You are on page 1of 16

For your Industrial, Commercial & Residential Building

Client Name : EMAMI UTILITY BUILDING Date :06.08.2017


Project Name : Ware house Shed
Project Location : Valuka, Mymensing

ABSTRACT COST OF CIVIL WORKS AND STEEL WORKS

AMOUNT WITHOUT AMOUNT FOR TOTAL AMOUNT WITH


SL NO ITEAM DESCRIPTION AREA (SFT)
ADDITIONAL (BDT) ADDITIONAL(BDT) ADDITIONAL( BDT)

1 CIVIL WORKS FOR WARE HOUSE 20,026.26 5,021,026.22 NIL Tk. 5,021,026.22

2 STEEL WORKS FOR WARE HOUSE 20,026.26 9,164,883.59 1,468,932.31 Tk. 10,633,815.90

GRAND TOTAL= Tk. 14,185,909.81 Tk. 1,468,932.31 Tk. 15,654,842.12

NOTE:
1, Above Rate is Excluded of VAT,AIT & Any other Govt TAXes.

PREPARED BY CHECKED BY APPROVED BY


For your Industrial, Commercial & Residential Building

Client Name : Date :01.03.2018


Project Name : Factory Building
Project Location :
Ground Floor Area= 3,600.00 Sft
Mezzanine Floor Area= 3600.00 Sft
Total Floor Area= 7200.00 Sft

ABSTRACT COST OF CIVIL WORKS

SL ITEAM DESCRIPTION UNIT QUANTITY RATE IN TAKA AMOUNT IN TAKA


1
Providing layout and conducting survey work for lay out of
the structure in accordance with drawing and design, carry
over Bench-Mark (BM) at site from nearby BM pillar,
Property lines, existing ground level (EGL), formation
ground level (FGL), highest flood levels (HFL), plinth levels
(PL), setting and marking all pillars, marker, pegs etc. Sft 3600.00 Tk. 6.00 Tk. 21,600.00
showing and maintaining reduced levels (RL’s) including
locating, establishing, protecting all public utilities within the
premise of work and finally all to be presented in black and
white.Including removal of all debrishes(mud,organic
materials etc)

2 Earth Excavation Cft 5292.00 Tk. 7.00 Tk. 37,044.00

3 Eart Bacfilling Cft 3704.40 Tk. 7.00 Tk. 25,930.80

4 Disposal of extra Excavated Work Cft 1587.60 Tk. 7.00 Tk. 11,113.20
5
Providing Vity Sand filling below foundation trenches and
plinth with coarse sand having min. F.M 0.8 in 150 mm
layers including leveling, watering and consolidating each Cft 4527.60 Tk. 25.00 Tk. 113,190.00
layer up to finished level (From FGL to PL within plinth area)
etc. all complete as per direction of the engineer-in-charge.

6
Providng and laying double layer polythene sheet weighing
1.00kg per 6.5 sqm under slab etc. all complete as per Sft 4527.60 Tk. 5.00 Tk. 22,638.00
direction of EIC.
SL ITEAM DESCRIPTION UNIT QUANTITY RATE IN TAKA AMOUNT IN TAKA
7
One layer of brick flat soling in foundation & Ground Floor
with 1st class or picked jhama bricks after preparation of
bed and filling the interstices with local sand by client,
Sft 3988.00 Tk. 45.00 Tk. 179,460.00
leveling in/c the supply of water, electricity and other
charges and costs of tools and plants etc. all complete as
per direction of the engineer-in-charge.

Mass concrete works having , with with cement confirming


to BDS 232 & ASTM standard , best quality coarse sand ,
20 mm down well graded crushed Brick chips including
breaking chips and screening through proper sieves ,
making , placing in position the centering and shuttering , Cft 97.00 260.00 Tk. 25,220.00
making shuttering water tight , concrete mixing with mixer
machine , casting in forms , compacting and curing at least
for 28 days , removing centering shuttering etc. all complete
as per direction of the engineer in charge .

Reinforcement cement concrete works having specified


compressive strength f'c 3500 psi at 28 days for Stone
Chips & 2500 psi for Brick chips on standard cylinder , with
with cement confirming to BDS 232 & ASTM standard ,
best quality coarse sand , 20 mm down well graded crushed
chips including breaking chips and screening through proper
sieves , making , placing in position the centering and
shuttering , making shuttering water tight , placing of
reinforcement in ,position; concrete mixing with mixer
machine , casting in forms , compacting and curing at least
for 28 days , removing centering shuttering etc. all complete
as per direction of the engineer in charge .

a) Base (1:1.5:3) using Stone chips Cft 485.00 Tk. 315.00 Tk. 152,775.00

b) Padestal Column (1:1.5:3) using Stone chips Cft 175.00 Tk. 320.00 Tk. 56,000.00

c) Grade Beam (1:1.5:3) using Stone chips Cft 720.00 Tk. 315.00 Tk. 226,800.00

d) Ground floor (1:2:4) using Brick chips Cft 1800.00 Tk. 305.00 Tk. 549,000.00

e) Lintel (1:2:4) using Brick chips Cft 60.00 Tk. 305.00 Tk. 18,300.00

f) Mezzanine floor (1:2:4) using Brick chips Cft 3024.00 Tk. 305.00 Tk. 922,320.00
10

Supplying, fabrication and fixing to details as per design M.S


deformed bar as reinforcement of required size and length
for all types of RCC work in/c straightening the rod,
removing rusts, cleaning, cutting, hooking, bending, binding
with 22 B.W.G. GI wire, placing the bars in position, in/c
lapping, spacing and securing them in position by concrete
blocks, metal chairs, etc. complete as per specifications,
drawings and direction of the Engineer-in-charge.

60 grade deformed bar with minimum fy = 412 Mpa


a) Base Kg 753.69 Tk. 86.00 Tk. 64,817.34
b) Padestal Column Kg 582.75 Tk. 86.00 Tk. 50,116.50
c) Grade Beam Kg 2877.12 Tk. 86.00 Tk. 247,432.32
d) Ground Floor Kg 2797.20 Tk. 86.00 Tk. 240,559.20
e) Lintel Kg 266.40 Tk. 86.00 Tk. 22,910.40
SL ITEAM DESCRIPTION UNIT QUANTITY RATE IN TAKA AMOUNT IN TAKA

f) Mezzanine Floor Kg 4699.30 Tk. 86.00 Tk. 404,139.46


SL ITEAM DESCRIPTION UNIT QUANTITY RATE IN TAKA AMOUNT IN TAKA
11
Supplying and fixing of Wooden Shutter. All complete as per
specifications, drawings and direction of the Engineer-in-
charge.
a) Base Sft 380.00 Tk. 48.00 Tk. 18,240.00

b) Padestal Column Sft 560.00 Tk. 48.00 Tk. 26,880.00

c) Ground Floor Sft 100.00 Tk. 48.00 Tk. 4,800.00

d) Grade Beam Sft 2400.00 Tk. 48.00 Tk. 115,200.00

e) Lintel Sft 480.00 Tk. 48.00 Tk. 23,040.00


12
250 mm thick brick work (EGL to PL) in Super structure with
1st class bricks in cement (Scan/Holcim/Akij) mortar (1:6)
including filling the interstices with mortar, racking out joints,
cleaning and soaking the bricks before use, curing for at
least 7 days etc. complete as per direction of the Engineer-
in-charge.

Below GB Cft 400.00 Tk. 192.00 Tk. 76,800.00


13

125 mm thick brick work in Super structure with 1st class


bricks in cement (Scan/Holcim/Akij) mortar (1:6) including
filling the interstices with mortar, racking out joints, cleaning
and soaking the bricks before use, curing for at least 7 days
etc. complete as per direction of the Engineer-in-charge.

FFLto Lintel Sft 4800.00 Tk. 82.00 Tk. 393,600.00


14
Minimum 12 mm thick cement sand (F.M. 1.2) plaster (1:4)
with fresh cement (Scan/Holcim/Akij) (conforming to BDS
232) to wall both inner-and outer surface, finishing the
corner and edges in/c washing of sand cleaning the surface, Sft 10080.00 Tk. 24.00 Tk. 241,920.00
scaffolding and curing at least for 7 days,all complete in all
respect as per drawing and direction of the engineer-in-
charge.

15
1.5'' Thick patenstone with net cement finishing Sft 7200.00 Tk. 65.00 Tk. 468,000.00

16
Plastic paint 3 (three) coats to inside wall making necessary
cleaning from plinth by washing ,rubbing,oiling if necessary
Sft 5040.00 Tk. 32.00 Tk. 161,280.00
after the wash for wall surface etc.all complate in all respect
as per drawing and direction of the Engineering-in-charge.
SL ITEAM DESCRIPTION UNIT QUANTITY RATE IN TAKA AMOUNT IN TAKA
17
Supply fitting and fixing Alluminium Glass Window with 5mm
thick clear glass ,Alluminium frame,necessary accessories
Sft 180.00 Tk. 395.00 Tk. 71,100.00
etc,all complete in all respect as per drawing and direction
of the Engineering-in -charge.
18
Supply ,fitting and fixing window grill made of approx 12
mmX12mm MS Solid bar 140mm c/c ,as per design Sft 180.00 Tk. 160.00 Tk. 28,800.00
approved and accepted by the Engineeer.
Tk. 5,021,026.22
Grand Total Cost In BDT= Tk. 5,021,026.22
TOTAL COST/SFT(Civil Work) Tk. 697.36
Note:
1) This rate is excluded of VAT, AIT & any other govt. Taxes.
2) This rate is excluded of Drain & Apron System.

PREPARED BY CHECKED BY APPROVED BY


Sample of Civil BOQ .
Sl Description of
Item Nos Length (ft) Breath (ft) Height (ft)
No the work
F1 4 9 9 7
F2 12 6 6 7
Earth F3 0 7 7 5.5
1
Excavation TANK 0 13.2 12.2 5
F5 0 0 0 0
F6 0 0 0 0

F1 4 9 9 0.5
F2 12 4 4 0.5
Sand Filling F3 0 7 7 0.5
under
2 TANK 0 13.2 12.2 2
Foundation &
Floor F5 0 0 0 1
F6 0 0 0 1
G. Floor 1 60.00 60.00 2

F1 4 9 9
F2 12 4 4
F3 0 7 7
2
Polythene F4 0 13.2 12.2
Laying & F5 0 0 0
Levelling
F6 0 0 0

3 G. Floor 1 60.00 60

Earth Back
4 Filling (30%
compaction)

Disposal of
5 Extra Excavated
Soil

F1 4 7 7
F2 12 4 4
F3 0 7 7
6 1 layer BFS F4 0 13.2 12.2
F5 0 0 0
F6 0 0 0
Ground Floor 1 60.00 60

F1 4 7 7 0.25
F2 12 4 4 0.25
CC F3 0 7 7 0.25
7 Casting(Ratio=1:
2:4)
CC
7 Casting(Ratio=1:
2:4) F4 0 13.2 12.2 0.25
F5 0 0 0 0.25
F6 7 7 0.25

Pile 50
(Ratio=1:1.5:3) Total for Pile
F1 4 7 7 1.25
F2 12 4 4 1.25
F3 0 6 6 1.25
Base
F4 0 4 4 0.6666667
(Ratio=1:1.5:3)
F5 0 9.5 9.5 1.75
F6 0 9.5 9.5 1.75
Total for Base
C1 4 1.25 1.25 7.00
C2 12 1.25 1.25 7.00
Padestal C3 0 1.25 1.25 6.25
Column C4 0 1.50 1.00 7.50
(Ratio=1:1.5:3) C5 0 1.67 2.00 7.00
C6 0 1.67 1.00 9.00
Total for Padestal Column
C1 3 1.25 1.00 36.09
C1 2 1.25 1.00 43.96
C2 2 1.00 1.00 43.96
Column
C3 1 1.00 1.00 22.97
(Ratio=1:1.5:3)
C5 0 1.67 2.00 7.00
C6 0 1.67 1.00 9.00
Total for Column
GB 1 480.00 1.00 1.50
Grade Beam 0.83 1.67
8 Casting (Ratio=1:1.5:3) 0.83 1.67
Total for Grade Beam
FB 38.45 0.83 1.25
FB 25.52 0.83 1.25
Floor Beam FB 22.67 0.83 1.25
(Ratio=1:1.5:3) FB 29.02 0.83 1.25
LB 9.35 0.83 1.25
Total for Floor Beam
Ground Floor
1 60.00 60.00 0.50
(Ratio=1:2:4)
Total for Ground Floor
3
Mezzanine floor 1 60.00 60.00 0.42
(Ratio=1:2:4) 54446.00 1.00 0.33
Total for Mezzanine floor
1 240.00 0.50 0.50
Lintel 0 127.94 0.83 0.42
(Ratio=1:1.5:3) 0 0.00 0.00 0.00
Total for Lintel
0 19.67 9.35 0.54
Stair
0 127.94 0.83 0.42
(Ratio=1:1.5:3)
Total for Stair
13.20 12.20 0.83
Water Tank 13.20 12.20 0.42
(Ratio=1:1.5:3) 50.80 5.00 0.83
Water Tank
(Ratio=1:1.5:3)
Total for Water Tank

Pile
16 mm 55
All Pile
8 mm 4.178328
Total for Pile
Base
No of footing No of Bar Avg. length
F1 4 76 8 0.27
F2 12 68 7.11942257 0.27
F3 12 mm 0 58 6.1351706 0.27
(TOP &
F4 BOTTOM) 0 11 4 0.27
F5 0 0.48
F6 0 0.48
Total for Base
Padestal Column
C1 4 8 9.00 0.75
C2 12 8 9.00 0.75
C3 0 8 9.00 0.75
20 mm
C4 0 8 7.50 0.48
0 14 10.50
C4 0 14 10.50 0.48

C1 4 17 2.22 0.19
C2 12 17 2.00 0.19
10 mm
C3 0 17 2.00 0.19
C4 0 0 5.00 0.19
Total for Padestal Column

Column
C1 3 8 39.09 0.75
C1 2 8 46.96 0.75
C2 2 8 46.96 0.75
20 mm
C3 1 8 24.97 0.48
14 10.50
C4 14 10.50 0.48

C1 3 88 4.44 0.19
C1 2 110 4.00 0.19
10 mm
C2 2 110 4.00 0.19
C3 1 55 0.00 0.19
Total for Column
Reinforcement Floor Beam
Calculation

Total for Grade Beam


0 88 2.22 0.19
Stair 0 110 2.00 0.19
(Ratio=1:1.5:3)
Total for Stair
1 463 12.20 0.19
1 77 13.20 0.19

Water Tank
10
(Ratio=1:1.5:3)
1 124 13.20 0.19
Water Tank
10 1 132 13.20 0.19
(Ratio=1:1.5:3)
1 33 13.20 0.19
1 31 12.20 0.19
1 81 5.00 0.19
Total for Water Tank
Grade Beam
GB-1 20 mm 1 5.00 480.00 0.75
20 mm 1 1.00 320.00 0.75
10 mm 1 2.00 480.00 0.19
GB-1 1 0 5.33 0.19
10 mm
GB-2
Total for Grade Beam
Ground Floor
12 mm 1 80 38.45 0.27
12 mm 1 55 25.52 0.27
0 87.00 0.19
10 mm 0 45.5 0.19
Total for Ground Floor
Mezzanine Floor
0 0 0.00 0.19
0 0 0 0.19
10 mm
0 0 0.00 0.19
0 0 25 0.19
Total for Mezzanine Floor
Lintel
10 mm 1 4.00 240.00 0.19
8 mm 0 160 0.814 0.12
Total for Lintel
Base
F1 4 7 7 1.25
F2 12 4 4 1.25
F3 0 6 6 1.25
F4 0 4 4 0.6666667
F5 0 9.5 9.5 1.75
F6 0 9.5 9.5 1.75
Total for Base
Padestal Column
C1 4 1.25 1.25 7.00
C2 12 1.25 1.25 7.00
C3 0 1.25 1.25 6.25
C4 0 1.50 1.00 7.50
C5 0 1.67 2.00 7.00
C6 0 1.67 1.00 9.00
Total for Padestal Column

Column
C1 3 1.25 1.00 36.09
C1 2 1.25 1.00 43.96
Wooden Shutter C2 2 1.00 1.00 43.96
C4 1 1.00 1.00 22.97
Total for Column
Floor Beam
FB 4 38.45 0.83 1.25
FB 9 25.52 0.83 1.25
FB 2 22.67 0.83 1.25
FB 2 29.02 0.83 1.25
LB 3 9.35 0.83 1.25
Total for Floor Beam
Grade Beam
GB-1 1 1.00 1.50 480.00
GB-2 0 0.83 1.67 0.00
GB-2 0 0.83 1.67 0.00
Total for Padestal Column
Ground Floor
4 60.00 60 0.4166667
Total for Ground Floor
Lintel
1 0.50 0.50 240.00
Total for Lintel
Ground Floor 1 60.00 60.00
NCF Mezzanine Floor 2 736.27 0.00
Total for NCF
Ground Floor 1 60.00 60.00
Floor Tiles Mezzanine Floor 2 843.48
Total for Floor Tiles
10" B/W 1.00 240.00 0.83 2
10" B/W 150.00 0.83 13
10" B/W 50.00 0.83 10
Brick Work
5" B/W 1.00 240.00 0.41666667 20
5" B/W 200.00 0.41666667 13
5" B/W 50.00 0.41666667 10
Diduct for Window
Plastering
Distempering
Paintinig
(Inner Wall
Weather (Outer
Wall
Total
Over Head Expense
Profit
Grand Total
Area
Unit Rate

Note:
1) Above Rate is Excluded of VAT, AIT & TAX.
Date: 3/12/2014
ivil BOQ .
Unit Rate
Quantity Total Unit Amount (Tk.)
(Tk.)

2268.00
3024.00
0.00
5,292.00
0.00
0
0 Cft 4.00 21,168.00

162
96 46
0
0 7,458.00

0 Cft 17.00 126,786.00 31


7200.00 25
25
324
192
0

4,527.60
0 SFT - -

3600 3.00 13,582.80

3,704 3,704.40 3.00 11,113.20

1,588 1,587.60 3.00 4,762.80

196
192
0
0 3,988.00 Sft 28.00 111,664.00
0
0
3600

49
48 Cft 200.00 19,400.00
0
97.00
97.00
0
0
0

0
0
245.00
240.00
0.00
0
0
0
485.00
43.75
131.25
0.00
0.00
0.00
0.00
175.00
135.33
109.91
87.93
22.97
0.00
0.00
356.14
720.00
0.00
0.00 5,108.14 Cft 250.00 1,277,033.79
720
0.00
0.00
0.00
0.00
0.00
0.00
1800 736.273

1800.00

1512.00
0
1512.00
60.00
0.00

60.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0
0.0
0

658.27
1572.44 0.4166667
0.00
0.00 10.714286
0.00 13.690476
0.00 8.3333333
2230.70101

216.53 10356.353
649.60
0.00
0.00

0.00

28.38
76.69
0.00
0.00
971.203874

705.35
564.95
564.95
96.11

0.00

220.32
165.41
165.41
0.00
2482.51
14955.90 Kg 58 867442.16260425
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
1061.73
191.05
307.66
327.51
81.88
71.09
76.13
2117.04

1804.46
240.59
180.45
0.00
0
2225.50

832.58
379.91
0.00
0.00
1212.49

3367.64 525.94
0.00 808.04
0.00 525.94
0.00 808.04
3536.02

180.45
0.00
180.445701 119.1
270.02
140
240
0
0
0
0
380

140.0
420.0
0.0 3920
0.0
0.0
0.0
560.00

487.2
395.7
351.7 6,575.39 Sft 25.00 164,384.63
91.9
1,326.44

392.8
593.0
117.5
149.3
76.4
1,328.94

2400.0
0.0
0.0
2400.00

100
100

480.00
480.00
3600

1472.546001 5,072.55 Sft 18.00 91,305.83

5072.546
762.35
1686.96 2,449.31 Sft - -
2449.31
400.00 400.00 Cft 160.00 64,000.00
- - Cft 160.00 -
- - Cft 160.00 -
4,800.00 4,800.00 Sft 160.00 768,000.00
- - Cft 160.00 -
- - Cft 160.00 -
-
960.00 960.00 Sft 18.00 17,280.00

5,200.00 5,200.00 Sft 22.00 114,400.00


1331.98

- Sft 22.00 -
3,672,323.21
3.50% 128,531.31
7.00% 257,062.62
4,057,917.15
Sft 8,195.0
Per Sft 495.17

You might also like