Point 1:- In technical bid page 3 section 1, 1.5 the complete land for ICP construction site shall be handed over to
Point 2:- In page 57 of technical bid schedule F 2(xiii) date of commencement of work 15 dayes from the date o
whichever is later. OR Point 3:- clause 5.1(a) Mention in schedule F from the date of issue of letter of acceptan
whichever is later.

Point 4:- Clause 18 of GCC contractor to supply T & P


Point 5:- Clause 11 of GCC executed in accordance with specification, drawings and order.
Point 6:- Clause 25 Settlement of Arbitration.
Point7:- Clause 26 Contractor to indemnify the Employer against patent rights.
Point8:- Clause 39 Termination of contract on death of contractor.
Point9:- Clause 43 Compensation during warlike situation.
Point10:- Clause45A Release of Security deposit after clearance by state government authority for mineral extractio
Point11:-
on site shall be handed over to contractor in one go at the beginning of the project.
work 15 dayes from the date of issue of LOA or the first date of handing over of site
e of issue of letter of acceptance or from the first date of handing over of the site
er is later.

authority for mineral extraction.