Professional Documents
Culture Documents
Executed by
HDD by Available Work
S.No Activity Description UOM Scope Revised Scope Previous Since Previous
Others Front contractor
A B C D E F=D-E G H I
1 ROU Boundary Marking* Mtr 96,826.00 6,220.00 90,606.00 90,606.00 21,217.00 69,389.00
2 ROU front availability for Cleaning and Grading Mtr 96,826.00 6,220.00 90,606.00 90,606.00 19,464.00 71,142.00
9 Trenching including HDD and other crossing Mtr 96,826.00 6,220.00 90,606.00 90,606.00 11,932.00 77,575.00
10 Holiday Testing & Lowering including HDD and Mtr 96,826.00 6,220.00 90,606.00 90,606.00 11,932.00 77,301.82
other crossing
11 Cased Crossing Nos 6 0 6 6 6
12 HDPE Duct Laying Mtr 96,826.00 6,220.00 90,606.00 90,606.00 10,344.29 76,499.00
14 Backfilling including HDD and other crossing Mtr 96,826.00 6,220.00 90,606.00 90,606.00 9,813.00 76,457.00
21 HDD Crossing 22 10 12 9 1 11
A Pond Crossing (Ch-5.5) Mtr 511 511 511.00
B Periyar River (Ch-10.7) Mtr 624 624 624.00
C Uzhattu Puzha Crossing (Ch-11.84) Mtr 317 317 317
D Creek Crossing (Ch-13.123) Mtr 325 325 325
E Unlined Canal Crossing (Ch-41) Mtr 608 608 608.00
F Crossing (Ch-45) Mtr 343 343 343
G Crossing (Ch-14.5) Mtr 412 412 412
H Unlined Canal Crossing (Ch-59.1) Mtr 282 282 282
I Canal Crossing (Ch-61) Mtr 230 230 230
J Canal Crossing (Ch-71.6) Mtr 497 497 497
K Nala Crossing (Ch-10) Mtr 96 96 96.00
Today' s HIGHLIGHTS
Lighting Fixtures and Ceiling Fan Installation under Progress at IP-1
Executed by
HDD by Available Work
S.No Activity Description UOM Scope Revised Scope Previous Since Previous
Others Front contractor
Miscellaneous Progress
PMC comments
J K=(I+J) L=(H+K)
- 69,389.00 90,606.00
- 71,142.00 90,606.00 -
- 5,705.31 7,466
- 71,142.00 90,606.00 -
- 5,733.00 7,695
- 70,195.00 90,652.00
- 500.00 535.00
12 71,994.00 90,348.00
1 2,863 3,799
Cumulative for Overall
Today's Remarks
ILFS Cumulative
12 37,006.00 49,174.00
- 3,257 3,846
- 34,816.45 41,002.45
- 136 147
- - -
- 6,110 7,625
- 6,110 7,625
- 5,531 7,046
- 397 397
- 203 203
- - -
- 424 424
- 163 163
- 6,118 7,633
6,112 7,627
- 77,575.00 89,507.00
- 77,301.82 89,233.82
- 6 6
- 40 50
Cumulative for Overall
Today's Remarks
ILFS Cumulative
- 76,499.00 86,843.29
- 50,066.00 50,066.00
- 76,457.00 86,270.00
- 38,874.00 38,874.00
- 38,874.00 38,874.00
- 220.00 220.00
- 84,776.00 84,776.00
- 70 70
- 37,363.74 37,363.74
0 11 12
- 511.00 511.00 Completed
- 624.00 624.00 Completed
317 317 Completed
325 325 Completed
608.00 608.00 Completed
343 343 Completed
412 412 Completed
282 282 Completed
230 230 Completed
497 497 Completed
- 96.00 96.00 Completed
Cumulative for Overall
Today's Remarks
ILFS Cumulative
Gr. Total
S.No Activity Description UOM Since
Scope Today's Cumu.
Previous
II STATION PIPING WORK
1 Fit up ID 8,893 7,939.55 - 7,939.55
2 Welding ID 8,893 7,936.75 - 7,936.75
3 Erection IM 10,965.00 9,507.80 - 9,507.80
4 NDT ID 8,893.00 7,935.55 - 7,935.55
5 Equipment Erection MT 290.00 290.00 - 290.00
6 Hydrotesting Loops NOS 14.00 1.00 - 1.00
DT SV-01
Since Since
Scope Today's Cumu. Scope Today's Cumu. Remarks
Previous Previous
otal DT SV-01
Since Since
Cumu. Scope Today's Cumu. Scope Today's
Previous Previous
81.00 - -
10,846.17 - 1563 1563
-
158.00 - -
4,874.00 - 1,500.00 1,471.00 -
271.62 - 27.02 27.40 -
884.30 - 122.90 117.53
299.03 - 60.00 57.79 -
965.33 - 149.95 57.64 -
6,302.98 - 1,781.32 447.77 -
- - 1,781.32 -
287.00 - 73.00 28.00 -
- - 190.00
- - 900.00
- - 1.00
-
-
1,512.75 266.00 266.00 -
234.34 32.57 32.57 -
475.04 71.11 71.11 -
592.58 89.75 89.75 -
59.39 4.00 4.00 -
- 23.00
- 1.50
-
512.61 53.39 53.39 -
5,151.14 770.27 770.27 -
1,121.00 - 192.00 205.00 -
834.26 170.00 170.00 -
182.05 100.00
- 36.00
- 5.00
- 8.00
- -
67.03 70.00 30.00 -
700.00 577.98 400.00 -
- 320.00
- 1.00
- -
- -
-
-
432.55 - 63.00 63.00 -
26.79 4.68 4.68 -
73.35 14.80 14.80 -
65.75 12.61 12.61 -
- 0.90
-
118.31 20.13 20.13 -
1,136.71 176.93 176.93 -
130.00 26.00 26.00 -
160.78 82.00
- 3.00
- 5.00
16.00 26.00
- 184.00
- 218.00
-
- - 1.00
- - 1.00
- 1.00
- 2.00
2.00 1.00
1.00 1.00
- 1.00
-
21.00 90.00
4.30 10.60
8.00 31.00
-
15.00 - 50.00
125.00 23.59 30.00 - 30.00 25.00
143.45 83.97 48.00 - 48.00 37.50
- 47.00
-
- - 1.00
- - 1.00
-
-
49.50 - 168.00
146.37 10.00 10.00 10.00 12.00
308.91 250.00 35.97 - 35.97 20.00
- 1.00
- - 1.00
- - 36.00
- - 4.00
- - 1.00
KOCHI KOOTANAD BANGALORE MANGAL
PHASE -II - (SECTION
CHAINAGE (0.000 KM to 90
SV-01 SV-02
Since
Cumu. Remarks Scope Today's Cumu. Remarks Scope
Previous
78
1,563.00 Comp. 1962
- -
1,471.00 758.94 758.00 - 758.00 777.96
27.40 50.03 50.03 50.03 27.53
117.53 133.00 131.30 - 131.30 107.21
57.79 30.00 27.98 - 27.98 25.42
57.64 104.00 62.69 - 62.69 128.51
447.77 1,158.20 771.78 - 771.78 1,775.22
- 1,158.20 1,775.22
28.00 72.00 65.00 - 65.00 75.00
170.00 215.00
900.00 900.00
1.00 1.00
1.00 - 1.00
58.00 - 42.00
29.00 - 21.00
43.50 - 31.50
50.40 - 47.00
1.00 - 1.00
1.00 - 1.00
168.00 - 168.00
12.00 - 12.00
20.00 3.06 - 3.06 20.00
1.00 1.00
1.00 1.00
36.00 36.00
4.00 4.00
1.00 1.00
ANGALORE MANGALORE PIPELINE PROJECT
PHASE -II - (SECTION-I)
AGE (0.000 KM to 90.615 KM)
SV-03 SV-04
Since Since
Today's Cumu. Remarks Scope
Previous Previous
78 78 Comp. 20 0
383 - 383 4452.8 3013.24
158.00 158.00
497.00 - 497.00 669.89 660.00
23.79 - 23.79 50.00 49.70
73.00 - 73.00 187.34 140.00
25.56 - 25.56 25.42 10.30
53.17 - 53.17 250.00 239.87
1,326.32 - 1,326.32 1,532.38 318.58
- - - 1,532.38 -
43.00 - 43.00 65.00 -
185.00 -
900.00 -
1.00 -
1.00 -
1.00 -
1.00 -
2.00 -
1.00 1.00 1.00 -
1.00 -
1.00 -
95.00 -
11.40 -
32.30 -
48.00 -
24.00 -
36.00 -
77.00 -
1.00 -
1.00 -
168.00 -
12.00 -
20.00 -
1.00 -
1.00 -
36.00 -
4.00 -
1.00 -
SV-04 SV-05
Since
Today's Cumu. Remarks Scope Today's Cumu.
Previous
- 3 3 3.00
3,013.24 2034.5 43.23 - 43.23
- 158.00 -
- 660.00 442.65 442.00 - 442.00
- 49.70 50.00 50.00 - 50.00
- 140.00 127.99 127.44 - 127.44
- 10.30 65.00 64.82 - 64.82
- 239.87 230.00 220.62 - 220.62
15.00 333.58 1,690.04 1,571.76 - 1,571.76
- 1,690.04 - -
- 74.00 63.00 - 63.00
- 218.00 - -
- 900.00 - - -
- 1.00 - -
- 1.00 - -
- 1.00 - -
- 1.00 - -
- 2.00 - -
- 1.00 - -
- 1.00 - -
- 1.00 - -
- 90.00 - -
- 10.80 - -
- 36.00 - -
- 48.00 - -
- 24.00 - -
- 36.00 0.45 - 0.45
- 47.00 - -
- 1.00 - -
- 1.00 - -
- 1.00 - -
REPORT NO
REPORT DATE
PROGRESS DATE
WEATHER
IP
2 0 - -
9550.7 5,843.70 - 5,843.70
-
1,046.00 1,046.00 - 1,046.00 Comp.
70.00 70.70 - 70.70 Comp.
327.36 295.03 - 295.03
120.00 112.58 - 112.58
385.12 331.35 - 331.35
3,686.00 1,851.77 - 1,851.77
3,686.00 - - -
180.00 88.00 - 88.00
500.00 - -
1,150.00 - -
1.00 - -
1.00 - -
1.00 - -
1.00 - -
2.00 - -
1.00 - -
1.00 - -
1.00 - -
330.00 - -
39.60 - -
145.00 - -
2.00 - -
2.00 - -
6.00 - -
691
24-Oct-2018
24-Oct-2018
Sunny
Remarks
KOCHI KOOTANAD BANGALORE MANGALORE P
PHASE -II - (SECTION-I)
CHAINAGE (0.000 KM to 90.615 K
Total Requirement as
SL.No. Category per contract
2 Section Incharge 1
3 Planning Engineer 2
4 QA/ QC Engineer 1
5 Safety Officer 1
6 Surveyor 2
7 Welding/NDT Engineer 4
9 Foreman/Supervisor 30
14 Fitter 20
15 Grinder 50
16 Machine operator 40
19 Rigger 50
20 Drivers 40
21 Pipe Bending 2
25 Hydrotesting crew 3
28 HDD Crew 2
1 1
1 1
2 3
1 1
1 1
2 1
4 2
15 10
30 4
4 1
2 2
2 2
45 4
20 2
50 4
40 10
4 0
22 1
50 9
40 5
2 0
As Required 0
2 0
8 3
3 0
4 0
6 0
2 0
2 0
1 1
As Required 23
200 28
3 4
As Required 11
569 134
KOCHI KOOTANAD BANGALORE MANGALORE PIPELINE PROJECT
PHASE -II - (SECTION-I)
CHAINAGE (0.000 KM to 90.615 KM)
Requirement as
Total Requirement as per MCEDS End of Total Deployed at
SL.No. Category per contract Site Remarks
18th Month
10 HORIZONTAL AUGER BORING MACHINE WITH ROCK BRAKING TOOL 1 1 1 Additional 2 nos Jack pushing Boring equipment
available at site
11 PIPE CLAMP (PNUMATIC/HYDRAULIC)-INTERNAL 2 2 2
12 PIPE CLAMP- EXTERNAL 2 2 14
13 HDD RIG WITH ALL EQUIPMENT & ACCESSIORIES 1 1 0 ALL HDDs are completed
4 Stringing
5 Bending Yard
Ch:3,Ch:10,Ch:14,Ch:20,Ch:47,Ch:52,Ch:65,Ch:
6 Main Line Welding 67
8 Tie-in
Ch:3,Ch:10,Ch:14,Ch:20,Ch:47,Ch:52,Ch:65,Ch:
9 NDT 67
11 Trenching Ch-3,Ch-11,Ch-67,Ch-65
12 Lowering Ch-3,Ch-67,Ch-65
14 Boring
15 HDD Ch-45
16 Cased/Un-cased Crossing
18 Restoration Ch-69,Ch:69
20 HSE Overall
7034661852,
Mr. Gokul, Surinder, Vikram Singh 9072653620
& Tinku Tom 9846603413
9072653614
Heerabhai 9072653613
7034661852,
Mr. Gokul, Surinder,Vikram Singh & 8330014822,
Tinku Tom 9846603413
9072653603,
OP Chowbey/Mr. Pushparaj 7871480520
9072653606
Ravi Jha / Suresh Babu 9072653621
9072653621 /
Mr. Ravi Jha / Surinder Singh 7510441104
Remarks