Professional Documents
Culture Documents
ONGC
Contractor : M/s. LTHE
Sub‐Contractor : M/s DOEPL
PROJECT : Balance work for Pipeline Replacement Project ‐ 4
A) Piping
3 Fit up Adiitional work Nos N/A N/A N/A N/A N/A NA N/A N/A
Welding (Field Joints) Inch Dia 83.5 29.00% 0 83.5 0 0.00% 29.00% 0.00%
4
Welding (Modification joints) Inch Dia 42 0.00% 0 42 0 0.00% 0.00% 0.00%
5 Welding of Additional work Inch Dia N/A N/A N/A N/A N/A NA N/A N/A
B) DEMOLITION
Activities performed
1 Towing from NLM10 platform and reached North Field outer Anchorage
2 Anchor Handling
1 According to ONGC Specification 2009F Rev.7 Clause No. 1.3 " Gamma rays can be used with permission from Company". LTHE yet to be submit the ONGC Approval for using Gamma rays at Barge Ocean303
According to BID Document , ONGC Specification No. 2005 Rev.No. 5.1 to be followed for Protective Coating. But the existing Blasting & Protective coating procedure No.PRP4‐DAS‐GN00‐QUA‐PRC‐0013 Rev.No.1 follows the ONGC Specification
2
No. 2005 Rev.No.4. LTHE yet to submit the updated approved Painting procedure.