DAILY REPORT OF 03/10/2019 DAY N° /PLANED DAYS : 77/178 Global progress board of the Project Code : TMP-04

CMA's Project Manager: Sami HDAYA MARETAP's representative : Mejdi jerbi PLANNED ACTUAL VARIANCE Date d’émission:15-08-2017
Version : 01
CMA's Piping/Project Eng: Alaa edine SMAALI CMA's QHSE: Marwene METHENI 52,47% 54,05% 1,58%

SOW: REPALCEMENT OF DAMAGED PIPES AT EZZAOUIA FIELD_ZARZIS

Contractor: CMA engineering & Consulting

QHSE
Passed Today Total
HEALTH & SECURITY
Wasted time % Total working time (Hrs/Hrs) 0 0 0
First Aids 0 0 0
ENVIRONNEMENTAL PROBLEMS
Major environnemental Incident 0 0 0
Minor environnemental Incident 0 0 0

EZZ#9 related pipes grid

Progress Per activities (Till 03/10/2019)

ACTIVITY WEIGHT PLANIFIED ACTUAL VARIANCE


MOBILIZATION 0,56% 100,00% 100,00% 0,00%
KICK OF MEETING 0,00% 100,00% 100,00% 0,00%
CAMP INSTALLATION 1,74% 100,00% 100,00% 0,00%
EZZ#9 FLOW LINE REPLACEMENT 25,16% 100,00% 100,00% 0,00%
3'' HDPE LINE REPLACEMENT 18,76% 100,00% 99,50% -0,50%
EZZ#10 INJECTION LINE REPLACEMENT 5,23% 0,00% 0,00% 0,00%
EZZ#10 FLOW LINE REPLACEMENT 5,23% 0,00% 0,00% 0,00%
EZZ#1 RISERS REPLACEMENT 0,00% 100,00% 99,25% -0,75%
50-110B1-4-WS-IH 0,00% 100,00% 92,25% -7,75%
EZZ#2 FL risers 1,74% 100,00% 87,50% -12,50%
50-105B1-4-WS-IH 0,00% 100,00% 87,50% -12,50%
EZZ#17 FL risers 4,06% 0,00% 100,00% 100,00%
EZZ#18 FL risers + EXTRAS (FLUL + FL risers at EZZ#18 WH side) 4,06% 84,00% 44,00% -40,00%
EZZ#11 FL risers 1,50% 73,08% 36,54% -36,54%
50-117A1-6-PW + 50-117A1-4-PW (EXTRA TASK) PREFABRICATION 0,00% 100,00% 100,00% 0,00%
50-185A1-4-CR PREFABRICATION 0,00% 100,00% 0,00% -100,00%
50-214A1-6-PW PREFABRICATION 0,00% 100,00% 100,00% 0,00%
50-126A1-8-PW PREFABRICATION PREFABRICATION 0,00% 100,00% 100,00% 0,00%
50-125A1-3-CR-IH-ET PREFABRICATION 0,00% 100,00% 100,00% 0,00%
50-143A1-4-CR-IH-ET PREFABRICATION 0,00% 100,00% 100,00% 0,00%
50-183A1-6-PW PREFABRICATION 0,00% 100,00% 80,00% -20,00%
50-128A1-PW-IH-ET (EXTRA TASK) PREFABRICATION 0,00% 100,00% 100,00% 0,00%
50-137A1-4-CR (EXTRA TASK) PREFABRICATION 0,00% 100,00% 100,00% 0,00%
50-117A1-6-PW + 50-117A1-4-PW (EXTRA TASK) MOUNTING 6,39% 0,00% 0,00% 0,00%
50-185A1-4-CR MOUNTING 0,00% 0,00% 0,00% 0,00%
50-214A1-6-PW MOUNTING 0,58% 0,00% 0,00% 0,00%
50-126A1-8-PW MOUNTING 4,65% 0,00% 0,00% 0,00%
50-125A1-3-CR-IH-ET MOUNTING 0,00% 0,00% 0,00% 0,00%
50-143A1-4-CR-IH-ET MOUNTING 0,58% 0,00% 0,00% 0,00%
50-183A1-6-PW MOUNTING 13,95% 0,00% 0,00% 0,00%
50-128A1-PW-IH-ET (EXTRA TASK) MOUNTING 1,74% 0,00% 0,00% 0,00%
50-137A1-4-CR (EXTRA TASK) MOUNTING 0,00% 0,00% 0,00% 0,00%
Process line area Restoration 2,90% 0,00% 0,00% 0,00%
Demobilization 0,58% 0,00% 0,00% 0,00%
As-buit File 0,58% 0,00% 0,00% 0,00%
TOTAL 52,47% 54,05% 1,58%
Crew
Non Manuel Manuel
Job description Company Number Job description Company Number
Maretap representative SIS 1 Operator CMA 4
QHSE engineer CMA 1 Pipe fitter CMA 2
Project Manager CMA 1 Welder CMA 2
Project/Piping engineer 1 Inspector (SGI) SGI 2
Logistic responsible CMA 1

Work executed on 03/10/2019


-EZZ#11 and 18 CPF Underground riser welding and fitting works are in progress
-EZZ#18 Well head riser prefabrication
-Process lines prefabrication works are in progress
-100% radiography exmaination of prefabricated process lines spool at workshop is in progress (All prefabrication spools NDT works were finished, remainning the Field welds examination)
-Connecting works (fitting, welding and NDT) of EZZ#1 flowline, at its well head, on EZZ#12 flowline (regarding to the leaky state of EZZ#1 flowline), and aboundonning of EZZ#17 flowline by installing an
underground cap. EZZ#1 wellhead riser replacement works are finished and a partial backfilling was performed.
-Backfilling of EZZ#1, 2 and 17 risers at CPF after all replacement works replacement after REFERENCE ELECTRODE + TEST STATION backfilling and cabling.
RECAP:
** EZZ#1 risers replacement works were performed
**EZZ#2 riser at CPF replacement works were finished
**EZZ#17 riser at CPF replacement works were performed . Remmaing the installation of COSSASCO flareweld fitting + CP TEST STATION at WH side.
**EZZ#18 and EZZ#11 risers at CPF and WH prefabrication and installation works are in progress
DAILY REPORT OF 03/10/2019 DAY N° /PLANED DAYS : 77/178 Global progress board of the Project Code : TMP-04
CMA's Project Manager: Sami HDAYA MARETAP's representative : Mejdi jerbi PLANNED ACTUAL VARIANCE Date d’émission:15-08-2017
Version : 01
CMA's Piping/Project Eng: Alaa edine SMAALI CMA's QHSE: Marwene METHENI 52,47% 54,05% 1,58%

SOW: REPALCEMENT OF DAMAGED PIPES AT EZZAOUIA FIELD_ZARZIS

Contractor: CMA engineering & Consulting

Activities Planned next day


-EZZ#1, 2, 9,10,11 and 17, 18 WH and CPF, CP test station (including their cabline +references electrode) mounting
-EZZ#18 and 11 risers at CPF and WH prefabrication continuation
-3'' HDPE electrofusion works inside CPF, As per MARETAP demand. (installation of additional water grid inside CPF)
-100% Radiography examination of all prefabricated spool weld joints continuation

Pending
-HDPE line installation completion inside CPF
-Process lines fitting and welding works
-EZZ#18 and EZZ#11 risers replacement
-EZZ#1 risers replacement works
-Thermal insulation works
-Process lines prefabrication works

PHOTOS

EZZ#1 risers at CPF fitting and welding works Prefabriction works at workshop area