MSPR6 - BASELINE REV02 Classic Schedule Layout 07-Mar-17 21:06

Activity Name Original Duration Remaining Start Finish Total Float 14 2015 2016 2017
Duration JA J A J JA J A JJA J A JJ
MSPR6 - BASELINE REV02 933 930 30-Jun-14 31-Jul-17 0

Key Access Date 933 930 30-Jun-14 31-Jul-17 0

LOA 0 0 30-Jun-14* 0 LOA, 30-Jun-14*


Notice to Proceed 5 21 30-Jun-14 24-Jul-14 0
TNB Substation (Month 42) 0 0 30-Jun-15* 0 TNB Substation (Month 42),
System Equipment Room Ready (Month 46) 0 0 31-Oct-15* 0 System Equipment Room Rea
Practical Completion (Month 54) 0 0 30-Jun-16* 0 Practical Complet
Care of Work 329 327 01-Jul-16 31-Jul-17 0
TENDER DESIGN 607 601 30-Jun-14 28-Jun-16 0 28-Jun-16, TEND
PRIME COST SUM 99 99 09-Jan-16 07-May-16 42 07-May-16, PRIME C
PROVISIONAL SUM 524 524 02-Sep-14 28-May-16 25 28-May-16, PROVI
CONSTRUCTION 527 527 20-Sep-14 18-Jun-16 7 18-Jun-16, CONS
SITE PREPARATION 215 188 20-Sep-14 07-May-15 277 07-May-15, SITE PREPARATION
STRUCTURAL TEST PILE IN FOUNDATION ENGINEER DRAW 43 43 26-Sep-14 18-Nov-14 0 18-Nov-14, STRUCTURAL TEST PILE IN FO
RETAINING WALL 262 262 03-Oct-14 17-Aug-15 137 17-Aug-15, RETAINING WALL
ELEVATED STRUCTURE BORED PILE & CONTIGUOS BORED 201 208 27-Sep-14 08-Jun-15 124 08-Jun-15, ELEVATED STRUCTURE
R.C Square Pile 300mmx300mm 145 145 09-Mar-15 28-Aug-15 62 28-Aug-15, R.C Square Pile 300
WORK BELOW LOWEST FLOOR 160 160 18-Dec-14 01-Jul-15 168 01-Jul-15, WORK BELOW LOWES
Frame 258 258 20-Apr-15 29-Feb-16 98 29-Feb-16, Frame
Ground Floor 101 101 20-Apr-15 18-Aug-15 148 18-Aug-15, Ground Floor
1st Floor 100 100 30-Apr-15 28-Aug-15 157 28-Aug-15, 1st Floor
2nd Floor 112 112 09-May-15 21-Sep-15 154 21-Sep-15, 2nd Floor
3rd Floor 126 126 16-May-15 15-Oct-15 149 15-Oct-15, 3rd Floor
4th Floor 140 140 22-May-15 07-Nov-15 144 07-Nov-15, 4th Floor
5th Floor 157 157 29-May-15 05-Dec-15 136 05-Dec-15, 5th Floor
6th Floor 170 170 08-Jun-15 30-Dec-15 131 30-Dec-15, 6th Floor
7th Floor 187 187 15-Jun-15 28-Jan-16 123 28-Jan-16, 7th Floor
Roof 40 40 09-Jan-16 29-Feb-16 92 29-Feb-16, Roof
ABWF WORKS 327 327 30-Apr-15 01-Jun-16 22 01-Jun-16, ABWF W
ARCHITECTURAL 327 327 30-Apr-15 01-Jun-16 22 01-Jun-16, ARCHIT
LEVEL LG 108 108 30-Apr-15 09-Sep-15 150 09-Sep-15, LEVEL LG
LEVEL G 132 132 25-May-15 31-Oct-15 110 31-Oct-15, LEVEL G
LEVEL 1 113 113 17-Jun-15 31-Oct-15 113 31-Oct-15, LEVEL 1
LEVEL 2 113 113 09-Jul-15 25-Nov-15 96 25-Nov-15, LEVEL 2
LEVEL 3 99 99 20-Aug-15 17-Dec-15 79 17-Dec-15, LEVEL 3
LEVEL 4 113 113 28-Aug-15 13-Jan-16 62 13-Jan-16, LEVEL 4
LEVEL 5 116 116 22-Sep-15 12-Feb-16 42 12-Feb-16, LEVEL 5
LEVEL 6 116 116 17-Oct-15 07-Mar-16 25 07-Mar-16, LEVEL 6
LEVEL 7 119 119 09-Nov-15 02-Apr-16 22 02-Apr-16, LEVEL 7
ROOF LEVEL 59 59 17-Feb-16 25-Apr-16 22 25-Apr-16, ROOF LE
Floor Coating 30 30 25-Apr-16 01-Jun-16 22 01-Jun-16, Floor C
BWF 412 412 07-Feb-15 18-Jun-16 7 18-Jun-16, BWF
BUILDING SERVICES 412 412 07-Feb-15 18-Jun-16 7 18-Jun-16, BUILD
Electrical 323 323 11-May-15 06-Jun-16 0 06-Jun-16, Electric
LEVEL LG 261 261 11-May-15 23-Mar-16 51 23-Mar-16, LEVEL LG
LEVEL G 125 125 01-Jun-15 30-Oct-15 140 30-Oct-15, LEVEL G
LEVEL 1 121 121 11-Jul-15 07-Dec-15 109 07-Dec-15, LEVEL 1
LEVEL 2 143 143 10-Sep-15 04-Mar-16 68 04-Mar-16, LEVEL 2
LEVEL 3 121 121 17-Sep-15 15-Feb-16 59 15-Feb-16, LEVEL 3
LEVEL 4 121 121 05-Sep-15 01-Feb-16 94 01-Feb-16, LEVEL 4
LEVEL 5 121 121 01-Oct-15 26-Feb-16 74 26-Feb-16, LEVEL 5
LEVEL 6 127 127 26-Oct-15 28-Mar-16 48 28-Mar-16, LEVEL 6
LEVEL 7 121 121 18-Nov-15 13-Apr-16 34 13-Apr-16, LEVEL 7
ROOF LEVEL 87 87 23-Feb-16 06-Jun-16 0 06-Jun-16, ROOF
MECHANICAL 412 412 07-Feb-15 18-Jun-16 7 18-Jun-16, MECH
Auto Waste Collection System (AWCS) 363 363 07-Feb-15 20-Apr-16 26 20-Apr-16, Auto Was
SOIL, WASTE & VENT PIPE SYSTEM 96 96 07-Feb-15 01-Jun-15 200 01-Jun-15, SOIL, WASTE & VENT P
COLD WATER INSTALLATION 216 216 04-Jul-15 25-Mar-16 70 25-Mar-16, COLD WA
ENVIRONMENTAL CONTROL SYSTEM 288 288 04-Jul-15 18-Jun-16 7 18-Jun-16, ENVIR
FIRE PROTECTION & DETECTION SYSTEM 267 267 04-Jul-15 25-May-16 13 25-May-16, FIRE P
EXTERNAL / ANCILLIARY WORKS 461 461 03-Oct-14 15-Apr-16 61 15-Apr-16, EXTERNA
ROAD WORKS 431 431 03-Oct-14 11-Mar-16 91 11-Mar-16, ROAD WO
INTERNAL ROAD 109 109 28-Aug-15 08-Jan-16 142 08-Jan-16, INTERNAL RO
EXISTING ROAD 431 431 03-Oct-14 11-Mar-16 82 11-Mar-16, EXISTING
Maintain Existing Road for Construction of Retaining Wall along 60 60 03-Oct-14 15-Dec-14 255
Construct New Alignment Expansion Road Level 116 116 08-Jun-15 27-Oct-15 82 27-Oct-15, Construct New Alig
Drainage / Culvert Crossing 60 60 13-Jul-15 26-Sep-15 115 26-Sep-15, Drainage / Culvert
New Alignment Road Construction 111 111 28-Oct-15 11-Mar-16 82 11-Mar-16, New Alignm
Elevated Walkway 60 60 12-Dec-15 27-Feb-16 93 27-Feb-16, Elevated W
SEWERAGE WORKS 125 125 11-Jul-15 11-Dec-15 164 11-Dec-15, SEWERAGE W
WATER RETICULATION 120 120 21-Nov-15 15-Apr-16 52 15-Apr-16, WATER R
FINALISATION WORKS 86 86 19-Mar-16 30-Jun-16 0 30-Jun-16, FINAL
As-Built 60 60 19-Mar-16 30-May-16 15
Testing & Commissioning 10 5 17-Jun-16 23-Jun-16 0
Hand Over 2 2 28-Jun-16 30-Jun-16 0