Professional Documents
Culture Documents
1 CIVIL WORKS FOR WARE HOUSE 20,026.26 5,021,026.22 NIL Tk. 5,021,026.22
2 STEEL WORKS FOR WARE HOUSE 20,026.26 9,164,883.59 1,468,932.31 Tk. 10,633,815.90
NOTE:
1, Above Rate is Excluded of VAT,AIT & Any other Govt TAXes.
4 Disposal of extra Excavated Work Cft 1587.60 Tk. 7.00 Tk. 11,113.20
5
Providing Vity Sand filling below foundation trenches and
plinth with coarse sand having min. F.M 0.8 in 150 mm
layers including leveling, watering and consolidating each Cft 4527.60 Tk. 25.00 Tk. 113,190.00
layer up to finished level (From FGL to PL within plinth area)
etc. all complete as per direction of the engineer-in-charge.
6
Providng and laying double layer polythene sheet weighing
1.00kg per 6.5 sqm under slab etc. all complete as per Sft 4527.60 Tk. 5.00 Tk. 22,638.00
direction of EIC.
SL ITEAM DESCRIPTION UNIT QUANTITY RATE IN TAKA AMOUNT IN TAKA
7
One layer of brick flat soling in foundation & Ground Floor
with 1st class or picked jhama bricks after preparation of
bed and filling the interstices with local sand by client,
Sft 3988.00 Tk. 45.00 Tk. 179,460.00
leveling in/c the supply of water, electricity and other
charges and costs of tools and plants etc. all complete as
per direction of the engineer-in-charge.
a) Base (1:1.5:3) using Stone chips Cft 485.00 Tk. 315.00 Tk. 152,775.00
b) Padestal Column (1:1.5:3) using Stone chips Cft 175.00 Tk. 320.00 Tk. 56,000.00
c) Grade Beam (1:1.5:3) using Stone chips Cft 720.00 Tk. 315.00 Tk. 226,800.00
d) Ground floor (1:2:4) using Brick chips Cft 1800.00 Tk. 305.00 Tk. 549,000.00
e) Lintel (1:2:4) using Brick chips Cft 60.00 Tk. 305.00 Tk. 18,300.00
f) Mezzanine floor (1:2:4) using Brick chips Cft 3024.00 Tk. 305.00 Tk. 922,320.00
10
15
1.5'' Thick patenstone with net cement finishing Sft 7200.00 Tk. 65.00 Tk. 468,000.00
16
Plastic paint 3 (three) coats to inside wall making necessary
cleaning from plinth by washing ,rubbing,oiling if necessary
Sft 5040.00 Tk. 32.00 Tk. 161,280.00
after the wash for wall surface etc.all complate in all respect
as per drawing and direction of the Engineering-in-charge.
SL ITEAM DESCRIPTION UNIT QUANTITY RATE IN TAKA AMOUNT IN TAKA
17
Supply fitting and fixing Alluminium Glass Window with 5mm
thick clear glass ,Alluminium frame,necessary accessories
Sft 180.00 Tk. 395.00 Tk. 71,100.00
etc,all complete in all respect as per drawing and direction
of the Engineering-in -charge.
18
Supply ,fitting and fixing window grill made of approx 12
mmX12mm MS Solid bar 140mm c/c ,as per design Sft 180.00 Tk. 160.00 Tk. 28,800.00
approved and accepted by the Engineeer.
Tk. 5,021,026.22
Grand Total Cost In BDT= Tk. 5,021,026.22
TOTAL COST/SFT(Civil Work) Tk. 697.36
Note:
1) This rate is excluded of VAT, AIT & any other govt. Taxes.
2) This rate is excluded of Drain & Apron System.
F1 4 9 9 0.5
F2 12 4 4 0.5
Sand Filling F3 0 7 7 0.5
under
2 TANK 0 13.2 12.2 2
Foundation &
Floor F5 0 0 0 1
F6 0 0 0 1
G. Floor 1 60.00 60.00 2
F1 4 9 9
F2 12 4 4
F3 0 7 7
2
Polythene F4 0 13.2 12.2
Laying & F5 0 0 0
Levelling
F6 0 0 0
3 G. Floor 1 60.00 60
Earth Back
4 Filling (30%
compaction)
Disposal of
5 Extra Excavated
Soil
F1 4 7 7
F2 12 4 4
F3 0 7 7
6 1 layer BFS F4 0 13.2 12.2
F5 0 0 0
F6 0 0 0
Ground Floor 1 60.00 60
F1 4 7 7 0.25
F2 12 4 4 0.25
CC F3 0 7 7 0.25
7 Casting(Ratio=1:
2:4)
CC
7 Casting(Ratio=1:
2:4) F4 0 13.2 12.2 0.25
F5 0 0 0 0.25
F6 7 7 0.25
Pile 50
(Ratio=1:1.5:3) Total for Pile
F1 4 7 7 1.25
F2 12 4 4 1.25
F3 0 6 6 1.25
Base
F4 0 4 4 0.6666667
(Ratio=1:1.5:3)
F5 0 9.5 9.5 1.75
F6 0 9.5 9.5 1.75
Total for Base
C1 4 1.25 1.25 7.00
C2 12 1.25 1.25 7.00
Padestal C3 0 1.25 1.25 6.25
Column C4 0 1.50 1.00 7.50
(Ratio=1:1.5:3) C5 0 1.67 2.00 7.00
C6 0 1.67 1.00 9.00
Total for Padestal Column
C1 3 1.25 1.00 36.09
C1 2 1.25 1.00 43.96
C2 2 1.00 1.00 43.96
Column
C3 1 1.00 1.00 22.97
(Ratio=1:1.5:3)
C5 0 1.67 2.00 7.00
C6 0 1.67 1.00 9.00
Total for Column
GB 1 480.00 1.00 1.50
Grade Beam 0.83 1.67
8 Casting (Ratio=1:1.5:3) 0.83 1.67
Total for Grade Beam
FB 38.45 0.83 1.25
FB 25.52 0.83 1.25
Floor Beam FB 22.67 0.83 1.25
(Ratio=1:1.5:3) FB 29.02 0.83 1.25
LB 9.35 0.83 1.25
Total for Floor Beam
Ground Floor
1 60.00 60.00 0.50
(Ratio=1:2:4)
Total for Ground Floor
3
Mezzanine floor 1 60.00 60.00 0.42
(Ratio=1:2:4) 54446.00 1.00 0.33
Total for Mezzanine floor
1 240.00 0.50 0.50
Lintel 0 127.94 0.83 0.42
(Ratio=1:1.5:3) 0 0.00 0.00 0.00
Total for Lintel
0 19.67 9.35 0.54
Stair
0 127.94 0.83 0.42
(Ratio=1:1.5:3)
Total for Stair
13.20 12.20 0.83
Water Tank 13.20 12.20 0.42
(Ratio=1:1.5:3) 50.80 5.00 0.83
Water Tank
(Ratio=1:1.5:3)
Total for Water Tank
Pile
16 mm 55
All Pile
8 mm 4.178328
Total for Pile
Base
No of footing No of Bar Avg. length
F1 4 76 8 0.27
F2 12 68 7.11942257 0.27
F3 12 mm 0 58 6.1351706 0.27
(TOP &
F4 BOTTOM) 0 11 4 0.27
F5 0 0.48
F6 0 0.48
Total for Base
Padestal Column
C1 4 8 9.00 0.75
C2 12 8 9.00 0.75
C3 0 8 9.00 0.75
20 mm
C4 0 8 7.50 0.48
0 14 10.50
C4 0 14 10.50 0.48
C1 4 17 2.22 0.19
C2 12 17 2.00 0.19
10 mm
C3 0 17 2.00 0.19
C4 0 0 5.00 0.19
Total for Padestal Column
Column
C1 3 8 39.09 0.75
C1 2 8 46.96 0.75
C2 2 8 46.96 0.75
20 mm
C3 1 8 24.97 0.48
14 10.50
C4 14 10.50 0.48
C1 3 88 4.44 0.19
C1 2 110 4.00 0.19
10 mm
C2 2 110 4.00 0.19
C3 1 55 0.00 0.19
Total for Column
Reinforcement Floor Beam
Calculation
Water Tank
10
(Ratio=1:1.5:3)
1 124 13.20 0.19
Water Tank
10 1 132 13.20 0.19
(Ratio=1:1.5:3)
1 33 13.20 0.19
1 31 12.20 0.19
1 81 5.00 0.19
Total for Water Tank
Grade Beam
GB-1 20 mm 1 5.00 480.00 0.75
20 mm 1 1.00 320.00 0.75
10 mm 1 2.00 480.00 0.19
GB-1 1 0 5.33 0.19
10 mm
GB-2
Total for Grade Beam
Ground Floor
12 mm 1 80 38.45 0.27
12 mm 1 55 25.52 0.27
0 87.00 0.19
10 mm 0 45.5 0.19
Total for Ground Floor
Mezzanine Floor
0 0 0.00 0.19
0 0 0 0.19
10 mm
0 0 0.00 0.19
0 0 25 0.19
Total for Mezzanine Floor
Lintel
10 mm 1 4.00 240.00 0.19
8 mm 0 160 0.814 0.12
Total for Lintel
Base
F1 4 7 7 1.25
F2 12 4 4 1.25
F3 0 6 6 1.25
F4 0 4 4 0.6666667
F5 0 9.5 9.5 1.75
F6 0 9.5 9.5 1.75
Total for Base
Padestal Column
C1 4 1.25 1.25 7.00
C2 12 1.25 1.25 7.00
C3 0 1.25 1.25 6.25
C4 0 1.50 1.00 7.50
C5 0 1.67 2.00 7.00
C6 0 1.67 1.00 9.00
Total for Padestal Column
Column
C1 3 1.25 1.00 36.09
C1 2 1.25 1.00 43.96
Wooden Shutter C2 2 1.00 1.00 43.96
C4 1 1.00 1.00 22.97
Total for Column
Floor Beam
FB 4 38.45 0.83 1.25
FB 9 25.52 0.83 1.25
FB 2 22.67 0.83 1.25
FB 2 29.02 0.83 1.25
LB 3 9.35 0.83 1.25
Total for Floor Beam
Grade Beam
GB-1 1 1.00 1.50 480.00
GB-2 0 0.83 1.67 0.00
GB-2 0 0.83 1.67 0.00
Total for Padestal Column
Ground Floor
4 60.00 60 0.4166667
Total for Ground Floor
Lintel
1 0.50 0.50 240.00
Total for Lintel
Ground Floor 1 60.00 60.00
NCF Mezzanine Floor 2 736.27 0.00
Total for NCF
Ground Floor 1 60.00 60.00
Floor Tiles Mezzanine Floor 2 843.48
Total for Floor Tiles
10" B/W 1.00 240.00 0.83 2
10" B/W 150.00 0.83 13
10" B/W 50.00 0.83 10
Brick Work
5" B/W 1.00 240.00 0.41666667 20
5" B/W 200.00 0.41666667 13
5" B/W 50.00 0.41666667 10
Diduct for Window
Plastering
Distempering
Paintinig
(Inner Wall
Weather (Outer
Wall
Total
Over Head Expense
Profit
Grand Total
Area
Unit Rate
Note:
1) Above Rate is Excluded of VAT, AIT & TAX.
Date: 3/12/2014
ivil BOQ .
Unit Rate
Quantity Total Unit Amount (Tk.)
(Tk.)
2268.00
3024.00
0.00
5,292.00
0.00
0
0 Cft 4.00 21,168.00
162
96 46
0
0 7,458.00
4,527.60
0 SFT - -
196
192
0
0 3,988.00 Sft 28.00 111,664.00
0
0
3600
49
48 Cft 200.00 19,400.00
0
97.00
97.00
0
0
0
0
0
245.00
240.00
0.00
0
0
0
485.00
43.75
131.25
0.00
0.00
0.00
0.00
175.00
135.33
109.91
87.93
22.97
0.00
0.00
356.14
720.00
0.00
0.00 5,108.14 Cft 250.00 1,277,033.79
720
0.00
0.00
0.00
0.00
0.00
0.00
1800 736.273
1800.00
1512.00
0
1512.00
60.00
0.00
60.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0
0.0
0
658.27
1572.44 0.4166667
0.00
0.00 10.714286
0.00 13.690476
0.00 8.3333333
2230.70101
216.53 10356.353
649.60
0.00
0.00
0.00
28.38
76.69
0.00
0.00
971.203874
705.35
564.95
564.95
96.11
0.00
220.32
165.41
165.41
0.00
2482.51
14955.90 Kg 58 867442.16260425
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1061.73
191.05
307.66
327.51
81.88
71.09
76.13
2117.04
1804.46
240.59
180.45
0.00
0
2225.50
832.58
379.91
0.00
0.00
1212.49
3367.64 525.94
0.00 808.04
0.00 525.94
0.00 808.04
3536.02
180.45
0.00
180.445701 119.1
270.02
140
240
0
0
0
0
380
140.0
420.0
0.0 3920
0.0
0.0
0.0
560.00
487.2
395.7
351.7 6,575.39 Sft 25.00 164,384.63
91.9
1,326.44
392.8
593.0
117.5
149.3
76.4
1,328.94
2400.0
0.0
0.0
2400.00
100
100
480.00
480.00
3600
5072.546
762.35
1686.96 2,449.31 Sft - -
2449.31
400.00 400.00 Cft 160.00 64,000.00
- - Cft 160.00 -
- - Cft 160.00 -
4,800.00 4,800.00 Sft 160.00 768,000.00
- - Cft 160.00 -
- - Cft 160.00 -
-
960.00 960.00 Sft 18.00 17,280.00
- Sft 22.00 -
3,672,323.21
3.50% 128,531.31
7.00% 257,062.62
4,057,917.15
Sft 8,195.0
Per Sft 495.17