Reply to Delay due to non-availability of forest-clearance
S.No. Document Contents Pg. No.
1. 1.3.2017 The Respondent had obtained Ann. C- 13 requisite permission from Forest Department. 2. Respondent’s Respondent alleges that It is the Annexure R-30 page letter dated Claimant, who had failed to progress 49-53 SOD Vol-RD1 13.4.2017 the work due to inadequate deployment of resources and non- Annexure R-36 page Respondent’s completion of pre-construction 61 SOD Vol-RD1 letter dated 30- activities. 05-2017