Professional Documents
Culture Documents
Municipal of Bangued
MUNICIPAL/PROVINCIAL ENGINEERING OFFICE
PROGRAM OF WORK
Project Title : Road Opening of Bangued Road Width incl. shouldering (m) 9.1
Road Width (m) 6.1
Location : Bangued Abra Bridge Width (m)
Appropriation : Type of Bridge Sub-structure:
Source of Fund : Type of Superstructure:
Implementation Procedure: Number of Spans / bays :
Classification : No. of Piers No. of Abuts: ____
Limits Starting Date :
Net Length : 1000.00 meters No. of Calendar Days to Complete:
MINIMUM EQUIPMENT REQUIRED
Description No. Description No. Description No.
COMPLETION DATE
M-Y
REL. DAY
ITEM ACTIVITY/WORK DESCRIPTION UNIT QUANTITY UNIT COST COST WEIGHT
% WK. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
D.E. 5 12 19 26 33 40 47 54 61 68 75 82 89 96 103 110 117 124 131 138 145 152 159 166
Planned
1 0 0 - - #DIV/0! - #N/A
Actual
Planned 100%
2 0.00 0.00 - - #DIV/0! - #N/A
Actual
Planned
3 0.00 0.00 - - #DIV/0! - #N/A
Actual
Planned
4 0 0 - - #DIV/0! - #N/A
Actual
Planned
5 0 0 - - #DIV/0! - #N/A
Actual
Planned
6 0 0 - - #DIV/0! - #N/A
Actual
Planned
7 0 0 - - #DIV/0! - #N/A
Actual
Planned
8 0 0 - - #DIV/0! - #N/A
Actual
Planned
9 0 0 - - #DIV/0! - #N/A 80%
Actual
Planned
10 0 0 - - #DIV/0! - #N/A
Actual
Planned
11 0 0 - - #DIV/0! - #N/A
Actual
PART C EARTHWORKS
Planned
12 100(1) Clearing & Grubbing (with Stripping) sq.m. 9,100.00 14.63 133,159.81 #N/A
Actual
Planned
Individual Removal of Trees (small a, 150-300mm
13 100(2)a ea. 18.00 706.84 12,723.09 #N/A
φ) Actual
Planned
Individual Removal of Trees (small a, 301-500mm
14 100(2)b ea. 3.00 1,973.52 5,920.55 #N/A
φ) Actual
Planned
15 102(2)a Roadway Excavation (Surplus Common) cu.m 1,793.20 129.52 232,260.82 #N/A
Actual
Planned
16 103(1)a Structure Excavation (Common Soil) cu.m 251.03 16.12 4,046.89 #N/A
Actual 60%
Planned
#N/A #N/A #N/A #N/A #N/A #N/A #N/A
Actual
Planned
17 103(6) Pipe Culvert and Drain Excavation cu.m 16.89 239.60 4,046.89 #N/A
Actual
Planned
18 104(1)a Embankment (from Borrow) cu.m 2,999.28 612.74 1,837,792.98 #N/A
Actual
Planned
19 0 0 - - #DIV/0! - #N/A
Actual
Planned
20 0 0 - - #DIV/0! - #N/A
Actual
Planned
21 0 0 - - #DIV/0! - #N/A
Actual
Planned
PCC Pavement (Plain) - Conventional Method,
22 311(1)a.3 sq.m. 6,100.00 1,007.44 6,145,353.88 #N/A
230mm thk. Actual
40%
Planned
23 0 0 - - #DIV/0! - #N/A
Actual
Planned
24 0 0 - - #DIV/0! - #N/A
Actual
Planned
25 0 0 - - #DIV/0! - #N/A
Actual
Planned
26 0 0 - - #DIV/0! - #N/A
Actual
Planned
27 404 Reinforcing Steel Bar, Grade 40 (Minor Structures) - - #DIV/0! - #N/A
Actual
Planned
28 405 Structural Concrete Class A (Minor Structures) - - #DIV/0! - #N/A
Actual
Planned
29 500(1)c Pipe Culverts, 910mm dia (36" Ø) - - #DIV/0! - #N/A
Actual
Planned
30 505(5) Grouted Riprap (Class A) - - #DIV/0! - #N/A 20%
Actual
Planned
31 506 Stone Masonry cu.m 460.80 3,411.95 1,572,227.77 #N/A
Actual
Planned
Metal Guardrails (Metal Beam) including Concrete
32 603(3)a l.m. 240.00 2,788.08 669,138.45 #N/A
Post Actual
Planned
33 603(3)b Metal Beam End Piece ea. 4.00 1,667.64 6,670.56 #N/A
Actual
Planned
Reflectorized Thermoplastic Pavement Markings
34 612(1) - - #DIV/0! - #N/A
(White) Actual
Planned
Reflectorized Thermoplastic Pavement Markings
35 612(2) - - #DIV/0! - #N/A
(Yellow) Actual
Planned
36 620b Chevron Signs (600mmx800mm) ea. 8.00 18,920.12 151,360.98 #N/A
Actual
Weekly 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Actual
Actual Progress Cumulative 0 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Weekly 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Slippage
Cumulative 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Project
Description
Location
ESTIMATED MARK-UPS IN PERCENT TOTAL MARK - UP
ITEM NO. DESCRIPTION QTY UNIT
DIRECT COST OCM PROFIT %
(8)
(1) (2) (3) (4) (5) (6) (7)
(6)+(7)
PART A FACILITIES FOR THE ENGINEER
1 0%
2 0%
3 0%
4 0%
5 0%
6 0%
6.1 TOTAL OF PART A -
PART B OTHER GENERAL REQUIREMENTS
7 0%
8 0%
9 0%
10 0%
11 0%
11.1 TOTAL OF PART B -
PART C EARTHWORKS
12 100(1) Clearing & Grubbing (with Stripping) 9100.00 sq.m. 126,818.87 0%
13 100(2)a Individual Removal of Trees (small a, 150-300mm φ) 18.00 ea. 12,117.23 0%
14 100(2)b Individual Removal of Trees (small a, 301-500mm φ) 3.00 ea. 5,638.62 0%
15 102(2)a Roadway Excavation (Surplus Common) 1793.20 cu.m 221,200.78 0%
16 103(1)a Structure Excavation (Common Soil) 251.03 cu.m 3,854.18 0%
17 103(6) Pipe Culvert and Drain Excavation 16.89 cu.m 3,854.18 0%
18 104(1)a Embankment (from Borrow) 2999.28 cu.m 1,750,279.03 0%
105(1) Subgrade Preperation 9100.00 sq.m. 126,742.37 0%
16.1 TOTAL OF PART C 2,123,762.90
PART D SUBBASE AND BASE COURSE
17 200 Aggregate Subbase Course 1910.00 cu.m 1,433,581.82 0%
18 201 Aggregate Base Course 915.00 cu.m 760,425.76 0%
19 0%
20 0%
21 0%
21.1 TOTAL OF PART D 2,194,007.58
PART E SURFACE COURSES
22 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk. 6100.00 sq.m. 5,852,717.98 0%
23 0%
24 0%
25 0%
26 0%
26.1 TOTAL OF PART E 5,852,717.98
PART G DRAINAGE AND SLOPE PROTECTION
27 404 Reinforcing Steel Bar, Grade 40 (Minor Structures) 0%
28 405 Structural Concrete Class A (Minor Structures) 0%
29 500(1)c Pipe Culverts, 910mm dia (36" Ø) 0%
30 505(5) Grouted Riprap (Class A) 0%
31 506 Stone Masonry 460.80 cu.m 1,497,359.78 0%
31.1 TOTAL OF PART G 1,497,359.78
PART H MISCELLANEOUS STRUCTURE
32 603(3)a Metal Guardrails (Metal Beam) including Concrete Post 240.00 l.m. 637,274.71 0%
33 603(3)b Metal Beam End Piece 4.00 ea. 6,352.91 0%
34 612(1) Reflectorized Thermoplastic Pavement Markings (White) 0%
35 612(2) Reflectorized Thermoplastic Pavement Markings (Yellow) 0%
36 620b Chevron Signs (600mmx800mm) 8.00 ea. 144,153.31 0%
36.1 TOTAL OF PART H 787,780.93
TOTAL 12,455,629.17
RACT
Station:
Length: meters
Duration:
TOTAL MARK - UP TOTAL INDIRECT
VAT TOTAL COST UNIT COST
VALUE COST
(9) (10) (11) (12) (13)
(5)x(8) 5%[(5)+(9)] (9)+(10) (5)+(11) (12)/(3)
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- - - - #DIV/0!
- 74,867.99 74,867.99 1,572,227.77 3,411.95
- 74,867.99 74,867.99 1,572,227.77 #DIV/0!
2.88
3.16 - 60.40 72.48 (72.48)
2.93 - 60.90 73.08 (145.56)
5.52 - 84.50 101.40 (246.96)
7.89 78.90 55.20 66.24 (234.30)
8.50 163.90 - - (70.40)
10.13 186.30 - - 115.90
9.28 194.10 - - 310.00
5.20 123.08 - - 433.08
3.28 12.72 - - 445.80
3.60 68.80 - - 514.60
3.88 74.80 - - 589.40
4.58 38.80 45.80 54.96 573.24
8.79 - 133.70 160.44 412.80
8.00 - 167.90 201.48 211.32
7.52 - 155.20 186.24 25.08
3.71 - 112.30 134.76 (109.68)
3.86 - 75.70 90.84 (200.52)
4.54 - 84.00 100.80 (301.32)
6.06 - 106.00 127.20 (428.52)
6.13 - 121.90 146.28 (574.80)
9.25 - 153.80 184.56 (759.36)
9.71 - 189.60 227.52 (986.88)
7.10 71.00 97.10 116.52 (1,032.40)
8.07 151.70 - - (880.70)
5.14 80.70 51.40 61.68 (861.68)
7.07 - 122.10 146.52 (1,008.20)
13.64 - 207.10 248.52 (1,256.72)
11.69 - 253.30 303.96 (1,560.68)
10.92 - 226.10 271.32 (1,832.00)
14.18 - 251.00 301.20 (2,133.20)
11.82 - 260.00 312.00 (2,445.20)
14.67 - 264.90 317.88 (2,763.08)
10.20 - 248.70 298.44 (3,061.52)
4.52 - 147.20 176.64 (3,238.16)
4.64 - 91.60 109.92 (3,348.08)
5.22 - 98.60 118.32 (3,466.40)
6.00 - 112.20 134.64 (3,601.04)
5.23 - 112.30 134.76 (3,735.80)
7.46 - 126.90 152.28 (3,888.08)
5.20 - 126.60 151.92 (4,040.00)
6.97 - 121.70 146.04 (4,186.04)
5.35 - 123.20 147.84 (4,333.88)
5.56 - 109.10 130.92 (4,464.80)
5.55 - 111.10 133.32 (4,598.12)
6.79 - 123.40 148.08 (4,746.20)
6.37 63.70 67.90 81.48 (4,763.98)
5.52 118.90 - - (4,645.08)
4.71 102.30 - - (4,542.78)
3.86 85.70 - - (4,457.08)
4.86 87.20 - - (4,369.88)
4.20 90.60 - - (4,279.28)
Note:
Assumed hauling distance is 3km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the
time of dump truck will be adjusted accordingly
based on the hauling cycle time analysis.
a. Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 400.00 500.00
Err:522 232.07
Name and Capacity No. Units No. of Hours Hourly Rate Amount
B. Equipment
Item No./Description : 311(1)a.3 PCC Pavement (Plain) - Conventional Method, 230mm thk.
Unit of Measurement : . sq.m.
Output per hour : 70 sq.m.
Installation/Removal of Formworks
a. Skilled Laborer 4 1.00 79.70 318.80
b. Laborer 8 1.00 61.44 491.52
Note:
*Quantities for lumber, plywood and CWN are
dependent on the type pf minor structure.
The above-computed quantities are based on box
culvert.
Item No./Description : 603(3)a Metal Guardrails (Metal Beam) including Concrete Post
Unit of Measurement : l.m.
Output per hour : 4.20 l.m.