You are on page 1of 2

SONARGAON SEED CRUSHING MILLS LTD.

Working Schedule for the Piling Work

Date 12.05.2017
Department : Project
Period of Work -2017
Qty of Completion
Name of work Start date date
Total days Ramarks
Piling
May. 2017 Jun.2017 Jul.2017 Aug.2017 Sep.2017 Oct.2017 Nov.2017

1 Seed Preparation Building 196 01.05.2017 10.06.2017 35 Day


3rd machine will start from 17.5.17

2 Seed Extruction Building 153 11.06.2017 21.07.2017 41 Days


3 nos machine will run

3 Pre-Cleaning Building 37 22.07.2017 07.08.2017 14 Days


one machine will run

4 Meal Baging House 64 22.07.2017 14.08.2017 21 Days


two machine will run

5 Meal Storage Silo 360 15.08.2017 31.10.2017 75 Days


3 nos machine will run EID

6 Dry bin 30 15 Days


08.08.2017 22.08.2017

Total = 840 196 Days

NOTE: We are going to purchasde two more rig soon. Hopefully it will arrive at site by End of July which will be added in the piling work of Meal Storage silo.

and in this case piling will be started at Meal silo from 1st week of August and will be completed by September, 2017

AGM (Project) GM (Project)

You might also like