.00 79,522.80

17 4.4 Providing and laying Cement concrete


wearing coat M-30 grade including
reinforcement complete as per drawing and
Technical Specifications as per relevant
clause of section 2700 Cum 1.00 12.00 9.40 0.075 8.46 1 8.46 11,847.00 100,225.62

18 4.9 Drainage Spouts complete as per


drawing and Technical specifications of Each 2.00 2.00 1 2.00 2,007.00 4,014.00
section 2705
19 5.4 Providing and laying Pitching on slopes laid
over prepared filter media including
boulder apron laid dry in front of toe of
embankment complete as per drawing
and Technical specifications as per section
2504
a) Stone/Boulder (All four side slopes ) Cum 1.00 Area= 103.50 0.30 31.05 1 31.05 2,413.00 74,926.46

20 5.5 Providing and laying Filter material


underneath pitching in slopes complete as
per drawing and Technical specification
including trimming of slopes to proper
profile and preparation of bed as per
section 2504. Cum 1.00 Area= 103.50 0.15 15.53 1 15.53 2,079.00 32,277.68

21 4.27 Providing and fixing for hand railing top of


crash barrier in cluding cost of material
complete as per approved drawing Rmt 2 9.40 18.80 1 18.80 600.00 11,280.00

TOTAL COST (Rs.) 2,241,592.02


TOTAL COST (Cr.) 0.22
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF SLAB CULVERT
AT CH-14+510 SPAN = 1 X 5.00 M
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

1 1.4 (ix) Removing all type of hume pipes and


stacking within a lead upto 1000 meters
including earthwork and dismantling of
masonry works around pipes.
(A ) Above to 1000 mm dia RM 6 7.5 45 531.00 23,895.00

2 2.1 Excavation for Structures Earth work in


excavation of foundation of structures as
per drawing and technical specification,
including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides
and bottom and backfilling with approved
material including dewatering etc. complete.

I Ordinary Soil

(i) Depth upto 3 m


For Abutment Cum 2 12.15 3.64 2.72 240.50
For Return Cum 4 4.15 2.767 2.72 124.89
Sub Total 365.39 1 365.39 146.00 53,347.03

3 2.6 Plain/Reinforced cement concrete in open


foundation complete as per drawing and
technical specifications.

A Using concrete mixer


(i) PCC Grade M15
Below foundation
For Abutment Cum 2 12.15 3.640 0.15 13.27
For Return Cum 4 4.15 2.767 0.15 6.89
Sub Total 20.16 1 20.16 4,613.00 92,987.15

4 2.6 Plain/Reinforced cement concrete in open


foundationcomplete as per drawing and
technical specifications.

A Using concrete mixer


(ii) PCC Grade M25
For Abutment Foundation Cum 2 12.00 3.490 0.200 16.75
Cum 2 12.00 3.190 0.200 15.31
Cum 2 12.00 2.790 0.400 26.78
Cum 2 12.00 2.390 0.400 22.94
Cum 2 12.00 0.400 0.400 1.92
Return wall Foundation Cum 4 4.00 2.617 0.400 16.75
Cum 4 4.00 2.317 0.400 14.83
Cum 4 4.00 2.117 0.400 13.55
Cum 4 4.00 0.200 0.400 0.64
Total 129.48 1 129.48 5,921.00 766,641.61

5 2.24 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in foundation complete as
per drawing and technical specifications as
per section 1600
Reinforcement @ 5kg/Cum MT 129.48 0.005 0.65 1 0.65 68,693.00 44,471.3

6 3.6 Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
as per drawing and technical
specifications section 1500, 1700 and
2200 (Newly laid concrete shall be covered
A by gunny
Height bags)
upto 5m
(a) Using concrete Mixer
(iii) P.C.C. Grade M-25
A Height upto 5m
For abutment Substructure Cum 2 12.0 1.345 2.90 93.48
For Return Wall Substructure Cum 4 4.0 1.31 3.40 71.10
Total 164.58 1 164.58 6,278.00 1,033,242.88
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

(ii) R.C.C. Grade M-25


Durt wall Cum 2 12.0 0.3 0.500 3.60
abutment Cap Cum 2 12.0 0.7 0.500 8.40
Bracket 2 12.0 Area= 0.032 0.78
Total 12.78 1 12.78 6,339.00 80,997.21

7 3.7 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bars
reinforcement in sub-structure complete as
per drawing and technical specifications
section 1600 and 2200.

Substructure Reinforcement @ 5kg/sqm MT 164.58 0.005 0.82


Abt cap, Dirt wall (70kg/cum) MT 12.78 0.07 0.89
Sub Total 1.72 1 1.7 69,002.0 118,499.87

8 4.1 Furnishing and Placing


Reinforced/Prestressed cement concrete in
super-structure as per drawing and
Technical Specification sections 1500, 1600
and 1700 (Newly laid concrete shall be
covered by gunny bags).
C RCC Grade M 30
(ii) Height UPTO 5m
I. Solid slab Super structure Cum 1.0 5.40 12.00 0.50 32.40 1 32.4 6,973.0 225,925.20

9 4.2 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in super-structurecomplete
as per drawing and technical specifications

Super structure@ 100kg/Cum MT 1 32.40 0.1 3.240


Total 3.240 1 3.24 70,101.00 227,127.24

10 3.8 Providing weep holes in Brick masonry/


Plain/ Reinforced concrete abutment, wing
wall/return wall with 100 mm dia. AC
pipe, extending through the full width of the
structure with slope of 1 V: 20 H towards
drawing face. Complete as per drawing and
Technical specifications section 2706 and
2200.

For abutment meter 2 11.00 1.35 29.59


For Return meter 4 3.50 1.31 18.00
Total Qty. 47.59 1 47.59 321.00 15,276.39

11 3.9 Back filling behind abutment, wing wall


and return wall complete as per drawing
and Technical specification 710.1.4 of I.R.C.
78 and 2200.
(i.) Granular Material Cum 2 7.77 2.90 1.68 37.78
Total Qty. 37.78 1 37.78 905.00 34,187.79

12 3.10 Providing and laying of Filter media with


granular materials/stone crushed
aggregates satisfying the requirements laid
down in clause 2504.2.2. of MORT&H
specifications to a thickness of not less
than 600 mm with smaller size towards
the soil and bigger size towards the wa ll
and provided over the entire surface behind
abutment, wing wall and return wall to
the full height compacted to a firm
condition complete as per drawing and
technical Specifications 710.1.4 of I.R.C. 78
and 2200

Cum 2 7.77 2.90 0.60 26.99


Cum 4 3.40 2.90 0.60 23.63
Total Qty. 50.62 1 50.62 1,926.00 97,493.66
13 3.17 Providing and fixing in position tar paper
bearing for slab as per approved drawings
and specification.
Sqm 2.00 12 0.40 9.60 1 9.60 66.00 633.60
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 12.00 0.50 12.00 1 12.00 1,204.00 14,448.00

15 4.10 PCC M15 Grade leveling course below


approach slab complete as per drawing and
Technical specification and as
per relevant section 2700 Cum 1.00 12.00 3.50 0.10 42.00 1 42.00 4,437.00 186,354.00

16 4.11 Providing and laying M-30 grade


Reinforced cement concrete approach slab
including reinforcement and formwork
complete as per drawing and Technical
specification and as per relevant sections
1500, 1600, 1700 and 2704
Cum 1.00 12.0 3.500 0.200 8.40 1 8.40 9,467.00 79,522.80

17 4.4 Providing and laying Cement concrete


wearing coat M-30 grade including
reinforcement complete as per drawing and
Technical Specifications as per relevant
clause of section 2700 Cum 1.00 12.00 12.40 0.075 11.16 1 11.16 11,847.00 132,212.52

18 4.9 Drainage Spouts complete as per drawing


and Technical specifications of section 2705
Each 2.00 2.00 1 2.00 2,007.00 4,014.00

19 5.4 Providing and laying Pitching on slopes laid


over prepared filter media including
boulder apron laid dry in front of toe of
embankment complete as per drawing
and Technical specifications as per section
2504
a) Stone/Boulder (All four side slopes ) Cum 1.00 Area= 223.22 0.30 66.97 1 66.97 2,413.00 161,591.49

20 5.5 Providing and laying Filter material


underneath pitching in slopes complete as
per drawing and Technical specification
including trimming of slopes to proper
profile and preparation of bed as per
section 2504.
Cum 1.00 Area= 223.22 0.15 33.48 1 33.48 2,079.00 69,612.25

21 4.27 Providing and fixing for hand railing top of


crash barrier in cluding cost of material
complete as per approved drawing Rmt 2 13.40 26.80 1 26.80 600.00 16,080.00

TOTAL COST (Rs.) 3,478,560.99


TOTAL COST (Cr.) 0.35
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF SLAB CULVERT BHS WIDENING
AT CH-4+200 SPAN = 1 X 6.00 M
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

1 2.1 Excavation for Structures Earth work in


excavation of foundation of structures as
per drawing and technical specification,
including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides
and bottom and backfilling with approved
material including dewatering etc. complete.

I Ordinary Soil

(i) Depth upto 3 m


For Abutment Cum 2 4.65 3.625 2.75 92.54
For Return Cum 4 4.65 2.63 2.75 134.28
Sub Total 226.82 1 226.82 146.00 33,115.83

2 2.6 Plain/Reinforced cement concrete in open


foundation complete as per drawing and
technical specifications.

A Using concrete mixer


(i) PCC Grade M15
Below foundation
For Abutment Cum 2 4.65 3.625 0.15 5.06
For Return Cum 4 4.65 2.630 0.15 7.34
Sub Total 12.39 1 12.39 4,613.00 57,176.17

3 2.6 Plain/Reinforced cement concrete in open


foundationcomplete as per drawing and
technical specifications.

A Using concrete mixer


(ii) PCC Grade M25
For Abutment Foundation Cum 2 4.50 3.475 0.200 6.26
Cum 2 4.50 3.175 0.200 5.72
Cum 2 4.50 2.875 0.400 10.35
Cum 2 4.50 2.475 0.400 8.91
Cum 2 4.50 0.400 0.400 0.72
Return wall Foundation Cum 4 4.50 2.480 0.400 17.86
Cum 4 4.50 2.180 0.400 15.70
Cum 4 4.50 1.980 0.400 14.26
Cum 4 4.50 0.200 0.400 0.72
Total 80.48 1 80.48 5,921.00 476,510.24

4 2.24 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in foundation complete as
per drawing and technical specifications as
per section 1600
Reinforcement @ 5kg/Cum MT 80.48 0.005 0.40 1 0.40 68,693.00 27,641.4

5 3.6 Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
as per drawing and technical
specifications section 1500, 1700 and
2200 (Newly laid concrete shall be covered
A Height upto 5m
(a) Using concrete Mixer
(iii) P.C.C. Grade M-25
A Height upto 5m
For abutment Substructure Cum 2 4.5 1.288 2.53 29.32
For Return Wall Substructure Cum 4 4.5 1.24 3.03 67.63
Total 96.95 1 96.95 6,278.00 608,626.83
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

(ii) R.C.C. Grade M-25


Durt wall Cum 2 4.5 0.3 0.600 1.62
abutment Cap Cum 2 4.5 0.7 0.500 3.15
Bracket 2 4.5 Area= 0.032 0.29
Total 5.06 1 5.06 6,339.00 32,085.48

6 3.7 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bars
reinforcement in sub-structure complete as
per drawing and technical specifications
section 1600 and 2200.

Substructure Reinforcement @ 5kg/sqm MT 96.95 0.005 0.48


Abt cap, Dirt wall (70kg/cum) MT 5.06 0.07 0.35
Sub Total 0.84 1 0.8 69,002.0 57,895.57

7 4.1 Furnishing and Placing


Reinforced/Prestressed cement concrete in
super-structure as per drawing and
Technical Specification sections 1500, 1600
and 1700 (Newly laid concrete shall be
covered by gunny bags).
C RCC Grade M 30
(ii) Height UPTO 5m
I. Solid slab Super structure Cum 1.0 6.40 4.50 0.60 17.28 1 17.3 6,973.0 120,493.44

8 4.2 Supplying, fitting and placing HSD (High


Strength Deformed Steel) bar
reinforcement in super-structurecomplete
as per drawing and technical specifications

Super structure@ 100kg/Cum MT 1 17.28 0.1 1.728


Total 1.728 1 1.73 70,101.00 121,134.53

9 3.8 Providing weep holes in Brick masonry/


Plain/ Reinforced concrete abutment, wing
wall/return wall with 100 mm dia. AC
pipe, extending through the full width of the
structure with slope of 1 V: 20 H towards
drawing face. Complete as per drawing and
Technical specifications section 2706 and
2200.

For abutment meter 2 3.50 1.29 9.01


For Return meter 4 4.00 1.24 20.00
Total Qty. 29.01 1 29.01 321.00 9,313.01

10 3.9 Back filling behind abutment, wing wall


and return wall complete as per drawing
and Technical specification 710.1.4 of I.R.C.
78 and 2200.
(i.) Granular Material Cum 2 0.54 2.53 1.47 2.00
Total Qty. 2.00 1 2.00 905.00 1,814.31

11 3.10 Providing and laying of Filter media with


granular materials/stone crushed
aggregates satisfying the requirements laid
down in clause 2504.2.2. of MORT&H
specifications to a thickness of not less
than 600 mm with smaller size towards
the soil and bigger size towards the wa ll
and provided over the entire surface behind
abutment, wing wall and return wall to
the full height compacted to a firm
condition complete as per drawing and
technical Specifications 710.1.4 of I.R.C. 78
and 2200

Cum 2 0.54 2.53 0.60 1.64


Cum 4 3.90 2.53 0.60 23.68
Total Qty. 25.32 1 25.32 1,926.00 48,766.78
12 3.17 Providing and fixing in position tar paper
bearing for slab as per approved drawings
and specification.
Sqm 2.00 12 0.40 9.60 1 9.60 66.00 633.60
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)

Filler joint
13 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 4.50 0.60 5.40 1 5.40 1,204.00 6,501.60

14 4.10 PCC M15 Grade leveling course below


approach slab complete as per drawing and
Technical specification and as
per relevant section 2700 Cum 1.00 12.00 3.50 0.10 42.00 1 42.00 4,437.00 186,354.00

15 4.11 Providing and laying M-30 grade


Reinforced cement concrete approach slab
including reinforcement and formwork
complete as per drawing and Technical
specification and as per relevant sections
1500, 1600, 1700 and 2704
Cum 1.00 12.0 3.500 0.200 8.40 1 8.40 9,467.00 79,522.80

16 4.4 Providing and laying Cement concrete


wearing coat M-30 grade including
reinforcement complete as per drawing and
Technical Specifications as per relevant
clause of section 2700 Cum 1.00 12.00 13.40 0.075 12.06 1 12.06 11,847.00 142,874.82

17 4.9 Drainage Spouts complete as per drawing


and Technical specifications of section 2705
Each 2.00 2.00 1 2.00 2,007.00 4,014.00

18 5.4 Providing and laying Pitching on slopes laid


over prepared filter media including
boulder apron laid dry in front of toe of
embankment complete as per drawing
and Technical specifications as per section
2504
a) Stone/Boulder (All four side slopes ) Cum 1.00 Area= 170.37 0.30 51.11 1 51.11 2,413.00 123,328.20

19 5.5 Providing and laying Filter material


underneath pitching in slopes complete as
per drawing and Technical specification
including trimming of slopes to proper
profile and preparation of bed as per
section 2504.
Cum 1.00 Area= 170.37 0.15 25.55 1 25.55 2,079.00 53,128.75

20 4.27 Providing and fixing for hand railing top of


crash barrier in cluding cost of material
complete as per approved drawing Rmt 2 15.40 30.80 1 30.80 600.00 18,480.00

TOTAL COST (Rs.) 2,209,411.34


TOTAL COST (Cr.) 0.22
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR REHABILATION OF SLAB (CANAL)

CH- 4+730 Size = 1 x 1.20 M


Sr. Item Length Width Thickness No. Of
ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Sealing of cracks/porous concrete by injection
process through nipples/Grouting complete as per
6.5

1
Technical specification.
1 20.000 KG 20.000 1 172.00 3440.00

2 8.8 Painting on Concrete Surfaces


Road A Two coats on new surfaces (Painting two coats after
SOR filling the surface with synthetic enamel paint in all shades
on new plastered concrete surfaces)
2 8.000 1.400 Sqm 22.400 1 62.00 1388.80

TOTAL 4828.80
Say ` 0.05 Lacs
Chhattisgarh Road Development Corporation Limited
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF MAJOR BRIDGE
BRIDGE AT CH - 1+455 KM. Span= 2 x10.0 m

No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100

For Abutment Cum 2.0 12.15 7.05 4.59 785.48 1 785.48


For Pier Cum 1.0 11.80 4.65 3.45 189.25 1 189.25
For Toe Wall Cum 1.0 50.0 1.70 0.60 51.00 1 51.00

I Ordinary soil
(i) Upto 3 m depth Cum 307.72 1 307.72 146.00 44,926.79

II Ordinary rock (not requiring blasting) Cum 410.29 1 410.29 246.00 100,931.43

III Hard rock (requiring blasting) Cum 307.72 1 307.72 802.00 246,789.65

Add extra 20% in the rates of above items for


dewatering (Assessment of dewatering shall be
made as per site condition ) 69544.22

Providing Plain cement concrete M-15


nominal mix in foundation as per relevant
2 2.6
clauses of sections 1500, 1700 and 2100. (Rate
may be taken as per items 12.5.)
(i) PCC Grade M15
Below foundation
For Abutment Cum 2.0 12.15 7.05 0.15 25.70
For Pier Cum 1.0 11.80 4.65 0.15 8.23
For Toe Wall Cum 1.0 50.00 1.70 0.10 8.50
Total 42.43 1 42.43 4613.00 195,719.21

(ii) PCC Grade M20 Cum 1.0 50.0 1.50 0.4 30.00
Cum 1.0 50.0 0.45 0.7 15.75
Total 45.75 1 45.75 5247.00 240,050.25

Provdiing and laying Plain/Reinforced


cement concrete in open foundation including
form work shuttering etc. complete as per
3 2.6
drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100
with .
A Using concrete mixer
(vii) RCC Grade M30
Base Slab Cum 2.0 6.90 12.00 0.30 49.68
Toe slab Cum 2.0 0.35 12.00 0.40 3.36
Pier Foundation Cum 1.0 11.50 4.50 0.85 43.99
Total 97.03 1 97.03 5992.00 581,388.78

Supplying, fitting and placing un-coated


HYSD bar reinforcement in foundation
8 2.24 complete as per drawing and technical
specifications and as per relevant clauses of
section 1600.
Reinforcement @ 100 kg/sqm MT 97.03 0.1 9.70
Sub Total 9.70 1 9.7 68693.00 666,511.01

C) SUBSTRUCTURE.

Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
5 3.6 as per drawing and technical specifications
section 1500, 1700 and 2200 (Newly laid
concrete shall be covered by gunny bags).
iii RCC Grade M30
E Height 5m to 10m
SIDE WALLS Cum 4.0 5.960 4.450 0.30 31.83
Cum 4.0 5.510 1.60 0.30 10.58
INTERMEDIATE SHORT WALL Cum 4.0 5.960 4.450 0.25 26.52
Cum 4.0 5.510 1.60 0.25 8.82
INTERMEDIATE LONG WALLS Cum 6.0 3.633 6.05 0.20 26.38
FRONT WALL Cum 2.0 12.00 0.30 4.45 32.04
REAR WALL Cum 2.0 12.00 0.30 6.05 43.56

PIER SHAFT RECTANGULAR Cum 1.0 10.20 4.65 1.00 47.42


PIER SHAFT CIRCULAR Cum 1.0 0.79 4.65 3.65
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
ABUTMENT CAP Cum 2.0 12.00 0.80 0.5 9.60
DIRT WALL Cum 2.0 12.00 0.30 1.60 11.52
PIER CAP Cum 1.0 11.50 1.60 0.50 9.20
PEDESTAL
For Abutment Cum 8.0 0.70 0.55 0.50 1.54
For Pier Cum 8.0 0.70 0.55 0.50 1.54

Total 264.190 1 264.190 6549.00 1,730,182.25

Supplying, fitting and placing HYSD bar


reinforcement in sub-structure complete as
6 3.7
perdrawing and technical specifications and as
per relevant clause of section 1600.
Substructure Reinforcement @ 100 kg/sqm MT 230.79 0.1 23.08
Abt & pier cap, Chairs, Approach slab & Dirt
wall (150kg/cum) MT 33.40 0.15 5.01
Sub Total 28.089 1 28.089 69002.00 1,938,199.22

Furnishing and Placing Reinforced /


Prestressed cement concrete in super-
7 4.1 structure as per drawing and Technical
Specification and as per relevant clauses of
sections 1500, 1700 and 2300 in
B RCC Grade M 30
(a) Using Concrete Mixer
(ii) Height 5m to 10m
I. Solid slab Super structure Cum 2.0 10.60 9.00 0.90 171.72 1 171.7 7554.00 1,297,172.88
Cum 2.0 10.60 Area= 0.450 9.54 1 9.5 7554.00 72,065.16

Supplying, fitting and placing HYSD bar


reinforcement in super-structure complete as
8 4.2
per drawing and technical specifications as per
relevant clauses of section 1600

Super structure@ 150kg/sqm MT 1.0 181.3 0.15 27.19


Total 27.19 1 27.19 70101.00 1,905,976.09

Back filling behind abutment, wing wall and


return wall complete as per drawing and
Technical specification and as per relevant
9 3.9 clauses 305 of specifications and as per
appendix
6 of IRC-78.

(i) Granular Material inside Box Cum 12.0 3.633 2.880 6.05 759.62
(ii) Back filling behind abutment, Cum 2.0 12.000 3.557 6.05 258.27
Total Qty. 1,017.88 1 1,017.88 905.00 921,184.97

Providing and laying of Filter media with


granular materials/stone crushed aggregates
satisfying the requirements laid down in clause
2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with smaller
10 3.10 size towards the soil and bigger size towards
the wall and provided over the entire surface
behind abutment, wing wall and return wall to
the full height compacted to a firm condition
complete as per drawing and technical
specification.
Behind abutment Cum 2.0 12.00 3.5 0.60 50.40
Total Qty. 50.40 1 50.40 1926.00 97,070.40

Supplying, fitting and fixing in position true


to line and level elastomeric bearing
conforming to IRC: 83 (Part-II) section IX and
11 3.14 clause 2005 of MORT&H specifications
complete including all accessories as per Per
drawing and Technical Specifications section cubic
2000 and 2200. CM 16.0 55.00 40.00 10.000 352,000.00 1 352,000.00 1.00 352,000.00

4.14 Filler joint


(ii) Providing & fixing 20 mm thick
compressible fibre board in expansion joint
12
complete as per drawing & Technical
Specification. Sqm 3.0 12.00 0.90 32.40 1 32.40 1204.00 39,009.60

PCC M15 Grade leveling course below


13 4.10 approach slab complete as per drawing and
Technical specification Cum 2.0 12.00 6.00 0.15 21.60 1 21.60 4437.00 95,839.20

Reinforced cement concrete approach slab


including reinforcement and formwork
14 4.11
complete as per drawing and Technical
specification Cum 2.0 12.00 6.000 0.300 43.20 1 43.20 9467.00 408,974.40
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
Providing and laying Cement concrete wearing
coat M-30 grade including reinforcement
15 4.4 complete as per drawing and Technical
Specifications as per relevant clause of section
2700. Cum 1.0 33.20 12.00 0.075 29.88 1 29.88 11847.00 353,988.36

Construction of RCC railing of M30 Grade in-


situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
16 4.6
between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post
for expansion, complete as per approved
drawings and technical specifications. (vide metre 2.0 33.20 66.40 1 66.40 1819.00 120,781.60
drawing No. SD/201, SD/304)
Painting on kerbs in black and yellow alternate
bands including cost of material and labour
17 4.20
complete as per drawings and specifications as
per clause 803. metre 2.0 33.20 66.40 1 66.40 56.00 3,718.40

Painting on concrete surface of R.C.C. Railing


(Providing and applying 2 coats of water based
cement paint to unplastered concrete surface
18 4.21
after cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying paint @ of 1
litre for 2 Sq.m. ) SQM 2.0 33.20 1.20 79.68 1 79.68 151.00 12,031.68

Drainage Spouts complete as per drawing and


19 4.9 Technical specification and as per clause 2705
of specifications. No. 2.0 4.00 8.00 1 8.00 2007.00 16,056.00

Providing and laying Pitching on slopes laid


over prepared filter media including boulder
20 5.4 apron laid dry in front of toe of embankment
complete as per drawing and Technical
specifications as per section 2504.
Cum 1.0 Area= 425.86 0.30 127.76 1 127.76 2413.00 308,280.05

Providing and laying Filter material


underneath pitching in slopes complete as
21 5.5 per drawing and Technical specification
including trimming of slopes to proper profile
and preparation of bed as per section 2504. Cum 1.0 Area= 425.86 0.15 63.88 1 63.88 2079.00 132,804.44

(ix) Removing all type of hume pipes and


stacking within a lead upto 1000 meters
22 1.4
including earthwork and dismantling of
masonry works around pipes.
A Up to 1000 mm dia Cum 6.0 8.00 48.00 1 48.00 400.00 19,200.00

Total cost (in Rs.) 11,970,396.04


Chhattisgarh Road Development Corporation Limited
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF MAJOR BRIDGE
BRIDGE AT CH - 8+066 KM. Span= 2 x10.0 m

No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100

For Abutment Cum 2.0 12.15 6.55 6.10 971.38 1 971.38


For Pier Cum 1.0 11.80 4.65 5.21 285.93 1 285.93
For Toe Wall Cum 1.0 65.0 1.70 0.60 66.30 1 66.30

I Ordinary soil
(i) Upto 3 m depth Cum 397.08 1 397.08 146.00 57,974.19

II Ordinary rock (not requiring blasting) Cum 661.81 1 661.81 246.00 162,804.22

III Hard rock (requiring blasting) Cum 264.72 1 264.72 802.00 212,307.30

Add extra 20% in the rates of above items for


dewatering (Assessment of dewatering shall be
made as per site condition ) 75022.30

Providing Plain cement concrete M-15


nominal mix in foundation as per relevant
2 2.6 clauses of sections 1500, 1700 and 2100. (Rate
may be taken as per items 12.5.)
(i) PCC Grade M15
Below foundation
For Abutment Cum 2.0 12.15 6.55 0.15 23.87
For Pier Cum 1.0 11.80 4.65 0.15 8.23
For Toe Wall Cum 1.0 65.00 1.70 0.10 11.05
Total 43.16 1 43.16 4613.00 199,075.17

(ii) PCC Grade M20 Cum 1.0 65.0 1.50 0.4 39.00
Cum 1.0 65.0 0.45 0.7 20.48
Total 59.48 1 59.48 5247.00 312,065.33

Provdiing and laying Plain/Reinforced


cement concrete in open foundation including
form work shuttering etc. complete as per
3 2.6
drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100
with .
A Using concrete mixer
(vii) RCC Grade M30
Base Slab Cum 2.0 6.40 12.00 0.30 46.08
Toe slab Cum 2.0 0.35 12.00 0.40 3.36
Pier Foundation Cum 1.0 11.50 4.50 0.85 43.99
Total 93.43 1 93.43 5992.00 559,817.58

Supplying, fitting and placing un-coated


HYSD bar reinforcement in foundation
8 2.24 complete as per drawing and technical
specifications and as per relevant clauses of
section 1600.
Reinforcement @ 100 kg/sqm MT 93.43 0.1 9.34
Sub Total 9.34 1 9.3 68693.00 641,781.53

C) SUBSTRUCTURE.

Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
5 3.6 as per drawing and technical specifications
section 1500, 1700 and 2200 (Newly laid
concrete shall be covered by gunny bags).
iii RCC Grade M30
E Height 5m to 10m
SIDE WALLS Cum 4.0 5.460 6.24 0.30 40.89
Cum 4.0 5.010 1.60 0.30 9.62
INTERMEDIATE SHORT WALL Cum 4.0 5.460 6.24 0.25 34.08
Cum 4.0 5.010 1.60 0.25 8.02
INTERMEDIATE LONG WALLS Cum 6.0 3.633 7.84 0.20 34.18
FRONT WALL Cum 2.0 12.00 0.30 6.24 44.94
REAR WALL Cum 2.0 12.00 0.30 7.84 56.46

PIER SHAFT RECTANGULAR Cum 1.0 10.20 7.47 1.00 76.15


PIER SHAFT CIRCULAR Cum 1.0 0.79 7.47 5.86
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
ABUTMENT CAP Cum 2.0 12.00 0.80 0.5 9.60
DIRT WALL Cum 2.0 12.00 0.30 1.60 11.52
PIER CAP Cum 1.0 11.50 1.60 0.50 9.20
PEDESTAL
For Abutment Cum 8.0 0.70 0.55 0.50 1.54
For Pier Cum 8.0 0.70 0.55 0.50 1.54

Total 343.593 1 343.593 6549.00 2,250,191.20

Supplying, fitting and placing HYSD bar


reinforcement in sub-structure complete as
6 3.7
perdrawing and technical specifications and as
per relevant clause of section 1600.
Substructure Reinforcement @ 100 kg/sqm MT 310.19 0.1 31.02
Abt & pier cap, Chairs, Approach slab & Dirt
wall (150kg/cum) MT 33.40 0.15 5.01
Sub Total 36.029 1 36.029 69002.00 2,486,094.44

Furnishing and Placing Reinforced /


Prestressed cement concrete in super-
7 4.1 structure as per drawing and Technical
Specification and as per relevant clauses of
sections 1500, 1700 and 2300 in
B RCC Grade M 30
(a) Using Concrete Mixer
(ii) Height 5m to 10m
I. Solid slab Super structure Cum 2.0 10.60 9.00 0.90 171.72 1 171.7 7554.00 1,297,172.88
Cum 2.0 10.60 Area= 0.450 9.54 1 9.5 7554.00 72,065.16

Supplying, fitting and placing HYSD bar


reinforcement in super-structure complete as
8 4.2
per drawing and technical specifications as per
relevant clauses of section 1600

Super structure@ 150kg/sqm MT 1.0 181.3 0.15 27.19


Total 27.19 1 27.19 70101.00 1,905,976.09

Back filling behind abutment, wing wall and


return wall complete as per drawing and
Technical specification and as per relevant
9 3.9 clauses 305 of specifications and as per
appendix
6 of IRC-78.

(i) Granular Material inside Box Cum 12.0 3.633 2.630 7.84 899.03
(ii) Back filling behind abutment, Cum 2.0 12.000 4.611 7.84 433.81
Total Qty. 1,332.84 1 1,332.84 905.00 1,206,221.30

Providing and laying of Filter media with


granular materials/stone crushed aggregates
satisfying the requirements laid down in clause
2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with smaller
10 3.10 size towards the soil and bigger size towards
the wall and provided over the entire surface
behind abutment, wing wall and return wall to
the full height compacted to a firm condition
complete as per drawing and technical
specification.
Behind abutment Cum 2.0 12.00 4.5 0.60 64.80
Total Qty. 64.80 1 64.80 1926.00 124,804.80

Supplying, fitting and fixing in position true


to line and level elastomeric bearing
conforming to IRC: 83 (Part-II) section IX and
11 3.14 clause 2005 of MORT&H specifications
complete including all accessories as per Per
drawing and Technical Specifications section cubic
2000 and 2200. CM 16.0 55.00 40.00 10.000 352,000.00 1 352,000.00 1.00 352,000.00

4.14 Filler joint


(ii) Providing & fixing 20 mm thick
compressible fibre board in expansion joint
12
complete as per drawing & Technical
Specification. Sqm 3.0 12.00 0.90 32.40 1 32.40 1204.00 39,009.60

PCC M15 Grade leveling course below


approach slab complete as per drawing and
13 4.10
Technical specification
Cum 2.0 12.00 5.50 0.15 19.80 1 19.80 4437.00 87,852.60

Reinforced cement concrete approach slab


including reinforcement and formwork
14 4.11
complete as per drawing and Technical
specification Cum 2.0 12.00 5.500 0.300 39.60 1 39.60 9467.00 374,893.20
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
Providing and laying Cement concrete wearing
coat M-30 grade including reinforcement
15 4.4 complete as per drawing and Technical
Specifications as per relevant clause of section
2700. Cum 1.0 32.20 12.00 0.075 28.98 1 28.98 11847.00 343,326.06

Construction of RCC railing of M30 Grade in-


situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
16 4.6
between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post
for expansion, complete as per approved
drawings and technical specifications. (vide metre 2.0 32.20 64.40 1 64.40 1819.00 117,143.60
drawing No. SD/201, SD/304)
Painting on kerbs in black and yellow alternate
bands including cost of material and labour
17 4.20
complete as per drawings and specifications as
per clause 803. metre 2.0 32.20 64.40 1 64.40 56.00 3,606.40

Painting on concrete surface of R.C.C. Railing


(Providing and applying 2 coats of water based
cement paint to unplastered concrete surface
18 4.21
after cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying paint @ of 1
litre for 2 Sq.m. ) SQM 2.0 32.20 1.20 77.28 1 77.28 151.00 11,669.28

Drainage Spouts complete as per drawing and


19 4.9 Technical specification and as per clause 2705
of specifications. No. 2.0 4.00 8.00 1 8.00 2007.00 16,056.00

Providing and laying Pitching on slopes laid


over prepared filter media including boulder
20 5.4 apron laid dry in front of toe of embankment
complete as per drawing and Technical
specifications as per section 2504.
Cum 1.0 Area= 665.40 0.30 199.62 1 199.62 2413.00 481,683.06

Providing and laying Filter material


underneath pitching in slopes complete as
21 5.5 per drawing and Technical specification
including trimming of slopes to proper profile
and preparation of bed as per section 2504. Cum 1.0 Area= 665.40 0.15 99.81 1 99.81 2079.00 207,504.99

(ix) Removing all type of hume pipes and


stacking within a lead upto 1000 meters
22 1.4
including earthwork and dismantling of
masonry works around pipes.
A Up to 1000 mm dia Cum 5.0 8.00 40.00 1 40.00 400.00 16,000.00

Total cost (in Rs.) 13,614,118.27


Chhattisgarh Road Development Corporation Limited
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF MAJOR BRIDGE
BRIDGE AT CH -11+524 KM. Span= 2 x10.0 m

No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100

For Abutment Cum 2.0 12.15 6.55 4.89 777.52 1 777.52


For Pier Cum 1.0 11.80 4.65 3.15 172.84 1 172.84
For Toe Wall Cum 1.0 65.0 1.70 0.60 66.30 1 66.30

I Ordinary soil
(i) Upto 3 m depth Cum 305.00 1 305.00 146.00 44,529.77

II Ordinary rock (not requiring blasting) Cum 508.33 1 508.33 246.00 125,049.37

III Hard rock (requiring blasting) Cum 203.33 1 203.33 802.00 163,072.51

Add extra 20% in the rates of above items for


dewatering (Assessment of dewatering shall be
made as per site condition ) 57624.38

Providing Plain cement concrete M-15


nominal mix in foundation as per relevant
2 2.6 clauses of sections 1500, 1700 and 2100. (Rate
may be taken as per items 12.5.)
(i) PCC Grade M15
Below foundation
For Abutment Cum 2.0 12.15 6.55 0.15 23.87
For Pier Cum 1.0 11.80 4.65 0.15 8.23
For Toe Wall Cum 1.0 65.00 1.70 0.10 11.05
Total 43.16 1 43.16 4613.00 199,075.17

(ii) PCC Grade M20 Cum 1.0 65.0 1.50 0.4 39.00
Cum 1.0 65.0 0.45 0.7 20.48
Total 59.48 1 59.48 5247.00 312,065.33

Provdiing and laying Plain/Reinforced


cement concrete in open foundation including
form work shuttering etc. complete as per
3 2.6
drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100
with .
A Using concrete mixer
(vii) RCC Grade M30
Base Slab Cum 2.0 6.40 12.00 0.30 46.08
Toe slab Cum 2.0 0.35 12.00 0.40 3.36
Pier Foundation Cum 1.0 11.50 4.50 0.85 43.99
Total 93.43 1 93.43 5992.00 559,817.58

Supplying, fitting and placing un-coated


HYSD bar reinforcement in foundation
8 2.24 complete as per drawing and technical
specifications and as per relevant clauses of
section 1600.
Reinforcement @ 100 kg/sqm MT 93.43 0.1 9.34
Sub Total 9.34 1 9.3 68693.00 641,781.53

C) SUBSTRUCTURE.

Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
5 3.6 as per drawing and technical specifications
section 1500, 1700 and 2200 (Newly laid
concrete shall be covered by gunny bags).
iii RCC Grade M30
E Height 5m to 10m
SIDE WALLS Cum 4.0 5.460 4.65 0.30 30.47
Cum 4.0 5.010 1.60 0.30 9.62
INTERMEDIATE SHORT WALL Cum 4.0 5.460 4.65 0.25 25.39
Cum 4.0 5.010 1.60 0.25 8.02
INTERMEDIATE LONG WALLS Cum 6.0 3.633 6.25 0.20 27.25
FRONT WALL Cum 2.0 12.00 0.30 4.65 33.48
REAR WALL Cum 2.0 12.00 0.30 6.25 45.00

PIER SHAFT RECTANGULAR Cum 1.0 10.20 5.10 1.00 52.02


PIER SHAFT CIRCULAR Cum 1.0 0.79 5.10 4.01
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
ABUTMENT CAP Cum 2.0 12.00 0.80 0.5 9.60
DIRT WALL Cum 2.0 12.00 0.30 1.60 11.52
PIER CAP Cum 1.0 11.50 1.60 0.50 9.20
PEDESTAL
For Abutment Cum 8.0 0.70 0.55 0.50 1.54
For Pier Cum 8.0 0.70 0.55 0.50 1.54

Total 268.644 1 268.644 6549.00 1,759,349.76

Supplying, fitting and placing HYSD bar


reinforcement in sub-structure complete as
6 3.7
perdrawing and technical specifications and as
per relevant clause of section 1600.
Substructure Reinforcement @ 100 kg/sqm MT 235.24 0.1 23.52
Abt & pier cap, Chairs, Approach slab & Dirt
wall (150kg/cum) MT 33.40 0.15 5.01
Sub Total 28.534 1 28.534 69002.00 1,968,930.88

Furnishing and Placing Reinforced /


Prestressed cement concrete in super-
7 4.1 structure as per drawing and Technical
Specification and as per relevant clauses of
sections 1500, 1700 and 2300 in
B RCC Grade M 30
(a) Using Concrete Mixer
(ii) Height 5m to 10m
I. Solid slab Super structure Cum 2.0 10.60 9.00 0.90 171.72 1 171.7 7554.00 1,297,172.88
Cum 2.0 10.60 Area= 0.450 9.54 1 9.5 7554.00 72,065.16

Supplying, fitting and placing HYSD bar


reinforcement in super-structure complete as
8 4.2
per drawing and technical specifications as per
relevant clauses of section 1600

Super structure@ 150kg/sqm MT 1.0 181.3 0.15 27.19


Total 27.19 1 27.19 70101.00 1,905,976.09

Back filling behind abutment, wing wall and


return wall complete as per drawing and
Technical specification and as per relevant
9 3.9 clauses 305 of specifications and as per
appendix
6 of IRC-78.

(i) Granular Material inside Box Cum 12.0 3.633 2.630 6.25 716.61
(ii) Back filling behind abutment, Cum 2.0 12.000 3.675 6.25 275.62
Total Qty. 992.23 1 992.23 905.00 897,972.00

Providing and laying of Filter media with


granular materials/stone crushed aggregates
satisfying the requirements laid down in clause
2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with smaller
10 3.10 size towards the soil and bigger size towards
the wall and provided over the entire surface
behind abutment, wing wall and return wall to
the full height compacted to a firm condition
complete as per drawing and technical
specification.
Behind abutment Cum 2.0 12.00 1.9 0.60 27.22
Total Qty. 27.22 1 27.22 1926.00 52,418.02

Supplying, fitting and fixing in position true


to line and level elastomeric bearing
conforming to IRC: 83 (Part-II) section IX and
11 3.14 clause 2005 of MORT&H specifications
complete including all accessories as per Per
drawing and Technical Specifications section cubic
2000 and 2200. CM 16.0 55.00 40.00 10.000 352,000.00 1 352,000.00 1.00 352,000.00

4.14 Filler joint


(ii) Providing & fixing 20 mm thick
compressible fibre board in expansion joint
12
complete as per drawing & Technical
Specification. Sqm 3.0 12.00 0.90 32.40 1 32.40 1204.00 39,009.60

PCC M15 Grade leveling course below


approach slab complete as per drawing and
13 4.10
Technical specification
Cum 2.0 12.00 5.50 0.15 19.80 1 19.80 4437.00 87,852.60

Reinforced cement concrete approach slab


including reinforcement and formwork
14 4.11
complete as per drawing and Technical
specification Cum 2.0 12.00 5.500 0.300 39.60 1 39.60 9467.00 374,893.20
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
Providing and laying Cement concrete wearing
coat M-30 grade including reinforcement
15 4.4 complete as per drawing and Technical
Specifications as per relevant clause of section
2700. Cum 1.0 32.20 12.00 0.075 28.98 1 28.98 11847.00 343,326.06

Construction of RCC railing of M30 Grade in-


situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
16 4.6
between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post
for expansion, complete as per approved
drawings and technical specifications. (vide metre 2.0 32.20 64.40 1 64.40 1819.00 117,143.60
drawing No. SD/201, SD/304)
Painting on kerbs in black and yellow alternate
bands including cost of material and labour
17 4.20
complete as per drawings and specifications as
per clause 803. metre 2.0 32.20 64.40 1 64.40 56.00 3,606.40

Painting on concrete surface of R.C.C. Railing


(Providing and applying 2 coats of water based
cement paint to unplastered concrete surface
18 4.21
after cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying paint @ of 1
litre for 2 Sq.m. ) SQM 2.0 32.20 1.20 77.28 1 77.28 151.00 11,669.28

Drainage Spouts complete as per drawing and


19 4.9 Technical specification and as per clause 2705
of specifications. No. 2.0 4.00 8.00 1 8.00 2007.00 16,056.00

Providing and laying Pitching on slopes laid


over prepared filter media including boulder
20 5.4 apron laid dry in front of toe of embankment
complete as per drawing and Technical
specifications as per section 2504. Cum 1.0 Area= 665.50 0.30 199.65 1 199.65 2413.00 481,755.45

Providing and laying Filter material


underneath pitching in slopes complete as
21 5.5 per drawing and Technical specification
including trimming of slopes to proper profile
and preparation of bed as per section 2504. Cum 1.0 Area= 665.50 0.15 99.83 1 99.83 2079.00 207,536.18

(ix) Removing all type of hume pipes and


stacking within a lead upto 1000 meters
22 1.4
including earthwork and dismantling of
masonry works around pipes.
B Up to 1000 mm dia Cum 7.0 8.00 56.00 1 56.00 400.00 22,400.00

Total cost (in Rs.) 12,114,148.77


Chhattisgarh Road Development Corporation Limited
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF MAJOR BRIDGE
BRIDGE AT CH - 8+478 KM. Span= 2 x10.0 m

No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100

For Abutment Cum 2.0 12.15 6.55 6.20 986.98 1 986.98


For Pier Cum 1.0 11.80 4.65 5.49 301.24 1 301.24
For Toe Wall Cum 1.0 65.0 1.70 0.60 66.30 1 66.30

I Ordinary soil
(i) Upto 3 m depth Cum 406.36 1 406.36 146.00 59,327.91

II Ordinary rock (not requiring blasting) Cum 677.26 1 677.26 246.00 166,605.77

III Hard rock (requiring blasting) Cum 270.90 1 270.90 802.00 217,264.76

Add extra 20% in the rates of above items for


dewatering (Assessment of dewatering shall be
made as per site condition ) 76774.11

Providing Plain cement concrete M-15


nominal mix in foundation as per relevant
2 2.6 clauses of sections 1500, 1700 and 2100. (Rate
may be taken as per items 12.5.)
(i) PCC Grade M15
Below foundation
For Abutment Cum 2.0 12.15 6.55 0.15 23.87
For Pier Cum 1.0 11.80 4.65 0.15 8.23
For Toe Wall Cum 1.0 65.00 1.70 0.10 11.05
Total 43.16 1 43.16 4613.00 199,075.17

(ii) PCC Grade M20 Cum 1.0 65.0 1.50 0.4 39.00
Cum 1.0 65.0 0.45 0.7 20.48
Total 59.48 1 59.48 5247.00 312,065.33

Provdiing and laying Plain/Reinforced


cement concrete in open foundation including
form work shuttering etc. complete as per
3 2.6
drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100
with .
A Using concrete mixer
(vii) RCC Grade M30
Base Slab Cum 2.0 6.40 12.00 0.30 46.08
Toe slab Cum 2.0 0.35 12.00 0.40 3.36
Pier Foundation Cum 1.0 11.50 4.50 0.85 43.99
Total 93.43 1 93.43 5992.00 559,817.58

Supplying, fitting and placing un-coated


HYSD bar reinforcement in foundation
8 2.24 complete as per drawing and technical
specifications and as per relevant clauses of
section 1600.
Reinforcement @ 100 kg/sqm MT 93.43 0.1 9.34
Sub Total 9.34 1 9.34 68693.00 641,781.53

C) SUBSTRUCTURE.

Providing and laying Plain/Reinforced


cement concrete in sub-structure complete
5 3.6 as per drawing and technical specifications
section 1500, 1700 and 2200 (Newly laid
concrete shall be covered by gunny bags).
iii RCC Grade M30
E Height 5m to 10m
SIDE WALLS Cum 4.0 5.460 6.80 0.30 44.55
Cum 4.0 5.010 1.60 0.30 9.62
INTERMEDIATE SHORT WALL Cum 4.0 5.460 6.80 0.25 37.13
Cum 4.0 5.010 1.60 0.25 8.02
INTERMEDIATE LONG WALLS Cum 6.0 3.633 8.40 0.20 36.62
FRONT WALL Cum 2.0 12.00 0.30 6.80 48.96
REAR WALL Cum 2.0 12.00 0.30 8.40 60.48

PIER SHAFT RECTANGULAR Cum 1.0 10.20 7.57 1.00 77.21


PIER SHAFT CIRCULAR Cum 1.0 0.79 7.57 5.95
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
ABUTMENT CAP Cum 2.0 12.00 0.80 0.5 9.60
DIRT WALL Cum 2.0 12.00 0.30 1.60 11.52
PIER CAP Cum 1.0 11.50 1.60 0.50 9.20
PEDESTAL
For Abutment Cum 8.0 0.70 0.55 0.50 1.54
For Pier Cum 8.0 0.70 0.55 0.50 1.54

Total 361.937 1 361.937 6549.00 2,370,324.78

Supplying, fitting and placing HYSD bar


reinforcement in sub-structure complete as
6 3.7
perdrawing and technical specifications and as
per relevant clause of section 1600.
Substructure Reinforcement @ 100 kg/sqm MT 328.54 0.1 32.85
Abt & pier cap, Chairs, Approach slab & Dirt
wall (150kg/cum) MT 33.40 0.15 5.01
Sub Total 37.864 1 37.864 69002.00 2,612,670.37

Furnishing and Placing Reinforced /


Prestressed cement concrete in super-
7 4.1 structure as per drawing and Technical
Specification and as per relevant clauses of
sections 1500, 1700 and 2300 in
B RCC Grade M 30
(a) Using Concrete Mixer
(ii) Height 5m to 10m
I. Solid slab Super structure Cum 2.0 10.60 9.00 0.90 171.72 1 171.7 7554.00 1,297,172.88
Cum 2.0 10.60 Area= 0.450 9.54 1 9.5 7554.00 72,065.16

Supplying, fitting and placing HYSD bar


reinforcement in super-structure complete as
8 4.2
per drawing and technical specifications as per
relevant clauses of section 1600

Super structure@ 150kg/sqm MT 1.0 181.3 0.15 27.19


Total 27.19 1 27.19 70101.00 1,905,976.09

Back filling behind abutment, wing wall and


return wall complete as per drawing and
Technical specification and as per relevant
9 3.9 clauses 305 of specifications and as per
appendix
6 of IRC-78.

(i) Granular Material inside Box Cum 12.0 3.633 2.630 8.40 963.12
(ii) Back filling behind abutment, Cum 2.0 12.000 4.939 8.40 497.87
Total Qty. 1,460.99 1 1,460.99 905.00 1,322,199.74

Providing and laying of Filter media with


granular materials/stone crushed aggregates
satisfying the requirements laid down in clause
2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with smaller
10 3.10 size towards the soil and bigger size towards
the wall and provided over the entire surface
behind abutment, wing wall and return wall to
the full height compacted to a firm condition
complete as per drawing and technical
specification.
Behind abutment Cum 2.0 12.00 4.5 0.60 64.80
Total Qty. 64.80 1 64.80 1926.00 124,804.80

Supplying, fitting and fixing in position true


to line and level elastomeric bearing
conforming to IRC: 83 (Part-II) section IX and
11 3.14 clause 2005 of MORT&H specifications
complete including all accessories as per Per
drawing and Technical Specifications section cubic
2000 and 2200. CM 16.0 55.00 40.00 10.000 352,000.00 1 352,000.00 1.00 352,000.00

4.14 Filler joint


(ii) Providing & fixing 20 mm thick
compressible fibre board in expansion joint
12
complete as per drawing & Technical
Specification. Sqm 3.0 12.00 0.90 32.40 1 32.40 1204.00 39,009.60

PCC M15 Grade leveling course below


approach slab complete as per drawing and
13 4.10
Technical specification
Cum 2.0 12.00 5.50 0.15 19.80 1 19.80 4437.00 87,852.60

Reinforced cement concrete approach slab


including reinforcement and formwork
14 4.11
complete as per drawing and Technical
specification Cum 2.0 12.00 5.500 0.300 39.60 1 39.60 9467.00 374,893.20
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
Providing and laying Cement concrete wearing
coat M-30 grade including reinforcement
15 4.4 complete as per drawing and Technical
Specifications as per relevant clause of section
2700. Cum 1.0 32.20 12.00 0.075 28.98 1 28.98 11847.00 343,326.06

Construction of RCC railing of M30 Grade in-


situ with 20 mm nominal size aggregate, true to
line and grade, tolerance of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
16 4.6
between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post
for expansion, complete as per approved
drawings and technical specifications. (vide metre 2.0 32.20 64.40 1 64.40 1819.00 117,143.60
drawing No. SD/201, SD/304)
Painting on kerbs in black and yellow alternate
bands including cost of material and labour
17 4.20
complete as per drawings and specifications as
per clause 803. metre 2.0 32.20 64.40 1 64.40 56.00 3,606.40

Painting on concrete surface of R.C.C. Railing


(Providing and applying 2 coats of water based
cement paint to unplastered concrete surface
18 4.21
after cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying paint @ of 1
litre for 2 Sq.m. ) SQM 2.0 32.20 1.20 77.28 1 77.28 151.00 11,669.28

Drainage Spouts complete as per drawing and


19 4.9 Technical specification and as per clause 2705
of specifications. No. 2.0 4.00 8.00 1 8.00 2007.00 16,056.00

Providing and laying Pitching on slopes laid


over prepared filter media including boulder
20 5.4 apron laid dry in front of toe of embankment
complete as per drawing and Technical
specifications as per section 2504.
Cum 1.0 Area= 665.40 0.30 199.62 1 199.62 2413.00 481,683.06

Providing and laying Filter material


underneath pitching in slopes complete as
21 5.5 per drawing and Technical specification
including trimming of slopes to proper profile
and preparation of bed as per section 2504. Cum 1.0 Area= 665.40 0.15 99.81 1 99.81 2079.00 207,504.99

(ix) Removing all type of hume pipes and


stacking within a lead upto 1000 meters
22 1.4
including earthwork and dismantling of
masonry works around pipes.
A Up to 1000 mm dia Cum 5.0 8.00 40.00 1 40.00 400.00 16,000.00

Total cost (in Rs.) 13,988,670.76