You are on page 1of 1

CLIENT : M/s.

ONGC
Contractor : M/s. LTHE
Sub‐Contractor : M/s DOEPL
PROJECT : Balance work for Pipeline Replacement Project ‐ 4

CA : M/S. ABSIV (India) Pvt.Ltd. PRODUCTION DATE: 01.04.2018

TPI : M/S. DNV‐GL REPORTING DATE : 02.04.2018


Location : North Field Outer Anchorage ( N7 Platform)
Barge: Ocean303
Achieved Cumulative Balance Achieved % Cumulative
Sr. no Description UOM Scope Alloted % Balance % Remarks
Qty.Today Qty. Qty. Today %
Over all Progress ( A+B+C) 100.00% 0.00% 100.00% 0.00%

A) Piping

1 Erection of piping spools Nos 14 20.00% 0 14 0 0.00% 20.00% 0.00%

Fit up of (Field Joints) Nos 27 13.00% 0 27 0 0.00% 13.00% 0.00%


2
Fit up of (Modification joints) Nos 7 0.00% 0 7 0 0.00% 0.00% 0.00%

3 Fit up Adiitional work Nos N/A N/A N/A N/A N/A NA N/A N/A

Welding (Field Joints) Inch Dia 83.5 29.00% 0 83.5 0 0.00% 29.00% 0.00%
4
Welding (Modification joints) Inch Dia 42 0.00% 0 42 0 0.00% 0.00% 0.00%

5 Welding of Additional work Inch Dia N/A N/A N/A N/A N/A NA N/A N/A

6 Installation of Piping Supports Nos. 6 7.00% 0 6 0 0.00% 7.00% 0.00%

NDT of (Field Joints) Nos 27 12.00% 0 27 0 0.00% 12.00% 0.00%


7
NDT of (Modification Joints) Nos 7 0.00% 0 7 0 0.00% 0.00% 0.00%

8 Hydrotesting of Piping Loops Nos. 2 4.00% 0 2 0 0.00% 4.00% 0.00%

9 Hook up/Tie in points Nos. 2 4.00% 0 2 0 0.00% 4.00% 0.00%

10 Painting Touch-up work lot 1 1.00% 0 1 0 0.00% 1.00% 0.00%

11 Insulation lot N/A N/A N/A N/A N/A NA N/A N/A

TOTAL-A 90.00% 0.00% 90.00% 0.00%

B) DEMOLITION

1 NIL lot 0 0.00% 0 0 0 0.00% 0.00% 0.00%

TOTAL-B 0 0.00% 0.00% 0.00% 0.00%

C) ELECTRICAL & INSTRUMENTATION

1 Instrument Installation No 4 3.50% 0 4 0 0.00% 3.50% 0.00%

2 Impulse Tubing mtr 20 1.00% 0 20 0 0.00% 1.00% 0.00%

3 Cable Tray mtr 50 1.00% 0 50 0 0.00% 1.00% 0.00%

4 Cable laying mtr 300 1.50% 0 300 0 0.00% 1.50% 0.00%

5 Cable termination and glanding No 8 1.00% 0 8 0 0.00% 1.00% 0.00%

6 Calibration No 4 1.00% 0 4 0 0.00% 1.00% 0.00%

7 Loop checking No 4 1.00% 0 4 0 0.00% 1.00% 0.00%

TOTAL-C 10.00% 0 0 0.00% 10.00% 0.00%

Distribution and Contact List


ABSIV sekumaran@eagle.org, pramanathan@absconsulting.com, dbhujbal@absconsulting.com
ONGC pandey_ak5@ongc.co.in, khanra_Rajat@ongc.co.in, Thakur_Ashish@ongc.co.in
DNV‐GL birju.jaiswal@dnvgl.com, mani.choudhary@dnvgl.com, merlyn.menezes@dnvgl.com

Activities performed
1 Towing from NLM10 platform and reached North Field outer Anchorage

Planned activities(Next Day) :‐

1 Attend meeting with ONGC at North Process Platform

2 Anchor Handling

Area of Concern if any :

1 According to ONGC Specification 2009F Rev.7 Clause No. 1.3 " Gamma rays can be used with permission from Company". LTHE yet to be submit the ONGC Approval for using Gamma rays at Barge Ocean303
According to BID Document , ONGC Specification No. 2005 Rev.No. 5.1 to be followed for Protective Coating. But the existing Blasting & Protective coating procedure No.PRP4‐DAS‐GN00‐QUA‐PRC‐0013 Rev.No.1 follows the ONGC Specification
2
No. 2005 Rev.No.4. LTHE yet to submit the updated approved Painting procedure.

Bhabesh Porel Vipin James EL.Krishnan


DNV ‐Mech. ( ONGC‐TPI) DNV‐E&I (ONGC‐TPI) ABSIV‐Mech. (ONGC‐CA) ABSIV‐E & I (ONGC‐CA) (ONGC REP.)

You might also like