PROPOSED SINGLE STOREY RESEDENTIAL BUILDING IN POBLACION RONDA CEBU

NAME: MARC STEVE L. MORENO

COURSE & YEAR: BSCE-BT-4

LENGTH WIDTH
SR. NO DESCRIPTION OF WORK NO. HEIGHT (m)
(m) (m)

1.00 MOBILIZATION/DEMOBILIZATION 1.00

2.00 EARTHWORKS
EXCAVATION FOR FOOTING 1.00 6.30 0.75 1.00
1.00 8.00 0.75 1.00
1.00 6.76 0.75 1.00
1.00 1.00 0.75 1.00
1.00 5.76 0.75 1.00
1.00 1.10 0.75 1.00
1.00 2.35 0.75 1.00
1.00 2.35 0.75 1.00
1.00 3.46 0.75 1.00
SEPTIC TANK 1.00 3.30 1.90 1.50
TOTAL =
3.00 CONCRETE WORKS
FOOTING GL 10.00 6.30 0.75 0.30
8.00 0.75 0.30
6.76 0.75 0.30
1.00 0.75 0.30
5.76 0.75 0.30
1.10 0.75 0.30
2.35 0.75 0.30
2.35 0.75 0.30
3.46 0.75 0.30
TOTAL =

WALLS 10.00 6.30 0.12 3.00


8.00 0.12 3.00
6.76 0.12 3.00
1.00 0.12 3.00
5.76 0.12 3.00
1.10 0.12 0.70
2.35 0.12 0.70
2.35 0.12 0.70
3.46 0.12 0.70
TOTAL =

4.00 MASONRY WORKS


CONCRETE HOLLOW BLOCKS
.10m x .20m x .40m 4.00

TOTAL=

CONCRETE CLASS "A" MIXTURE QUANTITY-UNIT SUB-TOTAL QUANTITY-UNIT

PORTLAND CEMENT (40 kg) 9.00 19.14 m3 172.22


SAND 0.50 19.14 m 3
9.57
GRAVEL 1.00 19.14 m 3
19.14
ONDA CEBU

QUANTITY UNIT

1.00 lot

4.73 m3
6.00 m3
5.07 m3
0.75 m3
4.32 m3
0.83 m3
1.76 m3
1.76 m3
2.60 m3
9.41 m3
37.22 m3

1.42 m3
1.80 m3
1.52 m3
0.23 m3
1.30 m3
0.25 m3
0.53 m3
0.53 m3
0.78 m3
8.34 m3

2.27 m3
2.88 m3
2.43 m3
0.36 m3
2.07 m3
0.09 m3
0.20 m3
0.20 m3
0.29 m3
10.79 m3

120.00 PC's
185.00 PC's
20.00 PC's
325.00 PC's

TAL QUANTITY-UNIT COST/UNIT TOTAL COST

Bags 220.00 PHP 37,889.36


m 3
1750.00 PHP 16,744.04
m 3
1750.00 PHP 33,488.07
TOTAL = PHP 88,121.46
SR. NO. NAME OF ITEM QTY UNIT COST/UNIT TOTAL ACCOMPLISHMENT
1 MOBILIZATION/DEMOBILIZATION 1 lot
2 EARTHWORKS 37.215 m3
3 CONCRETE WORKS 19.136 m3
4 MASONRY WORKS 325 PC's
REMARKS CONDITIONS