You are on page 1of 2

SWT 11-Feb-17 10:38

Activity ID Activity Name Original Start Finish Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Duration Jun
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
NEWPROJ-3 SWT 107 28-Jan-17 31-May-17 31-May-17, NEWPROJ-3 SWT

NEWPROJ-3.6 First Stage up to level +1.4 71 28-Jan-17 19-Apr-17 19-Apr-17, NEWPROJ-3.6 First Stage up to level +1.4

NEWPROJ-3.6.1 Area 1 41 28-Jan-17 15-Mar-17 15-Mar-17, NEWPROJ-3.6.1 Area 1


NEWPROJ-3.6.1.2 Columns 14 28-Jan-17 10-Feb-17 10-Feb-17, NEWPROJ-3.6.1.2 Columns
A1010 Rebars,Formwork&Concrete 14 28-Jan-17 10-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.1.3 Walls 14 07-Feb-17 20-Feb-17 20-Feb-17, NEWPROJ-3.6.1.3 Walls
A1020 Rebars,Formwork&Concrete 14 07-Feb-17 20-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.1.4 Slabs 23 17-Feb-17 15-Mar-17 15-Mar-17, NEWPROJ-3.6.1.4 Slabs
A1030 FormWork 11 17-Feb-17 27-Feb-17 FormWork
A1040 Rebar 9 24-Feb-17 04-Mar-17 Rebar
A1250 concrete 10 05-Mar-17 15-Mar-17 concrete
NEWPROJ-3.6.2 Area 2 45 28-Jan-17 20-Mar-17 20-Mar-17, NEWPROJ-3.6.2 Area 2
NEWPROJ-3.6.2.1 Foundation 6 28-Jan-17 02-Feb-17 02-Feb-17, NEWPROJ-3.6.2.1 Foundation
A1050 Rebars,Formwork&Concrete 6 28-Jan-17 02-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.2.2 Columns 14 07-Feb-17 20-Feb-17 20-Feb-17, NEWPROJ-3.6.2.2 Columns
A1060 Rebars,Formwork&Concrete 14 07-Feb-17 20-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.2.3 Walls 16 10-Feb-17 25-Feb-17 25-Feb-17, NEWPROJ-3.6.2.3 Walls
A1070 Rebars,Formwork&Concrete 16 10-Feb-17 25-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.2.4 Slabs 26 19-Feb-17 20-Mar-17 20-Mar-17, NEWPROJ-3.6.2.4 Slabs
A1080 FormWork 16 19-Feb-17 06-Mar-17 FormWork
A1090 Rebar 10 25-Feb-17 06-Mar-17 Rebar
A1260 concrete 12 07-Mar-17 20-Mar-17 concrete
NEWPROJ-3.6.3 Area 3 55 28-Jan-17 01-Apr-17 01-Apr-17, NEWPROJ-3.6.3 Area 3
NEWPROJ-3.6.3.1 Foundation 13 28-Jan-17 09-Feb-17 09-Feb-17, NEWPROJ-3.6.3.1 Foundation
A1100 Rebars,Formwork&Concrete 13 28-Jan-17 09-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.3.2 Columns 7 16-Feb-17 22-Feb-17 22-Feb-17, NEWPROJ-3.6.3.2 Columns
A1110 Rebars,Formwork&Concrete 7 16-Feb-17 22-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.3.3 Walls 11 23-Feb-17 05-Mar-17 05-Mar-17, NEWPROJ-3.6.3.3 Walls
A1120 Rebars,Formwork&Concrete 11 23-Feb-17 05-Mar-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.3.4 Slabs 27 01-Mar-17 01-Apr-17 01-Apr-17, NEWPROJ-3.6.3.4 Slabs
A1190 FormWork 15 01-Mar-17 15-Mar-17 FormWork
A1200 Rebar 11 10-Mar-17 20-Mar-17 Rebar
A1270 Concrete 10 21-Mar-17 01-Apr-17 Concrete
NEWPROJ-3.6.4 Area 4 65 28-Jan-17 12-Apr-17 12-Apr-17, NEWPROJ-3.6.4 Area 4
NEWPROJ-3.6.4.1 Foundation 20 28-Jan-17 16-Feb-17 16-Feb-17, NEWPROJ-3.6.4.1 Foundation
A1130 Rebars,Formwork&Concrete 20 28-Jan-17 16-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.4.2 Columns 6 26-Feb-17 03-Mar-17 03-Mar-17, NEWPROJ-3.6.4.2 Columns
A1140 Rebars,Formwork&Concrete 6 26-Feb-17 03-Mar-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.4.3 Walls 12 01-Mar-17 12-Mar-17 12-Mar-17, NEWPROJ-3.6.4.3 Walls
A1150 Rebars,Formwork&Concrete 12 01-Mar-17 12-Mar-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.4.4 Slabs 25 15-Mar-17 12-Apr-17 12-Apr-17, NEWPROJ-3.6.4.4 Slabs
A1210 FormWork 12 15-Mar-17 26-Mar-17 FormWork
A1220 Rebar 12 21-Mar-17 01-Apr-17 Rebar
A1280 Concrete 10 02-Apr-17 12-Apr-17 Concrete
NEWPROJ-3.6.5 Area 5 71 28-Jan-17 19-Apr-17 19-Apr-17, NEWPROJ-3.6.5 Area 5
NEWPROJ-3.6.5.1 Foundation 25 28-Jan-17 21-Feb-17 21-Feb-17, NEWPROJ-3.6.5.1 Foundation
A1160 Rebars,Formwork&Concrete 25 28-Jan-17 21-Feb-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.5.2 Columns 3 01-Mar-17 03-Mar-17 03-Mar-17, NEWPROJ-3.6.5.2 Columns
A1170 Rebars,Formwork&Concrete 3 01-Mar-17 03-Mar-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.5.3 Walls 11 09-Mar-17 19-Mar-17 19-Mar-17, NEWPROJ-3.6.5.3 Walls
A1180 Rebars,Formwork&Concrete 11 09-Mar-17 19-Mar-17 Rebars,Formwork&Concrete
NEWPROJ-3.6.5.4 Slabs 23 25-Mar-17 19-Apr-17 19-Apr-17, NEWPROJ-3.6.5.4 Slabs

Actual Work Critical Remaining Work Summary Page 1 of 2  


Remaining Work Milestone  
SWT 11-Feb-17 10:38
Activity ID Activity Name Original Start Finish Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018
Duration Jun
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
A1230 FormWork 8 25-Mar-17 01-Apr-17 FormWork
A1240 Rebar 8 01-Apr-17 08-Apr-17 Rebar
A1290 Concrete 10 09-Apr-17 19-Apr-17 Concrete
NEWPROJ-3.1 Second Stage up to level +5.49 56 28-Mar-17 31-May-17 31-May-17, NEWPROJ-3.1 Second Stage up to level +5.49

NEWPROJ-3.1.1 Shafts 32 28-Mar-17 03-May-17 03-May-17, NEWPROJ-3.1.1 Shafts


A1300 Area 2 12 28-Mar-17 10-Apr-17 Area 2
A1350 Area 3 12 09-Apr-17 22-Apr-17 Area 3
A1360 Area 4 12 20-Apr-17 03-May-17 Area 4
NEWPROJ-3.1.2 Walls 28 10-Apr-17 11-May-17 11-May-17, NEWPROJ-3.1.2 Walls
A1310 Second Lift Wall at Incoming Line 15 10-Apr-17 26-Apr-17 Second Lift Wall at Incoming Line
A1320 Second Lift Wall at Pump Station Area 12 29-Apr-17 11-May-17 Second Lift Wall at Pump Station Area
NEWPROJ-3.1.3 Slabs 26 02-May-17 31-May-17 31-May-17, NEWPROJ-3.1.3 Slabs
A1330 Slab at Incoming line 12 02-May-17 15-May-17 Slab at Incoming line
A1340 Slab at Pump Station 10 21-May-17 31-May-17 Slab at Pump Station

Actual Work Critical Remaining Work Summary Page 2 of 2  


Remaining Work Milestone  