Professional Documents
Culture Documents
Rate Amount
Sl.No Code Description of item Unit Quantity
(Nu) (Nu)
1000 EARTHWORK
The quantities for earthwork are calculated
as "Solid Volume"
1 1001 Structure excavation - Hard soil m3 256.93 54.31 13,953.18
2 1002 Structure excavation - Ordinary rock m3 28.55 57.30 1,635.77
3 1003 Backfilling for bridge (qty. for till the end of m3 657.63 114.09 75,030.80
approach slab) + River Training (RT) Wall
Total for Earth Works: 90,619.75
2000 CONCRETE WORKS + FORMWORK + REBAR
Providing & laying lean concrete M10 for bridge
4 2001 foundations, RT wall and underneath of approach m3 40.92 5,560.04 227,527.25
slabs.
2002 Prviding and laying M25 grade concrete for:
2002.1 Base slab + components m3 76.90 8,254.25 634,712.48
5 2002.2 End wall + intermediate wal + Return Walls m3 124.40 8,167.40 1,016,026.42
2002.3 Top slab & Components m3 64.32 8,432.37 542,382.88
2002.4 Approach slabs m3 43.30 8,254.25 357,434.75
2003 Providing and fixing formwork for:
2003.1 Base slab + components m2 33.06 729.83 24,128.12
6 2003.2 Wall & Components m2 691.46 735.12 508,304.56
2003.3 Top slab & Components m2 160.42 729.83 117,081.44
2003.4 Approach slab m2 26.36 729.83 19,239.73
Providing and laying Thermo Mechanically
7 2004
Treated (TMT) bars of Grade Fe 500:
8 2004.1 For all component of the bridge tons 22.70 97,010.10 2,202,129.27
Total for Concrete+Formwork+Rebar: 5,648,966.90
Rate Amount
Sl.No Code Description of item Unit Quantity
(Nu) (Nu)
Ashphat Wearing Course 50mm thick on the
18 3008 m2 134.64 511.09 68,813.80
bridge deck and the approach slabs.
Walkway surfacing for bridge and approach slabs -
19 3009 m2 92.43
material to be decided by Client
Total for Miscellaneous Works: 1,772,732.34
Grand Total 7,512,318.99