You are on page 1of 2

PEKERJAAN : PROYEK GADING ELAWANA

TYPE : CHALATEA
LOKASI
C3
NO URAIAN PEKERJAAN Volume Sat Bobot % 22 Juli 2022
PRESTASI PEKERJAAN KEMARIN % PRESTASI PEKERJAAN HARI INI % PRESTASI PEKERJAAN HARI KOMULATIF%
Volume % BOBOT Volume % BOBOT Volume % BOBOT

1 Sloof
1.1 Besi Dia. 6 24.451 m' 0.17% 24.45 100% 0.17% 0.00 0.00% 24.45 100% 0.17%
1.2 Besi Dia.8 27.900 m' 0.28% 27.90 100% 0.28% 0.00 0.00% 27.90 100% 0.28%
1.3 Footplat 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
1.4 Besi Dia.8 25.200 m' 0.26% 25.20 100% 0.26% 0.00 0.00% 25.20 100% 0.26%
1.5 Sloof 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
1.6 Besi 6 228.000 m' 1.63% 228.00 100% 1.63% 0.00 0.00% 228.00 100% 1.63%
1.7 Besi 10 166.408 m' 1.68% 166.41 100% 1.68% 0.00 0.00% 166.41 100% 1.68%
1.8 Kolom 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
1.9 Besi 6 126.400 m' 0.90% 126.40 100% 0.90% 0.00 0.00% 126.40 100% 0.90%
1.10 Besi 8 235.760 m' 2.39% 235.76 100% 2.39% 0.00 0.00% 235.76 100% 2.39%
1.11 Ring balok 0.00 50% 0.00% 0.00 0.00% 0.00 50% 0.00%
1.12 Besi 6 152.000 m' 1.09% 121.60 80% 0.87% 0.00 0.00% 121.60 80% 0.87%
1.13 Besi 8 166.408 m' 1.68% 133.13 80% 1.35% 0.00 0.00% 133.13 80% 1.35%
1.14 Balok latai 0.00 50% 0.00% 0.00 0.00% 0.00 50% 0.00%
1.15 Besi 6 32.000 m' 0.23% 25.60 80% 0.18% 0.00 0.00% 25.60 80% 0.18%
1.16 Besi 8 31.200 m' 0.32% 24.96 80% 0.25% 0.00 0.00% 24.96 80% 0.25%
1.17 Phase I 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
1.18 Pekerjaan Persiapan 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
1.19 Pembersihan 1.000 Ls 0.12% 1.00 100% 0.12% 0.00 0.00% 1.00 100% 0.12%
1.20 Bowplank 28.000 m' 0.57% 28.00 100% 0.57% 0.00 0.00% 28.00 100% 0.57%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
2 Pekerjaan Galian Tanah 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
2.1 Galian Pondasi 0.756 m3 0.17% 0.76 100% 0.17% 0.00 0.00% 0.76 100% 0.17%
2.2 Galian Foot Plat 40/40 0.240 m3 0.05% 0.24 100% 0.05% 0.00 0.00% 0.24 100% 0.05%
2.3 Strause dan tapak (pilecap) 9.000 m' 0.40% 9.00 100% 0.40% 0.00 0.00% 9.00 100% 0.40%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
3 Pekerjaan Pondasi 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
3.1 Strosse 0.00 100% 0.00% 0.00 0.00% 0.00 100% 0.00%
3.2 Beton 175 0.283 m3 0.44% 0.28 100% 0.44% 0.00 0.00% 0.28 100% 0.44%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
4 Foot Plate 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
4.1 Beton 175 0.240 m3 0.37% 0.24 100% 0.37% 0.00 0.00% 0.24 100% 0.37%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
5 Pondasi bata merah 7.564 m2 1.70% 7.56 100% 1.70% 0.00 0.00% 7.56 100% 1.70%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
6 Pekerjaan Pipa Air Kotor 0.00 70% 0.00% 0.00 0.00% 0.00 70% 0.00%
6.1 Pipa 3" 23.800 m' 2.05% 16.66 70% 1.44% 0.00 0.00% 16.66 70% 1.44%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
7 Sloof 10/20 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
7.1 Beton K175 0.756 m3 1.17% 0.76 100% 1.17% 0.00 0.00% 0.76 100% 1.17%
7.2 Bekisting 4x 14.800 m2 1.19% 14.80 100% 1.19% 0.00 0.00% 14.80 100% 1.19%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
8 Urugan Tanah 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
8.1 Urugan Tanah biasa 7.416 m3 0.92% 0.74 10% 0.09% 2.97 40% 0.37% 3.71 50% 0.46%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
9 Phase II 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
9.1 Pekerjaan Dinding dalam dan luar 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
9.2 Pasangan Bata ringan 106.030 m2 18.19% 106.03 100% 18.19% 0.00 0.00% 106.03 100% 18.19%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
10 Kolom 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
10.1 Kolom Praktis (KL) 0.00 80% 0.00% 0.00 0.00% 0.00 80% 0.00%
10.2 Beton K175 0.589 m3 0.91% 0.47 80% 0.73% 0.12 20% 0.18% 0.59 100% 0.91%
10.3 Bekisting 11.788 m2 11.79 100% 0.00% 0.00 0.00% 11.79 100% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Ring Balok 10/10 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
11 Ring Balok (RB) 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
11.1 Beton K175 0.378 m3 0.58% 0.00 0% 0.00% 0.15 40% 0.23% 0.15 40% 0.23%
11.2 Bekisting 7.564 m2 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
12 Balok Latai (BL) 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
12.1 Beton K175 0.078 m3 0.12% 0.06 80% 0.10% 0.00 0.00% 0.06 80% 0.10%
12.2 Bekisting 1.872 m2 1.50 80% 0.00% 0.00 0.00% 1.50 80% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
13 Pasang Pintu dan jendela 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
13.1 Pasang Kusen kayu 3.000 Unit 1.74% 3.00 100% 1.74% 0.00 0.00% 3.00 100% 1.74%
13.2 kusen jendela kayu 2.000 Unit 1.40% 2.00 100% 1.40% 0.00 0.00% 2.00 100% 1.40%
LOKASI
C3
NO URAIAN PEKERJAAN Volume Sat Bobot % 22 Juli 2022
PRESTASI PEKERJAAN KEMARIN % PRESTASI PEKERJAAN HARI INI % PRESTASI PEKERJAAN HARI KOMULATIF%
Volume % BOBOT Volume % BOBOT Volume % BOBOT

0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%


14 Pekerjaan Instalasi Listrik dan air 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
14.1 Instalasi Air Bersih 1/2" 14.000 m' 0.32% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
14.2 Acian 165.000 m2 9.13% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
14.3 Closet jongkok 1.000 Unit 0.32% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Phase III 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Pekerjaan Pasang Keramik 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
15 Area Lantai 1 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
15.1 Keramik 40 x 40 29.580 m2 4.75% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
15.2 Keramik Kamar Mandi 20 x 20 2.100 m2 0.40% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
16 Pekerjaan accesoris 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
16.1 Panel dinding depan conwood 6.900 m2 1.20% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Phase IV 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
17 Beton K175 Non Tulangan 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
17.1 Cor Beton 1.500 m3 2.34% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
18 Material bantu lot 2.67% 0.00 20% 0.53% 0.00 0.00% 0.00 20% 0.53%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Pekerjaan Atap 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Rangka 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
19 CNP besi 75 60.200 m' 4.63% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
19.1 Reng V 0,45 63.450 m' 1.44% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
19.2 Atap Galvalum Pasir 37.050 m2 6.19% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
20 Pekerjaan Instalasi Listrik dan air 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
20.1 Sparing, Kabel dan perlengkapannya 12.000 Titik 2.39% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
21 Phase III 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Pekerjaan Plafon 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
21.1 Rangka Plafon 82.000 m' 2.33% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
21.2 Plafon Gypsum 31.050 m2 1.45% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
22 Pekerjaan Pengecatan 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
Cat Ekterior 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
22.1 Cat Dinding Eksterior 57.500 m2 1.22% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
22.2 Cat Panel eksterior 6.900 m2 0.13% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
22.3 Cat WaterProfing 43.360 m2 1.95% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
22.4 Cat Interior 136.567 m2 2.51% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
22.5 Cat Plafon 33.690 m2 0.78% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
22.6 Cat Kayu 11.305 m2 0.69% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23 Pasang Pintu dan jendela 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.1 Pasang Daun Pintu kayu 2.000 Unit 1.43% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.2 Pasang Daun Pintu multiplek 2.000 Unit 1.34% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.3 Kusen hollow besi 4x8 11.150 m' 1.12% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.4 Kusen hollow besi 1 x 2 9.600 m' 0.71% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.5 Pasang Daun Jendela 1.000 Unit 0.58% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.6 Daun jendela depan 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.7 Hollow besi 3 x 6 4.800 m' 0.44% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.8 List U alumunium 5 mm 4.800 m' 0.11% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.9 Kaca polos 5 mm 0.604 m2 0.20% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
23.10 Kusen dan daun jendela depan aluminium1.000 Unit 1.26% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
24 Pasang kanopi depan 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
24.1 Hollow 4 x 8 14.320 m' 1.74% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
24.2 Hollow 4 x 4 3.200 m' 0.20% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
24.3 Grc T: 6 mm 4.086 m2 0.57% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
25 Pasang Lampu, Saklar, Stop Kontak 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
25.1 Saklar Single 4.000 Pcs 0.14% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
25.2 Saklar Double 1.000 Pcs 0.04% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
25.3 Stop Kontak 4.000 Pcs 0.18% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
25.4 Lampu Downled 6.000 Pcs 0.23% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
25.5 MCB 1.000 Pcs 0.17% 0.00 0% 0.00% 0.00 0.00% 0.00 0% 0.00%
TOTAL 40.38% 0.78% 41.17%