Medor Adminstration Building Consultant : prof.

Dr Kamal Hassan

Activity ID Activity Name Original Start Finish Qtr 3, 2010 Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr J un
May
271 07-Jul-10 03-Apr-11 03-Apr-11, Medor Adminstration B
Medor Adminstration Building
general 271 07-Jul-10 03-Apr-11 03-Apr-11, general

A1000 Receiving IFC drawings 0 07-Jul-10 Receiving IFC drawings


A1010 Receiving advance payement 0 07-Jul-10 Receiving advance payement
A1020 start construction phase 0 17-Jul-10 start construction phase
A1030 finish construction 0 03-Apr-11 finish construction

engineering 37 07-Jul-10 12-Aug-... 12-Aug-10, engineering

A1990 submit ground floor's shop drawings for ap... 1 07-Jul-10 07-Jul-10 submit ground floor's shop drawings for approval
A2010 submit 1st floor shop drawings for approval 1 12-Jul-10 12-Jul-10 submit 1st floor shop drawings for approval
A2000 ground floor's shop drawings approval 0 15-Jul-10 ground floor's shop drawings approval
A2030 submit 2nd floor shop drawings for approval 1 17-Jul-10 17-Jul-10 submit 2nd floor shop drawings for approval
A2020 1st floor shop drawings approval 0 20-Jul-10 1st floor shop drawings approval
A2050 submit 3rd floor shop drawings for approval 1 21-Jul-10 21-Jul-10 submit 3rd floor shop drawings for approval
A2040 2nd floor shop drawings approval 0 25-Jul-10 2nd floor shop drawings approval
A2070 submit 4th floor shop drawings for approval 1 26-Jul-10 26-Jul-10 submit 4th floor shop drawings for approval
A2060 3rd floor shop drawings approval 0 29-Jul-10 3rd floor shop drawings approval
A2090 submit 5th floor shop drawings for approval 1 31-Jul-10 31-Jul-10 submit 5th floor shop drawings for approval
A2080 4th floor shop drawings approval 0 03-Aug-... 4th floor shop drawings approval
A2110 submit 6th floor shop drawings for approval 1 04-Aug-10 04-Aug-... submit 6th floor shop drawings for approval
A2100 5th floor shop drawings approval 0 08-Aug-... 5th floor shop drawings approval
A2120 6th floor shop drawings approval 0 12-Aug-... 6th floor shop drawings approval

skeleton 261 17-Jul-10 03-Apr-11 03-Apr-11, skeleton

ground floor 25 17-Jul-10 10-Aug-... 10-Aug-10, ground floor


A1330 columns Formwork & Rft. Part 2 8 17-Jul-10 25-Jul-10 columns Formwork & Rft. Part 2
A1350 Slab Formwork & Rft. Part1 10 17-Jul-10 27-Jul-10 Slab Formwork & Rft. Part1
Date Revision Checked Approved
Remaining Level of Effort Milestone TASK filter: All Activities
24-Aug-10 Revision 2
Actual Work Summary
Remaining Work 1 of 4
Critical Remaining Work
Medor Adminstration Building Consultant : prof. Dr Kamal Hassan

Activity ID Activity Name Original Start Finish Qtr 3, 2010 Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr J un
May
A1340 Columns Pouring Part2 1 26-Jul-10 26-Jul-10 Columns Pouring Part2
A1370 Slab Formwork & Rft. Part2 10 29-Jul-10 09-Aug-... Slab Formwork & Rft. Part2
A1380 Slab Pouring 1 10-Aug-10 10-Aug-... Slab Pouring
1st floor 36 12-Aug-10 16-Sep-10 16-Sep-10, 1st floor
A1390 columns Formwork & Rft. Part1 8 12-Aug-10 21-Aug-... columns Formwork & Rft. Part1
A1400 Columns Pouring Part1 1 22-Aug-10 22-Aug-... Columns Pouring Part1
A1410 columns Formwork & Rft. Part 2 8 22-Aug-10 30-Aug-... columns Formwork & Rft. Part 2
A1420 Slab Formwork & Rft. Part1 10 24-Aug-10 04-Sep-10 Slab Formwork & Rft. Part1
A1440 Columns Pouring Part2 1 31-Aug-10 31-Aug-... Columns Pouring Part2
A1460 Slab Formwork & Rft. Part2 10 04-Sep-10 15-Sep-10 Slab Formwork & Rft. Part2
A1480 Slab Pouring 1 16-Sep-10 16-Sep-10 Slab Pouring
2nd floor 35 19-Sep-10 23-Oct-10 23-Oct-10, 2nd floor
A1490 columns Formwork & Rft. Part1 8 19-Sep-10 27-Sep-10 columns Formwork & Rft. Part1
A1500 Columns Pouring Part1 1 28-Sep-10 28-Sep-10 Columns Pouring Part1
A1510 columns Formwork & Rft. Part 2 8 28-Sep-10 06-Oct-10 columns Formwork & Rft. Part 2
A1520 Slab Formwork & Rft. Part1 10 30-Sep-10 11-Oct-10 Slab Formwork & Rft. Part1
A1540 Columns Pouring Part2 1 07-Oct-10 07-Oct-10 Columns Pouring Part2
A1560 Slab Formwork & Rft. Part2 10 11-Oct-10 21-Oct-10 Slab Formwork & Rft. Part2
A1580 Slab Pouring 1 23-Oct-10 23-Oct-10 Slab Pouring
3rd floor 37 25-Oct-10 30-Nov-10 30-Nov-10, 3rd floor
A1590 columns Formwork & Rft. Part1 8 25-Oct-10 02-Nov-10 columns Formwork & Rft. Part1
A1610 columns Formwork & Rft. Part 2 8 02-Nov-10 10-Nov-10 columns Formwork & Rft. Part 2
A1600 Columns Pouring Part1 1 03-Nov-10 03-Nov-10 Columns Pouring Part1
A1620 Slab Formwork & Rft. Part1 10 06-Nov-10 20-Nov-10 Slab Formwork & Rft. Part1
A1640 Columns Pouring Part2 1 11-Nov-10 11-Nov-10 Columns Pouring Part2

Date Revision Checked Approved


Remaining Level of Effort Milestone TASK filter: All Activities
24-Aug-10 Revision 2
Actual Work Summary
Remaining Work 2 of 4
Critical Remaining Work
Medor Adminstration Building Consultant : prof. Dr Kamal Hassan

Activity ID Activity Name Original Start Finish Qtr 3, 2010 Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr J un
May
A1660 Slab Formwork & Rft. Part2 10 15-Nov-10 29-Nov-10 Slab Formwork & Rft. Part2
A1680 Slab Pouring 1 30-Nov-10 30-Nov-10 Slab Pouring
4th floor 34 02-Dec-10 04-Jan-11 04-Jan-11, 4th floor
A1690 columns Formwork & Rft. Part1 8 02-Dec-10 11-Dec-... columns Formwork & Rft. Part1
A1710 columns Formwork & Rft. Part 2 8 11-Dec-10 19-Dec-... columns Formwork & Rft. Part 2
A1700 Columns Pouring Part1 1 12-Dec-10 12-Dec-... Columns Pouring Part1
A1720 Slab Formwork & Rft. Part1 10 14-Dec-10 25-Dec-... Slab Formwork & Rft. Part1
A1740 Columns Pouring Part2 1 20-Dec-10 20-Dec-... Columns Pouring Part2
A1760 Slab Formwork & Rft. Part2 10 23-Dec-10 03-Jan-11 Slab Formwork & Rft. Part2
A1780 Slab Pouring 1 04-Jan-11 04-Jan-11 Slab Pouring
5th floor 34 06-Jan-11 08-Feb-11 08-Feb-11, 5th floor
A1790 columns Formwork & Rft. Part1 8 06-Jan-11 15-Jan-11 columns Formwork & Rft. Part1
A1810 columns Formwork & Rft. Part 2 8 15-Jan-11 23-Jan-11 columns Formwork & Rft. Part 2
A1800 Columns Pouring Part1 1 16-Jan-11 16-Jan-11 Columns Pouring Part1
A1820 Slab Formwork & Rft. Part1 10 18-Jan-11 29-Jan-11 Slab Formwork & Rft. Part1
A1840 Columns Pouring Part2 1 24-Jan-11 24-Jan-11 Columns Pouring Part2
A1860 Slab Formwork & Rft. Part2 10 27-Jan-11 07-Feb-11 Slab Formwork & Rft. Part2
A1880 Slab Pouring 1 08-Feb-11 08-Feb-11 Slab Pouring
6th floor 34 10-Feb-11 15-Mar-11 15-Mar-11, 6th floor
A1890 columns Formwork & Rft. Part1 8 10-Feb-11 19-Feb-11 columns Formwork & Rft
A1910 columns Formwork & Rft. Part 2 8 19-Feb-11 27-Feb-11 columns Formwork & Rft
A1900 Columns Pouring Part1 1 20-Feb-11 20-Feb-11 Columns Pouring Part1
A1920 Slab Formwork & Rft. Part1 10 22-Feb-11 05-Mar-11 Slab Formwork & Rft
A1940 Columns Pouring Part2 1 28-Feb-11 28-Feb-11 Columns Pouring Part
A1960 Slab Formwork & Rft. Part2 10 03-Mar-11 14-Mar-11 Slab Formwork & Rft
A1980 Slab Pouring 1 15-Mar-11 15-Mar-11 Slab Pouring
Date Revision Checked Approved
Remaining Level of Effort Milestone TASK filter: All Activities
24-Aug-10 Revision 2
Actual Work Summary
Remaining Work 3 of 4
Critical Remaining Work
Medor Adminstration Building Consultant : prof. Dr Kamal Hassan

Activity ID Activity Name Original Start Finish Qtr 3, 2010 Qtr 4, 2010 Qtr 1, 2011 Qtr 2, 2011
Duration Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr J un
May
Roof floor 16 19-Mar-11 03-Apr-11 03-Apr-11, Roof floor
A2130 columns Formwork & Rft. 5 19-Mar-11 23-Mar-11 columns Formwork
A2140 Columns Pouring 1 24-Mar-11 24-Mar-11 Columns Pouring
A2150 Slab Formwork & Rft. 7 26-Mar-11 02-Apr-11 Slab Formwork
A2160 Slab Pouring 1 03-Apr-11 03-Apr-11 Slab Pouring

Date Revision Checked Approved


Remaining Level of Effort Milestone TASK filter: All Activities
24-Aug-10 Revision 2
Actual Work Summary
Remaining Work 4 of 4
Critical Remaining Work