You are on page 1of 1

Project Schedule 24-Aug-19 22:52

Client Name: CNOOC Iraq Limited


Combustor Installation
Activity ID Activity Name Original Start 2020 2021 2022
Duration Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
12-Sep-22, Combustor Installation
Combustor Installation 955d 26-Aug-19

Thermal Design 42d 26-Aug-19 12-Oct-19, Thermal Design

A1000 Design Thermal 14d 26-Aug-19 Design Thermal


A1010 Design Structural 14d 26-Aug-19 Design Structural
A1020 Design pressure parts per scantling 28d 26-Aug-19 Design pressure parts per scantling
A1030 Design Mechanical 14d 27-Sep-19 Design Mechanical

Pressure Parts Assembly 35d 14-Oct-19 22-Nov-19, Pressure Parts Assembly

A1040 Drawing pressure parts assembly 35d 14-Oct-19 Drawing pressure parts assembly

Project Drawing 72d 23-Nov-19 14-Feb-20, Project Drawing

A1050 Drawing project & layout 32d 23-Nov-19 Drawing project & layout
A1060 Drawing P&I 40d 31-Dec-19 Drawing P&I

Foundation 49d 15-Feb-20 11-Apr-20, Foundation

A1070 Drawing main foundation 12d 15-Feb-20 Drawing main foundation


A1080 Drawing Bunker Foundation 21d 15-Feb-20 Drawing Bunker Foundation
A1090 Drawing auxiliary foundation 28d 15-Feb-20 Drawing auxiliary foundation
A1100 Cast main foundation 28d 11-Mar-20 Cast main foundation
A1110 Cast auxiliary foundation 5d 19-Mar-20 Cast auxiliary foundation

Structure 490d 13-Apr-20 04-Nov-21, Structure

A1120 Approval of structure 20d 13-Apr-20 Approval of structure


A1130 structure drawing 18d 06-May-20 structure drawing
A1140 procure raw material 90d 27-May-20 procure raw material
A1150 manufacture structure 120d 09-Sep-20 manufacture structure
A1160 Dispatch structure 102d 27-Jan-21 Dispatch structure
A1170 Errect Structure 140d 26-May-21 Errect Structure

Combustor 267d 05-Nov-21 12-Sep-22, Combustor

A1180 Approval of combustor 27d 05-Nov-21 Approval of combustor


A1190 Drawing coal spout 21d 07-Dec-21 Drawing coal spout
A1200 Enquiry of coal spout 14d 31-Dec-21 Enquiry of coal spout
A1210 Ordering of coal spout 7d 17-Jan-22 Ordering of coal spout
A1220 procure of coal spout 21d 25-Jan-22 procure of coal spout
A1230 Manufacture coal spout 84d 18-Feb-22 Manufacture coal spout
A1240 Dispatch coal spout 7d 27-May-22 Dispatch coal spout
A1250 Errect coal spout 8d 04-Jun-22 Errect coal spout
A1260 Drawing ash hopper 7d 07-Dec-21 Drawing ash hopper
A1270 procure ash hopper 14d 15-Dec-21 procure ash hopper
A1280 Manufacture ash hopper 56d 31-Dec-21 Manufacture ash hopper
A1290 Dispatch ash hopper 7d 07-Mar-22 Dispatch ash hopper
A1300 Errect Ash Hopper 14d 15-Mar-22 Errect Ash H opper
A1310 Drawing combustor 28d 07-Dec-21 Drawing combustor
A1320 Enquiry of combustor items 27d 08-Jan-22 Enquiry of combustor items
A1330 Ordering of combustor items 35d 09-Feb-22 Ordering of combustor items
A1340 Manufacturing of combustor parts 28d 22-Mar-22 Manufacturing of combustor parts
A1350 Fabrication of combustor parts 56d 23-Apr-22 Fabrication of combustor parts
A1360 Assembly of combustor parts 38d 28-Jun-22 Assembly of combustor parts
A1370 Dispatch of combustor 7d 11-Aug-22 Dispatch of combustor
A1380 Errection of combustor 21d 19-Aug-22 Errection of combustor

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation

You might also like