You are on page 1of 77

BASIC RATES

(B) USAGE RATES OF PLANT & MACHINERY


Description of Output of Machine Usage Rates in Rs.
Sr. No. Rate add
Machine Activity Unit Output Unit Rate
90%
Supplying compressed
PM-001 Air Compressor 210 cfm cfm 210.00 per hour 206.00 391.40
air
PM-002 Batch mix HMP 40-60 TPH BM, DBM, SDBC, PM t/h 50.00 per hour 7,150.00 13,585.00
PM-003 Batch type HMP 30/40 TPH BM, DBM, SDBC, PM t/h 35.00 per hour 7,150.00 13,585.00
PM-004 Bitumen boiler oil fired Heating of bitumen
200 litre Heating of bitumen litre / h 400.00 per hour 128.00 243.20
1000 litre litre / h 2000.00 per hour 138.00 262.20
Applying bitumen tack
PM-005 Bitumen emulsion pressure distributor sqm/h 1750.00 per hour 516.00 980.40
coat
PM-006 Concrete mixer 0.28/0.4 cum Mixing of ingradients cum/h 2.50 per hour 150.00 285.00
PM-007 Crane upto 8T Lifting of materials per hour 550.00 1,045.00
PM-008 cum/h 200.00 1,423.00 2,703.70
Dozer D 50 Dozing cutting per hour
cum/h 100.00 1,423.00 2,703.70
PM-009 Electric generator set, 125 KVA Electricity generation KVA 100.00 per hour 450.00 855.00
PM-010 Emulsion Sprayer with Tractor Spraying of Emulsion per hour 516.00 980.40
Applying bitumen tack Sqm/hou
PM-010 Bitumen Pressure Distributor 1750.00 Per hour 692.00 1,314.80
coat r
PM-011 Front end-loader 1 cum bucket capacity @ Loading Aggregates cum/h 45.00 520.00 988.00
per hour
45 cum/hour Loading Soil cum/h 100.00 520.00 988.00
PM-012 Hydraulic broom with tractor Surface cleaning sqm/h 1250.00 per hour 230.00 437.00
PM-013 Hydraulic Excavator 0.9 cum Excavation cum/h 100.00 per hour 840.00 1,596.00
PM-014 Hydraulic self propelled chip spreader Surface Dressing sqm/h 1500.00 per hour 1,700.00 3,230.00
Pavement breaking &
PM-015 Jack Hammer with tractor cum/h 05. to 1 per hour 83.00 157.70
rock drilling
PM-016 Joint Cutting Machine with 2-3 blades Cutting of Joints h per hour 405.00 769.50
Mixing of bituminous
PM-017 Mixall 6-10 t capacity t/h 8.00 per hour 810.00 1,539.00
materials
PM-018 200.00 1,545.00 2,935.50
Motor Grader Scarifier & levelling cum/h per hour
50.00 1,545.00 2,935.50
Vibrating cement
PM-019 Needle vibrator cum/h 3.50 per hour 101.00 191.90
concrete mix
PM-020 Paver finisher Laying/spreading t/h 75.00 per hour 629.00 1,195.10
PM-021 Plate compactor Compaction cum/h per hour 101.00 191.90
PM-022 Plate vibrator Compaction cum/h per hour 107.31 203.89
PM-023 Screed vibrator Compaction cum/h per hour 107.31 203.89
Compaction of Sub-base/
PM-024 Smooth wheeled 80-100 kN tandem roller cum/h 30.00 per hour 297.00 564.30
Asphalt
PM-025 Stone crusher (Integrated) of 200 TPH Crushing of Spalls t/h 200.00 per hour 11,760.00 22,344.00
PM-026 Three wheel 80-100 kN Static Roller Compaction/ Rolling 297.00 564.30
Earth:- Embankment or
sub-grade cum/h 80/70 297.00 564.30

Sub-base G-I cum/h 10.00 297.00 564.30


Sub-base G-II/G-III cum/h 8.00 297.00 564.30
WMM cum/h 16.00 297.00 564.30
BUSG cum/h 10.00 297.00 564.30
per hour
BM 50/75 mm cum/h 12.00 297.00 564.30
Premix 20 mm sqm/h 250.00 297.00 564.30
Seal Coat sqm/h 500.00 297.00 564.30
Surface Dressing 1st
sqm/h 400.00 297.00 564.30
Coat
Surface Dressing
sqm/h 500.00 297.00 564.30
2ndCoat
PM-027 Tipper 5.5 cum/10 t Carriage cum/trip 5.50 per hour 200.00 380.00
PM-028 Tractor with Disc Harrows Pulverisation of soil cum/h 80.00 per hour 234.00 444.60
Ripping Pavements,
PM-029 Tractor with ripper @ 60 cum per hour cum/h 60.00 per hour 234.00 444.60
uprooting trees
Transportation of
PM-030 Tractor with trolley t/trip 3 to 5 per hour 234.00 444.60
materials
PM-031 Tractor with Rotavator Scarifier cum/h 25.00 per hour 234.00 444.60
PM-032 Truck 10 t capacity Carriage cum/trip 5.50 per hour 200.00 380.00
PM-033 Compaction of soil WMM cum/h 100.00 994.00 1,888.60
Vibratory roller 80-100 kN per hour
Compaction of BM cum/h 60.00 994.00 1,888.60
Water tanker 6 kl capacity (Truck
PM-034 Carriage of water litre / h ### per hour 200.00 380.00
Mounted)
PM-035 Wet mix plant (Pug Mill) Wet Mix cum/h 25.00 per hour 777.00 1,476.30
BASIC RATES
(A) Labour
Sl. No. Description of Labour Unit Rate (Rs.)
L-01 Bhisti day 260.00
L-02 Bitumen Sprayer day 280.00
L-03 Blacksmith day 350.00
L-04 Blaster day 390.00
Beldar day 235.00
Coolie day 235.00
L-05 Carpenter 1st Class day 400.00
L-06 Chips spreader day 222.00
L-07 Chiseller day 222.00
L-08 Dresser (Skilled) day 227.00
L-09 Driller day 390.00
L-10 Electrician day 350.00
L-11 Fitter day 285.00
Hammer Man day 200.00
L-12 Mason (1st class) day 380.00
L-13 Mason (2nd Class) day 350.00
L-14 Mate day 250.00
L-15 Mazdoor (Unskilled) day 235.00
L-16 Mazdoor (Semi skilled) day 235.00
L-17 Mazdoor (Skilled) day 250.00
L-18 Painter (Ist class) day 385.00
L-19 Plumber day 350.00
L-19 Riveter day 290.00
L-20 Surveyor day 320.00
Welder day 275.00
L-21 White Washer day 245.00
CHANGE POINT
YEAR :– 2019-20

PRADHAN MANTRI GRAM SADAK YOJANA

3
RCPLWEA (Additional)
4 Sonebhadra State: Uttar Pradesh
1 District: Sonebhadra Sonebhadra
2 Block: Duddhi Duddhi
5 Name of Work: Constrcution of Bridge on Nala at Km.
20 on Windamgunj Piparkhad to
Auradad Road (Package No.: UP-67163)

6 From to Windamgunj Auradad


Piparkhad
7 Package No: Package: UP-67163
8 Bridge Length: 40.100
9 Reference Pillar
10 Width of Bridge 8.500 8
11 In Open Area 31.600
12 Local Earth 33874.21
13 Carted Earth 14322.15

14 EXISTING SURFACE
S.NO. CH Width EXISTING LENGTH Width
SURFACE

1 0.000 13.000 3.00 3.00 M BT 13.000 3.00


2 13.000 19.000 3.00 3.00 M BT 6.000 3.00
3 19.000 20.150 3.00 3.00 M BT 1.150 3.00
TOTAL 20.150
2 0.000 0.000 0.00 3.75 M BT 0.000 0.00
4 0.000 0.000 0.00 3.75 M BT 0.000 0.00
TOTAL 0.000
2 0.000 0.000 0.00 EARTHEN 0.000 0.00
TOTAL 0.000
TOTAL= 20.150 -19.950
1 TYPE OF PROPOSAL U
2 EXISTING B.T.
3 SURFACE
FACILITIES ACCESSED TYPE
( USE A/B/C/D) A
4 EXISTING ROAD 3.00 m
5 PROPOSED ROAD 5.50 m
6 ROADWAY 9.00 m
15 QUARRY RATE
QUARRY DISTANC ROBERTSG DALA TO CHOPAN TO CH 0.000 TO TOTAL DISTANCE
E TO ANJ TO STARTIN STARTING MIDDLE OF Bridge
ROBERTS STARTUNG G CHAINAGE
GANJ CHAINAGE CHAINAG (CH 0.000)
E (CH
Sukrut 26 83 0.000)
- - 20 129
Dalla - 51 - 20 71
Chopan - - 59 20 79

16 CARTAGE With CP
1 UPTO 30KM #REF!
2 51 to 75 9.00
3 76 to 100 8.00
4 101 to 200 7.50
5 >200 km #REF!
6 KACHCHA 15.90

17 BITUMEN RATE
REFINERY DISTANC ROBERTSG 0.00 TO TOTAL RATE DATE
E TO ANJ TO MIDDLE DISTANCE
ROBERTS STARTUNG OF ROAD
GANJ CHAINAGE
MATHURA 665 83 20 1536
Jhansi 580 83 20 1366 BITUMEN DATE
VG-30 28940.00 16/12/2019
SS-1 32965.00 16/12/2019

18 No of Junction , Curves
1 Nos 15
2 AREA OF JUNCTION AT CH 0.000 #REF!
3 AREA OF JUNCTION AT CHAKROADS #REF!
4 NO OF CURVES 218
5 TOTAL WIDENING OF CURVES 1652.98
6 5TH KM STONE 9
7 KM STONE 31
8 HECTOMETER STONES 162
9 TRAFFIC SIGNS 218
10 DIRECTION AND PLACE IDENTIFICATION SIGNS 436
WITH SIZE MORE THAN 0.9 SQM SIZE BOARD
11 INFORMATORY BOARDS WITH LOGO 2
12 LOGO BOARD WITH DIAMOND SIGN 2
13 LOGO BOARDS 20
14 VILLAGE NAME PLATE 12
15 OVERHEAD @ 10%
16 CONTRACTOR PROFIT @ 10%
17 REDUCTION FACTOR ( RATE X1.125/1.21)= 0.9297520661
18 LABOUR CESS 1%
19 ABADI LENGTH
S.NO. Abadi portion Chaniage LENGTH POPULATION
1 LOTE VILLAGE 1.200 1.900 700.00 331
2 MOHAN LAINE 9.100 9.800 700.00 550
3 VILLAGE
KHAJURA VILLAGE 12.400 12.700 300.00
4 KHAJURA VILLAGE 13.800 13.950 150.00 992
5 KHAJURA VILLAGE 15.270 15.370 100.00
6 CHANDU BAHRA 15.650 16.800 1150.00 331
7 VILLAGE
BIRAN BAHRA 17.600 19.350 1750.00
VILLAGE
8 JAGENDRA VILLAGE 19.500 20.150 650.00 479

TOTAL 5500.00 2683.00


20 U- Type Deep Drain 0.000
S.NO. NAME LENGTH
1 LOTE VILLAGE 0.000
2 MOHAN LAINE VILLAGE 0.000
3 KHAJURA VILLAGE 0.000
4 KHAJURA VILLAGE 0.000
5 KHAJURA VILLAGE 0.000
6 CHANDU BAHRA VILLAGE 0.000
7 BIRAN BAHRA VILLAGE 0.000
8 JAGENDRA VILLAGE 0.000

21 KC Drain 2100.000
S.NO. NAME LENGTH
1 LOTE VILLAGE 0.000
2 MOHAN LAINE VILLAGE 400.000
3 KHAJURA VILLAGE 100.000
4 KHAJURA VILLAGE 100.000
5 KHAJURA VILLAGE 250.000
6 CHANDU BAHRA VILLAGE 0.000
7 BIRAN BAHRA VILLAGE 100.000
8 JAGENDRA VILLAGE 100.000

22 HUME PIPE RATE


S.NO. DIA OF PIPE Basic rate Cartage @15% total
1 100 MM NP-3 195.000 29.250 224.25
2 350 MM NP-3 870.000 130.500 1000.50
3 600 MM NP-3 1560.000 234.000 1794.00
4 900 MM NP-3 3385.000 507.750 3892.75
5 1000 MM NP-3 4000.000 600.000 4600.00
23 Maint Cost for five years
1 Ist Year 67600.00
2 IInd Year 111800.00
3 IIIrd Year 156080.00
4 IV th Year 200100.00
5 V th Year 244430.00

24 EXISTING CULVERT
1X600 MM H.P. CULVERT
S.NO Km NO Type Span/ Dia. (m) Condition
1 Km - 03 1 H.P. CULVERT 1X0.600 Good.
2 Km - 11 1 H.P. CULVERT 1X0.600 Good.
3 Km - 17 1 H.P. CULVERT 1X0.600 Good.
4 Km - 18 1 H.P. CULVERT 1X0.600 Good.
5 Km - 19 1 H.P. CULVERT 1X0.600 Good.
Total 5
1X900 MM H.P. CULVERT
S.NO Km NO Type Span/ Dia. (m) Condition
1 Km - 15 1 H.P. CULVERT 1X0.900 Good.
Total 1
1x1000 MM H.P. CULVERT
S.NO Km NO Type Span/ Dia. (m) Condition
1 Km - 14 1 H.P. CULVERT 1X1.000 Good.
2 Km - 15 1 H.P. CULVERT 1X1.000 Good.
3 Km - 16 1 H.P. CULVERT 1X1.000 Good.
4 Km - 17 1 H.P. CULVERT 1X1.000 Good.
Total 4
R.C.C. CULVERT 1x1.50 M
S.NO Km NO LENGTH NO Type Span/ Dia. (m)
1 Km - 05 1 1.50 1 R.C.C. CULVERT 1X1.500
2 Km - 05 1 1.50 1 R.C.C. CULVERT 1X1.500
3 Km - 05 1 1.50 1 R.C.C. CULVERT 1X1.500
4 Km - 06 1 1.50 1 R.C.C. CULVERT 1X1.500
5 Km - 06 1 1.50 1 R.C.C. CULVERT 1X1.500
6 Km - 06 1 1.50 1 R.C.C. CULVERT 1X1.500
7 Km - 07 1 1.50 1 R.C.C. CULVERT 1X1.500
Total 7 10.50
R.C.C. CULVERT 1x2.00 M
S.NO CH NO LENGTH NO Type Span / Dia. (m)
1 Km - 02 1 2.00 1 R.C.C. CULVERT 1X2.000
2 Km - 02 1 2.00 1 R.C.C. CULVERT 1X2.000
3 Km - 20 1 14.00 1 R.C.C. CULVERT 7X2.000
4 Km - 20 1 2.00 1 R.C.C. CULVERT 1X2.000
5 Km - 20 1 2.00 1 R.C.C. CULVERT 1X2.000
Total 4 22.00 Total Length
R.C.C. CULVERT 1x3.00 M
S.NO CH NO LENGTH NO Type Span / Dia. (m)
1 Km - 04 1 3.00 1 R.C.C. CULVERT 1X3.000
2 Km - 05 1 3.00 1 R.C.C. CULVERT 1X3.000
3 Km - 06 1 3.00 1 R.C.C. CULVERT 1X3.000
4 Km - 08 1 18.00 1 R.C.C. CULVERT 6X3.000
5 Km - 16 1 6.00 1 R.C.C. CULVERT 2X3.000
6 Km - 17 1 3.00 1 R.C.C. CULVERT 1X3.000
7 Km - 17 1 3.00 1 R.C.C. CULVERT 1X3.000
Total 7 33.00 Total Length
G/TOTAL LENGTH OF CULVERTS 32.50
G/TOTAL NO OF EXISTING 28
CULVERTS

25 PROPOSED CULVERT
1X350 MM H.P. CULVERT
1 X 350MM NEW 10
1X600 MM H.P. CULVERT
1 X 600MM NEW 20
1X1000 MM H.P. CULVERT
1 X 1000MM NEW 9
1x2.000 R.C.C. CULVERT
1x2.00 m NEW 2
1x3.000 R.C.C. CULVERT
1x3.00 m NEW 5
TOTAL 46
RETAINING WALL
S.NO CH LENGTH
1 0.000 1.000 1000.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 1000.000
TOE WALL
S.NO CH LENGTH
1 0.000 0.500 500.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 500.00
BREAST WALL
S.NO CH LENGTH
1 0.000 0.300 300.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 300.00
CAUSEWAY
S.NO CH LENGTH
1 0.000 0.450 450.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 450.00
BOX CULVERT
S.NO CH NO DEDUCTIONS BOX CULVERT
1 Km - 07 3X7.5X4 1 BOX CULVERT
2 Km - 08 3X7.5X4 1 CUASEWAY
3 0 0 0 CC ROAD
4 0 0 0
5 0 0 0
6 0 0 0
TOTAL= 2
PARAPET WALL
S.NO CH LENGTH NOS
1 0.000 0.700 700.000 311
2 0.000 0.000 0.000 0
3 0.000 0.000 0.000 0
4 0.000 0.000 0.000 0
5 0.000 0.000 0.000 0
6 0.000 0.000 0.000 0
TOTAL= 700.000 311
WIRE CRATES
S.NO CH LENGTH HEIGHT
1 15.950 16.145 155.000 AVG. 4.00
2 17.200 17.400 180.000 AVG. 3.00
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 335.000

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
Crust Proposed Proposed GSB Proposed Width Proposed Width Propose
Width WIDENING G-2 G-3 d Width
Excvn Prime
Thickness Width Thickness Width Thickness Width
0.175 5.800 0.175 2.800 0.075 5.500 0.075 5.500 5.500
0.150 5.800 0.150 2.800 0.100 5.500 0.075 5.500 5.500
0.110 5.800 0.100 2.800 0.150 5.500 0.075 5.500 5.500

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000


0.175 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000


LOADING 35.000
UNLOADING 18.000
CC ROAD
0.00
360.00
0.00
0.00
250.00
0.00
0.00
0.00

610.00
Condition
Good.
Good.
Good.
Good.
Good.
Good.
Good.

Condition
Good.
Good.
Damaged
Good.
Good.
Condition
Good.
Good.
Good.
Damaged
Good.
Good.
Good.
24.100
24.100
450.000
610
1108.200
BASIC RATES
(C) Material
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-001 110mm PVC pipe m 110.00
M-002 Aggregate - For 37.5 mm Maximum size - 22.4 mm to 5.6 mm cum
M-003 Aggregate - For 37.5 mm Maximum size - 45 mm to 22.5 mm cum
M-004 Aggregate - For 37.5 mm Maximum size - Below 5.6 mm cum
M-005 Aggregate - For 53 mm Maximum size - 22.5 mm to 5.6 mm cum
M-006 Aggregate - For 53 mm Maximum size - 63 mm to 45 mm cum
M-007 Aggregate - For 53 mm Maximum size - Below 5.6 mm cum
M-008 Aggregate - Grading I (40 mm nominal Size) 10 mm - 5 mm cum
M-009 Aggregate - Grading I (40 mm nominal Size) 25 mm – 10 mm cum
M-010 Aggregate - Grading I (40 mm nominal Size) 37.25 mm - 25 mm cum
M-011 Aggregate - Grading I (40 mm nominal Size) 5 mm and below cum
M-012 Aggregate - Grading II (19 mm nominal Size) 10 mm - 5 mm cum
M-013 Aggregate - Grading II (19 mm nominal Size) 25 mm – 10 mm cum
M-014 Aggregate - Grading II (19 mm nominal Size) 5 mm and below cum
M-015 Aggregate 10 mm cum 800.00
M-016 Aggregate 20 mm cum 1,450.00
M-017 Aggregate 40 mm cum 830.00
Aggregate- Crushable type such as moorum or Gravel for
M-018 cum
Grading I
Aggregate- Crushable type such as moorum or Gravel for
M-019 cum
Grading II
Aggregate- Crushable type such as moorum or Gravel for
M-020 cum
Grading III
M-021 Aggregate-Grading I 90 mm to 45 mm cum 450.00
Aggregate-Grading I 90 mm to 45 mm cum 450.00
M-022 Aggregate-Grading II 63 mm to 45 mm cum 520.00
Aggregate-Grading II 63 mm to 45 mm cum 520.00
M-023 Aggregate-Grading III 53 mm to 22.4 mm cum 740.00
Aggregate-Grading III 53 mm to 22.4 mm cum 740.00
M-024 Aggregates 22.4 mm to 2.36 mm for wet mix macadam cum
M-025 Aggregates 45 mm to 22.4 mm for wet mix macadam cum
M-025 Aluminium sheeting (1.5 mm thick) sqm
M-026 Aluminium Studs 100 mm x 100 mm fitted with lense reflectors Nos.
Angle iron 50mm x 50mm x 5 mm for lugs kg 40.00
M-027 Bamboo (1st Class) 85 mm - 100 mm dia, 2.0 m long No.
M-028 Bamboo (1st Class) 85 mm - 100 mm dia, 2.5 m long No.
M-028 Bamboo (1st Class) 85 mm - 100 mm dia, 3.0 m long No.
M-029 Bamboo (1st Class) 85 mm - 100 mm dia, 4.5 m - 5.5 m long No.
M-028 Bamboo (2nd Class) 75mm dia, 1.8 m - 2.5 m long No.
M-029 Bamboo (2nd Class) 75mm dia, 2.1 m - 3.0 m long No.
M-030 Barbed wire kg 57.75
M-031 Binding Material cum 460.00
M-032 Binding wire kg 57.75
M-033 Bitumen (Crumb Rubber Modified) tonne
M-034 Bitumen (Natural Rubber Modified) tonne
M-035 Bitumen (Polymer Modified) tonne
M-036 Bitumen (VG-30) t
M-037 Bitumen (VG-10) t 28,940.00
M-038 Bitumen Emulsion (RS-1) t
M-039 Bitumen Emulsion (SS-1) t 32,965.00
M-040 Bituminous sealant litre 40.20
M-041 Blasted rubble cum 1,565.60
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-042 Blasting material kg
M-043 Bond stone (400 mm x 150 mm x 150 mm) No.
M-044 Brick 1st Class No. 6.19
Brick bats cum 1,238.00
M-045 Cement t 5,560.00
M-046 Cement Primer litre 68.25
M-047 Chlorprene Elastomer or Closed Cell Foam Sealing Element m
M-048 Compensation for earth taken from private land cum 14.00
M-049 Compressible Fibre Board sqm 682.50
M-050 Copper plate kg
M-051 Corbelling Stones (300 mm x 150 mm x 150 mm) No.
M-052 Corrosion Resistant Structural Steel Grating kg 69.00
M-053 Credit for excavated rock found suitable for use cum
M-054 Crow bars 40 mm dia (hire charges) hour
M-055 Crushed Sand or Grit Passing 2.36 mm and retained on 180 micro cum 600.00
M-056 Crushed Slag cum
22.4-53 mm sukrut cum 740.00
11.2 mm Dala cum 1,080.00
Dust cum 505.00
M-057 Crushed Stone Aggregate 26.5 mm to 75 micron cum 775.00
13.2 mm 805.00
11.2 mm Dala 780.00
Stone Chips 13.2 mm to 5.6 mm (2part 13.2mm+one part 796.70
M-058 cum
11.2mm)/3
Crushed Stone Chipping 6.7 mm size 100% passing 11.2 mm 760.00
M-059 cum
and retained on 2.36 mm
Crushed Stone Chipping 6.7 mm size 100% passing 9.5 mm and 755.00
M-060 cum
retained on 2.36 mm
M-061 Crushed Stone chipping 9.5 mm nominal size cum
Crushed Stone Coarse Aggregate Passing 53 mm and retained
M-062 cum
on 2.8 mm
M-063 Curing compound litre 63.50
M-064 Debonding strips m 100.00
M-065 Edge Stone (450 mm x 350 mm x 100 mm) No. 66.00
M-066 Edge Stone (450 mm x 350 mm x 200 mm) No. 66.00
M-067 Elastomeric bearing assembly Nos.
M-068 Electric Detonator each
M-069 Epoxy Paint litre 275.00
M-070 Epoxy Primer litre 126.00
M-071 Farmyard manure cum
M-072 Fevicol adhesive kg 215.30
M-073 Filter media cum 531.90
M-074 Fine aggregate/Crushed sand 2.36 mm to 75 micron cum
20 mm thick compressible fibre board 7.5 m long and 250 mm 682.50
sqm
deep
M-075 Galvanised angle kg
M-076 Galvanised angle Section 100 mm x 100 mm of 12 mm thickness kg
M-077 Gelatine 80 per cent kg
M-078 GI Pipe 100 mm dia m 299.25
M-079 GI Pipe 50 mm dia m
M-080 GI wires kg 440.00
M-081 Graded stone aggregate cum
Granular material (Natural occuring, soil gravel mixture / quarry
M-082 cum
waste, kankar, laterite, dhandla
Geroo quintel 2,500.00
M-083 Hand Broken Metal 40 mm size cum
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-084 Indigo kg 225.00
M-085 Interlocking Blocks with 60 mm thickness sqm
M-086 Interlocking Blocks with 80 mm thickness sqm 702.20
M-087 Joint filler board sqm 60.00
M-088 Jute netting, open weave 25 mm square opening sqm
M-089 Jute rope 12 mm dia m 51.70
M-090 Key Aggregates passing 22.4 mm and retained on 2.8 mm cum
M-091 Lime t 667.00
M-092 Lime putty t 6,000.00
M-093 Local Wood Piles (1st Class) 150-200 mm dia ,6m long No.
M-094 Local Wood Piles (1st Class) 100 mm x 75 mm cum
M-095 Loose stone cum 385.00
M-096 MS clamps Nos. 16.00
M-097 MS Flat / Structural Steel t 33,898.00
M-098 MS Sheet Tube (47 mm x 47 mm x 12 SWG Sheet) kg 60.00
M-098 2 nos. MS tubes 75mx75mm of 12 SWG sheet 2650 mm long kg 60.00
M-099 MS Sheet 1.5 mm thick sqm 176.40
M-100 MS Sheet 2 mm thick sqm 840.00
MS sheet 1.6 mm thick sqm 840.00
1 No. MS tube 47mm x 47mm of 12 SWG 1100 mm long kg 60.00
Angle iron 50mm x 50mm x 5 mm for lugs kg 40.00
M-101 Nuts, Bolts and Rivets t 65,000.00
M-102 Paint (Synthetic Enamel) litre 273.00
Paint conforming litre 198.55
Paint ready mixed litre 230.00
M-103 Plasticizer litre
M-104 Polythene sheet (125 micron) sqm 31.00
M-105 Polythene Sheething Nos. 20.00
M-106 Quarried Stone 150-200 mm size cum
M-107 RCC Pipe NP3 (1200 mm dia) m
M-108 RCC Pipe NP3 (1000 mm dia) m 3,996.00
M-109 RCC Pipe NP3 (750 mm dia) m
M-110 RCC Pipe NP3 (600 mm dia) m 1,560.00
M-111 RCC Pipe NP3 (500 mm dia) m 1,560.00
M-112 RCC Pipe NP4 (1200 mm dia) m
M-113 RCC Pipe NP4 (1000 mm dia) m
M-114 RCC Pipe NP4 (750 mm dia) m
M-115 RCC Pipe NP4 (600 mm dia) m
M-116 RCC Pipe NP4 (500 mm dia) m
Brick Edging KM 75,000.00
organo silane nano technology Nanotac KG 1,200.00
Nano Technology Based Organo Silane Compound @ 1,350.00
KG
0.1%Zycotherm
M-117 Red-oxide Primer litre 78.75
M-118 Road marking paint litre
Recron Fibre @ 100gm per 50 Kg cement KG 700.00
M-119 Sand (Coarse) cum 500.00
M-120 Sand (Fine) cum 450.00
M-121 Seeds kg
M-122 Steel Pipe 50 mm dia m
M-123 Steel Reinforcement (HYSD Bars) t 41,000.00
M-124 Steel Reinforcement (MS Round Bars) t
M-125 Steel Reinforcement (TMT Bars) t
M-126 Stone Boulder of size 150 mm and below cum
M-127 Stone Chips 12 mm size cum
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-128 Stone Chips 13.2 mm to 5.6 mm cum
M-129 Stone Crushed Aggregate 11.2 mm to 0.09 mm cum
M-130 Stone for Coarse Rubble Masonry 1st Sort cum
M-131 Stone for Coarse Rubble Masonry 2nd Sort cum
M-132 Stone for Random Rubble Masonry cum 1,530.60
M-133 Stone for Stone Set Pavement (300 mm x 200 mm x 150 mm) No. 9.05
M-134 Stone Screening - Type A 13.2 mm for Grading-1 cum
M-135 Stone Screening - Type A 13.2 mm for Grading-2 cum
M-136 Stone Screening - Type B 11.2 mm for Grading-2 cum 1,040.00
M-137 Stone Screening - Type B 11.2 mm for Grading-3 cum 1,040.00
M-138 Stone spall cum 400.00
Through and bond stone No. 9.50
M-139 Traffic cones No.
M-140 Water kl 50.00
Water for mixing and curing for 14-days day 192.00
M-141 Well graded Granular Base Material - Grading A 2.36 mm below cum
Well graded Granular Base Material - Grading A 26.5 mm to 4.75
M-142 cum
mm
Well graded Granular Base Material - Grading A 53 mm to 26.5
M-143 cum
mm
M-144 Well graded Granular Base Material - Grading B 2.36 mm below cum
Well graded Granular Base Material - Grading B 26.5 mm to 4.75
M-145 cum
mm
M-146 Well graded Granular Base Material - Grading C 2.36 mm below cum
Well graded Granular Base Material - Grading C 9.5 mm to 4.75
M-147 cum
mm
M-148 Well Graded Material for Sub-Base - Grading I 2.36 mm below cum

M-149 Well Graded Material for Sub-Base - Grading I 53 mm to 9.5 mm cum

Well Graded Material for Sub-Base - Grading I 9.5 mm to 2.36


M-150 cum
mm
Well Graded Material for Sub-Base - Grading I (from Kabarai 775.00
stone crusher)
M-151 Well Graded Material for Sub-Base - Grading II 2.36 mm below cum
Well Graded Material for Sub-Base - Grading II 26.5 mm to 9.5
M-152 cum
mm
M-153 Well Graded Material for Sub-Base - Grading II 9.5 mm to 2.36 m cum
M-154 Well Graded Material for Sub-Base - Grading III 2.36 mm below cum
M-155 Well Graded Material for Sub-Base - Grading III 4.75 mm to 2.36 cum
M-156 Well Graded Material for Sub-Base - Grading III 9.5 mm to 4.75 m cum
Edge blocks 60 m x 2 m 105.33
M-157 Wooden sleepers (250 mm x 250 mm x 125 mm) (hire charges) No.
State: Uttar Pradesh
PUBLIC WORKS DEPARTMENT, Sonebhadra

DETAILED PROJECT REPORT


FOR
CONSTRUCTION OF BRIDGE UNDER
RCPLWEA (ADDITIONAL)
YEAR :– 2019-20
Package: UP-67163
Name of Work: Constrcution of Bridge on Nala at Km. 20 on
Windamgunj Piparkhad to Auradad Road (Package
No.: UP-67163)

No. of Bridge in Package :- 1


Bridge Length: 40.100 Mtr.
CONSTRUCTION COST :- #VALUE! Lacs
MAINTENANCE COST :- 3.00 Lacs
TOTAL COST :- #VALUE! Lacs
BLOCK :- Duddhi

P.M.G.S.Y. Division
Public Works Department
Sonebhadra (U.P.)
PRADHAN MANTRI GRAM SADAK YOJANA
RCPLWEA (Additional)
Proforma - A

Package: UP-67163
PROPOSALS

Sl. No. District Name of Bridge No of Length Value (Lacs) Avg. Cost/Mtr. (Lacs)
Habitation (Mtr.)
s Coverd Construction Maint. Construction Maint.

1 Constrcution of Bridge on Nala at 9 40.100 #VALUE! 3.00 #VALUE! 0.07


Km. 20 on Windamgunj Piparkhad to
Sonebhadra

Auradad Road (Package No.: UP-


67163)

Total 9 40.100 #VALUE! 3.00 #VALUE! 0.07


PRADHAN MANTRI GRAM SADAK YOJANA
RCPLWEA (Additional)
PROFORMA-B
PACKAGE SUMMARY
Package: UP-67163 District: Sonebhadra
Name of Work: Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to Auradad Road (Package No.: UP-67163)

Sl. Name Name of Bridge Type of Proposed Cost of Length of Cost of Cost of Total Estimated Cost Average Cost per M.
No of Block Proposal length of Bridge Approach Approach Protection Work (Rs.) Lacs (Rs.) Lacs
Bridge Road Road + (Bridge + River)
Construction Maintenance Construction Maintenance
Diversion

From N/U M. Rs in Lacs M. Rs in Lacs Rs in Lacs Rs in Lacs Rs in Lacs


1 2 3 4 5 6 7 8 9 10 11 12 13

Constrcution of Bridge on
Nala at Km. 20 on
1 Duddhi Windamgunj Piparkhad to N 40.100 200.69 60.00 #VALUE! 30.19 #VALUE! 3.00 #VALUE! 0.07
Auradad Road (Package No.:
UP-67163)

Total Estimated without GST (in Lacs) 200.69 #VALUE! 30.19 #VALUE! 3.00 #VALUE! 0.07

Add 12% GST #VALUE! 0.00 #VALUE! 0.00


Add 1% Labour Cess - #VALUE! 0.00 #VALUE! 0.00
Total Cost with GST (In Lacs) Say #VALUE! 3.00 #VALUE! 0.07

Prepared By: Technical Scrutiny Done By:


Signature Signature
Name: Name:

Checked By: Co-Ordinator STA


Signature Signature
Name: Name:

Scrutinized By:
Signature
Name:
PRADHAN MANTRI GRAM SADAK YOJANA ( PMGSY)
CHECK LIST FOR P.I.U. & S.T.A.
( For Indvidual Bridge works with length more than15 m )
(To be filled by PIU)

Proforma C
(For Long Span Bridges only)
1. Location :- State: Uttar Pradesh District: Sonebhadra Block: Duddhi

2. Package No:- UP-67163

3. Name of the Road: From Windamgunj Piparkhad To Auradad

4. Total Length of Approach Road (m) - 60 m

Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to


5. Name of Proposed Bridge (if any) Auradad Road (Package No.: UP-67163)

6. Length of Proposed Bridge (Excluding Approaches) 40.100 m

7. Width of Bridge in m: 8.500 m

8. Through Route/ Link Route Nos as per Core Network.:


(i) Is the road a part of core network : YES / NO
if Yes, Sl no. of road CN-I : Sl no. of road CN -VI :
If Yes Through Route/ Link Route No. T- or L-

(ii) Name of the benefitted Habitation (s) (to be cross Sr.N Name of Habitations Population
checked with CN-VI) with population 1 KUDWA VILLAGE 806
2 KUDWA YADAV BASTI 0
3 KUDWA TUNIYA BASTI 1258
4 PANDU CHATAW 687
VILLAGE
5 GHICHORWA VILLAGE 180
6 KARIYA VILLAGE 511
7 NIMYA SUKAR 109
8 GULARIYA 192
9 AURADANDI VILLAGE 687
9 Total 4430

9. Whether the Road proposal was sanctioned earlier : Yes No √

(i) If Yes, please mention the Phase, MoRD Sanction letter No and Date of sanction :

(ii)

(iii) Whether any CD/ Causeway was Sanctioned at or nearby location with the road
proposal and whether the same was constructed or not (if yes, the details thereof with
chainage: NO.
(iv) Whether the roadwork has been completed or in progress and likely date of completion:

(v) If not, How the connectivity and movement of traffic was ensured:

The Existing Road is in Running Stage and traffic is moving.


(vi) Reasons for not proposing the Bridge at the time of submission of Road proposal:
A causeway exists at the said location.The Home Ministery,Govt. of India has proposed the const. of above
bridge in Naxalite Area for Smooth Movement of Vehicles in Naxalite Area in all weather.

10. Estimated Cost (Rs. In Lakhs) Item Total Cost (Rs in Lakhs) Cost per m

Approaches 11.46 0.29


ApproachSlab 2.01 0.05
Bridge Super Structure 80.01 2
Foundation 74.70 1.86
Protection Work of Bridge 31.01 0.77
Protection Work of River 30.19 0.75
Diversion #VALUE! #VALUE!

Others 11.41 0.28

Cost of Preparation of DPR 1.55 0.04


(1% of Cost of Bridge)

Total #VALUE! #VALUE!


Mord Share ### Lacs State Share ### Lacs
(MoRD share and State share to be calculated as per the norms of MoRD/NRRDA)
11. INDEX MAP (not to scale ) : Attached
saperately

Target Habitation Nos 09


Windamgunj to
Piparkhad
MDR-42
Road

No
Proposed Bridge Location - Km. 20

12 Typical Sketch of proposed bridge showing schematic arrangement of spans


13. Typical Photographs of proposed Bridge Location.

(i) In Km. 20

PHOTO

(ii) U/S of Bridge Site In


Km. 20

(iii) D/S of Bridge Site In


Km. 20
14. Type of Proposed Bridge :
(I) Submersible Structures like Vented Causeway or Submersible Bridge
(ii) Box Culvert √
(iii) Bridge With RCC Piers and Abutments

a. Type of foundation Open √ / Raft /Well / Pile / Any other

b. Bearing Capacity at Foundation Level 8.60 T/Sqm


c. Arrangement of Spans
Total Span No. of Vents Clear Span of Vent

d. Critical Levels Road top level (RTL) 203.9 mtrs.


Average Ground Level(AGL) 203.300 mtrs.
Nala Bed level (NBL) 196.795 mtrs.
Ordinary flood level (OFL) 201.836 mtrs.
Foundation level (FL) 195.795 mtrs.
Ht. of bridge h= (RTL-NBL) 7.105 mtrs.
Ht. of bridge H=(RTL-FL) 8.105 mtrs.
e. Catchment Area
(Catchment area should be based on hydrological survey or from toposheet)
Catchment area serve 6000.00 Hect
Heaviest Rainfall 1100 mm/Hour
Basis of Design Discharge Catchment Area
Waterway required 240.00 Sq.M
Waterway provided 214.00 Sq.M

f. Scour Depth (m) Nil

15. Cost Details


A. General Costs
Cost of Preparation of DPR (1% of Cost of Bridge) 1.55 LACS
B. Brdige Components
Description of Components Quantity Cost Rs. Grade of
concrete
Bridge Super Structure i) CC (Cum.) 565.026 4930264.90 M-30

ii) Steel (Mt.) 53.23 3028318.53


Approach Slab Rmt. 7.0000 201304.61 M-30
Foundation i) CC (Cum.) 199.99 1161473.78 M-15

ii) CC (Cum.) 382.64 2646653.52 M-30

iii) Steel (Mt.) 27.03 1506536.07

iv) GSB (CUM) 609.33 1938223.89


Excavation Work in Foundation CUM 2145.97 216742.97
Joints Rmt. 42.5 42500.00 -

Others Such as Cleaning & Grubbing, Drainage Spout Pipe, 753723.42


Weep hole, Filter media and Pressure Relief pipes

Total (Rs.) 16425741.69

Total - A (Rs. Lacs) 164.26

C. Road Component (for approaches)


Excavation work Cum 112.00 11312.00
Construction of Embankment & Subgrade Cum 252.48 151488.00
Granular Sub base Cum 60.23 191586.21
WBM Gr - 2 Cum 25.31 80618.42
WBM Gr - 3 Cum 25.31 83410.62
Prime Coat Sqm 337.50 10057.50
Tack Coat Sqm 337.50 4195.13
OGPC / Surface Dressing Sqm 337.50 47709.00
Seal Coat Sqm 337.50 13986.00
D. Protection works
Protection Work of Bridge 3100926.36 -
Protection Work of River 3018513.26 -
Protection of Approaches 551764.86 -

E. Road Logo, other Road Furniture 76963.15


F. Dismantling, Dewatering, confirmetary Boring &
310455.00
Proof Checking of Bridge Design etc
G. Diversion #VALUE!

Total (Rs.) #VALUE!

Total - B (Rs. Lacs) #VALUE!

Total Cost of the Project (Rs) #VALUE!


Total Cost of the Project (Rs) (In Words) : Rupees Two Hundred Eighty Seven Lacs and
Seventeen Thousand only

16. Five Year Routine Maintenance


Year Cost in lakhs % Cost
I 0.25 #VALUE!
II 0.40 #VALUE!
III 0.60 #VALUE!
IV 0.75 #VALUE!
V
Total Maintenance 1.00 #VALUE!
Cost 3.00

17. Whether the Bridge has Geometrics as per latest Circular of NRRDA.:
DO.#P-17035/1/2007-Tech. 30th September, 2010. √YES / NO

18. Whether the Cost etimates are as per standerd data analysis and S.S.R. √YES / NO

19. Sources and the Lead distances of Materials are as under


Material Sourc Lead Material Source Lead Distance
e Distan
Earth Carted ce Cement Local
(Km)
Stone Ballast Sukrut 129 Emulsion Jhansi 1366
Aggregate Dala 71 Bitumen Mathura 1536
Sand Chopan 79 Steel Local

This is to Certified that,


1. Span details of bridge tallies with DPR & data uploaded on omms.nic.in. & there is no deviation.
2. Information furnished herewith is true to the best of my knowledge.
3. Total cost of the project, State share & MoRD share worked out by PIU is justified.
4. The proposal of bridge is missing bridge proposal on sanctioned road & in the same stretch as it
was sanctioend in previous phase under PMGSY.

Checked & recommended


DPR Prepared By DPR Checked by
(Name & Sign) (Name & Sign) (Name & Sign)

Counter Signatures of
Co-ordinator STA :
To be filled by State Technical Agency
Name of the STA :
Name of Road :
Name of Bridge (if any) :

20. Is the proposed work is for CD/Causeway of any length or brigde with span excluding approaches less
YES / NO
than 15m.
STAs need not clear such proposals

21 Is the Proposal entered on the OMMS : Yes/ No


(Data entries to be verified by STA before Clicking the Propopsal)
a. Span of Bridge on web: m. b. Span of Bridge As per DPR

* Span of bridge: C/C distance along the centre line of the bridge between inner faces of dirt walls.

c. Whether type of foundation & resting strata as per survey report justified to be safe YES / NO

d. Whether Hydraulic design is checked & found to be adequete as per site requirements YES / NO

e. Whether RCC designs are checked and found to be economical & safe. YES / NO

f. Whether the provisions made by PIU are sufficient & essentia from economy point of view. YES / NO

22 If the Proposal is for a Bridge for which Road was already Sanctioned
If Yes, Have you verified and satisfied yourself with all the items listed at Sr. No. 7, by PIU Yes / No
Have you satisfied yourself that the road is a part of Core Network Yes / No

23 Are you satisfied with the following


Engineering Surveys (L section, X sections must be verified) Yes / No
Soil/ Material Investigation Yes / No
Hydraulic Studies. Yes / No
( Catchment for structures to be verified from topo sheet. Location and requirement of structures to be
verified from L section and catchment area to be marked on Topo Sheet Copy )

24 Is the design of the following elements as per relevant I S/ IRC codes


Foundations / Abutments / Piers / Deck Slab / Wing Walls Yes / No

25 Does the Estimation Conform to Standard Rate Analysis and SoR generated for the Yes / No
current Phase for PMGSY works and a copy of SoR provided to STA

26 Does the proposal have provisions for

PMGSY Logo Sign Boards and Information Board


Yes / No

27 Whether STA and Superintendent Engineer have visited the site? If Yes, Date of Visit :

Kindly indicate whether the program of visit was informed to NRRDA for prior approval ?
28 Secific Remarks, if any, by STA

( Specific remarks of STA about the overall Bridge Project are necessary on each DPR)
29. Certificates:
Certified that the proposal of bridge is checked & found to be it is missing bridge on sanctioned
road & in the same stretch as it was sanctioend in previous phase under PMGSY.

Certified that the Design and Estimation for the Proposed bridge are based on the latest Circular of
NRRDA:vide DO.letter #P-17035/1/2007-Tech. 30th September, 2010.

Certified that the Design and Estimation for the Proposed bridge are based on the data and SSR
provided by PIU Engineers . The Proposal after final Correction is entered on the OMMS.The Propasal
may be considered for clearance.

Technical Scrutiny at STA done by:


Signature Signature Co-ordinator STA:
Name Name Signature
Date Date Name
Date
PRADHAN MANTRI GRAM SADAK YOJANA
RCPLWEA (Additional)
Cost Estimate
F-5
Block: Duddhi
District: Sonebhadra
State: Uttar Pradesh Package: UP-67163

S.No. Name Name of the Bridge Type of Proposed Cost of Cost of Cost of Total Estimated cost (Lacs) Average cost per Mtr.
of Block length of Bridge Approach Road Protection Work (Lacs)
Proposal Bridge + Diversion (Bridge + River)

N/U M Rs. (Lacs) Rs. (Lacs) Rs. (Lacs) Rs. Rs.


Construction Maintenance Construction Maintenance
1 Duddhi Constrcution of Bridge N 40.100 200.69 #VALUE! 30.19 #VALUE! 3.00 #VALUE! 0.07
on Nala at Km. 20 on
Windamgunj
Piparkhad to Auradad
Road (Package No.: UP-
67163)

Total Estimated of the package Rs.= #VALUE! Lacs


Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to
Auradad Road (Package No.: UP-67163)
District:
Package No: Format - 6
S.
Item of work Quantity Unit Rate Amount
No
1 2 7 9 9
1 Clearing and grubbing road land including
uprooting wild vegetation, grass, bushes,
shrubs, saplings and trees of girth upto 300 mm,
removal of stumps of such trees cut earlier and
disposal of unserviceable materials and stacking
of serviceable material to be used or auctioned, 1130.94 Sqm 4.23 4783.88
upto a lead of 1000 m including removal and
disposal of top organic soil not exceeding 150
mm in thickness as per Technical Specification
Clause 201.

2 Dismantling of existing structures like culverts,


bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled
material, disposal of unserviceable material and 75.00 Cum 465.00 34875.00
stacking the serviceable material with all lifts
and lead of 1000 m as per Technical
Specification Clause 202. (SOR Sl. No. 2.11) for
CC Pavement

3 Dismantling of existing structures like culverts,


bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled
material, disposal of unserviceable material and 800.00 Cum 320.00 256000.00
stacking the serviceable material with all lifts
and lead of 1000 m as per Technical
Specification Clause 202. (SOR Sl. No. 2.11) for
Stone Masonary work

4 Dewatering of water trenches during excavation,


concreting, masonary work upto sub soil/water
level including hire charges of 5 HP Pump 178.00 Hrs 110.00 19580.00

5 Excavation in fondation in soil mixed with


moorum/single/kankar including filling upto 1.50
m and lead upto 30 m and including
filling,watering and ramming of excavated earth
into the trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal of 2533.65 Cum 101.00 255898.65
surface earth as directed by Engineer in charge
upto a distance of 30 m from the foundation
trenches including all T& P and material etc
complete as per UPPWD specification SNo.2-
252

6 Laying reinforced cement concrete pipe of 1000


mm dia NP-3 for culverts on first class bedding
of granular material in single row including fixing
collar with cement motar 1:2 but excluding
excavation,protection works,back filling,concrete 15.00 RM 5295.38 79430.70
and masonary works in head walls and parapets

7 Providing concrete for plain/reinforced concrete


in open foundations complete as per drawings
and technical specifications Clause 802, 803, 315.76 Cum 5807.78 1833839.95
1202 & 1203 -M-15

8 Construction of embankment / Subgrade of


approach road with approved material obtained
from borrow pits with a lift upto 1.5 m,
transporting to site, spreading, grading to
required slope and compacting to meet 600.00 Cum 252.48 151488.00
requirement of Tables 300.1 and 300.2 with a
lead upto 5 Km as per Technical Specification
Clause 301.5
9 Construction of Granular Sub-Base by providing
well graded material, spreading in uniform
layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at
OMC, and compacting with smooth wheel 50.63 Cum 2993.05 151538.25
roller to achieve the desired density, complete
as per Technical Specification Clause 401. For
Approach Road & For Diversion

10 Construction of Granular Sub-Base by


providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with smooth 735.04 Cum 3180.91 2338096.09
wheel roller to achieve the desired density,
complete as per Technical Specification Clause
401. below foundation

11 Providing, laying, spreading and compacting


stone aggregates of specific sizes to water
bound macadam specification including
spreading in uniform thickness, hand packing,
rolling with smooth wheel roller 80-100 kN in
stages to proper grade and camber, applying
and brooming, stone screening/binding 25.31 Cum 3185.24 80618.42
materials to fill-up the interstices of coarse
aggregate, watering and compacting to the
required density grading 2 as per Technical
Specification Clause 405. For Approach Road

12 Providing, laying, spreading and compacting


stone aggregates of specific sizes to water
bound macadam specification including
spreading in uniform thickness, hand packing,
rolling with smooth wheel roller 80-100 kN in
stages to proper grade and camber, applying
and brooming, stone screening to fill-up the #N/A Cum #N/A #N/A
interstices of coarse aggregate, watering and
compacting to the required density Grading 3 as
per Technical Specification Clause 405. For
Approach Road

13 Providing and Laying brick edging with first


class brick 8 cm wide and 12 cm deep laid on
either side of the mettaled surface as per
direction of Engineer-in-charge including of all
materials, labour, T&P etc required for proper #N/A Km #N/A #N/A
completion of work ( as per SI 765 of Shedule of
Rate of UPPWD)

14 Providing and applying primer coat with bitumen


emulsion on prepared surface of granular base
including cleaning of road surface and spraying
primer at the rate of 0.70-1.0 kg/sqm using
mechanical means as per Technical #N/A Sqm #N/A #N/A
Specification Clause 502 For Approach Road

15 Providing and applying tack coat with Bitumen


VG-10 using emulsion distributor at the rate of
0.25 to 0.30 kg per sqm on the prepared dry
and hungry bituminous surface cleaned with
Hydraulic broom as per Technical Specification #N/A Sqm #N/A #N/A
Clause 503. For Approach Road

16 Providing, laying and rolling of open-graded


premix carpet of 20 mm thickness composed of
13.2 mm to 5.6 mm aggregates either using VG-
30 bitumen to required line, grade and level to
serve as wearing course on a previously
prepared base, including mixing in a suitable
plant, laying and rolling with a three wheel 80- #N/A Sqm #N/A #N/A
100 kN static roller capacity, finished to required
level and grades to be followed by seal coat of
either Type A or Type B or Type C as per
Technical Specification Clause 508. For
Approach Road

17 Providing and laying seal coat sealing the voids


in a bituminous VG-30 surface laid to the
specified levels, grade and cross fall using Type #N/A Sqm #N/A #N/A
B as per Technical Specification Clause 510 For
Approach Road
18 Stone masonry in 1:5 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204 (Stone Masonary Retaining walls for
Approach Road with stone recover from old #N/A Cum #N/A #N/A
structure @ 40 % = 800*40 %= 320 cub from
Item No 2)

19 Plain/reinforced cement concrete in open


foundation complete as per drawings and
technical specification Clauses 802, 804, 805, #N/A Cum #N/A #N/A
806, 807, 1202 and 1203 (M-30)

20 Providing pressure release pipe, plain/


reinforced concrete with 100 mm dia AC pipe
extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face
#N/A No #N/A #N/A
complete as per drawing and technical
specification Clauses 614, 709, 1204.3.7 @ 6
Nos Per Span

21 Plain/reinforced cement concrete in super


structure complete as per drawings and
technical specification Clauses 802, 804, 805, #N/A Cum #N/A #N/A
806, 807, 1202 and 1204 (M-30)

22 Supplying, fitting, and placing HYSD bar


reinforcement in foundation complete as per
drawing and technical specifications Clauses #N/A MT #N/A #N/A
1000 and 1202 Foundation

23 Suplying, Fixing, and placing HYSD bar


reinforcement in superstructure as per drawing
and technical specifications Clause #N/A MT #N/A #N/A
1002,1010,1202 Superstructure

24 Providing and fixing of drainage spout as per


drawing and Technical Specifications Claause #N/A No #N/A #N/A
2705
25 Providing weepholes in brick masonry/stone
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 75 mm dia AC pipe
extending through the full width of the structures
#N/A No #N/A #N/A
with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical
specification Clauses 614, 709, 1204

26 Suplying, Fixing, of expansion joint complete as


per drawing and technical specifications for 20
#N/A RM #N/A #N/A
mm asphalt plug Joint

27 Providing and laying of boulder apron laid in


wire crates with 4 mm dia GI wire conforming to
IS:280 and IS:4826 in 100 mm x 100 mm mesh
(woven diagonally) including 10 per cent extra
for laps and joints laid with stone boulders #N/A Cum #N/A #N/A
weighing not less than 25 kg each as per
drawing and technical specifications Clause
1301

28 Providing and laying 150 mm Thk Flat Stone


Embeded in 300 mm Thk M15 Concrete for
Rigid Apron for bed protection to complete as
per drawing and technical specifications Clause #N/A Cum #N/A #N/A
1301 for Flat Stone for Rigid Apron U/s and D/s

29 Providing and laying 150 mm Thk Flat Stone


Embeded in 300 mm Thk M15 Concrete for
Rigid Apron for bed protection to complete as
per drawing and technical specifications Clause #N/A Cum #N/A #N/A
1301 for M-15 Cement Concrete for Rigid
Apron U/s and D/s

30 Providing and laying filter media with granular


crushed aggregates as per specification to a
thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards
the wall and providing over the entire surface
behind abutment, wing wall, return wall to the #N/A Cum #N/A #N/A
full height, compacted to firm condition complete
as per drawing and technical specification
Clause 1204.3.8
31 Providing and laying pitching on slopes laid
over prepared filter media as per drawing and
technical specifications Clause 1302 forStone #N/A Cum #N/A #N/A
Pitching on Slopes (U/S & D/S)

32 Providing and laying filter material underneath


pitching in slopes complete as per drawing and
technical specifications Clause 1302 for Under #N/A Cum #N/A #N/A
Stone Pitching on Slopes (U/S & D/S)

33 Cement Plum Concrete with 40% plum & 60%


1:3:6 Cement Concrete including Supply of All
material, labour,T&P etc. required for proper
completion of the work as per drawing/Technical #N/A Cum #N/A #N/A
specifications clause 802,803,1202 & 1203
forU/S & D/S

34 Pointing with cement mortar (1:3) on stone


masonary as per drawing and technical
specification Clauses 613.3 and 1204 For Stone
Masonary Retaining wall #N/A Sqm #N/A #N/A
35 Providing and fixing of typical PMGSY
informatory sign board with Logo as per MORD
specifications and drawing. Three MS Plates of
1.6 mm thick, top and middle plate duly welded
with MS flat iron 25mm x 5m size on back on
edges. The lower plate will be welded with MS
angle iron frame of 25mm x 25mm x 5mm. The
angle iron frame of the lower most plate and flat
iron frame of middle plate will be welded to 2
nos. 75mm x 75 mm of 12 SWG sheet tubes
posts duly embedded in cement concrete M-15
grade blocks of 450mm x 450mm x 600mm,
600mm below ground level. The top most
diamond plate will be welded to middle plate by #N/A No #N/A #N/A
47mm x 47mm of 12 SWG steel plate tube. All
M.S. will be stove enameled on both sides.
Lettering and printing arrows, border etc. will be
painted with ready mixed synthetic enamel paint
of superior quality in required shade and colour.
All sections of framed posts and steel tube will
be painted with primer and two coats of epoxy
paint as per drawing Clause 1701 and Annexure
1700.1

36 Providing and fixing of typical PMGSY Citizen


information board (Nagrik Suchana Board) as
per standard drawing of NRRDA with two
18SWG MS sheets of size 900x750mm duly
welded with 4 nos, MS Flat iron frame of size
1000x75x5mm & 2 nos. MS flat iron frame on
back side of board. The flat iron frame will be
welded with two nos 75x75mm of 12SWG
horizontal sheets in square are tube posts of
1000mm length & two nos 75x75mm of 12 SWG
verticle steel tubes in square are round post of
3050mm length dully embed nominal hand
mixed ass per IRC:67 upto
600mmx600mmx750mm blocks 600mm below #N/A No #N/A #N/A
ground level. all M:S will be stove enabled on
both sides lettering & Painting and arrows,
border etc will be painted with ready mixed
synthetic enamled paint of superior quality
section of framed posts and steel tube will be
painted with primer and two coats of epoxy paint
as per drawing & information on the road shall
also be mentioned as per direction of E/I
including all labour, material & T&P etc.

37 Providing and erecting direction and place


identification of semi reflective sign boards as
per IRC-67 made of 2 mm thick M.S. Sheet
duly stove enameled paint white colour in front
and grey colour on back with reflective border of
70 mm width and required message, letters,
figures with reflective tape of engineering grade
as per MORD specifications of required shade
and colour. Supported and welded on two nos.
47 mm x 47 mm of 12 SWG square tube of #N/A No #N/A #N/A
3050 mm height duly strengthened by 25 mm x
5 mm MS flat iron on edges on back firmly fixed
to the ground by means of properly designed
foundations with M-15 grade cement concrete
450 mm x 450 mm x 600 mm, 600 mm below
ground level as per approved drawing and
Technical Specification Clause 1701

38 Supply and ixing of liner Delineator system


(LDS) palels made of micro prismatic retro
reflective sheeting duly laminated on the
aluminium foil to a unique corrugated safe to
provide retro reflection across wide range of
observations and external angles. each LDS
panel should be off nominal length of 33 inch #N/A No #N/A #N/A
and each ridge shall be approximatley 0.34 inch
high. Each LDS panel in to b firmly fixed on
existing MS railing through MS sections welding
as and when required (as pr SOR Sl. No. 5
UPPWD)

Total (Rs.) #N/A


Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to Auradad Road
(Package No.: UP-67163)
District: Sonebhadra
Package No: Package: UP-67163 Format - 6
Width Height
S. Length
Item of work No. Quantity Unit Rate Amount
No (m)
(m) (m)
1 2 3 4 5 6 7 8 9 10
Clearing and grubbing road land including ###
uprooting wild vegetation, grass, bushes,
shrubs, saplings and trees of girth upto 300 mm,
removal of stumps of such trees cut earlier and
disposal of unserviceable materials and stacking
of serviceable material to be used or auctioned,
upto a lead of 1000 m including removal and
disposal of top organic soil not exceeding 150
mm in thickness as per Technical Specification
Clause 201.

For Bridge 1 58.100 17.400 1010.94 Sqm ###


For Approach Road 2 30.000 2.000 120.00 Sqm ###
1 1130.94 Sqm 4.23 4783.88
Dismantling of existing structures like culverts, ###
bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled
material, disposal of unserviceable material and
stacking the serviceable material with all lifts
and lead of 1000 m as per Technical
Specification Clause 202. (SOR Sl. No. 2.11)

2 CC Pavement 1 50.000 5.000 0.300 75.000 Cum 465.00 34875.00


3 Stone Masonary work 1 50.000 5.000 3.200 800.000 Cum 320.00 256000.00
###
Dewatering of water trenches during excavation, ###
concreting, masonary work upto sub soil/water
level including hire charges of 5 HP Pump

1 178.00 178.00 Hrs ###


4 Total 178.000 Hrs 110.00 19580.00
Excavation in fondation in soil mixed with ###
moorum/single/kankar including filling upto 1.50
m and lead upto 30 m and including
filling,watering and ramming of excavated earth
into the trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal of
surface earth as directed by Engineer in charge
upto a distance of 30 m from the foundation
trenches including all T& P and material etc
complete as per UPPWD specification SNo.2-
252

Bridge 1 40.300 8.700 1.500 525.92 Cum ###


Bridge shear key 2 40.300 1.000 0.700 0.00 Cum ###
RCC Retaining wall left 2 9.300 6.000 5.123 571.73 Cum ###
RCC Retaining wall right 2 9.300 6.000 5.123 571.73 Cum ###
Cutoffwall (U/S) 1 46.100 1.500 2.000 138.30 Cum ###
Cutoffwall (D/S) 1 50.100 1.500 2.000 150.30 Cum
Stone Pitching Toe wall Left 2 13.000 0.800 0.750 15.60 Cum
Stone Pitching Toe wall right 2 13.000 0.800 0.750 15.60 Cum
For GSB below raft 1 40.300 8.700 0.450 157.77 Cum
Deduction For GSB below Shear Key -2 40.300 0.500 0.450 -18.14 Cum
For Compacted Earth below apron U/S 1 40.300 3.000 0.200 24.18 Cum
For Compacted Earth below apron D/S 1 40.300 5.000 0.200 40.30 Cum
for flexible apron key 2 40.300 0.500 1.200 48.36 Cum
For Diversion (wire crates wall) 2 100.000 1.500 0.600 180.00 Cum
Retaining walls for Approach Road 4 20.000 1.400 1.000 112.00 Cum
Deduction For Cutoffwall -1 40.300 0.450 0.800 0.00 Cum
-1 40.300 0.100 0.750 0.00 Cum
-1 40.300 0.530 0.550 0.00 Cum
-1 40.300 0.200 0.750 0.00 Cum
-1 40.300 0.100 0.750 0.00 Cum
5 Total 2533.65 Cum 101.00 255898.65
Laying reinforced cement concrete pipe of 1000 ###
mm dia NP-3 for culverts on first class bedding
of granular material in single row including fixing
collar with cement motar 1:2 but excluding
excavation,protection works,back filling,concrete
and masonary works in head walls and parapets

For Diversion 2x3 2.500 15.000 RM ###


6 Total 15.000 RM 5295.38 79430.70
Providing concrete for plain/reinforced concrete
in open foundations complete as per drawings
and technical specifications Clause 802, 803,
1202 & 1203 -M-15

Bridge 1 40.300 8.700 0.100 35.06 Cum


Bridge shear key 2 40.300 1.250 0.100 10.08 Cum ###
Below rigid apron (U/S) 1 46.100 2.800 0.150 19.36 Cum F
Below rigid apron (D/S) 1 50.100 4.800 0.150 36.07 Cum ### o
u
Bottom of RCC Retaining wall (left) 2 9.200 6.000 0.100 11.04 Cum ### n
Bottom of RCC Retaining wall (right) 2 9.200 6.000 0.100 11.04 Cum ###
Cutoffwall (Left) 1 46.100 1.500 0.100 6.92 Cum ###
Cutoffwall (Right) 1 50.100 1.500 0.100 7.52 Cum ###
C/o Toe Wall for slope pitching (0.400+0. ###
2x2 13.000 1.200 31.20 Cum
600)/2
Below Toe Wall for slope pitching 2x2 13.000 0.600 0.150 4.68 Cum ###
Below Approach slab (Left) 1 8.700 3.600 0.100 3.13 Cum ###
Below Approach slab (Right) 1 8.700 3.600 0.100 3.13 Cum ###
Stone Masonary Retaining walls for Approach 4 20.000 1.400 0.100 11.20 Cum ###
Road (0.250+0.
Parapet Wall
4x5 2.000 0.500 7.000 Cum ###
450)/2
Construction of Cutoffwall U/S 1 46.100 1.400 0.300 19.362 Cum
1 46.100 0.550 1.200 30.426 Cum
1 46.100 0.300 0.500 6.915 Cum
Construction of Cutoffwall D/S 1 50.100 1.400 0.300 21.042 Cum
1 50.100 0.550 1.200 33.066 Cum
1 50.100 0.300 0.500 7.515 Cum

7 Total 315.756 Cum 5807.78 1833839.95


Construction of embankment / Subgrade of
approach road with approved material obtained
from borrow pits with a lift upto 1.5 m,
transporting to site, spreading, grading to
required slope and compacting to meet
requirement of Tables 300.1 and 300.2 with a
lead upto 5 Km as per Technical Specification
Clause 301.5

For Approach Road both sides (7.50+8.5 (2.50+


2 30.000 600.00 Cum
)/2 0.00)/2
8 Total 600.00 Cum 252.48 151488.00
Construction of Granular Sub-Base by
providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with smooth
wheel roller to achieve the desired density,
complete as per Technical Specification Clause
401.
Below RCC Raft of Box 1 40.300 8.700 0.450 157.77 Cum
Deduct Bridge shear key -2 40.300 0.500 0.450 -18.14 Cum
Deuction for Cutoffwall -1 40.300 0.200 0.200 0.00 Cum
-1 40.300 0.200 0.200 0.00 Cum
9 For Approach Road (3.75+7.5
2 30.000 0.150 50.63 Cum 2993.05 151538.25
)/2
For Diversion 1 100.000 3.750 0.165 61.88
112.51
9 Under Stone Masonary Retaining walls for
4 20.000 1.200 0.100 9.60 Cum
Approach Road
Below pipe 1 7.500 3.200 0.150 3.600 Cum ###
Behind Abutement A1 1 7.3 1/2x6..5x6.5 tan 30 88.98 Cum
Behind Abutement A2 1 7.3 1/2x6..5x6.5 tan 30 88.98 Cum
RCC Retaining wall (Left) 2 9 1/2x5.3x5.3 tan 30 145.87 Cum
RCC Retaining wall (Right) 2 9 1/2x5.3x5.3 tan 30 145.87 Cum
10 Total 735.04 Cum 3180.91 2338096.09
Providing, laying, spreading and compacting
stone aggregates of specific sizes to water
bound macadam specification including
spreading in uniform thickness, hand packing,
rolling with smooth wheel roller 80-100 kN in
stages to proper grade and camber, applying
and brooming, stone screening/binding
materials to fill-up the interstices of coarse
aggregate, watering and compacting to the
required density grading 2 as per Technical
Specification Clause 405.

For Approach Road (3.75+7.5


2 30.000 0.075 25.31 Cum
)/2
11
Total 25.31 Cum 3185.24 80618.42
Providing, laying, spreading and compacting
stone aggregates of specific sizes to water
bound macadam specification including
spreading in uniform thickness, hand packing,
rolling with smooth wheel roller 80-100 kN in
stages to proper grade and camber, applying
and brooming, stone screening to fill-up the
interstices of coarse aggregate, watering and
compacting to the required density Grading 3
as per Technical Specification Clause 405.

For Approach Road (3.75+7.5


2 30.000 0.075 25.31 Cum
)/2
Total 25.31 Cum 3295.56 83410.62
Providing and Laying brick edging with first class brick 8
cm wide and 12 cm deep laid on either side of the mettaled
surface as per direction of Engineer-in-charge including of
all materials, labour, T&P etc required for proper
completion of work ( as per SI 765 of Shedule of Rate of
UPPWD)
1 x 2 30.000 60.00
0.060 Km 75000.00 4500.00
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular base
including cleaning of road surface and spraying
primer at the rate of 0.70-1.0 kg/sqm using
mechanical means as per Technical
Specification Clause 502

For Approach Road (3.75+7.5


2 30.000 337.50 Sqm
)/2
Total 337.50 Sqm 29.80 10057.50

Providing and applying tack coat with Bitumen


VG-10 using emulsion distributor at the rate of
0.25 to 0.30 kg per sqm on the prepared dry
and hungry bituminous surface cleaned with
Hydraulic broom as per Technical Specification
Clause 503.

For Approach Road (3.75+7.5


2 30.000 337.50 Sqm
)/2
Total 337.50 Sqm 12.43 4195.13
Providing, laying and rolling of open-graded
premix carpet of 20 mm thickness composed of
13.2 mm to 5.6 mm aggregates either using VG-
30 bitumen to required line, grade and level to
serve as wearing course on a previously
prepared base, including mixing in a suitable
plant, laying and rolling with a three wheel 80-
100 kN static roller capacity, finished to required
level and grades to be followed by seal coat of
either Type A or Type B or Type C as per
Technical Specification Clause 508.

For Approach Road (3.75+7.5


2 30.000 337.50 Sqm
)/2
Total 337.50 Sqm 141.36 47709.00
Providing and laying seal coat sealing the voids
in a bituminous VG-30 surface laid to the
specified levels, grade and cross fall using Type
B as per Technical Specification Clause 510

For Approach Road (3.75+7.5


2 30.000 337.50 Sqm
)/2
Total 337.50 Sqm 41.44 13986.00
Stone masonry in 1:5 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
Stone Masonary Retaining walls for Approach
(1.200+0.
Road with stone recover from old structure @ 4 20.000 2.500 180.00 Cum
60)/2
40 % = 800*40 %= 320 cub from Item No 2
Total 180.000 Cum 2400.57 432102.60
Plain/reinforced cement concrete in open
foundation complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1203 (M-30)

Box Bottom Slab 1 40.100 8.500 0.600 204.510 Cum


Shear Key 2 40.100 0.500 0.750 30.080 Cum
Bridge bottom Haunch 10 8.500 0.300 0.300 7.650 Cum
Retaining wall (Left) bottom slab 2 9.000 5.750 0.500 51.750 Cum
Retaining wall (toe side) 2 9.000 0.550 9.900 Cum
Retaining wall (heel side) 2 9.000 0.650 11.700 Cum
Retaining wall (Right) bottom slab 2 9.000 5.300 0.500 47.700 Cum
Retaining wall (toe side) 2 9.000 0.450 8.100 Cum
Retaining wall (heel side) 2 9.000 0.625 11.250 Cum
Total 382.640 Cum 6916.82 2646653.52
Providing pressure release pipe, plain/
reinforced concrete with 100 mm dia AC pipe
extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical
specification Clauses 614, 709, 1204.3.7 @ 6
Nos Per Span
5 6.00 30.00 No
Total 30.000 No 907.17 27215.10
Plain/reinforced cement concrete in super
structure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 (M-30)
Box Top Slab 1 40.100 8.500 0.600 204.510 Cum
Bridge outer wall 2 8.500 0.600 6.300 64.260 Cum
Bridge inner wall 4 8.500 0.350 6.300 74.970 Cum
Top Haunch 10 8.500 0.300 0.300 7.650 Cum
Nose for resting Approach Slab (0.600+0.
2 8.500 0.300 2.300 Cum
300)/2
Approach slab (left) 1 8.700 3.500 0.300 9.140 Cum
Approach slab (right) 1 8.700 3.500 0.300 9.140 Cum
RCC Retaining walls (left) Vertical wall 2 9.000 0.500 7.459 67.130 Cum
RCC Retaining walls (right) Vertical wall 2 9.000 0.500 7.459 67.131 Cum
Wearing coat 1 40.100 8.500 0.075 25.560 Cum
Copping on Retaining wall of apprach road 2*2 30.000 0.060 0.050 0.360 Cum
Crash Barrier 2 50.000 0.450 0.175 7.875 Cum
(0.275+0.
2 50.000 0.250 9.060 Cum
450)/2
(0.175+0.
2 50.000 0.750 15.940 Cum
275)/2
Total 565.026 Cum 9023.41 5098461.26
Supplying, fitting, and placing HYSD bar
reinforcement in foundation complete as per
drawing and technical specifications Clauses
1000 and 1202
Foundation 382.64 0.90% 27.03 MT ###
Total 27.03 MT 55735.70 1506536.07
Suplying, Fixing, and placing HYSD bar
reinforcement in superstructure as per drawing
and technical specifications Clause
1002,1010,1202

Superstructure 565.03 1.20% 53.23 MT


Total 53.23 MT 56891.20 3028318.53
Providing and fixing of drainage spout as per
drawing and Technical Specifications Claause
2705
2x10 20.00 No
Total 20.00 No 151.59 3031.80
Providing weepholes in brick masonry/stone
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 75 mm dia AC pipe
extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical
specification Clauses 614, 709, 1204

Abutment 2 5x7 70.000 No


RCC Retaining wall L/s & R/s 2x2 6x8 192.000 No
Stone masonary Retaining Wall 2x2 12.00 48.000 No
Toe Wall 2x2 10.00 40.000 No
Total 350.000 No 151.59 53056.50
Suplying, Fixing, of expansion joint complete as
per drawing and technical specifications

20 mm asphalt plug Joint 2 8.500 17.000 RM


Total 17.00 RM 2500.00 42500.00
Providing and laying of boulder apron laid in
wire crates with 4 mm dia GI wire conforming to
IS:280 and IS:4826 in 100 mm x 100 mm mesh
(woven diagonally) including 10 per cent extra
for laps and joints laid with stone boulders
weighing not less than 25 kg each as per
drawing and technical specifications Clause
1301

For Diversion 2 50.000 1.500 1.500 225.000 Cum


Flexible Apron U/s 1 46.100 1.500 1.500 103.730 Cum
Flexible Apron D/s 1 50.100 1.500 1.500 112.730 Cum
key for flexible apron both side 0 46.100 0.500 1.200 0.000 Cum
To Protct Banks of Nala/River 25 3.000 1.500 1.500 168.750 Cum
Total 610.21 Cum 8402.71 5127417.67
Providing and laying 150 mm Thk Flat Stone
Embeded in 300 mm Thk M15 Concrete for
Rigid Apron for bed protection to complete as
per drawing and technical specifications Clause
1301
Flat Stone for Rigid Apron U/s 1 40.100 3.000 0.150 18.050 Cum
Flat Stone for Rigid Apron D/s 1 40.100 5.000 0.150 30.080 Cum
Total 48.13 Cum 2544.07 122446.09
M-15 Cement Concrete for Rigid Apron U/s 1 40.100 3.000 0.150 18.050 Cum
M-15 Cement Concrete for Rigid Apron D/s 1 40.100 5.000 0.150 30.080 Cum
Total 48.13 Cum 5807.78 279528.23
Providing and laying filter media with granular
crushed aggregates as per specification to a
thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards
the wall and providing over the entire surface
behind abutment, wing wall, return wall to the
full height, compacted to firm condition complete
as per drawing and technical specification
Clause 1204.3.8

Behind Abutement A1 1 8.500 0.600 6.500 33.150 Cum


Behind Abutement A2 1 8.500 0.600 6.500 33.150 Cum
RCC Retaining wall (Left) 2 9.000 0.600 7.459 80.560 Cum
RCC Retaining wall (Right) 2 9.000 0.600 7.459 80.560 Cum
Total 227.42 Cum 2985.56 678976.06
Providing and laying pitching on slopes laid over
prepared filter media as per drawing and
technical specifications Clause 1302
Stone Pitching on Slopes (U/S & D/S) 4 77.72 0.300 93.260 Cum
area of slope Cum
Total 93.26 Cum 2269.30 211634.92
Providing and laying filter material underneath
pitching in slopes complete as per drawing and
technical specifications Clause 1302
Under Stone Pitching on Slopes (U/S & D/S) 4 77.72 0.150 46.630 Cum
Total 46.63 Cum 2625.59 122431.26
Cement Plum Concrete with 40% plum & 60%
1:3:6 Cement Concrete including Supply of All
material, labour,T&P etc. required for proper
completion of the work as per drawing/Technical
specifications clause 802,803,1202 & 1203

U/S & D/S 60 3.000 1.500 1.500 405.000 Cum


Total 405.00 Cum 3951.99 1600555.95
Pointing with cement mortar (1:3) on stone
masonary as per drawing and technical
specification Clauses 613.3 and 1204

For Stone Masonary Retaining wall 2x2 30.000 0.500 60.00 Sqm
Total 60.00 Sqm 57.27 3436.00
Providing and fixing of typical PMGSY
informatory sign board with Logo as per MORD
specifications and drawing. Three MS Plates of
1.6 mm thick, top and middle plate duly welded
with MS flat iron 25mm x 5m size on back on
edges. The lower plate will be welded with MS
angle iron frame of 25mm x 25mm x 5mm. The
angle iron frame of the lower most plate and flat
iron frame of middle plate will be welded to 2
nos. 75mm x 75 mm of 12 SWG sheet tubes
posts duly embedded in cement concrete M-15
grade blocks of 450mm x 450mm x 600mm,
600mm below ground level. The top most
diamond plate will be welded to middle plate by
47mm x 47mm of 12 SWG steel plate tube. All
M.S. will be stove enameled on both sides.
Lettering and printing arrows, border etc. will be
painted with ready mixed synthetic enamel paint
of superior quality in required shade and colour.
All sections of framed posts and steel tube will
be painted with primer and two coats of epoxy
paint as per drawing Clause 1701 and Annexure
1700.1

1 1 No
Total 1 No 10784.00 10784.00
Providing and fixing of typical PMGSY Citizen
information board (Nagrik Suchana Board) as per
standard drawing of NRRDA with two 18SWG MS
sheets of size 900x750mm duly welded with 4 nos,
MS Flat iron frame of size 1000x75x5mm & 2 nos.
MS flat iron frame on back side of board. The flat
iron frame will be welded with two nos 75x75mm of
12SWG horizontal sheets in square are tube posts of
1000mm length & two nos 75x75mm of 12 SWG
verticle steel tubes in square are round post of
3050mm length dully embed nominal hand mixed
ass per IRC:67 upto 600mmx600mmx750mm blocks
600mm below ground level. all M:S will be stove
enabled on both sides lettering & Painting and
arrows, border etc will be painted with ready mixed
synthetic enamled paint of superior quality section of
framed posts and steel tube will be painted with
primer and two coats of epoxy paint as per drawing
& information on the road shall also be mentioned as
per direction of E/I including all labour, material &
T&P etc.

1 1 No
Total 1 No 9032.53 9032.53
Providing and erecting direction and place
identification of semi reflective sign boards as
per IRC-67 made of 2 mm thick M.S. Sheet
duly stove enameled paint white colour in front
and grey colour on back with reflective border of
70 mm width and required message, letters,
figures with reflective tape of engineering grade 2 2 No
as per MORD specifications of required shade Total 2 No 3173.31 6346.62
and colour. Supported and welded on two nos.
Supply
47 mm and x 47 ixing
mm of of 12
liner
SWGDelineator system
square tube of
(LDS)
3050 mm palels
heightmade of micro prismatic
duly strengthened by 25 mmretrox
reflective
5 mm MS flat sheeting duly laminated
iron on edges on fixed
on back firmly the
aluminium
to the groundfoil by
to ameans
uniqueof corrugated safe to
properly designed
provide retrowith
foundations reflection acrosscement
M-15 grade wide range
concreteof
observations
450 mm x 450and mmexternal
x 600 mm,angles.
600 each LDS
mm below
panel
groundshould
level beas off
pernominal length
approved of 33 inch
drawing and
and each ridge shall be approximatley 0.34 inch
4x10 40 No
Total 40 No 1270.00 50800.00
Total (Rs.) 26431271.90
Cost of Preparation of DPR (1% of Cost of Bridge) 1% 154707.14
Total (Rs.) 26585979.03
Say (Lacs) 265.86
PRADHAN MANTRI GRAM SADAK YOJANA
RCPLWEA (Additional)
Detail of Cartage Calculation
Name of Work: Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to Auradad Road (Package
No.: UP-67163)

District: Sonebhadra Package: UP-67163


Loading + Unloading Charges 53.00
1st Km cartage -(Loading + Unloading Charges) 47.70
1/3 of Net Cartage_15.90
Km Rate Amount Commulative Commulative Commulative
amount for Grit amount for Coarse amount for GSB ,
from Sand from Chopan 45-63, 22.4-53 from
DISTANCE FORM SUKRUT QUARRY TO ROBERTSGANJ Dala
0 0 Sukrut26
DISTANCE FORM ROBERTSGANJ TO STARTING CHAINAGE - - 83
DISTANCE FORM DALA QUARRY TO STARTING CHAINAGE 51 - -
DISTANCE FORM CHOPAN QUARRY TO STARTING CHAINAG - 59 -
DISTANCE FORM STARTING CHAINAGE TO Site 20 20 20
TOTAL DISTANCE = 71 79 129
Add for Kachcha Road = 15.90 15.90 15.90
1 1.00 100.70 100.70 100.70 100.70 100.70
2 1.00 24.10 24.10 124.80 124.80 124.80
3 1.00 21.40 21.40 146.20 146.20 146.20
4 1.00 19.50 19.50 165.70 165.70 165.70
5 1.00 17.00 17.00 182.70 182.70 182.70
6 1.00 16.50 16.50 199.20 199.20 199.20
7 1.00 15.50 15.50 214.70 214.70 214.70
8 1.00 14.60 14.60 229.30 229.30 229.30
9 1.00 13.90 13.90 243.20 243.20 243.20
10 1.00 13.20 13.20 256.40 256.40 256.40
11 1.00 12.70 12.70 269.10 269.10 269.10
12 1.00 12.30 12.30 281.40 281.40 281.40
13 1.00 12.00 12.00 293.40 293.40 293.40
14 1.00 11.70 11.70 305.10 305.10 305.10
15 1.00 11.30 11.30 316.40 316.40 316.40
16 1.00 11.10 11.10 327.50 327.50 327.50
17 1.00 10.90 10.90 338.40 338.40 338.40
18 1.00 10.70 10.70 349.10 349.10 349.10
19 1.00 10.50 10.50 359.60 359.60 359.60
20 1.00 10.40 10.40 370.00 370.00 370.00
21 1.00 10.20 10.20 380.20 380.20 380.20
22 1.00 10.10 10.10 390.30 390.30 390.30
23 1.00 10.00 10.00 400.30 400.30 400.30
24 1.00 9.90 9.90 410.20 410.20 410.20
25 1.00 9.70 9.70 419.90 419.90 419.90
26 1.00 9.60 9.60 429.50 429.50 429.50
27 1.00 9.50 9.50 439.00 439.00 439.00
28 1.00 9.50 9.50 448.50 448.50 448.50
29 1.00 9.40 9.40 457.90 457.90 457.90
30 1.00 9.30 9.30 467.20 467.20 467.20
31th to 71Km 41.00 9.00 369.00 836.20 836.20 836.20
72th to 75 Km 4.00 9.00 36.00 872.20 872.20
76th to 79Km 4.00 9.00 36.00 908.20 908.20
80th to 100 Km 21.00 8.00 168.00 1076.20
101th to 129 Km 29.00 7.50 217.50 1293.70
852.10 924.10 1309.60
After Deductuction of 10% CP 774.64 840.09 1190.55
PRADHAN MANTRI GRAM SADAK YOJANA
RCPLWEA (Additional)
ANALYSIS OF CARTAGE FOR BITUMEN AND BITUMEN EMULSION
Name of Work: Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to Auradad Road
(Package No.: UP-67163)

District: Sonebhadra Package: UP-67163

For Bitumen Emulsion (SS-1) For Bitumen (VG-30)


Km as per schedule Kms Rate Per Total Km as per schedule Kms Rate Per Total
Km. Km
Km. - 1 1.0 68.40 68.40 Km. - 1 1 68.40 68.40
Km. 2 - 3 2.0 16.30 32.60 Km. 2 - 3 2 16.30 32.60
Km. 4 - 5 2.0 13.35 26.70 Km. 4 - 5 2 13.35 26.70
Km. 6 - 10 5.0 10.55 52.75 Km.6 - 10 5 10.55 52.75
Km. 11 - 20 10.0 8.15 81.50 Km. 11 - 20 10 8.15 81.50
Km. 21 - 30 10.0 7.00 70.00 Km. 21 - 30 10 7.00 70.00
Km. 31 - 50 20.0 6.25 125.00 Km. 31 - 50 20 6.25 125.00
Km. 51 - 75 25.0 5.45 136.25 Km. 51 - 75 25 5.45 136.25
Km. 76 - 100 25.0 4.30 107.50 Km. 76 - 100 25 4.30 107.50
Km. 101 200 100.0 3.85 385.00 Km. 101 200 100 3.85 385.00
Km. 201 1366.0 1166 3.70 4314.20 Km. 201 1536 1336 3.70 4943.20
Total 1366 5399.90 Total 1536 6028.90
Deduct 10% CP 4909.00 5480.82
Total Cartage 4909.00 Total Cartage 5480.82
Cartage for Emulsion 1.74 Cartage for Bitumen 1.74

Analysis of Emulsion (SS-1) Bulk (Jhansi)


SI. No. Item Basic Rate Rs.
1 Supply of Bitumen Emulsion ( SS-1) from Jhansi 32965.00
2 Cartage for SS-1 @ 1.74 /Mt/Km 2376.84
Total (Rs.) 35341.84

Analysis of Bitumen (VG-30) Bulk (Mathura)


SI. No. Item Basic Rate Rs.
1 Supply of Bitumen ( VG-30) from Mathura 28940.00
2 Cartage for VG-30 @ 1.74 /Mt/Km 2672.64
Total (Rs.) 31612.64

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
PRADHAN MANTRI GRAM SADAK YOJANA
RCPLWEA (Additional)
RMR
Name of Work: Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to Auradad Road (Package No.: UP-67163)
District: Sonebhadra Package: UP-67163
Sl. Name of Basic Loading and Deduct Quarry Rate Distance in Km. Total Distance Total Cost VAT @ Total Total (5) Total
No. Quarry / Rate at charges Royalty (Exclusive for cortage of Cartage 4.5% 5+10 Round To
Crusher of Quarry Loading and (Km) 10 Paise
loading unloading & (excluding
Station royalty) CP)
Kachcha Pakka Kachcha
1 2 3 4 5 6 7 8 9 10 11 12 15 18
45-63mm gauge stone ballast
1 Sukrut 520.00 35.00 110.00 375.00 1 129 0 130 1190.55 1565.55 1565.60 1565.60
22.4-53 mm gauge stone ballast
2 Sukrut 740.00 35.00 110.00 595.00 1 129 0 130 1190.55 1785.55 1785.60 1785.60
53-9.5 mm for GSB -Gr-I
3 Sukrut 820.00 35.00 110.00 675.00 1 129 0 130 1190.55 1865.55 1865.60 1865.60
9.5-2.36 mm for GSB -Gr-I
4 Sukrut 585.00 35.00 110.00 440.00 1 129 0 130 1190.55 1630.55 1630.60 1630.60
2.36 mm & below for GSB -Gr-I
5 Sukrut 495.00 35.00 110.00 350.00 1 129 0 130 1190.55 1540.55 1540.60 1540.60
Stone Dust
6 Sukrut 505.00 35.00 100.00 370.00 1 129 0 130 1190.55 1560.55 1560.60 1560.60
Boulder for RCR
7 Sukrut 485.00 35.00 110.00 340.00 1 129 0 130 1190.55 1530.55 1530.60 1530.60
40mm gauge stone ballast
8 Sukrut 830.00 35.00 110.00 685.00 1 129 0 130 1190.55 1875.55 1875.60 1875.60
Stone for random rubble Stone masonry
9 Sukrut 485.00 35.00 110.00 340.00 1 129 0 130 1190.55 1530.55 1530.60 1530.60
Stone boulder for pitching
9 Sukrut 435.00 35.00 110.00 290.00 1 129 0 130 1190.55 1480.55 1480.60 1480.60
19 mm gauge stone grit
10 Dalla ### 35.00 160.00 1255.00 1 71 0 72 774.64 2029.64 2029.60 2029.60
Sl. Name of Basic Loading and Deduct Quarry Rate Distance in Km. Total Distance Total Cost VAT @ Total Total (5) Total
No. Quarry / Rate at charges Royalty (Exclusive for cortage of Cartage 4.5% 5+10 Round To
Crusher of Quarry Loading and (Km) 10 Paise
loading unloading & (excluding
Station royalty) CP)
Kachcha Pakka Kachcha
1 2 3 4 5 6 7 8 9 10 11 12 15 18
13.2 mm gauge stone grit
11 Dalla ### 35.00 160.00 955.00 1 71 0 72 774.64 1729.64 1729.60 1729.60
11.2 mm gauge stone grit
12 Dalla ### 35.00 160.00 885.00 1 71 0 72 774.64 1659.64 1659.60 1659.60
Screening ’B’ type
13 Dalla 670.00 35.00 160.00 475.00 1 71 0 72 774.64 1249.64 1249.60 1249.60
2.36 mm & below
14 Dalla 600.00 35.00 160.00 405.00 1 71 0 72 774.64 1179.64 1179.60 1179.60
20mm gauge Stone Grit
15 Dalla ### 35.00 160.00 1255.00 1 71 0 72 774.64 2029.64 2029.60 2029.60
10mm gauge Stone Grit
16 Dalla 800.00 35.00 160.00 605.00 1 71 0 72 774.64 1379.64 1379.60 1379.60
Fine Sand
17 Chopan 500.00 35.00 65.00 400.00 1 79 0 80 774.64 1174.64 1174.60 1174.60
Coarse Sand
18 Chopan 550.00 35.00 150.00 365.00 1 79 0 80 840.09 1205.09 1205.10 1205.10
Note:

2 Quarry Rates and cartage rates taken as per approved rates by competent authority.

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
ABUTMENT WALL SECTION RETURN WALL SECTION
SPAN - 2 M
HEIGHT , CLEAR BETWEEN SLAB BOTTOM AND BED LEVEL- 3 M
GHT BETWEEN ROAD TOP LEVEL AND TOP OF FOOTING - 4.66 M
LENGTH OF RETURN WALL- 5 M

face painted and gap filled with bitumen


SPAN SLAB THICKNESS Wearing Coat - 20 mm premix carpet with seal coat PCC M15
1.5 1.5 210 400 300 400
2 2.0 240
2.5 3.0 300 PCC M20 ### ###
3 4.0 370 with surface reinf.
5.0 430 200
6.0 480
Top painted with bitumen

1:3
VERTICAL
1:3
2820 3260

100
1640 ### 1487

1400 1400

100 100 100 100


### ###

2440 2287

2640 2487
450 400 X 400 X 1000 RCC M20
450 X 375 KERB IN BRICK MASONRY IN 1:4
6600
SLAB 600 ABOVE GL

7500

X-SECTION SLAB

7500
END PILLARS

5000 DIRT 2000 DIRT 5000


RW SLAB RW
PLAN

SLAB REINFORCEMENT DETAILING NOTES :


1 Concrete - 1:1.5:3 .
10 DIA @ 300 C/C BOTH LONGITUDENAL AND TRANSVERSE DIRECTION 2 Steel - HYSD bars as per IS:1786
3 Cover - 40 mm at bottom and eac
88 NO. MAIN BARS 12 DIA @ 85 C/C 4 Only one bar to be cranked in each
DISTRIBUTION BARS 10 DIA @ 250 C/C
150 1688 150 5 All bars are cranked at one end on

. . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 240 6 Design Loading - 2 Lanes IRC Cl
7 Bricks crushing strength > 7 MPa
8 Foundation concrete - M15.
300 2000 300 9 Abut. cap and cap on dirt wall and

416

160 1960

2 M SPAN
QUANTITY CALCULATION :
COMPONENT
SL NO ITEM QTT UNIT SUMMARY

1 FOUNDATION EXCAVATION RCC GRADE M25 4.68 CUM


ABUTMENTS 65.05 CUM 7.7 x 2.6 x 1.6 x 2 PCC GRADE M20 4.24 CUM
RETURN WALLS 79.58 CUM 5.0 x 2.5 x 1.6 x 2 X 2 REINFORCEMENT HYSD 723.2 KG
PCC GRADE M15 18.0792 CUM
2 ABUTMENT WALL BW 1:4 213.1832 CUM
PCC_FOUNDATION M15 8.13 CUM 7.7 X 2.64 X 0.2 X 2
BW 1:4 43.89 CUM ( 2.44 + 1.74 ) / 2 X 1.4 X 7.5 X 2 FOUNDATION EXCAVATION 144.6336 CUM
BW 1:5 49.49 CUM ( 1.64 + 0.7 ) / 2 X 2.82 X 7.5 X 2 POINTING 115.396 SQM

3 DIRT WALL AND ABUTMENT CAP


CONCRETE PCC M20 3.54 CUM ( 0.4 + 0.3 ) x ( 0.24 + 0.2 ) - ( 0.3 X 0.24 )X 7.5 X 2.0
REINFORCEMENT HYSD 108.00 KG 8 dia bars at 200 mm c/c on exposed faces.

4 RETURN WALL
PCC_FOUNDATION M15 9.95 CUM 5.0 X 2.487 X 0.2 X 2 X 2
BW 1:4 54.24 CUM ( 2.287 + 1.587 ) / 2 X 1.4 X 5.0 X 2 X 2
BW 1:5 61.52 CUM ( 1.487 + 0.4 ) / 2 X 3.26 X 5.0 X 2 X 2
PCC_COPING M20 0.06 CUM as per RRM
REINFORCEMENT HYSD 0.24 KG as per RRM

5 SLAB
CONCRETE RCC M25 4.68 CUM 1 X ( 2 + 2 X 0.3 ) X 7.5 X 0.24
REINFORCEMENT HYSD 478.00 KG as per RRM

6 KERB
BW 1:4 4.05 CUM ( 2 X 0.45 X 0.375 ) X 12

7 RC PILLARS AT THE ENDS


PCC M20 0.64 CUM 0.4 x 0.4 x 1x 4
REINFORCEMENT HYSD 136.96 KG 8 # 8 dia bars each 1 m long + 6 stirrups each 3.6 m long

8 POINTING
ABUT FACE WALL 42.3 SQM 2.82 x 7.5 x 2
ABUT SIDE WALL 7.90 SQM 0.7 x 2.82 x 4
RETURN FACE WALL 65.2 SQM 3.26 x 5 x 4
TYPICAL PROPOSED X-SECTION FOR UPGRADATION FORMAT - 3

IN CH.0.00 TO 6.075 Km

WBM Grade -II (75mm)and WBM Grade -III (75mm)in layers 3.75 m width
BASE COURSE
Premix carpet followed by seal coat type C GSB 200mm thick in widing only

Road way 7.5 m

Shoulder at 4% slope Carriageway 3.75 m at 3 % slope 1.875 m wide shoulder


Existing Embankment

Existing pavement

J.E. A.E. E.E.


CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow
TYPICAL EXISTING X-SECTION FOR UPGRADATION FORMAT - 3

IN CH.0.00 TO 6.075 Km

WBM- 200mm layers 3.00 m width


BASE COURSE
###

Road way 5.00 m

Carriageway 3.00 m 1.00 m wide shoulder


Existing Embankment

Existing pavement

J.E. A.E. E.E.


CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow
Cost for Widening of Causeway 200m length & 4m width and 800 Sqm.
Sl.
No. Description of Item Unit No L (m) B (m) H (m) Qty. Rate (Rs.) Amount (Rs.)

1 Dewatering of water trenches during


excavation, concreting, masonary work upto
sub soil/water level including hire charges of 5 Hrs 840 840 200.00 168000.00
HP Pump
2 #REF!
Cum 2 200.00 2.0 1.98 1584.00 131.25 207900.00

3 Random Rubble Stone Masonry laid in 1:5


cement and sand mortar, in breast walls,
retaining walls, parapets, scuppers, etc.
including supply of all material, labour, T&P
and royaltiies etc. complete as per drawing
and technical specifications Clauses 702,
704,1202 & 1203 of MORD Specifiction

Section-1 Cum 2 200.00 2.05 820.00


Section-2 Cum 2 315.00 0.55 346.50
Total 1166.50 2398.50 2797850.25
4 Providing and laying cement concrete M-30 in
superstructure as per drawing & technical
specifications Clauses 800, 1205.4 and
1205.5 Standard Data Book For Analysis Of
Rates for Rural Roads,Sr No 13.1(iii), Pg-13 -
overlay on damaged causeways

Section-1 Cum 2 200.00 10.00 0.19 760.00


Section-2 Cum 2 315.00 10.00 0.19 1197.00
Total 1957.00 7489.10 14656168.70
5 Concrete with cement, coarse sand and 40
mm gauge stone ballast in proportion 1:4:8 in
foundations and floors including supply of au·
material, labour and T&P etc. requited for
proper completion of the work as per
drawings and technical specifications Clause
802, 803, 1202 & 1203

Section-1 (Below Retaing wall) Cum 2 200.00 1.54 0.10 61.60


Section-2 (Below Retaing wall) Cum 2 315.00 0.75 0.10 47.25
Section-1 (Below PQC) Cum 2 200.00 2.00 0.10 80.00
Section-2 (Below PQC) Cum 2 315.00 2.50 0.10 157.50
Total 188.85 4580.90 865102.97
6 Construction of granular sub-base by
providing Well graded material grade-
I,spreading in uniform layers with motor
grader on prepared surface mixing by mix in
place method with rotavator at OMC,and
compacted with smooth wheel roller to
achieve the desired

Section-1 Cum 2 200.00 2.00 0.15 120.00


Section-2 Cum 2 315.00 2.50 0.15 236.25
Total 356.25 2586.50 921440.63
7 Hand Packed stone filling in back of wallis
including cost' of all materials, royality, T&P
e.t. c. complete as per direction of Engineer-in Cum 2 200.00 2.00 2.16 1728.00 1828.80 3160166.4
charge.
8 Making provision for weep holes with 100mm
dia polymer pipes fixed at an angle of 45 No 160.00 - - 160.00 60.00 9600.00
degrees placed 2.5m c/c
9 Cement Plum Concrete with 40% plum & 60%
1:3:6 Cement Concrete including Supply of All
material,labour,T&P etc. required for proper
completion of the work as per
drawing/Technical specifications clause
802,803,1202 & 1203 of MORD specification

Section-1 Cum 2 200.00 1.20 1.25 600.00


Section-2 Cum 2 315.00 1.15 1.25 905.63
Total 1505.63 4720.00 7106550.00
10 Providing and laying boulder pitching as per
drawing and technical specifications Clause
1302 (25-40 Kg)
Section-1 Cum 1 200.00 8.00 0.30 480.00
Section-2 Cum 1 315.00 8.00 0.30 756.00
Total 1236.00 832.00 1028352.00
Cost For 800 Sqm area Total (Rs.) 30921130.95
Say(Rs.) 309.21
Lacs

Assistant Engineer Executive Engineer


Junior Engineer PMGSY Division, PWD PMGSY Division, PWD
PMGSY Division, PWD Sonebhadra Sonebhadra
Sonebhadra
RATE ANALYSIS
Package No: Package: UP-67163
Name of Work: Constrcution of Bridge on Nala at Km. 20 on Windamgunj Piparkhad to Auradad Road (Package No.: UP-671
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
2.2 201 Clearing and Grubbing Road Land
Clearing and grubbing road land including uprooting wild
vegetation, grass, bushes, shrubs, saplings and trees of girth
upto 300 mm, removal of stumps of such trees cut earlier and
disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned, upto a lead of 1000 m
including removal and disposal of top organic soil not
exceeding 150 mm in thickness as per Technical Specification
Clause 201.

Unit = hectare
Taking output = 1 hectare
(I) By Manual Means
(A) In area of non-thorny jungle
a) Labour
Mate day 6.00 250.00 1,500.00
Mazdoor (Unskilled) day 150.00 235.00 35,250.00
b) Machinery
Tractor with trolley hour 1.00 444.60 444.60
c) Overheads @ 10% on 3,719.46
d) Contractor Profit @ 10% on 4,091.41
Rate per hectare = a+b+c+d 45,005.47
Rate per sqm = a+b+c+d 4.5
Rate with Reduction factor=1.125/1.21 4.184
Labour cess 1% 0.042
Say (Rs.) 4.23
3.4 301.5 Construction of Embankment with Material Obtained from
Borrow Pits
Construction of embankment with approved material obtained
from borrow pits with a lift upto 1.5 m, transporting to site,
spreading, grading to required slope and compacting to meet
requirement of Tables 300.1 and 300.2 with a CARTED upto
5000 m as per Technical Specification Clause 301.5

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum hour 1.67 1,596.00 2,665.32
per hour
Tipper 5.5 cum with 10 t capacity hour 4.50 380.00 1,710.00
Dozer D-50 for spreading @ 200 cum per hour hour 0.00 2,703.70 0.00
Motor grader for grading @ 200 cum per hour hour 0.50 2,935.50 1,467.75
Water tanker 6 kl capacity hour 0.00 380.00 0.00
Three wheel 80-100 kN Static Roller @ 80 cum per hour hour 1.25 564.30 705.38
Add cartage of 5 km without CP
=( Cartage of 5 km 182.70-35.00(loading))/1.10 cum 100.00 134.27 13,427.27
c) Material
Water kl 0.00 50.00 0.00
Compensation for earth taken from private land cum 100.00 20.00 2,000.00
d) Overheads @ 10% on (a+b+c) 2,222.07
e) Contractor’s profit @ 10% on (a+b+c+d) 2,444.28
Cost for 100 cum = a+b+c+d+e 26,887.07
Rate per cum = (a+b+c+d+e)/100 268.87
Rate with Reduction factor=1.125/1.21 249.98
Labour cess 1% 2.50
Say (Rs.) 252.48
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
4.1 401 Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by providing well
graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired density,
complete as per Technical Specification Clause 401.

(i) For GradingIII Material


Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 250.00 100.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 8.00 235.00 1,880.00
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.00 2,935.50 17,613.00
Three wheel 80-100 kN static roller @ 10 cum hour 30.00 564.30 16,929.00
per hour
Tractor with Rotavator 25 cum per hour hour 12.00 444.60 5,335.20
Water tanker 6 kl capacity hour 5.00 380.00 1,900.00
c) Material
Well graded granular sub-base material as per
Table 400.1
53 mm to 9.5 mm @ 50 per cent cum 180.00 1,865.60 335,808.00
9.5 mm to 2.36 mm @ 20 per cent cum 72.00 1,630.60 293,508.00
2.36 mm below @ 30 per cent cum 108.00 1,540.60 110,923.20
Water kl 30.00 50.00 5,400.00
d) Overheads @ 10% on 78,989.64
e) Contractor Profit @ 10% on 86,888.60
Rate for 300 cum = a+b+c+d+e 955,774.64
Rate for per cum = (a+b+c+d+e)/300 3,185.92
Rate with Reduction factor=1.125/1.21 2,962.11
Add Royalty per cum for 53 mm to 9.5 mm,9.5 mm to 2.36 mm &cum 360.00 110.00 132.00
Labour cess 1% 30.94
Say (Rs.) 2,993.05
4.7 405 Water Bound Macadam Sub-base/base
2) WBM Grading 2
Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness,
hand packing, rolling with smooth wheel roller 80-100 kN
in stages to proper grade and camber, applying and
brooming, stone screening/binding materials to fill-up the
interstices of coarse aggregate, watering and compacting
to the required density grading 2 as per Technical
Specification Clause 405.

(A) By Manual Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.08 250.00 2,520.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 250.00 235.00 58,750.00
b) Machinery
Three wheel 80-100 kN static roller @ 8 cum per hour 45.00 564.30 25,393.50
hour
Water tanker 6 kl capacity hour 24.00 380.00 9,120.00
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 cum 435.60 1,565.60 681,975.36
sqm for compacted thickness of 75 mm
Stone Screening
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Type B 11.2 mm for Grading 2 @ 0.20 cum per cum 96.01 1,249.60 119,974.10
10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for cum 28.80 1,560.60 44,945.28
Grading 2 material
Water kl 144.00 50.00 7,200.00
d) Overheads @ 10% on 95,037.82
e) Contractor Profit @ 10% on 104,541.61
Rate for 360 cum = a+b+c+d+e 1,149,957.67
Rate for per cum = (a+b+c+d+e)/360 3,194.33
Rate with Reduction factor=1.125/1.21 2,969.93
Add Royalty per cum for 45-63 mm stone ballast cum 435.60 110.00 133.10
Add Royalty per cum for type B 11.2 mm screening matcum 96.01 160.00 42.67
Add Royalty per cum binding material (stone dust) cum 28.80 100.00 8.00
Labour cess 1% 31.54
Say (Rs.) 3,185.24
3) WBM Grading 3
Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness,
hand packing, rolling with smooth wheel roller 80-100 kN
in stages to proper grade and camber, applying and
brooming, stone screening to fill-up the interstices of
coarse aggregate, watering and compacting to the
required density Grading 3 as per Technical Specification
Clause 405.

(A) By Manual Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.08 250.00 2,520.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 250.00 235.00 58,750.00
b) Machinery
Three wheel 80-100 kN static roller @ 8 cum per hour 45.00 564.30 25,393.50
hour
Water tanker 6 kl capacity hour 24.00 380.00 9,120.00
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 3 53 mm to 22.4 mm @ 0.91 cum per cum 435.60 1,785.60 777,807.36
10 sqm for compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 3 @ 0.18 cum per cum 86.40 1,249.60 107,965.44
10 sqm
Water kl 144.00 50.00 7,200.00
d) Overheads @ 10% on 98,925.63
e) Contractor Profit @ 10% on 108,818.19
Rate for 360 cum = a+b+c+d+e 1,197,000.1
Rate for per cum = (a+b+c+d+e)/360 3,325.00
Rate with Reduction factor=1.125/1.21 3,091.43
Add Royalty per cum for 22.4-53 mm stone ballast cum 435.60 110.00 133.10
Add Royalty per cum for type B 11.2 mm screening matcum 86.40 160.00 38.40
Add 1% Labour cess 32.63
Say (Rs.) 3,295.56
5.1 502 Prime Coat
(i) Low porosity
Providing and applying primer coat with bitumen emulsion on
prepared surface of granular base including cleaning of road
surface and spraying primer at the rate of 0.70-1.0 kg/sqm
using mechanical means as per Technical Specification Clause
502
Unit = sqm
Taking output = 1750 sqm
a) Labour
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 437.00 611.80
Air compressor 210 cfm hour 1.40 391.40 547.96
Bitumen emulsion pressure distributor @ 1750 sqm hour 1.00 980.40 980.40
per hour
Water tanker 6 kl capacity 1 trip per hour hour 0.50 380.00 190.00
c) Material
Bitumen emulsion (SS-1) @ 0.70 kg per sqm t 1.23 35,341.84 43,293.75
Water for mixing in emulsion two times of water kl 1.17 20.00 23.40
d) Overheads @ 10% on 4,589.23
e) Contractor Profit @ 10% on 5,048.15
Rate for 1750 sqm = a+b+c+d+e 55,529.70
Rate for per sqm = (a+b+c+d+e)/1750 31.73
Rate with Reduction factor=1.125/1.21 29.50
Add 1% Labour cess 0.30
Say (Rs.) 29.80
5.2 503 Tack Coat
(ii) Providing and applying tack coat with Bitumen VG-30
using emulsion distributor at the rate of 0.25 to 0.30 kg
per sqm on the prepared dry and hungry bituminous
surface cleaned with Hydraulic broom as per Technical
Specification Clause 503.

Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 437.00 611.80
Air compressor 210 cfm hour 1.40 391.40 547.96
Emulsion pressure distributor @1750 sqm per hour hour 1.00 980.40 980.40
c) Material
Bitumen VG-30 @ 0.30 kg per sqm t 0.53 31,612.64 16,754.70
d) Overheads @ 10% on 1,913.99
e) Contractor Profit @ 10% on 2,105.38
Rate for 1750 sqm = a+b+c+d+e 23,159.23
Rate for per sqm = (a+b+c+d+e)/1750 13.23
Rate with Reduction factor=1.125/1.21 12.304
Add 1% Labour cess 0.123
Say (Rs.) 12.43
5.9 508 Open Graded Premix Carpet
20mm thick Open-Graded Premix Carpet using
Providing, laying and rolling of open-graded premix carpet of
20 mm thickness composed of 13.2 mm to 5.6 mm aggregates
either using VG-30 bitumen to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a
three wheel 80-100 kN static roller capacity, finished to
required level and grades to be followed by seal coat of either
Type A or Type B or Type C as per Technical Specification
Clause 508.

Case - II By Mechanical Means


(I) Bitumen (VG-30)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day 0.52 250.00 130.00
Mazdoor (Unskilled) day 10.00 235.00 2,350.00
Mazdoor (Skilled) day 3.00 250.00 750.00
b) Machinery
HMP 30/40 t per hour hour 6.00 13,585.00 81,510.00
Electric generator set 125KVA hour 6.00 855.00 5,130.00
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Front end loader 1 cum bucket capacity hour 6.00 988.00 5,928.00
Tipper 5.5-10 capacity hour 3.64 380.00 1,383.20
Paver finisher hour 6.00 1,195.10 7,170.60
Three wheel 80-100 kN static roller hour 16.00 564.30 9,028.80
c) Material
Bitumen VG-30 @ 14.60 kg per 10 sqm t 5.84 31,612.64 184,617.82
Crushed stone chipping 13.2 mm @ 0.18 cum/10 cum 72.00 1,729.60 124,531.20
sqm
Crushed stone chipping 11.2 mm @ 0.09 cum/10 cum 36.00 1,659.64 59,747.04
sqm
d) Overheads @ 10% on 48,227.67
e) Contractor Profit @ 10% on 53,050.43
Rate for 4000 sqm = a+b+c+d+e 583,554.76
Rate for per sqm = (a+b+c+d+e)/4000 145.89
Rate with Reduction factor=1.125/1.21 135.64
Add Royalty per cum for 13.2 mm &11.2 mm stone grit cum 108 160 4.320
Add 1% Labour cess 1.400
Say (Rs.) 141.36
5.12 510 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous VG-30 surface laid to the specified levels, grade
and cross fall using Type B as per Technical Specification
Clause 510
A. By Manual Means
(I) Bitumen(vg-30)
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate day 0.85 250.00 212.50
Mazdoor (Unskilled) day 15.00 235.00 3,525.00
Mazdoor (Semi-Skilled) day 2.00 235.00 470.00
b) Machinery
Mixall 6/10 t capacity hour 2.50 1,350.00 3,375.00
Three wheel 80-100 kN static roller hour 2.50 564.30 1,410.75
Bitumen boiler oil fired 1000 litre capacity fitted with hour 2.50 243.20 608.00
spray set
c) Material
Bitumen (VG-30) @ 6.80 kg per 10 sqm t 0.85 31,612.64 26,870.74
Crushed sand or grit as passing 2.36 mm sieve and cum 7.50 1,179.60 8,847.00
retained on 180 micron sieve applied @ 0.06 cum per 10
d) sqm
Overheads @ 10% on (a+b+c) 4,531.90
e) Contractor’s profit @ 10% on (a+b+c+d) 4,985.09
Cost of 1250 sqm = a+b+c+d+e 54,835.98
Rate per sqm = (a+b+c+d+e)/1250 43.87
Rate with Reduction factor=1.125/1.21 40.79
Add Royalty per cum for stone grit cum 7.50 160 0.240
Add 1% Labour cess 0.410
Say (Rs.) 41.44
10.1 1700 Printing New Letters and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade as per drawings and Technical Specification
Clause 1701
i) Hindi (Matras commas and the like not to be
Details for 100 letters of 160 mm height, i.e., 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.12 250.00 30.00
Painter 1st Class day 2.00 385.00 770.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
b) Material
Paint litre 0.70 198.55 138.99
c) Overheads @ 10% on 117.40
d) Contractor Profit @ 10% on 129.14
Rate for cm height per letter 1600 m = a+b+c+d 1,420.52
Rate for cm height per letter = (a+b+c+d)/1600 0.89
Rate with Reduction factor=1.125/1.21 0.83
Say (Rs.) 0.83
ii) English and Roman
Hyphens, commas and the like not to be measured and
paid for. Detail for 100 letters of 160 mm height, i.e.,
1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 250.00 17.50
Painter Ist class day 1.25 385.00 481.25
Mazdoor day 0.50 235.00 117.50
b) Material
Paint litre 0.50 198.55 99.28
c) Overheads @ 10% on 71.55
d) Contractor Profit @ 10% on 78.71
Rate for cm height per letter 1600 m = a+b+c+d 865.79
Rate for cm height per letter = (a+b+c+d)/1600 0.54
Rate with Reduction factor=1.125/1.21 0.50
Add 1% Labour cess 0.005
Say (Rs.) 0.51
10.4 1700, 800 & B. Semi-Reflective Traffic signs
300 Providing and erecting direction and place identification of
semi reflective sign boards as per IRC-67 made of 2 mm
thick M.S. Sheet duly stove enameled paint white colour
in front and grey colour on back with reflective border of
70 mm width and required message, letters, figures with
reflective tape of engineering grade as per MORD
specifications of required shade and colour. Supported
and welded on two nos. 47 mm x 47 mm of 12 SWG
square tube of 3050 mm height duly strengthened by 25
mm x 5 mm MS flat iron on edges on back firmly fixed to
the ground by means of properly designed foundations
with M-15 grade cement concrete 450 mm x 450 mm x
600 mm, 600 mm below ground level as per approved
drawing and Technical Specification Clause 1701

Unit = each
Taking output = 1.5 sqm
(i) Excavation for foundations as
As per item no. 11.1 Chapter 11 cum 0.252 100.00 25.20
(ii) Cement Concrete M15 grade
As per item No.11.4 of Chapter 11 cum 0.252 4,589.65 1,156.59
(iii) Painting M.S. tube posts with primer and two
coats of epoxy paint as per specification
As per item No. 10.7 of chapter 10 sqm 0.92 81.10 74.61
a) Labour (fox fixing at site)
Mate day 0.02 250.00 5.00
Mazdoor (Unskilled) day 0.50 235.00 117.50
b) Material
i) Support of MS Sheet tubes 47 mm x 47 mm x 12 kg 24.80 60.00 1,488.00
SWG sheet 3050 mm long
ii) Angle iron 50 mm x 50 mm x 6 mm for lugs kg 2.12 40.00 84.80
iii) 2 mm thick MS Sheet strengthened by 25 mm x 5 mm sqm 1.50 840.00 1,260.00
M.S. flat iron and painted with stove enameled paint
including lettering, signs, messages, border with
reflective tape of engineering grade of required size,
shade and colour as per MORD specifications

Add 3% cost of MS sheet and angle iron towards the 84.98


cost of fabrications, drilling, holes, nuts, bolts etc.
c) Machinery
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Tractor with trolley hour 0.16 444.60 71.14
d) Overheads @ 10% on 311.14
e) Contractor Profit @ 10% on 342.26
Cost for 1.5 sqm board = (i+ii+iii+a+b+c+d+e) 5,021.22
Rate per sqm = (i+ii+iii+a+b+c+d+e) / 1.5 3,347.48
Rate with Reduction factor=1.125/1.21 3,112.33
Add Royalty per cum for coarse sand cum 0.121 150 12.10
Add Royalty per cum for40mm cum 0.121 110 8.87
Add Royalty per cum for20mm & 10 mm cum 0.081 160 8.60
Add 1% Labour cess 31.42
Say (Rs.) 3,173.31
10.5 1700 Painting Two Coats on New Concrete Surfaces
Painting two coats including primer coat after filling the surface
with synthetic enamel paint in all shades on new, plastered /
concrete surfaces as per drawing and Technical Specification
Clause 1701

Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.20 250.00 50.00
Painter (1st Class) day 3.00 385.00 1,155.00
Mazdoor (Unskilled) day 2.00 235.00 470.00
b) Material
Cement Primer as per specifications litre 3.00 68.25 204.75
Paint conforming to requirement of Clause 1701.3.8 litre 6.00 198.55 1,191.30
Add for scaffolding @ 1 per cent of labour cost where 16.75
required
d) Overheads @ 10% on 308.78
e) Contractor Profit @ 10% on 339.66
Cost for 40 sqm = a+b+c+d+e 3,736.24
Rate per sqm = (a+b+c+d+e)/40 93.41
Rate with Reduction factor=1.125/1.21 86.84
Add 1% Labour cess 0.87
Say (Rs.) 87.71
10.7 1700 Painting on Concrete/Steel Surfaces with Epoxy
Painting two coats including prime coat with epoxy paint of
approved brand on concrete/steel surfaces after through
cleaning of surface to give an even shade as per drawing and
Technical Specification Clause 1701
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.25 250.00 62.50
Painter (1st Class) day 0.60 385.00 231.00
Mazdoor (Unskilled) day 0.40 235.00 94.00
b) Material
Epoxy primer/Red-oxide litre 0.60 126.00 75.60
Epoxy paint litre 1.25 275.00 343.75
Add @ 1 per cent on cost of material for scaffolding 4.19
wherever required
d) Overheads @ 10% on 81.10
e) Contractor Profit @ 10% on 89.21
Cost for 10 sqm = (a+b+c+d+e) 981.36
Rate per sqm = (a+b+c+d+e)/10 98.14
Rate with Reduction factor=1.125/1.21 91.24
Add 1% Labour cess 0.91
Say (Rs.) 92.15
10.4 1700, 800 & B. Semi-Reflective Traffic signs
300
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification
1700, 800 & (Rs.) (Rs.)
s
300 Providing and erecting direction and place identification of
semi reflective sign boards as per IRC-67 made of 2 mm
thick M.S. Sheet duly stove enameled paint white colour
in front and grey colour on back with reflective border of
70 mm width and required message, letters, figures with
reflective tape of engineering grade as per MORD
specifications of required shade and colour. Supported
and welded on two nos. 47 mm x 47 mm of 12 SWG
square tube of 3050 mm height duly strengthened by 25
mm x 5 mm MS flat iron on edges on back firmly fixed to
the ground by means of properly designed foundations
with M-15 grade cement concrete 450 mm x 450 mm x
600 mm, 600 mm below ground level as per approved
drawing and Technical Specification Clause 1701

Unit = each
Taking output = 1.5 sqm
(i) Excavation for foundations as
As per item no. 11.1 Chapter 11 cum 0.252 101.00 25.45
(ii) Cement Concrete M15 grade
As per item No.11.4 of Chapter 11 cum 0.252 4,589.65 1,156.59
(iii) Painting M.S. tube posts with primer and two
As per item No. 10.7 of chapter 10 sqm 0.92 81.10 74.61
a) Labour (fox fixing at site)
Mate day 0.02 250.00 5.00
Mazdoor (Unskilled) day 0.50 235.00 117.50
b) Material
i) Support of MS Sheet tubes 47 mm x 47 mm x 12 kg 24.80 60.00 1,488.00
SWG sheet 3050 mm long
ii) Angle iron 50 mm x 50 mm x 6 mm for lugs kg 2.12 40.00 84.80
iii) 2 mm thick MS Sheet strengthened by 25 mm x 5 sqm 1.50 840.00 1,260.00
mm M.S. flat iron and painted with stove
enameled paint including lettering, signs,
messages, border with reflective tape of
engineering grade of required size, shade and
colour as per MORD specifications
Add 3% cost of MS sheet and angle iron towards 84.98
the cost of fabrications, drilling, holes, nuts, bolts
etc.
c) Machinery
Tractor with trolley hour 0.16 444.60 71.14
d) Overheads @ 10% on (a+b+c) 436.81
e) Contractor Profit @ 10% on (a+b+c+d) 354.82
Cost for 1.5 sqm board = (i+ii+iii+a+b+c+d+e) 5,159.71
Rate per sqm = (i+ii+iii+a+b+c+d+e) / 1.5 3,439.80
Rate with Reduction factor=1.125/1.21 3,198.16
Add Royalty per cum for coarse sand cum 0.121 150 12.10
Add Royalty per cum for40mm cum 0.121 110 8.87
Add Royalty per cum for20mm & 10 mm cum 0.081 160 8.60
Add 1% Labour cess 32.28
Say (Rs.) 3,260.01
10.16 1700 Providing and Fixing 'Logo' of PMGSY Project
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Providing and fixing of typical PMGSY informatory sign board
with Logo as per MORD specifications and drawing. Three MS
Plates of 1.6 mm thick, top and middle plate duly welded with
MS flat iron 25mm x 5m size on back on edges. The lower
plate will be welded with MS angle iron frame of 25mm x
25mm x 5mm. The angle iron frame of the lower most plate
and flat iron frame of middle plate will be welded to 2 nos.
75mm x 75 mm of 12 SWG sheet tubes posts duly embedded
in cement concrete M-15 grade blocks of 450mm x 450mm x
600mm, 600mm below ground level. The top most diamond
plate will be welded to middle plate by 47mm x 47mm of 12
SWG steel plate tube. All M.S. will be stove enameled on both
sides. Lettering and printing arrows, border etc. will be painted
with ready mixed synthetic enamel paint of superior quality in
required shade and colour. All sections of framed posts and
steel tube will be painted with primer and two coats of epoxy
paint as per drawing Clause 1701 and Annexure 1700.1

Unit = Each
Taking out put = one typical board
(i) Excavation for foundations
As per item No. 11.1 of Chapter 11 cum 0.252 100.000 25.20
(ii) Cement Concrete M15 grade
As per item No. 11.4 of Chapter 11 cum 0.252 4,589.65 1,156.59
(iii) Painting on MS Steel tubes with primer and two coats
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 10.7 of Chapter 10 sqm 1.80 81.10 145.98
iv) Printing new letters and figures of any shade with
Logo Border 60x4x5 = 1200 per cm height per letter
Figure 60x10 = 600 per cm height per letter
Middle plate words 28x5 = 140 per cm height per letter
Bottom plate border 150x2x5 = 1500 per cm height per letter
Bottom plate border 60x2x5 = 600 per cm height per letter
Words 101x2.5 = 252.5
Words 80x3 = 240.00
Total 4532.5 per cm height per letter
As per item No.10.1 of Chapter 10 per cm 4,532.50 0.71 3,218.08
a) Labour (for fixing at site) height
per litre
Mate day 0.03 250.00 7.50
Mazdoor (Unskilled) day 0.75 235.00 176.25
b) Material
2 nos. MS tubes 75mx75mm of 12 SWG sheet 2650 kg 63.15 60.00 3,789.00
1 No. MS tube 47mm x 47mm of 12 SWG 1100 mm kg 4.47 60.00 268.20
Angle iron 50mm x 50mm x 5 mm for lugs kg 2.12 40.00 84.80
1.6 mm thick MS sheet strengthened by 25mm x 5 sqm 1.44 840.00 1,209.60
MS flat iron on logo and middle plate angle iron
25mm x 25mm x 5mm on bottom plate painting with
stove enameled paint on both sides as per MORD
specifications

Add 3% cost of MS tube and angle iron towards the 160.55


cost of fabrications, drilling holes, nuts, bolts, etc.
c) Machinery
Tractor with trolley hour 0.24 444.60 106.70
d) Overheads @ 10% on 580.26
e) Contractor Profit @ 10% on 638.29
Cost for one Board= (i+ii+iii+iv+a+b+c+d+e) 11,566.99
Rate with Reduction factor=1.125/1.21 10,754.44
Add Royalty per cum for coarse sand cum 0.121 150 12.10
Add Royalty per cum for40mm cum 0.121 110 8.9
Add Royalty per cum for20mm & 10 mm cum 0.081 160 8.60
Add 1% Labour cess 107.84
Say 10,784.00
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
11.1 300 Excavation for Structures
Excavation in fondation in soil mixed with
moorum/single/kankar including filling upto 1.50 m and lead
upto 30 m and including filling,watering and ramming of
excavated earth into the trnches or into the sapce between the
building/ structure and the side of fondation trenches or plinth
and removel and disposal of surface earth as directed by
Engineer in charge upto a distance of 30 m from the
foundation trenches including all T& P and material etc
complete as per UPPWD specification SNo.2-252

As per SOR 100.00


With Labour cess 1% Say (Rs.) 101.00
11.4 800 & 1200 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203

I. P.C.C grade M 10
(i) Nominal mix 1:3:6
Unit = cum
a) Material
Cement t 0.250 5,560.00 1,390.00
Coarse sand cum 0.48 1,205.10 578.45
40 mm aggregate cum 0.576 1,875.60 1,080.35
20 mm aggregate cum 0.288 2,029.60 584.52
10 mm aggregate cum 0.096 1,379.60 132.44
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.10 380.00 38.00
Mazdoor (Unskilled) day 1.63 235.00 383.05
Bhisti day 0.27 260.00 70.20
c) Machinery
Mechnical concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
fitted with water measuring device and preferably
also with load cell.
d) Formwork @ 2% on cost of material, labour and 2% 87.82
machinery (a+b+c)
e) Overheads @ 10% on (a+b+c+d) 10% 447.88
f) Contractor’s profit @ 10% on (a+b+c+d+e) 10% 492.67
Rate per cum = a+b+c+d+e+f 5,419.38
Add Royalty per cum for coarse sand cum 0.48 150 72.00
Add Royalty per cum for40mm cum 0.58 110 63.36
Add Royalty per cum for20mm & 10 mm cum 0.38 160 61.44
Add 1% Labour cess 56.16
Say (Rs.) 5672.35
P.C.C grade M 10

(ii) Nominal mix 1:3.6 (Hand mixing)


Unit = cum
a) Material
Cement t 0.250 5,560.00 1,390.00
Coarse sand cum 0.480 1,205.10 578.45
40 mm aggregate cum 0.576 1,875.60 1,080.35
20 mm aggregate cum 0.288 2,029.60 584.52
10 mm aggregate cum 0.100 1,379.60 137.96
b) Labour
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Mate day 0.09 250.00 22.50
Mason (1st Class) day 0.10 380.00 38.00
Mazdoor (Unskilled) day 2.00 235.00 470.00
Bhisti day 0.27 260.00 70.20
c) Formwork @ 4% on cost of material (a) and 4% 174.88
labour (b)
d) Overheads @ (a+b+c) 10% on 454.69
e) Contractor Profit @ 10% on 500.15
Rate for per cum = a+b+c+d+e 5,501.70
Add Royalty per cum for coarse sand cum 0.48 150 72.00
Add Royalty per cum for40mm cum 0.58 110 63.36
Add Royalty per cum for20mm & 10 mm cum 0.38 160 61.44
Add 1% Labour cess 56.98
Say (Rs.) 5755.48
II. P.C.C grade M 15

(i) Nominal mix (1:2.5:5)


Unit = cum
a) Material
Cement t 0.275 5,560.00 1,529.00
Coarse sand cum 0.48 1,205.10 578.45
40 mm aggregate cum 0.48 1,875.60 900.29
20 mm aggregate cum 0.33 2,029.60 669.77
10 mm aggregate cum 0.08 1,379.60 110.37
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.10 380.00 38.00
Mazdoor (Unskilled) day 1.63 235.00 383.05
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
d) Formwork @ 4% on cost of material, labour and 4% 176.52
machinery (a+b+c)
e) Overheads @ 10% on (a+b+c+d) 10% 458.96
f) Contractor’s profit @ 10% on (a+b+c+d+e) 10% 504.86
Rate per cum = a+b+c+d+e+f 5,553.47
Add Royalty per cum for coarse sand cum 0.48 150 72.00
Add Royalty per cum for40mm cum 0.58 110 63.36
Add Royalty per cum for20mm & 10 mm cum 0.38 160 61.44
Add 1% Labour cess 57.50
Say (Rs.) 5807.78
III. P.C.C. grade M 20

(i) Nominal mix (1:2:4)


Unit = cum
a) Material
Cement t 0.33 5,560.00 1,834.80
Sand cum 0.45 1,205.10 542.30
40 mm aggregate cum 0.36 1,875.60 675.22
20 mm aggregate cum 0.36 2,029.60 730.66
10 mm aggregate cum 0.18 1,379.60 248.33
b) Labour
Mate day 0.08 250.00 20.00
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Mason (1st Class) day 0.10 380.00 38.00
Mazdoor (Unskilled) day 1.63 235.00 383.05
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
d) Formwork @ 4% on (a+b+c) 4% 186.26
e) Overheads @ 10% on (a+b+c+d) 10% 484.28
f) Contractor’s profit @ 10% on (a+b+c+d+e) 10% 532.71
Rate per cum = a+b+c+d+e+f 5,859.80
Add Royalty per cum for coarse sand cum 0.45 150 67.50
Add Royalty per cum for40mm cum 0.36 110 39.60
Add Royalty per cum for20mm & 10 mm cum 0.54 160 86.40
Add 1% Labour cess 60.53
0.00 6113.83
IV. R.C.C grade M 20
Unit = cum
a) Material
Cement t 0.35 5,560.00 1,946.00
Coarse sand cum 0.45 1,205.10 542.30
20 mm aggregate cum 0.54 2,029.60 1,095.98
10 mm aggregate cum 0.36 1,379.60 496.66
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.12 380.00 45.60
Mazdoor (Unskilled) day 1.73 235.00 406.55
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
d) Formwork @ 4% on (a+b+c) 4% 189.49
e) Overheads @ 10% on (a+b+c+d) 10% 492.68
f) Contractor’s profit @ 10% on a+b+c+d+e 10% 541.95
Rate per cum = (a+b+c+d+e+f) 5,961.40
Add Royalty per cum for coarse sand cum 0.35 150 52.50
Add Royalty per cum for40mm cum 0.45 110 49.50
Add Royalty per cum for20mm & 10 mm cum 0.90 160 144.00
Add 1% Labour cess 62.07
0.00 6269.47
V. R.C.C. grade M 25
Unit = cum
a) Material
Cement t 0.40 5,560.00 2,246.24
Coarse sand cum 0.45 1,205.10 542.30
20 mm aggregate cum 0.54 2,029.60 1,095.98
10 mm aggregate cum 0.36 1,379.60 496.66
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.12 380.00 45.60
Mazdoor (Unskilled) day 1.73 235.00 406.55
Bhisti day 0.27 260.00 70.20
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
d) Formwork @ 3.75% on (a+b+c) 3.75% 188.91
e) Overheads @ 10% on (a+b+c+d) 10% 522.64
f) Contractor’s profit @ 10% on (a+b+c+d+e) 10% 574.91
Rate per cum = a+b+c+d+e+f 6,323.98
Add Royalty per cum for coarse sand cum 0.40 150 60.60
Add Royalty per cum for40mm cum 0.45 110 49.50
Add Royalty per cum for20mm & 10 mm cum 0.90 160 144.00
Add 1% Labour cess 65.78
0.00 6643.86
III. R.C.C. Grade M 30
Unit =cum
a) Material
Cement t 0.43 5,560.00 2,390.80
Sand cum 0.45 1,205.10 542.30
20 mm aggregate cum 0.54 2,029.60 1,095.98
10 mm aggregate cum 0.36 1,379.60 496.66
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.12 380.00 45.60
Mazdoor (Unskilled) day 1.73 235.00 406.55
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
d) For formwork and staging refer to sub-item (d) of I (II) 302.91
above
e) Overheads @ 10% on (a+b+c+d) 10% 548.50
f) Contractor’s profit @ 10% on (a+b+c+d+e) 10% 603.35
Rate per cum = a+b+c+d+e+f Say (Rs.) 6,636.84
Add Royalty per cum for coarse sand cum 0.45 150 67.50
Add Royalty per cum for20mm & 10 mm cum 0.90 160 144.00
Add 1% Labour cess 68.48
0.00 6916.82

Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
a) Material
Cement t 0.51 5,560.00 2,835.60
Sand cum 1.05 1,205.10 1,265.36
b) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 0.90 235.00 211.50
Bhisti day 0.08 260.00 20.80
Total material and labour = (a+b) Say (Rs.) 4343.255
12.2 600 Pointing with cement mortar (1:3) on stone masonary as
per drawing and technical specification Clauses 613.3 and
1204

Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1.3 (Rate as in item 11.5. I) cum 0.03 4,343.26 130.30
b) Labour
Mate day 0.04 250.00 10.00
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Mason 1st Class day 0.50 380.00 190.00
Mazdoor (Unskilled) day 0.50 235.00 117.50
Bhisti day 0.20 260.00 52.00
c) Overheads @ 10% on 49.98
d) Contractor Profit @ 10% on 54.98
Rate for 10 sqm = a+b+c+d 604.76
Rate for per sqm = (a+b+c+d)/10 60.48
Reduction factor=1.125/1.21 56.23
Add Royalty per cum for coarse sand cum 0.03 150 0.47
Add 1% Labour cess 0.57
Say (Rs.) 57.27
12.4 700 Stone masonry in cement mortar for substructure
complete as per drawing & technical specification Clauses
702, 704, 1202 and 1204
I. Coursed rubble masonry (1st sort)
(i) In 1:3 cement mortar
Unit = cum
a) Material
Stone for CR masonry 1st sort cum 1.10 1,530.60 1,683.66
Through and bond stone Nos. 7.00 9.50 66.50
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5. I) cum 0.30 4,343.26 1,302.98
b) Labour
Mate day 0.14 250.00 35.00
Mason (1st Class) day 1.50 380.00 570.00
Mazdoor (Unskilled) day 2.10 235.00 493.50
Bhisti day 0.08 260.00 20.80
Add for scaffolding @ 5 per cent of cost of 208.62
material (a) and labour (b) (a+b)
c) Overheads @ 10% 10% on 438.11
d) Contractor Profit @ 10% 10% on 481.92
Rate per cum = a+b+c+d 5,301.08
Reduction factor=1.125/1.21 4,928.69
Add Royalty per cum for sand cum 0.32 150 47.25
Add Royalty per cum for stone cum 1.10 110 121.00
Add 1% Labour cess 50.97
Say (Rs.) 5,147.91
13.1 800 Providing and laying reinforced cement concrete in
superstructure complete as per drawings and technical
specification Clauses 800, 1205.4 and 1205.5

Unit = cum
III. R.C.C. Grade M 30
Unit =cum
a) Material
Cement t 0.43 5,560.00 2,390.80
Sand cum 0.45 1,205.10 542.30
Recron Fibre @ 100gm per 50 Kg cement Kg 0.86 700.00 602.00
20 mm aggregate cum 0.54 2,029.60 1,095.98
10 mm aggregate cum 0.36 1,379.60 496.66
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.12 380.00 45.60
Mazdoor (Unskilled) day 1.73 235.00 406.55
Bhisti day 0.27 260.00 70.20
c) Machinery
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
d) Add for Formwork and staging height upto 5.0m @ 20% 1,156.82
20% (a+b+c)
e) Overheads @ 10% on 694.09
f) Contractor Profit @ 10% on 763.50
Rate for 1 cum = a+b+c+d+e+f 8,398.49
Add Royalty per cum for sand cum 0.45 150 67.50
Add Royalty per cum for stone cum 0.90 160 144.00
Add 1% Labour cess 413.42
Say (Rs.) 9,023.41
II. P.C.C grade M 15
(i) Nominal mix (1:2.5:5)
Unit = cum
a) Material
Cement t 0.275 5,560.00 1,529.00
Coarse sand cum 0.48 1,205.10 578.45
40 mm aggregate cum 0.48 1,875.60 900.29
20 mm aggregate cum 0.24 2,029.60 487.10
10 mm aggregate cum 0.08 1,379.60 110.37
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.10 380.00 38.00
Mazdoor (Unskilled) day 1.63 235.00 383.05
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 285.00 114.00
d) Formwork @ 4% on cost of material, labour 0.00
e) and machinery
Overheads (a+b+c)
@ 10% on (a+b+c+d) 10% 423.05
f) Contractor’s profit @ 10% on (a+b+c+d+e) 10% 465.35
Rate per cum = a+b+c+d+e+f 5,118.85
Cement Plum Concrete with 40% plum & 60% 1:3:6 Cement
Concrete including Supply of All material, labour,T&P etc.
required for proper completion of the work as per
drawing/Technical specifications clause 802,803,1202 & 1203

Unit =cum
Taking output 1 cum
a) Material
Stone for RR Masonry cum 0.40 1,124.41 449.76
b) Sub item M-10 (136)
PCC grade M-10 (1:3:6) cum 0.60 5,501.70 3,301.02
Rate for 1 cum = a+b+c 3,750.78
3,750.78
Add Royalty per cum for stone cum 0.40 110 44.00
Add Royalty per cum for 40mm Stone grit cum 0.35 110 38.02
Add Royalty per cum for 20mm &10mm Stone grit cum 0.23 160 36.86
Add Royalty per cum for coarse sand cum 0.29 150 43.20
Add 1% Labour cess 39.13
Say (Rs.) 3,951.99

11.7 1000 & Supplying, fitting, and placing HYSD bar reinforcement in
1200 foundation complete as per drawing and technical
specifications Clauses 1000 and 1202
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Unit = t
a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 41,000.00 43,050.00
Binding wire kg 6.00 57.75 346.50
b) Labour for cutting, bending, tying and placing in
position
Mate day 0.40 250.00 100.00
Blacksmith day 2.00 350.00 700.00
Mazdoor (Unskilled) day 6.00 235.00 1,410.00
c) Overheads @ 10% on 4,560.65
d) Contractor Profit @ 10% on 5,016.72
Rate for per Tonne = a+b+c+d 55,183.87
Add 1% Labour cess 551.84

Say (Rs.) 55,735.70


12.6 1000 Supplying, fitting, and placing HYSD bar reinforcement in
superstructure complete as per drawing and technical
specifications Clauses 1002, 1010 and 1202
Unit = t
a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 41,000.00 43,050.00
Binding wire kg 8.00 57.75 462.00
b) Labour for cutting, bending, tying and placing in position
Mate day 0.44 250.00 110.00
Blacksmith day 3.00 350.00 1,050.00
Mazdoor (Unskilled) day 8.00 235.00 1,880.00
c) Overheads @ 10% on 4,655.20
d) Contractor Profit @ 10% on 5,120.72
Rate for per Tonne = a+b+c+d 56,327.92
Add 1% Labour cess 563.28

Say (Rs.) 56,891.20


14.5 1300 Providing and laying pitching on slopes laid over prepared
filter media as per drawing and technical specifications
Clause 1302

I. Stone/Boulder
Unit = cum
a) Material
Stone boulder (25 kg minimum) cum 1.00 1,480.60 1,480.60
Stone spalls of minimum 25 mm size cum 0.20 400.00 80.00
b) Labour
Mate day 0.04 250.00 10.00
Mason 1st Class day 0.35 380.00 133.00
Mazdoor (Unskilled) day 0.75 235.00 176.25
c) Overheads @ 10% on 187.99
d) Contractor Profit @ 10% on 206.78
Rate for 1 cum = a+b+c+d 2,274.62
Rate for 1 cum = (a+b+c+d)/1 2,274.62
Reduction factor=1.125/1.21 2,114.83
Add Royalty per cum for stone boulder & spalls cum 1.20 110 132.00
Add 1% Labour cess 22.47
Say (Rs.) 2,269.30
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
14.5 1300 Providing and laying boulder apron for bed protection
with stone boulders of minimum size and weight as per
Table 1300.1, no fragment weighing less than 25 kg laid
dry complete as per drawing and technical specifications
Clause 1301

I. Stone/Boulder
Unit = cum
a) Material
Stone boulder (25 kg minimum) cum 1.00 1480.60 1,480.60
Stone spalls of minimum 25 mm size cum 0.20 400.00 80.00
b) Labour
Mate day 0.04 250.00 10.00
Mason 1st Class day 0.35 380.00 133.00
Mazdoor (Unskilled) day 0.75 235.00 176.25
c) Overheads @ 10% on 187.99
d) Contractor Profit @ 10% on 206.78
Rate for 1 cum = a+b+c+d 2,274.62
Rate for 1 cum = (a+b+c+d)/1 2,274.62
Reduction factor=1.125/1.21 2,114.83
Add Royalty per cum for stone boulder & spalls cum 1.2 110 132.00
Add 1% Labour cess 22.47
Say (Rs.) 2,269.30
14.6 1300 Providing and laying filter material underneath pitching in
slopes complete as per drawing and technical
specifications Clause 1302
Unit = cum
a) Material
Graded stone aggregate of required size cum 1.20 1,565.60 1,878.72
b) Labour
Mate day 0.05 250.00 12.50
Mazdoor (Skilled) day 0.25 250.00 62.50
Mazdoor (Unskilled) day 1.02 235.00 239.70
c) Overheads @ 10% on 219.34
d) Contractor Profit @ 10% on 241.28
Rate for 1 cumsqm = a+b+c+d 2,654.04
Rate for 1 cum = (a+b+c+d)/1 2,654.04
Reduction factor=1.125/1.21 2,467.60
Add Royalty per cum for stone boulder & spalls cum 1.20 110 132.00
Add 1% Labour cess 26.00
Say (Rs.) 2,625.59
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Providing and Fixing Citizen information Board of PMGSY
Project
Providing and fixing of typical PMGSY Citizen information
board (Nagrik Suchana Board) as per standard drawing of
NRRDA with two 18SWG MS sheets of size 900x750mm duly
welded with 4 nos, MS Flat iron frame of size 1000x75x5mm &
2 nos. MS flat iron frame on back side of board. The flat iron
frame will be welded with two nos 75x75mm of 12SWG
horizontal sheets in square are tube posts of 1000mm length &
two nos 75x75mm of 12 SWG verticle steel tubes in square
are
1 round
Supplypost of 3050mm
of 75x5mm MS Ironlength dully embed nominal hand
plate. Kg 22.53 60.00 1,351.80
mixed ass per IRC:67 upto 600mmx600mmx750mm blocks
2 Supply
600mm belowof 75x5mm dia steel
ground level. tubewill be stove enabled on
all M:S Rm 8.50 256.10 2,176.85
both
3 Supply of 18 guage iron plate arrows, border etc will be
sides lettering & Painting and Kg 14.11 105.96 1,495.10
painted with ready mixed synthetic enamled paint of superior
4 Lettering/painting
quality section of framed by superior
posts and paint
steel tube will be painted Sqm 4.17 87.00 362.79
with primer ofand
5 Fixing Boardtwoincoats
CC 1:2:4of epoxy
as perpaint
IRC:67as per drawing & Cum 0.54 4,589.65 2,478.41
information on the road shall also be mentioned as per
6 Labour
direction rate
of E/I for cutting/welding/primer
including all labour, material && carrige upto site
T&P etc. 0.00
LS
Add 3% cost of MS tube and angle iron towards the cost 0.00
of fabrication, drilling holes, nuts, bolts etc
c) Overheads @ 10 % on (a+b) 786.49
d) Contractor Profit @ 10 % on (a+b+c) 865.14
Rate for 1 cumsqm = a+b+c+d 9,516.58
Rate for 1 cum = (a+b+c+d)/1 9,516.58
Reduction factor=1.125/1.21 8,848.06
Add Royalty per cum for Sand cum 0.26 150 38.88
Add Royalty per cum for 20mm &10mm Stone grit cum 0.17 160 27.65
Add Royalty per cum for 40mm Stone ballast cum 0.26 110 28.51
Add 1% Labour cess 89.43
Say (Rs.) 9,032.53
14.2 1300 Providing and laying of boulder apron laid in wire crates with 4
mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x
100 mm mesh (woven diagonally) including 10 per cent extra
for laps and joints laid with stone boulders weighing not less
than 25 kg each as per drawing and technical specifications
Clause 1301

Unit = cum
Taking ouput = 3 m x 1.5 m x 1.25 m = 5.63 cum
a) Material
Stone boulder (25 kg minimum) cum 5.63 1,480.60 8,335.78
Stone spalls cum 1.13 400.00 452.00
GI wires 4 mm dia @ 32 kg/10 sqm kg 64.00 440.00 28,160.00
b) Labour
Mate day 0.18 250.00 45.00
Mazdoor (Skilled) day 1.50 250.00 375.00
Mazdoor (Unskilled) day 3.00 235.00 705.00
Add for labour for weaving the wire crates @ 2 per cent of 22.50
cost of GI wire
c) Overheads @ 10% on 3,809.53
d) Contractor Profit @ 10% on 4,190.48
Cost for 5.63 cum = a+b+c+d 46,095.29
Rate per cum = (a+b+c+d)/5.63 8,187.44
Add Royalty per cum for stone boulder & spalls cum 6.76 110 132.08
Add 1% Labour cess 83.20
Say (Rs.) 8,402.71
14.10 1300 Providing and laying Flat Stone apron for bed protection to
complete as per drawing and technical specifications Clause
1301
Unit = cum
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
a) Material
Stone boulder cum 1.00 1,530.60 1,530.60
Stone spalls cum 0.20 400.00 80.00
b) Labour
Mate day 0.05 250.00 12.50
Mason 1st Class day 0.25 380.00 95.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
Add: 1 per cent of cost of (a+b) for trimming and 19.53
preparation of bed
c) Overheads @ 10% on (a+b) 10% 197.26
d) Contractor’s profit @ 10% on (a+b+c) 10% 216.99
Rate per cum = a+b+c+d 2,386.88
Add Royalty per cum for stone boulder & spalls cum 1.2 110 132.00
Add 1% Labour cess 25.19
Say (Rs.) 2,544.07
12.9 600 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia PVC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7

Unit = Nos
Taking output = 30 Nos
a) Material
PVC pipe 100 mm dia including wastage @ 5 per cent. m 31.50 110.00 3,465.00
Average length of weep hole is taken as one metre for the
b) Labour
purpose of estimating
Mate day 0.03 250.00 7.50
Mason 1st Class day 0.50 380.00 190.00
Mazdoor (Unskilled) day 0.25 235.00 58.75
c) Overheads @ 10% on (a+b) 10% 372.13
d) Contractor’s profit @ 10% on (a+b+c) 10% 409.34
Cost for 30 Nos = (a+b+c+d) 4,502.71
Rate per No = (a+b+c+d)/30 150.09
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
Add 1% Labour cess 1.50
Say (Rs.) 151.59
12.11 1200 Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less than
600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted to
firm condition complete as per drawing and technical
specification Clause 1204.3.8

Unit = cum
Taking output = 10 cum
a) Material
Filter media as per specification cum 12.00 1,875.60 22,507.20
b) Labour
Mate day 0.40 250.00 100.00
Mazdoor (Unskilled) day 9.00 235.00 2,115.00
Mazdoor (Skilled) day 1.00 250.00 250.00
Bhisti day 0.50 260.00 130.00
c) Overheads @ 10% on (a+b) 10% 2,510.22
d) Contractor’s profit @ 10% on (a+b+c) 10% 2,761.24
Cost for 10 cum of filter media = a+b+c+d 30,373.66
Rate per cum = (a+b+c+d)/10 Say (Rs.) 3,037.37
Reduction factor=1.125/1.21 2,824.00
Add Royalty per cum for stone boulder & spalls cum 12.00 110 132.00
Add 1% Labour cess 29.56
Say (Rs.) 2,985.56
12.14 1200 Providing pressure relief pipes 100 mm dia in bottom slab
of box cell on a filter media base of 500 mm x 500 mm as
per drawing and technical specification Clause 1205.5.7

Unit = Nos
a) Material

PVC pipe 100 mm dia i/c wastage of 5 per cent 600 mm m 0.63 110.00 69.30
long upto the bottom of levelling course
Filter media base with stone aggregate 0.5 m x 0.5 m cum 0.25 1,875.60 468.90
area 1 m deep
b) Labour
Mate day 0.031 250.00 7.75
Mason 1st Class day 0.016 380.00 6.08
Mazdoor (Unskilled) day 0.80 235.00 188.00
c) Overheads @ 10% on (a+b) 10% 74.00
d) Contractor’s profit @ 10% on (a+b+c) 10% 81.40

Rate per No = (a+b+c+d) 895.44


Add Royalty per cum for stone boulder & spalls cum 0.25 110 2.75
Add 1% Labour cess 8.98
Say (Rs.) 907.17
9.30 1100 Laying Reinforced Cement Concrete Pipe NP3 on First Class
Bedding in Single Row
Laying reinforced cement concrete pipe for culverts on first
class bedding of granular material in single row including fixing
collar with cement motar 1:2 but excluding
excavation,protection works,back filling,concrete and
masonary works in head walls and parapets

Unit = metre
Taking output = 7.5 metre
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
1000 mm dia
a) Labour
Mate Day 0.090 250.00 22.50
Mason Day 0.250 380.00 95.00
Mazdoor Day 2.000 235.00 470.00
b) Material
Coarse Sand at site cum 0.040 1205.10 48.20
Cement at site tonne 0.030 5560.00 166.80
RCC pipe including collar at site mtr 7.500 4600.00 34500.00
c) Overheads @ 10% on (a+b) 3530.25
d) Contractor’s profit @ 10% on (a+b+c) 3883.28
Cost for 7.5 RM = a+b+c+d 42716.03
Rate per R/m 5695.47
Reduction factor=1.125/1.21 5295.38
Add Royalty per cum for coarse sand cum 0.04 150 0.80
Add 1% Labour cess 52.96
5349.14

Say (Rs.) 5295.38


4.1 401 Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method under foundation
Construction of granular sub-base by providing well
(i) For GradingIII Material
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 250.00 100.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 8.00 235.00 1,880.00
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.00 2,935.50 0.00
Three wheel 80-100 kN static roller @ 10 cum hour 30.00 564.30 0.00
per hour
Tractor with Rotavator 25 cum per hour hour 12.00 444.60 0.00
Water tanker 6 kl capacity hour 5.00 380.00 0.00
c) Material
Well graded granular sub-base material as per
Table 400.1
53 mm to 9.5 mm @ 50 per cent cum 180.00 1,865.60 335,808.00
9.5 mm to 2.36 mm @ 20 per cent cum 72.00 1,630.60 293,508.00
2.36 mm below @ 30 per cent cum 108.00 1,540.60 110,923.20
Water kl 30.00 50.00 5,400.00
d) Overheads @ 10% on 74,811.92
e) Contractor Profit @ 10% on 82,293.11
Rate for 300 cum = a+b+c+d+e 905,224.23
Rate for per cum = (a+b+c+d+e)/300 3,017.41
3,017.41
Add Royalty per cum for 53 mm to 9.5 mm,9.5 mm to 2.36 mm &cum 360.00 110.00 132.00
Labour cess 1% 31.49
Say (Rs.) 3180.91
11.5 III 600 & Sub-Analysis 1200
Cement mortar 1:5 (1 cement, 5 sand)
a) Material
Cement t 0.31 5,560.00 1,723.60
Sand cum 1.05 1,205.10 1,265.36
b) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 0.90 235.00 211.50
Bhisti day 0.08 260.00 20.80
Total material and labour = (a+b) 3,231.26
Reference to
Sr. MORD Rate Amount
Description Unit Quantity
No. Specification (Rs.) (Rs.)
s
(iii) In cement mortar (1:5)
Unit = cum
a) Material
Stone for CR masonry 1st sort cum 0.60 1,530.60 918.36
Spalls/blasted rubbles cum 0.50 1,530.60 765.30
Cement mortar cum 0.33 3,231.26 1,066.31
b) Labour
Mate day 0.14 110.00 15.40
Mason 1st Class day 1.30 380.00 494.00
Mazdoor (Unskilled) day 2.00 235.00 470.00
Bhisti day 0.08 260.00 20.80
c) Overheads @ 10% on 375.02
d) Contractor Profit @ 10% on 412.52
Rate per cum = a+b+c+d 4,537.71
Reduction factor=1.125/1.21 4,218.95
Add Royalty per cum for sand cum 0.35 150 51.98
Add Royalty per cum for stone cum 1.1 110 121.00
Add 1% Labour cess 43.92
Say (Rs.) 4,435.84
11.5 III 600 & Sub-Analysis 1200
Cement mortar 1:5 (1 cement, 5 sand)
a) Material
Cement t 0.31 5,560.00 1,723.60
Sand cum 1.05 1,205.10 1,265.36
b) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 0.90 235.00 211.50
Bhisti day 0.08 260.00 20.80
Total material and labour = (a+b) 3,231.26
(iii) In cement mortar (1:5)
Unit = cum
a) Material
Stone for CR masonry 1st sort cum 0.60 0.00 0.00
Spalls/blasted rubbles cum 0.50 0.00 0.00
Cement mortar cum 0.33 3,231.26 1,066.31
b) Labour
Mate day 0.14 110.00 15.40
Mason 1st Class day 1.30 380.00 494.00
Mazdoor (Unskilled) day 2.00 235.00 470.00
Bhisti day 0.08 260.00 20.80
c) Overheads @ 10% on 206.65
d) Contractor Profit @ 10% on 227.32
Rate per cum = a+b+c+d 2,500.48
Reduction factor=1.125/1.21 2,324.82
Add Royalty per cum for sand cum 0.35 150.00 51.98
Add Royalty per cum for stone cum 1.10 110.00 0.00
Add 1% Labour cess 23.77
Say (Rs.) 2,400.57

You might also like