EOT PROGRAMME - CRITICAL PATH

ID Task Name Duration Start Finish Baseline Start Baseline Finish Total Slack 2019 2020


Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 ROL 1C & 1D: BASELINE PROGRAMME REV.920.5 days 9/12/16 23/12/19 9/12/16 29/1/20 0 days
2 CONTRACT DELIVERABLES 920.5 days 9/12/16 23/12/19 9/12/16 29/1/20 0 days
5 Completion of Package 1D 304.54 days 17/12/18 23/12/19 17/12/18 29/1/20 ‐19.5 days
8 Completion of Jalan Masjid India 0 days 21/12/19 21/12/19 29/1/20 29/1/20 ‐19 days 21/12
10 Completion of Jalan Melayu 0 days 23/12/19 23/12/19 21/1/20 21/1/20 ‐19.5 days 23/12
15 Date of Completion 0 days 23/12/19 23/12/19 29/1/20 29/1/20 ‐19.5 days 23/12
62 BEAUTIFICATION WORKS 771.5 days 1/6/17 23/12/19 1/6/17 29/1/20 ‐19.5 days
63 PACKAGE 1D 771.5 days 1/6/17 23/12/19 1/6/17 29/1/20 ‐19.5 days
64 Jalan TAR 564.3 days 1/6/17 16/4/19 1/6/17 16/4/19 187.7 days
180 Lorong TAR 466.96 days 1/6/17 17/12/18 1/6/17 17/12/18 195.04 days
181 Hardscape Works 337 days 1/6/17 10/7/18 1/6/17 16/8/18 ‐19 days
210 Lorong Masjid India 4 ‐ Jalan Melayu 41.4 days 3/4/18 22/5/18 3/4/18 9/6/18 19.6 days
211 Demolition & relocation of existing stru 14 days 3/4/18 30/4/18 3/4/18 30/4/18 0 days 0 days
217 Dang Wangi ‐ Lorong TAR 7 35 days 2/5/18 13/6/18 14/5/18 14/7/18 ‐19 days
218 Demolition & relocation of existing stru 14 days 2/5/18 17/5/18 14/5/18 31/5/18 ‐19 days ‐10.4 days
219 Piloting and trenching works 14 days 10/5/18 25/5/18 22/5/18 9/6/18 ‐19 days ‐10.4 days
220 Services Works (Water ret, Sump,  14 days 10/5/18 25/5/18 31/5/18 20/6/18 ‐19 days ‐17.4 days
Drains, Sewerage) & accesories
224 Lorong TAR 7 ‐ Lorong Bunus 6 35 days 26/5/18 10/7/18 20/6/18 16/8/18 ‐19 days
225 Demolition & relocation of existing stru 14 days 26/5/18 13/6/18 20/6/18 6/7/18 ‐19 days ‐17.4 days
226 Piloting and trenching works 14 days 6/6/18 23/6/18 28/6/18 14/7/18 ‐19 days ‐17.4 days
227 Services Works (Water ret, Sump,  14 days 6/6/18 23/6/18 6/7/18 23/7/18 ‐19 days ‐24.4 days
Drains, Sewerage) & accesories
228 Kerb construction 14 days 14/6/18 2/7/18 14/7/18 31/7/18 ‐19 days ‐24.4 days
229 Slab construction 14 days 14/6/18 2/7/18 23/7/18 8/8/18 ‐19 days ‐31.4 days
230 Laying Interlocking paver 14 days 25/6/18 10/7/18 31/7/18 16/8/18 ‐19 days ‐31.4 days
291 Jalan Masjid India 434 days 11/7/18 21/12/19 16/8/18 29/1/20 ‐19 days
292 Hardscape Works 364 days 11/7/18 30/9/19 16/8/18 6/11/19 ‐19 days
293 Semua House ‐ Junction Jalan Bunus 119 days 11/7/18 4/12/18 16/8/18 12/1/19 ‐19 days
294 Demolition & relocation of existing stru 35 days 11/7/18 20/8/18 16/8/18 2/10/18 ‐19 days ‐31.4 days
295 Piloting and trenching works 35 days 4/8/18 19/9/18 14/9/18 26/10/18 ‐19 days ‐31.4 days
296 Services Works (Water ret, Sump,  35 days 30/8/18 13/10/18 10/10/18 22/11/18 ‐19 days ‐31.4 days
Drains, Sewerage) & accessories
297 Laying crusher run & compaction 35 days 20/9/18 30/10/18 26/10/18 8/12/18 ‐19 days ‐31.4 days
298 Slab & planter construction 35 days 6/10/18 16/11/18 13/11/18 26/12/18 ‐19 days ‐31.4 days
299 Laying Interlocking paver 35 days 23/10/18 4/12/18 30/11/18 12/1/19 ‐19 days ‐31.4 days
300 Junction Jalan Bunus ‐ Junction Masjid Ind 119 days 5/12/18 27/4/19 12/1/19 8/6/19 ‐19 days
301 Demolition & relocation of existing stru 35 days 5/12/18 16/1/19 12/1/19 26/2/19 ‐19 days ‐31.4 days
302 Piloting and trenching works 35 days 31/12/18 13/2/19 9/2/19 22/3/19 ‐19 days ‐31.4 days
303 Services Works (Water ret, Sump,  35 days 25/1/19 9/3/19 6/3/19 16/4/19 ‐19 days ‐31.4 days
Drains, Sewerage) & accesories
304 Laying crusher run & compaction 35 days 14/2/19 26/3/19 22/3/19 3/5/19 ‐19 days ‐31.4 days
305 Slab & planter construction 35 days 2/3/19 11/4/19 8/4/19 20/5/19 ‐19 days ‐31.4 days
306 Laying Interlocking paver 35 days 19/3/19 27/4/19 24/4/19 8/6/19 ‐19 days ‐31.4 days
307 Walkway Infront of Wisma Yakin 126 days 29/4/19 30/9/19 8/6/19 6/11/19 ‐19 days
308 Demolition shelter infront of Wisma Yak35 days 29/4/19 12/6/19 8/6/19 19/7/19 ‐19 days ‐31.4 days
309 Piloting and trenching works 35 days 13/6/19 23/7/19 19/7/19 30/8/19 ‐19 days ‐31.4 days
310 Services Works (Water ret, Sump,  35 days 29/6/19 9/8/19 6/8/19 18/9/19 ‐19 days ‐31.4 days
Drains, Sewerage) & accesories
311 Laying crusher run & compaction 35 days 16/7/19 26/8/19 22/8/19 4/10/19 ‐19 days ‐31.4 days
312 Slab & planter construction 35 days 2/8/19 12/9/19 9/9/19 21/10/19 ‐19 days ‐31.4 days
313 Laying Interlocking paver 35 days 19/8/19 30/9/19 26/9/19 6/11/19 ‐19 days ‐31.4 days
314 Electrical Works 304.04 days 17/12/18 21/12/19 12/1/19 29/1/20 ‐19 days
315 Connection to nearest LV point 7 days 6/12/19 13/12/19 13/1/20 21/1/20 ‐19 days ‐31.4 days
316 Inspection and Testing 7 days 14/12/19 21/12/19 21/1/20 29/1/20 ‐19 days ‐31.4 days
317 Street lighting 275.04 days 17/12/18 18/11/19 12/1/19 26/12/19 ‐19 days
324 Walkway Infront of Wisma Yakin 41 days 1/10/19 18/11/19 6/11/19 26/12/19 ‐19 days
325 Cabling works 28 days 1/10/19 1/11/19 6/11/19 10/12/19 ‐19 days ‐31.4 days

Page 1
EOT PROGRAMME - CRITICAL PATH
ID Task Name Duration Start Finish Baseline Start Baseline Finish Total Slack 2019 2020
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
326 Installation of street lighting &  28 days 16/10/19 18/11/19 22/11/19 26/12/19 ‐19 days ‐31.4 days
landscape lighting
327 Street Lighting Feeder Pillar  15 days 19/11/19 5/12/19 26/12/19 13/1/20 ‐19 days
328 Installation of feeder pillar 7 days 19/11/19 26/11/19 26/12/19 3/1/20 ‐19 days ‐31.4 days
329 Cabling works 7 days 27/11/19 4/12/19 3/1/20 11/1/20 ‐19 days ‐31.4 days
330 Earthing 1 day 5/12/19 5/12/19 11/1/20 13/1/20 ‐19 days ‐31.4 days
331 Softscape 266 days 5/12/18 24/10/19 12/1/19 2/12/19 ‐5 days
334 Walkway Infront of Wisma Yakin 21 days 1/10/19 24/10/19 6/11/19 2/12/19 ‐5 days ‐31.4 days
335 Furniture & Fixture 266 days 31/12/18 19/11/19 9/2/19 27/12/19 ‐5 days
338 Walkway Infront of Wisma Yakin 21 days 25/10/19 19/11/19 2/12/19 27/12/19 ‐5 days ‐31.4 days
339 Signages 259 days 25/1/19 5/12/19 6/3/19 13/1/20 ‐5 days
342 Walkway Infront of Wisma Yakin 14 days 20/11/19 5/12/19 27/12/19 13/1/20 ‐5 days ‐31.4 days
343 Jalan Melayu 575.5 days 17/1/18 23/12/19 17/1/18 21/1/20 ‐19.5 days
344 Hardscape Works 505.5 days 17/1/18 1/10/19 17/1/18 21/10/19 ‐1.4 days
345 Junction Tun Perak ‐ Junction Masjid India 70 days 12/4/19 6/7/19 20/5/19 14/8/19 ‐12 days
346 Demolition & relocation of existing stru 35 days 12/4/19 24/5/19 20/5/19 3/7/19 ‐12 days ‐31.4 days
347 Piloting and trenching works 35 days 20/4/19 1/6/19 29/5/19 11/7/19 ‐12 days ‐31.4 days
348 Services Works (Water ret, Sump,  35 days 29/4/19 12/6/19 8/6/19 19/7/19 ‐12 days ‐31.4 days
Drains, Sewerage) & accesories
349 Kerb construction 21 days 25/5/19 20/6/19 3/7/19 29/7/19 ‐5 days ‐31.4 days
350 Slab construction 21 days 3/6/19 28/6/19 11/7/19 6/8/19 ‐5 days ‐31.4 days
351 Laying Interlocking paver 21 days 13/6/19 6/7/19 19/7/19 14/8/19 ‐5 days ‐31.4 days
352 Junction Masjid India ‐ Junction Lorong TA 70 days 25/5/19 17/8/19 3/7/19 26/9/19 ‐12 days
353 Demolition & relocation of existing stru 35 days 25/5/19 6/7/19 3/7/19 14/8/19 ‐12 days ‐31.4 days
354 Piloting and trenching works 35 days 3/6/19 15/7/19 11/7/19 22/8/19 ‐12 days ‐31.4 days
355 Services Works (Water ret, Sump,  35 days 13/6/19 23/7/19 19/7/19 30/8/19 ‐12 days ‐31.4 days
Drains, Sewerage) & accesories
356 Kerb construction 21 days 8/7/19 1/8/19 14/8/19 9/9/19 ‐12 days ‐31.4 days
357 Slab construction 21 days 16/7/19 9/8/19 22/8/19 18/9/19 ‐12 days ‐31.4 days
358 Laying Interlocking paver 21 days 24/7/19 17/8/19 30/8/19 26/9/19 ‐12 days ‐31.4 days
359 Junction Lorong TAR ‐ Jln TAR 505.5 days 17/1/18 1/10/19 17/1/18 21/10/19 ‐1.4 days
360 Demolition & relocation of existing stru 35 days 17/1/18 9/9/19 17/1/18 9/9/19 0 days
363 Kerb construction 21 days 27/3/18 13/9/19 27/3/18 13/9/19 ‐19.5 days 0 days
364 Slab construction 21 days 27/8/19 23/9/19 27/8/19 23/9/19 ‐19.5 days 0 days
365 Laying Interlocking paver 21 days 5/9/19 1/10/19 26/9/19 21/10/19 ‐19.5 days ‐16.9 days
366 Electrical Works 140.5 days 8/7/19 23/12/19 14/8/19 21/1/20 ‐19.5 days
367 Connection to nearest LV point 11 days 2/12/19 14/12/19 31/12/19 13/1/20 ‐19.5 days ‐23.9 days
368 Inspection and Testing 7 days 14/12/19 23/12/19 13/1/20 21/1/20 ‐19.5 days ‐23.9 days
369 Street lighting 98.5 days 8/7/19 2/11/19 14/8/19 2/12/19 ‐19.5 days
370 Junction Tun Perak ‐ Junction Masjid Ind28 days 8/7/19 9/8/19 14/8/19 18/9/19 ‐5 days
371 Cabling works 14 days 8/7/19 23/7/19 14/8/19 30/8/19 ‐5 days ‐31.4 days
372 Installation of street lighting &  14 days 24/7/19 9/8/19 30/8/19 18/9/19 ‐5 days ‐31.4 days
landscape lighting
373 Junction Masjid India ‐ Junction Lorong  28 days 19/8/19 21/9/19 26/9/19 29/10/19 ‐12 days
TAR
374 Cabling works 14 days 19/8/19 4/9/19 26/9/19 12/10/19 ‐12 days ‐31.4 days
375 Installation of street lighting &  14 days 5/9/19 21/9/19 12/10/19 29/10/19 ‐12 days ‐31.4 days
landscape lighting
376 Junction Lorong TAR ‐ Jln TAR 28 days 1/10/19 2/11/19 29/10/19 2/12/19 ‐19.5 days
377 Cabling works 14 days 1/10/19 17/10/19 29/10/19 15/11/19 ‐19.5 days ‐23.9 days
378 Installation of street lighting &  14 days 17/10/19 2/11/19 15/11/19 2/12/19 ‐19.5 days ‐23.9 days
landscape lighting
379 Street Lighting Feeder Pillar  24 days 2/11/19 2/12/19 2/12/19 31/12/19 ‐19.5 days
380 Installation of feeder pillar 14 days 2/11/19 20/11/19 2/12/19 18/12/19 ‐19.5 days ‐23.9 days
381 Cabling works 8 days 20/11/19 29/11/19 18/12/19 28/12/19 ‐19.5 days ‐23.9 days
382 Earthing 2 days 29/11/19 2/12/19 28/12/19 31/12/19 ‐19.5 days ‐23.9 days
395 Bunus area 711.4 days 13/7/17 25/11/19 13/7/17 25/11/19 4.6 days
485 Ancillary Buildings 643 days 11/10/17 4/12/19 11/10/17 11/1/20 ‐4 days
586 PACKAGE 1C 599.75 days 1/9/17 3/9/19 1/9/17 3/9/19 73.25 days