LAPORAN PROGRES PEKERJAAN

NAMA PROJECT : SPAM Komunal Rusun Daan Mogot PERIODE : 01 Febuari - 07 Febuari
CLIENT : PAM Jaya LOKASI : Rusun Pesakih Daan Mogot - Jakarta
CONTRACTOR : PT Memiontec Indonesia No : 17

I. Progres Pekerjaan
Bobot Bobot Minggu Lalu Bobot Minggu ini Bobot Komulatif s/d
NO Uraian Matrial
% % Minggu ini %
1 Rumah Pompa 2,51% 0,00% 0,00%
2 Listrik sambungan Mookervart 3,31% 0,00% 0,00%
3 Jaringan Pipa Transmisi - Distribusi 3,17% 3,17% 0,00% 3,17%
4 Water Intake Pump 2,01% 0,00% 0,00%
5 Aeration Tank 16,28% 4,54% 0,00% 4,54%
6 Blower 1,24% 0,00% 0,00%
7 Return Activated Sludge (RAS) 1,34% 0,00% 0,00%
8 Desinfectant Agent Injection Facility 0,25% 0,00% 0,00%
9 pH Adjustment Agent Injection Facility 0,13% 0,00% 0,00%
10 Coagulant Agent Injection Facility 0,18% 0,00% 0,00%
11 Flocculant Agent Injection Facility 0,14% 0,00% 0,00%
12 Blade Agitator for flocculator 0,29% 0,00% 0,00%
13 Water Clarifier Tank 7,55% 4,48% 0,00% 4,48%
14 Clarified Water Storage Tank 0,83% 0,47% 0,00% 0,47%
15 UF Feed Pump 1,02% 0,00% 0,00%
16 Auto Cleaning Filter 1,18% 0,00% 0,00%
17 UF Machine 8,80% 0,00% 0,03% 0,03%
18 UF Backwash Pump 0,78% 0,00% 0,00%
`19 Chlorine CEB Injection Facility 0,72% 0,00% 0,00%
20 Compressor AF for plant air UF and Instrument air 0,45% 0,00% 0,00%
21 Air Receiver Tank 0,15% 0,00% 0,07% 0,07%
22 UF Product Storage Tank 1,05% 1,05% 0,00% 1,05%
23 BWRO Feed Pump 0,89% 0,00% 0,00%
24 BWRO High Pressure Pump 2,30% 0,00% 0,00%
25 BWRO Machine 6,10% 0,00% 6,10% 6,10%
26 CIP system 0,89% 0,00% 0,17% 0,17%
27 Distribution Pump 0,89% 0,00% 0,00%
28 Chlorine Injection Facility - post treatment 0,22% 0,00% 0,00%
29 Instrumentation 3,71% 0,00% 0,00%
30 Central control system 3,88% 0,00% 0,00%
31 Local control box for Intake, Blower & Distribution 0,54% 0,00% 0,00%
32 Packaging 0,38% 0,00% 0,00%
33 Piping & Fitting interconnecting 2,79% 0,00% 0,00%
34 Civil work ( Pilling pondasi pancang) 10,23% 10,23% 0,00% 10,23%
35 Inlet Chamber Tank 0,77% 0,77% 0,00% 0,77%
36 Sludge Tank 0,75% 0,75% 0,00% 0,75%
37 Panel Control & Lab Room 1,05% 0,20% 0,00% 0,20%
38 Meeting Room 1,16% 0,30% 0,00% 0,30%
39 Pump Room 0,97% 0,36% 0,00% 0,36%
40 Storage Room 0,56% 0,09% 0,00% 0,09%
41 Toilet 0,44% 0,04% 0,00% 0,04%
42 Blower Room 1,04% 0,39% 0,00% 0,39%
43 Civil sub struktur 2,65% 2,65% 0,00% 2,65%
44 Pondasi 1,51% 1,36% 0,00% 1,36%
45 Pekerjaan Atap UF & RO 0,95% 0,00% 0,00%
46 Pintu dan Jendela 0,11% 0,00% 0,00%
47 Intake Sumuran Waduk 1,61% 0,00% 0,00%
48 Chemical for commissioning (1 lot) 0,25% 0,00% 0,00%

Total 100,00% 6,36% 37,21%


Bobot Rencana Minggu ke 17 38,39%
Deviasi -1,19%

III. Laporan Keselamatan Kesehatan Kerja


No Uraian Keterangan
1 Alat Pelindung Diri (APD) Kelengkapan Alat Pelindung Diri (APD) sudah sesuai dengan standar K3
2 Pengaman di Lokasi Kerja Lokasi pengecoran sudah di beri akses tangga sudah di siapkan terpal jika
Terjadi hujan, pemasangan scafolding buat bekisting sudah sesuai standar K3

IV. Laporan Quality Control


No Uraian Keterangan
1 Matrial UF Sudah di setujui dan sudah sesuai dengan spesifikasi
2 Matrial RO Sudah di setujui dan sudah sesuai dengan spesifikasi
3 Sudah di setujui dan sudah sesuai dengan spesifikasi