You are on page 1of 126

BLUE BRICK BUILDING

RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

CLIENT : KUWAIT NAVAL BASE

CONSULTANT : AIR FORCE CIVIL ENGINEER CENTER

PROJECT : BLUE BRICK BUILDING RENOVATION


AT KUWAIT NAVAL BASE

MAIN CONTRACTOR : JFCS/VERSAR, LLC :

MEP SUBCONTRACTOR MEDCO KUWAIT

TESTING & COMMISSIONING PROCEDURE


FOR
ELECTRICAL SYSTEM

Page 1 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

TABLE OF CONTENTS

1.0 PURPOSE

2.0 LIST OF DOCUMENTS

2.1 APPROVED MATERIALS

2.2 APPROVED DESIGN DRAWINGS

3.0 LIST OF TESTING EQUIPMENTS

4.0 LIST OF PERSONNELS INVOLVED

5.0 LIST OF TESTING PROCEDURES

5.1 MSB

5.2 DB

5.3 ISOLATORS

5.4 FIRE ALARM SYSTEM

5.5 PA SYSTEM

5.6 SMATV SYSTEM

5.7 TELEPHONE SYSTEM

6.0 TEST REPORTS

Page 2 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

1.0 PURPOSE:

The procedures stated in this Testing and Commissioning Procedure


cover the activities in final tests and inspections, functional
performance tests and the commissioning of MSB, DB, Isolators, Fire
Alarm System, PA System, SMATV System, and Telephone System.

2.0 LIST OF DOCUMENTS:

2.1 Approved Material

Page 3 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

3.0 TESTING TOOLS & EQUIPMENTS:

Clamp Meter
Megger
Multi Meter
Earth Tester
Hand Tools

4.0 LIST OF PERSONNELS INVOLVED:

Experienced Electrical Engineer and Commissioning Team from NBTC


will be involved during the T & C.
Page 4 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

5.0 LIST OF TESTING PROCEDURES:

5.1 MSB

Check the panel has been installed properly. Level and fixed properly.
Check all the Electrical connections are completed and ensure that there are no
loose wires or cables inside panel.
Check the tightness of all the incoming and outgoing connections and wires
are properly dressed inside the panel.
Check whether the bus bar section is properly covered so that there is no
chance of anyone accidently touching the bus bar.
Check all the Meters (Ammeters & Voltmeter) are installed correctly. Meters
should not show any values.
Check the cable connection to the Incoming Breaker. Make sure that the
Incoming Breaker is in the OFF position.
Switch ON the power supply from Electrical Panel feeding this particular
Panel.
Check the Voltmeter. It should show 415 volts.
Rotate the Selector switch and check Voltage between phases and between
Phase and Neutral.
Make sure that the Voltage between Phases and Phase is around 415volts and
Phase to Neutral is around 240volts.
Check and confirm all the outgoing Breakers are switched OFF
Page 5 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

Now switch on the Main Breaker of the Electrical Panel.


Now check all the outgoing Cables / Wires are terminated properly on the
other end.
Switch ON the outgoing Breakers one by one and check the Power supply at
the other end.

5.2 DB

Check the DB has been installed properly. Level and fixed properly to the
wall.
Check all the Electrical connections are completed and see that there are no
loose wires or cables inside the DB.
Check the tightness of all the Incoming and Outgoing connections and wires
are properly dressed and labeled inside the DB.
Check whether the Bus bar section is properly covered so that there is no
chance of anyone accidentally touching the bus bar.
Check the cable connection to the Incoming Breaker. Make sure that the
Incoming Breaker is in the OFF position.
Switch ON the power supply from MSB panel feeding the particular DB.
Make sure that the Voltage between Phases and Phase is around 415volts and
Phase to Neutral is around 240volts.
Check and confirm all the outgoing Breakers are switched OFF
Now switch on the Main Breaker of the Electrical DB.
Now check all the outgoing Wires are terminated properly on the other end.
Page 6 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

Switch ON the outgoing Breakers one by one circuit wise and check the
Power supply at the other end.
Check all lights, power sockets and FCUs are working.

5.3 ISOLATORS

Check the isolator has been erected properly - level and fixed properly to the
wall.
Check all the Electrical connections are completed and see that there are no
loose wires or cables inside the isolator.
Check the tightness of all the Incoming and Outgoing connections and cables
are properly dressed inside the isolator.
Check the cable connection to the Incoming Breaker. Make sure that the
Incoming Breaker is in the OFF position.
Switch ON the power supply from Electrical Panel feeding this particular
isolator.
Make sure that the Voltage between Phases and Phase is around 415volts and
Phase to Neutral is around 240volts.
Now check outgoing Cable is terminated properly on the other end.
Now switch on the Breaker of the Electrical isolator.

5.4 FIRE ALARM SYSTEM

Make sure that all the pre commissioning works and checks are completed.
Switch on the AC power to the control panel.

Page 7 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

Check all the field connections are done correctly and all devices fitted.
Start Fire Alarm Panel and check for its functionality.
Activate Smoke detector / Heat detector by using spray / flame and check
whether sounder of that particular detector is energize. After that check
whether all detectors on that floor and other floors getting energize with time
delay.
Activate manual call point and verify fire alarm system getting activates on
that floor immediately and other floors with time delay.
Use fire hose and check whether flow switch of fire pump activates and giving
signal to Fire alarm system, and then verify all fire alarm devices are activating
with time delay.
Check Fire bells, strobes and alarm systems are working properly.
Check the battery capacity for operates the system under quiescent load
(system operating in a non-alarm condition) for 24 hours and, at the end of that
period battery shall be capable of operating all alarm notification appliances
for 5 min. Please refer attached NFPA 72 - Section 10.6.7.2.
Record all the test results.

5.5 PA SYSTEM

Ensure that Precommissioning works and checks are completed.


Check the PA system rack, DVD Player, wireless mic, FM tuner and speakers
are installed properly.
Check the power supply of PA system rack is correct and connections are
tight.
Page 8 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

Check number of elements (Speakers) are installed as per approved drawings.


Check all equipments (wireless mic, DVD player, FMs) are working
properly.

5.6 SMATV SYSTEM

Make sure that all the precommissioning works and checks are completed.
Ensure that TV racks, Multi switches (Distribution switches), face plates are
installed properly.
Ensure the Dish installations are as per manufacturer recommendation (Dish
location, Supports, Levels etc.)
Connect SAT Finder equipment in each point at all rooms, measure Signal
strength and record it.
Perform visual check for TV channels which is showing in SAT Finder.
Record number of TV outlets Installed in Buildings.

5.7 TELEPHONE SYSTEM

Make sure that all the precommissioning works and checks are completed.
Ensure that Telephone racks, Patch panels, face plates, cables are installed
properly.
Connect FLUKE TUNER in rack side, Auxiliary equipment (Fluke) has to be
connected in room side and test Installed CAT 6 cables.
Test result will be shown in testing equipment as green colour tick mark, and
reports will be saved in same equipment. (Please find attached sample report).
All reports shall be printed and attach with check sheets.
Page 9 o f 10
BLUE BRICK BUILDING
RENOVATION AT
KUWAIT NAVAL BASE

TESTING & COMMISSIONING PROCEDURE Doc. MEDCO/JFCS/VER/EL/01


FOR
ELECTRICAL SYSTEM Date: 31/12/2016

Each and every installed CAT 6 cables has to be tested by same method in all
rooms and report to be taken from FLUKE TUNER.
Record number of Telephone outlets Installed in Buildings.
Ensure the labeling is done at all points and Patch panel side.

6.0 TEST REPORTS

Page 10 o f 10
Electrical Test Forms
PRE COMMISSIONING CHECKLIST FOR MSB

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: DB1, DB2, MSB-ROOF SYSTEM : 312.50KW / 440V / 630A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR MSB

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB-ROOF

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: W.H.1, W.H.2, FIRE, BOOSTER, CHILLER SYSTEM : 312.50KW / 440V / 630A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: CU-G1 to CU-G7, DB-GL/P SYSTEM : 40.272KW / 440V / 100A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST
FOR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:CU-F1 to CU-F8 SYSTEM :23.872KW / 240 V / 63A

LOCATION : 502 A DRW REF:BLDG-502A-ELE-02

SL.NO DESCRIPTION YES NO N/A


1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all dust and rubs are cleaned.

6 Check Name plate and lidentification for Distribution boards are done.

7 Make sure Earthing done properly.

8 Make sure the breaker is "OFF" position.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF : BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 40.272KW / 440V / 100A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISAOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTNG, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 40.272KW / 440V / 100A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 A DRW REF :BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
MSB

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: DB1, DB2, MSB-ROOF SYSTEM : 376.64KW / 440V / 630A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR MSB

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB-ROOF

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: W.H.1, W.H.2, FIRE, BOOSTER, CHILLER SYSTEM : 312.50KW / 440V / 630A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: CU-G1 to CU-G7, DB-GL/P SYSTEM : 40.272KW / 440V / 100A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: CU-F1 to CU-F8 SYSTEM : 23.872KW / 440V / 63A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM :2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-02

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF : BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISAOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTNG, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 40.272KW / 440V / 100A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
PRE COMMISSIONING CHECKLIST FOR
ISOLATER

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW / 240V / 32A

LOCATION : 502 B DRW REF :BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A

1 Confirm that all preservation measures have been removed.

2 Confirm that all components are free from damages.

3 Confirm bus bars are properly covered to avoid direct contact.

4 Check the incoming cables are properly terminated and fixed.

5 Check all openings of the panels are properly closed.

6 Check inside panel all dust and rubs are cleaned.

7 Check lidentification for breakers are done.

8 Make sure the breaker is "OFF" position.

9 Make sure Earthing done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:DB1, DB2, MSB-ROOF SYSTEM :376.64KW / 440V / 630A

LOCATION : 502A DRW REF:BLDG-502A-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Manufacturer : GENERAL CONTROL GROUP FACTORY G.C.G

2 Incoming Breaker Rating : 376.64KW,630A

3 System Voltage : 440V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB-ROOF

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:W.H.1,W.H.2, FIRE, BOOSTER,CHILLER(2) SYSTEM : 312.50KW/440V/630A

LOCATION : 502A DRW REF: BLDG-502A-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Manufacturer : GENERAL CONTROL GROUP FACTORY G.C.G

2 Incoming Breaker Rating :3 12.50KW/630A

3 System Voltage : 440 V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:CU-G1 to CU-G8, DB-GL/P SYSTEM : 40.272KW / 440 V / 100A

LOCATION : 502A DRW REF: BLDG-502A-ELE-02

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GROUP FACTORY G.C.G

2 Incoming Breaker Rating :40.272KW/100A

3 System Voltage : 440V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built DB Schedule prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: CU-F1 to CU-F2 SYSTEM : 23.872KW / 440V / 63A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-02

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer :

2 Incoming Breaker Rating :

3 System Voltage :

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built DB Schedule prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating : 2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 A DRW REF: BLDG-502A-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:DB1, DB2, MSB-ROOF SYSTEM :376.64KW / 440V / 630A

LOCATION : 502B DRW REF:BLDG-502B-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Manufacturer : GENERAL CONTROL GROUP FACTORY G.C.G

2 Incoming Breaker Rating : 376.64KW,630A

3 System Voltage : 440V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR MS B

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : MSB-ROOF

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:W.H.1,W.H.2, FIRE, BOOSTER,CHILLER(2) SYSTEM : 312.50KW/440V/630A

LOCATION : 502B DRW REF: BLDG-502B-ELE-01

SL.NO DESCRIPTION YES NO N/A

1 Manufacturer : GENERAL CONTROL GROUP FACTORY G.C.G

2 Incoming Breaker Rating :3 12.50KW/630A

3 System Voltage : 440 V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:CU-G1 to CU-G8, DB-GL/P SYSTEM : 40.272KW / 440 V / 100A

LOCATION : 502B DRW REF: BLDG-502B-ELE-02

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GROUP FACTORY G.C.G

2 Incoming Breaker Rating :40.272KW/100A

3 System Voltage : 440V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built DB Schedule prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
DISTRIBUTION BOARDS

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : DB2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: CU-F1 to CU-F2 SYSTEM : 23.872KW / 440V / 63A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-02

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating : 23.872KW / 63A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built DB Schedule prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-G8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-03 & 05

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F1

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F2

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F3

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F4

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F5

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F6

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating : 2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F7

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating :2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST FOR ISOL ATOR

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : CU-F8

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: LIGHTING, POWER, AC SYSTEM : 2.984KW/240V/32A

LOCATION : 502 B DRW REF: BLDG-502B-ELE-04 & 06

SL.NO DESCRIPTION YES NO N/A


1 Manufacturer : GENERAL CONTROL GRUOUP FACTORY G.C.G

2 Incoming Breaker Rating : 2.984KW/32A

3 System Voltage : 240V

4 Check all Incoming and Outgoing breakers are working properly.

5 Check as built drawings are prepared and placed in appropriate place.

6 Check Name plate details and labelling done properly.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
CHECKLIST FOR EARTHIN
G
AND LIGHTNING PROTECTI
ON

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : 502 A- EARTHING

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING:N/A SYSTEM : N/A

LOCATION : 502 A DRW REF:BLDG-502A-ELE-08

SL.NO DESCRIPTION YES NO N/A


1 Check if sizes of Earthing tapes are as per approved drawings.

2 Check cable trays,trunking and all equipments are bonded with Earthing system.

3 Check sizes of earth bars are as per specification and approved drawings.

4 Check Earthing wire(s) is connected to equipment as per drawing in proper way.

5 Check the level and location of earth pits are as per approved drawings.

6 Check if earth pit fixing is as per approved drawings.

7 Check the connections of Earthing tape to Earthing rod electrode.

8 Record Earth resistance reading(Less than 2Ohms)

9 Check Earth continuity test for all metal parts and equipment of buildings.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
CHECKLIST FOR EARTHIN
G
AND LIGHTNING PROTECTI
ON

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : 502B- EARTHING

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: N/A SYSTEM : N/A

LOCATION : 502B DRW REF: BLDG-502B-ELE-08

SL.NO DESCRIPTION YES NO N/A


1 Check if sizes of Earthing tapes are as per approved drawings.

2 Check cable trays,trunking and all equipments are bonded with Earthing system.

3 Check sizes of earth bars are as per specification and approved drawings.

4 Check Earthing wire(s) is connected to equipment as per drawing in proper way.

5 Check the level and location of earth pits are as per approved drawings.

6 Check if earth pit fixing is as per approved drawings.

7 Check the connections of Earthing tape to Earthing rod electrode.

8 Record Earth resistance reading(Less than 2Ohms)

9 Check Earth continuity test for all metal parts and equipment of buildings.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
CHECKLIST FOR EARTHIN
G
AND LIGHTNING PROTECTI
ON

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO : 505

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: N/A SYSTEM : N/A

LOCATION : 505 DRW REF: BLDG-505-ELE-06

SL.NO DESCRIPTION YES NO N/A


1 Check if sizes of Earthing tapes are as per approved drawings.

2 Check cable trays,trunking and all equipments are bonded with Earthing system.

3 Check sizes of earth bars are as per specification and approved drawings.

4 Check Earthing wire(s) is connected to equipment as per drawing in proper way.

5 Check the level and location of earth pits are as per approved drawings.

6 Check if earth pit fixing is as per approved drawings.

7 Check the connections of Earthing tape to Earthing rod electrode.

8 Record Earth resistance reading(Less than 2Ohms)

9 Check Earth continuity test for all metal parts and equipment of buildings.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
FIRE ALARM SYSTEM

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO :

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: SYSTEM :

LOCATION : DRW REF:

SL.NO DESCRIPTION YES NO N/A


1 Check FA panel, Detectors are Installed as per approved drawing.

2 Check Power supply is given properly.

3 Check each equipments are connected with system and working properly.

4 Check Fire strobe, Fire bells are Installed properly and as per approved drawing.

5 Check Battery's voltage and record.

6 Check Installed Battery's are connected properly.

7 Perform tests and check Fire strobs and Fire bells are working properly.

8 Check As built drawings are prepared and placed.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
PUBLIC ADDRESS SYSTEM

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO :

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: SYSTEM :

LOCATION : DRW REF:

SL.NO DESCRIPTION YES NO N/A

1 Check PA system racks and equipments are Installed properly as per approved drawing.

2 Check Speakers are Installed as per approved drawing.

3 Check DVD Players and Mic systems are Installed properly.

4 Check Power supply is given properly.

5 Check all Equipments (Players,Mic) are working properly.

6 Check as built drawings are prepared and placed.


REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
TELEPHONE SYSTEM

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO :

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: SYSTEM :

LOCATION : DRW REF:

SL.NO DESCRIPTION YES NO N/A

1 Check Telephone system racks and switches are Installed as per approved drawing.

2 Check patch panels are Properly Installed in all racks.

3 Check all telephone cables are terminated with Patch panel properly.

4 Check identification of the cables are done.

5 Test all cables and record the results.

6 Check as built drawings are prepared and placed.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDECO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII
COMMISSIONING CHECKLIST F
OR
SMATV SYSTEM

PROJECT NAME : BLUE BRICK BUILDING RENOVATION REPORT NO :

CONTRACT NO : FA300208D0024 TG07 DATE OF TESTED :

AREA'S FEEDING: SYSTEM :

LOCATION : DRW REF:

SL.NO DESCRIPTION YES NO N/A

1 Check TV racks are Installed as per approved drawings.

2 Check Multi switches are Properly Installed and connections are done.

3 Check Installed dish are as per approved drawings(Check location,levels,Supports etc)

4 Check continuity from Multi switch to all points.

5 Check connections are properly done from Dish to Multi switches.

6 Confirm power supply properly given for Switches.

7 Record total number of TV outlets Installed_____________

8 Record Signal strength for Installed TV outlets_____________

9 Check channels visually with Testing Equipment for all points.

REMARKS/COMMENTS

NAME SIGNATURE DATE ORGANIZATION


CHECKED BY Project Engineer MEDCO

INSPECTED BY QC ENGINEER. MEDCO

WITNESSED BY QA MANAGER. VERSAR

OBSERVED BY TITLEII

You might also like