PCC Grade M 15
a)
Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688 28 3768.00 283594.75
PCC M20
a)
For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 Area = 1.629 Cum -2.687
Sub Total 25.719 28 4174.00 3005855.20
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 28 2413.00 713475.84
Sr. Item Length Width Thickness No. Of
ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
CH- 9- 9.12
Technical specification including trimming of slopes
7
to proper profile and preparation of bed and as per
clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 28 2079.00 307359.36
9
dismantling of masonry works around pipes.
TOTAL 8975149.01
Say ` 89.75 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR RE-CONSTRUCTION OF HPC ON PROJECT ROAD
AT Ch-0+935, Ch-7+731, Ch-10+653, Ch-11+991, Ch-16+920, Ch-21+729, Ch-22+948, Ch-24+660, Ch-24+830, Ch-26+260
Formation Width = 12.0 m Size = 1 x 1200
SOR
Sr. Length Width Thickness No. Of
Item ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. (M) (M) (M) Structure
No.
1 Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
CH- 9- 9.1
PCC Grade M 15
Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688
Under Pipe (Base Concrete) 1 12.000 2.040 0.100 Cum 2.448
PCC M20
a)
For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 1.629 Cum -2.687
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 10 2413.00 254812.80
Formation Width = 12.0 m Size = 1 x 1200
SOR
Sr. Length Width Thickness No. Of
Item ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. (M) (M) (M) Structure
No.
7 Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
CH- 9- 9.12
Technical specification including trimming of
slopes to proper profile and preparation of bed
and as per clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 10 2079.00 109771.20
TOTAL 4486628.33
Say ` 44.87 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR RE-CONSTRUCTION OF HPC ON PROJECT ROAD
AT Ch-6+360, Ch-19+460, Ch-20+922, Ch-21+322, Ch-22+135
Formation Width = 12.0 m Size = 2 x 1200
a) PCC Grade M 15
Under head wall (Base Concrete) 2 8.100 1.400 0.150 Cum 3.402 5 3768.00 64093.68
a) PCC M15
For Headwall
Average breath
(0.4+1.25)/2=0.825 2 8.100 0.825 2.690 Cum 35.952
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 4 -0.825 1.629 Cum -5.374
Sub Total 30.577 5 3768.00 576079.43
Providing and fixing guard stones 200 x 200 x 900
mm made of precast RCC M-20 grade fixed at 300 mm
CH- 4 -4.17
CH- 9 -9.12
Technical specification including trimming of slopes
7
to proper profile and preparation of bed and as per
clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 5 2079.00 54885.60
TOTAL 2393665.560
Say ` 23.94 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR LHS WIDENING OF HPC ON PROJECT ROAD
AT Ch-19+180
Formation Width = 12.0 m Size = 1 x 1200
PCC Grade M 15
a)
Under head wall (Base Concrete) 1 6.400 1.400 0.150 Cum 1.344 1 3768.00 5064.19
PCC M20
a)
For Headwall
Average breath
(0.40+1.25)/2=0.825 1 6.400 0.825 2.690 Cum 14.203
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 1 -0.825 Area = 1.629 Cum -1.344
Sub Total 12.860 1 4174.00 53675.99
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 1 2413.00 25481.28
Sr. Item Length Width Thickness No. Of
ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) (M) Structure
Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
CH- 9- 9.12
Technical specification including trimming of slopes
7
to proper profile and preparation of bed and as per
clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 1 2079.00 10977.12
a) PCC Grade M 15
Under head wall (Base Concrete) 2 9.300 1.400 0.150 Cum 3.906 1 3768.00 14717.81
a) PCC M15
For Headwall
Average breath
(0.4+1.25)/2=0.825 2 9.300 0.825 2.690 Cum 41.278
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 6 -0.825 1.629 Cum -8.062
Sub Total 33.216 1 3768.00 125159.67
CH- 9 -9.12
pitching in slopes complete as per drawing and
7 Technical specification including trimming of slopes
to proper profile and preparation of bed and as per
clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 1 2079.00 10977.12
TOTAL 498255.851
Say ` 4.98 Lacs
CHHATTISGARH ROAD DEVLELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR LHS WIDEINING OF CROSS DRAINAGE STRUCTURES
Formation Width = 12.0 m Size = 4 x 1000
AT CH- 2+482
SOR
Sr. Length Width Thickness No. Of
ITEM ITEM No. Unit Quantity Rate (Rs) Amount (Rs)
No. (M) (M) (M) Structure
NO.
1 Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out,construction of shoring and bracing,
9.1
PCC Grade M 15
a)
Under head wall (Base Concrete) 1 12.500 1.400 0.150 Cum 2.625 1 3768.00 9891.00
4
x 400 x 400 mm and given two coats of paint with
white and black bands including excavation.
TOTAL 397112.42
Say ` 3.97 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR NEW- CONSTRUCTION OF HPC ON PROJECT ROAD
AT CH-6+200
Formation Width = 12.0 m Size = 1 x 1200
PCC Grade M 15
a)
Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688 1 3768.00 10128.38
PCC M20
a)
For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 Area = 1.629 Cum -2.687
Sub Total 25.719 1 4174.00 107351.97
U/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
D/S (Half cone volume) 0.5 Area= 35.200 0.300 Cum 5.280
Sub Total 10.560 1 2413.00 25481.28
Sr. Item Length Width No. Of
ITEM No 3.000 Unit Quantity Rate (Rs) Amount (Rs)
No. No. (M) (M) Structure
Providing and laying Filter material underneath
CH- 9- 9.12
pitching in slopes complete as per drawing and
7 Technical specification including trimming of slopes
to proper profile and preparation of bed and as per
clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 1 2079.00 10977.12
TOTAL 322863.58
Say ` 3.23 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE FOR NEW- CONSTRUCTION OF HPC ON JUNCTIONS
Provide New 16 No. HPC at Junctions
Size = 1 x 1200
Ordinary soil
A Mechanical Means
Depth Upto 3M
Under head wall 2 6.400 1.400 0.920 Cum 16.486
Under pipe 1 27.200 2.040 2.290 Cum 127.068
Apron U/S 1 6.400 1.500 0.300 Cum 2.880
Apron D/S 1 6.400 3.000 0.300 Cum 5.760
Sub Total 152.194 16 146.00 355525.00
PCC Grade M 15
Under head wall (Base Concrete) 2 6.400 1.400 0.150 Cum 2.688 16 3768.00 162054.14
3
and Technical Specifications
PCC M20
For Headwall
Average breath
(0.40+1.25)/2=0.825 2 6.400 0.825 2.690 Cum 28.406
Deduction of pipes
Area of pipe
3.14/4X(1.44)2=1.629 2 -0.825 1.629 Cum -2.687
Sub Total 25.719 16 4174.00 1717631.54
CH- 9-9.12
Technical specification including trimming of
7
slopes to proper profile and preparation of bed
and as per clause 2504.
U/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
D/S (Half cone base Area) 0.5 Area= 35.200 0.150 Cum 2.640
Sub Total 5.280 16 2079.00 175633.92
TOTAL 7493110.20
Say ` 74.93 Lacs
CHHATTISGARH ROAD DEVELOPMENT CORPORATION LIMITED
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF SLAB CULVERT
AT CH- 3+180 SPAN = 1 X 2.00 M
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)
(B ) Cement Concrete Grade M-15 & M-20 RM 1 1.5 7.5 1.5 16.88 1 16.88 348.00 5,872.50
A Height upto 5m
(a) Using concrete Mixer
(iii) P.C.C. Grade M-25
A Height upto 5m
For abutment Substructure Cum 2 12.0 1.165 0.96 26.90
For Return Wall Substructure Cum 4 3.5 1.10 1.46 22.57
Total 49.46 1 49.46 6,278.00 310,531.79
(ii) R.C.C. Grade M-25
Durt wall Cum 2 12.0 0.3 0.250 1.80
abutment Cap Cum 2 12.0 0.7 0.500 8.40
Bracket 2 12.0 Area= 0.032 0.78
Total 10.98 1 10.98 6,339.00 69,587.01
Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 12.00 0.25 6.00 1 6.00 1,204.00 7,224.00
(B ) Cement Concrete Grade M-15 & M-20 RM 1 1.5 7.5 1.5 16.88 1 16.88 348.00 5,872.50
I Ordinary Soil
Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 12.00 0.25 6.00 1 6.00 1,204.00 7,224.00
S.No. SOR Item Description Unit No. Length Width (m) Depth Quantity No. of Total
No. (m) (m) str. Quantity Rate (Rs.) Amount (Rs.)
(B ) Cement Concrete Grade M-15 & M-20 RM 1 1.5 7.5 1.5 16.88 1 16.88 348.00 5,872.50
A Height upto 5m
For abutment Substructure Cum 2 12.0 1.238 1.97 58.57
For Return Wall Substructure Cum 4 3.5 1.19 2.47 41.01
Total 99.58 1 99.58 6,278.00 625,156.21
(ii) R.C.C. Grade M-25
Durt wall Cum 2 12.0 0.3 0.250 1.80
abutment Cap Cum 2 12.0 0.7 0.500 8.40
Bracket 2 12.0 Area= 0.032 0.78
Total 10.98 1 10.98 6,339.00 69,587.01
Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete
as per drawing & Technical Specification
Sqm 2 12.00 0.25 6.00 1 6.00 1,204.00 7,224.00
I Ordinary Soil
Filler joint
14 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 12.00 0.50 12.00 1 12.00 1,204.00 14,448.00
I Ordinary Soil
Filler joint
13 4.14 (B) Providing & fixing 20 mm thick
compressible fiber board (12 m long x 25
cm deep ) in expansion joint complete as
per drawing & Technical Specification
Sqm 2 4.50 0.60 5.40 1 5.40 1,204.00 6,501.60
1
Technical specification.
1 20.000 KG 20.000 1 172.00 3440.00
TOTAL 4828.80
Say ` 0.05 Lacs
Chhattisgarh Road Development Corporation Limited
KAWARDHA- RAMPUR- KHAMHRIYA- ROAD
COST ESTIMATE OF MAJOR BRIDGE
BRIDGE AT CH - 1+455 KM. Span= 2 x10.0 m
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100
I Ordinary soil
(i) Upto 3 m depth Cum 307.72 1 307.72 146.00 44,926.79
II Ordinary rock (not requiring blasting) Cum 410.29 1 410.29 246.00 100,931.43
III Hard rock (requiring blasting) Cum 307.72 1 307.72 802.00 246,789.65
(ii) PCC Grade M20 Cum 1.0 50.0 1.50 0.4 30.00
Cum 1.0 50.0 0.45 0.7 15.75
Total 45.75 1 45.75 5247.00 240,050.25
C) SUBSTRUCTURE.
(i) Granular Material inside Box Cum 12.0 3.633 2.880 6.05 759.62
(ii) Back filling behind abutment, Cum 2.0 12.000 3.557 6.05 258.27
Total Qty. 1,017.88 1 1,017.88 905.00 921,184.97
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100
I Ordinary soil
(i) Upto 3 m depth Cum 397.08 1 397.08 146.00 57,974.19
II Ordinary rock (not requiring blasting) Cum 661.81 1 661.81 246.00 162,804.22
III Hard rock (requiring blasting) Cum 264.72 1 264.72 802.00 212,307.30
(ii) PCC Grade M20 Cum 1.0 65.0 1.50 0.4 39.00
Cum 1.0 65.0 0.45 0.7 20.48
Total 59.48 1 59.48 5247.00 312,065.33
C) SUBSTRUCTURE.
(i) Granular Material inside Box Cum 12.0 3.633 2.630 7.84 899.03
(ii) Back filling behind abutment, Cum 2.0 12.000 4.611 7.84 433.81
Total Qty. 1,332.84 1 1,332.84 905.00 1,206,221.30
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100
I Ordinary soil
(i) Upto 3 m depth Cum 305.00 1 305.00 146.00 44,529.77
II Ordinary rock (not requiring blasting) Cum 508.33 1 508.33 246.00 125,049.37
III Hard rock (requiring blasting) Cum 203.33 1 203.33 802.00 163,072.51
(ii) PCC Grade M20 Cum 1.0 65.0 1.50 0.4 39.00
Cum 1.0 65.0 0.45 0.7 20.48
Total 59.48 1 59.48 5247.00 312,065.33
C) SUBSTRUCTURE.
(i) Granular Material inside Box Cum 12.0 3.633 2.630 6.25 716.61
(ii) Back filling behind abutment, Cum 2.0 12.000 3.675 6.25 275.62
Total Qty. 992.23 1 992.23 905.00 897,972.00
No.
Item Length Width Depth Total
S.N0. Description Unit No. Quantity of RATE AMOUNT
No. (m) (m) (m) Quantity
str.
FOUNDATION.
Excavation for Structures (Earth work in
excavation of foundation of structures as per
drawing and technical specification, including
setting out, construction of shoring and
1 2.1 bracing, removal of stumps and other
deleterious matter, dressing of sides and
bottom and backfilling with approved
material.)as per relevant clauses of section 300
& 2100
I Ordinary soil
(i) Upto 3 m depth Cum 406.36 1 406.36 146.00 59,327.91
II Ordinary rock (not requiring blasting) Cum 677.26 1 677.26 246.00 166,605.77
III Hard rock (requiring blasting) Cum 270.90 1 270.90 802.00 217,264.76
(ii) PCC Grade M20 Cum 1.0 65.0 1.50 0.4 39.00
Cum 1.0 65.0 0.45 0.7 20.48
Total 59.48 1 59.48 5247.00 312,065.33
C) SUBSTRUCTURE.
(i) Granular Material inside Box Cum 12.0 3.633 2.630 8.40 963.12
(ii) Back filling behind abutment, Cum 2.0 12.000 4.939 8.40 497.87
Total Qty. 1,460.99 1 1,460.99 905.00 1,322,199.74