PEMASANGAN LAMPU TENAGA SURYA HEMAT ENERGI (LTSHE) PAPUA V

NO DESCRIPTION WEIGHT (%) 22/09/2017 25/09/2017 02/10/2017 09/10/2017 16/10/2017 23/10/2017 30/10/2017 06/11/2017 13/11/2017 20/11/2017 27/11/2017 04/12/2017 11/12/2017 18/12/2017 25/12/2017
PEMASANGAN LAMPU TENAGA SURYA HEMAT ENERGI (LTSHE) PAPUA V
SURAT PERINTAH MULAI KERJA
A1000 SPMK
PERSIAPAN
A1010 Kick Off Meeting 0,14% 0,14%
A1020 Perizinan 1,91% 100% 0,38% 0,96% 0,57%
A1030 Survey 2,87% 0,29% 0,57% 0,72% 1,29%
A1040 Temporary Fasility 2,87% 0,29% 0,57% 0,72% 1,29%
A1050 Sewa Akomodasi 2,87% 0,29% 0,57% 0,72% 1,29%
A1060 Mobilisasi 2,87% 0,57% 1,43% 0,86%
ENGINEERING
A1080 Detail Engineering 0,27% 90% 0,27%
MANUFACTURING/PROCUREMENT
A2160 Peralatan Kerja 2,87% 0,29% 0,57% 1,00% 1,00%
PENGADAAN KOMPONEN
A1090 Lampu LED 3 W 4,10% 0,20% 0,41% 1,23% 1,23% 1,02%
A1100 Modul Surya Mono/Pollycristaline 4,10% 0,20% 0,41% 1,23% 1,23% 1,02%
A1110 Baterai Lithium 4,10% 0,20% 0,41% 1,23% 1,23% 1,02%
80%
A1120 Hub 4,10% 0,20% 0,41% 1,23% 1,23% 1,02%
A1130 Kabel 4,10% 0,20% 0,41% 1,23% 1,23% 1,02%
A1140 Tiang Penyangga Solar Panel 4,10% 0,20% 0,41% 1,23% 1,23% 1,02%
A1150 Kabel USB Charger 4,10% 0,20% 0,41% 1,23% 1,23% 1,02%
PROSES PRODUKTIVITAS LAMPU LTHSE
A2150 Proses Produksi 4,10% 0,82% 0,82% 1,43% 0,82% 0,20%
A2380 Assembly 4,10% 70% 0,82% 0,82% 1,43% 0,82% 0,20%
A2390 Packing 3,42% 0,68% 1,20% 1,20% 0,34%
A2400 QC Inspection 3,42% 0,68% 1,20% 1,20% 0,34%
PENGIRIMAN MATERIAL
PENGIRIMAN KE IBU KOTA
TOLIKARA
A2410 Karubaga 1,64% 60% 0,98% 0,66%
DISTRIBUSI KE LOKASI
TOLIKARA 0,41% 0,16% 0,25%
A2420 kai 0,41% 0,16% 0,25%
A2430 Geya 0,41% 0,16% 0,25%
A2440 Bewani 0,41% 0,16% 0,25%
A2450 Anawi 0,41% 0,16% 0,25%
50%
A2460 Kondaga 0,41% 0,16% 0,25%
A2470 Wunin 0,41% 0,16% 0,25%
A2480 Kubu 0,41% 0,16% 0,25%
A2490 Wenan 0,41% 0,16% 0,25%
A2500 Numba 0,41% 0,16% 0,25%
A2510 Timori 0,41% 0,16% 0,25%
A2520 Wugi 0,41% 40% 0,16% 0,25%
A2530 Yuneri 0,41% 0,16% 0,25%
A2540 Gundadi 0,41% 0,16% 0,25%
A2550 Dow 0,41% 0,16% 0,25%
A2560 Karubaga 0,41% 0,16% 0,25%
A2570 Wakuo 0,41% 0,16% 0,25%
INSTALASI/PEMASANGAN 30%
TOLIKARA
A2610 Kai 2,05% 0,20% 1,02% 0,82%
A2620 Geya 2,05% 0,20% 1,02% 0,82%
A2630 Bewani 1,37% 0,14% 0,68% 0,55%
A2640 Anawi 2,05% 0,20% 1,02% 0,82%
A2650 Kondaga 2,05% 0,20% 1,02% 0,82%
20%
A2660 Wunin 2,05% 0,20% 1,02% 0,82%
A2670 Kubu 2,05% 0,20% 1,02% 0,82%
A2680 Wenan 2,05% 0,20% 1,02% 0,82%
A2690 Numba 1,64% 0,16% 0,82% 0,66%
A2700 Timori 2,05% 0,20% 1,02% 0,82%
A2710 Wugi 1,64% 0,16% 0,82% 0,66%
A2720 Yuneri 2,87% 10% 0,57% 1,00% 1,00% 0,29%
A2730 Gundadi 2,05% 0,20% 1,02% 0,82%
A2740 Dow 0,96% 0,38% 0,57%
A2750 Karubaga 2,05% 0,20% 1,02% 0,82%
A2760 Wakuo 2,05% 0,20% 1,02% 0,82%
FINISH
A2020 Serah Terima Pekerjaan 0%
TOTAL (%) 100%
PLAN (%) 1,65% 4,11% 5,88% 13,05% 9,61% 10,39% 4,44% 6,12% 4,03% 1,09% 3,77% 8,51% 15,17% 11,88% 0,29%
CUMMULATIVE PLAN (%) 1,65% 5,77% 11,65% 24,70% 34,31% 44,70% 49,14% 55,26% 59,29% 60,38% 64,15% 72,66% 87,83% 99,71% 100,00%