WORK PROGRAMME CHART

IMPLEMENTATION SCHEDULE 2016 2017 2018


XX XX
Development of Integrated Check Post at
Dawki (Meghalaya) along Indo- Bangladesh
Border.
L.O.A.: RITES/AP/ICP DAWKI/2016/ 10159
Dated: 30/09/2016
Date of Commencement 15.10.2016
Completion Date as per agreement 14.10.2018
Revised Date of Completion

Revised Revised
Task Name Duration Unit Start Finish October November December January February March April May June July August September October November December January February March April May June July August September October
Start Finish

Topographical Survey work 70 Days 18.11.2016 27.01.2017 Completed


Demarking of Boundary wall & Building Locations 40 Days 18.12.2016 27.01.2017
Soil Bearing Capacity Testings 30 Days 18.12.2016 17.01.2017

Local Authorites Clearance Work 330 Days 18.10.2016 20.09.2017


Forest Clearance 18.10.2016 01.03.2017 Completed
Mine Clearance 18.10.2016 01.03.2017 Completed
HT & LT Line Shifting 18.10.2016 20.09.2017 20.09.2017
Water Supply Line Shifting 18.10.2016 20.09.2017 20.09.2017
40 mtr international border Issue
Diverted Drain & Culvert Work 180 Days 01.03.2017 01.09.2017 10.05.2017 01.12.2017
Excavation of Diverted Drain 01.03.2017 01.04.2017 10.05.2017 01.09.2017
P.C.C. work 03.03.2017 03.08.2017 28.05.2017 30.10.2017
Reinforcement Work 06.03.2017 26.08.2017 28.05.2017 26.11.2017
Centering & Shuttering work 06.03.2017 26.08.2017 06.06.2017 26.11.2017
RCC work 07.03.2017 01.09.2017 10.06.2017 01.12.2017
40 mtr international border Issue
Road Work 316 Days 05.03.2017 15.01.2018 05.03.2017 15.01.2018
Excavation/Formation cutting/Filling 05.03.2017 20.05.2017 05.03.2017 20.07.2017
Levelling Work 05.05.2017 05.06.2017 30.06.2017 05.08.2017
Preparation of subgrade 05.06.2017 05.08.2017 30.06.2017 05.08.2017
Laying of GSB 01.08.2017 25.08.2017 01.08.2017 25.08.2017
Laying of WMM 28.08.2017 30.09.2017 28.08.2017 30.09.2017
Laying of Paver Block 15.10.2017 15.01.2018 15.10.2017 15.01.2018

Paver Block 474 Days 01.03.2017 17.09.2018


Qoutation collection, Giving supply order of paver
01.03.2017 25.04.2017 Completed
block machine.
Mix design for paver block 10.03.2017 15.04.2017 15.06.2017 15.07.2017
Manufacture of Paver Block 15.04.2017 17.09.2018 15.07.2017 17.09.2018

Parking Area 540 Days 18.03.2017 17.09.2018


A) Cargo Area
Earth work 18.03.2017 18.06.2017 30.06.2017
Laying of GSB 18.06.2017 17.07.2017 15.07.2017 15.08.2017
Laying of WMM 18.07.2017 17.09.2017 15.08.2017 15.10.2017
Laying of Paver Block 18.12.2017 17.09.2018
B) PTB Area
Earth work 18.03.2017 18.04.2017 30.06.2017
Laying of GSB 18.04.2017 17.06.2017 15.08.2017 15.10.2017
Laying of WMM 18.06.2017 17.09.2017 15.10.2017 15.12.2017
Laying of Paver Block 18.12.2017 17.09.2018

External Water supply 360 Days 18.02.2017 17.03.2018


Boring of Borewell 18.02.2017 17.06.2017
Installtion of Pump etc. 18.04.2017 01.09.2017 18.06.2017 01.09.2017
UG Tank & Pump House 18.05.2017 17.03.2018 28.06.2017 17.03.2018
Location Not finalized, Drawing no available
Sewer work 180 Days 18.05.2017 17.11.2017 18.07.2017 17.01.2018
Civil work (Pipe Line) 18.05.2017 17.11.2017 18.07.2017 17.01.2018
40 mtr international border Issue
Sewage 360 Days 18.10.2017 17.09.2018
Civil work for STP 18.10.2017 17.12.2017
Installation of STP Equipments 18.05.2018 17.09.2018
40 mtr international border Issue
External Drainage & Water supply 510 Days 18.03.2017 17.08.2018 18.07.2017
Construction of Drainage & Water supply system 18.03.2017 17.08.2017 18.07.2017 17.09.2017
Construction & Provision of Covers 18.04.2017 17.08.2018 18.09.2017
40 mtr international border Issue
Construction of Boundary wall & Fencing 270 Days 28.02.2017 27.11.2017 10.06.2016 27.01.2018
Excavation of Foundation 28.02.2017 27.05.2017 15.06.2016 27.11.2017
Procurement of sleet Frame 18.03.2017 17.05.2017 18.06.2017 17.07.2017
RCC Retaining wall 18.03.2017 27.07.2017 18.06.2017 27.07.2017 Uncertain
Chain link Fence 18.04.2017 27.11.2017 18.07.2017 27.01.2018
40 mtr international border Issue
Construction of Passenger Terminal Building 468 Days 28.02.2017 10.06.2018 28.02.2017 10.06.2018
Design of PEB 28.02.2017 15.03.2017 Completed
Design of Foundation 10.03.2017 20.03.2017 Under Process
Vetting of Design 20.03.2017 05.04.2017 15.06.2017 30.06.2017
Excavation for foundation 01.04.2017 15.04.2017 01.04.2017 15.04.2017
RCC Frame Structure for Sub structure for including
10.04.2017 31.05.2017 10.04.2017 31.05.2017
concreting uptoplinth level
RCC Frame Structure for Super structure for
25.04.2017 31.07.2017 25.04.2017 31.07.2017
including concreting of Top slab etc.
Plinth filling 10.05.2017 10.06.2017 10.05.2017 10.06.2017
Fabrication and Supply of PEB Structure 15.05.2017 30.09.2017 15.05.2017 30.09.2017
Erection of PEB Structure 30.09.2017 31.12.2017 30.09.2017 31.12.2017
Roof Sheeting 01.12.2017 15.01.2018 01.12.2017 15.01.2018
Partition wall and wall cladding 15.12.2017 31.01.2018 15.12.2017 31.01.2018
Brick work upto First Floor 28.07.2017 27.09.2017 28.07.2017 27.09.2017
Brick work of Second Floor 28.09.2017 27.11.2017 28.09.2017 27.11.2017
Conduit work 10.07.2017 17.02.2018 10.07.2017 17.02.2018
Piping work for Water supply & Sanitary 18.08.2017 27.02.2018 18.08.2017 27.02.2018
External & Internal Plastering work in Ground Floor 15.01.2018 27.09.2017 15.01.2018 27.09.2017
WORK PROGRAMME CHART
IMPLEMENTATION SCHEDULE 2016 2017 2018
XX XX
Development of Integrated Check Post at
Dawki (Meghalaya) along Indo- Bangladesh
Border.
L.O.A.: RITES/AP/ICP DAWKI/2016/ 10159
Dated: 30/09/2016
Date of Commencement 15.10.2016
Completion Date as per agreement 14.10.2018
Revised Date of Completion

Revised Revised
Task Name Duration Unit Start Finish October November December January February March April May June July August September October November December January February March April May June July August September October
Start Finish

EXTErnal & Internal Plastering work in First Floor 15.01.2018 27.02.2018 15.01.2018 27.02.2018
Flooring 01.02.2018 28.02.2018 01.02.2018 28.02.2018
Doors & Windows etc. 01.02.2018 28.02.2018 01.02.2018 28.02.2018
False ceiling etc. 10.03.2018 10.04.2018 10.03.2018 10.04.2018
Electrical works 28.11.2017 15.04.2018 28.11.2017 15.04.2018
Water supply & Sewarage 28.11.2017 20.04.2018 28.11.2017 20.04.2018
Painting 01.04.2018 10.06.2018 01.04.2018 10.06.2018
40 mtr international border Issue
Construction of Cargo Terminal Building 483 Days 28.02.2017 25.06.2018 28.02.2017 25.07.2018
Design of PEB 28.02.2017 15.03.2017 Completed
Design of Foundation 10.03.2017 20.03.2017 Under Process
Vetting of Design 20.03.2017 05.04.2017 15.06.2017 30.06.2017
Excavation for foundation 10.04.2017 25.04.2017 10.07.2017 20.07.2017
RCC Frame Structure for Sub structure for including
24.04.2017 10.06.2017 25.07.2017 24.09.2017
concreting uptoplinth level
RCC Frame Structure for Super structure for
10.06.2017 15.08.2017 25.09.2017 24.11.2017
including concreting of Top slab etc.
Plinth filling 25.05.2017 25.06.2017 15.09.2017 30.09.2017
Fabrication and Supply of PEB Structure 15.05.2017 30.10.2017 10.07.2017 30.10.2017
Erection of PEB Structure 30.10.2017 31.01.2018 30.10.2017 31.01.2018
Roof Sheeting 01.12.2017 15.02.2018 01.12.2017 15.02.2018
Partition wall and wall cladding 15.12.2017 28.02.2018 15.12.2017 28.02.2018
Brick work upto First Floor 28.07.2017 27.09.2017 28.08.2017 27.10.2017
Brick work of Second Floor 28.09.2017 27.11.2017 28.10.2017 27.12.2017
Conduit work 10.07.2017 17.02.2018 10.08.2017 17.02.2018
Piping work for Water supply & Sanitary 18.08.2017 17.02.2018 18.08.2017 17.02.2018
External & Internal Plastering work in Ground Floor 15.01.2018 27.02.2018 15.01.2018 27.02.2018

EXTErnal & Internal Plastering work in First Floor 15.01.2018 27.02.2018 15.01.2018 27.02.2018
Flooring 01.02.2018 28.03.2018 01.02.2018 28.03.2018
Doors & Windows etc. 01.02.2018 28.03.2018 01.02.2018 28.03.2018
False ceiling etc. 10.03.2018 10.05.2018 10.03.2018 10.05.2018
Electrical works 28.11.2017 15.05.2018 28.12.2017 15.06.2018
Water supply & Sewarage 28.11.2017 20.04.2018 28.12.2017 20.05.2018
Painting 01.04.2018 25.06.2018 01.05.2018 25.07.2018

Construction of ESS Building & Drivers Rest


513 Days 28.02.2017 25.07.2018 28.02.2017 25.07.2018
House
Design of PEB 28.02.2017 15.03.2017 Completed
Design of Foundation 10.03.2017 20.03.2017 Under Process
Vetting of Design 20.03.2017 05.04.2017 15.06.2017 30.06.2017
Excavation for foundation 10.04.2017 25.04.2017 10.07.2017 20.07.2017
RCC Frame Structure for Sub structure for including
24.04.2017 10.06.2017 25.07.2017 24.09.2017
concreting uptoplinth level
RCC Frame Structure for Super structure for
10.06.2017 15.08.2017 25.09.2017 24.11.2017
including concreting of Top slab etc.
Plinth filling 25.05.2017 25.06.2017 15.09.2017 30.09.2017
Fabrication and Supply of PEB Structure 15.05.2017 30.10.2017 10.07.2017 30.10.2017
Erection of PEB Structure 30.10.2017 31.01.2018 30.10.2017 31.01.2018
Roof Sheeting 01.12.2017 15.02.2018 01.12.2017 15.02.2018
Partition wall and wall cladding 15.12.2017 28.02.2018 15.12.2017 28.02.2018
Brick work upto First Floor 28.07.2017 27.09.2017 28.08.2017 27.10.2017
Brick work of Second Floor 28.09.2017 27.11.2017 28.10.2017 27.12.2017
Conduit work 10.07.2017 17.02.2018 10.07.2017 17.02.2018
Piping work for Water supply & Sanitary 18.08.2017 17.02.2018 18.08.2017 17.02.2018
External & Internal Plastering work in Ground Floor 15.01.2018 27.02.2018 15.01.2018 27.02.2018

EXTErnal & Internal Plastering work in First Floor 15.01.2018 27.02.2018 15.01.2018 27.02.2018
Flooring 01.02.2018 28.05.2018 01.02.2018 28.05.2018
Doors & Windows etc. 01.02.2018 28.03.2018 01.02.2018 28.03.2018
False ceiling etc. 10.03.2018 10.06.2018 10.03.2018 10.06.2018
Electrical works 28.11.2017 15.05.2018 28.11.2017 15.05.2018
Water supply & Sewarage 28.11.2017 20.04.2018 28.11.2017 20.04.2018
Painting 01.05.2018 25.07.2018 01.05.2018 25.07.2018

Construction of WareHouse for Arrival 483 Days 28.02.2017 25.06.2018 28.02.2017 25.07.2018
Design of PEB 28.02.2017 15.03.2017 Completed
Design of Foundation 10.03.2017 20.03.2017 Under Process
Vetting of Design 20.03.2017 05.04.2017 15.06.2017 30.06.2017
Excavation for foundation 10.04.2017 25.04.2017 10.07.2017 20.07.2017
RCC Frame Structure for Sub structure for including
24.04.2017 10.06.2017 25.07.2017 24.09.2017
concreting uptoplinth level
RCC Frame Structure for Super structure for
10.06.2017 15.08.2017 25.09.2017 24.11.2017
including concreting of Top slab etc.
Plinth filling 25.05.2017 25.06.2017 15.09.2017 30.09.2017
Fabrication and Supply of PEB Structure 15.05.2017 30.10.2017 10.07.2017 30.10.2017
Erection of PEB Structure 30.10.2017 31.01.2018 30.10.2017 31.01.2018
Roof Sheeting 01.12.2017 15.02.2018 01.12.2017 15.02.2018
WORK PROGRAMME CHART
IMPLEMENTATION SCHEDULE 2016 2017 2018
XX XX
Development of Integrated Check Post at
Dawki (Meghalaya) along Indo- Bangladesh
Border.
L.O.A.: RITES/AP/ICP DAWKI/2016/ 10159
Dated: 30/09/2016
Date of Commencement 15.10.2016
Completion Date as per agreement 14.10.2018
Revised Date of Completion

Revised Revised
Task Name Duration Unit Start Finish October November December January February March April May June July August September October November December January February March April May June July August September October
Start Finish

Partition wall and wall cladding 15.12.2017 28.02.2018 15.12.2017 28.02.2018


Brick work upto First Floor 28.07.2017 27.09.2017 28.08.2017 27.10.2017
Brick work of Second Floor 28.09.2017 27.11.2017 28.10.2017 27.12.2017
Conduit work 10.07.2017 17.02.2018 10.08.2017 17.02.2018
Piping work for Water supply & Sanitary 18.08.2017 17.02.2018 18.08.2017 17.02.2018
External & Internal Plastering work in Ground Floor 15.01.2018 27.02.2018 15.01.2018 27.02.2018

EXTErnal & Internal Plastering work in First Floor 15.01.2018 27.02.2018 15.01.2018 27.02.2018
Flooring 01.02.2018 28.03.2018 01.02.2018 28.03.2018
Doors & Windows etc. 01.02.2018 28.03.2018 01.02.2018 28.03.2018
False ceiling etc. 10.03.2018 10.05.2018 10.03.2018 10.05.2018
Electrical works 28.11.2017 15.05.2018 28.12.2017 15.06.2018
Water supply & Sewarage 28.11.2017 20.04.2018 28.12.2017 20.05.2018
Painting 01.04.2018 25.06.2018 01.05.2018 25.07.2018

Rummaging Shed 300 Days 28.05.2017 27.03.2018 28.08.2017 27.04.2018


Procurement of Materials 28.05.2017 27.09.2017 28.08.2017 27.11.2017
Civil work 28.05.2017 27.10.2017 28.08.2017 27.01.2018
Structuralwork 28.07.2017 27.03.2018 28.09.2017 27.04.2018

Common Toilet 120 Days 18.08.2017 17.12.2017 18.08.2017 17.12.2017


Civil work 18.08.2017 17.12.2017 18.08.2017 17.12.2017

Urinals 120 Days 18.08.2017 17.12.2017 18.08.2017 17.12.2017


Civil work 18.08.2017 17.12.2017 18.08.2017 17.12.2017

Pump House & UG WaterStorageTank 360 Days 18.06.2017 17.06.2018 18.06.2017 17.06.2018
Civil work 18.06.2017 17.09.2017 18.06.2017 17.09.2017
Procurement of Pumps 18.09.2017 17.12.2017 18.09.2017 17.12.2017
Installationof Pumps 18.02.2018 17.06.2018 18.02.2018 17.06.2018

Entrance Gate 01 & 02 360 Days 28.06.2017 27.06.2018 28.06.2017 27.06.2018


0000000

RCC Frame Structure for Sub structure for including


28.06.2017 27.08.2017 28.06.2017 27.08.2017
concreting uptoplinth level
RCC Frame Structure for Super structure for
28.08.2017 27.07.2017 28.08.2017 27.07.2017
including concreting of Top slab etc.
Brick work upto First Floor 28.10.2017 27.11.2017 28.10.2017 27.11.2017
Conduit work 18.11.2017 17.01.2018 18.11.2017 17.01.2018
Piping work for Water supply & Sanitary 18.01.2018 17.01.2018 18.01.2018 17.01.2018
External & Internal Plastering work in Ground Floor 18.01.2018 27.02.2018 18.01.2018 27.02.2018
Flooring 28.02.2018 15.03.2018 28.02.2018 15.03.2018
Doors & Windows etc. 28.02.2018 15.03.2018 28.02.2018 15.03.2018
False ceiling etc. 15.03.2018 10.04.2018 15.03.2018 10.04.2018
Electrical works 15.05.2018 10.06.2018 15.05.2018 10.06.2018
Water supply & Sewarage 15.05.2018 10.06.2018 15.05.2018 10.06.2018
Painting 15.05.2018 27.06.2018 15.05.2018 27.06.2018

External Electrical Works 270 Days 18.03.2017 17.02.2018 18.06.2017 17.02.2018


Giving supply order & Procurement of HT / LT
18.03.2017 17.05.2017 18.06.2017 20.08.2017
Panels & Transformers
Procurement of DG Sets 18.03.2017 17.05.2017 18.09.2017 20.12.2017
Procurement of High mast 18.03.2017 17.05.2017 18.06.2017 20.08.2017
Procurement of Street Lights Poles & Luminaries 18.03.2017 17.05.2017 18.06.2017 20.08.2017
Installation of High mast & Poles 18.06.2017 18.07.2017 18.08.2017 18.10.2017
Procurement of Cables 18.06.2017 18.08.2017 18.08.2017 18.10.2017
Installation of HT / LT Panels & Transformers 18.06.2017 18.08.2017 18.09.2017 18.12.2017
Installation of DG Sets 18.06.2017 18.09.2017 18.12.2017 18.01.2018
Laying of Cables 18.09.2017 17.02.2017 18.09.2017 17.02.2018

CCTV & PA Systems 360 Days 18.09.2017 17.09.2018 18.09.2017 17.09.2018


Procurement of Materials 18.09.2017 17.03.2018 18.09.2017 17.03.2018
Laying & Installation 18.03.2018 17.09.2018 18.03.2018 17.09.2018

Installation of Fire Fighting Systems 360 Days 18.06.2017 17.05.2018 18.06.2017 17.05.2018
Procurement of Materials including Pipes , Valves &
18.06.2017 17.09.2017 18.06.2017 17.09.2017
Pumps etc.
Installation of the Piping systems, Valves & Pumps
18.09.2017 17.05.2018 18.09.2017 17.05.2018
etc.

Weight Bridges 100 Days 10.01.2018 10.04.2018 10.01.2018 10.04.2018


Procurement of Materials 10.01.2018 10.03.2018 10.01.2018 10.03.2018
Civil work 10.01.2018 10.03.2018 10.01.2018 10.03.2018
Installation including Civil works etc. 10.03.2018 10.04.2018 10.03.2018 10.04.2018

Cold Storage 118 Days 10.01.2018 17.04.2018 10.01.2018 17.04.2018


Procurement of Materials 10.01.2018 10.03.2018 10.01.2018 10.03.2018
Installation 10.03.2018 17.04.2018 10.03.2018 17.04.2018
Procurement & Installation of other equipments and
180 Days 15.02.2018 14.10.2018 15.02.2018 14.10.2018
finishing of other components not covered above
STATEMENT OF EXPENDITURE AT DAWKI
Activity Centre : 55 Name : Ashish Srivastava
( From 12.11.2016 to 26.12.2016 )
Project Code : RT550-00003 Empolyee No. : 11440

Consultancy Group : B&A Deppt to which attached : Airport Division

0501 Survey 0502 Sorvey 0503 Sorvey 0504 Vehicle 0505 Vehicle 0506 Vehicle 0308 0309 310 Hotel 0113 Staff 0601 Printing & 0608 Telphone, 0610 Postage 0611 Office 0612 Office 0619 0629 Sundry
Wages consumable Others store Hire Charges fuel Charges Repair Charges Travelling Travelling Charges (Rs.) Walfare (Rs.) stationery (Rs.) Telex/Fax and teligram rent (Rs.) main Entertainment (Rs.)
( RS) store (Rs.) (Rs.) (Rs.) (Rs.) Expences (Rs) Expences (Rs) (Rs.) charges (Rs.) (Rs.) (Rs.)
S. (Rs.)
Bill/suporting Bill No. Vr. Date Particulars Total Amount
No.

1 Tea allowance November 15.11.2016 Tea allowance of Ashish 250.00 250.00


2 Dhar / 17 24.11.2016 Print & Photocopy 48.00 48.00
3 Dhar / 20 05.12.2016 Print & Photocopy 390.00 390.00
4 453 06.12.2016 Print & Photocopy 38.00 38.00
5 Tea allowance December 06.12.2016 Tea allowance of Ashish 250.00 250.00
6 RE4412856121IN 06.12.2016 Registerd post 52.00 52.00
7 1852 19.12.2016 Print & Photocopy 171.00 171.00
8 RE441298718IN 19.12.2016 Registerd post 47.00 47.00
9 Myntoilang Computor Centre 20.12.2016 Print & Photocopy 70.00 70.00
10 1853 22.12.2016 Print & Photocopy 210.00 210.00
11 1855 23.12.2016 Print & Photocopy 102.00 102.00
12 RE441285705IN 24.12.2016 Registerd post 37.00 37.00
13 RE441285878IN 24.12.2016 Registerd post 47.00 47.00
0.00
0.00
0.00
Total 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 500.00 1029.00 0.00 183.00 0.00 0.00 0.00 0.00 1712.00

(Ashish Srivastava)
Manager (Civil)
ICP Project,
Dawki
Sr. DGM / AP
ADJUSTMENT OF ADVANCE
(INSTRUCTIONS OVERLEAF)

PROJECT NAME (In Capital) : ICP PROJECT AT DAWKI

PROJECT CODE : RT550-00003

PERSON TO BE CREDITED (In capital) : ASHISH SRIVASTAVA


Manager (Civil)
Employee No. : 11440

I submit the attached Bills / Supporting vouchers for Expenses / Payments as summarised
below, totalling Rs. 1752/- only, to be credited to the above named, against the Advance of Rs. Nil /-
taken on ……………………………. (Date / Dates) .

SUMMARY
(As per "Statement of Expenditure" attached)
( From 12.11.2016 to 26.12.2016 )
CODE NO. AMOUNT
308 Rs. 0.00
113 Rs. 500.00
601 Rs. 1029.00
608 Rs. 0.00
610 Rs. 183.00

Grand Total Rs. 1712.00

Signature

APPROVING COORDINATORS

Sr.DGM(AP) -

OFFICER IN CHARGE
(For use of Acconts Department)

Passed for Adjustment for Rupees …………………………………… Account Officer


SCHEDULE FOR MATERIALS PROCUREMENT ICP
DAWKI

SL NO. DESCRIPTION OF MATERIALS AND TENTATIVE DATE OF


MACHINARIES PROCUREMENT MATERIALS
1 Material for PEB 08/03/2017 TO 10/02/2018
2 PAVER BLOCK 10/03/2017 T0 15/09/2018
3 Material for CHAINLINK FENCING work 15/03/2017 to 25/06/2017
4 SWEAGE TREATMENT PLANT 18/04/2017 to 17/08/2018
5 DG Set 05/05/2017 to 17/01/2018
6 TRANSFORMER 05/05/2017 to 17/01/2018
7 PANEL BOARD 05/05/2017 to 17/02/2018
8 WEIGH BRIDGE 17/05/2017 to 17/09/2017
9 COLD STORAGE 17/05/2017 to 17/12/2017
10 HIGH MAST & ELECTRIC POLES 18/06/2017 to 18/12/2017
11 WEIGH BRIDGE 17/05/2017 to 17/01/2018
12 COLD STORAGE 17/05/2017 to 17/01/2018
MATERIALS FOR PLUMBING AND SANITARY
13 28/07/2017 to 27/10/2017
WORKS
MATERIALS FOR INTERNAL
14 28/08/2017 to 27/09/2017
ELECTRIFICATION WORK
MATERIALS FOR DOOR & WINDOWS WITH
15 28/09/2017 to 27/10/2017
ACCESESORIES
16 MATERIALS FOR CCTV SYSTEM 15/09/2017 to 15/03/2018
17 MATERIALS FOR TELEPHONIC SYSTEM 15/09/2017 to 15/03/2018
18 FURTINURES 20/01/2018 to 20/09/2018