This Summary for construction Cost for NRC

Amount
Sl. No. Particular's of work
(Rs. in lacs)
1 2 3
1 Building works 12842060.00
Add 5 % for internal Land profile
642103.00
correction
Add 4 % for Internal water Supply 513682.40
Add 5 % for external water Supply 642103.00

Add 12.5 % for Internal Electrification 1605257.50

Add 4 % for Power plug and wiring 513682.40

Add 1% for Central callbell system 128420.60


Total Construction cost 16887308.90
2 Add 1 % contingency 168873.09
Total(1+2) 17056181.99
3 Add 12 % GST 2046741.84
4 Add 1 % Labour cess 170561.82
5 Add 0.5% of construction cost for soil test 84436.54
Add 1.5% of construction cost structural
6 drawing, design, working drawings for layout, 253309.63
electrical and plumbing fittings.

7 ADD 18 % GST on 5 and 6


60794.31
Total(1+2+3+4+5+6+7) 19672026.13
Says 196.72 Lacs