Temporary Facility Fabrication Schedule Daelim QC Lab Schedule_4 01-Oct-14 14:00

Activity ID Activity Name Original Start Finish September 2014 October 2014 November 2014 December 2014
Duration
24 31 07 14 21 28 05 12 19 26 02 09 16 23 30
1-1 Temporary Facility Fabrication Schedule 76 27-Aug-14 10-Nov-14 10-Nov-14, 1-1 Temporary Facility Fabrication Schedule

1-1.2 Intecsa Utilities Management & Supervision Office (EPC-8) 55 27-Aug-14 20-Oct-14 20-Oct-14, 1-1.2 Intecsa Utilities Management & Supervision Office (EPC-8)

1-1.2.1 Fabrication Work From MCCL Fabrication shop 39 27-Aug-14 04-Oct-14 04-Oct-14, 1-1.2.1 Fabrication Work From MCCL Fabrication shop
A2665 Base Frame Works 6 27-Aug-14* 01-Sep-14 Base Frame Works
A2666 Coloumn Errection 6 02-Sep-14* 07-Sep-14 Coloumn Errection
A2667 Floor with cement board 11 09-Sep-14* 19-Sep-14 Floor with cement board
A2668 Roofing works 13 06-Sep-14* 18-Sep-14 Roofing works
A2670 Internal partition wall 14 16-Sep-14* 29-Sep-14 Internal partition wall
A2680 Painting for partition wall 7 27-Sep-14* 03-Oct-14 Painting for partition wall
A2710 Ceiling works 13 18-Sep-14* 30-Sep-14 Ceiling works
A2720 Electrical works Inc Partial wiring , Partial outlets & partial fixtures 15 17-Sep-14* 01-Oct-14 Electrical works Inc Partial wiring , Partial outlets & partial fixtures
A2730 Plumbing Works 3 29-Sep-14* 01-Oct-14 Plumbing Works
A2740 Outside sheeting works 10 25-Sep-14* 04-Oct-14 Outside sheeting works
A2750 Installation of Windows & Door 8 27-Sep-14* 04-Oct-14 Installation of Windows & Door
1-1.2.2 Site Works 20 01-Oct-14 20-Oct-14 20-Oct-14, 1-1.2.2 Site Works
A2690 Site Preparation 2 01-Oct-14* 02-Oct-14 Site Preparation
A2700 Installation & Alignment of Foundation 3 02-Oct-14* 04-Oct-14 Installation & Alignment of Foundation
A2760 Delivery of Building to site 3 05-Oct-14* 07-Oct-14 Delivery of Building to site
A2770 Installation & Alignment of Building 5 05-Oct-14* 09-Oct-14 Installation & Alignment of Building
A2780 Electrical & IT works 11 09-Oct-14* 19-Oct-14 Electrical & IT works
A2790 Vinyl Sheet Flooring 5 12-Oct-14* 16-Oct-14 Vinyl Sheet Flooring
A2800 A/C installation Indoor & outdoor unit 6 13-Oct-14* 18-Oct-14 A/C installation Indoor & outdoor unit
A2810 Plumbing & Sanitary fixing works 4 16-Oct-14* 19-Oct-14 Plumbing & Sanitary fixing works
A2820 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Covering6Etc
15-Oct-14* 20-Oct-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Covering Etc
1-1.3 Intecsa DAP Management office (EPC-2) 46 10-Sep-14 25-Oct-14 25-Oct-14, 1-1.3 Intecsa DAP Management office (EPC-2)

1-1.3.1 Fabrication Work From MCCL Fabrication shop 31 10-Sep-14 10-Oct-14 10-Oct-14, 1-1.3.1 Fabrication Work From MCCL Fabrication shop
A2830 Base Frame Works 5 10-Sep-14* 14-Sep-14 Base Frame Works
A2840 Coloumn Errection 4 15-Sep-14* 18-Sep-14 Coloumn Errection
A2850 Floor with cement board 6 26-Sep-14* 01-Oct-14 Floor with cement board
A2860 Roofing works 8 27-Sep-14* 04-Oct-14 Roofing works
A2870 Internal partition wall 7 30-Sep-14* 06-Oct-14 Internal partition wall
A2880 Painting for partition wall 5 04-Oct-14* 08-Oct-14 Painting for partition wall
A2890 Ceiling works 11 28-Sep-14* 08-Oct-14 Ceiling works
A2900 Electrical works Inc Partial wiring , Partial outlets & partial fixtures 12 26-Sep-14* 07-Oct-14 Electrical works Inc Partial wiring , Partial outlets & partial fixtures
A2990 Plumbing Works 4 04-Oct-14* 07-Oct-14 Plumbing Works
A3000 Outside sheeting works 7 04-Oct-14* 10-Oct-14 Outside sheeting works
A3010 Installation of Windows & Door 4 07-Oct-14* 10-Oct-14 Installation of Windows & Door
1-1.3.2 Site Works 20 06-Oct-14 25-Oct-14 25-Oct-14, 1-1.3.2 Site Works
A2910 Site Preparation 3 06-Oct-14* 08-Oct-14 Site Preparation
A2920 Installation & Alignment of Foundation 3 08-Oct-14* 10-Oct-14 Installation & Alignment of Foundation
A2930 Delivery of Building to site 2 11-Oct-14* 12-Oct-14 Delivery of Building to site
A2940 Installation & Alignment of Building 4 11-Oct-14* 14-Oct-14 Installation & Alignment of Building
A2950 Electrical & IT works 9 16-Oct-14* 24-Oct-14 Electrical & IT works
A2960 Vinyl Sheet Flooring 6 19-Oct-14* 24-Oct-14 Vinyl Sheet Flooring
A2970 A/C installation Indoor & outdoor unit 4 19-Oct-14* 22-Oct-14 A/C installation Indoor & outdoor unit
A2980 Plumbing & Sanitary fixing works 3 20-Oct-14* 22-Oct-14 Plumbing & Sanitary fixing works
A3020 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Covering7Etc
19-Oct-14* 25-Oct-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Cove
1-1.6 MA'ADEN Utilities Office ( EPC-8) 42 20-Sep-14 31-Oct-14 31-Oct-14, 1-1.6 MA'ADEN Utilities Office ( EPC-8)

1-1.6.1 Fabrication Work From MCCL Fabrication shop 26 20-Sep-14 15-Oct-14 15-Oct-14, 1-1.6.1 Fabrication Work From MCCL Fabrication shop
A3230 Base Frame Works 5 20-Sep-14* 24-Sep-14 Base Frame Works

Actual Work Critical Remaining Work Summary Page 1 of 5 TASK filter: Normal.

Remaining Work Milestone © Primavera Systems, Inc.


Temporary Facility Fabrication Schedule Daelim QC Lab Schedule_4 01-Oct-14 14:00

Activity ID Activity Name Original Start Finish September 2014 October 2014 November 2014 December 2014
Duration
24 31 07 14 21 28 05 12 19 26 02 09 16 23 30
A3240 Coloumn Errection 6 24-Sep-14* 29-Sep-14 Coloumn Errection
A3250 Floor with cement board 8 04-Oct-14* 11-Oct-14 Floor with cement board
A3260 Roofing works 9 01-Oct-14* 09-Oct-14 Roofing works
A3270 Internal partition wall 8 06-Oct-14* 13-Oct-14 Internal partition wall
A3280 Painting for partition wall 8 08-Oct-14* 15-Oct-14 Painting for partition wall
A3290 Ceiling works 9 06-Oct-14* 14-Oct-14 Ceiling works
A3300 Electrical works Inc Partial wiring , Partial outlets & partial fixtures 10 06-Oct-14* 15-Oct-14 Electrical works Inc Partial wiring , Partial outlets & partial fixtures
A3310 Plumbing Works 4 11-Oct-14* 14-Oct-14 Plumbing Works
A3320 Outside sheeting works 7 08-Oct-14* 14-Oct-14 Outside sheeting works
A3430 Installation of Windows & Door 6 10-Oct-14* 15-Oct-14 Installation of Windows & Door
1-1.6.2 Site Works 23 09-Oct-14 31-Oct-14 31-Oct-14, 1-1.6.2 Site Works
A3330 Site Preparation 3 09-Oct-14* 11-Oct-14 Site Preparation
A3340 Installation & Alignment of Foundation 4 12-Oct-14* 15-Oct-14 Installation & Alignment of Foundation
A3350 Delivery of Building to site 2 16-Oct-14* 17-Oct-14 Delivery of Building to site
A3360 Installation & Alignment of Building 5 16-Oct-14* 20-Oct-14 Installation & Alignment of Building
A3370 Electrical & IT works 11 20-Oct-14* 30-Oct-14 Electrical & IT works
A3380 Vinyl Sheet Flooring 6 23-Oct-14* 28-Oct-14 Vinyl Sheet Flooring
A3390 A/C installation Indoor & outdoor unit 4 23-Oct-14* 26-Oct-14 A/C installation Indoor & outdoor unit
A3400 Plumbing & Sanitary fixing works 4 23-Oct-14* 26-Oct-14 Plumbing & Sanitary fixing works
A3410 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Covering7Etc
25-Oct-14* 31-Oct-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof J
1-1.7 MA'ADEN DAP Office ( EPC-2) 42 20-Sep-14 31-Oct-14 31-Oct-14, 1-1.7 MA'ADEN DAP Office ( EPC-2)

1-1.7.1 Fabrication Work From MCCL Fabrication shop 26 20-Sep-14 15-Oct-14 15-Oct-14, 1-1.7.1 Fabrication Work From MCCL Fabrication shop
A3440 Base Frame Works 5 20-Sep-14* 24-Sep-14 Base Frame Works
A3450 Coloumn Errection 3 01-Oct-14* 03-Oct-14 Coloumn Errection
A3460 Floor with cement board 5 05-Oct-14* 09-Oct-14 Floor with cement board
A3470 Roofing works 5 04-Oct-14* 08-Oct-14 Roofing works
A3480 Internal partition wall 8 06-Oct-14* 13-Oct-14 Internal partition wall
A3490 Painting for partition wall 7 09-Oct-14* 15-Oct-14 Painting for partition wall
A3500 Ceiling works 9 07-Oct-14* 15-Oct-14 Ceiling works
A3510 Electrical works Inc Partial wiring , Partial outlets & partial fixtures 9 07-Oct-14* 15-Oct-14 Electrical works Inc Partial wiring , Partial outlets & partial fixtures
A3520 Plumbing Works 3 11-Oct-14* 13-Oct-14 Plumbing Works
A3530 Outside sheeting works 8 06-Oct-14* 13-Oct-14 Outside sheeting works
A3650 Installation of Windows & Door 4 12-Oct-14* 15-Oct-14 Installation of Windows & Door
1-1.7.2 Site Works 23 09-Oct-14 31-Oct-14 31-Oct-14, 1-1.7.2 Site Works
A3540 Site Preparation 3 09-Oct-14* 11-Oct-14 Site Preparation
A3550 Installation & Alignment of Foundation 4 12-Oct-14* 15-Oct-14 Installation & Alignment of Foundation
A3560 Delivery of Building to site 2 16-Oct-14* 17-Oct-14 Delivery of Building to site
A3570 Installation & Alignment of Building 5 16-Oct-14* 20-Oct-14 Installation & Alignment of Building
A3580 Electrical & IT works 11 20-Oct-14* 30-Oct-14 Electrical & IT works
A3590 Vinyl Sheet Flooring 6 23-Oct-14* 28-Oct-14 Vinyl Sheet Flooring
A3600 A/C installation Indoor & outdoor unit 4 23-Oct-14* 26-Oct-14 A/C installation Indoor & outdoor unit
A3610 Plumbing & Sanitary fixing works 4 23-Oct-14* 26-Oct-14 Plumbing & Sanitary fixing works
A3620 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Covering7Etc
25-Oct-14* 31-Oct-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof J
1-1.4 Intecsa DAP Direct Supervision Office (EPC-2) 41 01-Oct-14 10-Nov-14 10-Nov-14, 1-1.4 Intecsa DAP Direct Supervision Office (EPC-2

1-1.4.1 Fabrication Work From MCCL Fabrication shop 25 01-Oct-14 25-Oct-14 25-Oct-14, 1-1.4.1 Fabrication Work From MCCL Fabrication shop
A3030 Base Frame Works 4 01-Oct-14* 04-Oct-14 Base Frame Works
A3040 Coloumn Errection 5 05-Oct-14* 09-Oct-14 Coloumn Errection
A3050 Floor with cement board 7 12-Oct-14* 18-Oct-14 Floor with cement board
A3060 Roofing works 6 10-Oct-14* 15-Oct-14 Roofing works
A3070 Internal partition wall 8 15-Oct-14* 22-Oct-14 Internal partition wall

Actual Work Critical Remaining Work Summary Page 2 of 5 TASK filter: Normal.

Remaining Work Milestone © Primavera Systems, Inc.


Temporary Facility Fabrication Schedule Daelim QC Lab Schedule_4 01-Oct-14 14:00

Activity ID Activity Name Original Start Finish September 2014 October 2014 November 2014 December 2014
Duration
24 31 07 14 21 28 05 12 19 26 02 09 16 23 30
A3080 Painting for partition wall 7 19-Oct-14* 25-Oct-14 Painting for partition wall
A3081 Ceiling Works 8 18-Oct-14* 25-Oct-14 Ceiling Works
A3090 Electrical works Inc Partial wiring , Partial outlets & partial fixtures 7 18-Oct-14* 24-Oct-14 Electrical works Inc Partial wiring , Partial outlets & partial fixtures
A3100 Plumbing Works 4 20-Oct-14* 23-Oct-14 Plumbing Works
A3110 Outside sheeting works 7 16-Oct-14* 22-Oct-14 Outside sheeting works
A3120 Installation of Windows & Door 5 21-Oct-14* 25-Oct-14 Installation of Windows & Door
1-1.4.2 Site Works 26 16-Oct-14 10-Nov-14 10-Nov-14, 1-1.4.2 Site Works
A3140 Site Preparation 3 16-Oct-14* 18-Oct-14 Site Preparation
A3150 Installation & Alignment of Foundation 4 19-Oct-14* 22-Oct-14 Installation & Alignment of Foundation
A3160 Delivery of Building to site 2 26-Oct-14* 27-Oct-14 Delivery of Building to site
A3170 Installation & Alignment of Building 5 26-Oct-14* 30-Oct-14 Installation & Alignment of Building
A3180 Electrical & IT works 11 31-Oct-14* 10-Nov-14 Electrical & IT works
A3190 Vinyl Sheet Flooring 7 03-Nov-14* 09-Nov-14 Vinyl Sheet Flooring
A3200 A/C installation Indoor & outdoor unit 4 03-Nov-14* 06-Nov-14 A/C installation Indoor & outdoor unit
A3210 Plumbing & Sanitary fixing works 4 04-Nov-14* 07-Nov-14 Plumbing & Sanitary fixing works
A3220 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Covering7Etc
04-Nov-14* 10-Nov-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet
1-1.9 First Aid Building (EPC-8) 18 08-Oct-14 25-Oct-14 25-Oct-14, 1-1.9 First Aid Building (EPC-8)
A3870 Fabrication from fabrication shop 10 08-Oct-14* 17-Oct-14 Fabrication from fabrication shop
A3880 Site Leveling 1 16-Oct-14* 16-Oct-14 Site Leveling
A3890 Installation & alignment of Foundation 1 17-Oct-14* 17-Oct-14 Installation & alignment of Foundation
A3900 Delivery of Building to site 1 18-Oct-14* 18-Oct-14 Delivery of Building to site
A3910 Installation & alignment of Building 2 18-Oct-14* 19-Oct-14 Installation & alignment of Building
A3920 Electrical works 3 20-Oct-14* 22-Oct-14 Electrical works
A3930 Vinyl Sheet Flooring 3 22-Oct-14* 24-Oct-14 Vinyl Sheet Flooring
A3940 A/C installation Indoor & outdoor unit 2 22-Oct-14* 23-Oct-14 A/C installation Indoor & outdoor unit
A3960 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,etc 4 22-Oct-14* 25-Oct-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,etc
1-1.10 Prayer Hall (EPC-8) 18 08-Oct-14 25-Oct-14 25-Oct-14, 1-1.10 Prayer Hall (EPC-8)
A3970 Fabrication from fabrication shop 10 08-Oct-14* 17-Oct-14 Fabrication from fabrication shop
A3980 Site Leveling 1 16-Oct-14* 16-Oct-14 Site Leveling
A3990 Installation & alignment of Foundation 1 17-Oct-14* 17-Oct-14 Installation & alignment of Foundation
A4000 Delivery of Building to site 1 18-Oct-14* 18-Oct-14 Delivery of Building to site
A4010 Installation & alignment of Building 2 18-Oct-14* 19-Oct-14 Installation & alignment of Building
A4020 Electrical works 3 20-Oct-14* 22-Oct-14 Electrical works
A4030 Vinyl Sheet Flooring 3 22-Oct-14* 24-Oct-14 Vinyl Sheet Flooring
A4040 A/C installation Indoor & outdoor unit 2 22-Oct-14* 23-Oct-14 A/C installation Indoor & outdoor unit
A4050 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,etc 4 22-Oct-14* 25-Oct-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,etc
1-1.5 Client DAP Direct Supervision Office (EPC-2) 35 07-Oct-14 10-Nov-14 10-Nov-14, 1-1.5 Client DAP Direct Supervision Office (EPC-2)

1-1.5.1 Fabrication Work From MCCL Fabrication shop 20 07-Oct-14 26-Oct-14 26-Oct-14, 1-1.5.1 Fabrication Work From MCCL Fabrication shop
A3660 Base Frame Works 4 07-Oct-14* 10-Oct-14 Base Frame Works
A3670 Coloumn Errection 3 11-Oct-14* 13-Oct-14 Coloumn Errection
A3680 Floor with cement board 4 15-Oct-14* 18-Oct-14 Floor with cement board
A3690 Roofing works 5 14-Oct-14* 18-Oct-14 Roofing works
A3700 Internal partition wall 6 18-Oct-14* 23-Oct-14 Internal partition wall
A3710 Painting for partition wall 5 22-Oct-14* 26-Oct-14 Painting for partition wall
A3720 Ceiling Works 7 19-Oct-14* 25-Oct-14 Ceiling Works
A3730 Electrical works Inc Partial wiring , Partial outlets & partial fixtures 8 19-Oct-14* 26-Oct-14 Electrical works Inc Partial wiring , Partial outlets & partial fixtures
A3740 Plumbing Works 4 22-Oct-14* 25-Oct-14 Plumbing Works
A3750 Outside sheeting works 6 18-Oct-14* 23-Oct-14 Outside sheeting works
A3860 Installation of Windows & Door 3 24-Oct-14* 26-Oct-14 Installation of Windows & Door
1-1.5.2 Site Works 25 17-Oct-14 10-Nov-14 10-Nov-14, 1-1.5.2 Site Works

Actual Work Critical Remaining Work Summary Page 3 of 5 TASK filter: Normal.

Remaining Work Milestone © Primavera Systems, Inc.


Temporary Facility Fabrication Schedule Daelim QC Lab Schedule_4 01-Oct-14 14:00

Activity ID Activity Name Original Start Finish September 2014 October 2014 November 2014 December 2014
Duration
24 31 07 14 21 28 05 12 19 26 02 09 16 23 30
A3760 Site Preparation 2 17-Oct-14* 18-Oct-14 Site Preparation
A3770 Installation & Alignment of Foundation 2 19-Oct-14* 20-Oct-14 Installation & Alignment of Foundation
A3780 Delivery of Building to site 2 27-Oct-14* 28-Oct-14 Delivery of Building to site
A3790 Installation & Alignment of Building 2 29-Oct-14* 30-Oct-14 Installation & Alignment of Building
A3800 Electrical & IT works 5 29-Oct-14* 02-Nov-14 Electrical & IT works
A3810 Vinyl Sheet Flooring 3 02-Nov-14* 04-Nov-14 Vinyl Sheet Flooring
A3820 A/C installation Indoor & outdoor unit 2 04-Nov-14* 05-Nov-14 A/C installation Indoor & outdoor unit
A3830 Plumbing & Sanitary fixing works 3 04-Nov-14* 06-Nov-14 Plumbing & Sanitary fixing works
A3840 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,Roof Joint Covering5Etc
06-Nov-14* 10-Nov-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet
1-1.8 Guard House (EPC-8) 20 22-Oct-14 10-Nov-14 10-Nov-14, 1-1.8 Guard House (EPC-8)
A1650 Fabrication from fabrication shop 10 22-Oct-14* 31-Oct-14 Fabrication from fabrication shop
A1660 Site Leveling 2 28-Oct-14* 29-Oct-14 Site Leveling
A1661 Installation & alignment of Foundation 2 30-Oct-14* 31-Oct-14 Installation & alignment of Foundation
A2240 Delivery of Building to site 1 01-Nov-14* 01-Nov-14 Delivery of Building to site
A2250 Installation & alignment of Building 2 01-Nov-14* 02-Nov-14 Installation & alignment of Building
A2260 Electrical works 3 03-Nov-14* 05-Nov-14 Electrical works
A2270 Vinyl Sheet Flooring 2 06-Nov-14* 07-Nov-14 Vinyl Sheet Flooring
A2280 A/C installation Indoor & outdoor unit 2 06-Nov-14* 07-Nov-14 A/C installation Indoor & outdoor unit
A2290 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,etc 3 08-Nov-14* 10-Nov-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet
1-1.23 Guard House (EPC-2) 20 22-Oct-14 10-Nov-14 10-Nov-14, 1-1.23 Guard House (EPC-2)
A2330 Fabrication from fabrication shop 10 22-Oct-14* 31-Oct-14 Fabrication from fabrication shop
A2340 Site Leveling 2 28-Oct-14* 29-Oct-14 Site Leveling
A2350 Installation & alignment of Foundation 2 30-Oct-14* 31-Oct-14 Installation & alignment of Foundation
A2360 Delivery of Building to site 1 02-Nov-14* 02-Nov-14 Delivery of Building to site
A2370 Installation & alignment of Building 2 02-Nov-14* 03-Nov-14 Installation & alignment of Building
A2380 Electrical work 3 04-Nov-14* 06-Nov-14 Electrical work
A3130 Vinyl Sheet Flooring 2 06-Nov-14* 07-Nov-14 Vinyl Sheet Flooring
A3420 A/C installation Indoor & outdoor unit 2 07-Nov-14* 08-Nov-14 A/C installation Indoor & outdoor unit
A3630 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,etc 3 08-Nov-14* 10-Nov-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet

1-1.24 First Aid Building (EPC-2) 20 22-Oct-14 10-Nov-14 10-Nov-14, 1-1.24 First Aid Building (EPC-2)

A2390 Fabrication from Fabrication Shop 10 22-Oct-14* 31-Oct-14 Fabrication from Fabrication Shop
A2400 Site Leveling 2 28-Oct-14* 29-Oct-14 Site Leveling
A2410 Installation & alignment of Foundation 2 30-Oct-14* 31-Oct-14 Installation & alignment of Foundation
A2420 Delivery of Building to site 1 02-Nov-14* 02-Nov-14 Delivery of Building to site
A2430 Installation & alignment of Building 2 02-Nov-14* 03-Nov-14 Installation & alignment of Building
A2440 Electrical 3 04-Nov-14* 06-Nov-14 Electrical
A3640 Vinyl Sheet Flooring 3 07-Nov-14* 09-Nov-14 Vinyl Sheet Flooring
A3850 A/C installation Indoor & outdoor unit 3 07-Nov-14* 09-Nov-14 A/C installation Indoor & outdoor unit
A3950 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet covering,etc 3 08-Nov-14* 10-Nov-14 Miscellaneous Works like Beeding ,Paint Touch up,Bottom sheet
1-1.11 External Electrical Works (EPC-8) 35 07-Oct-14 10-Nov-14 10-Nov-14, 1-1.11 External Electrical Works (EPC-8)
A1720 Precasting of Lighting pole Foundation 15 07-Oct-14* 21-Oct-14 Precasting of Lighting pole Foundation
A2450 Eacavation for Trench Generator to Building 8 10-Oct-14* 17-Oct-14 Eacavation for Trench Generator to Building
A2451 Cable Pulling Generator to building 5 15-Oct-14* 19-Oct-14 Cable Pulling Generator to building
A2452 Eacavation for Trench external lighting & Foundation 10 17-Oct-14* 26-Oct-14 Eacavation for Trench external lighting & Foundation
A2461 Cable Pulling External Lighting 8 27-Oct-14* 03-Nov-14 Cable Pulling External Lighting
A2470 Installation of Pole foundation 2 21-Oct-14* 22-Oct-14 Installation of Pole foundation
A2480 Backfilling foundation & cable trench 7 04-Nov-14* 10-Nov-14 Backfilling foundation & cable trench
A2490 Installation of pole & Light 3 06-Nov-14* 08-Nov-14 Installation of pole & Light
A2500 Testing & Termination 3 08-Nov-14* 10-Nov-14 Testing & Termination
A2510 Installation of Generator 3 18-Oct-14* 20-Oct-14 Installation of Generator

Actual Work Critical Remaining Work Summary Page 4 of 5 TASK filter: Normal.

Remaining Work Milestone © Primavera Systems, Inc.


Temporary Facility Fabrication Schedule Daelim QC Lab Schedule_4 01-Oct-14 14:00

Activity ID Activity Name Original Start Finish September 2014 October 2014 November 2014 December 2014
Duration
24 31 07 14 21 28 05 12 19 26 02 09 16 23 30
1-1.12 External Electrical Works (EPC-2) 31 11-Oct-14 10-Nov-14 10-Nov-14, 1-1.12 External Electrical Works (EPC-2)
A2220 Precasting of Lighting pole Foundation 15 11-Oct-14* 25-Oct-14 Precasting of Lighting pole Foundation
A2230 Eacavation for Trench Generator to Building 6 14-Oct-14* 19-Oct-14 Eacavation for Trench Generator to Building
A2520 Cable Pulling Generator to building 4 20-Oct-14* 23-Oct-14 Cable Pulling Generator to building
A2530 Eacavation for Trench external lighting & Foundation 7 20-Oct-14* 26-Oct-14 Eacavation for Trench external lighting & Foundation
A2540 Cable Pulling External Lighting 9 27-Oct-14* 04-Nov-14 Cable Pulling External Lighting
A2550 Installation of Pole foundation 2 26-Oct-14* 27-Oct-14 Installation of Pole foundation
A2560 Backfilling foundation & cable trench 6 05-Nov-14* 10-Nov-14 Backfilling foundation & cable trench
A2570 Installation of pole & Light 3 08-Nov-14* 10-Nov-14 Installation of pole & Light
A2580 Testing & Termination 3 08-Nov-14* 10-Nov-14 Testing & Termination
A2590 Installation of Generator 3 23-Oct-14* 25-Oct-14 Installation of Generator
1-1.13 External Sewer & Plumbing Works (EPC-8) 29 22-Sep-14 20-Oct-14 20-Oct-14, 1-1.13 External Sewer & Plumbing Works (EPC-8)
A1740 Procurement of Water tank , Septic Tank & Other Accessories 25 22-Sep-14* 16-Oct-14 Procurement of Water tank , Septic Tank & Other Accessories
A1750 Excavation for Water line & Sewer Line 6 15-Oct-14* 20-Oct-14 Excavation for Water line & Sewer Line
A1751 Water tank foundation 7 05-Oct-14* 11-Oct-14 Water tank foundation
A2460 Installation of Water tank 4 17-Oct-14* 20-Oct-14 Installation of Water tank
A2462 Installation of Septic tank inc excavation , backfilling etc 4 17-Oct-14* 20-Oct-14 Installation of Septic tank inc excavation , backfilling etc
A2600 Laying Pipe for Water line 8 10-Oct-14* 17-Oct-14 Laying Pipe for Water line
A2610 Laying Pipe for Sewer Line 8 10-Oct-14* 17-Oct-14 Laying Pipe for Sewer Line
1-1.14 External Sewer & Plumbing Works (EPC-2) 33 22-Sep-14 24-Oct-14 24-Oct-14, 1-1.14 External Sewer & Plumbing Works (EPC-2)

A2190 Procurement of Water tank , Septic Tank & Other Accessories 25 22-Sep-14* 16-Oct-14 Procurement of Water tank , Septic Tank & Other Accessories
A2200 Excavation for Water line & Sewer Line 6 17-Oct-14* 22-Oct-14 Excavation for Water line & Sewer Line
A2201 Water tank foundation 7 10-Oct-14* 16-Oct-14 Water tank foundation
A2620 Installation of Water tank 4 21-Oct-14* 24-Oct-14 Installation of Water tank
A2630 Installation of Septic tank inc excavation , backfilling etc 4 21-Oct-14* 24-Oct-14 Installation of Septic tank inc excavation , backfilling etc
A2640 Laying Pipe for Water line 8 17-Oct-14* 24-Oct-14 Laying Pipe for Water line
A2650 Laying Pipe for Sewer Line 8 17-Oct-14* 24-Oct-14 Laying Pipe for Sewer Line
1-1.15 Fencing Works 41 01-Oct-14 10-Nov-14 10-Nov-14, 1-1.15 Fencing Works
A1160 Procurement of Material 19 01-Oct-14* 19-Oct-14 Procurement of Material
A1170 Construction of Foundation with post from fabrication yard 18 15-Oct-14* 01-Nov-14 Construction of Foundation with post from fabrication yard
A1180 Excavation 14 20-Oct-14* 02-Nov-14 Excavation
A1190 Installation of Fence post & other Accessories Inc Gate 19 23-Oct-14* 10-Nov-14 Installation of Fence post & other Accessories Inc Gate
1-1.16 Car Parking Shed(EPC-8) 43 13-Sep-14 25-Oct-14 25-Oct-14, 1-1.16 Car Parking Shed(EPC-8)
A1760 Procurement of Material 30 13-Sep-14* 12-Oct-14 Procurement of Material
A1770 Fabrication from Yard 10 05-Oct-14* 14-Oct-14 Fabrication from Yard
A1780 Installation & Finishing Works 16 10-Oct-14* 25-Oct-14 Installation & Finishing Works
1-1.17 Car Parking Shed(EPC-2) 59 13-Sep-14 10-Nov-14 10-Nov-14, 1-1.17 Car Parking Shed(EPC-2)
A2160 Procurement of Material 30 13-Sep-14* 12-Oct-14 Procurement of Material
A2170 Fabrication from Yard 15 05-Oct-14* 19-Oct-14 Fabrication from Yard
A2180 Installation & Finishing Works 25 17-Oct-14* 10-Nov-14 Installation & Finishing Works
1-1.18 Generator Shed(EPC-8) 17 14-Oct-14 30-Oct-14 30-Oct-14, 1-1.18 Generator Shed(EPC-8)
A1790 Fabrication of Generator Shed 8 14-Oct-14* 21-Oct-14 Fabrication of Generator Shed
A1800 Installation of Generator Shed 9 22-Oct-14* 30-Oct-14 Installation of Generator Shed
1-1.19 Generator Shed(EPC-2) 17 14-Oct-14 30-Oct-14 30-Oct-14, 1-1.19 Generator Shed(EPC-2)

A2140 Fabrication of Generator Shed 8 14-Oct-14* 21-Oct-14 Fabrication of Generator Shed


A2150 Installation of Generator Shed 9 22-Oct-14* 30-Oct-14 Installation of Generator Shed

Actual Work Critical Remaining Work Summary Page 5 of 5 TASK filter: Normal.

Remaining Work Milestone © Primavera Systems, Inc.