ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date

Before 31th August


Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
UOL PAKPATTAN
PAKPATTA CAMPUS, ADMIN BLOCK 225d -13d 0d 01-Feb-2017 A 15-Sep-2017

5d 0d 01-Feb-2017 A 05-Feb-2017 A 05-Feb-2017 A, Preliminary Work


Preliminary Work
Wo
A1000 Project Start 0d 01-Feb-2017 A 01-Feb-2017 A Project Start
A1010 Issuance of Project 1d 01-Feb-2017 A 01-Feb-2017 A Issuance of Project
A1020 Mobilization of Contractor 1d 02-Feb-2017 A 02-Feb-2017 A Mobilization of Contractor
A1030 Initial Survey 1d 03-Feb-2017 A 03-Feb-2017 A Initial Survey
A1040 Clearance of Site 1d 04-Feb-2017 A 04-Feb-2017 A Clearance of Site
A1050 Issuance of Drawings 1d 05-Feb-2017 A 05-Feb-2017 A Issuance of Drawings
181d 24d 0d 08-Feb-2017 A 08-Aug-2017 08-Aug-2017
Structural Work
Sub Structural W
Work 61d -13d 0d 08-Feb-2017 A 09-Apr-2017 09-Apr-2017, Sub Structural Work
Earth Work 18d 0d 08-Feb-2017 A 25-Feb-2017 A 25-Feb-2017 A, Earth Work
A1060 Layout for Excavation 1d 08-Feb-2017 A 08-Feb-2017 A Layout for Excavation
A1070 Excavation (Foundation, Trenches) 15d 09-Feb-2017 A 23-Feb-2017 A Excavation (Foundation, Trenches)
A1080 Trimming and Levelling of Trenches 15d 10-Feb-2017 A 24-Feb-2017 A Trimming and Levelling of Trenches
A1090 Termite control Treatment 15d 11-Feb-2017 A 25-Feb-2017 A Termite control Treatment Updated # 1
Foundation Work
Wo 57d -13d 0d 12-Feb-2017 A 09-Apr-2017 09-Apr-2017, Foundation Work on 25/2/2017
A1095 Sand Filling in Foundation 15d 12-Feb-2017 A 26-Feb-2017 A Sand Filling in Foundation
Laying of 4" PCC (1:4:8) Work
Update # 2 on
A1100 Laying of 4" PCC (1:4:8) Work 15d 13-Feb-2017 A 27-Feb-2017 A
1/3/2017
A1110 Steel Fixing of Sloped Isolated Footing 20d -13d 0d 01-Mar-2017 20-Mar-2017 Steel Fixing of Sloped Isolated Footing
A1120 Shuttering Work of Footing 20d -13d 0d 02-Mar-2017 21-Mar-2017 Shuttering Work of Footing
A1130 Pouring of Concrete (Footing) 20d -13d 0d 03-Mar-2017 22-Mar-2017 Pouring of Concrete (Footing)
A1140 Steel Fixing of Colume up to F.F.L 20d -13d 0d 03-Mar-2017 22-Mar-2017 Steel Fixing of Colume up to F.F.L
A1145 Shuttering of Colume up to F.F.L 20d -13d 0d 04-Mar-2017 23-Mar-2017 Shuttering of Colume up to F.F.L
A1150 Pouring of Concrete in Colume up to F.F.L 20d -13d 0d 05-Mar-2017 24-Mar-2017 Pouring of Concrete in Colume up to F.F.L
A1160 Steel Fixing of Plinth Beam 20d -13d 0d 06-Mar-2017 25-Mar-2017 Steel Fixing of Plinth Beam
A1170 Shuttering of Plinth Beam 20d -13d 0d 07-Mar-2017 26-Mar-2017 Shuttering of Plinth Beam
A1180 Pouring of Concrete in Plinth Beam 20d -13d 0d 08-Mar-2017 27-Mar-2017 Pouring of Concrete in Plinth Beam
A1190 DPC Work 5d -13d 0d 25-Mar-2017 29-Mar-2017 DPC Work
A1200 Back Filling and Compaction 12d -13d 0d 27-Mar-2017 07-Apr-2017 Back Filling and Compaction
A1205 Kassu Filling 12d -13d 0d 29-Mar-2017 09-Apr-2017 Kassu Filling

Super Structura
Structural Work 129d 24d 0d 01-Apr-2017 08-Aug-2017 08-Aug-2017
Ground Floor 65d 88d 0d 01-Apr-2017 05-Jun-2017 05-Jun-2017, Ground Floor
Column Work 12d -13d 0d 01-Apr-2017 12-Apr-2017 12-Apr-2017, Column Work
A1210 Steel Fixing of Column (G.F) 10d -13d 0d 01-Apr-2017 10-Apr-2017 Steel Fixing of Column (G.F)
A1220 Shuttering of Column (G.F) 10d -13d 0d 02-Apr-2017 11-Apr-2017 Shuttering of Column (G.F)
A1230 Pouring of Concrete of Column (G.F) 10d -13d 0d 03-Apr-2017 12-Apr-2017 Pouring of Concrete of Column (G.F)
Beam and Slab
S Work 27d -13d 0d 04-Apr-2017 30-Apr-2017 30-Apr-2017, Beam and Slab Work
A1240 Bottoms of Beam (G.F) 10d -13d 0d 04-Apr-2017 13-Apr-2017 Bottoms of Beam (G.F)
A1250 Steel Fixing of Beams (G.F) 10d -13d 0d 06-Apr-2017 15-Apr-2017 Steel Fixing of Beams (G.F)
A1260 Shuttering of Beams (G.F) 10d -13d 0d 11-Apr-2017 20-Apr-2017 Shuttering of Beams (G.F)
A1270 Shuttering of Slab (G.F) 10d -13d 0d 16-Apr-2017 25-Apr-2017 Shuttering of Slab (G.F)
A1280 Steel Fixing of Slab (G.F) 5d -13d 0d 24-Apr-2017 28-Apr-2017 Steel Fixing of Slab (G.F)
A1290 Electrical Conduiting (G.F) 2d -13d 0d 28-Apr-2017 29-Apr-2017 Electrical Conduiting (G.F)

Actual Level of Effort Remaining Work Milestone Page 1 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
A1300 Pouring of Concrete of Slab (G.F) 1d -13d 0d 30-Apr-2017 30-Apr-2017 Pouring of Concrete of Slab (G.F)
Stairs Work 11d 102d 0d 12-May-2017 22-May-2017 22-May-2017, Stairs Work
A2620 Shuttering of the Stairs (G.F) 10d 102d 0d 12-May-2017 21-May-2017 Shuttering of the Stairs (G.F)
A2630 Steel fixing of the Stairs (G.F) 10d 102d 0d 12-May-2017 21-May-2017 Steel fixing of the Stairs (G.F)
A2640 Pouring of the concrete in Stairs (G.F) 1d 102d 115d 22-May-2017 22-May-2017 Pouring of the concrete in Stairs (G.F)
Masonary Work
W 20d 88d 0d 17-May-2017 05-Jun-2017 05-Jun-2017, Masonary Work
A1660 Masonary Work 20d 45d 0d 17-May-2017 05-Jun-2017 Masonary Work
A1670 Lintel Work 8d 90d 103d 27-May-2017 03-Jun-2017 Lintel Work
First Floor 66d 55d 0d 04-May-2017 08-Jul-2017 08-Jul-2017, First Floor
Column Work 12d -13d 0d 04-May-2017 15-May-2017 15-May-2017, Column Work
A1310 Steel Fixing of Column (F.F) 10d -13d 0d 04-May-2017 13-May-2017 Steel Fixing of Column (F.F)
A1320 Shuttering of Column (F.F) 10d -13d 0d 05-May-2017 14-May-2017 Shuttering of Column (F.F)
A1330 Pouring of Concrete of Column (F.F) 10d -13d 0d 06-May-2017 15-May-2017 Pouring of Concrete of Column (F.F)
Beam and Slab
S Work 27d -13d 0d 08-May-2017 03-Jun-2017 03-Jun-2017, Beam and Slab Work
A1400 Bottoms of Beam (F.F) 10d -13d 0d 08-May-2017 17-May-2017 Bottoms of Beam (F.F)
A1410 Steel Fixing of Beams (F.F) 10d -13d 0d 10-May-2017 19-May-2017 Steel Fixing of Beams (F.F)
A1420 Shuttering of Beams (F.F) 10d -13d 0d 15-May-2017 24-May-2017 Shuttering of Beams (F.F)
A1430 Shuttering of Slab (F.F) 10d -13d 0d 20-May-2017 29-May-2017 Shuttering of Slab (F.F)
A1440 Steel Fixing of Slab (F.F) 5d -13d 0d 28-May-2017 01-Jun-2017 Steel Fixing of Slab (F.F)
A1450 Electrical Conduiting (F.F) 2d -13d 0d 01-Jun-2017 02-Jun-2017 Electrical Conduiting (F.F)
A1460 Pouring of Concrete of Slab (F.F) 1d -13d 0d 03-Jun-2017 03-Jun-2017 Pouring of Concrete of Slab (F.F)
Stairs Work 12d 68d 0d 14-Jun-2017 25-Jun-2017 25-Jun-2017, Stairs Work
A2560 Shuttering of the Stairs (F.F) 10d 68d 0d 14-Jun-2017 23-Jun-2017 Shuttering of the Stairs (F.F)
A2570 Steel fixing of the Stairs (F.F) 10d 68d 0d 15-Jun-2017 24-Jun-2017 Steel fixing of the Stairs (F.F)
A2580 Pouring of the concrete in Stairs (F.F) 1d 68d 81d 25-Jun-2017 25-Jun-2017 Pouring of the concrete in Stairs (F.F)
Masonary Work
W 20d 55d 0d 19-Jun-2017 08-Jul-2017 08-Jul-2017, Masonary Work
A1680 Masonary Work (F.F) 20d 12d 0d 19-Jun-2017 08-Jul-2017 Masonary Work (F.F)
A1690 Lintel Work (F.F) 8d 57d 70d 29-Jun-2017 06-Jul-2017 Lintel Work (F.F)
2nd Floor 64d 24d 0d 06-Jun-2017 08-Aug-2017 08-Aug-2017
Column Work 12d -13d 0d 06-Jun-2017 17-Jun-2017 17-Jun-2017, Column Work
A1340 Steel Fixing of Column (S.F) 10d -13d 0d 06-Jun-2017 15-Jun-2017 Steel Fixing of Column (S.F)
A1350 Shuttering of Column (S.F) 10d -13d 0d 07-Jun-2017 16-Jun-2017 Shuttering of Column (S.F)
A1360 Pouring of Concrete of Column (S.F) 10d -13d 0d 08-Jun-2017 17-Jun-2017 Pouring of Concrete of Column (S.F)
Beam and Slab
S Work 27d -13d 0d 10-Jun-2017 06-Jul-2017 06-Jul-2017, Beam and Slab Work
A1470 Bottoms of Beam (S.F) 10d -13d 0d 10-Jun-2017 19-Jun-2017 Bottoms of Beam (S.F)
A1480 Steel Fixing of Beams (S.F) 10d -13d 0d 12-Jun-2017 21-Jun-2017 Steel Fixing of Beams (S.F)
A1490 Shuttering of Beams (S.F) 10d -13d 0d 17-Jun-2017 26-Jun-2017 Shuttering of Beams (S.F)
A1500 Shuttering of Slab (S.F) 10d -13d 0d 22-Jun-2017 01-Jul-2017 Shuttering of Slab (S.F)
A1510 Steel Fixing of Slab (S.F) 5d -13d 0d 30-Jun-2017 04-Jul-2017 Steel Fixing of Slab (S.F)
A1520 Electrical Conduiting (S.F) 2d -13d 0d 04-Jul-2017 05-Jul-2017 Electrical Conduiting (S.F)
A1530 Pouring of Concrete of Slab (S.F) 1d -13d 0d 06-Jul-2017 06-Jul-2017 Pouring of Concrete of Slab (S.F)
Stairs Work 11d 36d 0d 17-Jul-2017 27-Jul-2017 27-Jul-2017, Stairs W
A2590 Shuttering of the Stairs (S.F) 10d 36d 0d 17-Jul-2017 26-Jul-2017 Shuttering of the Stair
A2600 Steel fixing of the Stairs (S.F) 10d 36d 0d 17-Jul-2017 26-Jul-2017 Steel fixing of the Sta

Actual Level of Effort Remaining Work Milestone Page 2 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
A2610 Pouring of the concrete in Stairs (S.F) 1d 36d 49d 27-Jul-2017 27-Jul-2017 Pouring of the concr
Masonary Work
W 18d 24d 0d 22-Jul-2017 08-Aug-2017 08-Aug-2017
A1700 Masonary Work (2nd. Floor) 17d -13d 0d 22-Jul-2017 07-Aug-2017 Masonary Wo
A1710 Lintel Work (2nd. Floor) 8d 24d 37d 01-Aug-2017 08-Aug-2017 Lintel Work (
Top Floor 26d 31d 0d 07-Jul-2017 01-Aug-2017 01-Aug-2017, To
Mumty Work 26d 31d 0d 07-Jul-2017 01-Aug-2017 01-Aug-2017, Mu
A1370 Steel Fixing of Column (T.F) 5d 0d 0d 07-Jul-2017 11-Jul-2017 Steel Fixing of Column (T.F)
A1380 Shuttering of Column (T.F) 5d 27d 0d 08-Jul-2017 12-Jul-2017 Shuttering of Column (T.F)
A1390 Pouring of Concrete of Column (T.F) 5d 27d 0d 09-Jul-2017 13-Jul-2017 Pouring of Concrete of Colum
A1540 Slab Work (T.F) 1d 27d 0d 14-Jul-2017 14-Jul-2017 Slab Work (T.F)
A1810 Masonary Work 3d 27d 0d 30-Jul-2017 01-Aug-2017 Masonary Work
A1820 Lintel work 1d 31d 44d 01-Aug-2017 01-Aug-2017 Lintel work
Parapeth Wall
Wa Work 8d 0d 0d 07-Jul-2017 14-Jul-2017 14-Jul-2017, Parapeth Wall W
A1720 Parapeth Wall Work 8d 0d 0d 07-Jul-2017 14-Jul-2017 Parapeth Wall Work
Water Proofing
Proof Work 5d 44d 0d 15-Jul-2017 19-Jul-2017 19-Jul-2017, Water Proofi
A1550 Water Proofing Work (T.F) 5d 44d 57d 15-Jul-2017 19-Jul-2017 Water Proofing Work (T.F

Architectural W
Wrok (Civil) 100d -12d 0d 06-Jun-2017 14-Sep-2017

Ground Floor 78d 10d 0d 06-Jun-2017 22-Aug-2017 22-A


Plaster /Guttka Work 74d 10d 0d 10-Jun-2017 22-Aug-2017 22-A
A1620 Ceiling Plaster Work 10d 45d 0d 10-Jun-2017 19-Jun-2017 Ceiling Plaster Work
A1630 Internal Plaster Work 15d 45d 0d 15-Jun-2017 29-Jun-2017 Internal Plaster Work
A1640 External Plaster Work 10d 0d 0d 13-Aug-2017 22-Aug-2017 Exte
A1650 Guttca Work 5d 24d 37d 04-Aug-2017 08-Aug-2017 Guttca Work
Internal Electri
Electrical Work 40d 48d 0d 06-Jun-2017 15-Jul-2017 15-Jul-2017, Internal Electri
A1560 Conduiting Work 5d 45d 0d 06-Jun-2017 10-Jun-2017 Conduiting Work
A1570 Wiring Work 5d 63d 76d 26-Jun-2017 30-Jun-2017 Wiring Work
A1580 Switch Boards and Sockets 2d 48d 61d 14-Jul-2017 15-Jul-2017 Switch Boards and Sockets
Internal Water Supply Work 14d 62d 0d 06-Jun-2017 19-Jun-2017 19-Jun-2017, Internal Water Supply Work
A1590 PPRC Piping 10d 62d 0d 06-Jun-2017 15-Jun-2017 PPRC Piping
A1600 Galvanized Iron Piping 10d 62d 0d 08-Jun-2017 17-Jun-2017 Galvanized Iron Piping
A1610 UPVC Piping 10d 62d 0d 10-Jun-2017 19-Jun-2017 UPVC Piping
Flooring Work 17d 62d 0d 15-Jun-2017 01-Jul-2017 01-Jul-2017, Flooring Work
A1730 Laying of Brick Ballast 15d 62d 0d 15-Jun-2017 29-Jun-2017 Laying of Brick Ballast
A1740 PCC Work 15d 62d 75d 17-Jun-2017 01-Jul-2017 PCC Work

First Floor 40d 15d 0d 09-Jul-2017 17-Aug-2017 17-Aug


Plaster /Guttka Work 31d 15d 0d 13-Jul-2017 12-Aug-2017 12-Aug-20
A2480 Ceiling Plaster Work 10d 12d 0d 13-Jul-2017 22-Jul-2017 Ceiling Plaster Work
A2490 Internal Plaster Work 15d 12d 0d 18-Jul-2017 01-Aug-2017 Internal Plaster W
A2500 External Plaster Work 10d 0d 0d 03-Aug-2017 12-Aug-2017 External P
A2510 Guttca Work 5d 24d 0d 30-Jul-2017 03-Aug-2017 Guttca Work
Internal Electri
Electrical Work 40d 15d 0d 09-Jul-2017 17-Aug-2017 17-Aug
A1930 Conduiting Work 5d 12d 0d 09-Jul-2017 13-Jul-2017 Conduiting Work
A1940 Wiring Work 5d 30d 43d 29-Jul-2017 02-Aug-2017 Wiring Work
A1950 Switch Boards and Sockets 2d 15d 28d 16-Aug-2017 17-Aug-2017 Switch

Actual Level of Effort Remaining Work Milestone Page 3 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
Internal Water Supply Work 12d 31d 0d 09-Jul-2017 20-Jul-2017 20-Jul-2017, Internal Wat
A2020 PPRC Piping 10d 31d 0d 09-Jul-2017 18-Jul-2017 PPRC Piping
A2030 Galvanized Iron Piping 10d 31d 0d 10-Jul-2017 19-Jul-2017 Galvanized Iron Piping
A2040 UPVC Piping 10d 31d 0d 11-Jul-2017 20-Jul-2017 UPVC Piping
Flooring Work 17d 31d 0d 16-Jul-2017 01-Aug-2017 01-Aug-2017, Flo
A1750 Laying of Brick Ballast 15d 31d 0d 16-Jul-2017 30-Jul-2017 Laying of Brick Ba
A1760 PCC Work 15d 31d 44d 18-Jul-2017 01-Aug-2017 PCC Work

2nd Floor 52d -12d 0d 24-Jul-2017 14-Sep-2017


Plaster /Guttka Work 37d -7d 0d 24-Jul-2017 29-Aug-2017
A2520 Ceiling Plaster Work 10d -13d 0d 12-Aug-2017 21-Aug-2017 Ceilin
A2530 Internal Plaster Work 13d -13d 0d 17-Aug-2017 29-Aug-2017
A2540 External Plaster Work 10d 0d 0d 24-Jul-2017 02-Aug-2017 External Plaster W
A2550 Guttca Work 5d 24d 0d 25-Jul-2017 29-Jul-2017 Guttca Work
Internal Electri
Electrical Work 37d -12d 0d 08-Aug-2017 14-Sep-2017
A1960 Conduiting Work 4d -13d 0d 08-Aug-2017 11-Aug-2017 Conduiting
A1970 Wiring Work 5d 2d 0d 26-Aug-2017 30-Aug-2017
A1980 Switch Boards and Sockets 2d -12d 1d 13-Sep-2017 14-Sep-2017
Internal Water Supply Work 10d 2d 0d 09-Aug-2017 18-Aug-2017 18-Aug
A2050 PPRC Piping 10d 2d 0d 09-Aug-2017 18-Aug-2017 PPRC P
A2060 Galvanized Iron Piping 10d 2d 0d 09-Aug-2017 18-Aug-2017 Galvan
A2070 UPVC Piping 10d 2d 0d 09-Aug-2017 18-Aug-2017 UPVC
Flooring Work 17d 2d 0d 14-Aug-2017 30-Aug-2017
A1770 Laying of Brick Ballast 15d 2d 0d 14-Aug-2017 28-Aug-2017 L
A1780 PCC Work 15d 2d 15d 16-Aug-2017 30-Aug-2017
Top Floor 46d -5d 0d 23-Jul-2017 07-Sep-2017
Plaster /Guttka Work 14d 27d 0d 23-Jul-2017 05-Aug-2017 05-Aug-2017,
A1895 Ceiling Plaster Work (Mumty) 1d 27d 0d 04-Aug-2017 04-Aug-2017 Ceiling Plaster W
A1900 Internal Plaster Work 1d 27d 40d 05-Aug-2017 05-Aug-2017 Internal Plaster
A1910 External Plaster Work 1d 0d 0d 23-Jul-2017 23-Jul-2017 External Plaster Work
A1920 Guttca Work 2d 24d 0d 23-Jul-2017 24-Jul-2017 Guttca Work
Internal Electri
Electrical Work 36d -5d 0d 02-Aug-2017 07-Sep-2017
A1990 Conduiting Work 2d 27d 0d 02-Aug-2017 03-Aug-2017 Conduiting Work
A2000 Wiring Work 2d 2d 15d 29-Aug-2017 30-Aug-2017
A2010 Switch Boards and Sockets 2d -5d 8d 06-Sep-2017 07-Sep-2017
Flooring Work 3d 16d 0d 14-Aug-2017 16-Aug-2017 16-Aug-
A1790 Laying of Brick Ballast 2d 16d 0d 14-Aug-2017 15-Aug-2017 Laying o
A1800 PCC Work 2d 16d 29d 15-Aug-2017 16-Aug-2017 PCC Wo

Architectural Work
W (Finishes) 76d -12d 0d 30-Jun-2017 14-Sep-2017

Ground Floor 19d 45d 0d 30-Jun-2017 18-Jul-2017 18-Jul-2017, Ground Floo


A2200 Fixing of Wall and Floor Tiles 5d 45d 0d 30-Jun-2017 04-Jul-2017 Fixing of Wall and Floor Tiles
A2210 Fixing of Door and Marble Sills 5d 45d 0d 05-Jul-2017 09-Jul-2017 Fixing of Door and Marble Sills
A2220 Paint Work (2 Coats) 7d 48d 0d 07-Jul-2017 13-Jul-2017 Paint Work (2 Coats)
A2225 Aluminium Work 2d 45d 0d 10-Jul-2017 11-Jul-2017 Aluminium Work
A2230 Fixing of Doors and Windows 7d 45d 58d 12-Jul-2017 18-Jul-2017 Fixing of Doors and Windo

Actual Level of Effort Remaining Work Milestone Page 4 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
A2240 Fixing of Hand Railing 2d 55d 68d 07-Jul-2017 08-Jul-2017 Fixing of Hand Railing
A2250 Grinding and Polishing 10d 49d 62d 05-Jul-2017 14-Jul-2017 Grinding and Polishing

First Floor 19d 12d 0d 02-Aug-2017 20-Aug-2017 20-Au


A2150 Fixing of Wall and Floor Tiles 5d 12d 0d 02-Aug-2017 06-Aug-2017 Fixing of Wall
A2160 Fixing of Door and Marble Sills 5d 12d 0d 07-Aug-2017 11-Aug-2017 Fixing of D
A2165 Paint Work (2 Coats) 7d 15d 0d 09-Aug-2017 15-Aug-2017 Paint Wo
A2167 Aluminium Work 2d 12d 0d 12-Aug-2017 13-Aug-2017 Aluminium
A2170 Fixing of Doors and Windows 7d 12d 25d 14-Aug-2017 20-Aug-2017 Fixing
A2180 Fixing of Hand Railing 2d 22d 35d 09-Aug-2017 10-Aug-2017 Fixing of H
A2190 Grinding and Polishing 10d 16d 29d 07-Aug-2017 16-Aug-2017 Grinding

2nd Floor 15d -12d 0d 30-Aug-2017 14-Sep-2017


A2260 Fixing of Wall and Floor Tiles 5d -13d 0d 30-Aug-2017 04-Sep-2017
A2270 Fixing of Door and Marble Sills 5d -13d 0d 05-Sep-2017 09-Sep-2017
A2280 Paint Work (2 Coats) 6d -12d 0d 07-Sep-2017 12-Sep-2017
A2285 Aluminium Work 2d -13d 0d 10-Sep-2017 11-Sep-2017
A2290 Fixing of Doors and Windows 3d -13d 0d 12-Sep-2017 14-Sep-2017
A2300 Fixing of Hand Railing 2d -6d 7d 07-Sep-2017 08-Sep-2017
A2310 Grinding and Polishing 8d -10d 3d 05-Sep-2017 12-Sep-2017
Top Floor 6d -6d 0d 02-Sep-2017 08-Sep-2017
A2320 Fixing of Wall and Floor Tiles 1d -6d 0d 02-Sep-2017 02-Sep-2017
A2330 Fixing of Door and Marble Sills 1d -6d 0d 04-Sep-2017 04-Sep-2017
A2340 Paint Work (2 Coats) 2d -5d 0d 04-Sep-2017 05-Sep-2017
A2345 Aluminium Work 1d -6d 0d 05-Sep-2017 05-Sep-2017
A2350 Fixing of Doors and Windows 1d -6d 0d 06-Sep-2017 06-Sep-2017
A2360 Grinding and Polishing 2d -6d 7d 07-Sep-2017 08-Sep-2017

External Servic
Services 49d 0d 0d 15-Jul-2017 01-Sep-2017

A2400 External Electrical Work 8d 0d 0d 15-Jul-2017 22-Jul-2017 External Electrical Work


A2410 External Water Supply Work 8d 7d 0d 30-Jul-2017 06-Aug-2017 External Water
A2420 DWARF wall and External Drainage 12d 7d 20d 14-Aug-2017 25-Aug-2017 DW
A2440 Weather Resistant Paint 10d 0d 13d 23-Aug-2017 01-Sep-2017
22d 9d 0d 01-Aug-2017 22-Aug-2017 22-A
Final Phase
A2370 Internal Rectification Works 12d 9d 0d 01-Aug-2017* 12-Aug-2017 Internal Re
A2380 External Rectification Works 10d 9d 0d 06-Aug-2017 15-Aug-2017 External
A2390 Paint Final Coat 10d 9d 22d 13-Aug-2017 22-Aug-2017 Pain

Project Hand O
Over 1d -13d 0d 15-Sep-2017 15-Sep-2017

A2450 Project Handover 1d -13d 0d 15-Sep-2017 15-Sep-2017


A2460 Contractor Mobilization 1d -13d 0d 15-Sep-2017 15-Sep-2017
A2470 Project Completion 0d -12d 1d 15-Sep-2017 15-Sep-2017

Actual Level of Effort Remaining Work Milestone Page 5 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed