S No Description Date Remarks

1 Site Handed Over from KRDCL to KMV Projects Ltd 06-05-19

2 Request for Tree Cutting Permission Letter Submitted to KRDCL 03-08-19 Still it is in DFO Office,awaiting approval for permision
BESCOM to KRDCL agreement done,awaiting for KRDCL & KMV
3 Electrical Line Shifting Estimate (Jigani & Anekal) Submitted to KRDCL 07-09-19
agreement
4 Pipe Line Shifting Details Submitted to KRDCL 03-08-19 Estimate signed by Rural Water Supply engineers,awaiting for PMC sign
Till date no authorized person from Land acquisition team visit at site
5 Land Acquisition
,awaiting for Land acquisition since 06-05-19
6 Submission of Pavement Design 17-07-19 Awaiting approval from KRDCL

7 Submission of Plan and Profile with Cross Sections 17-07-19 Awaiting approval from KRDCL

8 Submission of Drain Design with Drawings 19-07-19 Awaiting approval from KRDCL

9 Submission of Encumbrance free land Details 19-10-19

10 Request for Bypass Alignment Finalization 28-08-19 Awaiting approval from KRDCL

Submission of Pipe Culverts,Box Culverts,Retainingwalls drawings to PMC,CC


11 15-11-19 Awaiting approval from KRDCL
to KRDCL