NO URAIAN PEKERJAAN Volume Sat Bobot % 22 Juli 2022
PRESTASI PEKERJAAN KEMARIN % PRESTASI PEKERJAAN HARI INI % PRESTASI PEKERJAAN HARI KOMULATIF%
Volume % BOBOT Volume % BOBOT Volume % BOBOT
1 Sloof
1.1 Besi Dia. 6 24.451 m' 0.17% 24.45 100% 0.17% 0.00 0.00% 24.45 100% 0.17%
1.2 Besi Dia.8 27.900 m' 0.28% 27.90 100% 0.28% 0.00 0.00% 27.90 100% 0.28%
1.3 Footplat 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
1.4 Besi Dia.8 25.200 m' 0.26% 25.20 100% 0.26% 0.00 0.00% 25.20 100% 0.26%
1.5 Sloof 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
1.6 Besi 6 228.000 m' 1.63% 228.00 100% 1.63% 0.00 0.00% 228.00 100% 1.63%
1.7 Besi 10 166.408 m' 1.68% 166.41 100% 1.68% 0.00 0.00% 166.41 100% 1.68%
1.8 Kolom 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
1.9 Besi 6 126.400 m' 0.90% 126.40 100% 0.90% 0.00 0.00% 126.40 100% 0.90%
1.10 Besi 8 235.760 m' 2.39% 235.76 100% 2.39% 0.00 0.00% 235.76 100% 2.39%
1.11 Ring balok 0.00 50% 0.00% 0.00 0.00% 0.00 50% 0.00%
1.12 Besi 6 152.000 m' 1.09% 121.60 80% 0.87% 0.00 0.00% 121.60 80% 0.87%
1.13 Besi 8 166.408 m' 1.68% 133.13 80% 1.35% 0.00 0.00% 133.13 80% 1.35%
1.14 Balok latai 0.00 50% 0.00% 0.00 0.00% 0.00 50% 0.00%
1.15 Besi 6 32.000 m' 0.23% 25.60 80% 0.18% 0.00 0.00% 25.60 80% 0.18%
1.16 Besi 8 31.200 m' 0.32% 24.96 80% 0.25% 0.00 0.00% 24.96 80% 0.25%
1.17 Phase I 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
1.18 Pekerjaan Persiapan 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
1.19 Pembersihan 1.000 Ls 0.12% 1.00 100% 0.12% 0.00 0.00% 1.00 100% 0.12%
1.20 Bowplank 28.000 m' 0.57% 28.00 100% 0.57% 0.00 0.00% 28.00 100% 0.57%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
2 Pekerjaan Galian Tanah 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
2.1 Galian Pondasi 0.756 m3 0.17% 0.76 100% 0.17% 0.00 0.00% 0.76 100% 0.17%
2.2 Galian Foot Plat 40/40 0.240 m3 0.05% 0.24 100% 0.05% 0.00 0.00% 0.24 100% 0.05%
2.3 Strause dan tapak (pilecap) 9.000 m' 0.40% 9.00 100% 0.40% 0.00 0.00% 9.00 100% 0.40%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
3 Pekerjaan Pondasi 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
3.1 Strosse 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
3.2 Beton 175 0.283 m3 0.44% 0.28 100% 0.44% 0.00 0.00% 0.28 100% 0.44%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
4 Foot Plate 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
4.1 Beton 175 0.240 m3 0.37% 0.24 100% 0.37% 0.00 0.00% 0.24 100% 0.37%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
5 Pondasi bata merah 7.564 m2 1.70% 7.56 100% 1.70% 0.00 0.00% 7.56 100% 1.70%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
6 Pekerjaan Pipa Air Kotor 0.00 70% 0.00% 0.00 0.00% 0.00 70% 0.00%
6.1 Pipa 3" 23.800 m' 2.05% 16.66 70% 1.44% 0.00 0.00% 16.66 70% 1.44%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
7 Sloof 10/20 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
7.1 Beton K175 0.756 m3 1.17% 0.76 100% 1.17% 0.00 0.00% 0.76 100% 1.17%
7.2 Bekisting 4x 14.800 m2 1.19% 14.80 100% 1.19% 0.00 0.00% 14.80 100% 1.19%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
8 Urugan Tanah 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
8.1 Urugan Tanah biasa 7.416 m3 0.92% 0.74 10% 0.09% 2.97 40% 0.37% 3.71 50% 0.46%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
9 Phase II 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
9.1 Pekerjaan Dinding dalam dan luar 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
9.2 Pasangan Bata ringan 106.030 m2 18.19% 106.03 100% 18.19% 0.00 0.00% 106.03 100% 18.19%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
10 Kolom 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
10.1 Kolom Praktis (KL) 0.00 80% 0.00% 0.00 0.00% 0.00 80% 0.00%
10.2 Beton K175 0.589 m3 0.91% 0.47 80% 0.73% 0.12 20% 0.18% 0.59 100% 0.91%
10.3 Bekisting 11.788 m2 11.79 100% 0.00% 0.00 0.00% 11.79 100% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Ring Balok 10/10 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
11 Ring Balok (RB) 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
11.1 Beton K175 0.378 m3 0.58% 0.00 0% 0.00% 0.15 40% 0.23% 0.15 40% 0.23%
11.2 Bekisting 7.564 m2 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
12 Balok Latai (BL) 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
12.1 Beton K175 0.078 m3 0.12% 0.06 80% 0.10% 0.00 0.00% 0.06 80% 0.10%
12.2 Bekisting 1.872 m2 1.50 80% 0.00% 0.00 0.00% 1.50 80% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
13 Pasang Pintu dan jendela 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
13.1 Pasang Kusen kayu 3.000 Unit 1.74% 3.00 100% 1.74% 0.00 0.00% 3.00 100% 1.74%
13.2 kusen jendela kayu 2.000 Unit 1.40% 2.00 100% 1.40% 0.00 0.00% 2.00 100% 1.40%