NAMA PROJECT : SPAM Komunal Rusun Daan Mogot PERIODE : 01 Febuari - 07 Febuari
CLIENT : PAM Jaya LOKASI : Rusun Pesakih Daan Mogot - Jakarta
CONTRACTOR : PT Memiontec Indonesia No : 17
I. Progres Pekerjaan
Bobot Bobot Minggu Lalu Bobot Minggu ini Bobot Komulatif s/d
NO Uraian Matrial
% % Minggu ini %
1 Rumah Pompa 2,51% 0,00% 0,00%
2 Listrik sambungan Mookervart 3,31% 0,00% 0,00%
3 Jaringan Pipa Transmisi - Distribusi 3,17% 3,17% 0,00% 3,17%
4 Water Intake Pump 2,01% 0,00% 0,00%
5 Aeration Tank 16,28% 4,54% 0,00% 4,54%
6 Blower 1,24% 0,00% 0,00%
7 Return Activated Sludge (RAS) 1,34% 0,00% 0,00%
8 Desinfectant Agent Injection Facility 0,25% 0,00% 0,00%
9 pH Adjustment Agent Injection Facility 0,13% 0,00% 0,00%
10 Coagulant Agent Injection Facility 0,18% 0,00% 0,00%
11 Flocculant Agent Injection Facility 0,14% 0,00% 0,00%
12 Blade Agitator for flocculator 0,29% 0,00% 0,00%
13 Water Clarifier Tank 7,55% 4,48% 0,00% 4,48%
14 Clarified Water Storage Tank 0,83% 0,47% 0,00% 0,47%
15 UF Feed Pump 1,02% 0,00% 0,00%
16 Auto Cleaning Filter 1,18% 0,00% 0,00%
17 UF Machine 8,80% 0,00% 0,03% 0,03%
18 UF Backwash Pump 0,78% 0,00% 0,00%
`19 Chlorine CEB Injection Facility 0,72% 0,00% 0,00%
20 Compressor AF for plant air UF and Instrument air 0,45% 0,00% 0,00%
21 Air Receiver Tank 0,15% 0,00% 0,07% 0,07%
22 UF Product Storage Tank 1,05% 1,05% 0,00% 1,05%
23 BWRO Feed Pump 0,89% 0,00% 0,00%
24 BWRO High Pressure Pump 2,30% 0,00% 0,00%
25 BWRO Machine 6,10% 0,00% 6,10% 6,10%
26 CIP system 0,89% 0,00% 0,17% 0,17%
27 Distribution Pump 0,89% 0,00% 0,00%
28 Chlorine Injection Facility - post treatment 0,22% 0,00% 0,00%
29 Instrumentation 3,71% 0,00% 0,00%
30 Central control system 3,88% 0,00% 0,00%
31 Local control box for Intake, Blower & Distribution 0,54% 0,00% 0,00%
32 Packaging 0,38% 0,00% 0,00%
33 Piping & Fitting interconnecting 2,79% 0,00% 0,00%
34 Civil work ( Pilling pondasi pancang) 10,23% 10,23% 0,00% 10,23%
35 Inlet Chamber Tank 0,77% 0,77% 0,00% 0,77%
36 Sludge Tank 0,75% 0,75% 0,00% 0,75%
37 Panel Control & Lab Room 1,05% 0,20% 0,00% 0,20%
38 Meeting Room 1,16% 0,30% 0,00% 0,30%
39 Pump Room 0,97% 0,36% 0,00% 0,36%
40 Storage Room 0,56% 0,09% 0,00% 0,09%
41 Toilet 0,44% 0,04% 0,00% 0,04%
42 Blower Room 1,04% 0,39% 0,00% 0,39%
43 Civil sub struktur 2,65% 2,65% 0,00% 2,65%
44 Pondasi 1,51% 1,36% 0,00% 1,36%
45 Pekerjaan Atap UF & RO 0,95% 0,00% 0,00%
46 Pintu dan Jendela 0,11% 0,00% 0,00%
47 Intake Sumuran Waduk 1,61% 0,00% 0,00%
48 Chemical for commissioning (1 lot) 0,25% 0,00% 0,00%