PLANNING VILLA Classic Schedule Layout 12-Apr-22 17:51

Activity ID Activity Name Original Start Finish Predecessor Details Activity Type
Duration

PLANNING VILLA 245d 04-Apr-22 13-Jan-23

JALONS CLES 245d 04-Apr-22 13-Jan-23


A34460 Ordre de Service 0d 04-Apr-22 Start Milestone
A34470 Fin ETUE 0d 19-May-22 A1110: FS Finish Milestone
A34480 Fin Validation 0d 19-May-22 A1110: FS Finish Milestone
A34490 Demarrage Travaux 0d 19-May-22 A10560: SS Start Milestone
A34500 Fin Dallage 0d 04-Jul-22 A10610: FS Finish Milestone
A34510 Fin GOE 0d 24-Sep-22 A33860: FS Finish Milestone
A34530 Fin Etanchéité 0d 26-Oct-22 A10860: FS Finish Milestone
A34520 Fin TCE 0d 13-Jan-23 A32710: FS Finish Milestone
ETUDE 36d 04-Apr-22 19-May-22
A1400 Lancement des Etudes 0d 04-Apr-22 A34460: FS Start Milestone
APS 12d 04-Apr-22 18-Apr-22
A1000 Preparation Plans 5d 04-Apr-22 08-Apr-22 A1400: FS Task Dependent
A1010 Preparation Note de Claclue 5d 04-Apr-22 08-Apr-22 A1000: SS Task Dependent
A1020 Revue BCT 5d 11-Apr-22 15-Apr-22 A1000: FS,A1010: FS Task Dependent
A1030 Validation APS 0d 18-Apr-22 A1020: FS 1d Finish Milestone
APD 13d 18-Apr-22 04-May-22
A1040 Preparation Plans 5d 18-Apr-22 25-Apr-22 A1030: FS Task Dependent
A1050 Preparation Note de Claclue 5d 18-Apr-22 25-Apr-22 A1030: FS Task Dependent
A1060 Revue BCT 5d 26-Apr-22 03-May-22 A1040: FS 1d,A1050: FS Task Dependent
A1070 Validation APD 0d 04-May-22 A1060: FS 1d Finish Milestone
PE 12d 04-May-22 19-May-22
A1080 Preparation Plans 5d 04-May-22 11-May-22 A1070: FS Task Dependent
A1090 Preparation Note de Claclue 5d 04-May-22 11-May-22 A1070: FS Task Dependent
A1100 Revue BCT 5d 11-May-22 18-May-22 A1080: FS,A1090: FS Task Dependent
A1110 Validation DCE 0d 19-May-22 A1100: FS 1d Finish Milestone
APPROVISIONNEMENT 77d 19-May-22 17-Aug-22

GOE / ETANCHEITE 9d 19-May-22 31-May-22


A1160 Remise Echantillons & Fiches Techniques pour validation
5d 19-May-22 25-May-22 A1110: FS Task Dependent
A1170 Revue Dossier par BCT &/ou BET 5d 25-May-22 31-May-22 A1160: FS Task Dependent
A1180 Validation Produits 0d 31-May-22 A1170: FS Finish Milestone
CET 15d 25-May-22 14-Jun-22
FLUIDE 15d 25-May-22 14-Jun-22
PLOMBERIE 10d 25-May-22 07-Jun-22
A1130 Remise Echantillons & Fiches Techniques pour validation
5d 25-May-22 01-Jun-22 A1160: FS Task Dependent
A1140 Revue Dossier par BCT &/ou BET 5d 01-Jun-22 07-Jun-22 A1130: FS Task Dependent
A1150 Validation Produits 0d 07-Jun-22 A1140: FS Finish Milestone
CVC 10d 01-Jun-22 14-Jun-22
A1220 Remise Echantillons & Fiches Techniques pour validation
5d 01-Jun-22 07-Jun-22 A1130: FS Task Dependent
A1230 Revue Dossier par BCT &/ou BET 5d 07-Jun-22 14-Jun-22 A1220: FS Task Dependent
A1240 Validation Produits 0d 14-Jun-22 A1230: FS Finish Milestone
ELECTRICITE 15d 25-May-22 14-Jun-22
CFO 10d 25-May-22 07-Jun-22
A1190 Remise Echantillons & Fiches Techniques pour validation
5d 25-May-22 01-Jun-22 A1160: FS Task Dependent
A1200 Revue Dossier par BCT &/ou BET 5d 01-Jun-22 07-Jun-22 A1190: FS Task Dependent
A1210 Validation Produits 0d 07-Jun-22 A1200: FS Finish Milestone
CFA 10d 01-Jun-22 14-Jun-22
A1250 Remise Echantillons & Fiches Techniques pour validation
5d 01-Jun-22 07-Jun-22 A1190: FS Task Dependent
A1260 Revue Dossier par BCT &/ou BET 5d 07-Jun-22 14-Jun-22 A1250: FS Task Dependent
A1270 Validation Produits 0d 14-Jun-22 A1260: FS Finish Milestone
CEA 61d 07-Jun-22 17-Aug-22
FAUX PLAFOND 38d 07-Jun-22 21-Jul-22
A1280 Remise Echantillons & Fiches Techniques pour validation
5d 07-Jun-22 14-Jun-22 A1250: FS Task Dependent
A1290 Revue Dossier par BCT &/ou BET 5d 14-Jun-22 21-Jun-22 A1280: FS Task Dependent
A1300 Validation Produits 0d 21-Jun-22 A1290: FS Finish Milestone
A33870 Livraison sur Site 0d 21-Jul-22 A1300: FS 24d Finish Milestone
REVETEMENT 38d 21-Jun-22 04-Aug-22
A1310 Remise Echantillons & Fiches Techniques pour validation
5d 21-Jun-22 27-Jun-22 A1250: FS,A1290: FS Task Dependent
A1320 Revue Dossier par BCT &/ou BET 5d 27-Jun-22 04-Jul-22 A1310: FS Task Dependent
A1330 Validation Produits 0d 04-Jul-22 A1320: FS Finish Milestone
A33880 Livraison sur Site 0d 04-Aug-22 A1330: FS 24d Finish Milestone
MENUISERIE 38d 27-Jun-22 10-Aug-22
A1340 Remise Echantillons & Fiches Techniques pour validation
5d 27-Jun-22 04-Jul-22 A1310: FS Task Dependent
A1350 Revue Dossier par BCT &/ou BET 5d 04-Jul-22 11-Jul-22 A1340: FS Task Dependent
A1360 Validation Produits 0d 11-Jul-22 A1350: FS Finish Milestone
A33890 Livraison sur Site 0d 10-Aug-22 A1360: FS 24d Finish Milestone
PEINTURE 38d 04-Jul-22 17-Aug-22
A1370 Remise Echantillons & Fiches Techniques pour validation
5d 04-Jul-22 11-Jul-22 A1340: FS Task Dependent
A1380 Revue Dossier par BCT &/ou BET 5d 11-Jul-22 15-Jul-22 A1370: FS Task Dependent
A1390 Validation Produits 0d 15-Jul-22 A1380: FS Finish Milestone
A33900 Livraison sur Site 0d 17-Aug-22 A1390: FS 24d Finish Milestone
CONSTRUCTION 205d 19-May-22 13-Jan-23

INSTALLATION DE CHANTIER 0d
TRAVAUX 205d 19-May-22 13-Jan-23
VILLA 1 205d 19-May-22 13-Jan-23
INFRASTRUCUTRE 39d 19-May-22 04-Jul-22

Page 1 of 2 TASK filter: All Activities


© Oracle Corporation
PLANNING VILLA Classic Schedule Layout 12-Apr-22 17:51
Activity ID Activity Name Original Start Finish Predecessor Details Activity Type
Duration

A10560 Fouilles yc Béton de Propreté 4d 19-May-22 24-May-22 A1110: FS Task Dependent


A34420 Ferraillage Infrastrcutre 39d 19-May-22 04-Jul-22 A10560: SS Level of Effort
A34540 TACHE HEURES INFRASTRUCTURE 39d 19-May-22 04-Jul-22 WBS Summary
A10570 Semelles 7d 24-May-22 01-Jun-22 A10560: FS Task Dependent
A10620 Futs de Poteaux 5d 01-Jun-22 07-Jun-22 A10570: FS Task Dependent
A10700 Chainages 5d 07-Jun-22 11-Jun-22 A10620: FS Task Dependent
A10590 Remblaiement 5d 11-Jun-22 17-Jun-22 A10700: FS Task Dependent
A10580 Longrines 5d 17-Jun-22 23-Jun-22 A10590: FS Task Dependent
A10600 Réseaux Sous Dallage yc Mise à la Terre & 5d 23-Jun-22 28-Jun-22 A10580: FS Task Dependent
Regards
A10610 Dallage 5d 28-Jun-22 04-Jul-22 A10600: FS,A34420: FF Task Dependent
RDC 171d 28-Jun-22 13-Jan-23
SUPERSTRUCUTRE & MACONNERIE 70d 28-Jun-22 17-Sep-22
A34430 Ferraillage Elevation 27d 28-Jun-22 30-Jul-22 A10610: SS Level of Effort
A10720 Poteaux & Voiles 5d 04-Jul-22 09-Jul-22 A10610: FS Task Dependent
A10730 Etaiment & Coffrage Plancher 8d 09-Jul-22 19-Jul-22 A10720: FS Task Dependent
A10740 Plancher 10d 19-Jul-22 30-Jul-22 A10730: FS,A34430: FF Task Dependent
A10750 Décoffrage Plancher 2d 30-Aug-22 01-Sep-22 A10740: FS 26d Task Dependent
A10760 Cloisonnement 6d 08-Sep-22 15-Sep-22 A10750: FS,A10900: FS Task Dependent
A33810 Pose Faux Cadres 2d 15-Sep-22 17-Sep-22 A10760: FS Task Dependent
SECOND OEUVRE 101d 17-Sep-22 13-Jan-23
CET 86d 17-Sep-22 27-Dec-22
A32080 Descente EP 5d 17-Sep-22 23-Sep-22 A32190: FS Task Dependent
A32090 Incoporation Electrique Mural 6d 17-Sep-22 24-Sep-22 A32190: FS Task Dependent
A32190 M-à-D pour travaux incorporation mural 0d 17-Sep-22 A33810: FS Start Milestone
A32100 Pose réseaux CVC y compris calorifuge au 5d 04-Oct-22 10-Oct-22 A32200: FS Task Dependent
plafond
A32200 M-à-D Pour travaux CET au plafond 0d 04-Oct-22 A32590: FS Start Milestone
A33670 CDC au plafond 6d 04-Oct-22 11-Oct-22 A32200: FS Task Dependent
A32120 Pose Unité CVC au plafond 4d 10-Oct-22 14-Oct-22 A32200: FS,A32100: FS Task Dependent
A32130 Tirage de câbles 8d 11-Oct-22 20-Oct-22 A32200: FS,A33670: FS Task Dependent
A33800 Equipements des Tableaux Electrique 12d 05-Dec-22 19-Dec-22 A32660: FS Task Dependent
A32150 Pose Terminaux Electriques 12d 13-Dec-22 27-Dec-22 A32210: FS Task Dependent
A32160 Pose Terminaux Fluides 12d 13-Dec-22 27-Dec-22 A32210: FS Task Dependent
A32210 M-à-D pour pose terminaux 0d 13-Dec-22 A32600: FS,A32660: FS, A32670: FS Start Milestone
CEA 95d 24-Sep-22 13-Jan-23
A32540 M-à-D Pour Travaux de l'Enduit mural 0d 24-Sep-22 A32080: FS,A32090: FS Start Milestone
A32590 Enduit: Enduit Intérieur 8d 24-Sep-22 04-Oct-22 A32540: FS Task Dependent
A32550 M-à-D Pour Travaux Faux Plafond, 0d 20-Oct-22 A32120: FS,A32130: FS, A32100: FS,A33670: FS,A1300: Start Milestone
Revêtement, Menuiserie & Enduit Peinture FS,A33870: FS
A32600 Faux Plafond 9d 20-Oct-22 31-Oct-22 A32550: FS Task Dependent
A32620 Chape de Forme 8d 31-Oct-22 08-Nov-22 A32550: FS,A32600: FS, A33880: FS Task Dependent
A33630 Revêtement Sol 8d 08-Nov-22 17-Nov-22 A32620: FS Task Dependent
A32660 Peinture: Enduit Pour Peinture & 1ère 15d 17-Nov-22 05-Dec-22 A33630: FS Task Dependent
Couche de finition
A32670 Menuiserie Portes & Fenêtres 15d 25-Nov-22 13-Dec-22 A32550: FS,A32660: SS 8d, A33630: FS,A33890: FS Task Dependent
A32560 M-à-D Pour Travaux de Finition Peinture 0d 27-Dec-22 A32150: FS,A32160: FS, A33800: FS Start Milestone
A32710 Peinture: Finition Peinture 15d 27-Dec-22 13-Jan-23 A32560: FS,A32150: FS, A32160: FS,A33900: FS Task Dependent
TOITURE 74d 01-Aug-22 26-Oct-22
GOE & ETANCHEITE 74d 01-Aug-22 26-Oct-22
SUPERSTRUCTURE 47d 01-Aug-22 24-Sep-22
A33820 Poteaux & Voiles 5d 01-Aug-22 06-Aug-22 A10740: FS 1d Task Dependent
A33830 Etaiment & Coffrage Plancher 3d 06-Aug-22 09-Aug-22 A33820: FS Task Dependent
A33840 Plancher 5d 09-Aug-22 15-Aug-22 A33830: FS Task Dependent
A33850 Décoffrage Plancher 2d 15-Sep-22 17-Sep-22 A33840: FS 26d Task Dependent
A33860 Acrotères 6d 17-Sep-22 24-Sep-22 A33850: FS,A1180: FS Task Dependent
ETANCHEITE 27d 24-Sep-22 26-Oct-22
A34440 Forme de Pente 5d 24-Sep-22 30-Sep-22 A33860: FS Task Dependent
A10830 Etanchéité 14d 30-Sep-22 17-Oct-22 A33860: FS,A1180: FS,A34440: FS Task Dependent
A10840 Mise en Eau 4d 17-Oct-22 21-Oct-22 A10830: FS Task Dependent
A10850 Test 4d 21-Oct-22 26-Oct-22 A10840: FS Task Dependent
A10860 Réception d'Etanchéité 0d 26-Oct-22 A10850: FS Finish Milestone
CET 0d
FACADE 29d 01-Sep-22 05-Oct-22
A10900 Maçonnerie Envellope Nappe Intérieur - 6d 01-Sep-22 08-Sep-22 A10750: FS,A33840: FS Task Dependent
RDC
A10880 Isolation Thermique 5d 15-Sep-22 21-Sep-22 A10900: FS,A10760: FS Task Dependent
A10890 Maçonnerie Envellope Nappe Extérieur 6d 21-Sep-22 29-Sep-22 A10880: FS Task Dependent
A34450 Enduit Façades 5d 29-Sep-22 05-Oct-22 A10890: FS Task Dependent

Page 2 of 2 TASK filter: All Activities