Redesigning Widenig and Strengthening of Varansi Saktinagar Road SH-5A (Auri to Shaktinagar) from ch.
166.130 to 184.417 under Inter State connectivity in district Sonbhadra.
This road is situated between Auri mod to Shaktinar. There are various plants and
industries (Anpara power Plant, Renusagar Power Plant, Shaktinagar Power
Plant, Khadiya cole Mines, Kakri Pariyozana, Krishnshila, duddhichua coal mines
and units of lanco Power Plant) are placed in the alignment of road. Also this road
is connecting MP boder Sinrauli district. Due to above reasons traffic density is
very high at the stretch of this road.
2 SH No. SH 5A
3
Length 18.42 Kms.
4
Project Cost Rs. 121.00 Cr.
5
Client Public Works Department Uttar Pradesh
6
Independent Engineer Executive Engineer CD PWD Sonbhadra
7
Bond Date 30/SE-SON CIRCLE/18-19 DATE 08.08.2018
8
Contractor GAWAR ROHNA JHAJJAR HIGHWAY PVT. LTD.
9
Start date as per Bond 08.08.2020
Actual work start date 09.09.2019
10 Completion Date as per
bond 07.08.2019
11 Completion Date as per
bond 07.08.2019
12 Extended Completion
Date 31.03.2021
The problem face during the commissioning of the
project
Tree cutting is started by Van Nigam on date 20.03.2020 and pole shifting is
started by Electrical Department by date 21.07.2020.
At present 910 tress is cut downed from total 1787, 105 new pole is placed from
total 753 and 31 handpump is shifted from total 49.
The progress of construction is affected also COVID-19 and lockdown.
Removal of encroachment is not completed due to occupancy of district
administration in management from the protection of COVID-19.
Earthwork, GSB and WMM work is under progress as per the availability of land
at Site.
Provision in road
4 DBM 50 mm thickness
5 BC 40 mm thickness
Progress
Sr.No. Description Length (m) Completed Length (m) Physical Progress Comment
Earth Work 15 RHS - -
1 18.42
2.5 LHS - -
GSB 13 RHS - -
2 18.42
2.5 LHS - -
WMM Ist Layer 8 RHS - -
3 18.42
2 LHS - -
WMM Iind Layer
4 18.42 - - - -
DBM
5 18.42 - - - -
BC
6 18.42 - - - -
Widening of RRC
Culverts
Widening of abudment and piers is
9 14 14 - -
completed and slab is pending.
11 Hume pipe 26 - - - -
12 Monor Bridge - - - - -
Progress
Land Purchase Ha
1 - - -
Tree Cutting NO
2 1787 910 -
Electrical Pole Shifting NO The fixing of new pole is stopped
by electrical department due to
encroachment
3 753 105
Handpump Shifting NO
4 49 31 -
Provision in road
Sr No Discription Provision
GSB
1
300 mm thickness
WMM 1st layer
2
140 mm thickness
WMM 2nd layer (Emulsion Treated Aggregate)
3
130 mm thickness
DBM
4
50 mm thickness
BC
5
40 mm thickness