Super Structura
Structural Work 129d 24d 0d 01-Apr-2017 08-Aug-2017 08-Aug-2017
Ground Floor 65d 88d 0d 01-Apr-2017 05-Jun-2017 05-Jun-2017, Ground Floor
Column Work 12d -13d 0d 01-Apr-2017 12-Apr-2017 12-Apr-2017, Column Work
A1210 Steel Fixing of Column (G.F) 10d -13d 0d 01-Apr-2017 10-Apr-2017 Steel Fixing of Column (G.F)
A1220 Shuttering of Column (G.F) 10d -13d 0d 02-Apr-2017 11-Apr-2017 Shuttering of Column (G.F)
A1230 Pouring of Concrete of Column (G.F) 10d -13d 0d 03-Apr-2017 12-Apr-2017 Pouring of Concrete of Column (G.F)
Beam and Slab
S Work 27d -13d 0d 04-Apr-2017 30-Apr-2017 30-Apr-2017, Beam and Slab Work
A1240 Bottoms of Beam (G.F) 10d -13d 0d 04-Apr-2017 13-Apr-2017 Bottoms of Beam (G.F)
A1250 Steel Fixing of Beams (G.F) 10d -13d 0d 06-Apr-2017 15-Apr-2017 Steel Fixing of Beams (G.F)
A1260 Shuttering of Beams (G.F) 10d -13d 0d 11-Apr-2017 20-Apr-2017 Shuttering of Beams (G.F)
A1270 Shuttering of Slab (G.F) 10d -13d 0d 16-Apr-2017 25-Apr-2017 Shuttering of Slab (G.F)
A1280 Steel Fixing of Slab (G.F) 5d -13d 0d 24-Apr-2017 28-Apr-2017 Steel Fixing of Slab (G.F)
A1290 Electrical Conduiting (G.F) 2d -13d 0d 28-Apr-2017 29-Apr-2017 Electrical Conduiting (G.F)
Actual Level of Effort Remaining Work Milestone Page 1 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
A1300 Pouring of Concrete of Slab (G.F) 1d -13d 0d 30-Apr-2017 30-Apr-2017 Pouring of Concrete of Slab (G.F)
Stairs Work 11d 102d 0d 12-May-2017 22-May-2017 22-May-2017, Stairs Work
A2620 Shuttering of the Stairs (G.F) 10d 102d 0d 12-May-2017 21-May-2017 Shuttering of the Stairs (G.F)
A2630 Steel fixing of the Stairs (G.F) 10d 102d 0d 12-May-2017 21-May-2017 Steel fixing of the Stairs (G.F)
A2640 Pouring of the concrete in Stairs (G.F) 1d 102d 115d 22-May-2017 22-May-2017 Pouring of the concrete in Stairs (G.F)
Masonary Work
W 20d 88d 0d 17-May-2017 05-Jun-2017 05-Jun-2017, Masonary Work
A1660 Masonary Work 20d 45d 0d 17-May-2017 05-Jun-2017 Masonary Work
A1670 Lintel Work 8d 90d 103d 27-May-2017 03-Jun-2017 Lintel Work
First Floor 66d 55d 0d 04-May-2017 08-Jul-2017 08-Jul-2017, First Floor
Column Work 12d -13d 0d 04-May-2017 15-May-2017 15-May-2017, Column Work
A1310 Steel Fixing of Column (F.F) 10d -13d 0d 04-May-2017 13-May-2017 Steel Fixing of Column (F.F)
A1320 Shuttering of Column (F.F) 10d -13d 0d 05-May-2017 14-May-2017 Shuttering of Column (F.F)
A1330 Pouring of Concrete of Column (F.F) 10d -13d 0d 06-May-2017 15-May-2017 Pouring of Concrete of Column (F.F)
Beam and Slab
S Work 27d -13d 0d 08-May-2017 03-Jun-2017 03-Jun-2017, Beam and Slab Work
A1400 Bottoms of Beam (F.F) 10d -13d 0d 08-May-2017 17-May-2017 Bottoms of Beam (F.F)
A1410 Steel Fixing of Beams (F.F) 10d -13d 0d 10-May-2017 19-May-2017 Steel Fixing of Beams (F.F)
A1420 Shuttering of Beams (F.F) 10d -13d 0d 15-May-2017 24-May-2017 Shuttering of Beams (F.F)
A1430 Shuttering of Slab (F.F) 10d -13d 0d 20-May-2017 29-May-2017 Shuttering of Slab (F.F)
A1440 Steel Fixing of Slab (F.F) 5d -13d 0d 28-May-2017 01-Jun-2017 Steel Fixing of Slab (F.F)
A1450 Electrical Conduiting (F.F) 2d -13d 0d 01-Jun-2017 02-Jun-2017 Electrical Conduiting (F.F)
A1460 Pouring of Concrete of Slab (F.F) 1d -13d 0d 03-Jun-2017 03-Jun-2017 Pouring of Concrete of Slab (F.F)
Stairs Work 12d 68d 0d 14-Jun-2017 25-Jun-2017 25-Jun-2017, Stairs Work
A2560 Shuttering of the Stairs (F.F) 10d 68d 0d 14-Jun-2017 23-Jun-2017 Shuttering of the Stairs (F.F)
A2570 Steel fixing of the Stairs (F.F) 10d 68d 0d 15-Jun-2017 24-Jun-2017 Steel fixing of the Stairs (F.F)
A2580 Pouring of the concrete in Stairs (F.F) 1d 68d 81d 25-Jun-2017 25-Jun-2017 Pouring of the concrete in Stairs (F.F)
Masonary Work
W 20d 55d 0d 19-Jun-2017 08-Jul-2017 08-Jul-2017, Masonary Work
A1680 Masonary Work (F.F) 20d 12d 0d 19-Jun-2017 08-Jul-2017 Masonary Work (F.F)
A1690 Lintel Work (F.F) 8d 57d 70d 29-Jun-2017 06-Jul-2017 Lintel Work (F.F)
2nd Floor 64d 24d 0d 06-Jun-2017 08-Aug-2017 08-Aug-2017
Column Work 12d -13d 0d 06-Jun-2017 17-Jun-2017 17-Jun-2017, Column Work
A1340 Steel Fixing of Column (S.F) 10d -13d 0d 06-Jun-2017 15-Jun-2017 Steel Fixing of Column (S.F)
A1350 Shuttering of Column (S.F) 10d -13d 0d 07-Jun-2017 16-Jun-2017 Shuttering of Column (S.F)
A1360 Pouring of Concrete of Column (S.F) 10d -13d 0d 08-Jun-2017 17-Jun-2017 Pouring of Concrete of Column (S.F)
Beam and Slab
S Work 27d -13d 0d 10-Jun-2017 06-Jul-2017 06-Jul-2017, Beam and Slab Work
A1470 Bottoms of Beam (S.F) 10d -13d 0d 10-Jun-2017 19-Jun-2017 Bottoms of Beam (S.F)
A1480 Steel Fixing of Beams (S.F) 10d -13d 0d 12-Jun-2017 21-Jun-2017 Steel Fixing of Beams (S.F)
A1490 Shuttering of Beams (S.F) 10d -13d 0d 17-Jun-2017 26-Jun-2017 Shuttering of Beams (S.F)
A1500 Shuttering of Slab (S.F) 10d -13d 0d 22-Jun-2017 01-Jul-2017 Shuttering of Slab (S.F)
A1510 Steel Fixing of Slab (S.F) 5d -13d 0d 30-Jun-2017 04-Jul-2017 Steel Fixing of Slab (S.F)
A1520 Electrical Conduiting (S.F) 2d -13d 0d 04-Jul-2017 05-Jul-2017 Electrical Conduiting (S.F)
A1530 Pouring of Concrete of Slab (S.F) 1d -13d 0d 06-Jul-2017 06-Jul-2017 Pouring of Concrete of Slab (S.F)
Stairs Work 11d 36d 0d 17-Jul-2017 27-Jul-2017 27-Jul-2017, Stairs W
A2590 Shuttering of the Stairs (S.F) 10d 36d 0d 17-Jul-2017 26-Jul-2017 Shuttering of the Stair
A2600 Steel fixing of the Stairs (S.F) 10d 36d 0d 17-Jul-2017 26-Jul-2017 Steel fixing of the Sta
Actual Level of Effort Remaining Work Milestone Page 2 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
A2610 Pouring of the concrete in Stairs (S.F) 1d 36d 49d 27-Jul-2017 27-Jul-2017 Pouring of the concr
Masonary Work
W 18d 24d 0d 22-Jul-2017 08-Aug-2017 08-Aug-2017
A1700 Masonary Work (2nd. Floor) 17d -13d 0d 22-Jul-2017 07-Aug-2017 Masonary Wo
A1710 Lintel Work (2nd. Floor) 8d 24d 37d 01-Aug-2017 08-Aug-2017 Lintel Work (
Top Floor 26d 31d 0d 07-Jul-2017 01-Aug-2017 01-Aug-2017, To
Mumty Work 26d 31d 0d 07-Jul-2017 01-Aug-2017 01-Aug-2017, Mu
A1370 Steel Fixing of Column (T.F) 5d 0d 0d 07-Jul-2017 11-Jul-2017 Steel Fixing of Column (T.F)
A1380 Shuttering of Column (T.F) 5d 27d 0d 08-Jul-2017 12-Jul-2017 Shuttering of Column (T.F)
A1390 Pouring of Concrete of Column (T.F) 5d 27d 0d 09-Jul-2017 13-Jul-2017 Pouring of Concrete of Colum
A1540 Slab Work (T.F) 1d 27d 0d 14-Jul-2017 14-Jul-2017 Slab Work (T.F)
A1810 Masonary Work 3d 27d 0d 30-Jul-2017 01-Aug-2017 Masonary Work
A1820 Lintel work 1d 31d 44d 01-Aug-2017 01-Aug-2017 Lintel work
Parapeth Wall
Wa Work 8d 0d 0d 07-Jul-2017 14-Jul-2017 14-Jul-2017, Parapeth Wall W
A1720 Parapeth Wall Work 8d 0d 0d 07-Jul-2017 14-Jul-2017 Parapeth Wall Work
Water Proofing
Proof Work 5d 44d 0d 15-Jul-2017 19-Jul-2017 19-Jul-2017, Water Proofi
A1550 Water Proofing Work (T.F) 5d 44d 57d 15-Jul-2017 19-Jul-2017 Water Proofing Work (T.F
Architectural W
Wrok (Civil) 100d -12d 0d 06-Jun-2017 14-Sep-2017
Actual Level of Effort Remaining Work Milestone Page 3 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
Internal Water Supply Work 12d 31d 0d 09-Jul-2017 20-Jul-2017 20-Jul-2017, Internal Wat
A2020 PPRC Piping 10d 31d 0d 09-Jul-2017 18-Jul-2017 PPRC Piping
A2030 Galvanized Iron Piping 10d 31d 0d 10-Jul-2017 19-Jul-2017 Galvanized Iron Piping
A2040 UPVC Piping 10d 31d 0d 11-Jul-2017 20-Jul-2017 UPVC Piping
Flooring Work 17d 31d 0d 16-Jul-2017 01-Aug-2017 01-Aug-2017, Flo
A1750 Laying of Brick Ballast 15d 31d 0d 16-Jul-2017 30-Jul-2017 Laying of Brick Ba
A1760 PCC Work 15d 31d 44d 18-Jul-2017 01-Aug-2017 PCC Work
Architectural Work
W (Finishes) 76d -12d 0d 30-Jun-2017 14-Sep-2017
Actual Level of Effort Remaining Work Milestone Page 4 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary
ATCON - THE CONSTRUCTION PROFFESIONALS UOL, PAKPATTAN CAMPUS, ADMIN BLOCK Project Completion Date
Before 31th August
Activity ID Activity Name Original Total Float Free Float Start Finish 2017
Duration February March April May June July August
2 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27
A2240 Fixing of Hand Railing 2d 55d 68d 07-Jul-2017 08-Jul-2017 Fixing of Hand Railing
A2250 Grinding and Polishing 10d 49d 62d 05-Jul-2017 14-Jul-2017 Grinding and Polishing
External Servic
Services 49d 0d 0d 15-Jul-2017 01-Sep-2017
Project Hand O
Over 1d -13d 0d 15-Sep-2017 15-Sep-2017
Actual Level of Effort Remaining Work Milestone Page 5 of 5 Prepared by: M.Asad Checked by: Faakhir Saeed
Actual Work Critical Remaining Work summary