1. 25.01.2017 The Claimant commenced the work of chain-link fencing on 25.01.2017 i.e. over 3 1/2 months after award. On the said date Claimant had not completed pre- construction activities. 2. Respondent’s letter Respondent stated various Annexure R-22 dated 17-02-2017 failures at end of Claimant, which page 33-35 SOD included pre-construction/ Vol-RD1 mobilization activities. The same were in no way related with minor issue stated by Claimant. There was no issue by local public and no land was in dispute. The local issues were resolved immediately. No response was offered by the Claimant 3. Respondent’s letter In response to Claimant’s letter dated 22.7.2017 dated 21-07-2017 the Respondent explained the factual position giving reference to discussions with the concerned authorities. The Respondent also stated illegal import/export business operations by Claimant’s staff. Claimant was warned and asked not to engage any staff, who was indulging in illegal business. 4. August 2017 The Claimant while submitting their application for grant of EOT in August 2017 did not consider any effect of the above so called hindrances in their EOT application. 5. Minutes of meeting Contention of mobilization of Ann. C-29 page 58- dated 04.08.2017 site/ work is contrary to the facts 59 SOC Vol-CD and submissions made above. 6. Respondent’s email The Claimant’s letter dated Ann. C-30 page 60- dated 10.08.2017 07.08.2017 was duly replied by 61 SOC Vol- CD1 the Respondent. 7. Minutes of meeting It is brought out that though SDO Annexure R-155 dated 27.9.2018 had come to site on 19-09- 2018 page 323-325 SOD and during discussions brought Vol-CD2 out some minor issues. The same was immediately resolved by the Respondent. The Claimant was advised to continue the work. This is the only reason the issue was not discussed in the subsequent meetings dated 27- 09-2018. 8. 11-10-2018 The Respondent’s reply it is clear that the Claimant has failed to Respondent’s email in complete the work of diversion of reply to Claimant’s Muktapur road even in 24 email dated 10-10- months after the award. It is also 2018 pertinent to add that there was no issue on the said work after the award.