EXCAVATION
A excavate trench 225x450x600 but not exceeding 1.0m depth CM 18,004 205 3,690,738
LEACHETS PIPING
TRENCH EXCAVATION
A Excavate trapezoidal pits to a depth not exceeding
4.8m CM 2,458,096 205 503,909,680.00
C
Excavate in bulk, from stripped ground, to reduce levels not
exceeding 0.6m deep and cart away excavated material CM 1200 210 252,000.00
F
Provide and spread 50mmm approved sand blinding to the
surface and compact to receive heavy duty interlocking
precast concrete paving blocks SM 2100 130 273,000.00
G
Provide and lay heavy duty 80mm interlocking precast
concrete paving blocks on road and parking
areas(min.strength 49 N/mm) SM 2100 1,345 2,824,500.00
H
Excavate trench for 250 x 125mm precast concrete half
battered kerbs and accompanying 300 x 325mm bed and
haunch CM 2000 205 410,000.00
A
Excavate for 450x225mm external dimension,precast concrete
I.B.D,trim sides to slope and cart away.Depth not exceeding
1.2m;average 900mm CM 2000 188 376,000.00
B
Provide, lay and compact 150mm thick well compacted Murram
bedding to IBD. CM 45 1500 67,500.00
GAS VENTING
A Provide 150mm PVC pipes to vent out LM 100,000 800 80,000,000.00
harzadous gas at every 20m.
GEOTEXTILE MATERIAL
A Provide a PC sum for geotextile membrane for drainage SUM 20,000,000.00
SUMMARY PAGE
TOTAL FROM PAGE 1 758,633,590.50
TOTAL FROM PAGE 2 110,468,250.00
SUBTOTAL 869,101,840.50
ADD 5% CONTIGENCIES 43,455,092.03
ESTIMATED VALUE OF LANDFILL 912,556,932.50