You are on page 1of 2

BoQ Bridge 02

BILL OF QUANTITIES (BoQ)


Bridge Name: Bridge 02, Boulevard 3, GA Pemathang
Bridge type: Reinforced Concrete Box Frame

Rate Amount
Sl.No Code Description of item Unit Quantity
(Nu) (Nu)
1000 EARTHWORK
The quantities for earthwork are calculated
as "Solid Volume"
1 1001 Structure excavation - Hard soil m3 256.93 54.31 13,953.18
2 1002 Structure excavation - Ordinary rock m3 28.55 57.30 1,635.77
3 1003 Backfilling for bridge (qty. for till the end of m3 657.63 114.09 75,030.80
approach slab) + River Training (RT) Wall
Total for Earth Works: 90,619.75
2000 CONCRETE WORKS + FORMWORK + REBAR
Providing & laying lean concrete M10 for bridge
4 2001 foundations, RT wall and underneath of approach m3 40.92 5,560.04 227,527.25
slabs.
2002 Prviding and laying M25 grade concrete for:
2002.1 Base slab + components m3 76.90 8,254.25 634,712.48
5 2002.2 End wall + intermediate wal + Return Walls m3 124.40 8,167.40 1,016,026.42
2002.3 Top slab & Components m3 64.32 8,432.37 542,382.88
2002.4 Approach slabs m3 43.30 8,254.25 357,434.75
2003 Providing and fixing formwork for:
2003.1 Base slab + components m2 33.06 729.83 24,128.12
6 2003.2 Wall & Components m2 691.46 735.12 508,304.56
2003.3 Top slab & Components m2 160.42 729.83 117,081.44
2003.4 Approach slab m2 26.36 729.83 19,239.73
Providing and laying Thermo Mechanically
7 2004
Treated (TMT) bars of Grade Fe 500:
8 2004.1 For all component of the bridge tons 22.70 97,010.10 2,202,129.27
Total for Concrete+Formwork+Rebar: 5,648,966.90

3000 MISCELLANEOUS WORKS


Compacted stone soling for bridge and RT wall
9 3001 m3 51.67 2,041.32 105,478.73
foundations
Providing and laying Random Rubble Masonry
10 3002 m3 111.24 4,751.31 528,536.02
with CM 1:4 for RT Wall
Providing and laying Coursed Rubble Masonry
11 3003 m3 32.82 5,138.29 168,617.16
with CM 1:4 for river bank protection wall
Providing and laying PCC capping for RT walls,
12 3004 m3 2.78 5,560.04 15,462.48
concrete grade M10
Material, fabrication and installation of drainage
15 3005 pcs 2.00 3,185.75 6,371.51
spouts as per drawings
Providing and laying 110mm diameter HDPE
3006
pipe as weep holes for:
16 3006.1 For bridge - Length = 400 mm pcs 18.00 409.96 7,379.30
3006.2 For RT wall - Length= 990mm pcs 40.00 409.96 16,398.45
Materal, fabrication , supply and installation of
17 3007 steel railings as per the details shown in the kg 3,227.45 265.12 855,674.89
drawings
BoQ Bridge 02

BILL OF QUANTITIES (BoQ)


Bridge Name: Bridge 02, Boulevard 3, GA Pemathang
Bridge type: Reinforced Concrete Box Frame

Rate Amount
Sl.No Code Description of item Unit Quantity
(Nu) (Nu)
Ashphat Wearing Course 50mm thick on the
18 3008 m2 134.64 511.09 68,813.80
bridge deck and the approach slabs.
Walkway surfacing for bridge and approach slabs -
19 3009 m2 92.43
material to be decided by Client
Total for Miscellaneous Works: 1,772,732.34
Grand Total 7,512,318.99

You might also like