Professional Documents
Culture Documents
RENOVATION AT
KUWAIT NAVAL BASE
Page 1 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE
TABLE OF CONTENTS
1.0 PURPOSE
5.1 MSB
5.2 DB
5.3 ISOLATORS
5.5 PA SYSTEM
Page 2 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE
1.0 PURPOSE:
Page 3 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE
Clamp Meter
Megger
Multi Meter
Earth Tester
Hand Tools
5.1 MSB
Check the panel has been installed properly. Level and fixed properly.
Check all the Electrical connections are completed and ensure that there are no
loose wires or cables inside panel.
Check the tightness of all the incoming and outgoing connections and wires
are properly dressed inside the panel.
Check whether the bus bar section is properly covered so that there is no
chance of anyone accidently touching the bus bar.
Check all the Meters (Ammeters & Voltmeter) are installed correctly. Meters
should not show any values.
Check the cable connection to the Incoming Breaker. Make sure that the
Incoming Breaker is in the OFF position.
Switch ON the power supply from Electrical Panel feeding this particular
Panel.
Check the Voltmeter. It should show 415 volts.
Rotate the Selector switch and check Voltage between phases and between
Phase and Neutral.
Make sure that the Voltage between Phases and Phase is around 415volts and
Phase to Neutral is around 240volts.
Check and confirm all the outgoing Breakers are switched OFF
Page 5 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE
5.2 DB
Check the DB has been installed properly. Level and fixed properly to the
wall.
Check all the Electrical connections are completed and see that there are no
loose wires or cables inside the DB.
Check the tightness of all the Incoming and Outgoing connections and wires
are properly dressed and labeled inside the DB.
Check whether the Bus bar section is properly covered so that there is no
chance of anyone accidentally touching the bus bar.
Check the cable connection to the Incoming Breaker. Make sure that the
Incoming Breaker is in the OFF position.
Switch ON the power supply from MSB panel feeding the particular DB.
Make sure that the Voltage between Phases and Phase is around 415volts and
Phase to Neutral is around 240volts.
Check and confirm all the outgoing Breakers are switched OFF
Now switch on the Main Breaker of the Electrical DB.
Now check all the outgoing Wires are terminated properly on the other end.
Page 6 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE
Switch ON the outgoing Breakers one by one circuit wise and check the
Power supply at the other end.
Check all lights, power sockets and FCUs are working.
5.3 ISOLATORS
Check the isolator has been erected properly - level and fixed properly to the
wall.
Check all the Electrical connections are completed and see that there are no
loose wires or cables inside the isolator.
Check the tightness of all the Incoming and Outgoing connections and cables
are properly dressed inside the isolator.
Check the cable connection to the Incoming Breaker. Make sure that the
Incoming Breaker is in the OFF position.
Switch ON the power supply from Electrical Panel feeding this particular
isolator.
Make sure that the Voltage between Phases and Phase is around 415volts and
Phase to Neutral is around 240volts.
Now check outgoing Cable is terminated properly on the other end.
Now switch on the Breaker of the Electrical isolator.
Make sure that all the pre commissioning works and checks are completed.
Switch on the AC power to the control panel.
Page 7 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE
Check all the field connections are done correctly and all devices fitted.
Start Fire Alarm Panel and check for its functionality.
Activate Smoke detector / Heat detector by using spray / flame and check
whether sounder of that particular detector is energize. After that check
whether all detectors on that floor and other floors getting energize with time
delay.
Activate manual call point and verify fire alarm system getting activates on
that floor immediately and other floors with time delay.
Use fire hose and check whether flow switch of fire pump activates and giving
signal to Fire alarm system, and then verify all fire alarm devices are activating
with time delay.
Check Fire bells, strobes and alarm systems are working properly.
Check the battery capacity for operates the system under quiescent load
(system operating in a non-alarm condition) for 24 hours and, at the end of that
period battery shall be capable of operating all alarm notification appliances
for 5 min. Please refer attached NFPA 72 - Section 10.6.7.2.
Record all the test results.
5.5 PA SYSTEM
Make sure that all the precommissioning works and checks are completed.
Ensure that TV racks, Multi switches (Distribution switches), face plates are
installed properly.
Ensure the Dish installations are as per manufacturer recommendation (Dish
location, Supports, Levels etc.)
Connect SAT Finder equipment in each point at all rooms, measure Signal
strength and record it.
Perform visual check for TV channels which is showing in SAT Finder.
Record number of TV outlets Installed in Buildings.
Make sure that all the precommissioning works and checks are completed.
Ensure that Telephone racks, Patch panels, face plates, cables are installed
properly.
Connect FLUKE TUNER in rack side, Auxiliary equipment (Fluke) has to be
connected in room side and test Installed CAT 6 cables.
Test result will be shown in testing equipment as green colour tick mark, and
reports will be saved in same equipment. (Please find attached sample report).
All reports shall be printed and attach with check sheets.
Page 9 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE
Each and every installed CAT 6 cables has to be tested by same method in all
rooms and report to be taken from FLUKE TUNER.
Record number of Telephone outlets Installed in Buildings.
Ensure the labeling is done at all points and Patch panel side.
Page 10 o f 10
Electrical Test Forms
PRE COMMISSIONING CHECKLIST FOR MSB
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR MSB
AREA'S FEEDING: W.H.1, W.H.2, FIRE, BOOSTER, CHILLER SYSTEM : 312.50KW / 440V / 630A
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST
FOR
DISTRIBUTION BOARDS
6 Check Name plate and lidentification for Distribution boards are done.
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISAOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
MSB
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR MSB
AREA'S FEEDING: W.H.1, W.H.2, FIRE, BOOSTER, CHILLER SYSTEM : 312.50KW / 440V / 630A
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISAOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER
REMARKS/COMMENTS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B
REMARKS/COMMENTS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B
REMARKS/COMMENTS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS
3 System Voltage :
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B
REMARKS/COMMENTS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B
REMARKS/COMMENTS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR
OBSERVED BY TITLEII
CHECKLIST FOR EARTHIN
G
AND LIGHTNING PROTECTI
ON
2 Check cable trays,trunking and all equipments are bonded with Earthing system.
3 Check sizes of earth bars are as per specification and approved drawings.
5 Check the level and location of earth pits are as per approved drawings.
9 Check Earth continuity test for all metal parts and equipment of buildings.
REMARKS/COMMENTS
OBSERVED BY TITLEII
CHECKLIST FOR EARTHIN
G
AND LIGHTNING PROTECTI
ON
2 Check cable trays,trunking and all equipments are bonded with Earthing system.
3 Check sizes of earth bars are as per specification and approved drawings.
5 Check the level and location of earth pits are as per approved drawings.
9 Check Earth continuity test for all metal parts and equipment of buildings.
REMARKS/COMMENTS
OBSERVED BY TITLEII
CHECKLIST FOR EARTHIN
G
AND LIGHTNING PROTECTI
ON
2 Check cable trays,trunking and all equipments are bonded with Earthing system.
3 Check sizes of earth bars are as per specification and approved drawings.
5 Check the level and location of earth pits are as per approved drawings.
9 Check Earth continuity test for all metal parts and equipment of buildings.
REMARKS/COMMENTS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
FIRE ALARM SYSTEM
3 Check each equipments are connected with system and working properly.
4 Check Fire strobe, Fire bells are Installed properly and as per approved drawing.
7 Perform tests and check Fire strobs and Fire bells are working properly.
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
PUBLIC ADDRESS SYSTEM
1 Check PA system racks and equipments are Installed properly as per approved drawing.
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
TELEPHONE SYSTEM
1 Check Telephone system racks and switches are Installed as per approved drawing.
3 Check all telephone cables are terminated with Patch panel properly.
REMARKS/COMMENTS
OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
SMATV SYSTEM
2 Check Multi switches are Properly Installed and connections are done.
REMARKS/COMMENTS
OBSERVED BY TITLEII