PRESENTATION

Redesigning Widenig and Strengthening of Varansi Saktinagar Road SH-5A (Auri to Shaktinagar) from ch.
166.130 to 184.417 under Inter State connectivity in district Sonbhadra.

( Er Anil Mishra) ( Er Y K Sharma)


( Er Udai Narayan)
Superintending Engineer Chief Engineer
Executive Engineer
Mirzapur Circle Mirzapur Zone
CD PWD Sonbhadra
PWD Mirzapur PWD Mirzapur
Redesigning Widenig and Strengthening of Varansi Saktinagar Road SH-5A (Auri to Shaktinagar) from ch.
166.130 to 184.417 under Inter State connectivity in district Sonbhadra.

UTTAR PRADESH PUBLIC WORKS DEPARTMENT


CONTRACTOR GAWAR
ROHNA JHAJJAR
HIGHWAY PVT. LTD.
PROJECT KEY MAP
PROJECT KEY MAP
PROJECT BRIEF

This road is situated between Auri mod to Shaktinar. There are various plants and
industries (Anpara power Plant, Renusagar Power Plant, Shaktinagar Power
Plant, Khadiya cole Mines, Kakri Pariyozana, Krishnshila, duddhichua coal mines
and units of lanco Power Plant) are placed in the alignment of road. Also this road
is connecting MP boder Sinrauli district. Due to above reasons traffic density is
very high at the stretch of this road.

Benifit of Widening and strengthening of this road


1 The people located nearby area shall be benefited from congestion of traffic.
2 This will be helpful for the patrolling of police force as it naxel affected area.
3 This district border is connected with the border of four districts MP,
Chattisgarh, Jharkhand and Bihar. So it will also beneficial to transportation
from these district.
Redesigning Widenig and Strengthening of Varansi Saktinagar Road SH-5A (Auri to
1 Scope of Project Shaktinagar) from ch. 166.130 to 184.417 under Inter State connectivity in district
Sonbhadra.

2 SH No. SH 5A
3
Length 18.42 Kms.
4
Project Cost Rs. 121.00 Cr.
5
Client Public Works Department Uttar Pradesh
6
Independent Engineer Executive Engineer CD PWD Sonbhadra
7
Bond Date 30/SE-SON CIRCLE/18-19 DATE 08.08.2018
8
Contractor GAWAR ROHNA JHAJJAR HIGHWAY PVT. LTD.
9
Start date as per Bond 08.08.2020
 
Actual work start date 09.09.2019
10 Completion Date as per
bond 07.08.2019
11 Completion Date as per
bond 07.08.2019
12 Extended Completion
Date 31.03.2021
The problem face during the commissioning of the
project

 Auri Shaktinagar Road is sanctiond by UP Government order no


33/2018/936/23-12-18-549/2017 dated 07.05.2018.
 This road is sanction under Central Road Fund Scheme and utility shifting
was not included in the original sanctioned estimate.
 Approximate all the length of the road is affected by forest land. The principal
approval for transfer of forest land is sanctioned on date 09.09.2019.
 The works under utility shifting ( Forest land transfer, Tree cutting, Electrical
Pole shifting and Hand pump shifting)is sanction by UP Government order no
681/23-11-2019-1/231/2019 dated 12.12.2019 of Rs 6.50 crore.
 Then the amount is paid to Electrical Department, Forest Department,Van
Nigam and Jal Nigam according to their approved estimate.
The problem face during the commissioning of the
project

 Tree cutting is started by Van Nigam on date 20.03.2020 and pole shifting is
started by Electrical Department by date 21.07.2020.
 At present 910 tress is cut downed from total 1787, 105 new pole is placed from
total 753 and 31 handpump is shifted from total 49.
 The progress of construction is affected also COVID-19 and lockdown.
Removal of encroachment is not completed due to occupancy of district
administration in management from the protection of COVID-19.
 Earthwork, GSB and WMM work is under progress as per the availability of land
at Site.
Provision in road

Sr No. GSB 300 mm thickness

2 WMM 1st layer 140 mm thickness

3 WMM 2nd layer (Emulsion Treated Aggregate) 130 mm thickness

4 DBM 50 mm thickness

5 BC 40 mm thickness
Progress

Sr.No. Description Length (m) Completed Length (m) Physical Progress Comment
Earth Work 15 RHS - -
1 18.42
2.5 LHS - -
GSB 13 RHS - -
2 18.42
2.5 LHS - -
WMM Ist Layer 8 RHS - -
3 18.42
2 LHS - -
WMM Iind Layer
4 18.42 - - - -
DBM
5 18.42 - - - -
BC
6 18.42 - - - -
Widening of RRC
Culverts
Widening of abudment and piers is
9 14 14 - -
completed and slab is pending.

New RCC Culverts


10 18 - - - -

11 Hume pipe 26 - - - -
12 Monor Bridge - - - - -
Progress

Pre Construction Work


Sr.No. Description Unit Target Progress Comment

Land Purchase Ha
1 - - -
Tree Cutting NO
2 1787 910 -
Electrical Pole Shifting NO The fixing of new pole is stopped
by electrical department due to
encroachment
3 753 105

Handpump Shifting NO
4 49 31 -
Provision in road

Sr No Discription Provision

GSB
1
300 mm thickness
WMM 1st layer
2
140 mm thickness
WMM 2nd layer (Emulsion Treated Aggregate)
3
130 mm thickness
DBM
4
50 mm thickness
BC
5
40 mm thickness
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
THANK YOU