2 Request for Tree Cutting Permission Letter Submitted to KRDCL 03-08-19 Still it is in DFO Office,awaiting approval for permision
BESCOM to KRDCL agreement done,awaiting for KRDCL & KMV
3 Electrical Line Shifting Estimate (Jigani & Anekal) Submitted to KRDCL 07-09-19
agreement
4 Pipe Line Shifting Details Submitted to KRDCL 03-08-19 Estimate signed by Rural Water Supply engineers,awaiting for PMC sign
Till date no authorized person from Land acquisition team visit at site
5 Land Acquisition
,awaiting for Land acquisition since 06-05-19
6 Submission of Pavement Design 17-07-19 Awaiting approval from KRDCL
7 Submission of Plan and Profile with Cross Sections 17-07-19 Awaiting approval from KRDCL
8 Submission of Drain Design with Drawings 19-07-19 Awaiting approval from KRDCL
10 Request for Bypass Alignment Finalization 28-08-19 Awaiting approval from KRDCL