Estimation of Bowstring Arch Bridge for Obligatory Span of 63.

4m @ LC-47 Gowribidanur

Arch Bridge
Sl. Total Amount
Description Unit Quantity Rates
No. (Rs.)

Earthwork in excavation of foundation for structures in all


6.01 types of soil including lead and lifts complete as per Tech. Cu.m.
Spec. Cl. 304
a) ordinary soil Cu.m. 1102.50 90.00 99,225
b) in soft/weathered rock Cu.m. 220.50 140.00 30,870

Cement Concrete/Reinforced Cement Concrete in open


foundation / leveling course including centering and
6.02
shuttering but excluding reinforcement all complete as per
Tech. Spec.Cl. 1500, 1700 & 2100
a) M15 Grade - Levelling Course Cum 31.83 4173.00 132,814

Cement concrete grade M35 in sub-structures and


6.03 Cu.m. 664.30 5400.00 3,587,195
Foundation as per Tech. Spec. Cl. 1700.

Cement concrete grade M40 in super structures as per Tech.


6.04 Cu.m.
Spec. Cl. 1700.
a) in RC Slab Cu.m. 152.92 6200.00 948,079
b) in footpath / Kerb/ etc Cu.m. 23.78 6200.00 147,405

Providing, cutting, bending and fixing in position of TMT


6.05 bar reinforcement in reinforced cement concrete structures T 124.62 65000.00 8,100,582
complete as per Tech. Spec. Cl 1600

6.06 Providing and fixing Expansion joint


c) Strip seal jt. in PSC Girder catering to maximum Rmtr 24.00 14500.00 348,000

Supply, fitting and fixing in position true to line and level


6.07
POT-PTFE Bearings complete as per Tech. Spec. Cl. 2000
Pot-PTFE Bearing - 750 MT No's 4.00 250000.00 1,000,000

Proving and fixing Drainage spouts complete as per Tech.


6.08 Each 28.00 1250.00 35,000
Spec. Cl. 2705

Providing and laying wearing course on top of deck


6.09 complete as per Tech.Spec.Cl.515 & 2702 65mm Thick Sq.m 507.20 880.00 446,336
(40BC+ 25 Asphaltic)

Construction of Crash Barrier M40 grade incl. cost of all


6.10 materials, labour, lead, lifts, loading, unloading etc., Rmtr 126.80 2480.00 314,464
complete

Providing and fixing MS Railing complete as per tech


6.11 Rmtr 126.80 3210.00 407,028
spec. MORTH Spec. No-2703.2, 1900

6.12 PVC Utility pipes (150 dia) Rmtr 126.80 500.00 63,400

Providing and applying 2 coats of Enamel paint to plastered


6.13 concrete surface complete as per Tech.Spec Cl. 800 for RC Sq.m 317.00 32.00 10,144
Crash barrier

Painting details of Structure and span arrangements as


6.14 No's 4.00 500.00 2,000
Tech.Spec.Cl. 800
Fabrication, erection and placing into position Structural
6.15 Tons 335.00 125000.00 41,875,000
Steel 60m Bow String Arch complete (Steel Grade -Fe410 )
Total 57,547,542
Excalation at 10% rate 5,754,754
Grand Total 63,302,296
Bill of Quantities for Major Bridge (Bowstring Arch Bridge) :
Number of spans 1 Open Foundation
Span configuration 63.4 length = 63.4
Overall Width: 12.0 m Footpath Yes (Yes / No)
Number of parallel structures 1 Nos
Sl. Length Breadth Depth
Description Unit No. Quantity
No. (m) (m) (m)

Earthwork in excavation of foundation for


6.01 structures in all types of soil including lead and Cu.m.
lifts complete as per Tech. Spec. Cl. 304
a) ordinary soil 1102.50
Pier - 1 1 10.50 10.50 5.00 551.25
Pier - 2 1 10.50 10.50 5.00 551.25

b) in soft/weathered rock 220.50


Pier - 1 1 10.50 10.50 1.00 110.25
Pier - 2 1 10.50 10.50 1.00 110.25

a) M25 Grade - Levelling Course 31.83


Pier - 1 1 10.30 10.30 0.15 15.91
Pier - 2 1 10.30 10.30 0.15 15.91

Cement concrete grade M35 in sub-structures and


6.03 Cu.m.
Foundation as per Tech. Spec. Cl. 1700.
Pier - P1
Pier Pedestal 1 3.50 3.50 3.50 42.88
Footing (straight) 1 9.50 9.50 1.50 135.38
Pier 1 Area = 4.91 6.60 32.40
Pier - P2
Pier Pedestal 1 3.50 3.50 3.50 42.88
Footing (straight) 1 9.50 9.50 1.50 135.38
Pier 1 Area = 4.91 6.60 32.40
Pier Cap -st section 2 15.00 3.00 2.70 243.00
Pier Cap -varying secn 0 15.00 2.40 2.70 0.00

664.30

Cement concrete grade M40 in super structures as


6.04 Cu.m. 176.69
per Tech. Spec. Cl. 1700.
a) in RC Slab 152.92
Slab 1 63.40 12.00 0.20 152.16
Bearing Pedestal 4 Area= 0.54 0.35 0.76
b) in footpath / Kerb/ etc 63.40 23.78
in footpath precast slabs 2 63.40 1.50 0.08 14.27
Railing Base 2 63.40 0.30 0.25 9.51
Sl. Length Breadth Depth
Description Unit No. Quantity
No. (m) (m) (m)
Providing, cutting, bending and fixing in position
of TMT bar reinforcement in reinforced cement
6.05 T 124.62
concrete structures complete as per Tech. Spec. Cl
1600
Pier - P1
Pier 1 wt = 5.35 5.35
Footing and Pedestal 1 wt = 26.74 26.74
Pier - P2
Pier 1 wt = 5.35 5.35
Footing and Pedestal 1 wt = 26.74 26.74
Pier Cap 1 wt = 43.74 43.74
RC Deck Slab/Bearing Pedestal 1 wt = 15.29 15.29
in footpath precast slabs 1 wt = 1.43 1.43

6.06 Providing and fixing Expansion joint


c) Strip seal jt. in PSC Girder catering to Rmtr 2 12.00 24.00

Supply, fitting and fixing in position true to line


6.07 and level POT-PTFE Bearings complete as per
Tech. Spec. Cl. 2000

Pot-PTFE Bearing - 750 MT No's 4.00 4.00

Proving and fixing Drainage spouts complete as


6.08 Each 28 28.00
per Tech. Spec. Cl. 2705

Providing and laying wearing course on top of


6.09 deck complete as per Tech.Spec.Cl.515 & 2702 Sq.m 1 63.40 8.00 507.20
65mm Thick (40BC+ 25 Asphaltic)

Construction of Crash Barrier M40 grade incl. cost


6.10 of all materials, labour, lead, lifts, loading, Rmtr 126.80
unloading etc., complete
Inner 2 63.40 126.80

Providing and fixing MS Railing complete as per


6.11 Rmtr
tech spec. MORTH Spec. No-2703.2, 1900
Outer 2 63.40 126.80

6.12 PVC Utility pipes (150 dia) Rmtr 2 63.40 126.80

Providing and applying 2 coats of Enamel paint to


6.13 plastered concrete surface complete as per Sq.m 2 63.4 2.50 317.00
Tech.Spec Cl. 800 for RC Crash barrier

Painting details of Structure and span


6.14 No's 4 4.00
arrangements as Tech.Spec.Cl. 800

Fabrication, erection and placing into position


6.15 Structural Steel 62m Bow String Arch complete as Tons 335.00
given in std. RDSO drawing (Steel Grade -Fe410 )