Point 1:- In technical bid page 3 section 1, 1.5 the complete land for ICP construction site shall be handed over to
Point 2:- In page 57 of technical bid schedule F 2(xiii) date of commencement of work 15 dayes from the date o
whichever is later. OR Point 3:- clause 5.1(a) Mention in schedule F from the date of issue of letter of acceptan
whichever is later.