You are on page 1of 3

KHWAJA GHULAM FARID UNIVERSITY OF ENGINEERING AND

INFORMATION TECHOLOGY RAHIMYAR KHAN


UNDER GROUND WATER TANK
Bill of Quantities

UNIT RATE
ITEM
DESCRIPTION UNIT QTY. TOTAL
NO. AMOUNT
(Rs)
(Rs)

1 EARTHWORKS
Excavation in all kind of sub-surface material complete in Cft 15,848
all respects as shown on the drawings, specifications
and/or as directed by the Engineer.

2 PVC WATER STOP


Providing embeding 10"(250mm) wide 1/4"
(6mm) thick rubber water stopper in RCC concrete
complete in all respect Lft 238

3 WATER PROOFING
SFT 1,316
4 BLINDING CONCRETE
Providing and laying 1500 Psi (Cylinder Strength) Plain
cement concrete using coarse sand and screened graded
and washed aggregate, in required shape and design,
including forms, moulds, shuttering, lifting, compacting, Cft 876
curing, rendering and finishing exposed surface, complete
as per drawings/specifications

5 CONCRETE
Providing and laying 3000 Psi (Cylinder Strength)
reinforced cement concrete using coarse sand and
screened graded and washed aggregate, in required
shape and design, including forms, moulds, shuttering,
lifting, compacting, curing, rendering and finishing
exposed surface, complete (but excluding the cost of
steel reinforcement, its fabrication and placing in position,
etc.

a) Slab Cft 245.7


b) Beams Cft 50.4

6 CONCRETE
Providing and laying 4000 Psi (Cylinder Strength)
reinforced cement concrete using coarse sand and
screened graded and washed aggregate, in required
shape and design, including forms, moulds, shuttering,
lifting, compacting, curing, rendering and finishing
exposed surface, complete (but excluding the cost of
steel reinforcement, its fabrication and placing in position,
etc.

a) Slab Cft 1,281


b) Columns Cft 151
c) RC Walls Cft 1,192
d) Foundation Cft 3,333
e) Beams Cft 203
KHWAJA GHULAM FARID UNIVERSITY OF ENGINEERING AND
INFORMATION TECHOLOGY RAHIMYAR KHAN
UNDER GROUND WATER TANK
Bill of Quantities

UNIT RATE
ITEM
DESCRIPTION UNIT QTY. TOTAL
NO. AMOUNT
(Rs)
(Rs)
6 REINFORCEMENT
Fabrication of High Tensile Steel deformed bars
conforming to ASTM-A615 Grade 60 (60,000Psi)
reinforcement for cement concrete, including cutting,
bending, laying in position, making joints and fastenings,
including cost of binding wire and labors charges for
binding of steel reinforcement (also includes removal of
rust from bars)

a).Slab Tons* 0.669


b).Columns Tons* 0.957
c).Foundation Tons* 9.830
d)Walls Tons* 3.244
e) Beams Tons* 1.378
7 Dia 3/4" M.S. RUNGS NO.S 20
8 1.5" DIA G.I. PIPE RAILING 3' HIGH FT 30
9 W12X30 STEEL GIRDER LENGTH FT 18

*(1 ton = 2204 lbs)


All the the quantities are increase by 5%.
KHWAJA GHULAM FARID UNIVERSITY OF ENGINEERING AND INFORMATION TECHOLOGY
RAHIMYAR KHAN
UNDER GROUND WATER TANK
Bill of Quantities
Sr # Item Length Width Height Nos. Quantity Unit
1 Excavation

UGWT 3018.63 5.00 1 15093.13 cft

Total 15093.13 cft


2 Blinding conc.

UGWT 3076.95 0.25 1 769.24 cft


38.75 1.63 1 63.13 cft
Under Ramp 6.65 0.25 1 1.66 cft
200.00 1.50 0.50 1 150.00 cft

834.03 cft
3 RCC in Foundation

UGWT 2357.63 1.25 1 2947.03 cft


At 18" depth location 38.75 1.64 2 126.71 cft
AT Section C-C 23.00 4.38 1 100.63 cft

Total 3174.37 cft

4 RCC WALLS

UGWT 227.00 0.833 6.000 1 1135.00 cft

1135.00 cft

5 Water Stoper

UGWT 227.0 1.0 227.0 Lft

227.00 Lft
6 Water proofing

UGWT 200.50 6.250 1 1253.13 Sft

1253.13 Sft
7 Columns Conc.
C1 5.500 1.5 1.5 2 24.75 cft
C2 18.000 1.3 1.3 4 112.50 cft
C3 9.000 0.83 0.83 1 6.25 cft

Total 143.50 cft

8 Beams Conc.
B1 16.000 1.0 1.5 3 72.00 cft
B5 11.000 1.0 1.5 1 16.50 cft
B2 16.750 1.0 1.5 3 75.38 cft
B3 16.000 1.0 1.5 2 48.00 cft
B4 9.750 1.0 1.5 2 29.25 cft

241.13 cft

9 Slab Conc.
UGWT 1894.50 0.5000 1 947.25 cft
62.00 0.5000 1 31.00 cft
Roof 468.00 0.5000 1 234.00 cft
Ramp 34.52 7.0000 1 241.64 cft

1453.89 cft

Quntity Unit wt Wt Wt
10 Reinforcement (cft) (lb/cft) (lbs) (tons)
Slab 234 6.0 1404.00 0.64
Walls 1135 6.0 6810.00 3.09
Beams 241 12.0 2893.50 1.31
Columns 144 14.0 2009.00 0.91
Foundation 3174 6.5 20633.40 9.36
Total 33749.90 15.3