Activity ID Activity Name Original Duration Schedule % Start Finish Total Float April 2017 May 2017 June 2017 July 2017 August 2017 September 2017 October 2017 November 2017
Complete 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19
Jasa Rekasaya, Pengadaan & Instalasi 1 (Satu)Unit Horizontal Production Separator 2 Phasa Lica 196 0% 03-Apr-17 08 15-Oct-17 17 0 15-Oct-17 17, Jasa Rekasaya, Pengadaan & Instalasi 1 (Satu)Unit Horiz ontal Production Separator 2 Phasa Lica
A1010 Jadw al Pelaksanaan Pekerjaan (Schedule) 5 0% 03-Apr-17 08 07-Apr-17 17 0 Jadw al Pelaksanaan Pekerjaan (Schedule)
A1020 S - Curve 5 0% 03-Apr-17 08 07-Apr-17 17 0 S - Curve
A1030 Kick Off Meeting 1 0% 08-Apr-17 08 08-Apr-17 17 0 Kick Off Meeting
A1190 Perizinan 7 0% 09-Apr-17 08 15-Apr-17 17 183 Perizinan
A1200 Mobilisasi & Demobilisasi 5 0% 19-Sep-17 08 23-Sep-17 17 22 Mobilisasi & Demobilisasi
Enginee ring 21 0% 09-Apr-17 08 29-Apr-17 17 169 29-Apr-17 17, Engineering
Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation