a b e 04-Feb 11-Feb 18-Feb 25-Feb 04-Mar 11-Mar 18-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr 29-Apr
INSTALLATION 90,00%
PROGRESS PLAN THIS WEEK (%) 1,08% 11,11% 12,52% 13,23% 17,39% 10,79% 11,12% 6,96% 5,80% 2,50% 7,50%
CUMMULATIVE PROGRESS THIS WEEK (%) 1,08% 12,19% 24,71% 37,93% 55,32% 66,12% 77,24% 84,20% 90,00% 92,50% 100,00%
ACTUAL PROGRESS (%) 0,54% 9,78% 18,56% 18,56% 11,71% 12,13% 7,79% 2,93% 0,00% 0,00% 0,00%
COMMULATIVE ACTUAL PROGRESS (%) 0,54% 10,32% 28,88% 47,45% 59,15% 71,29% 79,07% 82,00%
DEVIATION (%) -0,53% -1,87% 4,17% 9,51% 3,83% 5,17% 1,84% -2,20%