List of Projects Going Beyond 2017

Implementation Expected Contract


Total
Package ID Province Circulation Date
Projects Duration (Days) (PD)

S-NCB1.17 2 Wardak 120 30-Aug-17


NCB 40.1 1 Zabul 120 30-Aug-17
S-M-NCB 32 33 Kunar 150 30-Jul-17
New-M-NCB-14 14 Baghlan 180 30-Aug-17
S-M-NCB 23 16 Faryab 210 30-Aug-17
S-M-NCB 23.1 17 Faryab 210 30-Aug-17
S-M-NCB 23.2 23 Faryab 210 30-Aug-17
S-M-NCB 23.3 22 Faryab 210 30-Aug-17
Incomplete. Building. SAR.-19 9 Sare-Pul 180 30-Aug-17
Incomplete. Building. KAN.-3 1 Kandahar 120 30-Aug-17
Incomplete. Building. FAR.-2 3 Faryab 120 30-Aug-17
Incomplete. Building. KAP.-13 1 Kapisa 150 30-Aug-17
Incomplete. Building. HEL.-12 1 Helmand 150 30-Aug-17
Incomplete. Building. BAD.2 5 Badakhshan 150 30-Aug-17
Incomplete. Building. PANJ.-18 4 Panshir 180 30-Aug-17
Incomplete. Building. PANJ.-19 3 Panshir 180 30-Aug-17
Incomplete. Building. PANJ.-20 8 Panshir 180 30-Aug-17
Incomplete. Building. DAY.-8 9 Daikundi 180 30-Aug-17
Incomplete. Building. BAD.-1 4 Badakhshan 150 30-Aug-17
Incomplete. Building. BAM.-7 6 Bamyan 180 30-Aug-17
Incomplet. Building. KUN.-14 1 Kunar 150 30-Aug-17
Incomplete. Building. GAZ.-9 2 Ghazni 120 30-Aug-17
Incomplete. Building. GHO.-11 2 Ghor 150 30-Aug-17
Incomplete. Building. LAG.-4 1 Laghman 150 30-Aug-17
Incomplete. Building. UROZ.-20 10 Urozgan 150 30-Aug-17
NCB 20.1 1 KAPISA 120 30-Aug-17
NCB 28.4 1 Baghlan 120 30-Sep-17
S-W-S 5 1 Kabul City 90 30-Sep-17
S-M-NCB 34 62 Bamyan 250 1-Nov-10
S-M-NCB 3.1 30 Badakhshan 180 9-Sep-17
Status Summary
Under Procurement 168
Under Implementation 63
Stopped 62
Total number of Projects going beyond 2017 293
2017

Expected
NTPA Issuance Completion Current Status at PD
Date (ISD) Date

9-Sep-17 7-Jan-18 Under Evaluation Under Distribution 51


9-Sep-17 7-Jan-18 Under Distribution Under Evaluation 113
9-Aug-17 6-Jan-18 Newly contracted Under Contracting 4
9-Sep-17 6-Jun-18 Under Evaluation
9-Sep-17 6-Jul-18 Under Evaluation
9-Sep-17 6-Jul-18 Under Evaluation
9-Sep-17 6-Jul-18 Under Distribution
9-Sep-17 6-Jul-18 Under Evaluation
9-Sep-17 6-Jun-18 Under Evaluation
9-Sep-17 7-Jan-18 Under Evaluation
9-Sep-17 7-Jan-18 Under Distribution
9-Sep-17 6-Feb-18 Under Evaluation
9-Sep-17 6-Feb-18 Under Contracting
9-Sep-17 6-Feb-18 Under Distribution
9-Sep-17 8-Mar-18 Under Evaluation
9-Sep-17 8-Mar-18 Under Evaluation
9-Sep-17 8-Mar-18 Under Evaluation
9-Sep-17 6-Jun-18 Under Distribution
9-Sep-17 6-Feb-18 Under Evaluation
9-Sep-17 6-Jun-18 Under Evaluation
9-Sep-17 6-Feb-18 Under Contracting
9-Sep-17 7-Jan-18 Under Evaluation
9-Sep-17 6-Feb-18 Under Contracting
9-Sep-17 6-Feb-18 Under Distribution
9-Sep-17 6-Feb-18 Under Distribution
9-Sep-17 7-Apr-18 Under Distribution
10-Oct-17 7-Feb-18 Under Evaluation
10-Oct-17 8-Jan-18 Terminated
20-Sep-12 11-Sep-17 Stopped
10-Oct-17 17-Jan-18 Newly contracted
Ongoing Expired Projects

# of Contract Last Extension Deadline for Deadline for


Sr # Package ID Province Projects Start Date End Date ISD PD

1566 New-M-NCB-02 DAYKUNDI 3 3-Jul-16 29-May-17 2-Aug-17 22-Aug-17


261 S-M-NCB 5 GHAZNI 12 30-Aug-16 28-Jun-17 7-Sep-17 27-Sep-17
1298 NCB 40.2 ZABUL 1 7-Nov-16 6-Aug-17 28-Aug-17 22-Aug-17
472 S-M-NCB 9.1 WARDAK 16 27-Oct-15 26-May-17 5-Sep-17 27-Sep-17
781 NCB 20.3 KAPISA 1 13-Nov-10 10-Jul-13 28-Aug-17 7-Sep-17
1224 S-M-NCB 28 KUNDUZ 12 2-Oct-16 16-May-17 28-Aug-17 27-Sep-17
1561 New-M-NCB-01 BAMYAN 3 1-Oct-16 10-Jun-17 28-Aug-17 7-Sep-17
1573 New-M-NCB-04 KABUL PROVINCE 15 10-Dec-16 6-Jul-17 28-Aug-17 27-Sep-17
1595 New-M-NCB-07 PARWAN 4 5-Mar-17 4-May-17 28-Aug-17 7-Sep-17
Average
Deadline for Physical
Completion Progress % ISD actions
21-Oct-17 99% 13-Aug-17 submitted to cmu
26-Dec-17 41% 20-Aug-17 submiited to cmu change order
21-Oct-17 66% 16-Aug-17 submitted to cmu
27-Oct-17 87% 11-Aug-17 submitted to cmu
26-Nov-17 75% 13-Aug-17 submitted to cmu
27-Oct-17 84% 15-Jun-17 submiited to cmu change order
26-Nov-17 78% 7-Aug-17 submitted to cmu
26-Dec-17 66% 16-Aug-17 submitted to cmu
26-Dec-17 75% 16-Aug-17 submitted to cmu
Stopped Expired Projects

# of Contract Start Last Extension Deadline for Deadline for Deadline for
S. # Package ID Province Projects Date End Date ISD PD Completion

7 S-M-NCB 21 KANDAHAR 9 1-Aug-16 30-Nov-16 7-Sep-17 15-Sep-17 26-Nov-17


8 S-M-NCB 25.1 KHOST 1 7-Dec-15 22-Feb-17 7-Sep-17 12-Sep-17 28-Aug-17

12 S-M-NCB 28 KUNDUZ 3 2-Oct-16 16-May-17 12-Sep-17 17-Sep-17 26-Nov-17

18 New-M-NCB-07 PARWAN 1 5-Mar-17 29-May-17 7-Sep-17 17-Sep-17 26-Dec-17

20 S-M-NCB 20 UROZGAN 8 26-Oct-15 3-Sep-16 7-Sep-17 28-Aug-17 28-Aug-17


Physical Reasons for
Progress % Stoppages

17% Change Order 15-Aug-17


30% Expired 18-Jul-17
Completed by other
0% donor 5-Jun-17
98% Contractor weakness 13-Aug-17
19% Insecurity 22-Aug-17
ISD action

submitted to CMU-change order- 9 projects deducted from Scope of work


submitted to cmu for extetnion

submitted to cmu for extetnion, 3 completed by other donor

submitted to cmu for extetnion, 3 completed by other donor


submitted to cmu for extetnion
Not Started Expired Projects

Last
# of Contract Start Extension/Contract
Sr.# Package ID Province Deadline for ISD Deadline for PD
Projects Date End Date
254 S-M-NCB 5 GHAZNI 3 30-Aug-16 28-Jun-17 17-Sep-17 27-Sep-17

1650 New-M-NCB-16 JOWZJAN 19-Jul-16 18-Jun-17


1

KABUL
1580 New-M-NCB-04 1 10-Dec-16 9-May-17 26-Nov-17 7-Sep-17
PROVINCE

931 S-M-NCB 21 KANDAHAR 39 1-Aug-16 30-Nov-16 28-Aug-17 7-Sep-17


1515 S-M-NCB 20 UROZGAN 1 26-Oct-15 25-Jan-16 12-Aug-17 22-Aug-17
Deadline for Reasons for Not started
Completion

5-May-18 Social problem 20-Aug-17


26-Nov-17 Completed by other doner
25-Jul-17
Technical Problem
(Electricity system to be
17-Sep-17 reduced from the scope of
work) 16-Aug-17
26-Nov-17 Change Order 15-Aug-17
22-Dec-17 Insecurity 22-Aug-17
ISD Actions

change order

submitted to cmu for extetnion

submitted to CMU
submitted to CMU-change order
submitted to cmu for extetnion
Physically Completed Projects

# of Contract Contract End Last Extension Deadline for


S# Package ID Province Projects Start Date Date End Date ISD

1002 S-W-S3.4 BAGHLAN 5 5-Jun-16 4-Oct-16 4-Jan-17 12-Sep-17


1565 New-M-NCB-01 BAMYAN 1 1-Oct-16 30-Dec-16 10-Jun-17 2-Sep-17
1566 New-M-NCB-02 DAYKUNDI 1 3-Jul-16 3-Nov-16 29-May-17 17-Sep-17
1088 S-NCB1.41 FARAH 1 17-Aug-13 16-May-14 11-Dec-14 12-Sep-17
1242 S-NCB1.52 HELMAND 2 19-Oct-15 18-Feb-16 23-Apr-17 12-Sep-17
1646 New-M-NCB-16 JOWZJAN 3 19-Jul-16 18-Oct-16 18-Jun-17 12-Sep-17
1168 S-W-S 4 KABUL CITY 4 27-Jan-16 26-Mar-16 26-Mar-16 28-Aug-17
777 S-NCB1.27 KAPISA 1 3-Jun-15 2-Sep-15 2-Sep-15 7-Sep-17
795 S-M-NCB 16.1 KAPISA 26 25-Aug-14 24-Jan-15 24-Jan-15 17-Sep-17
1143 S-M-NCB 25.1 KHOST 6 7-Dec-15 6-Apr-16 22-Feb-17 7-Sep-17
1703 New-M-NCB-22 KHOST 10 3-Dec-16 2-Apr-17 29-May-17 7-Sep-17
1228 S-M-NCB 28 KUNDUZ 1 2-Oct-16 30-Jan-17 16-May-17 7-Sep-17
1665 New-M-NCB-19 TAKHAR 2 24-Jul-16 24-Oct-16 24-Oct-16 7-Sep-17
1484 S-M-NCB 20 UROZGAN 67 28-Oct-15 27-Jan-16 5-Sep-16 17-Sep-17
date of
Deadline for Deadline for ISD
PD FAD submiision Actions
to PD
22-Sep-17 27-Sep-17 27-Feb-17 submitted to cmu for extetnion
12-Sep-17 17-Sep-17 7-Aug-17 submitted to cmu for extetnion
27-Sep-17 2-Oct-17 13-Aug-17 submitted to cmu for extetnion
22-Sep-17 27-Sep-17 18-Jul-17 submitted to cmu for extetnion
22-Sep-17 27-Sep-17 11-Jun-17 submitted to cmu for extetnion
22-Sep-17 27-Sep-17 25-Jul-17 submitted to cmu for extetnion
7-Sep-17 12-Sep-17 8-Jul-17 submitted to cmu for extetnion
17-Sep-17 22-Sep-17 9-Apr-17 submitted to cmu for extetnion
27-Sep-17 2-Oct-17 16-Aug-17 submitted to cmu for extetnion
17-Sep-17 22-Sep-17 18-Jul-17 submitted to cmu for extetnion
17-Sep-17 22-Sep-17 5-Aug-17 submitted to cmu for extetnion
17-Sep-17 22-Sep-17 5-Jun-17 submitted to cmu for extetnion
17-Sep-17 22-Sep-17 5-Aug-17 submitted to cmu for extetnion
27-Sep-17 2-Oct-17 22-Aug-17 submitted to cmu for extetnion